Developers’ Manual Version 1.36.1 watercorporation.com.au 2 Revisions The following clauses in this manual were revised on the dates shown. Revision Number Issue Date Reason for Change 1.0 4 August 1999 Initial Issue 1.1 6 April 2000 1.2 16 January 2001 1.3 10 September 2001 1.4 May 2002 1.5 September 2003 1.6 January 2006 1.7 July 2006 1.8 May 2007 Amendments to clauses 2.1, 2.3.2, 4.1, 5.1, 18.1, 19.1.3, 19.1.5, 22.2, 23.1.2, 23.1.4, 26.1.1, 26.1.4, 26.2.1 and 27.1 Clauses 4.2 and 27.1.1 deleted New sections 28 and 29 added Modifications to table of contents, maps, glossary of terms and minor editorial changes Amendments to clauses 2.1, 2.2, 2.3.2, 2.3.3, 9.4.2, 9.4.3, 18.1.1, 18.1.2, 19.1.5, 22.1.2, 22.1.3 (deleted), 24.3.6, 25.1.3 (added), 25.2.5, 25.2.6, 25.3, 26.1.1, 26.1.2, 27.1.1 and 29 Modifications to table of contents, glossary of terms and minor editorial changes Amendments to clauses 2.1, 2.2, 10.1.3, 19.1.5, 24.1.1, 24.3.7 (added) Modification to table of contents Amendments to clauses 2.1,18.1.1, 19.1.5, 24.3.1, 24.3.6, 29.3 (added) Section 18 renamed and Section 10.1 clarified Modifications to table of contents and glossary of terms Amendments to Clauses:2.3 numbered in body of document, 9.4.3 Category g) added; drawing guidelines changed to” WCX CAD Standard (formerly WCX Pack)”, 2.2 Wastewater Manual Volume 2 replaced with “Design Standard Number 51” and “for drawing standards WCX CAD Standard (formerly WCX Pack)” added, and “Vacuum Sewerage Manual” added. 6. amended. 10.1.12 Vacuum Sewerage added. 25.2.6 inserted and existing 25.2.6 & 25.2.7 re numbered, 22.6.2 amended and 22.6.2.1, 22.6.2.2 and 22.6.2.3 added. “Design Standards” added to Glossary of Terms and in general text throughout manual as required. Modifications to table of contents Contact details in Clauses 5.1 5.2 & 5.3 amended Clause 2.2 – list of manuals amended to include External Approvals Manual Clause 8 Title changed to External Approvals – modifications to text to accommodate External Approvals Manual and new location of Prelims to Works Clause 10 – Initial Submission. General amendments to replace covering letter with Submission cover sheet included at Clause 10.1 Clause 12 – Final Submission. General amendments to replace covering letter with Submission cover sheet included at Clause 14.1 Requirement for Serviceable Lots list added at clause 10.1.7 – other clauses renumbered to suit and Submission Cover Sheet for Review of Initial Engineering Design Submissions amended Amendment to clauses Clause 2.3.3 Added “The Construction Engineer is responsible for arranging the construction of the works to meet the requirements of the relevant manuals, codes and standards”. Section 11 Numbering reformatted on Submission Cover Sheet 1.9 February 2008 External Approvals Paragraph to added outlining requirement to obtain comment from external agencies regarding developments adjacent to or crossing a road reserve or asset under control of an external agency. 3 Revision Number Issue Date Reason for Change 1.10 February 2008 Modifications to table of contents Clause 9.6 Deleted “from the Design Coordination by fax request on 9420 2203” and replaced it with “by completing the Application Form at Attachment 3 and forwarding it to your Submission Contact.” Added Attachment 3 ‘”Application for single use of Water Corporation example drawings for pumping station facility in electronic format”. 1.11 April 2008 1.12 May 2008 1.13 September 2008 1.14 October 2008 Submission Cover Sheet for Acceptance of Final Engineering Submissions paragraph 5 external approvals amended to ensure that the required actions are completed Clause 2.3.4 Paragraph to serve notice that the Corporation has the right to accept or reject nominated engineers. Clause 10.1.13 paragraph amended following request from Principal Engineer Infrastructure Design Branch Clause 10.1.14 Paragraph titled “Low Pressure Sewerage” and amended to explain in what circumstances Grinder Pumps are permitted. Clause 6 of the Submission Cover Sheet for Review of Initial Engineering Design Submission redrafted to indicate if adjacent lots are likely to become serviceable as a result of the works. Clause 6 of the Submission Cover Sheet for Acceptance of Final Engineering Submission redrafted to indicate property details of lots of lots rateable as a result of the works 1.15 February 2009 Paragraph 5.3 As Constructed Contact details amended Clause 15.2 re drafted to outline the requirement relating to the Final Design Submission for Urban Drainage works. March 2009 Contact details for Kalgoorlie para 5.2 amended also 5.3 amended to ensure all “as constructed” details are forwarded to the Spatial Information Management Group 1.16 April 2009 Submission Cover Sheet for Acceptance of Final Engineering Submissions paragraph 5 External Approvals amended to ensure that all requirements relating to the External Works Manual and the Utilities Code of Practice are met. 1.17 August 2009 Clauses 10.1, 11,22.5, 24, 24.5.3 and 26 aligned to similar provision in the Advanced Works Agreement Manual . Additional checklist examples added clause 11.2 also Attachment 4 (i.e. example of a Wastewater As Constructed plan) 1.18 September 2009 Amended the Wastewater Reticulation and Water Reticulation Initial Design Checklists Paragraphs 10.4.4 and 11.4 deleted Paragraph 24.5.2 relating to as constructed information for Water Reticulation works revised Clause 22.7 Joint Final Inspection changed to Final Takeover Inspection Clause 24.5.3 Amended to attachment 4 Clause 24.5.4 Typographical error amended Clause 24.5.5 amended to reflect details contained in 24.5.2 Clause 5.1 Main Extension contact details amended Appendix 4 Example Wastewater Reticulation As Constructed Plan reformatted as A3 1.15.1 1.18.1 October 2009 1.19 December 2009 1.20 January 2010 Clauses 10.1, 11.3, 11.4 & 11.5 changed to incorporate requirements of Urban Main Drainage Manual. 4 Revision Number Issue Date Reason for Change 1.21 July 2010 Section 3 Process Flowchart Prerequisites to Works amended to External Approvals and Prerequisites to Works Section 5 Perth Contacts amended to include Main Relocations Section 11 amended to include Design Standard Variation Request criteria Section 13 Manager Land Development amended to Manager Development Services Branch 1.22 October 2010 Section 11.2 Submission cover sheet for review of initial engineering design amended Section11.3 Water and wastewater reticulation initial design checklists amended 1.23 March 2011 Section 24 Incomplete submissions will not be accepted or captured until requested information is received. 1.24 June 2011 Section 5 Corporation Contacts Section 5.2 Inspection Contacts Section 5.3 As- Constructed Information Contacts Section 5.4 State Map Section 5.5 South West Region Map Section 5.6 Metropolitan Map 1.25 December 2011 Point 10.1.7 deleted from Initial Submission Requirements Section 28 Added reference to Section5 of the Working Near Water Corporation Pipeline Guidelines 1.26 January 2012 Section 5.2 Amended contact numbers for the Southwest Region Added Plan Number field to the Submission Cover Sheet for Acceptance of Final Engineering Submissions. Section 24 Added Water and Wastewater Reticulation As-Constructed Submission Checklist Section 28 Attachment 1 amended to include open drains 1.27 March 2012 Submission Cover Sheet for acceptance of final engineering submissions – section headings numbered Clause 24.1 Recording of as constructed information amended to include Licensed Surveyors or Engineering Surveyors 1.28 May 2012 1.29 February 2013 1.30 July 2013 1.31 December 2013 1.32 April 2014 Section 5.1 Amended submission contact details Section 5.2 Amended North West Region telephone / Fax numbers Section 2.2 Amended reference to Design Standards Section 4.1.2 Revised paragraph 2_Connection to Existing Works Section 5.3 As Constructed Information Contact details amended Section 11 Added Water and Wastewater Headworks Initial design checklists Amended the maps in Sections 5.4, 5.5 and 5.6 Section 11.1 amended to make reference to the Design Standard variation Request Form and Inserted new form (page 27) Section 8 Amended legislative requirement to provisions of the Water Services Act 2012 Section 9.4 Change phone contact to email inbox address Section 9.5 Amended fax number Section 11 Added Drainage Works Initial Design Check list Section 20.3 Added Construction of assets without all relevant approval requirements Amended Initial submission coversheet, Water and Wastewater retic and Drainage works check lists 5 Revision Number Issue Date Reason for Change 1.33 August 2014 South West Region map removed Initial Submission Cover sheet removed Headworks assets removed as scope of works Process diagram revised Application/Submission forms located at rear as appendices Additional Pre-calculated information included 1.34 December 2014 Section 10.2 Site plan information to be included with digital copy of design drawings Section 15.4 amended to include requirement where drawing amended and cost of project increases a revised Final Subdivision Cover Sheet must be included Section 23 revised sub paragraphs 23.1.3 and 23.1.5 removed Appendix 5 Final submission Cover Sheet added additional dot point under Important information for Design Engineers 1.35 May 2015 Section 14 Additional information required i.e. Name of Construction Engineer, Contractor , Sub contractor Section 17 redrafted - Constructed Phase – Start-up Section 18 redrafted.-. Construction Phase - Design amendment – alterations to an accepted final submission 1.36 November 2015 Country Inspection Contacts amended 2.3 and 2.4 added to Wastewater Initial Submission cover sheet to be consistent with Water Initial Submission cover sheet Minor updates to Water Initial Design Checklist August 2016 Appendix 8 – As Constructed Plan checklist updated Items 11, 12, 13 and 14 added to the Wastewater requirements Items 9,10, 10, 11 and 12 added to the Water requirements 1.36.1 6 Feedback Form To provide feedback on the Developers’ Manual, please complete this form. Publication Information Title: Developers’ Manual Revision Status: Your Information Address: Name: Fax: Phone: Proposed Change Information Section: Page No.: Para Reference (e.g. 1.2.3): Description of change: Reason for change: Do you require a response to your suggestion/request? Your signature: Please return completed form to: Development Services Branch Water Corporation PO Box 100 LEEDERVILLE WA 6902 Fax: 9420 3193 Date: Yes No 7 Table of Contents Developers’ Manual ......................................................................................................... 