MMM Group, a WSP company Regional District of Central Kootenay Arrow Creek Transmission Main - Phase 4 and Erickson Reservoir Site Grading Tender Documents Unit Price Contract Reference No. 11-5700-ERK-20 COMMUNITIES TRANSPORTATION BUILDINGS INFRASTRUCTURE March 2016 MASTER MUNICIPAL CONSTRUCTION DOCUMENTS – UNIT PRICE CONTRACT Arrow Creek Transmission Main – Phase 4 and Erickson Reservoir Site Grading Reference No. 11-5700-ERK-20 CONTENTS The complete Regional District of Central Kootenay (RDCK) Unit Price Contract Documents are based on the Master Municipal Construction Documents and consist of the following parts: 1. Standard Documents provided herein that Require Additional Information (available in the “MMCD – Tender Document Production Manual” or on disk) Invitation to Tenderers Instructions to Tender – Part I Form of Tender Appendix 1 – Schedule of Quantities and Prices Appendix 2 – Preliminary Construction Schedule Appendix 3 – Experience of Superintendent Appendix 4 – Comparable Work Experience Appendix 5 – Subcontractors Agreement Schedule 1 – Schedule of Contract Documents Schedule 2 – List of Drawings Supplementary General Conditions Supplementary Specifications Supplementary Standard Detail Drawings 2. Standard Documents that must be obtained by the Tenderer / Contractor and are Fully Complete (available in the “MMCD – General Conditions, Specifications and Standard Detail Drawings”) Master Municipal Construction Documents, Platinum Edition Volume II, 2009 (Available at MMCDA website mmcd.net ) Instructions to Tender – Part II General Conditions Schedules and Diagrams Schedule 17.5.3 – Letter Agreement with Referee Flow Chart – Changes and Extra Work Flow Chart – Disputes Resolution Process Standard Specifications Standard Detail Drawings All MMCD Platinum Supplemental Updates, up to and including March 1st, 2016 (document corrections prepared by MMCDA) (Available at MMCDA website mmcd.net ). 3. Appendix A: Geotechnical Report – Golder Associates, file number 10-1494-0270 – included as Reference Only MMCD - JANUARY 1996 (REV. APRIL 2000) Tenderer’s Initials REGIONAL DISTRICT CENTRAL KOOTENAY UNIT PRICE CONTRACT Owner: Contract: Reference No.: OF INVITATION TO TENDERERS INVITATION TO TENDERERS PAGE 1 OF 1 2016 The Regional District of Central Kootenay Arrow Creek Transmission Main – Phase 4 and Erickson Reservoir Site Grading 11-5700-ERK-20 The Regional District of Central Kootenay invites tenders for construction of watermain and reservoir site grading works in Erickson, BC (near Creston). A summary of specific work items includes the following: • • Supply and installation of approximately 2,000 metres of 600 mm diameter and 400 m of 450 mm diameter PVC watermain including service replacements, all appurtenances and all restoration works Reservoir site grading including access road, overflow pond and associated works Electronic Contract Documents are available on the RDCK web site at: http://www.rdck.ca/EN/main/administration/bids-tenders.html Hardcopy Contract Documents are not available. A bidder’s list will be compiled by the Contract Administrator at the mandatory site meeting. The list will be made available upon request. It is the sole responsibility of the proponent to check the RDCK’s website for any updated information and addenda issued before the closing date. www.rdck.ca is the only authorized website to obtain competitive bid documents for RDCK opportunities. The RDCK shall not be held responsible for our competitive bid documents that are located on any other website. The opportunity will be advertised on BCBid but the Electronic Contract Documents will not be available on BCBid. Tenderers are required to attend a mandatory site meeting on Thursday March 10th, 2016 at 1:00 PM at the project site at the intersection of 36th Avenue and Haskins Road. Tenderers are reminded that 1pm in Creston is 12pm Pacific Standard Time. Questions and clarifications regarding the Tender must be submitted to MMM Group no later than March 23rd, 2016 at 3:00 PM. Tenders are scheduled to close: Tender Closing Time: 2:00 PM Local Time Tender Closing Date: Thursday March 31st, 2016 at The Regional District of Central Kootenay 202 Lakeside Drive, Nelson, BC V1L 5R4 For additional information, please contact: Jim Roe, AScT, Contract Administrator MMM Group, a WSP company Phone: 250-869-1334 Email: RoeJ@mmm.ca REGIONAL DISTRICT CENTRAL KOOTENAY UNIT PRICE CONTRACT OF INSTRUCTIONS TO TENDERERS PART I TABLE OF CONTENTS IT – PART I 1 OF 2 2016 1.0 Introduction ........................................................ """""""""""""""IT - 1 2.0 Tender Documents ............................................ """""""""""""""IT - 1 3.0 Submission of Tenders ......................................................... """""""""IT - 2 4.0 Additional Instructions to Tenderers"""""""" ............ """"""""IT - 3 REGIONAL DISTRICT CENTRAL KOOTENAY UNIT PRICE CONTRACT OF INSTRUCTIONS TO TENDERERS PART I THIS PAGE INTENTIONALLY LEFT BLANK TABLE OF CONTENTS IT – PART I 2 OF 2 2016 THE REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT INSTRUCTIONS TO TENDERERS PART I IT – PART I IT - 1 2016 (FOR USE WHEN UNIT PRICES FORM THE BASIS OF PAYMENT TO BE USED ONLY WITH THE GENERAL CONDITIONS AND OTHER STANDARD DOCUMENTS OF THE UNIT PRICE MASTER MUNICIPAL CONSTRUCTION DOCUMENTS.) (TO BE READ WITH “INSTRUCTIONS TO TENDERERS - PART II” CONTAINED IN THE EDITION OF THE PUBLICATION “MASTER MUNICIPAL CONSTRUCTION DOCUMENTS” SPECIFIED IN ARTICLE 2.2 BELOW) Owner: The Regional District of Central Kootenay ( NAME OF OWNER ) Contract: Arrow Creek Transmission Main – Phase 4 and Erickson Reservoir Site Grading ( TITLE OF CONTRACT ) Reference No. 11-5700-ERK-20 ( OWNER’S CONTRACT REFERENCE NO. ) 1.0 Introduction 1.1 These Instructions apply to and govern the preparation of tenders for this Contract. The Contract is generally for the following work: • • Supply and installation of approximately 2,000 metres of 600 mm diameter and 400 m of 450 mm diameter PVC watermain including service replacements, all appurtenances and all restoration works Reservoir site grading including access road, overflow pond and associated works ( BRIEF DESCRIPTION OF THE WORK ) 1.2 Direct all inquiries regarding the Contract, to: Jim Roe, Contract Administrator MMM Group, a WSP company ( NAME AND POSITION OF INDIVIDUAL WHO WILL ANSWER INQUIRIS ) Address: 540 Leon Avenue Kelowna, BC V1Y 6J6 Email: RoeJ@mmm.ca 2.0 Tender Documents 2.1 Phone: 250 869 - 1334 Fax: 250 862 - 4849 The tender documents which a tenderer should review to prepare a tender consist of all of the Contract Documents listed in Schedule 1 entitled “Schedule of Contract Documents”. Schedule 1 is attached to the Agreement which is included as part of the tender package. The Contract Documents include the drawings listed in Schedule 2 to the Agreement, entitled “List of Contract Drawings”. THE REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT 3.0 Submission of Tenders IT – PART I INSTRUCTIONS TO TENDERERS PART I IT - 2 2016 2.2 A portion of the Contract Documents are included by reference. Copies of these documents have not been included with the tender package. These documents are the Instructions to Tenderers - Part II, General Conditions, Specifications and Standard Detail Drawings. They are those contained in the publication entitled “Master Municipal Construction Documents - General Conditions, Specifications and Standard Detail Drawings”. Refer to Schedule 1 to the Agreement or, if not specified in Schedule 1, then the applicable edition shall be the most recent edition as of the date of the Tender Closing Date. All sections of this publication are by reference included in the Contract Documents. 2.3 Any additional information made available to tenderers prior to the Tender Closing Time by the Owner or representative of the Owner, such as geotechnical reports or as-built plans, which is not expressly included in Schedule 1 or Schedule 2 to the Agreement, is not included in the Contract Documents. Such additional information is made available only for the assistance of tenderers who must make their own judgment about its reliability, accuracy, completeness and relevance to the Contract, and neither the Owner nor any representative of the Owner gives any guarantee or representation that the additional information is reliable, accurate, complete or relevant. 3.1 Tenders must be submitted in a sealed envelope, marked on the outside with the above Contract Title and Reference No., and must be received by the office of: Project Manager, Regional District of Central Kootenay (TITLE OF POSITION) on or before: Tender Closing Time: Tender Closing Date: , 2:00 st March 31 , 2016 pm local time at Address: The Regional District of Central Kootenay 202 Lakeside Drive Nelson, BC Fax: 250 3.2 352 V1L 5R4 - 9300 (for tender amendments only) Late tenders will not be accepted or considered, and will be returned unopened. THE REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT 4.0 Additional Instructions to Tenderers INSTRUCTIONS TO TENDERERS PART I IT – PART I IT - 3 2016 4.1 4.2 MMCD Instructions to Tenderers – Part II, Paragraph IT 15.1 is deleted and replaced by the following: 15.1 The Owner reserves the right to: 15.1.1 reject any or all tenders; the lowest tender will not necessarily be accepted. 15.1.2 waive informalities in or reject any or all tenders or accept the tender deemed most favourable in the interest of the Regional District of Central Kootenay. 15.1.3 reject any tenders of a tenderer if the tendered or its principal(s) have, within two years of the date of Invitation to Tenders, been engaged in pursuing claims for damages or compensation of any kind against the Regional District of Central Kootenay in relation to work similar to that being tendered. 15.1.4 cancel the tendering process at any time without reason and without claim damages. 15.1.5 select a Contractor that will give the greatest value based on quality, service and price. Pre-Tender Meeting A mandatory pre-tender meeting will be held on Thursday, March 10th, 2016 at 1:00 PM at the at the project site at the intersection of 36th Avenue and Haskins Road. Design team members and the Regional District of Central Kootenay will be available to answer questions regarding the tender. Any new information that is requested or generated will be included in an Addendum that will be issued at least three days prior to the Tender Close. 4.3 Deadline for Questions and Clarifications Questions and clarifications regarding the Tender must be submitted to the Contract Administrator no later than March 23rd, 2016 at 3pm. 4.4 Construction Schedule Milestone Dates for the project are listed in the Form of Tender, Appendix 2 – Preliminary Construction Schedule. Construction of certain portions of the work will only be allowed between certain dates. Detailed schedule requirements are identified in the Special Provisions. 4.5 Construction Site Surface Features The existence and location of all surface features which may be encountered during construction are not guaranteed to be shown on the Drawings. Notwithstanding any other provision of this Contract, the Contractor shall be solely responsible for confirming the existence, extent and location of surface features either shown on the Drawings or not, and the effect they may have on the Work. Surface features to be confirmed as part of the tender preparation shall include but not be limited to retaining walls, trees, shrubbery, ornamental features, signs, walkways, fences, THE REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT INSTRUCTIONS TO TENDERERS PART I IT – PART I IT - 4 2016 irrigation and utility boxes. Unless specifically noted otherwise, no additional compensation will be made for protection, restoration or removal of surface features affected by the Work, or for the effect they may have upon the Work itself. 4.6 Survey Layout and Digital Base Drawing Survey layout for all Work shall be the Contractor’s responsibility. The Contract Administrator will provide a digital base plan in AutoCAD format, including survey control points and bench marks. The Contractor’s surveyor shall locate, confirm and protect control points and preserve permanent reference points during construction, including property pins and survey monuments. 