ELECTRICAL POWER DISTRIBUTION Week 1-2 Course Contents These are the “main and big headlines” for the topics we will study ■ ■ ■ ■ ■ ■ ■ ■ Introduction to electrical distribution system Distribution system elements & configurations Electrical load characteristics Voltage regulation in distribution systems Protection and branching circuit design Distribution transformers Power factor correction in distribution systems Operation and control of distribution systems How will you be graded and assessed? ■ RULE 1: WORK AND READ A LOT! EVERY WEEK YOU HAVE AN ASSIGNMENT! ■ RULE 2: BE ON TIME IN ASSIGNMENTS, NO EXCUSES FOR LATE OR UN-HANDED ONES. IF YOU MISS IT, YOU CANT MAKE IT UP! ■ RULE 3: BE ON TIME! LATE ENTRIES ARE NOT TOLERATED ■ RULE 4: LEAVE THE REST FOR ME System voltage classes according to IEEE Std 141-1993 ■ Low voltage: A class of nominal system voltages less than 1000 V. ■ Medium voltage: A class of nominal system voltages equal to or greater than 1000 V and less than 100, 000 V. ■ High voltage: A class of nominal system voltages equal from 100 000 V to 230,000V. 4 System voltage classes according to IEC Standard no. 38 (International Electro technical Committee) ■ Low voltage (LV) For a phase-to-phase voltage between 100 V and 1000 V. The standard ratings are: 400 V - 690 V - 1000 V (at 50 Hz) ■ Medium voltage (MV) For a phase-to-phase voltage between 1000 V and 35 kV. The standard ratings are: 3.3 kV - 6.6 kV - 11 kV - 22 kV - 33 kV ■ High voltage (HV) For a phase-to-phase voltage between 35 kV and 230 kV. The standard ratings are: 45 kV - 66 kV - 110 kV - 132 kV - 150 kV - 220 kV. 66 kV= High voltage in Egypt 11-22 kV= Medium voltage in Egypt الكود المصري مستوحي من IEC Substation and Distribution system Station switch yard 13.8 kV Power Plant Step up transformer 220 kV rural feeder Step down transformer 66 kV su transmission line 11 kV rural feeder Step down transformer Large industrial customer Secondary distribution substation 11 kV feeder Step down transformer 11 kV feeder 66/11 kV Commercial / industrial customer 66 kV sub transmission line 220/66 kV 13.8/220 kV Primary distribution substation Other 66 kV sub transmission lines Sub transmission sub station 11 kV/ 400 V 11 kV feeder 66 kV 400 v Radial distributor Step down transformer 11 kV/ 400 V Ring distributor Sub-transmission lines carry large amounts of power from the bulk power substations to the main distribution substations within the immediate area of use at intermediate voltages. The medium voltage network carries electrical power from the main distribution substations either directly to large industrial and commercial consumers or to distributor centers within residential areas at medium voltages. The primary feeders carry the electrical power from distributer centers to step down distribution transformers. The three-phase 380 V four-wire secondary cable carries the electrical power from the distribution transformer to building main switchboard. Generating Station: The place where electric power produced by parallel connected three phase alternators/generators is called Generating Station. The Ordinary generating voltage may be 11kV, 11.5 kV 12kV or 13kV. But economically, it is good to step up the produced voltage to 132kV, 220kV or 500kV or greater by Step up transformer (power Transformer). Primary Transmission: The electric supply (in 132kV, 220 kV, 500kV or greater) is transmit to load center by overhead transmission system. Secondary transmission: Area far from city which have connected with receiving station by line is called Secondary transmission. At receiving station, the level of voltage reduced by step-down transformers up to 132kV, 66 or 33 kV, and Electric power is transmit by three phase three wire overhead system to different sub stations. Primary Distribution: At a sub station, the level of secondary transmission voltage (132kV, 66 or 33 kV) reduced to 11kV by step down transforms. Generally, electric supply is given to those heavy consumer whose demand is 11 kV, from these lines which caries 11 kV and a separate sub station exists to control and utilize this power. For heavier consumer (at large scale) their demand is about 132 kV or 33 kV, they take electric supply from secondary transmission or primary distribution (in 132 kV, 66kV or 33kV) and then step down the level of voltage by step-down transformers in their own sub station for utilization ( i.e. for electric traction etc). Secondary Distribution: Electric power is given by (from Primary distribution line i.e.11kV) to distribution sub