1 Version 1.37 ................................................................................................................... 1 Revisions ...................................................................................................................... 2 Feedback Form ............................................................................................................. 6 Foreword ...................................................................................................................... 9 1 Glossary of Terms ................................................................................................ 10 2 Introduction ......................................................................................................... 12 2.1 Scope ................................................................................................................ 12 2.2 Technical and Other Manuals ............................................................................ 12 2.3 Roles and Responsibilities ................................................................................. 12 2.4 Notification ....................................................................................................... 13 3 Fees ..................................................................................................................... 13 4 Corporation Contacts ........................................................................................... 15 6 Planning Phase - Preliminary investigation .......................................................... 19 7 Planning Phase - Land requirements .................................................................... 19 8 Planning Phase - External approvals .................................................................... 19 9 Design Phase - Design of works ........................................................................... 20 9.1 Design requirements.......................................................................................... 20 10 Design Phase - Initial Submission ..................................................................... 20 10.1 Purpose of the initial submission ................................................................... 20 10.2 Requirements of the initial submission .......................................................... 20 10.3 Drainage ........................................................................................................ 21 10.4 Vacuum Sewerage systems ............................................................................ 21 11 Design Phase - Design standard variation requests .......................................... 21 12 Design Phase - Review of the Initial Submission .............................................. 22 13 Design Phase - Objections to the Corporation’s requirements .......................... 22 14 Design Phase - Final Submission ....................................................................... 22 15 Design Phase - Acceptance of the Final Submission .......................................... 23 16 Design Phase - Alterations to an Accepted Final Submission ............................ 23 17 Construction Phase – Start-up ......................................................................... 23 18 Construction Phase – Design Amendment (Alterations to an accepted final submission) ............................................................................................................... 24 19 Construction Phase – Construction Requirements ............................................. 24 20 Construction Phase – Isolation of new works (wastewater only) ..................... 25 21 Construction Phase – Inspection of works during construction......................... 26 22 Construction Phase – Connecting to existing assets ......................................... 28 23 Takeover Phase – As-Constructed drawings ..................................................... 28 24 Takeover Phase – Takeover of the works .......................................................... 29 25 Takeover Phase – Warranty Period ................................................................... 29 8 26 Takeover Phase – Final Acceptance Certificate ................................................. 30 COVER SHEET FOR ACCEPTANCE OF FINAL ENGINEERING SUBMISSION .................... 35 9 Foreword The Developers’ Manual is an initiative by the Water Corporation in response to feedback from the development industry for greater standardisation of requirements for water, wastewater and urban drainage assets. The manual is made up of topics extracted from the technical manuals that deal with administrative rather than technical requirements. In bringing these requirements together considerable effort has been made to standardise, clarify and simplify them. The terminology of the manual reflects the reality that the only agreement the Corporation has is with the developer, not with any construction engineer or contractor. Please use the feedback form on page 3 if you have other ideas for improvements. Any feedback is welcome and all suggestions for improvement will be carefully reviewed and acknowledged. This manual refers to the Corporation’s technical manuals and design standards for technical information relating to water, wastewater and drainage works. These manuals will be updated in the future to remove information that is in this new manual and bring them in line with it where necessary. Should material in a technical manual or design standard conflict with information in this manual, this manual takes precedence. This manual does not apply to works required to serve large developments. For this type of development please refer to the Multi-Staged Development Works Manual. 10 1 Glossary of Terms In this Manual the following words and expressions shall have the following meanings. These meanings do not necessarily comply with the meanings given in the Water Corporation Act and other Water Corporation publications. Agreement Alignment As-constructed Document Asset Inspector Beneficiary Lot Clearance to Work Permit Construction Engineer Contract Contractor Contract Price Corporation Design Drawings Design Engineer Design Standard Developer Distribution Main The formal legal document between the developer and the Corporation with respect to delivering fit for purpose assets that are acceptable to the Corporation. The line on which the pipes are laid and measured from the adjacent cadastral boundary. The document on which details of the constructed works are recorded and submitted to the Corporation. An officer of the Corporation responsible for assessing and or inspecting the works. Lots that acquire water supply or wastewater service availability, as a result of an extension of the reticulation, without the owner having paid, or been deemed to have paid, Headworks Contributions. A permitting procedure to authorise a contractor to conduct work on, or near a designated asset, other than where the personnel carrying out the work are being directly supervised by a person who has operational control of the asset. The engineer or engineering firm appointed by the developer to manage the construction of the works. The agreement between the developer and the contractor for the execution of the works. A person or organisation bound to execute the works under a contract. The amount payable to the contractor for the execution of a contract. The body corporate known as the Water Corporation, Western Australia. The drawings prepared by the design engineer, showing the proposed works. The engineer or engineering firm appointed by a developer to prepare design drawings and documents for submission to the Corporation. The Corporation’s design standard relevant to the works being undertaken. The person or organisation that has made an agreement with the Corporation to provide drainage, water or wastewater infrastructure. A water supply pipeline to which standard services are not normally connected. 11 Easement Engineer Final Acceptance Certificate Final Inspection Clearance Final Inspection Headworks Inspection Land Development Agreement Main Drain Main Sewer Precalculated Cadastral Plan Prerequisites To Works Pre-handover inspection Region Regional Office Reticulation Shall Should Specification Standard Drawings Takeover Technical Manual Warranty Period A defined area of land over which the Corporation has a right to enter for purposes defined by agreement or statute and subject to any conditions/restrictions implied therein. Such purposes can include for example, access, construction, maintenance and repair. A person qualified to be a chartered professional engineer, and who has appropriate engineering experience. A certificate issued by the Corporation at the end of the warranty period provided conditions have been met. A letter issued by the asset inspector confirming that the Works are acceptable. The inspection by the asset inspector, with the construction engineer in attendance, to assess acceptance of the assets. The infrastructure that provides water, wastewater and drainage services, excluding reticulation and private plumbing e.g. dams, wastewater treatment plants, main drains, etc. Any activity undertaken to assess the condition of the works. The formal legal document between the developer and Corporation with respect to fulfilling any WAPC conditions imposed on a subdivision application. An existing or proposed drain within the metropolitan area that is controlled by the Corporation. A wastewater collection sewer to which connections are not normally made. A surveyor’s precalculated cadastral plan of the proposed subdivision development. The procedure necessary to address the Corporation’s statutory requirements under the Water Services Act 2012 for general and major works as set out in the External Approvals Manual. The inspection conducted by the construction engineer prior to booking a final inspection. An area of the state designated as a region of the Corporation. The principal office of that region. The pipelines that connect private works to major works, and are constructed to provide a water supply or wastewater service to a property. A mandatory requirement. A requirement to be adopted unless circumstances justify a variation. The document containing the technical clauses to be read in conjunction with the design drawings for the works. Registered Corporation drawings. When the Corporation assumes ownership of the works and the warranty commences. The Corporation’s technical manual relevant to the works being undertaken. The period commencing from takeover. 