Maintaining Long Rural Feeders with Large Interconnected Distributed Generation Keary R. Dosier, P.E. UC Synergetic The Proliferation of DG / IPPs • Solar Photovoltaic • Wind • Landfill Gas • Hydroelectric • Biomass • Other The Proliferation of DG / IPPs Economic Political Social The Proliferation of DG / IPPs • Resource Availability • – Sunlight • – Wind • – Landfills • Energy Cost Land Cost Interconnection Cost Generation Cost The Interconnection Request • • • • • Large Rural Land Fill Methane Gas 9 MW of Synchronous Generators Plan for 24 x 365 Operation Around 50 Years of Planned Operation Interconnection Options • Existing 115 kV Transmission Line – Utility Performance Risk Low – Cost Of Building a New Substation – Significant Time Required for Planning and Coordination • Existing 23 kV Distribution Feeder – Utility Performance Risk High – Cost of upgrading distribution facilities – Less Time Required The Rural Distribution Feeder 0.5 MW 0.2 MVAr 10.0 MW 7 mi Station 1.5mi 5 mi 2.0 MW 0.9 MVAr 2.0 MW 0.9 MVAr 3 mi 2.5 MW 0.9 MVAr - 1.2 MVAr 3.0 MW 1.1 MVAr - 1.2 MVAr 19 mi The Rural Distribution Feeder • • • • • • 10 MW Peek Demand 3 MW Valley Demand 1500 Customers 96 Line Miles 20 Miles to the Last Customer 7 Miles to the Land Fill Peak Load – No Generation Valley Load – No Generation Accommodating the Interconnection • Interconnection Study Objective – Determine the lowest cost method of supporting the interconnection why adhering to the utility requirements: • • • • Capacity Reliability Flicker Service Voltage Requirements Accommodating the Interconnection • For Reliability – Install Electronic (2) Electronic Reclosers • For Voltage Performance – Convert 2 miles of #2 ACSR to 477 AAC – Require Generators to be run at 96% PF Leading Common Mode of Operation • Non-Voltage Regulating • Constant Power Target • Constant Power Factor Target Low Voltage Station Watts VARs High Voltage G Customer Proceeds with Installation • Utility constructs infrastructure upgrades paid for by the landfill customer • Customer Proceeds with construction and commissioning of the 9 MW generator set Landfill Generator Added -9.0 MW 2.4 MVAr 1 MW Station 0.5 MW 0.2 MVAr 7 mi G 3 MW 1.5mi 5 mi 2.0 MW 0.9 MVAr 2.0 MW 0.9 MVAr 3 mi 2.5 MW 0.9 MVAr -1.2 MVAr 3.0 MW 1.1 MVAr -1.2 MVAr 19 mi Peak Load – Gen 9MW @ -96%PF Valley Load – Gen 9MW @ -96%pf Valley Load – Gen 9MW @ -96%pf 2-1200 kVAr Caps Closed Customer Complains of Nuisance Trips • Generator Protection Tripping – Power Factor limits – Overvoltage limits • Contributing Factors – 9 MW Gen Set Consumes around 2.4 MVAr to operate at 96% PF leading – Voltage fluctuation from distribution capacitor operations Corrective Action • • • • Change generator power factor target to unity Remove 2-1200 kVAR Capacitor Banks Install 4-600 kVAR Capacitor Banks Install 300A Voltage Regulator – At midpoint between Generator and Substation – Co-Generation Mode – Line Drop Compensation (LDC) Mitigation Applied -9.0 MW 0.0 MVAr 1.0 MW Station 0.5 MW 0.2 MVAr 7 mi G LDC 1.5mi 5 mi 2.0 MW 0.9 MVAr - 0.6 MVAr 2.0 MW 0.9 MVAr - 0.6 MVAr 3 mi 2.5 MW 0.9 MVAr - 0.6 MVAr 3.0 MW 1.1 MVAr - 0.6 MVAr 19 mi Peak Load – Gen 9MW @ Unity LDC Reg & 2-600 kVAr Caps Valley Load – Gen 9MW @ Unity LDC Reg & 2-600 kVAr Caps The solution works • No More Nuisance Tripping Complaints • No Customer Voltage Complaints • Utility Losses Reduced by 30 KW A New Customer is Cause for Reevaluation • Developer Plans Shopping Center & Residential • Beyond New Voltage Regulator 1 Mile New Customer -9.0 MW 0.0 MVAr 3.0 MW Station 0.5 MW 0.2 MVAr 7 mi G 2.0 MW LDC 1.5mi 5 mi 2.0 MW 0.9 MVAr - 0.6 MVAr 2.0 MW 0.9 MVAr - 0.6 MVAr 3 mi 2.5 MW 0.9 MVAr - 0.6 MVAr 3.0 MW 1.1 MVAr - 0.6 MVAr 19 mi Solution to Serve New Customer • Bypass regulator with a double circuit line • Build 1 wire mile of #1/0 ACSR under the existing 477 AAC feeder starting at the midpoint voltage regulator. Added Infrastructure -9.0 MW 0.0 MVAr 3.0 MW Station 0.5 MW 0.2 MVAr 7 mi G 2.0 MW LDC 1.5mi 5 mi 2.0 MW 0.9 MVAr - 0.6 MVAr 2.0 MW 0.9 MVAr - 0.6 MVAr 3 mi 2.5 MW 0.9 MVAr - 0.6 MVAr 3.0 MW 1.1 MVAr - 0.6 MVAr 19 mi Complication with IVVC Systems • IVVC – Integrated Volt-Var Control • CVR – Conservation Voltage Reduction • DSDR – Distribution System Demand Response Added Infrastructure -9.0 MW 0.0 MVAr 3.0 MW Station 0.5 MW 0.2 MVAr 7 mi G 2.0 MW LDC 1.5mi 5 mi 2.0 MW 0.9 MVAr - 0.6 MVAr 2.0 MW 0.9 MVAr - 0.6 MVAr 3 mi - 0.6 MVAr - 0.6 MVAr 19 mi 5.5 MW 2.0 MVAr Complication with IVVC Systems Peak Complication with IVVC Systems Valley Questions?