CAMPBELLFORD BRIDGE REPLACEMENT FEASIBILITY STUDY REVIEW OF FINAL TWO OPTIONS WTH MODIFIED 3 LANE ALTERNATIVE AUGUST 2011 AUGUST 2011 August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee PREFERRED OPTIONS DETERMINED BY STEERING COMMITTEE g Committee Meeting g on June 24, At the last Steering 2011, committee members choose the preferred options within the 11 alternatives presented by GENIVAR 2 options were chosen. GENIVAR. chosen Widen/Upgrade 3 Widen/Upgrade 3 Lane Bridge Matching Centreline Twin Existing Structure to the North August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 2 ALTERNATIVE II‐2N TWINNING THE STRUCTURE TO THE NORTH ADVANTAGES Existing Bridge to be used as a detour during the construction of a new f bridge, Traffic continues to use downtown crossing during downtown crossing during construction, Final configuration provides 4 lanes of traffic d l f ff Potential to enhance the downtown community, Potential for the addition of parking in the locations of removed buildings, Construction cost is for a new 2 lane bridge August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 3 ALTERNATIVE II‐2N TWINNING THE STRUCTURE TO THE NORTH DISADVANTAGES Roadway re‐alignment required at the intersections to join intersections to join connecting roads to the new bridge, Removal of Buildings beyond Queen St./Grand Rd and Front / Street, Loss of on‐street parking due to widened y, connection roadways, Loss of Housing and Businesses due to Businesses due to building removals, Requires the replacement of the existing bridge in the ( future (construction and economic impacts). August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 4 ALTERNATIVE III‐3b / WIDENING/UPGRADING THE EXISTING BRIDGE TO 3 LANES ADVANTAGES Existing Bridge used as a detour during May – a detour during May October, Final configuration provides 3 lanes of provides 3 lanes of traffic Only buildings at corners of bridge are required to be removed. Less removal of on‐ street parking than Alternative II‐2N,, Design allows for the utilization of the g g , existing bridge, Construction cost at the lowest comparable costs to the other alternatives. lt ti August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 5 ALTERNATIVE III‐3b / WIDENING/UPGRADING THE EXISTING BRIDGE TO 3 LANES DISADVANTAGES Off site detour is required from October required from October to May, Traffic will not be routed through the downtown crossing during October to May, Length of construction is longer than Alternative II‐2N. Loss of Housing and Businesses due to building removals (less building removals (less removal than Alternative II‐2N), Construction to begin in 5 years to utilize g g existing bridge August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 6 CONSTRUCTION METHODS Is there a different construction method that has Is there a different construction method that has the following advantages? – On‐site detour that is not temporary On site detour that is not temporary – No building removal beyond Front Street and Grand Road/Queen Street Grand Road/Queen Street. Suggestion – Rapid Lift Technology (Sliding Suggestion Rapid Lift Technology (Sliding Method) such as Trent Bridge Replacement August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 7 CONSTRUCTION METHODS RAPID LIFT REPLACEMENT ‐ PROCEDURE Traffic to remain on the existing bridge, g g , • • • • • Buildings at the three corners of the bridge would be removed due to the final configuration of the bridge. These building removals will allow for construction access and mobilization area for the new bridge construction. g Strengthening of existing piers/abutments and extension of the piers/abutments to the south, New concrete piers and footings would be constructed on the north side New concrete piers and footings would be constructed on the north side of the bridge. New superstructure consisting of a steel superstructure with concrete deck would be constructed on the new piers/abutments deck would be constructed on the new piers/abutments. Construction of beam and sliding system, August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 8 CONSTRUCTION METHODS RAPID LIFT REPLACEMENT ‐ PROCEDURE Traffic to be detoured to new bridge, g , • • Existing bridge superstructure to be removed New structure slide onto existing piers New structure slide onto existing piers, Traffic rerouted onto new 3 Lane structure. August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 9 CONSTRUCTION METHODS / RAPID LIFT REPLACEMENT – ADVANTAGES/DISADVANTAGES Advantages g • • No building removal beyond Front Street and Grand Road/Queen Street, Existing bridge and new bridge used as detours, no