12 2 Introduction 2.1 Scope This manual explains the administrative requirements for the provision of works that are covered by an agreement, so they can be incorporated into the Corporation’s schemes and taken over by the Corporation. It covers all aspects from the preliminary investigation stage to final acceptance of the works by the Corporation. Works consist of the following categories: Water and wastewater reticulation involving land subdivision Water and wastewater reticulation extensions not involving land subdivision Relocating existing headworks assets to facilitate land development* Urban main drainage works* Works covered by a MSWA are not included in the scope of this Manual. * Any works performed on headworks assets (category c & d) will be assessed to determine the scope of works and level of risk to the asset. Works that are deemed significant may be required to follow additional procedures that are not contained in this manual. Prior to lodging a submission, you should contact us on 9420 2099 or email land.servicing@watercorporation.com.au to discuss your options. 2.2 Technical and Other Manuals The Corporation has design standards and manuals that outline how each type of asset should be constructed. These are shown in the below table. Asset Type/Process Water reticulation Wastewater mains Vacuum Sewerage Water distribution mains Urban main drainage Drawing Standards Prerequisites to Works To protect pipelines from AC interference Design Standard or Manual Design Standard 63 Design Standard 50 and the Water Services Association of Australia Sewerage Code. Design Standard 53 Design Standard 60 Design Standard 66 Design Standard 80 External Approvals Manual Earth Potential Rise Manual To enquire about our design standards please email: idb.standardsenquiries@watercorporation.com.au Where this manual conflicts with another manual or standard, this manual takes precedence. 2.3 Roles and Responsibilities 2.3.1 Developer The developer is the proponent of the works. The developer is responsible for: • Carrying out the requirements of this manual for the provision of the works, • Appointing a design engineer, a construction engineer and a contractor to carry out the works in accordance with this manual, the technical manuals and design standards. 2.3.2 Design Engineer The design engineer is responsible for designing the works required to service land. The design engineer must be a registered holder of all of the Corporation’s manuals and design standards. 13 2.3.3 Construction Engineer The construction engineer is responsible for managing and arranging the construction of the works in accordance with relevant manuals, codes and design standards, and to ensure the works are acceptable to the Corporation. 2.4 Notification The Developer should inform the Corporation in writing of the details of all the parties engaged to deliver the works. The Corporation reserves the right to accept or reject nominations based on its assessment of the capability, capacity and past performance of the nominated party. 3 Fees The following fees are payable by the developer to the Corporation. Fees will remain valid for the life of the submission. 3.1 Water Reticulation Planning Fee – is a payment for water supply reticulation planning which is based on 3.75 per cent of the Corporation’s estimate of the construction of the cost of the works. 3.2 Connecting to existing works Fee – is a payment for the Corporation to connect new works to existing live works. This fee is dependent on the type and size of connection and is required to be paid prior to the connection being performed. Refer to 3.3, 3.4 and 3.5 for further information. 3.3 Potable and Non-potable Water Reticulation Connections 3.3.1 Metropolitan Perth Region Standard connection fees may be provided as part of an agreement. Where the works contain non-standard or complex connections, the land servicing consultant may direct the design/construction engineer to obtain a quote from ‘Reimbursements’, Perth region, prior to the start-up meeting. 3.3.2 Non-metropolitan Regions As part of the works design, the land servicing consultant may give direction to the design/construction engineer as to how the connections may be arranged. Connection requirements shall be discussed at the start-up meeting with the asset inspector. The fees and actions involved in connecting works in non-metropolitan regions may vary depending on the location and circumstances. 3.4 Wastewater Reticulation Connections 3.4.1 Metropolitan Perth Region All connection fees shall be paid prior to the connection. The design/construction engineer shall obtain a quote from ‘Reimbursements’. The isolation and connection requirements shall be discussed with the asset inspector at the start-up meeting. 3.4.2 Non-metropolitan Regions As part of the works design, the land servicing consultant may give direction to the design/construction engineer as to how the connections may be arranged. Connection requirements shall be discussed at the start-up meeting with the asset inspector. The fees and actions involved in connecting works in non-metropolitan regions may vary depending on the location and circumstances. 14 3.5 Headworks Connections When connecting to headworks infrastructure there is the potential for negative impact on many of the Corporation’s end customers. Options such as tankering and limited shutdown periods must be considered as part of the works design to minimise any disruption. The design engineer shall discuss these requirements with the land servicing consultant in the early stages of the design to determine any specific requirements. 15 4 Corporation Contacts The Corporation contacts are shown below: 4.1 Submissions Contact State-wide Manager Land Servicing Subdivision Development Services Branch Works Water Corporation John Tonkin Water Centre 629 Newcastle Street, Leederville PO Box 100 LEEDERVILLE WA 6902 4.2 Inspections Contact Metropolitan Inspection Services Perth Region Perth Region Alliance 273 Bannister Road , Canning Vale PO Box 1525 CANNING VALE Distribution Centre 6970 Phone: 9420 2099 Phone: 9424 8462 Agricultural Region Regional Works Inspector Agricultural Region Water Corporation 263 Fitzgerald Street PO Box 265 Northam, WA, 6401 Phone: 9622 4814 Great Southern Region Regional Works Inspector Great Southern Region Water Corporation 215 Lower Stirling Terrace Albany, WA, 6331 Phone: 9842 4201 Fax: 9791 4079 Mid-West Region Regional Works Inspector Mid-West Region Water Corporation SGIO Building, Cathedral Avenue PO Box 43 Geraldton, WA, 6531 Phone: 9923 4906 Fax:: 9923 4966 North-West Region Regional Works Inspector North-West Region Water Corporation Welcome Road PO Box 84 Karratha, WA, 6714 Phone: 9186 8273 South-West Region Regional Works Inspector South-West Region Water Corporation PO Box 305 Bunbury, WA, 6231 Phone: 9791 0495 OR 9791 4079 Fax: 9622 4866 4.3 As-Constructed Contact All water and wastewater as-constructed drawings are to be submitted to: spatial.datacapture@watercorporation.com.au 16 4.4 State Map 17 4.5 Metropolitan Perth Region 18 5 Process 19 6 Planning Phase - Preliminary investigation To ensure that the concept and capacity of the proposed works are compatible with the Corporation’s overall planning requirements; the design engineer shall discuss the broad planning concepts of the design with a land servicing consultant. If a vacuum sewerage system is required or another alternative servicing arrangement is proposed, its planning must be acceptable to the Corporation. The requirements shall be discussed at an early stage in the planning of the works. Any requirements that will be imposed by other authorities on the operation of the works must be discussed and agreed to by the Corporation. 7 Planning Phase - Land requirements 7.1 All easements, reserves and land to be owned by the Corporation required for a project shall be shown on the design drawings. 7.2 Where easements or reserves are required and are outside the developer’s land holding: written in-principle agreement of the arrangements necessary to acquire the easements or reserves from the registered landowner is required. 8 8.1 Planning Phase - External approvals During the preliminary stages of designing any works, the design engineer shall take into account the requirements of the Corporation’s External Approval Manual. This includes the statutory ‘Prerequisites to Works’ notification requirements as per the Water Services Act 2012. 8.1.1 Particular attention and early liaison needs to take place where any works are adjacent to, within or crossing a reserve or asset that is controlled by Main Roads (WA), Public Transport Authority, Western Power or Telstra. 8.1.2 Prior to discussing proposed works with all affected parties, the design engineer should consider alternative options that reduce impacting any parties. The Corporation may provide comments on a design prior to formal or informal approvals being sought. 