Pepco to Increase Capacity with New Substation Waterfront Substation, Buzzard Point Project Overview Pepco is always working to provide safe, reliable electric service to our customers, and to support the needs of the region. As part of this commitment, we have identified the need to construct a new distribution substation within the Ward 6, Buzzard Point area of the District of Columbia. The proposed Waterfront Substation is needed to support existing customers and planned development in the Capitol Riverfront and Southwest Waterfront areas and to replace aging infrastructure. The new substation is expected to be placed in service by June 2017. Architectural Rendering of the future Waterfront Substation Project Work Plan Description Phase 1: Substation site preparation and design • November 2013 - April 2015 o Pepco will complete environmental studies, evaluate environmental impacts, and will begin site demolition approvals. We have completed a Phase 1 Environmental Site Assessment and have completed geotechnical testing. Demolition of the current infrastructure will commence in the first quarter of 2015. Phase 2: Regulatory authorization and zoning • June 2014 - May 2015 o Pepco will file for zoning authorization with the BZA and has filed a notice of construction with the District of Columbia Public Service Commission for new transmission lines and a substation. While these authorizations typically take between six to nine months, the public will have an opportunity to address its concerns at public hearings, meetings and open houses. Phase 3: Construction of the substation, transmission and distribution lines • January 2015 - June 2017 o Construction of the Waterfront Substation is essential for maintaining and improving the overall reliability and electric service for customers in the communities surrounding the substation. As part of this enhancement project, Pepco has outlined three phases of construction leading up to the targeted completion date of 2017. (More) Phase 3: Substation construction time-line • Transmission Construction (Jan. 2015 - Oct 2016) o Pepco will install four underground duct banks and 138kV transmission lines to supply the substation. The proposed route is depicted on the map to the right. • Substation Construction (May 2015 – March 2017) o In this phase, Pepco will construct an indoor substation located on the 100 block of Q St., SW. The substation will have an ultimate capacity of 350 Megavolt-Amperes (MVA) to accommodate the area’s projected long-term growth. Pepco will design the Waterfront Substation with the community in mind. The building’s aesthetics and architectural features are meant to seamlessly tie into the neighborhood setting. • Distribution Construction (April 2016 – June 2017) o Pepco will install eight to twelve underground duct banks and begin transferring thirty-four 13kV distribution lines from the Buzzard Point Substation. Engineering continues to assess what streets will be most impacted by this work. We will provide details on the exact locations as we learn them in the upcoming months. Proposed Substation and Impacted Streets Impact on the Community Pepco will continue to work diligently to minimize the impact of the scheduled work on residents and business owners. We will continue to provide updates as we progress and want to ensure that you are informed about possible impacts with the following facts: • • • • • • All work will be performed within the times identified in the construction permit. Pepco will restore all roadways and sidewalks impacted by the construction. Pepco will use mitigating procedures to minimize any dust emissions as a result of demolition of the existing buildings. Pepco anticipates that noise levels will be consistent with typical building construction within the District and will make every attempt to minimize disturbances throughout this process. Pepco anticipates that there are no wildlife risks as part of this process. Pepco will be completing environmental tests and will be following all regulations as outlined by the District of Columbia and Federal Government. Pepco’s Commitment: Keeping you Informed Our commitment is to keep those in the project area informed every step of the way. We will notify residents and business owners near the project area in advance of when construction will occur, provide constructon updates, and aim to complete our work with as little disruption as possible. As we move forward with these enhancements, Pepco will maintain a special area on our website for updates and additional information. These updates are available by following our Twitter handle @PepcoConnect and by visiting www.pepco.com/reliabilityprojects. For further questions, please contact Chris Taylor, Pepco Public Affairs Manager DC Region, crtaylor@pepco.com. ###