4.7 Reference Material Geotechnical Assessment Report (See Appendix A) A geotechnical assessment report prepared by Golder Associates is contained in Appendix A. The report is provided as reference material only and is not part of the Contract Documents. The report provides information and recommendations for the design of the works and is prepared primarily for the use of the Designer. 4.8 Traffic Management The Contractor is responsible for the implementation of a traffic management strategy that is acceptable to the Regional District of Central Kootenay, the Town of Creston and the Ministry of Transportation and Infrastructure. Additional traffic management requirements are identified in the Special Provisions. 4.9 Incidental Items This contract is intended to include all works necessary to complete the project scope. Any items that are incidental to the project scope, as shown on the drawings or described in the contract documents, are to be included in the various unit prices on the Form of Tender. 4.10 The Owner may, at their sole discretion, choose to eliminate some or all "DR41" PVC C905 Watermain from the project and replace it with "DR32.5" PVC C905 Watermain. Should the Owner elect to make this change, the 15% Variance Threshold Percentage for Unit Rate Item’s ‘4.1’, ‘4.2’, ‘4.5’ and ‘4.6’ will not be applicable. If the Owner makes this change, applicable “DR32.5” Unit Rates will apply. There will be no consideration for additional payment above the applicable ‘DR32.5’ Unit Rates. This change, if made, will be formalized by way of Change Order after the Award of the Contract. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT FORM OF TENDER FORM OF TENDER PAGE 1 OF 3 2016 FOR USE WHEN UNIT PRICES FORM THE BASIS OF PAYMENT - TO BE USED ONLY WITH THE GENERAL CONDITIONS AND OTHER STANDARD DOCUMENTS OF THE UNIT PRICE MASTER MUNICIPAL CONSTRUCTION DOCUMENTS. The Regional District of Central Kootenay Owner: ( NAME OF OWNER ) Arrow Creek Transmission Main – Phase 4 And Erickson Reservoir Site Grading Contract: ( TITLE OF CONTRACT ) 11-5700-ERK-20 Reference No. ( OWNER’S CONTRACT REFERENCE NO. ) To Owner: WE, THE UNDERSIGNED: 1.1 have received and carefully reviewed all of the Contract Documents, including the Instructions to Tenderers, the specified edition of the “Master Municipal Construction Documents - General Conditions, Specifications and Standard Detail Drawings” and the following Addenda: ; ( ADDENDA, IF ANY ) ACCORDINGLY WE HEREBY OFFER 1.2 have full knowledge of the Place of the Work, and the Work required; and 1.3 have complied with the Instructions to Tenderers; and 2.1 to perform and complete all of the Work and to provide all the labour, equipment and material all as set out in the Contract Documents, in strict compliance with the Contract Documents; and 2.2 to achieve the Milestone Dates, including the dates for Substantial Performance and Total Performance of the Work as listed in Appendix 2 of this For of Tender; and 2.3 to do the Work for the price, which is the sum of the products of the actual quantities incorporated into the Work and the appropriate unit prices set out in Appendix 1, the “Schedule of Quantities and Prices”, plus any lump sums or specific prices and adjustment amounts as provided by the Contract Documents. For the purposes of tender comparison, our offer is to complete the Work for the “Tender Price” as set out on Appendix 1 of this Form of Tender. Our Tender Price is based on the estimated quantities listed in the Schedule of Quantities and Prices, and excludes GST. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT FORM OF TENDER FORM OF TENDER PAGE 2 OF 3 2016 WE CONFIRM: 3.1 that we understand and agree that the quantities as listed in the Schedule of Quantities and Prices are estimated, and that the actual quantities will vary. WE CONFIRM: 4.1 that the following appendices are attached to and form a part of this tender: WE AGREE: 5.1 4.1.1 the appendices as required by paragraph 5.3 of the Instructions to Tenderers – Part II; and 4.1.2 the Bid Security as required by paragraph 5.2 of the Instructions to Tenderers – Part II. that this tender will be irrevocable and open for acceptance by the Owner for a period of 30 calendar days from the day following the Tender Closing Date and Time, even if the tender of another tenderer is accepted by the Owner. If within this period the Owner delivers a written notice (“Notice of Award”) by which the Owner accepts our tender we will: 5.1.1 5.1.2 within 15 Days of receipt of the written Notice of Award deliver to the Owner: .1 a Performance Bond and a Labour and Material Payment Bond, each in the amount of 50% of the Contract Price, covering the performance of the Work including the Contractor’s obligations during the Maintenance Period, issued by a surety licensed to carry on the business of suretyship in the province of British Columbia, and in a form acceptable to the Owner; .2 a Baseline Construction Schedule, as provided by GC 4.6.1; .3 a “clearance letter” indicating that the tenderer is in Worksafe BC compliance; .4 a copy of the insurance policies as specified in GC 24 indicating that all such insurance coverage is in place; .5 a signed “Prime Contractor Declaration” confirming requirements of GC 21.2; .6 a suitable Business License; form within 2 Days of receipt of written “Notice to Proceed”, or such longer time as may be otherwise specified in the Notice to Proceed, commence the Work; and REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT FORM OF TENDER 5.1.3 WE AGREE: 6.1 FORM OF TENDER PAGE 3 OF 3 2016 sign the Contract Documents as required by GC 2.1.2. that, if we receive written Notice of Award of this Contract and, contrary to paragraph 5 of this Form of Tender, we: 6.1.1 fail or refuse to deliver the documents as specified by paragraph 5.1.1 of this Form of Tender; or 6.1.2 fail or refuse to commence the Work as required by the Notice to Proceed, then such failure or refusal will be deemed to be a refusal by us to enter into the Contract and the Owner may, on written notice to us, award the Contract to another party. We further agree that, as full compensation on account of damages suffered by the Owner because of such failure or refusal, the Bid Security shall be forfeited to the Owner, in an amount equal to the lesser of: 6.1.3 the face value of the Bid Security; and 6.1.4 the amount by which our Tender Price is less than the amount for which the Owner contracts with another party to perform the Work. OUR ADDRESS IS AS FOLLOWS: Phone: Fax: Attention: This Tender is executed this _______ day of ______________________, 20 ______. Contractor: (FULL LEGAL NAME OF CORPORATION, PARTNERSHIP OR INDIVIDUAL) (AUTHORIZED SIGNATORY) (AUTHORIZED SIGNATORY) Regional Disctrict of Central Kootenay UNIT PRICE CONTRACT APPENDIX 1 SCHEDULE OF QUANTITIES AND PRICES Appendix 1 PAGE 1 OF 4 Arrow Creek Transmission Main – Phase 4 And Erickson Reservoir Site Grading Reference # 11-5700-ERK-20 Form of Tender Appendix 1 QUANTITIES AND PRICES Beam Road, 36th. Ave., Haskins Road Summary Sheet Section Title 1 General Requirements 2 Reservoir 3 Roads 4 Utilities 5 150mm watermain on Beam Road (Optional) 6 Additional Optional Items Amount Tender Price GST %5 Tender Price plus GST Tenderer's Initials _____________________ March 1st, 2016 Regional Disctrict of Central Kootenay UNIT PRICE CONTRACT Payment Section Para Item # 1 APPENDIX 1 SCHEDULE OF QUANTITIES AND PRICES Appendix 1 PAGE 2 OF 4 Item Description Unit Quantity Unit Price Amount $20,000.00 $20,000.00 General Requirements 1.1 01 53 01 SSpec 1 Mobilization / De-Mobilization l.s. 1 1.2 01 33 01 SSpec 2 Survey Layout and Project Record Documents l.s. 1 1.3 01 55 00 SSpec 3 Traffic Control, Vehicle Access and Parking l.s. 1 1.4 01 57 01 SSpec 4 Erosion and Sediment Control l.s. 1 Sub-Total Division 1 2 Reservoir 2.1 31 11 01 SSpec 5 Clearing and Grubbing l.s. 1 2.2 31 22 01 SSpec 6 Topsoil Stripping m2 2385 2.3 31 22 01 SSpec 7 Mass Site Grading - Common Excavation - Excavation to Embankment m3 1725 2.5 31 23 17 SSpec 9 Rock Removal - To Embankment m3 3840 m3 1330 2.7 31 24 13 Sspec 10 Rock Removal - To Offsite Disposal 2.8 33 11 01 1.8.1/.2 600mm diameter DR41 PVC Watermain 2.9 33 11 01 SSpec 12 2.10 33 11 01 2.11 33 11 01 2.12 l.m. 6 600 FxH Gate Valve ea 2 SSpec 12 600 FxF Gate Valve ea 1 SSpec 12 600F x 600H x 600F Tee ea 2 33 11 01 SSpec 12 600mm diameter PVC Cap ea 2 2.13 33 42 13 1.5.3 Storm Headwall ea. 2 2.14 33 40 01 1.6.1/.2 2.15 33 44 01 1.5.1.1/.2 2.16 32 92 19 1.8.1/.2 450mm diamter SDR35 PVC Storm sewer l.m. 70 1050mm diameter manhole c/w base, concrete riser, lid, frame, and cover ea. 3 Hydroseeding of disturbed areas following mass site grading m2 2600 Sub-Total Division 2 3 Roads 3.1 31 11 01 1.4.2 Tree Removal and Disposal l.s. 1 3.2 32 11 16.1 1.4.3 Crushed Granular Sub-Base, 300mm thickness m2 5446 3.3 32 11 23 1.4.2 Granular Base, 225mm thickness m2 5067 3.4 32 12 16 SSpec 11 AC Pavement, 50mm thickness m2 5018 Sub-Total Division 3 4 4.1 Utilities 33 11 01 1.8.1/.2 450mm diameter DR41 PVC C905 Watermain l.m. 200 l.m. 134 4.2 33 11 01 1.8.1/.2 450mm diameter DR32.5 PVC C905 Watermain 4.3 33 11 01 1.8.1/.2 450mm diameter DR25 PVC C905 Watermain l.m. 70 4.4 33 11 01 1.8.1/.2 600mm diameter DR25 PVC C905 Watermain l.m. 780 4.5 33 11 01 1.8.1/.2 600mm diameter DR32.5 PVC C905 Watermain l.m. 190 4.6 33 11 01 1.8.1/.2 600mm diameter DR41 PVC C905 Watermain l.m. 998 4.7 33 11 01 1.8.5 150mm X 50mm diameter Blowoff Assembly as per MMCD W8, c/w 1050mm x 300mm MH barrel, lid, frame & cover ea. 1 4.8 33 11 01 1.8.4 25mm diameter water service: 100mm x 25mm service saddle, corp stop, pipe, curb stop and all miscellaneous fittings ea 2 4.9 33 11 01 1.8.4 25mm diameter water service: 150mm x 25mm service saddle, corp stop, pipe, curb stop and all miscellaneous fittings ea 3 4.10 33 11 01 1.8.4 50mm diameter water service: 150mm x 50mm service saddle, corp stop, pipe, curb stop, coupler, and all miscellaneous fittings ea 9 4.11 33 11 01 1.8.4 50mm diameter twin water service: 100mm x 50mm service saddle, 50mm corp stop, 15m x 50mm tubing, 50x25x25 Tee, 20m x 25mm tubing, 2-25mm curb stops, 2 marker posts ea 1 Tenderer's Initials _____________________ March 1st, 2016 Regional Disctrict of Central Kootenay UNIT PRICE CONTRACT Payment Section Para Item # APPENDIX 1 SCHEDULE OF QUANTITIES AND PRICES Item Description Appendix 1 PAGE 3 OF 4 Unit Quantity 4.12 33 11 01 1.8.4 50mm diameter twin water service: 150mm x 50mm service saddle, 50mm corp stop, 15m x 50mm tubing, 50x25x25 Tee, 20m x 25mm tubing, 2-25mm curb stops, 2 marker posts ea 2 4.13 33 11 01 1.8.4 50mm diameter water service: 600mm x 50mm service saddle, corp stop, pipe, curb stop, coupler, and all miscellaneous fittings ea 4 4.14 33 11 01 1.8.4 75mm diameter water service: 150mm x 75mm service saddle, 75mm gate valve, 75mm HDPE piping, and all miscellaneous fittings ea 1 4.15 33 11 01 SSpec 12 150H x 150H x 150H Tee ea 3 4.16 33 11 01 SSpec 12 150mm Robar couplings ea 6 4.17 33 11 01 1.8.1/.2 150mm Spool pieces flanged one end ea 6 4.18 33 11 01 SSpec 12 150 FxF 45 degree bend ea 2 4.19 33 11 01 SSpec 12 150 FxF gate valve ea 2 4.20 33 11 01 SSpec 12 150 FxH gate valve ea 3 4.21 33 11 01 SSpec 12 250FxF gate valve ea 1 4.22 33 11 01 SSpec 12 250FxH 45 degree bend ea 1 4.23 33 11 01 SSpec 12 250HxH 45 degree bend ea 1 4.24 33 11 01 SSpec 12 250H x 250H x 150F Tee ea 1 4.25 33 11 01 SSpec 12 250mm Robar couplings ea 2 4.26 33 11 01 1.8.1/.2 250mm C900 PVC pipe m 3 4.27 33 11 01 SSpec 12 450mm diameter mainline gate valves (all styles) ea 2 4.28 33 11 01 SSpec 12 450mm HF 45 degree bend ea 3 4.29 33 11 01 SSpec 12 450mm FH 11.25 degree bend ea 1 4.30 33 11 01 SSpec 12 450mm FH 5 degree bend ea 1 4.31 33 11 01 SSpec 12 600mm diameter mainline gate valve (all styles) ea 3 4.32 33 11 01 SSpec 12 600mm HxH 45 degree bend ea 7 4.33 33 11 01 SSpec 12 600mm HxF 45 degree bend ea 3 4.34 33 11 01 SSpec 12 600mm HxH 22.5 degree bend ea 7 4.35 33 11 01 SSpec 12 600mm HxH 11.25 degree bend ea 1 4.36 33 11 01 SSpec 12 600mm HxH 5 degree bend ea 1 4.37 33 11 01 SSpec 12 600F x 600F x 600F Tee ea 1 4.38 33 11 01 SSpec 12 600H x 600H x 150H Tee ea 3 4.39 33 11 01 SSpec 12 600H x 600H x 150F Tee ea 2 4.40 33 11 01 SSpec 12 600H x 450F reducer ea 1 4.41 33 11 01 SSpec 12 600H x 600H x 250F Tee ea 1 4.42 33 11 