MPC Planning Criteria Version 2.00 Effective Date: July 1, 2016 Supporting Policy: n/a MPC Planning Criteria Purpose: This document outlines the specific Minnkota Power Cooperative (MPC) Bulk Electric System (BES) transmission reliability criteria, which are to be used for MPC planning and operational planning studies. It also describes their relationship to the North American Electric Reliability Corporation (NERC) and Midwest Reliability Organization (MRO) Reliability Standards. This document provides deterministic criteria for use in MPC system studies so that a sound basis of comparison exists between MPC system performance studies. It also provides a set of evaluation criteria from which MPC study scopes, procedures, and reports can be produced. This document sets forth the specific BES reliability criteria established by MPC. These specific reliability criteria are in addition to the general criteria outlined in the NERC and MRO Reliability Standards. Referenced Documents: The following are referenced within this document. • MPC Open Access Transmission Tariff • MPC Facility Ratings Methodology Applicability: These criteria are applicable to MPC BES Facilities, but may be applied to MPC non-BES facilities if deemed appropriate. NERC Standard(s) of Reference: NERC Standard # TPL-001-4 – Transmission System Planning Performance Requirements Requirement # R3.5, R4.5, R5 Table 1 – Steady State & Stability Performance Planning Events; Table 1 – Steady State & Stability Performance Extreme Events Definitions: Capitalization indicates a MPC or NERC defined term. Capitalized terms and acronyms that are not otherwise defined in this document shall have the respective meanings set forth in the MPC Open Access Transmission Tariff, the NERC Glossary of Terms, or the meaning commonly understood within the electric utility industry. The NERC Glossary of Terms is located at www.nerc.com/pa/Stand/Glossary%20of%20Terms/Glossary_of_Terms.pdf. Page 1 of 8 MPC Planning Criteria Version 2.00 Effective Date: July 1, 2016 TABLE OF CONTENTS 1. Transmission Reliability Criteria.................................................................................................................... 3 1.1 Voltage Criteria ..................................................................................................................................... 3 1.1.1 Pre-Contingency Voltage Limitations........................................................................................ 3 1.1.2 Post-Contingency Period Voltage Limitations........................................................................... 3 1.1.3 Transient Stability Period Voltage Limitations .......................................................................... 3 1.1.4 Instantaneous Voltage Change ................................................................................................. 4 1.2 Facility Loading Limits ........................................................................................................................... 4 1.3 Short Circuit .......................................................................................................................................... 4 1.4 Fault Ride-Through ............................................................................................................................... 4 1.5 Transient Period Damping Criteria ....................................................................................................... 4 1.6 Relay Encroachment and Out-of-Step (OOS) Margins.......................................................................... 5 1.6.1 OOS Relay Margin Security Parameters .................................................................................... 5 1.6.1 Distance Relaying – Apparent Impedance Transient Criteria ................................................... 5 1.7 Voltage Stability Criteria ....................................................................................................................... 6 1.8 Cascading .............................................................................................................................................. 7 Appendix A: Revision Record ............................................................................................................................... 8 Page 2 of 8 MPC Planning Criteria Version 2.00 Effective Date: July 1, 2016 1. TRANSMISSION RELIABILITY CRITERIA MPC transmission reliability criteria are established in order to ensure safety, avoid equipment damage, and maintain reliable operation of the overall grid. 1.1 Voltage Criteria The criteria parameters monitored in the planning and operational study work shall be rounded to the nearest one-hundredth per unit (0.01 p.u.), to ensure consistent application of the criteria and to allow for small modeling variances. The “transient stability period” refers to the first ten (10) seconds after the contingency. The “post-contingency period” refers to the period ten (10) seconds to thirty (30) minutes after the contingency. Additionally, MPC has criteria for maximum allowable instantaneous voltage change, or delta-V. These voltage criteria can be utilized as guidelines for real-time operations; however, depending upon operating conditions, the real-time voltages may vary outside of the recommended ranges (see below), and MPC should be contacted for guidance on the application of these voltage criteria during real-time operations. 