8.2 Prerequisites to Works Works are classified in Part 6 of the Water Services Act 2012 as either major, general or exempt. Reticulation works will be either general or exempt works depending on where they are located. The design engineer is responsible for determining the class of works and completing all prerequisites to works requirements in accordance with the Act. If the proposed works are classed as general, all relevant documentation, E.G. notice plan/letters etc. shall be included in the initial design submission. 8.3 Objections The design engineer should make every reasonable effort to resolve any objections. Any objections that cannot be resolved shall be referred to the land servicing consultant. 8.4 Completion required Confirmation that all requirements of the prerequisites to works process is required before the Corporation accepts final design drawings. This includes full resolution of all objections. 20 9 Design Phase - Design of works 9.1 Design requirements Design drawings for the reticulation works shall be submitted by a design engineer. 9.2 Drawing certification Each drawing and document that is submitted shall be signed by the design engineer who has the authority to act on the behalf of the design engineer making the submission. 9.3 Design Responsibilities The design engineer is responsible for ensuring the design of the works complies with the Corporation’s manuals and design standards. Acceptance by the Corporation of a submission shall not relieve the design engineer of this responsibility or the responsibility for any discrepancies, errors or omissions in the submission or for the adequacy of the design. 9.4 Drafting Standards The drafting for all submissions shall be in accordance with Australian Standard 1100, Part 101. Drawings shall be suitable for microfilming. 9.5 Pre-Calculated Cadastral Plan A digital copy of the precalculated cadastral plan will expedite the incorporation of information into the Corporation’s spatial database. The digital file shall be in MGA94 coordinates. The plan shall be clear and legible and only include information that is relevant. Unnecessary information that should not be included is typically: • Road kerb lines, • Trees, • Power/light poles, • Stormwater pipes and gullies, • Other utilities services e.g. electricity, gas, Telstra etc. 9.6 Standard Drawings Example standard drawings are available in the design standards. 10 Design Phase - Initial Submission 10.1 Purpose of the initial submission The purpose of the initial submission is to enable the Corporation to: • Ensure that the planned works conform with the overall planning, • Provide administrative details that are required to be shown on the final design drawing; and, • Ensure that the prerequisites to works process has begun, if required. * An initial submission will not be accepted where the relevant documents are not supplied, or are incomplete. 10.2 Requirements of the initial submission The Initial submission shall contain: • The Initial Submission Design Checklist for the relevant asset type. • A digital copy (PDF) of the design drawings, including site plan information. • The prerequisites to works documentation if the works are classed as general. • A letter from the owner of any land other than the developer’s, agreeing in principle, to granting any easements or reserves required for the works. 21 • A list of any existing lots that becomes serviceable as a result of the works. The list shall show the property address, owners name and mailing address and a description of the land use (e.g. residence, industrial etc.) 10.3 Drainage In addition to the documents required in section 10.2, submissions for drainage works shall also contain: • One copy of the local water management strategy for the area. • One copy of the urban water management plan for the area. • A letter that includes: • A reference to the Department of Water’s drainage strategy for the area. • A statement setting out the developer’s understanding of who is responsible for funding of any proposed future connection of a catchment to any part of the drain covered by this submission. • A letter from the appropriate waterway/wetland catchment management agency (e.g. Swan River Trust) detailing its comments on the drainage proposal where appropriate. • One copy of a soils investigation report where an investigation is required. • One copy of the summary of the proposed pollutant removal processes and mechanisms within the drainage system including sizing calculations, where appropriate. • Two copies of the technical specification. The technical specification shall consist of the technical clauses covering the work, or a statement shall be included in the covering letter confirming that the specification is the same as one previously submitted. 10.4 Vacuum Sewerage systems In addition to the points contained in section 10.2, any vacuum sewerage system submissions will also require: • A statement from a supplier of an approved vacuum valve, as listed in the DS 36 Product Atlas stating that the supplier has received the system design prepared by an approved designer. The statement must guarantee the hydraulics of the system and confirm that the guarantee is transferable to the benefit of the Corporation. The review must be carried out by a suitably experienced engineer and the engineer must be explicitly identified in the statement referred to above. Current approved vacuum valves are: • Air vac (contact Watercon) and, • Flovac (contact Flovac Vacuum Sewerage Systems) *The initial submission should be emailed to dsbdesign.submission@watercorporation.com.au 11 Design Phase - Design standard variation requests 11.1 The Corporation’s design standards are developed to ensure fit for purpose assets that achieve their economic design life with minimal operating and maintenance costs are delivered. 11.2 Occasionally a design may not meet the requirements of the design standard or proposes an alternative solution. Where this occurs, the design engineer shall complete the request for design standard variation form (refer to Appendix 4) and include it with the initial submission documents. 22 11.3 When proposing a variation, the design engineer shall include at a minimum, the following: • Details of the reasons/circumstances for the variation. • An assessment of the impacts and benefits for the Corporation and the developer. • Details of options considered to negate the variation. 11.4 The following reasons for a variation will not generally be accepted by the Corporation: • Inadequate site investigation that results in obstacles or constraints of a non-latent nature. • Seasonal impacts that will resolve themselves over time. • Where the design engineer’s assessment will cause a significant impact to the Corporation’s fundamental objectives. • Where the request’s fundamental objective relates to financial benefit for the developer. • Where the request is lacking sufficient information to be able to assess. 12 Design Phase - Review of the Initial Submission 12.1 The submission will be checked for conformity with the Corporation’s overall planning requirements. The submission will be: • Accepted - if the submission is acceptable to the Corporation, it will be stamped as accepted, the Corporation reference numbers and one copy of the drawings will be returned to the design engineer. The design engineer will then be in a position to proceed with the final submission; or • Accepted with amendments – if the submission is acceptable to the Corporation with minor amendments, it will be stamped as accepted conditional to the amendments being made, or • Rejected – if the initial submission is not acceptable, the Corporation will reject the submission and request that the design be reconsidered. 13 Design Phase - Objections to the Corporation’s requirements Any objections to planning or design requirements by the Corporation shall be made in writing to the land servicing consultant. The objection shall state the reasons and efforts made to resolve any issues. Any unresolved objections between the design engineer and the land servicing consultant shall be referred to the Manager, Development Services. 14 Design Phase - Final Submission The Final Submission shall consist of: • The final submission cover sheet (refer appendix 5). • An agreement in writing that formalises the arrangements for the Corporation to acquire any easements or reserves required as a result of the works. • Confirmation that the prerequisites to works process has been completed, including resolving any objections. • Six (6) A1 hard copies of the design drawings which shall incorporate the comments and details provided by the Corporation. • Two (2) A1 hard copies of the design data plan (for wastewater submissions only). Where already known: • The name of the construction engineer and contact details • The name and contact details of the contractor and any sub-contractors. • The contract price for the works. • The proposed date of commencement of work. 23 Where contract details are not known at the time of submitting the final submission these details are to be provided prior to booking a Start Up Meeting. *Final submissions that are related to a subdivision application cannot be accepted prior to the application reaching conditional approval. 15 Design Phase - Acceptance of the Final Submission 15.1 The final design drawings will be signed by the Corporation to indicate that the submission is acceptable and one copy will be returned to the design engineer. 15.2 The final submission is valid for 12 months from the date of acceptance. If construction has not begun within this period, the submission will no longer be valid and a new submission will be required. 15.3 Acceptance of the design does not relieve the design engineer of any responsibilities for any discrepancies, errors, omissions or for the adequacy and conformance of the design with the relevant manuals and design standards. 