01 1.8.5 Air Release Valve Assembly as per Detail 11 Dwg D102 ea. 1 4.43 33 11 01 1.8.9 Pipe Anchor Blocks as per MMCD Detail G8 Dwg D103 ea. 57 1.8.1/.2 Low Point Drain as per Detail 2 Dwg D101. Tee, bend and gate valve are included in Fittings list above. ea. 2 SSpec 13 Existing water system removals, salvage, disposal, and decommissioning as shown on drawings l.s. 1 SSpec 14 Relocate and reinstall existing water meter at 33rd Avenue ea. 1 SSpec 14 Relocate and reinstall existing water meter at 35th Avenue ea. 1 ea. 1 ea. 2 4.44 4.45 4.46 4.47 33 11 01 33 11 01 33 11 01 33 11 01 4.48 33 11 01 SSpec 14 Relocate and reinstall existing water meter at Sylvester Road 4.49 33 11 01 SSpec 14 Relocate and reinstall existing water meter along Haskins Road East Tenderer's Initials _____________________ Unit Price Amount March 1st, 2016 Regional Disctrict of Central Kootenay UNIT PRICE CONTRACT Payment Section Para Item # APPENDIX 1 SCHEDULE OF QUANTITIES AND PRICES Appendix 1 PAGE 4 OF 4 Item Description Unit Quantity 4.50 33 11 01 SSpec 15 Install new 50mm water meter along Haskins Road East ea. 4 4.51 33 11 01 SSpec 15 Install new 150mm water meter along Haskins Road East ea. 1 4.52 32 92 19 1.8.1/.2 Hydroseeding of disturbed areas following watermain installation m2 6000 Unit Price Amount Sub-Total Division 4 5 5.1 150mm Watermain on Beam Road (Optional) 33 11 01 1.8.1/.2 150mm diameter DR41 PVC C900 Watermain l.m. 330 Sub-Total Division 5 6 Additional Optional Items 6.1 33 11 01 1.8.2/.3/.4 Install new water meter and chamber (MMCD Detail W2C) on new 25mm water service ea. 6 6.2 33 11 01 1.8.2/.3/.4 Install new water meter and chamber (MMCD Detail W2D) on new 50mm water service ea. 10 Sub-Total Division 6 Tenderer's Initials _____________________ March 1st, 2016 REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE APPENDIX 2 – PRELIMINARY CONSTRUCTION SCHEDULE APPENDIX 2 PAGE 1 OF 1 2016 CONTRACT Arrow Creek Transmission Main – Phase 4 And Erickson Reservoir Site Grading Reference No.: 11-5700-ERK-20 ( TITLE OF CONTRACT ) See paragraph 5.3.2 of the Instructions to Tenderers – Part II. Indicate Schedule with bar chart with major item descriptions and time. MILESTONE DATES: nd Anticipated Contract Award – April 22 , 2016 th Construction Start – May 13 , 2016 th Substantial Performance – Reservoir Site Grading – June 30 , 2016 th Substantial Performance - Remainder of Work – September 30 , 2016 st Total Performance – October 21 , 2016 ACTIVITY CONSTRUCTION SCHEDULE 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 Note: In the case of a discrepancy between the Preliminary Construction Schedule prepared by the Tenderer and the Milestone Dates prescribed by the Owner above, the Milestone Dates will govern. Tenderer’s Initials _______________________ 20 REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT APPENDIX 3 – EXPERIENCE OF SUPERINTENDENT APPENDIX 3 PAGE 1 OF 1 2016 The Regional District of Central Kootenay Arrow Creek Transmission Main – Phase 4 And Erickson Reservoir Site Grading Reference No.: 11-5700-ERK-20 ( TITLE OF CONTRACT ) See paragraph 5.3.3 of the Instructions to Tenderers – Part II. Name: Experience: Dates: Project Name: Responsibility: References: Dates: Project Name: Responsibility: References: Dates: Project Name: Responsibility: References: Dates: Project Name: Responsibility: References: Tenderer’s Initials _______________________ REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT APPENDIX 4 – COMPARABLE WORK EXPERIENCE APPENDIX 4 PAGE 1 OF 1 2016 The Regional District of Central Kootenay Arrow Creek Transmission Main – Phase 4 and Erickson Reservoir Site Grading Reference No.: 11-5700-ERK-20 ( TITLE OF CONTRACT ) See paragraph 5.3.4 of the Instructions to Tenderers – Part II. OWNER / CONTACT NAME PROJECT PHONE and FAX Owner / Contract Phone ( ) Fax ( ) Phone ( Owner / Contract ) Fax ( ) Phone ( Owner / Contract ) Fax ( ) Phone ( Owner / Contract ) Fax ( ) Phone ( Owner / Contract ) Fax ( ) Phone ( Owner / Contract ) Fax ( ) Phone ( Owner / Contract ) Fax ( ) Phone ( Owner / Contract ) Fax ( ) Phone ( Owner / Contract ) Fax ( ) Phone ) Fax ( ) Owner / Contract Tenderer’s Initials ( _____________________________ WORK DESCRIPTION VALUE ($) REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT APPENDIX 5 PAGE 1 OF 1 2016 APPENDIX 5 - SUBCONTRACTORS The Regional District of Central Kootenay Arrow Creek Transmission Main – Phase 4 And Erickson Reservoir Site Grading Reference No.: 11-5700-ERK-20 ( TITLE OF CONTRACT ) See paragraph 5.3.5 of the Instructions to Tenderers – Part II. TENDER ITEM Tenderer’s Initials TRADE SUBCONTRACTOR NAME _______________________ PHONE NUMBER REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT FORM OF AGREEMENT FORM OF AGREEMENT PAGE 1 OF 7 2016 (FOR USE WHEN UNIT PRICES FORM THE BASIS OF PAYMENT TO BE USED ONLY WITH THE GENERAL CONDITIONS AND OTHER STANDARD DOCUMENTS OF THE UNIT PRICE MASTER MUNICIPAL CONSTRUCTION DOCUMENTS.) BETWEEN OWNER AND CONTRACTOR This agreement made in duplicate this day of Contract: , 2016. ARROW CREEK TRANSMISSION MAIN – PHASE 4 AND ERICKSON RESERVOIR SITE GRADING ( TITLE OF CONTRACT ) Reference No. 11-5700-ERK-20 (OWNER’S CONTRACT REFERENCE NO.) BETWEEN: The The Regional District of Central Kootenay ( NAME OF OWNER ) (the “Owner”) AND: ( NAME AND OFFICE ADDRESS OF CONTRACTOR ) (the “Contractor”) The Owner and the Contractor agree as follows: Article 1 The Work Start / Completion Dates 1.1 The Contractor will perform all Work and provide all labour, equipment and material and do all things strictly as required by the Contract Documents. 1.2 The Contractor will commence the Work in accordance with the Notice to Proceed. The Contractor will proceed with the Work diligently, will perform the Work generally in accordance with the construction schedules as required by the Contract Documents and will achieve the Milestone Dates, including Substantial Performance and Total Performance of the Work on or before the dates listed in Appendix 2 of the Form of Tender, subject to the provisions of the Contract Documents for adjustments to the Contract Time. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT Article 2 Contract Documents Article 3 Contract Price Article 4 Payment FORM OF AGREEMENT FORM OF AGREEMENT PAGE 2 OF 7 2016 1.3 Time shall be of the essence of the Contract. 2.1 The “Contract Documents” consist of the documents listed or referred to in Schedule 1, entitled “Schedule of Contract Documents”, which is attached and forms a part of this Agreement, and includes any and all additional and amending documents issued in accordance with the provisions of the Contract Documents. All of the Contract Documents shall constitute the entire Contract between the Owner and the Contractor. 2.2 The Contract supersedes all prior negotiations, representations or agreements, whether written or oral, and the Contract may be amended only in strict accordance with the provisions of the Contract Documents. 3.1 The price for the Work (“Contract Price”) shall be the sum in Canadian dollars of the following 1.1.1 the product of the actual quantities of the items of Work listed in the Schedule of Quantities and Prices which are incorporated into or made necessary by the Work and the unit prices listed in the Schedule of Quantities and Prices; plus 1.1.2 all lump sums, if any, as listed in the Schedule of Quantities and Prices, for items relating to or incorporated into the Work; plus 1.1.3 any adjustments, including any payments owing on account of Changes and agreed to Extra Work, approved in accordance with the provisions of the Contract Documents. 3.2 The Contract Price shall be the entire compensation owing to the Contractor for the Work and this compensation shall cover and include all profit and all costs of supervision, labour, material, equipment, overhead, financing, and all other costs and expenses whatsoever incurred in performing the Work. 4.1 Subject to applicable legislation and the provisions of the Contract Documents, the Owner shall make payments to the Contractor. 4.2 If the Owner fails to make payments to the Contractor as they become due in accordance with the terms of the Contract Documents then interest calculated at 2% per annum over the prime commercial lending rate of the Royal Bank of Canada on such unpaid amounts shall also become due and payable until payment. Such interest shall be calculated and added to any unpaid amounts monthly. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT Article 5 Rights and Remedies Article 6 Notices FORM OF AGREEMENT FORM OF AGREEMENT PAGE 3 OF 7 2016 5.1 The duties and obligations imposed by the Contract Documents and the rights and remedies available thereunder shall be in addition to and not a limitation of any duties, obligations, rights and remedies otherwise imposed or available by law. 5.2 Except as specifically set out in the Contract Documents, no action or failure to act by the Owner, Contract Administrator or Contractor shall constitute a waiver of any of the parties’ rights or duties afforded under the Contract, nor shall any such action or failure to act constitute an approval of or acquiescence in any breach under the Contract. 6.1 Communications among the Owner, the Contract Administrator and the Contractor, including all written notices required by the Contract Documents, may be delivered by hand, or by fax, or by pre-paid registered mail to the addresses as set out below: The Owner: The Regional District of Central Kootenay 202 Lakeside Drive Nelson, BC V1L 5R4 Fax: 250‐352‐9300 Attention: Jeff Phillips, Project Manager The Contractor: Fax: Attention: The Contract Administrator: MMM Group Limited 540 Leon Avenue Kelowna, BC V1Y 6J6 6.2 Fax: (250) 862-4849 Attention: Jim Roe A communication or notice that is addressed as above shall be considered to have been received 1.1.4 immediately upon delivery, if delivered by hand; or REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT FORM OF AGREEMENT FORM OF AGREEMENT PAGE 4 OF 7 2016 1.1.5 immediately upon transmission if sent by fax and received in hard copy; or 1.1.6 after 5 Days from date of posting if sent by registered mail. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT Article 7 General FORM OF AGREEMENT FORM OF AGREEMENT PAGE 5 OF 7 2016 6.3 The Owner or the Contractor may, at any time, change its address for notice by giving written notice to the other at the address then applicable. Similarly if the Contract Administrator changes its address for notice then the Owner will give or cause to be given written notice to the Contractor. 6.4 The sender of a notice by fax assumes all risk that the fax is received in hard copy. 7.1 This Contract shall be construed according to the laws of British Columbia. 7.2 The Contractor shall not, without the express written consent of the Owner, assign this Contract, or any portion of this Contract. 7.3 The headings included in the Contract Documents are for convenience only and do not form part of this Contract and will not be used to interpret, define or limit the scope or intent of this Contract or any of the provisions of the Contract Documents. 7.4 A word in the Contract Documents in the singular includes the plural and, in each case, vice versa. 7.5 This agreement shall ensure to the benefit of and be binding upon the parties and their successors, executors, administrators and assigns. IN WITNESS WHEREOF the parties hereto have executed this Agreement the day and year first written above. Contractor: (FULL LEGAL NAME OF CORPORATION, PARTNERSHIP OR INDIVIDUAL) (AUTHORIZED SIGNATORY) (AUTHORIZED SIGNATORY) Owner: The Regional District of Central Kootenay (FULL LEGAL NAME OF CORPORATION, PARTNERSHIP OR INDIVIDUAL) (AUTHORIZED SIGNATORY) (AUTHORIZED SIGNATORY) REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT FORM OF AGREEMENT FORM OF AGREEMENT PAGE 6 OF 7 2016 (INCLUDE IN LIST ALL DOCUMENTS INCLUDING, IF ANY, SUPPLEMENTARY GENERAL CONDITIONS, SUPPLEMENTARY SPECIFICATIONS, SUPPLEMENTARY STANDARD DETAIL DRAWINGS.) Schedule 1 Schedule of Contract Documents The following is an exact and complete list of the Contract Documents, as referred to in Article 2.1 of the Agreement. NOTE: The documents noted with “*” are contained in the “Master Municipal Construction Documents – Platinum Edition Volume II”, Printed 2009. All sections of these publications are included in the Contract Documents. 