1.1.1 Pre-Contingency Voltage Limitations All steady state BES voltages in the study base case shall meet these criteria after all system adjustments have been made. These criteria are intended to be consistent with the NERC and MRO Reliability Standards, as applicable, and apply to the pre-contingency conditions. Facility All buses Young 1 Generator Bus (22 kV) Young 2 Generator Bus (20 kV) Maximum kV/p.u. 1.05 p.u. 0.991 p.u. 1.015 p.u. Minimum kV/p.u. 0.97 p.u. 0.936 p.u. 0.973 p.u. 1.1.2 Post-Contingency Period Voltage Limitations All steady-state BES voltages following contingencies in the power flow simulations must meet these criteria. These criteria are intended to be consistent with the NERC and MRO Reliability Standards, as applicable, and apply to the post-contingency conditions prior to any operator intervention. As long as mitigation occurs by automatic action, 0.88 p.u. voltages can be allowed at buses using the default criteria for durations up to ten (10) minutes. Facility All buses Young 1 Generator Bus (22 kV) Young 2 Generator Bus (20 kV) Maximum kV/p.u. 1.10 p.u. 0.991 p.u. 1.015 p.u. Minimum kV/p.u. 0.92 p.u. 0.936 p.u. 0.973 p.u. 1.1.3 Transient Stability Period Voltage Limitations MPC system voltage oscillations in transient analysis simulations shall meet these criteria: Facility All buses Drayton 230 kV Page 3 of 8 Maximum kV/p.u. 1.20 p.u. 1.15 p.u. Minimum kV/p.u. 0.70 p.u. 0.80 p.u. MPC Planning Criteria Version 2.00 Effective Date: July 1, 2016 The voltage must return within applicable post-contingency voltage limitations after ten (10) seconds. The bus voltages on the MPC system are allowed to increase to 1.3 p.u. for a duration up to two hundred milliseconds (200 msec), unless otherwise noted. 1.1.4 Instantaneous Voltage Change In order to protect against voltage flicker, typically caused by switching of reactive devices or motor starting, MPC allows a maximum instantaneous voltage change of 0.03 p.u. during system intact and 0.05 p.u. during an outage. 1.2 Facility Loading Limits Applicable facility loading limits must not be violated. Facility loading limits will be established by MPC in the MPC Facility Ratings Methodology, and these limits reside in the Facilities Library within the MPC NERC Document Management System. The normal rating is the continuous thermal rating unless noted otherwise. The emergency rating is the thirty- (30-) minute thermal rating. The continuous (normal) and emergency ratings are included in regional power flow models. Dynamic ratings can be both continuous and emergency. Some Facilities have specifically identified dynamic ratings for some facilities under certain conditions. These are documented through applicable operating guides. These ratings may differ from the continuous and emergency ratings that are included in regional power flow models. 1.3 Short Circuit All MPC buses shall be modeled having the minimum maximum fault current interrupting capability, which should not be violated. If it is violated, the actual equipment and contingency will be reviewed to make sure the individual equipment maximum fault current interrupting capability is not violated. 1.4 Fault Ride-Through All generators greater than twenty megawatts (20 MW) shall be able to ride through NERC Category P1 through P7 1 events. 1.5 Transient Period Damping Criteria All machine rotor angle oscillations will be positively damped and must meet the criteria below. The criterion does not apply to bus voltages. The Damping Factor will be calculated from the Successive Positive Peak Ratio (SPPR) of the peak-to-peak amplitude of the rotor oscillation. SPPR and the associated Damping Factor will be calculated as: • SPPR = Successive swing amplitude / previous swing amplitude, and • Damping Factor = (1 - SPPR) * 100 (in %) The damping criteria are as follows (with increased damping required for higher probability events): 1 • For disturbances (with faults): SPPR (maximum) = 0.95; Damping Factor (minimum) = 5% • For line trips: SPPR (maximum) = 0.90; Damping Factor (minimum) = 10% TPL-001-4, Table 1 – Steady State & Stability Performance Planning Events Page 4 of 8 MPC Planning Criteria Version 2.00 Effective Date: July 1, 2016 As an alternative method to automatic damping calculations, such as DAMPCK and the Prony analysis, the Damping Factor may be calculated manually by measuring the SPPR of the last two cycles (if they are discernible) of a 20-second simulation. If the swing within the last two cycles is less than one degree, the oscillations are sufficiently damped regardless of the SPPR calculation. When measuring damping in all cases, simulations should be run out to twenty (20) seconds in order to remove well-damped frequencies from the waveform. 