15.4 16 Amended drawings When drawings are amended and resubmitted, they shall be distinguished from previous submissions by a new revision identifier. A brief description and date of the amendment shall be included in the title block. If the revised amendment alters the overall cost of the project, a Final Subdivision Cover Sheet must be included with the revised plans. Design Phase - Alterations to an Accepted Final Submission 16.1 Once a plan has been accepted and before construction has started, any alterations to the design shall be discussed with the land servicing consultant who will determine whether a revised submission is required. 17 Construction Phase – Start-up 17.1 Prior to the start of the works, the construction engineer shall arrange and attend a ‘start-up’ meeting with the asset inspector 17.2 Once the design engineer receives the Corporation’s acceptance of a final design and contract details have been provided, if not provided with the final submission (see clause 14), the construction engineer can book a Start Up Meeting by contacting the relevant Inspections Contact (see clause 4.2). 17.3 The Corporation requires a minimum of 5 business days’ notice to arrange a Start Up Meeting 17.4 The construction engineer shall ensure that a record of the meeting is made. This record shall detail any key information and agreements reached. 17.5 The following matters shall be addressed at the ‘start-up’ meeting: • Indicative dates for the start and completion of construction of works. • Method of isolating the new works from the existing works during construction. • Inspection plan, detailing which parts of the works (including testing) the asset inspector will inspect, when these inspections are proposed to take place and any requirements necessary to facilitate these inspections. • Nomination of additional staff that will access the site of the proposed works to carry out Inspections. 24 17.6 17.7 • Contact and reporting arrangements including signing of site inspection reports. • Arrangements for the protection of Water Corporation assets. • Arrangements for the connection of new work to existing infrastructure. • Milestone meetings at which joint attendance is required. • Arrangements for inspection and testing processes. • A copy of the meeting record shall be forwarded to the asset inspector within five days of the ‘start-up’ meeting occurring. Before construction begins the construction engineer shall ensure: • The inspector has authorised construction to start. • A Clearance to Works Permit has been obtained from the Corporation’s Customer Service Delivery group, where necessary. • The contractor employs personnel that are capable and accredited to perform the works. Refer to the relevant manual or design standard for details of the appropriate accreditation required. 17.8 Notice of Proposed Works Where property, other than that owned by the developer, will be affected by the proposed works, the construction engineer shall ensure that written notice has been given to the occupiers of such property at least 10 days prior to the start of works. 18 Construction Phase – Design Amendment (Alterations to an accepted final submission) 18.1 Prior to the start of the works, the construction engineer shall arrange and attend a ‘start-up’ meeting with the asset inspector 18.2 If construction has started, any requests for minor realignments of pipes, alterations to connections and relocation of access chambers and valves shall be discussed with the asset inspector. The asset inspector will provide guidance on these matters or may refer complex matters to be dealt with by the land servicing consultant 18.3 A copy of the meeting record shall be forwarded to the asset inspector within five days of the ‘start-up’ meeting occurring. 19 Construction Phase – Construction Requirements 19.1 During construction the construction engineer shall liaise with the asset inspector for any matters that arise. The construction engineer shall ensure: • If a change of contractor becomes necessary, the construction engineer notifies the Corporation of the new contractor’s name and contact information. • Any requirements by the Corporation regarding the contractor’s work are directed to the construction engineer and NOT to the contractor. • Work shall be carried out in accordance with the requirements of the relevant technical manual or design standard, relevant acts and by-laws and this manual. • The construction engineer shall ensure that the contractor is aware of, and agrees to comply with, the requirements of any authority in regard to the protection, diversion or relaying of any service affected by the works. • The construction engineer shall ensure that the contractor is conversant with any agreement with any authority such as the Department of Aboriginal Affairs or Department for Planning and Infrastructure into which the design engineer, the developer or the Corporation may have entered for the works. 25 • The construction engineer shall ensure that the contractor verifies by survey the location and level of the point of connection of the works to the existing system. 19.2 Protection of Corporation Assets 19.2.1 Corporation assets shall not be disturbed without the approval of the appropriate regional office on each and every occasion, OR excavation or construction work shall not be performed in close proximity to any existing Corporation asset until: • A joint inspection of the asset has been performed by the Corporation and construction engineer to ascertain the condition of the asset, and • The asset inspector has been given two working days’ notice of the intention to commence working. 19.2.2 The construction engineer ensures adequate measures are taken to protect the Corporation’s assets from damage during construction of the works . 19.2.3 If any damage occurs to existing assets, the construction engineer shall immediately notify the Corporation. The Corporation will assess the damage and advise what action is to be taken. This may include the developer being charged the costs to repair any damage. 19.3 Construction of Assets without All relevant approvals Where the Corporation becomes aware that construction has commenced and due process has not been followed, the following actions will result: 19.3.1 The Corporation will instruct that works cease immediately. Should a cease work instruction not be complied with the Corporation may decline to accept any further involvement in the works. 19.3.2 A third party certified assessment of the works already constructed will need to be provided, at the developers’ cost, for the Corporation’s review. 19.3.3 The Corporation reserves the rights to refuse and accept the choice of the third party assessor. 19.3.4 Where the third party assessment identifies non-compliance with the relevant standard, faults will need to be remedied where possible, or the works removed. 19.3.5 Only after points 18.3.1 – 18.3.4 have been resolved and the requirements of any manual have been met, will works be able to recommence. 19.3.6 The Corporation will not offer the availability of early clearance of subdivision conditions associated with these works. 19.3.7 The Corporation may at its discretion decline to accept the involvement of the engineering consultant in future Corporation funded projects. 19.3.8 The warranty (defects liability) period for the works will be increased to two years. 20 Construction Phase – Isolation of new works (wastewater only) 20.1 The purpose of isolating non-commissioned sewers from live sewers is to provide a safe working environment for construction, testing and inspection of the new work. Where the non-commissioned sewer system is not isolated from the live sewer, entry to and work within the new sewer system is subject to the provisions of Australian Standard AS.2865, ‘Safe working in a confined space’. 26 20.2 The construction engineer shall make the necessary arrangements for the new works to be isolated from the live sewer prior to the commencement of construction and ensure that the isolation is maintained until the final inspection clearance has been issued by the asset inspector. 20.3 The new works shall be either not connected (physical break) or shall be physically isolated from the live sewer. A physical break is the preferred method and should be used wherever practical. 20.4 Where a physical break is not practical, the construction engineer shall apply to the Corporation’s Building Services department to have the live sewer sealed off prior to construction and removed following the issue of the final inspection clearance of the works. 20.5 The Water Corporation will notify the construction engineer in writing when the line has been isolated (seal installed and ready for testing) and again when the isolation has been removed. 20.6 Where the live sewer has been plugged (150 or 225mm sewers), the construction engineer shall arrange for the plug to be tested to 50 kPa for one minute with no drop in pressure. The test shall be conducted on the ‘upstream’ side of the plug prior to any entry by Corporation staff. The test shall be logged in the construction engineer’s log of inspections and tests. 20.7 Where an isolation of a live sewer involves sealing with a plastic membrane and brickwork (sewers 300mm and above), it is the responsibility of the construction engineer to develop and administer a test plan over the period of isolation to ensure the integrity of the isolation. 21 Construction Phase – Inspection of works during construction 21.1 In general, inspections will not be undertaken by the Corporation during construction of the works; however the Corporation reserves the right to request an inspection at any time for the purposes of auditing compliance. 21.1.1 The construction engineer shall make provision for access by Corporation officers or its representatives to inspect the works during construction when requested. 21.1.2 The asset inspector (including additional staff) shall have access to the site at any time provided the construction engineer or contractor is on site. 21.1.3 Inspections by the Corporation do not in any way relieve the construction engineer of the responsibility for ensuring that construction of the works is in accordance with the design documents and that it complies with the requirements of the technical manual or design standard. 