1.1 Agreement, including all Schedules; 1.2 Supplementary General Conditions; 1.3 Special Provisions; 1.4 General Conditions*; 1.5 Supplementary Specifications; 1.5.1 Project Specific Supplementary Specifications; 1.6 Specifications*; 1.7 Supplementary Standard Detail Drawings; 1.8 Standard Detail Drawings*; 1.9 MMCD Supplemental Updates (available at www.mmcd.net); All – up to and including March 1st, 2016 1.10 Executed Form of Tender, including all Appendices; 1.11 Contract Drawings listed in Schedule 2 to the Agreement –”List of Contract Drawings”; 1.12 Instructions to Tenderers - Part I; 1.13 Instructions to Tenderers - Part II*; 1.14 The following Addenda (if any): REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT FORM OF AGREEMENT PAGE 7 OF 7 FORM OF AGREEMENT 2016 (COMPLETE LISTING OF ALL DRAWINGS, PLANS AND SKETCHES WHICH ARE TO FORM A PART OF THE CONTRACT, OTHER THAN STANDARD DETAIL DRAWINGS AND SUPPLEMENTARY STANDARD DETAIL DRAWINGS.) Schedule 2 List of Contract Drawings TITLE DRAWING NO. DATE REVISION NO. REVISION DATE 000 2011/12/19 G Project Overview G000 2011/12/19 G 2016/03/01 2016/03/01 General Notes G001 2011/12/19 G 2016/03/01 Key Plan – South C100 2011/12/19 G 2016/03/01 South Watermain Plan – Profile (Sta. 0+620 – 0+920) C103 2011/12/19 G Beam Road Distribution Main Plan - Profile (Sta. 0+620 – 0+920) C103A 2011/12/19 D South Watermain Plan – Profile (Sta. 0+920 – 1+220) C104 2011/12/19 G Beam Road Distribution Main Plan - Profile (Sta. 0+920 – 1+220) C104A 2011/12/19 D South Watermain Plan – Profile (Sta. 1+220 – 1+530) C105 2011/12/19 G South Watermain Plan – Profile (Sta. 1+530 – 1+840) C106 2011/12/19 G South Watermain Plan – Profile (Sta. 1+840 – 2+120) C107 2011/12/19 G South Watermain Plan – Profile (Sta. 2+120 – 2+420) C108 2011/12/19 G South Watermain Plan – Profile (Sta. 2+420 – 2+740) C109 2011/12/19 G South Watermain Plan – Profile (Sta. 2+740 – Ph.2 Tie-in) C110 2011/12/19 G Erickson Reservoir Site Plan R100 2012/05/14 B 2016/03/01 Erickson Reservoir Site Plan and Profiles R101 2012/05/14 B 2016/03/01 Erickson Reservoir Sections R102 2012/05/14 B 2016/03/01 Details D101 2011/12/19 F 2016/03/01 Details D102 2011/12/19 F 2016/03/01 Details D103 2011/12/19 F 2016/03/01 Cover Sheet 2016/03/01 2016/03/01 2016/03/01 2016/03/01 2016/03/01 2016/03/01 2016/03/01 2016/03/01 2016/03/01 2016/03/01 REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT SUPPLEMENTARY GENERAL CONDITIONS PAGE 1 OF 6 2016 The General Conditions for this project are contained in the Master Municipal Construction Documents (MMCD) Platinum Edition Volume II, 2009, except as specified in the following Supplementary General Conditions and MMCD Supplemental Updates (see Schedule 1 of the Agreement). These Supplementary General Conditions take precedence over the applicable MMCD General Conditions. 1.0 DEFINITIONS SGC 1.21 – Contract Administrator SGC 1.21.1 – Delete 1.21.1 and replace with the following: “Contract Administrator” means the person appointed by the Owner and identified by the Owner in writing to the Contractor. The Contract Administrator may be the Owner’s Engineer, other employee or officer, or may be an outside consultant. 4.0 CONTRACTOR SGC 4.3 – Protection of Work, Property and the Public SGC 4.3.4 – Add the following paragraph: (4) expose all connection points and crossing locations for proposed utilities at least one week prior to construction at each site and notify the Contract Administrator of the exact location and elevation of the connection points and crossing utilities for design confirmation. If this confirmation is not completed as specified then the Contractor will not be eligible for any delay claims or extra costs incurred by conflicts or changes necessary to complete the related operations. Payment for pre-exposing of utilities will be incidental to payment for utility work unless shown otherwise in the Schedule of Quantities and Prices. SGC 4.7 – Superintendent SGC 4.7.1 – Delete 4.7.1 and replace with the following: The Contractor shall employ a competent senior representative at the Place of the Work (the “Superintendent”) who shall have the responsibility to ensure that the Work is performed in compliance with the Contract Documents. Unless otherwise permitted in writing by the Contract Administrator, the Superintendent shall be the person whose experience was submitted in Appendix 3 of the Tender. The Contractor shall also employ necessary assistants for the Superintendent and the Superintendent and assistants shall be in attendance at the Place of Work while Work is being performed. SGC 4.12 – Tests and Inspections SGC 4.12.4 – Add the following: As a minimum, the Contractor shall perform at their own cost all tests, inspections and approvals of the Work necessary for Quality Control to ensure materials, products and workmanship are in strict conformance with the Contract Documents. The Contractor shall provide the results of such tests, inspections and approvals to the Contract Administrator upon request. This is considered incidental to the project and so no separate unit rate is included for this requirement. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT SUPPLEMENTARY GENERAL CONDITIONS PAGE 2 OF 6 2016 SGC 4.12.6 (2) – Add the following: In all cases, the Contractor is responsible to facilitate and provide access to all Works for the purpose of inspection and testing. 6.0 OTHER CONTRACTORS SGC 6.1.1 – Add the following: The Contractor shall afford the Owner and any such Other Contractors reasonable opportunity for the introduction and storage of their materials and the execution of their work. The Contractor shall not commit or permit any act which will interfere with the performance of the work of the Owner or Other Contractors. SGC 6.1.2 – Add the following: If the Contractor fails to cooperate with or coordinate the Work with the work of the Owner or Other Contractors, he shall not make any claims founded on delays or costs which have resulted from such failure and he shall save the Owner harmless from all claims made by Other Contractors, which are founded on delays caused by such failure. Copies of Drawings and Specifications relating to another contract and reasonably required by the Contractor will be furnished to the Contractor on request, for his information in carrying out the above provisions SGC 6.4 – Shallow Utility Work and Work by Others – Add the following: 6.4.1 Utility removal, relocation, adjustment or upgrading work may be required to be completed by others within the work area during the project. The Owner reserves the right to make changes in the design and scope of the work as a result of conflicting utilities if required. Standard Contract clauses for Changes will apply. 6.4.2 9.0 The Contractor shall coordinate work with the RDCK, the Town of Creston, Gas, Electrical and Communication Companies, as required, for any conflicts, adjustments or protective measures. The Contractor shall permit and accommodate other contractors or companies working within the site on shallow utility work or other utility improvements. Contractor shall remain the Prime Contractor as per GC 21.2. VALUATION OF CHANGES AND EXTRA WORK 9.4 Quantity Variations GC 9.4, in its entirety, is not applicable to Unit Rate Item’s: ‘4.1, ‘4.2’, ‘4.5’, and ‘4.6’. 9.5 Adjustments of Contract Time SGC 9.5.3 – Delete 9.5.3 and replace with the following: REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT SUPPLEMENTARY GENERAL CONDITIONS PAGE 3 OF 6 2016 9.5.3 The Construction Schedule shall include allowance for all Optional Work unless specified otherwise in the Contract Documents. If the Contract Administrator authorizes Optional Work pursuant to GC 7.4.1 then the related Change Order shall not include any adjustment to the Contract Time. 10.0 FORCE ACCOUNT SGC 10.1 – Force Account Costs SGC 10.1 – Add the following subsections: 10.1.2 Within 15 Days of receipt of the written Notice of Award, the Contractor shall deliver a Force Account Rate Schedule to the Owner. The Force Account Rate Schedule shall include hourly rates for all Labour and Equipment intended to be used in completion of the works. These hourly rates are to be 'all‐inclusive', or 'all‐found'. Labour rates are to be inclusive of wages, insurance, holiday pay, benefits, small tools, overhead, and profit. Equipment rates are to be inclusive of operator, overhead, and profit. If the Owner is in agreement with the Force Account Rate Schedule as submitted, the payment for Force Account Work shall be calculated based on the rates included in the Force Account Rate Schedule, instead of the rates noted in General Conditions item 10.1.1. However, if the Owner does not agree to the rates shown in the Force Account Rate Schedule, or if the Contractor utilizes Labour, Equipment, or Subcontractors whose rates are not shown in the Force Account Rate Schedule, then MMCD items 10.1.1 (1), (2), (3), and (4) will be used to determine applicable payment for Force Account Work. 13.0 DELAYS SGC 13.1 – Delay by Owner or Contract Administrator SGC 13.1.1 (2) – Delete 13.1.1 (2) and replace with the following: 13.1.1 (2) reimbursement by the Owner for directly related out of pocket additional costs reasonably and necessarily incurred by the Contractor as a result of such delay, plus payment of a markup of 10% on such costs shall be allowed for overhead, plus a further markup of 10% on the total of the foregoing shall be allowed for profit. No payment shall be owed for lost opportunity of other indirect cost. Internal rentals and equipment standby costs are not an out of pocket additional cost. SGC 13.9 – Liquidated Damages for Late Completion Delete GC 13.9.1 (1) and replace with the following: 13.9.1(1) as a genuine pre-estimate of the Owner’s increased costs for the Contract Administrator and the Owner’s staff caused by such a delay an amount of $1,500.00 per day or pro rata portion for each Day that the actual Substantial Performance is achieved after the Substantial Performance Milestone Date; plus REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT 18.0 SUPPLEMENTARY GENERAL CONDITIONS PAGE 4 OF 6 2016 PAYMENT SGC 18.2 – Supporting Documentation SGC 18.2.3 – Add the following clause: 18.2.3 The Contractor shall provide an invoice in agreement with a finalized Payment Certificate. The invoice will accompany the Payment Certificate, and will be submitted by the Contract Administrator to the Owner for payment. SGC 18.5 - Payment SGC 18.5.1 – Delete GC 18.5.1 and replace with the following: 18.5.1 The net amount shown for payment on a Payment Certificate (and accompanying invoice per SGC 18.2.3) shall be due and payable to the Contractor on or before the 30th calendar day after the issuance of the Payment Certificate. SGC 18.6 – Substantial Performance SGC 18.6.4 – Delete GC 18.6.4 and replace with the following: 18.6.4 The Contract Administrator shall include the date of Substantial Performance in the Certificate of Substantial Performance. The date for Total Performance shall be the set number of Days after Substantial Performance as listed in Appendix 2 of the Form of Tender, unless otherwise agreed by the Contract Administrator. SGC 18.6.5 – Add the following: The Contract Administrator shall prepare a Payment Certificate for release of the lien holdback and the amount shall be due and payable in accordance with GC 18.5.1. The Contractor shall submit an invoice to the Regional District of Central Kootenay for the release. SGC 18.7 – Total Performance SGC 18.7.4 – Add the following clause: If the Total Performance is not achieved on the date as outlined in SGC 18.6.4, upon written notification to the Contractor, the Owner may complete or cause to be completed any and all outstanding deficiencies. All resulting costs incurred by the Owner in completing the Work, including administration and inspection costs, will be deducted from the amounts owing by the Owner to the Contractor. 