BRIDGES B.6 B OTHER BRIDGES AND STRUCTURES Other bridges and structures include drainage and fauna underpasses, property access bridges and underpasses, bridges over local roads and bridges off the main expressway alignment. These include the following: BR06 Tributary of Black Waterholes Creek – Drainage & Fauna Underpass BR07 Black Waterholes Creek – Drainage & Fauna underpass BR09 Sawyers Gully Creek – Drainage & Fauna Underpass BR10 Tributary of Sawyers Gully Creek – Drainage & Fauna Underpass BR11 Tributary of Sawyers Gully Creek - Property Access at 413 Majors Lane & Fauna Underpass BR12 Bishops Creek – Drainage & Fauna Underpass BR13 Twin Bridges over Allandale Quarry Property Access Track BR15 Twin Bridges over Camp Road BR16 Watercourse at Station 30870 - Drainage and Fauna Underpass BR20 Bridge over Main Northern Railway on Connection to New England Highway Underpasses The six combined drainage and fauna underpasses and the property access and fauna underpass at Majors Lane are of similar design and construction. Due to the low visibility of the underpasses with all situated in isolated bushland areas the headwalls and wing walls have a grooved off-form finish only. Each headwall and wing wall has a one metre galvanized steel twin rail safety fence on top. Each underpass unless otherwise described has a central cell that provides a low flow channel to make sure the other two cells will provide dry fauna access during normal flow conditions. The landscaping of bridge underpasses and the provision of fauna furniture is subject to the review and agreement of the project ecologist and OEH prior to finalisation. HBO+EMTB SEPTEMBER 2011 SYU-002251 H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) 69 B.6.1 BR06 Tributary of Black Waterholes Creek - Drainage and Fauna Underpass The underpass structure at the Tributary of Black Waterholes Creek has a box culvert construction that consists of three cells of 3000 x 2400 millimetre precast crown units on a cast in-situ reinforced concrete base slab. Reinforced concrete wingwalls will be cast onto the apron slabs. Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. The underpass supports approximately 1.5 metres maximum height of fill. Minimum fill is approximately 1.0 metres, which is adequate to accommodate the pavement thickness. Figure B.6.1.1 70 0 BR06 Tributary of Black Waterholes Creek - Drainage and Fauna Underpass: Elevation HBO+EMTB SEPTEMBER 2011 SYU-002251 10 20m H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) BRIDGES B Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. Figure B.6.1.2 HBO+EMTB BR06 Tributary of Black Waterholes Creek - Drainage and Fauna Underpass: Cross Sectional Elevation SEPTEMBER 2011 SYU-002251 H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) 0 5 10m 71 B.6.2 BR07 Black Waterhole Creek - Drainage and Fauna Underpass The underpass structure at Black Waterholes Creek has a box culvert construction that consists of three cells of 2700 x 2400 millimetres precast crown units and a fourth cell formed by a link slab. The underpass supports approximately 3.0 metres maximum height of fill. Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. Figure B.6.2.1 72 0 BR07 Black Waterholes Creek - Drainage and Fauna Underpass: Elevation HBO+EMTB SEPTEMBER 2011 SYU-002251 10 20m H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) BRIDGES B Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. Figure B.6.2.2 HBO+EMTB BR07 Black Waterholes Creek - Drainage and Fauna Underpass: Cross Sectional Elevation SEPTEMBER 2011 SYU-002251 H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) 0 5 10m 73 B.6.3 BR09 Sawyers Gully Creek - Drainage and Fauna Underpass The underpass structure at Sawyers Gully Creek has a box culvert construction that consists of three cells of 2400 x 2400 millimetre precast crown units and a fourth cell formed by a link slab. The underpass supports approximately 8 metres maximum height of fill. Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. Figure B.6.3.1 74 0 BR09 Sawyers Gully Creek - Drainage and Fauna Underpass: Elevation HBO+EMTB SEPTEMBER 2011 SYU-002251 10 20m H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) BRIDGES B Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. Figure B.6.3.2 HBO+EMTB BR09 Sawyers Gully Creek - Drainage and Fauna Underpass: Cross Sectional Elevation SEPTEMBER 2011 SYU-002251 H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) 0 5 10m 75 B.6.4 BR10 Tributary of Sawyers Gully Creek - Drainage and Fauna Underpass The underpass structure at the Tributary of Sawyers Gully Creek has a box culvert construction that consists of two cells of 3000 x 2400 millimetres precast crown units and a third cell formed by a link slab. The crown units are supported on a cast in-situ reinforced concrete base slab. Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. The underpass supports approximately 3.0 metres maximum height of fill. Figure B.6.4.1 76 0 BR10 Tributary of Sawyers Gully Creek - Drainage and Fauna Underpass: Elevation HBO+EMTB SEPTEMBER 2011 SYU-002251 10 20m H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) BRIDGES B Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. Figure B.6.4.2 HBO+EMTB BR10 Tributary of Sawyers Gully Creek - Drainage and Fauna Underpass: Cross Sectional Elevation SEPTEMBER 2011 SYU-002251 H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) 0 5 10m 77 B.6.5 BR11 Tributary of Sawyers Gully Creek - Property Access 413 Majors Lane and Fauna Underpass The combined property access and fauna underpass near the tributary of Sawyers Gully Creek consists of a single cell of 3600 x 3600 millimetres precast crown units on a cast in-situ slab. Fauna access will be along the roadway in the underpass. No specific fauna provisions have been provided in accordance with advice from the RTA. Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. The underpass supports approximately 1.6 metres maximum height of fill. The minimum fill is approximately 1.0 metres which is adequate to accommodate the pavement thickness. Figure B.6.5.1 78 BR11 Tributary of Sawyers Gully Creek - Property Access 413 Majors Lane and Fauna Underpass: Elevation HBO+EMTB SEPTEMBER 2011 SYU-002251 0 10 20m H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) BRIDGES B Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. Figure B.6.5.2 HBO+EMTB BR11 Tributary of Sawyers Gully Creek - Property Access 413 Majors Lane and Fauna Underpass: Cross Sectional Elevation SEPTEMBER 2011 SYU-002251 H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) 0 5 10m 79 B.6.6 BR12 Bishops Creek - Drainage and Fauna Underpass The underpass structure at Bishops Creek has a box culvert construction that consists of two cells of 3300 x 2400 millimetres precast crown units on a cast in-situ reinforced concrete base slab. Apron slabs at each end of the underpass will be cast as part of the base slab and reinforced concrete wingwalls will be cast onto the apron slabs. Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. One cell is provided with a low flow channel to ensure that the other cell will provide dry fauna access during normal flow conditions. The underpass supports approximately 10 metres maximum height of fill. Fish friendly features have been provided at this underpass including a low flow channel, rocks embedded in the invert to provide a more natural environment and to promote sediment accumulation and pools at each end to dissipate flow energy and provide a resting area for the fish. Figure B.6.6.1 80 0 BR12 Bishops Creek Drainage and Fauna Underpass: Elevation HBO+EMTB SEPTEMBER 2011 SYU-002251 5 10m H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) BRIDGES B Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. Figure B.6.6.2 HBO+EMTB BR12 Bishops Creek Drainage and Fauna Underpass: Section SEPTEMBER 2011 SYU-002251 H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) 0 10 20m 81 B.6.7 BR13 Twin Bridges over Allandale Quarry Property Access Track The twin bridges are 13.0 metres long single span structures over the combined Allandale Quarry Access Track and fauna access. The superstructure comprises spaced 480 millimetre deep prestressed concrete planks with a compositely acting reinforced concrete deck slab. The bridge is square to the main alignment. Longitudinal drainage is not required. Fauna access under the bridge is provided on the access track. The information document, Fauna Mitigation Measures Final Draft Report indicates that given the expected very low traffic volumes, the access track can be used by fauna. Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. A reinforced soil wall is provided at both abutments and will be placed flush with the wingwalls. Wingwalls will be precast with a finish to match the reinforced soil walls. During detailed design the ribbed panel shown in Figures 6.7.1 and 6.7.2 was replaced by a horizontal grooved panel to be consistent with the design of similar retaining wall structures developed for the Hunter Alliance project. Twin rail traffic barriers have been provided with two conduits encased in each barrier. The twin rail traffic barrier extends beyond the end of deck to the end of the reinforced soil wall. Provision has been made for Energy Australia conduits suspended between planks of the northbound bridge. Figure B.6.7.1 82 0 BR13 Twin Bridges over Allandale Quarry Property Access Track: Elevation HBO+EMTB SEPTEMBER 2011 SYU-002251 10 20m H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) BRIDGES B Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Figure B.6.7.2 HBO+EMTB BR13 Twin Bridges over Allandale Quarry Property Access Track: Cross Sectional Elevation SEPTEMBER 2011 SYU-002251 H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) 0 5 10m 83 B.6.8 BR15 Twin Bridges over Camp Road The Expressway crosses Camp Road as twin bridges with overall lengths of 23.4 metres. The road carriageway is 10.75 metres wide (northbound) and 10.5 metres wide (southbound). Each superstructure comprises 1000 millimetre deep precast prestressed Super-T girders acting compositely with a 180 millimetre minimum thickness in-situ concrete deck slab. Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. The bridge parapets comprise 1300 millimetre high twin rail traffic barriers. The parapets and twin rail traffic barriers extend along the bridge approaches to the top of batter where the standard RTA transition to a thrie beam barrier has been adopted. Two conduits are provided in each barrier. A longitudinal drainage pipe is provided under each bridge to minimise the flow of water over the expansion joint. Provision has been made for the future attachment by others of a 4.3 metres (minimum) high noise wall on the eastern side of the southbound carriageway using the same attachment detail as shown for Bridge BR24. During detailed design the ribbed panel shown in Figures 6.7.1 and 6.7.2 was replaced by a horizontal grooved panel to be consistent with the design of similar retaining wall structures developed for the Hunter Alliance project. Figure B.6.8.1 84 0 BR15 Twin Bridges over Camp Road: Elevation HBO+EMTB SEPTEMBER 2011 SYU-002251 10 20m H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) BRIDGES B Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Figure B.6.8.2 HBO+EMTB BR15 Twin Bridges over Camp Road: Cross Sectional Elevation SEPTEMBER 2011 SYU-002251 H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) 0 5 10m 85 B.6.9 BR16 Watercourse at Station 30870 - Drainage and Fauna Underpass The underpass structure at Station 30870 consists of a single 2400 x 2400 millimetre precast crown unit on a cast in-situ reinforced concrete base slab. Half of the cell has been detailed with a low flow channel to ensure that the remainder of the cell will provide dry fauna access during normal flow conditions. Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. The underpass supports approximately 11 metre maximum height of fill. Figure B.6.9.1 86 0 BR16 Watercourse at Station 30870 Drainage and Fauna Underpass: Elevation HBO+EMTB SEPTEMBER 2011 SYU-002251 5 10m H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) BRIDGES B Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. Figure B.6.9.2 HBO+EMTB BR16 Watercourse at Station 30870 Drainage and Fauna Underpass: Section SEPTEMBER 2011 SYU-002251 H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) 0 10 20m 87 B.6.10 BR20 Bridge over Main Northern Railway on Connection to New England Highway The bridge over the Main Northern Railway on the Connection to the New England Highway is a single span structure with an overall length of 33.75 metres. The road carriageway width varies and is a maximum of 20.9 metres wide between barriers. Conduits for Energy Australia are suspended between the outer girders on the northern side. The superstructure comprises 1500 millimetre deep precast prestressed Super-T girders acting compositely with a 180 millimetre minimum thickness in-situ concrete deck slab. It is simply supported on laminated elastomeric bearings. Transverse restraint is provided at each abutment. The abutments comprise reinforced concrete headstocks supported on 1200 millimetre diameter bored piles socketed into rock and 1000 millimetre diameter reinforced concrete column extensions within the reinforced soil embankment. the wingwalls. Two conduits are provided in each barrier. A minimum vertical clearance of 7.3 metres has been provided over the tracks and horizontal clearances complying with Drawing H8R-DWG-S2G-FEA-0505 of the ARTC Agreement, allowing for quadruplicated tracks, have been detailed. The abutment columns and piles have been designed for train impact loading and cement stabilised backfill has been detailed at the base of the reinforced soil block to ensure the integrity of the wall in the event of impact. The superstructure has also been reviewed for train impact. A longitudinal drainage pipe is provided on the northern side. The horizontal ribbed reinforced soil wall panels have been replaced during detailed design by horizontally grooved pre-cast panels. Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. The bridge parapets comprise 1300 millimetre high twin rail traffic barriers with an integrated safety screen. There is a connection to thrie beam at the ends of Figure B.6.10.1 88 0 BR20 Bridge over Main Northern Railway on Connection to New England Highway: Elevation HBO+EMTB SEPTEMBER 2011 SYU-002251 10 20m H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) BRIDGES B Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Figure B.6.10.2 HBO+EMTB BR20 Bridge over Main Northern Railway on Connection to New England Highway: Cross Sectional Elevation SEPTEMBER 2011 SYU-002251 H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) 0 10 20m 89 This page intentionally left blank 90 HBO+EMTB