Supplier Scheduling Systems Min/Max and PODS Suppliers Greg Smiley Central Supply Chain Procurement Systems Min/Max Supplier Training Min/Max Concept Min/Max History Min/Max Web Screens in the Portal Order Policy - Min and Max Values Min/Max System Updates PODS – Purchase Order Discrete Scheduling system Instructions and Reference Supplier Scorecard Assistance Slide 2 Min/Max Supplier Training - Concept Simple system where minimum and maximum inventory quantity are set for each part number Vought inventory levels are then managed by the supplier between the minimum and maximum levels Replenishment: The supplier action of ordering, producing and shipping product to Vought Vought receiving parts up to the max qty, prior to the inventory quantity going below the min qty Slide 3 Min/Max Supplier Training - Concept 40 Maximum 35 Inventory Quantity 30 25 Replenishment Replenishment 20 Consumption Consumption Consumption 15 10 Minimum 5 0 0 1 2 3 4 5 6 7 8 9 10 11 12 Time Beginning Inventory = 25 pcs Monthly Demand = 2 pcs Slide 4 13 14 Min/Max Supplier Training - History Late 2001 Min/Max inventory management was identified as a process and system to replace APORs In 2002 the first supplier began working to an early MM process (Excel spreadsheet) In July 2009 we have 42 suppliers in MM and approximately 50% of all parts purchased by Vought are managed in the Min/Max system 2009 decision was announced to abandon APORs and move to Min/Max as much as possible In August 2009 we moved most suppliers out of APORs and into Min/Max or PODS. Slide 5 Min/Max Supplier Training - Portal Slide 6 Min/Max Supplier Training - Portal Slide 7 Min/Max Supplier Training - Portal Part Number • Part Number as listed on Purchase Order • Only Part Numbers with open POs are listed Slide 8 Min/Max Supplier Training - Portal CH – Change Flag • An asterisk is shown when one of following conditions are • present: New Part Number, changed Min or Max value, new Purchase Order, or a new receipt is listed. The asterisk remains for 7 days Slide 9 Min/Max Supplier Training - Portal Site • Site that uses the part: STU, HAW, MSF, JSF, NAS, MIL Slide 10 Min/Max Supplier Training - Portal Min Qty – Inv Qty – Max Qty • Min value that inventory is to be maintained above • Inventory Qty (updated nightly) • Max value that inventory is to be maintained below Colors • Red = Under Min • Blue = Over Max • Green = Contact Buyer Slide 11 Min/Max Supplier Training - Portal Dir – Direction • Inventory vs Min or Max – U = Under = Inventory < Minimum – O = Over = Inventory > Maximum – V = Vought = Contact Buyer Slide 12 Min/Max Supplier Training - Portal Priority Need Date (Initial sort of web screen) • If the Inv Qty does not support a manufacturing need date within • the next 30 days, a Priority Need Date is displayed This is to help the supplier to identify critical PN requirements and potential shortages Slide 13 Min/Max Supplier Training - Portal Metric Eff Date – Metric Effective Date (MED) • For purposes of measurement of seller’s performance to min/max inventory management, the parties will agree to a metric effective date (MED) which shall be the date after which the seller agrees to manage the buyer’s inventory within the Min/Max range. If there is no date, the expectation is that the supplier is responsible for maintaining the inventory between the Min and the Max. Slide 14 Min/Max Supplier Training - Portal Behind Sch Demand – Behind Schedule Demand • If Vought’s manufacturing operation is behind schedule and did not pull parts from inventory in a prior month, the qty of those parts is listed. These quantities will be consumed prior to consuming parts in the “current” month. Slide 15 Min/Max Supplier Training - Portal Monthly Demand / Planned Consumption • The web page displays 12 discrete months (rolling) of planned consumption Download file has 24 months of planned consumption • • Suppliers may not have all the planned