21.0 WORKERS COMPENSATION REGULATIONS SGC 21.2 – Contractor is “Prime Contractor” SGC 21.2 – Add the following clause: REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT SUPPLEMENTARY GENERAL CONDITIONS PAGE 5 OF 6 2016 21.2.2 Prior to the issuance of the Notice to Proceed, the Contractor shall sign and submit a Prime Contractor Agreement form (to be provided by the Contract Administrator), acknowledging acceptance and understanding of the requirements and obligations of the Prime Contractor role. If at any time the Contractor believes he is no longer acting as the Prime Contractor, due to multiple contractors or other factors, written notification must be provided by the Contractor to the Contract Administrator. An investigation will then be completed and the Prime Contractor status will be confirmed or amended as warranted. 22.0 INDEMNIFICATION SGC 22.1 – Contractor to Indemnify SGC 22.1.1 - Delete GC 22.1.1 and replace with the following: 22.1.1 The Contractor releases, indemnifies and saves harmless the Owner (The Regional District of Central Kootenay) and its elected officials, officers, employees, contractors, consultants, solicitors, assigns and agents from and against all claims, demands, actions, proceedings, suits, loss, damage, costs (including legal costs), fines, penalties, charges and expenses (in this section collectively "Claims") which the Owner may incur, suffer or be put to arising out of or in connection with this Agreement or acts or omissions of the Contractor under this Agreement, including: a. those arising out of or in connection with any loss or damage to persons (including bodily injury and death) or property as a result of or in connection with, directly or indirectly, this Agreement, b. economic loss, c. those arising from a breach by the Contractor/Consultant of any of its agreements, representations, warranties or covenants set forth in this Agreement, provided, however, that this obligation to indemnify the Owner shall not apply to Claims to the extent, if any, to which they may arise from the wrongful or negligent act or failure to act of the Owner or from any Owner breach of this Agreement. Without limitation, the Contractor shall promptly pay the Owner in respect of any Claims recoverable by a third party from the Owner or the property of the Owner. SGC 22.1.2 - Add the following: 22.1.2 The Contractor shall indemnify the Owner from third party liability with respect to health care costs recoverable under the Health Care Costs Recovery Act arising out of the Contractor’s performance of the Contract Work. 24.0 INSURANCE SGC 24.1 Required Insurance SGC 24.1.1(1) - Increase the automobile liability insurance from $3,000,000 to $5,000,000 each occurrence, all inclusive on owned, non-owned or hired vehicles. SGC 24.1.1(4) – Add the following clause: REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT SUPPLEMENTARY GENERAL CONDITIONS PAGE 6 OF 6 2016 24.1.1(4) Contractor’s Pollution Liability or Environmental Impairment Liability with a limit of not less than One Million ($1,000,000.00) Dollars per occurrence for claims arising from bodily injury, death, or property damage caused or alleged to be caused by a spill, discharge, emission, dispersal, seepage, leakage, migration, release or escape of pollutants in or upon land, the atmosphere, drainage or sewage system, watercourse or body of water arising out of the performance of this contract. SGC 24.1.6 – Add the following clause: 24.1.6 Notwithstanding anything contained elsewhere herein, it is understood and agreed that the Owner shall not be liable for any loss or damage to the Contractor’s equipment including loss of use thereof. 26.0 EARLY USE OF THE WORKS SGC 26.3– Effect on Maintenance Period Delete GC 26.3.1 and replace with the following: 26.3.1 There will be no effect on the Maintenance Period if the Owner takes over and begins to use a portion of the Work before Substantial Performance is achieved. The Maintenance Period for all Work shall commence from the date of Substantial Performance of the Contract. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT SS PAGE 1 OF 1 SUPPLEMENTARY SPECIFICATIONS 2016 The Construction Specifications for this project are contained in the Master Municipal Construction Documents (MMCD) Platinum Edition Volume II, 2009, except as specified in the following Supplementary Specifications and MMCD Supplemental Updates (see Schedule 1 of the Agreement). These Supplementary Specifications take precedence over the applicable MMCD Specifications. CONTENTS Project Specific Supplementary Specifications Section 01 10 00S Section 01 29 00S Section 02 41 14S Special Provisions Supplemental Payment Procedures Site Demolition and Salvage No. of Pages 10 3 3 REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT 1.0 2.0 Section 01 33 01 SPECIAL PROVISIONS SECTION 01 10 00S PAGE 1 OF 9 2016 Project Record Documents 1.7 Recording Actual Site Conditions, Add the following: .6 Contractor to complete and submit a complete digital survey of all Work in AutoCAD format prior to Substantial Performance. Survey data shall include all visible and nonvisible construction items, including but not limited to manholes, inspection chambers, inverts, end stakes, valves, hydrants, curb stops, street lights, junction boxes, concrete curbs (horizontal and vertical transitions) and extent of sidewalk works. The survey shall include buried items, such as pipe inverts, bends, deflections and pipe crossings. .7 The Contractor shall be responsible for the cost of verifying non-disturbance or replacing any legal survey pins or monuments damaged during construction operations. In the event that the Contractor requires the removal of any legal survey markers for the purpose of the Work, the Contractor must receive written consent from the Contract Administrator and the pin must be adequately referenced by a BCLS prior to removal. Section 01 52 01 Temporary Structures – Site Office Delete 1.3.1, no Site Office is required for the Contract Administrator. 3.0 Section 01 55 00 Traffic Control, Vehicle Access and Parking 1.4 Traffic Control, Add the following .14 The Contractor will be required to provide a Traffic Control Plan for each stage of construction, as described in the MoTI Traffic Control Manual for Work on Roadways (latest edition). The Traffic Control Plan must be submitted to the Contract Administrator for review and approval 5 Days prior to commencement of work in each stage. No work can commence in the particular stage of construction until the Traffic Management Plan has been approved by the Contract Administrator. .15 All construction signage and traffic control must be in compliance with the Contract Documents, MOTI Manual, and as directed by the Contract Administrator. All signage, barricades, delineators and garments must comply with MoTI Technical Circular T09-05 for Retro-Reflectivity. .16 The Contractor shall designate a Traffic Control Supervisor responsible for site safety (pedestrian, cyclist and vehicles) with specific training as identified in the MoTI Traffic Control Manual. The Traffic control Supervisor and the Site Inspector will review signage identified in the Contractor's Traffic Plan prior to construction on each stage and on a daily basis. The Traffic Control Supervisor shall maintain a Traffic Control Log Book as required by the MoTI Manual to facilitate a safe traffic control system for dynamic and static construction zone operation. .17 The Contractor will be required to provide the Contract Administrator and Owner with a weekly notice of planned road or block closures, for review, before being passed on to local media outlets. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT SPECIAL PROVISIONS SECTION 01 10 00S PAGE 2 OF 9 2016 .18 In addition to the Public Notice required in Section 01 58 01, the Contractor shall provide additional written notice to residents and businesses two days prior to access closures or restrictions. The content and form of the written notifications shall be reviewed and approved by the Contract Administrator prior to delivery. Emergency access and pedestrian access to all businesses and residences shall be maintained at all times. Vehicle access for business and residential properties shall be maintained at all times unless otherwise approved by the Contract Administrator. Suitable access shall have a minimum lane width of 3.0m and be defined as a bladed and comfortable driving surface, free of potholes and other impediments, sufficient to accommodate a standard two-wheel drive passenger vehicle at a speed of 20 km/h. .19 The Contractor shall provide daily/weekly notification and coordination with all emergency and public services, including but not limited to fire, police, ambulance, transit, garbage collection and Canada Post. If regular recycling or garbage collection is impeded due to construction activity, the Contractor shall ensure that recycling and garbage is removed from the curbside and disposed of. .20 The Contractor shall make provision at all times for adequate separation between public and work area hazards, active and inactive, such as construction equipment, excavations and equipment by means of delineation, barricades and fencing. Applicable traffic control devices used for night time service must have ASTM9 equivalent or diamond grade equivalent reflectivity and flashing beacons. Where equipment enters or exists in the work area, Traffic Control Persons shall be used. .21 The Site Inspector is to approve any trenches left open overnight. These trenches shall be fenced, in conjunction with reflectorized signs, barricades and flashers. Any trenches left open overnight shall not disrupt access to or cause any other service inconvenience to any dwelling, business or pedestrian walkway. .22 The Contractor shall utilize H-20 traffic load steel plates for emergency crossings or other short term trench or excavation crossings required for access purposes. .23 Working hours shall be in accordance with the local bylaws unless otherwise approved by the Contract Administrator. .24 All regulatory signs that are affected by the work must be removed and replaced by Town or MOTi crews only (i.e. stop signs, speed zone signs, etc.). Contractor to provide 7 days written notice to Contract Administrator for sign removal. .25 All affected roads shall be swept and have dust control applied as conditions warrant or as directed by the Contract Administrator. .26 Long Weekends – no intersection closures will be allowed from noon on the Friday preceding the long weekend to 7am on the day following the long weekend. .27 Where intersections are closed to allow for construction, turnarounds must be implemented on each street to allow for cars to make a u-turn as they approach the affected intersection. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT .28 4.0 .5 SECTION 01 10 00S PAGE 3 OF 9 2016 Two Dynamic Message Signs (DMS) are to be provided by the contractor and utilized from 7 days before construction begins up until Total Performance. Both signs will be located on Highway 3, one east of the work site and one west of the work site. Section 01 57 01 1.2 SPECIAL PROVISIONS Environmental Protection Temporary Erosion and Sediment Controls, Add the following: Sediment Control Plan: .1 The Contractor shall provide a “Sediment Control Plan” to the Contract Administrator a minimum of one week prior to commencement of construction. No work can proceed until the plan has been approved by the Contract Administrator. 