station. This sub station is located near by consumers areas where the level of voltage reduced by step down transformers 440V by Step down transformers. These transformers called Distribution transformers, three phase four wire system). So there is 400 Volts (Three Phase Supply System) between any two phases and 230 Volts (Single Phase Supply) between a neutral and phase (live) wires. Residential load (i.e. Fans, Lights, and TV etc) may be connected between any one phase and neutral wires, while three phase load may be connected directly to the three phase lines. Egyptian Network الشبكة الموحدة220 kV Any electrical network usually feeds a certain zone or location. In case any power failure in the network, all services will be interrupted and leads to disconnection of loads. The unified grid solves such problems since it connects a number or a group of networks together. In case of any power failure in one network occurs, the rest of the network feeds the loads and prevents their cut out. There Egyptian grid consists of the following: Generation : 24- 30 kV محطات التوليد Transmission : محطات الرفع ألغراض النقل علي أكثر من مستوي 220 kV: - حدود مصر- وجه بحري- القاهرة الكبري-معظم الجمهوريه (شرق الدلتا – غرب الدلتا )سيناء 500 kV: كم950 خط رابط بين أسوان و القاهرة طوله تقريبا كيلو فولت تم إختيارها بهذه القيمة الن المسافة بعيدة بين الصعيد ووجه بحري و500 شبكة ال بالتالي المقاومة الكلية للكابالت ممكن تؤدي النخفاض التيار للنصف تقريبا و بالتالي الجهد تقريبا500 أو ال440 إلي220 سيزداد للضعف من Egyptian Grid Interconnection Marine cable line البيان OH line خط الربط المصري الليبي Since 1998 خط الربط المصري االردني Since 1998 جهد الربط (ك.ف) 220 400 دول الربط ليبيا االردن سوريا لبنان الطاقة المباعة (صادرة) (ج.و.س) 100 1277 220 82 الطاقة الواردة (ج.و.س) 64 26 2 - Egyptian Grid Useful Statistics البيان %إجمالي الطاقة الكهربية المنتجة الطاقة المائية 7.94 طاقة الرياح 0.79 الطاقة الشمسية 0.07 كهرباء مولدة من المحطات الحرارية المربوطة بالشبكة 91.02 كهرباء مولدة من المحطات الغير مربوطة بالشبكة 0.14 كهرباء مشتراة من فائض الشركات الصناعية 0.04 إجمالي (مليون ك.و.س) 168069 تقرير وزارة الكهرباء عم 2014-2013 )Alexandria Network (Distribution 66 kV المنتزة + المعمورة +أبو قير 11 kV Incoming feeder 66 kV سيدي جابر جليم 11 kV سيدي جابر + سموحة 11 kV غرب (المنشيه +محطة الرمل) 11 kV غرب (العجمي) 20 kV 66 kV Subtransmission Distribution Systems Elements: General Overview First: 66 kV Subtransmission line Load-break Switch Second: Main Distribution Substation 11-kV High-rupture Capacity Fuse 11-kV bus Distribution Transformer 380-V Cable HV-Circuit Breaker 380-V Third: To the substation loads themselves LV Distribution Room N.C 380-V HRCF 11 kV Primary feeder 380-V Circuit Breaker (optional) N.C MV Tap Point Primary Feeder Sectionalizing Switches Fourth: to step down distribution transformers 11kV/380V Distribution Systems Configurations: أنماط شبكات التوزيع Primary Distribution System Arrangements The structure of distribution system and components used depends on two factors: • • • • • • The initial cost. Reliability. Service continuity. Voltage regulation. Efficiency. Operating and maintenance costs. More reliable systems mean higher installation costs which will be translated into higher price for kWh consumption The choice between reliability and cost depends on the infra structure example: Milling factories Furnaces and steel residential area commercial and industrial areas MV Voltage Network: Primary Feeders 1. Radial configuration Supply disconnects, 66 kV down stream loads يتم التحكم في منطقة disconnects كبيره التغذية من ناحيه واحده و الحمل من الناحيه التانيه Time is required for BULK POWER LINE 66 kV Sub TL fixing faulted cable and thus power is interrupted Main CB 20 kV LV feeders 3 380/ 1 220V LV Distribution Substation HRCF DT HV HRCF 20 kV Isolating Switches Simplest system with minimum components , cables and cost To Major Consumers 20 kV MV Primary Feeders Distribution Transformer 20 kV Disconnection is done to the faulted part ONLY, however, sometimes the main switch (at transformer) is disconnected to disconnect multi consumers Radial System: Rural areas هذا النوع من الشبكات يتواجد في األرياف والقري The system offers the following advantages: • System investment is the lowest of all circuit arrangements. • Distribution is done at secondary voltage level • Operation and expansion are simple. • Simpler power flow calculations. • Current magnitude is high upsteam and lessen as we go downstream, thus the size of the conductor feeders are smaller downstream. BUT sometimes this puts more limitations to voltage drop