temporary detour required. required Disadvantages • • • • Additional piers required to be built to support bridge temporarily (Cost), Cost of sliding mechanism, Additional roadway work required at intersection for temporary condition, y q p y , All work required in 10 years for traffic requirements, existing bridge will still have some service life remaining. August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 10 CONSTRUCTION METHODS MODIFIED 3 LANE BRIDGE ALTERNATIVE Traffic to remain on the existing bridge, g g , • • • Buildings at the three corners of the bridge would be removed due to the final configuration of the bridge. These building removals will allow for construction access and mobilization area for the new bridge construction. g Strengthening of existing piers/abutments and extension of the piers/abutments to the north and south, New minimum 2 Lane post‐tensioned New minimum 2 Lane post tensioned concrete bridge with sidewalk concrete bridge with sidewalk constructed on pier extensions to the north, August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 11 CONSTRUCTION METHODS MODIFIED 3 LANE BRIDGE ALTERNATIVE Traffic to be detoured to new bridge, g , • • Existing bridge superstructure to be removed New post tensioned concrete superstructure constructed on existing New post‐tensioned concrete superstructure constructed on existing reinforced and south extension piers/abutments, Traffic rerouted onto new Modified 3 Lane structure with recreational facility and wide sidewalk on the north. August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 12 CONSTRUCTION METHODS / MODIFIED 3 LANE BRIDGE ALT. – ADVANTAGES/DISADVANTAGES Advantages g • • • • No building removal beyond Front Street and Grand Road/Queen Street, Existing bridge and new bridge used as detours, no temporary detour required. required Pier extensions are reduced by 8.5m from 20m to 12.5m. No sliding mechanism or other Rapid Lift Replacement technology required. required Disadvantages • All work required in 10 years for traffic requirements, existing bridge will still have some service life remaining. August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 13 CONSTRUCTION METHODS MODIFIED 3 LANE BRIDGE ALTERNATIVE – OPTION 2 Can we overcome this disadvantage? g • • • Stage 1 construction (construction of minimum 2 Lane bridge north of existing bridge) to occur in 10 years. Interim configuration using both new bridge and existing bridge for 10 Interim configuration using both new bridge and existing bridge for 10 years. Stage 2 construction (existing bridge removal and construction of new bridge) to occur in 20 years bridge) to occur in 20 years. The interim configuration will pose some structural challenges as well as traffic configuration challenges traffic configuration challenges. August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 14 CONSTRUCTION METHODS MODIFIED 3 LANE BRIDGE ALTERNATIVE – OPTION 2 August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 15 CONSTRUCTION METHODS MODIFIED 3 LANE BRIDGE ALTERNATIVE – OPTION 2 August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 16 CONSTRUCTION METHODS MODIFIED 3 LANE BRIDGE ALTERNATIVE – OPTION 2 August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 17 CONSTRUCTION METHODS MODIFIED 3 LANE BRIDGE ALTERNATIVE – OPTION 2 August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 18 CONSTRUCTION METHODS MODIFIED 3 LANE BRIDGE ALTERNATIVE – OPTION 2 August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 19 CONSTRUCTION METHODS MODIFIED 3 LANE BRIDGE ALTERNATIVE – OPTION 2 August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 20 CONSTRUCTION METHODS MODIFIED 3 LANE BRIDGE ALTERNATIVE – OPTION 2 Can we overcome this disadvantage? g • • • Stage 1 construction (construction of minimum 2 Lane bridge north of existing bridge) to occur in 10 years. Interim configuration using both new bridge and existing bridge for 10 Interim configuration using both new bridge and existing bridge for 10 years. Stage 2 construction (existing bridge removal and construction of new bridge) to occur in 20 years bridge) to occur in 20 years. The interim configuration will pose some structural challenges as well as traffic configuration challenges traffic configuration challenges. August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 21 PREFERRED OPTIONS From Steering Committee (June 24, 2011 Widen/Upgrade 3 Lane Bridge Matching Centreline • Critical Considerations • Time for Construction Planning (including EA plan and process, obtaining g g) g funds, detailed design and contract tendering) is longer than the time required to start construction due to