1.4.3 Environmental Protection, .3 Pollution Control, Add the following: .5 Ensure proper containment and disposal of concrete wash water. .6 Prepare written Spill Contingency Plan prior to commencement of construction activities. Spill Contingency Plan shall include the following: .1 Provisions for secondary containment for all stationary bulk fuelling tanks, equipment washing and maintenance areas. Secondary containment for fuelling tanks must be a minimum 110% of the volume of the tank or 40% of the volume of all containers stored, whichever is the greater volume. .2 Spill Kits and protective equipment that include absorbent pads, booms, etc. for containing and mopping up small spills, and gloves, coveralls, shovels, containers, etc. to use to mop up spilled substances. .3 Segregation and disposal procedures (or contingency plan) for contaminated soils and/or contaminated groundwater. .4 Reporting procedure that includes “reportable volumes” and numbers to call in the event of a spill. For example, spills of oil or diesel fuel equal to or in excess of 100 L must be reported to the Provincial Emergency Program (PEP) at 1.800.663.3456. When calling PEP be prepared to answer the following: • • • • • • • • Your name and contact phone number; Name and telephone number of the person who caused the spill; Location and time of the spill; Type and quantity of the substances spilled; Cause and effect of the spill; Details of action taken or proposed; Description of the spill location and surrounding area; Names of the agencies on scene; and REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT • .5 5.0 6.0 SPECIAL PROVISIONS SECTION 01 10 00S PAGE 4 OF 9 2016 Name of other persons or agencies advised concerning the spill. Small spills may be dealt with by the Contractor provided equipment is available (may be sub-contractor like NEWALTA) to contain and clean-up the spilled substances and all soils affected by the spill. Any spill to a surface water or sewer utility must be reported to the Fire Hall Dispatch at 250-428-4321, or use 911 in any emergency situations where response times are critical. Section 01 58 01 Project Identification 1.2.2 Public Notice, Delete 1.2.2.1 Public Notice and replace with the following: .1 The Contractor shall be responsible for notifying, in writing, all residents and businesses affected by the proposed construction within the project limits and affected area. This notification shall be done on a block by block basis, with each occupied parcel contacted 7 days in advance of construction in the particular area or block. The content and form of the written notification shall be reviewed by the Contract Administrator and the Contractor shall incorporate any modifications or comments made into the notification prior to issuance. .2 The written notice shall include an invitation for business owners and residents to meet the Contractor’s Superintendent and Resident Inspector at a brief street meeting prior to the commencement of the work in the particular block. Suggested time for the residential street meetings are 6:00 pm to 6:30 pm. Section 31 05 17 Aggregates and Granular Materials 1.3 Approvals, Add the following: .5 7.0 Crushing and /or screening of granular aggregates for this or other projects shall not be permitted within the project area or on any road right-of-way. Section 31 23 01 Excavating, Trenching and Backfilling 1.7 Disposal, Add the following: .2 Waste and/or excess clean excavated material and concrete not exceeding 300mm in maximum dimension may be disposed of on private property only upon approval from the property owner and provided it is legal and all necessary permits and approvals have been obtained and all necessary fees paid. Either the Owner or the Contract Administrator may request that a copy of the agreement between the Contractor and private property owner be provided by the Contractor. Such request does not constitute approval of the agreement as neither the Owner nor the Contract Administrator will be a party to the agreement. 3 Asbestos Cement (AC) pipe shall be separated from other waste and removed and disposed of at the Contractor’s expense in accordance with WorkSafeBC requirements and Special Waste Provisions of the Waste Management Act. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT 8.0 Section 33 11 01 SPECIAL PROVISIONS SECTION 01 10 00S PAGE 5 OF 9 2016 Waterworks 3.19 Testing Procedures, Add the following: .7 Minimum test pressure at the highest point of the new watermain to be 1035 kPa (150 psi). .8 As per the standards within “AWWA M23”, “AWWA C605” and the MMCD Platinum Edition, Contractor to provide the Contractor Administrator a written plan that identifies the Contractor’s pressure testing methods and procedures. This plan is to be submitted at least one week prior to pressure testing. No pressure testing can commence until the plan has been approved by the Contract Administrator. 3.21 Disinfection and Flushing Procedures, Add the following: .10 As part of disinfection and bacteriological testing efforts, the contractor may need to install temporary works to accommodate minimum flushing velocities (oversized blow-offs). This is considered incidental to the work. No additional payment for this will be approved. .11 Super-chlorinated water will need to be fully de-chlorinated prior to release. The preferred location for release of the de-chlorinated water is into the ditch on the north side of Beam Road at approximately station 1+470. At a minimum of one week before flushing, the Contract Administrator will require a written plan from the Contractor that identifies dechlorination and flushing methods and procedures. No flushing can commence until the plan has been approved by the Contract Administrator. .12 As there are no testing labs in the vicinity of the project, bacteriological samples may need to be couriered to an accredited lab. It is up to the Contractor to schedule testing so that samples can be delivered within the allowable time limits. At a minimum of one week before bacteriological testing, the Contract Administrator will require a written plan from the Contractor that identifies the Contractor’s testing methods and procedures. No testing can commence until the plan has been approved by the Contract Administrator. 3.23 Connection to Existing Mains, Add the following: .2 Notify the Contract Administrator a minimum 48 hours in advance of all scheduled connections (Tie-ins). .3 All connections to existing mains will be completed by the Contractor and witnessed by the Site Inspector. .4 All connections to existing services will be completed by the Contractor and witnessed by the Site Inspector. Connections to existing services can only be completed after all watermain testing has been completed and accepted by the Contract Administrator. .5 To facilitate the watermain connections at 3+030 (+-), the valve and fitting cluster must be installed onto the existing watermains prior to tie-in day. With the fittings and valves in place, the final connection at this location will be made on the south side of the new transmission main gate valve at station 3+023 (+-). REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT .6 9.0 10.0 11.0 SECTION 01 10 00S PAGE 6 OF 9 2016 At a minimum of one week before final connections, the Contract Administrator will require a written plan from the Contractor that identifies the Contractor’s methods, procedures and proposed tie-in schedules. No final connections can commence until the plan has been approved by the Contract Administrator. Connections to existing mains are considered incidental to the work. No additional payment for this work will be approved. Availability of AutoCAD Design Drawings 1. The AutoCAD design drawings will be made available to the Contractor for the purpose of site layout during construction. 2. The Contractor will be solely responsible for survey layout at the Place of Work, including the compilation or extraction of additional information from the AutoCAD Design drawings if required to complete the Work. 3. No additional information regarding layout of the Work will be supplied by the Owner unless the Contract Administrator determines that requests for information pertaining to layout cannot be extracted from the Contract Drawings or the AutoCAD design drawings. Dewatering 1. Dewatering may be required to complete portions of the Work in this Contract. 2. The Contractor shall provide, and maintain in good running condition, gas or diesel powered pumps for the purpose of dewatering within the limits of construction. The provision of this equipment will be considered incidental to payment for work described in other Sections. 3. Discharge of dewatering water directly to drainage systems will only be permitted by approval of the Contract Administrator. Dewatering water can be discharged to ditches only through approved settlement ponds and discharge structures. Construction Schedule 1. 12.0 SPECIAL PROVISIONS It is anticipated that staging (phasing) of construction will be required to facilitate vehicle, cyclist and pedestrian movements during construction. Contractor to provide the Contract Administrator with a construction staging plan at least five days before commencement of construction. Provisional Items 1. Provisional Items or Provisional Sums are allowances to cover the costs of possible Work for which the scope and extent is not known at the Tender Closing Date but which may, pursuant to provisions of the Contract Documents, become part of the work. The finalization and inclusion of these items is at the discretion of the Owner. The Owner will retain any unused portion of the Provisional Sum, and the Contractor cannot make a claim for lost overhead or profit on the unused portion of the Provisional Sum. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT 13.0 SECTION 01 10 00S PAGE 7 OF 9 2016 Blasting 13.1 14.0 SPECIAL PROVISIONS The Contractor shall provide a detailed blasting plan and conduct a Pre-Blasting Conditions Survey. The Blasting Plan and Pre-Blasting Conditions Survey shall include the following: 13.1.1 Detailed descriptions and typical cross sections of how blast holes will be loaded and initiated. A description of powder factors, delays, stemming, and loading procedures and the use of blast mats must also be included. 13.1.2 A description of how the proponent will ensure the fly rock, rock slides or overpressure and blast shock waves will not injure residents or damage any of the neighbouring properties or buildings. In particular, a plan to survey all homes that may be impacted by the project shall be conducted prior to commencement of the project to determine any pre-existing structural or glass damage. A plan to monitor blast overpressure and peak particle velocity shall be included. As well, videotaping of all blasts must form part of the plan. A plan to resurvey all neighbouring buildings and properties post-project completion must also be included. 13.2 Blasting will only be completed after securing approval from the Contract Administrator. Damage caused by blasting shall be repaired by the Contractor at his expense. The method and procedure for blasting and storage of explosives and other materials required to complete the blasting work shall be in accordance with Federal, Provincial and Municipal regulations. The Contractor shall not complete any blasting without first verifying that his insurance covers any loss of life or damage that may result from this work and includes a waiver of subrogation in favor of the Owner. The Contract Administrator, in granting approval for blasting, does not in any way assume responsibility for injury, loss of life, or damage that may result therefrom, and such approval shall not be construed as approval of the methods employed by the Contractor in blasting, the sole responsibility therefore being that of the Contractor. 13.3 Consistent with the above, the Contractor’s blaster must have experience in blasting work similar to the blasting work that will be performed on this project. Haul Routes 14.1 The Contractor shall obtain permission from the Contract Administrator to use any route as a haul route. The Contractor shall be responsible for maintaining all haul routes in good condition and free from excessive dust and mud. 14.2 The Contractor shall be responsible for damage and/or spillage on all roads used for hauling materials and equipment to and from the site. The Contractor shall immediately clean and/or restore the affected areas to the conditions that existed before the hauling of materials and equipment commenced. The Contractor shall be responsible for maintaining a record of the condition of the haul roads used for the supply of material and/or equipment through the use of colour photographs that will record the condition of the haul roads prior to initiating the work. These photographs shall be submitted to the Contract Administrator prior to proceeding with the hauling of materials and equipment. 14.3 The Contractor shall be responsible to ensure all employees and subcontractor employees obey all rules of the road, including the speed limit, while driving within the vicinity of the site. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT 15.0 16.0 17.0 SPECIAL PROVISIONS SECTION 01 10 00S PAGE 8 OF 9 2016 Barricades 15.1 The Contractor will conduct construction operations with minimum interference to adjacent roadways, sidewalks and access facilities in general. Keep such areas free of material, debris and equipment at all times. 