allowance • One transformer is responsible for a group of loads having only one primary feeder. The system takes advantage of the total diversity among the loads and requires less space. • Each feeder is connected to the switchgear or switchboard bus through a circuit breaker or other overcurrent protective device. A relatively small number of circuits are used to distribute power to the loads from the switchgear or switchboard assemblies and panelboards. Usually is very convenient up to 1000 kVA (1 MW) capacity The reliability of simple radial systems has the following characteristics: • Loss of a cable, primary supply, or transformer will cut off service. • Equipment must be shut down to perform routine maintenance and servicing. • When high quality components and appropriate ratings are used reliability is high. • The system is satisfactory for small industrial installations Radial Systems: A “new look” The modern simple-radial distribution system : It distributes power at the primary voltage level so that the length of the low-voltage feeders is kept to a minimum, reducing cable cost and energy losses and improving voltage regulation. The voltage is stepped down to utilization level in the several load areas within the building typically through secondary unit substation transformers. The transformers are usually connected to their associated load bus through a circuit breaker Each transformer must have sufficient capacity to carry the peak load of the area it serves. The main disadvantage of this system is that service to all transformers will be interrupted in case of a fault in the primary circuit or maintenance work on the main circuit breaker. Like the simple radial system continuity and flexibility are poor. Modern simple-radial distribution system Used with systems more than 1000 kVA (1 MW) capacity Radial Systems: A “new look” • • • • The modified modern simple-radial distribution system: Reducing the number of transformers per primary feeder by adding more primary feeder circuits will improve the flexibility and service continuity of this system provides all the advantages of the modern simple-radial type, but includes important improvements in reliability. Each distribution transformer is fed from an individual primary feeder so that under fault conditions only the loads supplied by the faulted feeder are disconnected. Initial cost is higher mainly due to having a circuit breaker in each primary feeder. The cost can be reduced by replacing the circuit breakers with loadbreak switches. In this case a fault on a primary feeder will cause power disconnection to all loads due to the operation of the main circuit breaker. The faulted feeder is identified by opening all load-break switches and then reclosing them one by one. The faulty feeder is isolated and service can be restored to all the others. Modified modern simple-radial distribution system 2. Open-Loop Configuration مشهور جدا في المدن مثل القاهره واإلسكندريه BULK POWER LINE عادة بتكون66 شبكة ال ) (حلقهRing Main Unit (RMU) Loop-connected 66-kV Sub-TL Means that NORMALLY the loop is open and in EMERGENCY the loop closes Each is fed from TWO WAY power supplies Two-way HV subtransmission 66 kV power supply Very large industrial substation Primary Distribution Substation MV Primary Feeders Radial system Disconnecting Switches (NO) Tie Lines خط ربط Radial system Open loop Configuration • لو لم تكن في شكل «حلقة» ده معناه إن عند66 شبكة ال إنقطاع الكهرباء جزء كبير جدا سيتأثر بهذا األنقطاع This is a “normally open system”, this means that normally the downstream acts as a radial system. In case of any fault in the downstream circuit, 1- First the main section CB trips so that all the downstream cct is isolated from the power source then determines which section is faulted (through SCADA and monitoring station) 2- the disconnecting switches isolates the faulted section and closes the tie line 3- then gets service back again through connecting the main CB again During fault the system becomes a “loop system” through the connection of the tie line while the faulted part is isolated from the system. High reliability system 3. Loop Configuration Two loops exist so any load has two supplies The higher the reliability, the more complex the control and decision making Sub-transmission Line Sub-transmission Line مشهور جدا في المناطق الحيويه ووسط المدن BULK POWER LINE Major Load Distribution substation MV Primary feeders MV Primary feeders 4. Combination of Loop Subtransmission & Radial Primary Feeders BULK POWER LINE Main distribution substation