21.1.4 The construction engineer shall arrange for the provision of all personnel and equipment required for any scheduled inspection and testing. 21.2 Construction Engineer’s Log of Inspections and Tests 21.2.1 The construction engineer shall arrange and undertake inspection and testing of the works to ensure that the requirements of the technical manual or design standard are satisfied. The construction engineer shall maintain a log of all inspections and tests undertaken, which shall be presented to the Corporation, if requested. The log shall record the following information: • Inspections and/or tests witnessed by the construction engineer of the works, which were considered satisfactory. To this effect the construction engineer shall sign the 27 following statement on the construction engineer’s log: “I am satisfied that the above inspection and tests have been carried out.” • Inspections and / or tests witnessed by the construction engineer of the works, which were considered unsatisfactory. • Any remedial action undertaken to the works as a result of an unsatisfactory inspection prior to re-inspection. 21.2.2 A copy of the construction engineer’s inspection log and test results shall be submitted to the asset inspector prior to a final inspection being undertaken. The log shall include but not be limited to the date, time, item tested, type of test, result of test and the name of the witness. 21.3 Site Safety 21.3.1 Asset inspectors will comply with the contractor’s site safety procedures while on site. 21.3.2 Asset inspectors will not enter sites that they consider unsafe by Worksafe Standards. 21.3.3 Where safety issues relating to the inspection cannot be resolved between the construction engineer and the asset inspector they shall be referred to Worksafe for advice/resolution. 21.4 Pre-Handover Inspection and booking of a final inspection 21.4.1 At least two (2) weeks prior to a planned final inspection date the construction engineer shall contact the Corporation’s inspections contact and make a tentative booking for a final inspection. 21.4.2 The construction engineer shall then confirm and book a final inspection giving a minimum of 5 business days notice. 21.4.3 Prior to confirming a booking for a final inspection the construction engineer shall undertake a pre-handover inspection. 21.4.4 A pre-handover inspection checklist shall be completed by the construction engineer and provided to the asset inspector with all test logs at the time of confirming a final inspection date. 21.5 Final Inspection 21.5.1 When the works have been completed and the construction engineer has conducted a pre-handover inspection, the construction engineer shall arrange a final inspection with the asset inspector. .The asset inspector will inspect the works with the construction engineer in attendance. 21.5.2 Where the number and/or seriousness of non-conformances indicate that the prehandover inspection has been inadequate the asset inspector shall terminate the final inspection and require the construction engineer to carry out further inspection of the works before booking another final inspection. A fee may be charged to the developer where a pre-handover inspection is deemed to have been inadequate. 21.5.3 Where the works are deemed to be acceptable the asset inspector shall arrange for a final inspection clearance to be issued to the construction engineer. 28 22 Construction Phase – Connecting to existing assets 22.1 Connections or alterations required to the Corporation’s existing infrastructure as a result of new works shall be made by prior arrangement with the Corporation. All such work shall be at the developer’s expense. 22.2 The construction engineer shall make the necessary arrangements for the payment of fees for the connection of the new works to the existing assets. 22.3 When the works are deemed to be acceptable, the asset inspector shall initiate the connection of the works upon the request from the construction engineer. 22.4 Works will not be connected to existing assets until payment of all associated fees has been made and a final inspection clearance has been issued. 23 Takeover Phase – As-Constructed drawings 23.1 The as-constructed drawings shall be certified "as-constructed", signed and dated by the design engineer, the construction engineer and by the surveyor (who is eligible for membership of I.E.M.S.A. or I.S.A.) responsible for the survey. The as-constructed drawings shall be in accordance with the relevant technical manual, design standard or this manual. 23.2 The completed and signed as-constructed submission shall be submitted to the asconstructed submission contact. 23.3 All as-constructed plans shall clearly display the Planset number which shall have the bundle number revised to indicate that it is an as-constructed plan, as per DS 80. 23.4 One copy of the as-constructed submission shall be submitted except where specified below. 23.5 As-constructed Information for Water works The as-constructed information shall consist of: 23.5.1 The as-constructed plan in accordance with the typical information provided in Water Corporation Design Standard 60 or 63. 23.5.2 A precalculated cadastral plan for areas which are not sewered, in electronic form whenever possible and particularly for large areas; otherwise a hard copy for small subdivisions. 23.5.3 A copy of the final new works site inspection report. 23.6 As-constructed Information for Wastewater works 23.6.1 The as-constructed plan in accordance with the typical information provided at Appendix 9 of this manual. 23.6.2 All aspects of Section 6 of Design Standard 50 must be complied with, other than the as-constructed plan mentioned at 22.5.1. replacing all references to field notes. 23.6.3 A precalculated cadastral plan, in electronic form whenever possible and particularly for large areas; otherwise a hard copy for small subdivisions. 29 23.6.4 A copy of the final new works inspection report. 23.6.5 A contour plan if earthworks have been carried out that has changed a contour by 0.5 metre or more. 24 Takeover Phase – Takeover of the works 24.1 Requirements for takeover Subject to connection to the existing system being available, takeover is achieved when: 24.1.1 A final inspection has been completed and a final inspection clearance has been issued by the asset inspector. 24.1.2 The construction engineer has certified that the works have been constructed in accordance with the documents accepted by the Corporation and the requirements of the technical manual or design standard. . 24.1.3 The construction engineer has certified that restoration has been performed to the satisfaction of any affected property owner and authorities. 24.2 Date of Takeover The Corporation will notify the developer in writing that takeover has been achieved. The date the Corporation takes over the works will be the date that final inspection clearance has been issued 25 Takeover Phase – Warranty Period 25.1 The warranty period shall commence on the date of take-over. 25.2 The warranty period shall be for one year. 25.3 During the warranty period, the Corporation shall be responsible for operational maintenance of the Works. 25.4 Remedial repairs during warranty 25.4.1 During the warranty period the developer shall be responsible for ensuring that satisfactory remedial repairs arising from faulty design, workmanship or materials are carried out. The cost of any consequential damage and claims resulting from such defects shall be charged to the developer. 25.4.2 During the warranty period, the Corporation may, at its discretion carry out remedial repairs where the fault affects the service to customers and/or public safety. The Corporation will notify the developer of the work carried out as soon as practicable where the remedial repairs are attributable to the construction of the works. The cost of the remedial repairs shall be charged to the developer. 25.5 Remedial Repairs post Warranty 25.5.1 Where remedial works carried out by the Corporation are determined to be attributable to a design or construction error or omission the cost of the remedial works shall be charged to the developer. 25.5.2 Remedial works shall include, but not be limited to, the absence of infrastructure components (i.e. missing sewer junctions), incorrect installation (i.e. inadequate bedding 30 or compaction) and inadequate separation of any component of the works from other infrastructure (i.e. inappropriate separation distance between water and electricity assets). 26 Takeover Phase – Final Acceptance Certificate 26.1 Prior to the end of the warranty period the Corporation will assess whether there are any defects. If so, the asset inspector will notify the developer of the list of defects. Otherwise, the asset inspector will issue the developer with the Final Acceptance Certificate at the end of the warranty period. 26.2 Providing that any defects identified in Clause 27.1.4 have been rectified to the satisfaction of the Corporation, a final acceptance certificate shall be issued by the Corporation. 31 27 Appendix 1: Water Initial Design Checklist Name of Company Address Phone No Design Engineer WAPC (if applicable) email Qualified to design works YES NO 1 1.1 Planning Considerations The design complies with the current Water Corporation Planning. 2 2.1 2.2 2.3 2.4 External Approvals A strategy for the approval of other parties has been developed with reference to the External Approvals Manual. If Prerequisites to Works is required, include Notice Plans/Letters etc. Works have been identified as: EXEMPT GENERAL General works 2 copies of the Notice of proposal. Draft letters and list outlining parties to be notified Exempt works Statement attached outlining the justification for this classification. 