ADDENDUM NO. 2 STANDBY GENERATOR AND ELEVATED BUS DUCT REPLACEMENT PROJECT PROJECT NO. ss1018, BID NO. 2528 NOVEMBER 6, 2012 NOTICE TO ALL PLAN HOLDERS/BIDDERS This addendum and its attachments shall become a part of the plans and specifications and shall apply to the bid proposals for the above named project. The bidder(s) shall notify all affected subcontractors, material suppliers, and others to incorporate necessary cost updates, to the bid proposal and the work changes affected by this Addendum. In the event of conflict between plans and specifications and this addendum, the addendum shall take precedence. Any modifications necessary to incorporate the revisions shall be included in the appropriate bid prices. The bid documents are hereby corrected, modified, and/or amended in the following manner: Date: November 6, 2012 ADDENDUM NO. 2 STANDBY GENERATOR AND ELEVATED BUS DUCT REPLACEMENT PROJECT PROJECT NO. ss1018, BID NO. 2528 ALL CONTRACT DOCUMENTS, VOLUMES 1 THROUGH 3 1. The process area number for Standby Generator Building No. 1 shall be 41. All uses of area number 43 in process area designations, equipment and electrical tags, sheet numbers, section and detail references, and other locations shall be changed to 41. This change will be updated in the Conformed Documents. TIMELINE FOR TECHNICAL QUESTIONS 2. The Due date for technical questions for this project is Tuesday, November 13, 2012 at Noon. Responses will be available by Friday, November 16 at noon. CONTRACT DOCUMENTS, VOLUME 1 OF 3, SPECIFICATIONS DIVISIONS 0 THROUGH 14 3. TABLE OF CONTENTS Division 1: Add the following text: “01210 Allowances” after Section 01201 Payment Procedures and before Section 01292 Schedule of Values. Division 2: Delete the following text: “02312 Controlled Low Strength Material”. 4. DOCUMENT 00410, BID FORM, ARTICLE 2, BIDDER’S ACKNOWLEDGEMENT: Remove the entire Document 00410 Bid Form and replace with the Bid Form in Attachment A. 5. DOCUMENT 00800, SUPPLEMENTARY PROVISIONS ARTICLE 3, PROPOSAL REQUIREMENTS AND CONDITIONS, Remove “TUESDAY, NOVEMBER 6, 2012” replace with “TUESDAY, NOVEMBER 20, 2012”. ARTICLE 4, REQUIRED LISTING OF PROPOSED SUB-CONTRACTORS, SECTION C.I Remove “60 calendar days” and replace with “90 calendar days”. ARTICLE 31, MODIFICATIONS TO THE GENERAL PROVISIONS Add the following text at the end of the section: “c) Record Drawings, Section V, Paragraph 11 i. Add the following text: Page 2 Date: November 6, 2012 ADDENDUM NO. 2 STANDBY GENERATOR AND ELEVATED BUS DUCT REPLACEMENT PROJECT PROJECT NO. ss1018, BID NO. 2528 “Monthly submittal of Record Drawings shall be a condition precedent to monthly progress payments. Contractor shall submit up-to-date record drawings to Construction Manager at the end of each and every month. The Construction Manager shall review the record drawings. Record drawings will be used to verify and document the progress of the Work. Work not included in the record drawings will not be included for payment in those progress payment requests. d) Award of Contract, Section III, Paragraph 1 i. Remove “sixty (60) calendar days” and replace with “ninety (90) calendar days”. ” 6. SECTION 01140, WORK RESTRICTIONS Section 1.02.B: Remove “to treat the quality of raw wastewater” and replace with “to treat the quantity of raw wastewater”. Section 1.03.A: Add the following text at the end of the section: “10. Provide 7 days written notice and 24-hour final written notice to the OWNER and ENGINEER for review and acceptance prior to all shut downs.” 7. SECTION 01201, PAYMENT PROCEDURES: Section 1.03.A: Delete the following text: “Generate Application for Payment by downloading cost data from the Progress Schedule to a spreadsheet type format. Identify each activity on the Progress Schedule that has a cost associated with it, the cost of each activity, the estimated Percent Complete for each activity, and the Value of Work Completed for both the payment period and job to date.” Section 1.04: Add the following text at the end of the Section: “F. Monthly submittal of Record Drawings shall be a condition precedent to monthly progress payments. Contractor shall submit up-to-date record drawings to Construction Manager at the end of each and every month. The Construction Manager shall review the record drawings. Record drawings will be used to verify and document the progress of the Work. Work not included in the record drawings will not be included for payment in progress payment requests. Refer to Document 00700 and Section 01770 for record drawing requirements.” Section 1.06.A.9: Remove “Obtaining all required permits, licenses, and fees.” replace with “Obtaining all required permits, licenses, and fees except fire alarm and protection permits.” 