Sub-transmission Line كوكتيل و موجود في القاهرة مثال Loop configuration for MV Primary feeders MV primary feeders Distribution substation Loop configuration for sub transmission system Distribution substation MV primary feeders Disconnecting Switches (NO) Radial configuration for MV primary feeders Tie line between two adjacent primary feeders (open loop_ MV primary feeders configuration Sub transmission and MV network Layout Radial Open loop Loop layout Combination (loop and radial) Advantages Disadvantages Applications Simple layout Low reliability Not used in sub Economical to install transmission systems compared to other layouts Simple layout Failure of one of the two Residential type consumers Economical to install primary feeders leaves a in urban areas and less compared to other number of consumers out density population areas layouts of service until the tie line Provision for switching switches are manually the load to the good line closed in the event of supply outage Reliable with two way Expensive and requires Residential type consumers supply more equipment in urban areas and less Malfunction section can density population areas be repaired without removing much of the sections from service Reliable and suitable for The radial part is Combination of residential, critical loads (such as arranged so that only industrial and commercial business and industrial residential customers are customers with a degree of loads) out of service in case of reliability which is load Reasonably econimical supply failure dependent Low-voltage Distribution Network Mesh system STANDARDIZED LV meshed feeder MV primary feeder BULK POWER Cable distribution cabinet Distribution transformer التخطيط للمدن العمرانيه الجديدة Each transformer receives a two way supply from two primary feeders One feeder Disconnecting or isolating switch Multi-line Fed meshed Single-line Fed meshed In single-fed meshed system, all In multi-line fed meshed systems, the substations of several medium-voltage lines can substations connected via the lowvoltage network are supplied from a be connected in parallel through the lowsingle medium-voltage primary feeder voltage system. Under ground low-voltage radial distribution system 3 to 6 MVA/km2 load density Residential area (3 to 6 MVA/km2 load density) Distribution Box D Typical residential area (Street width 7 meters), 5 floors C B Distribution transformer A Main cable Out of distribution box cable 240 mm2 4/C Aluminium conductor 1 kV 185 mm2 4/C Aluminium conductor 1 kV 50 mm2 4/C Aluminium conductor 1 kV To inside SMALL (5 FLOOR)building cable Or copper equivalent cable Another “dry type” transformer for voltage drop (expensive a bit, 11kv rating) Low voltage system of high rise buildings Lifts مباني مرتفعه ) طابق مثال14 (فوق Automatic sourcechangeover systems with mechanical interlocking Sub-panel boards for distributed loads in the floor شقق8 أكثر من محول توزيع غرفة الكهرباء و الدخول Bus-way type shaft riser for main supply Sub-panel board for Floor Emergency Bus-way type shaft riser for emergency supply الدورالثاني بدال من الكابالت ATS LV emergency bus 11 or 20 kV MV Feeder Entrance Cables Dotted line means emergency, solid means main G LV Main supply bus مولد إحتياطي Types of Installation of LV Distribution Systems in Buildings 1. Distribution by insulated conductors and cables: يستعمل في البنايات ذات عدد طوابق محدود Local general distribution board Sub-distribution board لوحة التوزيع الفرعية There could be 1 riser or more than one depending on the building size Main general distribution board Heating, etc. لوحة التوزيع الرئيسية General utilities distribution board Types of Installation of LV Distribution Systems in Buildings 2. Distribution by prefabricated bus-trunking & cables channels Bus-duct transformer to Main dist. board Main dist. board Main bus-bar trunking Transformer Local dist. board Prefabricated power and light current column Prefabricated prewired cable channels Also known as “bus way” Prefabricated bustrunking CHALLENGE QUESTION OF THE WEEK! TO BE HANDED IN BY NEXT WEEK IN THE SECTION. “Can you find other primary / secondary distribution systems layouts?” YOUR REPORT MUST: 1- hand written in clear (or computer typed), neat handwriting 2- includes references 3- Clear diagrams, labels .. Look first in your text book then you can look in the internet 4- cover page with your name and registration number 5- Be Subjective… don’t talk too much 6- DO NOT COPY AND PASTE 7- Marks will be rewarded according to subjectivity, organization, clarity and creativity