engineering design • Alternative Requires Temporary Detour T i E i ti St t Twin Existing Structure to the North t th N th • Critical Considerations • Further investigation required to address the impact of housing removal • Further investigation required to address the impact of loss of business August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 22 MODIFIED 3 LANE STRUCTURE REVIEW OF CRITICAL CONSIDERATIONS Time for Construction Planning • Existing Bridge is not utilized in final design. Construction can begin in 10 years Alternative Requires Temporary Detour • No additional Detour Structure is required. • Traffic will be maintained on existing bridge with minor modifications while Stage 1 construction is completed. • Traffic will be maintained on the Stage 1 bridge while Stage 2 is completed. Impact of housing removal and loss of business • Building removal is limited to the quadrants immediately adjacent to the bridge. August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 23 CONSTRUCTION START Twin Existing Bridge – North Side •Build new (2 lane) bridge ld ( l )b d in 10 years using existing bridge as detour. •Replace Existing bridge in y 20 years at end of service life using new bridge as detour Widen/Upgrade Existing Bridge – 3 Lanes Modified 3 Lane Bridge Option 1 Option 2 •Upgrade/Widen bridge in 5 d / d b d years. •Construction would commence in 2 years. •Requires detour structure q •Extend service life of existing bridge to 75 years. •Build new 3 lane bridge ld l b d with recreational facility in 2 stages in 10 years. •First stage to use existing g g bridge as detour bridge •Second stage to use Stage 1 bridge as detour. •Build new (narrow 2 ld ( lane) bridge in 10 years using existing bridge as detour. •Construct Stage 2 in 20 g years at end of service life Stage 1 bridge as detour Traffic Capacity at the intersections at the ends of the bridge will reach capacity in 10 years. Usable Existing Bridge Service Life is 20 years. August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 24 BUILDING REMOVAL REQUIRED Twin Existing Bridge – North Side 2Buildings ld at Northwest h and Northeast corners are to be removed. •Some buildings west of Q Queen Street on the north are required to be removed. •Some buildings east of Front Street on the north are required to be are required to be removed. •Building at Southeast corner of the bridge to be removed for the construction in 20 years. Widen/Upgrade Existing Bridge – 3 Lanes •Buildings ld at Northwest, h Northeast and Southeast corners of the bridge to be removed. Modified 3 Lane Bridge Option 1 Option 2 •Buildings ld at Northwest, h Northeast and Southeast corners of the bridge to be removed. •Buildings ld at Northwest h and Northeast corners are to be removed. •Building at Southeast g corner of the bridge to be removed for the construction in 20 years. August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 25 CAMPBELLFORD BRIDGE REPLACEMENT FEASIBILITY STUDY AUGUST 2011 August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee ROADWAY DRAWINGS INTERIM TRAFFIC CONFIGURATION August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee Slide 27 CAMPBELLFORD BRIDGE REPLACEMENT FEASIBILITY STUDY AUGUST 2011 August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee COST ESTIMATES Twin Existing Bridge – North Side Widen/Upgrade Existing Bridge – 3 L Lanes $10 ‐ $12 million (10 years) $11 ‐ $13 million (20 years) $10 – $12 million (10 years) Modified 3 Lane Bridge u Co s uc o in 10 0 Construction Full years STRUCTURAL COSTS * $16 ‐ $19 million (10 years) S ge 1 – 100 ye Stage yearss Stage 2 – 20 years $9 ‐ $11 million (10 years) $9.5 ‐ $11.5 million (20 years) COSTS TO ESTABLISH TEMPORARY DETOUR ROUTE ‐ $1.75 ‐$2 million (10 years) ‐ ‐ ROADWAY COSTS * $1 9 ‐ $2.5 million $1.9 ‐ $2 5 million (10 years) $0 5 ‐ $0.6 million $0.5 ‐ $0 6 million (10 years) (10 years) $1 3 ‐ $1.5 million $1.3 ‐ $1 5 million (10 years) (10 years) $1 3 ‐ $1.5 million $1.3 ‐ $1 5 million (10 years) (10 years) NET PROPERTY (LOW/HIGH) $1‐ $1.2 million $1.0 ‐ $1.2 million $1.0 ‐ $1.2 million (0 – 10 years) (0 – 10 years) (0 – 10 years) $0.75 ‐ $0.8 million (0–10 years) $0.3 million (0 – 20 years) TOTAL COST (LOW/HIGH) $12.9‐15.7 million (10 years) $11 – 13 million (20 years) $13.25‐15.8 million (10 years) * Engineering Design or Contract Administration not included. Slide 29 $18.3‐21.7 million (10 years) $11.05‐12.3 million (10 years) $9.8– 11.8 million (20 years) August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee CAMPBELLFORD BRIDGE REPLACEMENT FEASIBILITY STUDY AUGUST 2011 August g 22, 2011 – Meeting g of the Trent River Crossing g Steering g Committee