1.6 Relay Encroachment and Out-of-Step (OOS) Margins 1.6.1 OOS Relay Margin Security Parameters Relay Steady State Pre Post 110% 50% OOS relay Dynamic 25% The definitions of these specific relay margin calculations are shown in Figure 1, below. MARGIN = (D1 / D2) * 100% Operating Point D1 D2 Steady State (pre-contingency) . Figure 1 – OOS Relay Margins 1.6.1 Distance Relaying – Apparent Impedance Transient Criteria The transient apparent impedance swings on all lines shall be monitored, after fault clearing, against a three-zone mho (or offset impedance) circle characteristic with the following zones: Circle A = 1.00 x Line Impedance Circle B = 1.25 x Line Impedance Circle C = 1.50 x Line Impedance Apparent impedance transient swings into the inner zones (Circles A or B) are considered unacceptable, unless documentation is provided showing the actual relays will not trip for the event. Page 5 of 8 MPC Planning Criteria Version 2.00 Effective Date: July 1, 2016 A PSS/E 2 dynamic user model, MRELY1, is maintained in the UIP (User Interface Package), which performs the required global monitoring. 1.7 Voltage Stability Criteria A voltage stability study may be necessary to demonstrate that there is sufficient margin between the normal operating point and the collapse point. The study shall include voltage versus power transfer or system demand (P-V curve) and voltage versus reactive power (Q-V). For P-V, sufficient margin is maintained by operating at or below Plimit. The Plimit is determined by developing P-V curves for those buses that have the largest contribution to voltage instability due to the most limiting NERC Category P1 contingency, per NERC TPL standards. The Plimit is calculated as the lesser of: • (0.9) * Pcrit (shown below in Figure 2 as point “a”) where Pcrit is defined as the maximum power transfer or system demand (nose of P-V curve), or • The maximum power transfer or system demand which does not result in a postcontingency voltage violation as defined in this document. Figure 2 – P-V Curve For Q-V, sufficient reactive power margin, Qmargin, must be maintained. Qmargin is determined by developing Q-V curves for those buses that have the largest contribution to voltage instability due to the most limiting NERC Category P1 contingency 3, per NERC TPL standards. Qmargin is calculated as reactive power between the nose of the Q-V curve and the 0 MVAR injection. A positive value implies a negative reactive power margin, and a negative value implies a positive reactive power margin. See Figure 3, below. 2 3 Power System Simulator for Engineering (PSS/E) TPL-001-4, Table 1 – Steady State & Stability Performance Planning Events Page 6 of 8 MPC Planning Criteria Version 2.00 Effective Date: July 1, 2016 MPC requires the following reactive power margin: • For 345 kV buses Qmargin ≤ -100 MVAR • For 230 kV buses Qmargin ≤ -50 MVAR • For 115 kV buses Qmargin ≤ -10 MVAR Figure 3 – Q-V Curve 1.8 Cascading In all analyses, cascading must not occur for NERC Category P0 through P7 4 events. Cascading may occur for Extreme Events 5; however, an evaluation of possible actions designed to reduce the likelihood or mitigate the consequences and adverse impacts of the event(s) shall be conducted. Cascading is defined by MPC as the non-consequential loss of 1000 or more MW of load following a contingency, or the loss of more than four (4) elements. This can be modeled by: 4 5 • Steady State: review post-contingent loading on circuits in the steady-state analysis and tripping lines loaded at 125% emergency rating until no further overloaded circuits exist. • Transient Stability: review distance relay margins and trip any lines that violate distance relay transient criteria until no further violations exist. • If more than four (4) elements have tripped due to Steady State overloads or Transient Stability distance relaying, then cascading may have occurred. • Actual relay settings and element capabilities will be reviewed on each of the tripped elements to determine if tripping would have occurred. If four (4) or more elements trip assuming actual relay settings, then cascading has occurred. TPL-001-4, Table 1 – Steady State & Stability Performance Planning Events TPL-001-4, Table 1 – Steady State & Stability Performance Extreme Events Page 7 of 8 MPC Planning Criteria Version 2.00 Effective Date: July 1, 2016 APPENDIX A: REVISION RECORD This document must be reviewed and approved at least once every fifteen (15) calendar months. The review and approval process is documented in digital format using the MPC NERC Document Management System. This revision history is provided for informational purposes only and change summaries should not be considered a complete description of changes. In the event of a conflict between this document and the MPC NERC Document Management System, the MPC NERC Document Management System shall prevail. Version 1.05 2.00 6 TPL-001-4 R3.5, 4.5 Page 8 of 8 Change Summary Issue Date Updated cascading criteria language to cover Extreme Events, 6 and updated format. Effective Date 03/21/2016 07/01/2016