David Smith, Sales Support Manager, Product Solar Group, Grid Export Limitation Segen Seminar What is Network and Export control ? When the potential amount of locally generated electricity has reached a level when the DNO cannot accept any more without breaching its licence conditions & ESQCR*, a constraint may be needed. The solutions are; o Upgrade the network to accommodate the requirement. o Impose an export constraint to limit the export of energy generated *ESQCR - Electricity Safety Quality & Continuity Regulations (Principal stakeholders – HSE, DECC, DBIS, OFGEM) Key aspects ; • • • DNO is licensed and legally bound to provide phase voltage to customers at 230V +/- 10% (ie between 207 & 253V) and within frequency range Demand customers reduce voltage with increased demand Prosumers can increase grid voltage with increased generation (G83/2 and G59/3 is 262V to allow 3% volt rise between Point of connection and inverter) © ABB 17 April 2015 | Slide 2 When is export limiting network reinforcement required? The DNO may propose an export constraint or network reinforcement for 2 principal reasons when you apply to connect a generator o The voltage rise may put the network out of ESQCR compliance o The thermal capacity of the network has been reached. • • The delivering of active power ( current and voltage in phase) into the grid generates a voltage drop in the grid-line which increases the voltage in the connection point of the plant (Vinv). This is caused by grid line resistivity (RL). RL Vgrid Iinv XL PFV PDC Vinv If the inverter’s current lags the voltage with a certain phase angle (inductive behaviour), there is reduction of Vinv voltage. NB - If the network fault level has been reached, export constraint will not resolve the issue!! © ABB | Slide 3 UK Requirement for export limitation (Commercial/LV) • They must be fail safe. In other words they must limit export if the export limiter fails or it loses its power supply. • The system must not rely on wireless coms (e.g. Bluetooth, Wifi etc.) between the various component parts of the export limiter system (e.g. the sensors, the export limiter and the inverters). • The system must meet all relevant power quality requirements (e.g. G5/4 for harmonics, P28 for flicker, P29 for unbalance). • The system must operate within 1s • They system commissioning tests shall normally be witnessed by DNO • Note, if the system is not fail-safe by design then an additional reverse power relay must be included to disconnect the generation if the export goes above an agreed limit. © ABB | Slide 4 Export limiting control “Measure, calculate and control” PV Panels Inverter(s) Point of Connection Measurement G59 Loads Calculate and control © ABB 17 April 2015 | Slide 5 Grid Export limiting control “Measure, calculate and control” Measurement - Total active Power (kW) in the export line needs to be measured and monitored. Four Quadrant (Bi-directional) power energy meters • • • 2 x relay ouputs MID compliant option Modbus RS485 option Provides calculation reference • © ABB 17 April 2015 | Slide 6 Measurement class CTs Export limiting control “Measure, calculate and control” PV Panels Inverter(s) Point of connection Measurement G59 Loads Calculate and control © ABB 17 April 2015 | Slide 7 Grid Products to achieve export limiting control Introducing PMU Calculate and Control - with information of Total active Power (kW) and sum of each inverters output active power, export limiting device can instruct inverters to reduce active power. © ABB 17 April 2015 | Slide 8 Explanation of MPPT tracking © ABB 17 April 2015 | Slide 9 Products to achieve export limiting control “Measure, calculate and control” Calculate and Control - with information of Total active Power (kW) and sum of each inverters output active power, export limiting device can instruct inverters to reduce active power Shaded area demonstrates limitation mode and available power Inverter power limitation mode to keep exported power lower than required. Power 2nd threshold band 1st threshold band 100% inverter power consumed by load Time The METER measures the power injected to the grid and 2 power thresholds level are selected on the METER. When the thresholds are reached the METER closes a single digital output connected to the export limiter (PMU) Upon recieving signal, export limiter (PMU) reduces the inverter(s) output power via RS485 to set thresholds, The power limitation /threshold level is dependant upon % of export power allowed – ie adjusted according to plant needs © ABB 17 April 2015 | Slide 10 Measure, calculate and control Simplified schematic PV Panels 3 PH + N (Voltage reference Inverter(s) x 3 CT RS485 LINE Loads Input select = 7 Power management unit - PMU Digital signals from meter K4 K1/K2 GND © ABB | Slide 11 Q2+ Q1+ Q1- / Q2- Grid Products to achieve export limiting control “backup protection and failsafe” PV Panels Inverter(s) Point of connection Measurement G59 Loads Calculate and control © ABB 17 April 2015 | Slide 12 Grid Measure, calculate and control Failsafe - Simplified schematic 3 PH + N Voltage reference 3 PH + N Voltage reference Loads G59/3 relay CM-UFD.M33 Connected to G59 relay remote trip line (auto reclose) © ABB | Slide 13 x 3 CT Reverse power relay Grid Measure, calculate and control Failsafe - Simplified schematic – small scheme 3 PH + N Voltage reference x 3 CT x Example ; • Undervoltage trip option • Optionally motorized (auto reclose) Reverse power relay Connected to MCCB with undervoltage trip © ABB | Slide 14 Grid Measure, calculate and control Failsafe - Simplified schematic – single inverter scheme 3 PH + N Voltage reference x For example, TRIO has the power limitation set to 90% (maximum permitted power injection) meter relay output to power off the inverter if >90% of the max power is injected into the grid. Additional Meter output connected to inverters inhibit line © ABB | Slide 15 x 3 CT Grid Measure, calculate and control Introducing PLC – larger scheme 3 PH + N Voltage reference XT series Breakers Grid x 3 CT Trip and reclose B23-312-100 MID approved Meter Loads G59/3 relay CM-UFD.M33 RS485 Trip signal Inverter monitoring and Control – MODBUS RS485 © ABB | Slide 16 AC500 PLC Range Summary of architectures Solution Inverter Shedding Method Contactor on output of each inverter Pro Con o o o Low cost Inverter agnostic Simple to understand – DNOs happy o o Can loose significant power generation. Additional “wear and tear” through increased switching of inverters internal protection relays – impact inverters life. PV system shedding Disconnection of PV output o As above o None if used in correct application – ie “ Xmas day scenario” – IE 365 day onsite load Power Diverters Active power used in onsite load o Some devices DNO approved No loss of active generation o High cost especially for 3 phase systems. Flicker compliant? Proof of sufficient load to absorb energy Relatively low cost. No impact on inverter life and warranty. Grid control ready o o Intelligent Inverter Control + failsafe © ABB 17 April 2015 | Slide 17 Control of inverters active power + failsafe o o o o o o o Slight loss of generation but not significant if designed well. Inverter specific. DNO satisfaction. Inverters are already smart grid ready…….. Inverter has the capabiity to contribute to grid stability and control in order to increase grid quality Frequency control Capability to select Active power reduction and Reactive power regulation Voltage Control = Smart grid ready Power Factor Management Industry accepts inverters as part of the solution © ABB 17 April 2015 | Slide 18