15.2 Trenches are to have adequate barricades in accordance with all Provincial, Federal and Municipal regulations, including, but not limited to, the Industrial Health and Safety Regulations (WCB). 15.3 Temporary fencing shall be provided, installed and maintained to prevent unauthorized public access to the work area at the end of each construction day or shift. Temporary fencing shall also be provided, installed and maintained to prevent the public from entering construction zones and on-site haul routes while construction activities are occurring. All Temporary Fencing shall conform to Section 01550 of the general specifications and be installed to the approval of the Contract Administrator and consistent with the Industrial Health and Safety Regulations (WCB). Site Security and Access 16.1 The Contractor shall make all reasonable efforts to prevent vehicular access to the site after work hours. 16.2 No security will be provided or compensation paid by the Owner for material or work stolen, lost, damaged or destroyed. The Contractor shall be responsible for watching the site at all times and for making good all deficiencies at no extra cost to the Contract Price. 16.3 The Contractor shall ensure that the Subcontractors shall make their own arrangements to ensure security of their own equipment, materials and work, in co-operation with the Contract Administrator. The Contract Administrator shall designate certain areas to be used as temporary lock fast stores and Subcontractors shall comply with the Contractor's instructions in this regard. 16.4 The Contractor and the Subcontractors and their employees shall not park vehicles within the construction area, unless approved by the Contract Administrator. 16.5 The Owner's, Consultant’s, Contractor's and other contractor's work vehicles and construction equipment only will be allowed on the site. 16.6 The Contractor shall conduct construction operations with minimum interference to adjacent roadways, sidewalks and access facilities in general. Keep such areas free from materials, debris and equipment at all times. Confine operations to areas designated by the Contract Administrator. 16.7 The entry and removal of all materials, equipment and tools onto and off the site will be subject to inspection and approval. Waste Disposal REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT 18.0 SECTION 01 10 00S PAGE 9 OF 9 2016 17.1 Fires, burning, or burying of rubbish and waste materials on-site is not permitted. 17.2 All rubbish and waste materials that are generated by the Contractor during the performance of the contract shall be removed from the site and disposed of in a location that complies with all Provincial, Federal and Municipal regulations and must be approved by the Consultant and will be at the expense of the Contractor. Optional Items 18.1 19.0 SPECIAL PROVISIONS Any items indicated in the Tender Form as “Optional” are to be considered as Optional Work. This work will only occur if the Contract Administrator so directs by Change Order. Notice to Affected Residents 190.1 The Contractor shall provide written notice to residents and businesses two days prior to work in the direct vicinity of each affected property. Further to this, the Contractor shall provide one week notice to residents and businesses where work is expected to proceed during that upcoming week. The content and form of the written notifications shall be reviewed and approved by the Contract Administrator prior to delivery. No overnight disruptions (loss of access) will be allowed which will affect any access to any property within the project area or in areas that are outside the limits of the project. 20.0 Protection of Existing Utilities 20.1 Gas mains are in close proximity to the watermain works. The Contractor is to field locate all gas mains within the project limits at least seven days prior to construction commencing. Once the field locating has been completed, the Contractor shall layout relevant sections of the work and the Contract Administrator will review the proposed watermain alignments. Should minor alignment adjustments be required, the Contract Administrator will issue instructions to the Contractor regarding minor realignments. Minor alignment changes are considered as incidental to the Contract. No additional compensation will be approved. Should additional watermain or fittings be required due to these alignment changes, the additional work will be paid for at the applicable unit rates. 20.2 The proposed watermain and service alignments may be in close proximity to telephone poles, hydro poles and existing driveway culverts. These existing features may need to be supported during construction. This effort, if required, is considered as incidental to the work. No additional payment will be approved for supporting these existing features during construction. 21.0 Schedule 21.1 All work at the Reservoir site must be completed by June 30th, 2016. This is to allow for construction of a reservoir and control building as part of a separate construction contract. Due to agricultural irrigation demands, the schedules for tie-in work must be approved by the Contract Administrator. Tie-ins may need to be completed when weather is favourable (wetter weather). Such approval by the Contract Administrator will not be unreasonably withheld. END OF SECTION 01 10 00S REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT SUPPLEMENTAL PAYMENT PROCEDURES SECTION 01 29 00S PAGE 1 OF 5 2016 This section provides “Measurement for Payment” clauses for items not addressed in the MMCD specifications or provides revised/amended clauses for items included in the MMCD. These items have an "SSpec" notation in the 'Payment' column of Appendix 1 of the Form of Tender. Note that any minor items not listed in the Form of Tender but typical for this type of work, such as but not limited to utility locates, exploratory digging, protection of utilities, temporary construction fencing, disposal of waste materials, adjustment of existing surface features or appurtenances, removal and replacement of trees, shrubs and landscaping, public relations, miscellaneous fittings, connections or removals shall be considered incidental to the work and no separate payment will be made. PART 1.0 - GENERAL .1 Payments shall be made on the basis of the lump sum prices and the unit prices bid in the Unit Price Schedules in the Tender Form. .2 The prices bid for various items of work, unless specifically noted otherwise, shall include the supply of all labour, materials, plant and equipment required to construct the work in accordance with the drawings and specifications. .3 The method of measurement of the quantities for payment and the basis for payment will be in accordance with the following items of this section. Except as defined in the Supplemental Payment Procedures, the Contract Administrator will do all measurements. When requested by the Contract Administrator, the Contractor must provide construction survey information to the Contract Administrator. .4 The prices bid for supply and installation of materials shall be full compensation for supplying, delivering, loading, unloading, handling, storage, breakage, waste, hauling, installing, cleaning, testing and placing in service the work together with all work subsidiary and incidentals thereto for which separate payment is not provided elsewhere. Payment shall be only for materials actually installed. .5 All existing materials that are on-site, whether structures, vegetation, topsoil, gravel, sand or other excavated, or piled materials are the property of the Owner on which the work is located. Only those materials specifically noted in the specifications or on the drawings as belonging to the Contractor shall become the Contractor's property. .6 Where there are excess excavated materials, unsuitable materials or materials of any kind that are not used in the work, such materials are not the property of the Contractor unless authorized in writing by the Contract Administrator or are specified to be disposed of by the Contractor. .7 The sum of the payments in the Unit Price Schedules of the Tender Form shall constitute full payment for the complete works as described in these documents. Extra payment will only be made for items adding to the scope of the works, as described in these documents and/or shown on the drawings and as evident from inspection of the site of the works. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT SUPPLEMENTAL PAYMENT PROCEDURES SECTION 01 29 00S PAGE 2 OF 5 2016 PART 2.0 - NON-PAYMENT ITEMS .1 Supply of all equipment, labour, materials, plant, and services required to complete the Work for which no specific payment item has been assigned in the Unit Price Schedules of the Tender Form shall be considered incidental to the Works. .2 There shall be no separate payment for incidental work. Payment for incidental work shall be considered to be included in the total tendered price of the Unit Price Schedules of the Tender Form. .3 All work shown on the plans and drawings, or referred to in the General Conditions, the Supplementary General Conditions, or the General Specifications shall be considered as part of the complete work unless specifically deleted. .4 There shall be no separate payment for bonding and insurance. All bonding and insurance costs incurred by the contractor for the works shall be considered incidental work and shall be considered to be included in the total price of the Unit Price Schedules in the Tender Form. .5 Environmental Protection Environmental Protection is considered incidental work. PART 3.0 – MEASUREMENT AND PAYMENT 1. Mobilization / De-Mobilization (Section 01 53 01) is a fixed lump sum allowance item (amount predetermined by Owner) and will be paid 50% with the first progress payment and 50% with final progress payment after Total Performance has been achieved. The second 50% amount will not factor into the calculation for determination of Substantial Performance. 2. Survey Layout and Project Record Documents (Section 01 33 01) is a lump sum item with 50% to be paid as a percentage of the completed contract survey work and 50% after submission of the digital record drawings. 3. Traffic Control, Vehicle Access and Parking (Section 01 55 00) is a lump sum item and will be paid as a percentage of the completed contract work. 4. Erosion and Sediment Control (Section 01 57 01) is a lump sum item and will be paid 50% following substantial completion of the mass earthworks and 50% following Total Performance of the Contract. The lump sum price is to include supply, installation and maintenance of all erosion and sediment control measures and environmental protection as shown on the drawings and as directed by the Contract Administrator. 5. Clearing and Grubbing (Section 31 11 01) will be paid at the lump sum price shown in the Tender Form. For each progress payment, the Engineer shall estimate the percentage of work complete for this item. The lump sum price shall include allowances for all labour, material and equipment to clear and grub the site of all vegetation; tree cutting and pruning; excavation; loading; hauling; unloading; disposal at an approved off-site location; tipping fees; preservation of trees as required; and all other work incidental for a complete product. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT SUPPLEMENTAL PAYMENT PROCEDURES SECTION 01 29 00S PAGE 3 OF 5 2016 6. Topsoil Stripping (Section 31 22 01) will be measured and paid at the unit price in the Tender Form. The measurement will be based on the existing ground surface based on the current survey, and the ground surface following stripping. The Contractor shall complete the survey required to define the ground surface following stripping. Assumed stripping depth is 0.4m. Stripping shall be as directed by the Contract Administrator but the Contractor shall control and monitor their stripping activities such that the Contract Administrator’s directions are followed. If the stripping depth is more, or less, than 0.4m the Contractor shall immediately notify the Contract Administrator. The unit price is to include stock-piling for re-use; erosion and sediment control measures relating to the stockpiling of materials; and placement of topsoil on disturbed areas following mass grading, as directed by the Contract Administrator. 