3 3.1 3.2 3.3 3.4 3.5 3.6 3.7 Drawing Format Where the design covers more than one water supply zone, the zoning boundary is accurately shown The drafting is to the appropriate standard The drawings contain all of the relevant Water Corporation referencing (i.e. WAPC No ) Beneficiary lots have been identified and relevant details attached. All easements have been denoted. Drawings are WCX compliant , refer to DS 80 (headworks assets only) Drawings to have the following notation: Length and type of mains. Number of valves and hydrants 4 4.1 Design Criteria Without compromising the planning, the design meets the fundamental objectives of: a) minimising water main sizing, depth and length of water main b) efficient use of hydrants and valves (including air & scour valves for headworks assets) c) minimising bends & dead end mains d) minimising long services e) maximising dual services The valving considers shutdown requirements and the number of properties impacted. The design considers finished surface levels in relation to cover on mains. All water mains terminate at the extremity of the land served unless future extension does not need to be catered for. Connections to existing works have been appropriately designed. The design applies standard alignments OR non-standard alignments have been approved by both the Water Corporation and other service providers. The design considers the proposed construction technique and/or constraints. For designs proposing a variation to the Design Standard a formal request has been made to the Water Corporation for approval. 4.2 4.3 4.4 4.5 4.6 4.7 4.8 5 5.1 5.2 5.3 5.4 Influencing Factors The design engineer confirms that the design has made allowance for existing or proposed physical features of influence i.e. retaining walls, significant trees, other services, building etc. in established green field’s areas In the case of designs in existing established or green fields areas the design engineer confirms that the route has been “walked”. Where the design requires the approval of other parties (i.e.; DEC Clearing Permits, affected landowners, other service providers) a strategy to obtain these has been developed. A report is included for projects that relocate/divert headworks assets and includes: • Details of the proponent and justification for of the works (including alternative options) • Plan for the abandoned main • Plan for managing shutdowns for piece-ups I certify that this design has been reviewed and complies with Water Corporation requirements. ___/___ /____ Signature Date Print Name and Firm Complete this form and send to: dsbdesign.submission@watercorporation.com.au 32 28 Appendix 2: Wastewater Initial Design Checklist Name of Company Address Phone No Design Engineer WAPC (if applicable) 1 Planning Considerations 2 External Approvals 1.1 2.1 2.2 2.3 2.4 3 3.1 email Qualified to design works A strategy for the approval of other parties has been developed with reference to the External Approvals Manual. If Prerequisites to Works is required, include Notice Plans/Letters etc. Works have been identified as: EXEMPT GENERAL General works 2 copies of the Notice of proposal. Draft letters and list outlining parties to be notified Exempt works Statement attached outlining the justification for this classification Drawing Format The drafting is to the appropriate standard The drawings contain all of the relevant Water Corporation referencing (i.e. WAPC No ) 3.3 Beneficiary lots have been identified and relevant details attached. 3.4 All easements have been denoted. 3.5 Drawings are WCX compliant , refer to DS 80 (headworks assets only) 4 4.2 4.3 4.4 4.5 The design complies with the current Water Corporation Planning. 3.2 4.1 YES Design Criteria Without compromising the planning, the design meets the fundamental objectives of: a) minimising access chambers b) minimising sewer depths and lengths c) maximising the locating sewers in public land d) minimising bends, scour and air valves on pressure mains (headworks assets only) The most appropriate Access Chamber types and running traps have been shown where required. All lots served have sewer junctions at a location and depth suitable to correctly serve the lot/s and boundary traps where required. All fill requirements are denoted (i.e. if design based on contours appropriate tolerances have been applied) All sewer grades are within acceptable tolerances. 4.8 The design applies standard alignments OR non-standard alignments have been approved by both the Water Corporation and other service providers. Connections to existing works have been appropriately designed (i.e.: flow to flow where called for) and isolation from live works requirements have been considered and designed appropriately. The design considers the proposed construction technique and/or constraints. 4.9 Water Corporation approval has been sought for any design standard variations. 4.6 4.7 5 5.1 5.2 5.3 5.4 Influencing Factors The design makes appropriate allowance for existing or proposed physical features of influence i.e. retaining walls, trees, other services, building etc. In the case of designs in existing established areas the route has been “walked”. Where the design requires the approval of other parties (i.e.; DEC Clearing Permits, affected landowners, other service providers) a strategy to obtain these has been developed. A report is included for projects that relocate/divert headworks assets and includes: • Details of the proponent and justification for of the works (including alternative options) • Plan for the abandoned main • Plan for managing shutdowns for piece-ups I certify that this design has been reviewed and complies with Water Corporation requirements. Signature ___/___ /____ Date Print Name and Firm Complete this form and send to: dsbdesign.submission@watercorporation.com.au NO 33 29 Appendix 3: Drainage Submission Checklist Location_____________________________________________________________ Note: this checklist is to be used to undertake a review of an Initial Design Submission by the Design Engineer prior to lodging the submission with the Water Corporation. The certification at the bottom of this checklist is to be signed by an engineer qualified and authorised to do so. Content of submission Two copies of design drawings enclosed External Approval Requirements General works- 2 copies of the Notice of Proposal, Draft letters and a list outlining the parties to be notified Exempt Works- Statement attached outlining the justification for this classification Drawing format The drafting is to the appropriate scale i.e. plans are clear and the legend is in accordance with relevant design standard. Drawings are WCX Compliant (DS80) All easements have been denoted Note: if the submission is assessed as not meeting the above criteria, the submission will be returned and no further processing or assessment of the submission will occur. Design Criteria The design shall be prepared in accordance with the requirements of the Water Corporations Urban Main Drainage Standard (DS66). The Checklist below outlines some of the key considerations the Design Engineer shall address in preparing the design. • The design has been prepared in accordance with the Water Corporation’s Hydrological and Hydraulic principals and the design has the relevant Hydraulic Grade Lines shown on it. • Water Sensitive Urban Design has been considered - and input from the Department of Water has been sought. Water Sensitive Urban Design objectives and integration with public open space can result in maintenance requirements that exceed the level of maintenance that the Water Corporation is able to provide. Where this occurs agreements need to be reached about maintenance responsibilities and ownership before a Design Submission is made. • Where required, all structures and access chambers are adequately detailed on the design drawings. • Where required, the design drawings incorporate and detail adequate fencing and edge protection for the drain. • Where required, the design drawings incorporate and details all service and occupational crossings. • Access to the drain for maintenance and operations purposes has been considered in the preparation of the design. • All safety issues have been addressed and the design includes a “Safety in Design Report” for the construction and operation of the drain. • Land matters relating to the works (e.g. where Water Corporation land or reserve is to be used as public open space) have been discussed with the Water Corporation and an agreed strategy is in place to manage: • Easement requirements • Maintenance Agreements • Licence and Indemnity Agreements • For designs proposing a variation to the Design Standard a formal request has been made to the Water Corporation for approval, as per Section 11 of the Developers Manual Signature(Design Engineer) __________________________ Date ________________ Your name and company name _____________________________________________ Email____________________________________________________________________ 34 30 Appendix 4: Request for Variation to Design Standard Location and/or stage name: ___________WAPC No (if applicable) _____________ Note: This checklist is to be used where a design standard variation request is required. This checklist is to be completed as part of the review of an Initial Design Submission by the Design Engineer prior to lodging the submission with the Water Corporation. The certification at the bottom of this request is to be signed by an engineer qualified and authorised to do so. Considerations to be made before a design standard variation is submitted Design standard variations that are requested for any of the following reasons will generally not be considered by the Water Corporation: Substandard site investigation activities resulting in obstacles or constraints of a non-latent nature Seasonal impacts that will resolve themselves with time Where the Design Engineers assessment is for significant impact to the Corporations fundamental objectives Where the request relates purely to the financial benefit of the proponent Content of Request a) A design drawing detailing variations enclosed. b) Completion of all fields