SEPTEMBER 2011 SYU-002251 H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) BRIDGES B.7 B Creek or Watercourse Crossings There are three creek crossings required on the Hunter Expressway Design and Construct section, over the following creeks: – Swamp Creek (BR04) – Anvil Creek (BR21) – Black Creek (BR25) Black Creek and Swamp Creek are tributaries of the Hunter River and require several spans to cross. Generally only the parapets will be clearly visible from the expressway, but on the twin bridges at Swamp and Black Creeks the headstocks will also be visible. Distant views to the bridges will also be possible from the surrounding context. The design has been kept consistent for all the bridges over creeks to maintain a “family” bridge aesthetic. Headstock and Piers Parapets Abutments and Scour Protection The parapets consist of a 600 millimetre concrete barrier with twin metal rails on top allowing views to be maximised from the expressway to the creek and surrounding countryside and to minimise the apparent depth of the parapet when seen from each carriageway. The outer edge of the parapet extends downwards below the soffit of the bridge deck to hide the substructure, providing consistent proportions and casting a strong shadow line minimising the visual impact of the bridge structure. The parapets taper at 15 degrees and the top of the parapet has a cross fall towards the expressway for drainage to minimise staining on the face of the parapet. The parapets are formed from precast units 2.7 metres long and are integrated with the positions of the posts for the twin rail traffic barrier to occur at the centre point between the posts. The spill through abutments beneath the bridges are finished with rock filled rip rap and toe trenches in accordance with the scour protection and fauna passage requirements. Bridges over Creeks - Headstock Detail 1: Section at Pier Bridges over Creeks - Headstock Detail 2: End Elevation Bridges over Creeks - Headstock Detail 1: Elevation Bridges over Creeks - Headstock Detail 2: Plan Planting under Creek Crossings Scour protection below watercourse crossings will be landscaped to incorporate 70% planting of the area below the bridge excluding the low flow channel. Refer to Figure B.7.1 The design of the headstocks has been based on the headstock found on the existing bridge crossing the railway at Wine Country Drive (refer to photo below). The headstock in section has a 45 degree chamfer to the bottom edge of the taper to the circular piers. The soffit of the headstock also tapers in elevation at each end to close to the first pier further minimising the visual impact of the headstock. The corners of the headstocks are also rounded as illustrated in the sketches opposite giving a softer robust appearance. The piers have been positioned to minimise the impacts on the creek beds. Figure B.7.1 HBO+EMTB SEPTEMBER 2011 SYU-002251 Bridges over Creeks: Headstock Details H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % ) 91 B.7.1 BR04 Twin Bridges over Swamp Creek The twin bridges are 66.0 metres long and each has five spans of 13.2 metres with 8 degrees of skew to suit the creek alignment. The structures comprise a northbound carriageway bridge and a separate southbound bridge over Swamp Creek. The superstructure is made up of 480 millimetre deep prestressed concrete planks with a reinforced concrete deck slab. Notes Drawings are for illustrative purposes only. For dimensions and extent of works refer to Engineers Drawings. For Landscaping types and extents refer to Landscape Drawings. Design may be subject to change in the detailed design process. Landscaping on approaches to all combined drainage/ fauna underpasses must be reviewed by Project Ecologist and signed off by OEH. Piers are located clear of the Creek and 1050 millimetre diameter bored piles with 750 millimetre diameter column extensions have been adopted. The pier headstock depth is 900 millimetre and the width is 1000 millimetre. During detailed design the design for the shape of the headstocks has been simplified to be consistent with similar creek crossing bridges in the Hunter Alliance design. The abutments are spill-through and the headstocks are supported on 750 millimetre diameter bored piles. A batter slope of 1.5 to 1 has been adopted with scour protection for the 2000 year ARI flood. Twin rail barriers are detailed along the parapets with provision for two conduits in each barrier. Longitudinal drainage will be provided on each bridge. Provision has been made for Energy Australia conduits on the northbound bridge, suspended between planks. Fauna and fish friendly access under the bridges has been provided. Figure B.7.1.1 92 0 BR04 Twin Bridges over Swamp Creek: Elevation HBO+EMTB SEPTEMBER 2011 SYU-002251 10 20m H U N T E R E X P R E S S W AY: K U R R I K U R R I T O B R A N X T O N - F I N A L U R B A N + L A N D S C A P E D E S I G N S U B P L A N R E P O R T ( 1 0 0 % )