7. Mass Site Grading – Common Excavation - Excavation to Embankment (Section 31 22 01) will be measured and paid at the unit price in the Tender Form. The measurement will be based on the existing ground surface following stripping and the finished ground surface in excavation (cut) areas. The Contractor shall complete the survey required to define the ground surface following excavation. Payments are for excavation (cut) volumes only and the contractor will not be paid for excavation beneath the proposed design grades. The unit price for “Mass Site Grading – Common Excavation Excavation to Embankment” is to include cut and fill works including on-site redistribution and compaction to design elevations and grades. 8. Mass Site Grading – Common Excavation - Excavation to Offsite Disposal (Section 31 22 01) will be measured and paid at the unit price in the Tender Form. The measurement will be based on the existing ground surface following stripping and the finished ground surface in excavation (cut) areas. The Contractor shall complete the survey required to define the ground surface following excavation. Payments are for excavation (cut) volumes only and the contractor will not be paid for excavation beneath the proposed design grades. The unit price for “Mass Site Grading – Common Excavation Excavation to Offsite Disposal” to include all work that is required to complete the work. The Contractor is to provide a location for disposal as part of the unit rate for this item. No additional payment will be made if the disposal location and / or distance to the disposal location changes. 9. Rock Removal – To Embankment (Section 31 23 17) will be measured and paid at the unit price in the Tender Form. Measurement will be based on actual volume removed from solid rock masses as determined by the Contract Administrator. The calculation will be based on a survey of original bedrock surface and design subgrade lines for excavation as per the excavation details in the Engineering Drawings. The Contractor shall complete the survey that is required to define the bedrock surface. Overblasting is required to a depth 0.6m below design subgrade lines for excavation as per the excavation details in the Engineering Drawings. The overblast is to be removed, replaced and compacted per the instruction of the Contract Administrator. Payment for rock removal will be made for drilling and blasting or hydraulic rock hammer only. Rock removal of this type is only to be undertaken after all reasonable attempts at ripping/conventional excavation are made by the use of a D-9 Dozer with a ripping attachment. If the rock material is deemed suitable by the Contract Administrator, it will be placed in fill areas. The unit price is to include all necessary drilling; vibration monitoring and control to limits specified and all warning and protective measures; sorting, selecting and processing of blast rock for fill; placement of excavated material in fill areas or disposal off site as required; and all other work incidental to removing the rock material. 10. Rock Removal – To Offsite Disposal (Section 31 23 17) will be measured and paid at the unit price in the Tender Form. Measurement will be based on actual volume removed from solid rock masses as determined by the Contract Administrator. The calculation will be based on a survey of original bedrock surface and design subgrade lines for excavation as per the excavation details in the Engineering Drawings. The Contractor shall complete the survey that is required to define the bedrock REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT SUPPLEMENTAL PAYMENT PROCEDURES SECTION 01 29 00S PAGE 4 OF 5 2016 surface. Overblasting is required to a depth 0.6m below design subgrade lines for excavation as per the excavation details in the Engineering Drawings. The overblast is to be removed, replaced and compacted per the instruction of the Contract Administrator. Payment for rock removal will be made for drilling and blasting or hydraulic rock hammer only. Rock removal of this type is only to be undertaken after all reasonable attempts at ripping/conventional excavation are made by the use of a D-9 Dozer with a ripping attachment. The unit price is to include all necessary drilling; vibration monitoring and control to limits specified and all warning and protective measures; sorting, selecting and processing of blast rock; placement of excavated material at disposal site as required; and all other work incidental to removing and disposing of the rock material. The Contractor is to provide a location for disposal as part of the unit rate for this item. No additional payment will be made if the disposal location and / or distance to the disposal location changes. 11. Asphalt Concrete Paving (Section 32 12 16) includes all construction joint preparation, supply and placing of the asphaltic concrete, compaction, adjusting and cleaning frames, covers and lids of all castings affected and taped temporary pavement markings where warranted. Surface measurement for asphaltic concrete paving will be made separately for each specified tender item. The measurement will be based on the area of pavement actually installed. 12. Fittings and Gate Valves (Section 33 11 01) will be measured and paid at the unit price in the Tender Form. The measurement will be based on the number of gate valves and fittings actually installed. The unit price per gate valve or fitting shall include allowances for excavation; loading, hauling, and stockpiling excavated material at an approved location; dewatering; supply and installation of cages and shoring, as required; removal and disposal of existing gate valves or fittings, as required; supply and installation of bedding materials; supply and installation of the gate valve or fitting; supply and installation of thrust blocks or joint restraints; loading, hauling and placement of native backfill; compaction; moisture conditioning the backfill material as required to achieve the required density; and all other work incidental to a complete product. 13. Decommissioning Existing Water (Section 33.11.01, 33.30.11, 33.40.01) will be paid at the lump sum price shown in the tender form. The lump sum price shall include allowances for excavation; loading hauling, and stockpiling excavated material at an approved location; dewatering; supply and installation of cages and shoring, as required; removal and disposal of existing infrastructure as required; supply and installation of bedding materials; supply and installation of the gate valve or fitting; supply and installation of thrust blocks or joint restraints; loading, hauling and placement of native backfill; compaction; moisture conditioning the backfill material as required to achieve the required density; and all other work incidental to a complete product. 14. Relocate and Reinstall Existing Water Meters (Section 33 11 01) will be measured and paid at the unit price in the Tender Form. The measurement will be based on the number of water meters actually relocated and reinstalled. The unit price per water meter shall include allowances for excavation; loading, hauling, and stockpiling excavated material at an approved location; dewatering; supply and installation of cages and shoring, as required; removal of existing water meter; supply and installation of bedding materials; installation of existing water meter; supply and installation of water meter chamber; loading, hauling and placement of native backfill; compaction; moisture conditioning the backfill material as required to achieve the required density; and all other work incidental to a complete product. REGIONAL DISTRICT OF CENTRAL KOOTENAY UNIT PRICE CONTRACT 15. SUPPLEMENTAL PAYMENT PROCEDURES SECTION 01 29 00S PAGE 5 OF 5 2016 Install Water Meters (Section 33 11 01) will be measured and paid at the unit price in the Tender Form. The measurement will be based on the number of water meters actually installed. The unit price per water meter shall include allowances for excavation; loading, hauling, and stockpiling excavated material at an approved location; dewatering; supply and installation of cages and shoring, as required; supply and installation of water meter; supply and installation of bedding materials; supply and installation of water meter chamber; loading, hauling and placement of native backfill; compaction; moisture conditioning the backfill material as required to achieve the required density; and all other work incidental to a complete product. END OF SECTION 01 29 00S REGIONAL DISTRICT OF CENTRAL KOOTENAY SITE DEMOLITION AND SALVAGE UNIT PRICE CONTRACT SECTION 02 41 14S PAGE 1 OF 3 2016 1.0 GENERAL .1 Section 02 41 14S refers to those portions of the work that are unique to the salvage, demolition and/or removal of existing site items and materials. This section must be referenced to and interpreted simultaneously with all other sections pertinent in the works described herein. 1.1 Related Work .1 Environmental Protection Section 01 57 01 .2 Shrub and Tree Preservation Section 31 11 41 .3 Clearing and Grubbing Section 31 11 01 .4 Dust Control Section 31 1 560 .5 Site Grading Section 31 22 01 .6 Excavating, Trenching and Backfilling Section 31 23 01 .1 Dispose of all demolished items and materials off-site unless specified otherwise in the Contract Documents. .2 Except as specified in the Contract Documents disposal of demolished items and materials from the road right of way will not be without the written approval of the Contract Administrator. .3 Dispose demolished items and materials on non-road right of way property only upon approval from property owner and provided it is legal and all necessary permits and approvals have been obtained and all necessary fees paid. .1 Salvage work includes the removal, protection, transport and storage of salvaged items and materials identified in the Contract Documents. .2 Unless specified otherwise in the Contract Documents or approved by the Contract Administrator, all items and materials identified for salvage become the property of Owner. .3 Except as indicated in the Contract Documents salvage work will be the responsibility of the Contractor. .4 Except as specified in the Contract Documents for re-use or stockpiling, remove and store salvaged items and materials off-site. 1.2 Demolition permitted 1.3 Salvage REGIONAL DISTRICT OF CENTRAL KOOTENAY SITE DEMOLITION AND SALVAGE UNIT PRICE CONTRACT SECTION 02 41 14S PAGE 2 OF 3 2016 1.4 Protection of Work, Property and Public .1 Comply with General Conditions, Clause 4.3, Protection of Work, Property and Public. 1.5 Approvals, Permits and Fees .1 Comply with General Conditions, Clause 20, Laws, Notices, Permits and fees. 1.6 Measurement and Payment .1 Payment for salvage includes the dismantling, protection, transport and storage or stockpiling of the salvaged items and materials. Payment for salvage, if applicable, will be made by Lump Sum. .2 Payment for demolition includes demolition, transport and disposal of all items and materials shown on the Contract Drawings. Payment for demolition, if applicable, will be made by Lump Sum. .3 No payment will be made for demolition, removal or disposal of items and materials not shown in the Schedule of Quantities and Prices or in excess of the features and limits shown on the Contract Drawings. .4 All costs incurred as a result of unauthorized and illegal demolition, removal or disposal are the responsibility of the Contractor 2.0 PRODUCTS 3.0 EXECUTION 3.1 Preparation 3.2 Demolition NOT USED .1 Prior to demolition and salvage, verify locations and limits of items and materials to be removed and identify methods to undertake dismantling, protection, removal, storage and disposal. .2 Protect existing features and surfaces not scheduled for removal from damage. .3 Coordinate scheduling of demolition and salvage with related work. .1 Decommission utilities and irrigation system prior to demolition and salvage. .2 Take care to limit impacts of demolition work to the site of the feature being demolished or to the extent of the demolition area shown on the Contract Drawings. .3 Time is of the essence in demolition and removal of items and materials. .4 Report any hazardous materials to the Contract Administrator.