in this form. Below please state the reasons/circumstances prompting this request Below please provide an assessment of the impacts and the benefits for both the Water Corporation and your client Alternative options considered a) Have any alternative options been considered to negate the need for design standard variation? Y/N b) Please provide details below I Certify that the above information provided is true and correct. Signature (Design Engineer) ______________________________ Date ____________________ Your name and company name _____________________________________________________ Accepted/Declined by Water Corporation Plan No ___________ File Reference___________________ Signature ______________________________ Date ____________________ Name: ______________________________ Position: ___________________________________________ 35 31 Appendix 5: Final Submission Cover Sheet COVER SHEET FOR ACCEPTANCE OF FINAL ENGINEERING SUBMISSION Important information for Design Engineers: The following specific details are required to be sent to the Water Corporation with the Final Submission of a design. • Please make sure that all information listed is included so that the Final Submission can be processed without delay. • Please verify the following information by signing on the bottom of the page. • Please include the signed original of this form with the Final Submission when forwarding to Water Corporation • Please note that the Water Corporation will not accept a final submission until advice of WAPC conditional approval of the subdivision has been received. GENERAL WAPC number: Stage Name/Number Service type (water / wastewater) INITIAL DESIGN REVIEW I confirm that this Submission conforms with the Initial Submission returned by the Water Corporation including required amendments OR If any variations have been made, a description and reason for each variation is attached Where a variation to a Design Standard has been approved the relevant approval is attached DETAILS OF CONSTRUCTION ENGINEER Name of Company: Address: Phone: Email Project Manager: Qualified to carry out works Fax DETAILS OF CONTRACT Name of Contractor: Address: Phone: Email Project Manager: Contract Price (Excl GST): $ Qualified to carry out works Fax: Pre-calculated Plans Latest subdivision digital precal forwarded – Format to be DWG or DXF in MGA94 co-ords (For smaller 2-5 lot subdivisions a Landgate Deposited Plan (DP) provided). Email pre-calculated plans to spatial.datacapture@watercorporation.com.au EXTERNAL APPROVALS A statement is attached listing the authorities from which project approval has been obtained, including environmental clearances and copies of any conditions that have been imposed by those authorities on the construction or operation of the works. There are no unresolved objections arising from the Prerequisites to Works process for the proposed works. VERIFICATION OF CONTENT Signature (Design Engineer) ___________________ Date _________________ 36 32 Appendix 6: Clearance to Works Guidelines ASSETS LIKELY TO BE AFFECTED INCLUDE: • Water mains (especially RC, AC, CI etc) • Pressure mains • Main Sewers • Piped Water Corporation Main Drains • Pump stations (pipework, pits, electrical cables, alarm lines etc) REQUIREMENT FOR A PERMIT IS ESSENTIALLY A PRODUCT OF: • • • • Type of asset Proximity and depth of excavation in relation to an existing asset Soil conditions Construction method CLEARANCE TO WORK PERMITS WILL BE REQUIRED WHERE: 1. Open excavating parallel to or crossing an existing water main, pressure main, Main Sewer or piped drain at an acute angle (less than 45°) where the integrity of the asset may be impacted by the Works. (e.g. within 2 metres of an asset and greater than 1 metre below the invert of an asset). Note: there may be instances where this citeria is not appropriate and the desiginer must therefore consider the type of asset, proximity of the sewer, difference in invert levels and soil conditions. If any doubt exists the specific circumstances should be referred to the Region for assessment. 2. Crossing under an existing asset where the clearance between the assets will be minimal (say <500mm). 3. Any crossing under a water main with a diameter greater than 200mm. 4. Excavating in or around pump station sites as buried assets and services are not necessarily in accordance with that shown on 'as-constructed' plans. 5. Any connection to an existing asset. 6. All Works in the vicinity of RC mains should be referred to the Region for special consideration. Most failures have occurred as a result of the loss of support to RC or AC water mains and are preventable if a "cut and cap" is arranged at the appropriate time. IF ANY DOUBT EXISTS THE DESIGNER / CONTRACTOR SHOULD REFER THE SPECIFIC CIRCUMSTANCES FOR ASSESSMENT BY THE REGION. 37 33 Appendix 7: Pre-handover Checklist Plan Set No: _____________ WAPC Ref No._____________ Location and/or Stage Name: _____________________________ This Checklist is to be used by the Construction Engineer to undertake Pre-Handover Inspection prior to booking a Final Inspection with the Water Corporation’s Asset Inspector. The Certification at the bottom of this Checklist is to be signed by an Engineer qualified and authorised to do so. 1 Test and Inspection Logs / Certificates 1.1 Test and Inspection Logs have been maintained, checked and signed for (delete if not applicable): a) Pressure testing b) Ovality testing c) Lines sighted d) Spark testing e) Product specification (date of manufacture, supplier / brand) f) Bedding, jointing and installation of pipe work checked g) Anchor blocks in place and to specification h) Valve and hydrant supports are in place and to specification i) Denso tape and paste has been applied where required 1.2 Compaction Certificates have been maintained, checked and signed. 1.3 All testing equipment used has been recorded by Identification No. and current Calibration certification is provided. 2 2.1 Water Supply Physical Inspection Items The following items have been physically inspected and verified: a) All water services are in place , correctly positioned, protected and to specification b) Denso tape and paste has been applied where required c) All valves and hydrants are in place and to specification d) All marker posts are in position and to specification 3 3.1 Wastewater Physical Inspection Items The following items have been physically inspected and verified: a) Isolation is in place b) Access chambers (complete, clear , correct covers) c) Maintenance Shafts (complete, clear, correct covers) d) Property connection markers are in place 4 Copies of all test logs and relevant certification are attached I certify that the assets constructed meet all Water Corporation requirements. Signature Print Name and Firm __ /___ /____ Date 38 34 Appendix 8: As-Constructed Plan Checklist Planset No: _____________ WAPC Ref No._____________ Location and/or Stage Name: _____________________________ This checklist is to be used to undertake a review of water and wastewater As –Constructed plans by the Construction Engineer prior to lodging the submissions with the Water Corporation. The Certification at the bottom of this checklist is to be signed by an Engineer qualified and authorised to do so. Note: Water and Wastewater As-constructed Requirements 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Wastewater All text and as-constructed information clear and legible at A3: Otherwise clear and legible A1 to be submitted. Latest subdivision digital precal forwarded – Format to be DWG or DXF in MGA94 co-ords (For smaller 2-5 lot subdivisions a Landgate Deposited Plan (DP) provided). Location sketches provided for all access chambers, inspection openings and inspection shafts. All sewer gradients within acceptable tolerances. All served lots have sewer junctions shown and where applicable denoted as 150mm. Submission has been signed by Construction Engineer and Surveyor. Final Inspection date included on plan. As-constructed information has been checked for completeness and correctness as per statement below. A copy of the final new works inspection report. Plan bundle number is clear and has been revised. Total number of Access Chambers for submission(to be itemised on drawing) Total number of Lots Being Served for submission (to be itemised on drawing) Total number of Maintenance Shafts for submission (to be itemised on drawing) Total Length of Sewers (listed by nominal diameter) for submission (to be itemised on drawing) Water All text and as-constructed information clear and legible at A3: Otherwise clear and legible A1 to be submitted. 2 Latest subdivision digital precal forwarded – Format to be DWG or DXF in MGA94 co-ords (For smaller 2-5 lot subdivisions a Landgate Deposited Plan (DP) provided). 3 All prelaid services shown on plan are spatially correct. 4 Submission has been signed by Construction Engineer and Surveyor. 5 Final take over date included on plan. 6 As-constructed information has been checked for completeness and correctness as per statement below. 7 A copy of the final new works inspection report. 8 Plan bundle number is clear and has been revised. 9 Total number of Hydrants for submission(to be itemised on drawing) 10 Total number of Valves for submission(to be itemised on drawing) 11 Total number of Lots Being Served for submission (to be itemised on drawing) 12 Total Length of Mains (listed by nominal diameter) for submission (to be itemised on drawing) Notes: 1. Any items not addressed will result in the submission being rejected. 2. This form is to be completed and forwarded with the as-constructed submission. 1 I certify that the assets constructed meet all Water Corporation requirements. Signature _______________________ Date __________________ Your name and company name _______________________________________________ Complete this form and send to: asset.registration@watercorporation.com.au Appendix 9: Example of wastewater reticulation as constructed plan Note: All details must be clear and legible 39 Developers’ Manual ISBN 1 74043 930 9 August 2016