consumption on PO Slide 16 Min/Max Supplier Training - Portal Total Horizon Qty • Total quantity of parts loaded into Vought’s Master Schedule / • MRP System Supplier may not have the Total Horizon Quantity on open POs Slide 17 Min/Max Supplier Training - Portal Lead Time Calendar Days • The supplier lead-time in calendar days for the specific PN • (includes raw material acquisition and fabrication time) If these values are incorrect, please notify your Vought buyer that your lead-times have changed Slide 18 Min/Max Supplier Training - Portal Program • The Vought program that the PN supports Slide 19 Min/Max Supplier Training - Portal PO Number – PO Item – Open Qty • A listing of all open POs, item numbers & the remaining open qty • For a PN to show in MM there needs to be at least one open PO • There can be more than one PO open for a PN Slide 20 Min/Max Supplier Training - Portal Total Open Qty • This represents the sum of all open PO quantities Slide 21 Min/Max Supplier Training - Portal Last Receipt Date – Last Receipt Qty • The date of the last receipt of this PN • The quantity of the last receipt of this PN • The download file lists the last 5 receipts Slide 22 Min/Max Supplier Training - Portal Colorization of Consumption Plan Current Inv = 22 – (0 + 3 + 7+ 7) =7 7)12 +=7still 5)<<Min above 0 = =Red Yellow Min Slide 23 Min/Max Supplier Training - Portal Online Sort Capability • Underlined headings indicate a data field that can be sorted Slide 24 Min/Max Supplier Training – Download File Sample Supplier Slide 25 Min/Max Supplier Training – Download File Text file, tab delimited that can be opened by MicroSoft Excel (from within Excel). The same data as displayed on the web, but includes 24 months of demand and 5 receipt dates and quantities. Slide 26 Min/Max Supplier Training – Order Policy Monthly $ Usage Under $160 Min Ship Qty/ Max Span Ships Year 2 Mo 14 Mo 12 Mo 1 $161 to $300 1.5 Mo 7.5 Mo 6 Mo 2 1 Mo 5 Mo 4 Mo 3 $1K to $2K 0.5 Mo 2.5 Mo 2 Mo 6 Over $2K 0.5 Mo 1.5 Mo 1 Mo 12 $301 to $1K Slide 27 Min/Max Supplier Training – System Updates Real-time Updates (if input or changed by buyer) • Metric Effective Dates (MED) • Min Values • Max Values Nightly updates to MM system • Inventory values • Purchase Orders • Receipt information Weekly Updates to MM system • Demand data Slide 28 Min/Max and PODS Supplier Training Min/Max and PODS • APORs was replaced by Purchase Order Discrete Scheduling • System (PODS) – August 2009 Vought will have the ability to control by PN those parts that are in Min/Max vs PODS – PODS candidate PNs – High dollar, out of production spares, etc. • Some suppliers will have parts in both systems • Part delivery requirements/dates will be per the schedule on the • paper PO and will be reflected on the PODS screen Nothing automated. If the delivery requirements/dates change, supplier will receive a revised PO with the new dates Slide 29 PODS Supplier Training Slide 30 PODS Supplier Training Slide 31 PODS Supplier Training Slide 32 PODS Supplier Training ABC MACHINE SHOP INC Slide 33 Min/Max and PODS Supplier Training Slide 34 Min/Max and PODS Supplier Training Slide 35 Supplier Training – Supplier Scorecard Slide 36 Supplier Training – Supplier Scorecard PODS • Measures rolling twelve month average reflecting percentage of shipments that were shipped on or before the contract negotiated ship date Min/Max • Measures ratio of Part Numbers with: – At least one open Purchase Order; – Inventory under Min – Without a Metric Effective Date – (MED) in the future; Inventory over Max – Without a Metric Effective Date (MED) in the future Slide 37 Min/Max and PODS – Assistance Scheduling Standard Note – S121 • Nick Dyer • (972) 946-3285 • nick_dyer@voughtaircraft.com Min or Max Values and MEDs • Contact your Vought Buyer Portal, Min/Max or PODS Systems & Training • Greg Smiley • (972) 946-3181 • greg_smiley@voughtaircraft.com Slide 38 Min/Max Supplier Training Slide 39