8. SECTION 01210, ALLOWANCES Page 3 Date: November 6, 2012 ADDENDUM NO. 2 STANDBY GENERATOR AND ELEVATED BUS DUCT REPLACEMENT PROJECT PROJECT NO. ss1018, BID NO. 2528 Add Section 01210 Allowances to the Bidding Documents. Refer to Attachment B for Section 01210. 9. SECTION 01292, SCHEDULE OF VALUES Section 1.03.A: Remove “Submit preliminary schedule of values.” and replace with “Submit preliminary schedule of values with Baseline Schedule no more than 45 calendar days after Notice of Award.” 10. SECTION 01294, APPLICATIONS FOR PAYMENT Section 1.02.E: Remove “ENGINEER” and replace with “CONSTRUCTION MANAGER” in two (all) locations. 11. SECTION 01324, PROGRESS SCHEDULES AND REPORTS Section 1.02: Add the following text at the end of the Section: “D. References: Submit written reference of 3 project OWNERS who have personal experience with this scheduler on previous projects. Identify name, address, telephone number, project name, and cost.” Section 1.02.B.2: Remove “5 years verifiable experience in preparation of complex construction schedules for projects of similar value, size, and complexity.” and replace with “3 years verifiable experience in preparation of complex, cost-loaded construction schedules for projects of similar value, size, and complexity.” Section 1.08.A: Remove “submit the Baseline Schedule” and replace with “submit the Baseline Schedule and Schedule of Values”. Section 1.11.B: Remove “5 days” and replace with “10 days”. 12. SECTION 01354, HAZARDOUS MATERIAL PROCEDURES Section 1.02.F: Remove “OSHA” and replace with “Cal-OSHA”. 13. SECTION 01756, TESTING, TRAINING, AND FACILITY START-UP Section 1.03.A: Remove “3 weeks” and replace with “60 calendar days” 14. SECTION 01770, CLOSEOUT PROCEDURES Section 1.07.A: Add the following text at the end of the Section: Page 4 Date: November 6, 2012 ADDENDUM NO. 2 STANDBY GENERATOR AND ELEVATED BUS DUCT REPLACEMENT PROJECT PROJECT NO. ss1018, BID NO. 2528 “11. Certificate of Delivery of Spare Parts, Materials & Equipment.” 15. SECTION 02300, EARTHWORK Section 1.01.B.3.d: Delete the following text: “d. Section 02312 – Controlled Low Strength Material (CLSM).” Update the subsequent paragraph listing from “e.” and “f.” to “d.” and “e.”, respectively. Section 2.01.C: Delete the following text: “C. Controlled low strength material: As specified in Section 02312.” Update the subsequent paragraph listing from “D.” to “C.”. 16. SECTION 02312, CONTROLLED LOW STRENGTH MATERIAL Delete the entire Section 02312 from the contract documents. 17. SECTION 02318, TRENCHING Section 1.01.B.3.e: Delete the following text: “e. Section 02312 – Controlled Low Strength Material (CLSM).” Update the subsequent paragraph listing from “f.” to “e.”. Section 2.01.B: Delete the following text: “B. Controlled low-strength material: As specified in Section 02312.” 18. SECTION 02467, DRILLED CONCRETE PIERS Section 1.01.C: Delete the following text: “C. Payment Procedures: 1. Basis of payment: 1) Base lump sum bid price for pier work on the number and lengths of piers indicated on the Drawings. a) This price shall include all costs in connection with the Work, including pier material, installation, reinforcing, concrete, pier cutoff, and other related items for a complete installation.” 19. SECTION 13212, APPURTENANCES ABOVEGROUND FUEL STORAGE TANKS Section 2.03.I: Remove “specifications 13410” and replace with “specification 17950”. Section 2.03: Add the following text at the end of the section: Page 5 AND Date: November 6, 2012 ADDENDUM NO. 2 STANDBY GENERATOR AND ELEVATED BUS DUCT REPLACEMENT PROJECT PROJECT NO. ss1018, BID NO. 2528 “J. Provide a reset push button that clears all faults and allows resetting of the tank level monitoring system after an alarm condition.” Section 2.05.B: Delete the following text: “Do not use flexible connectors external to the piping containment chamber.” CONTRACT DOCUMENTS, VOLUME 2 OF 3, SPECIFICATIONS DIVISIONS 15 THROUGH 17 20. TABLE OF CONTENTS Division 1: Add the following text: “ 01210 Allowances”. Add after Section 01201 Payment Procedures and before Section 01292 Schedule of Values. Division 2: Delete the following text “02312 Controlled Low Strength Material”. 21. SECTION 15075, MECHANICAL IDENTIFICATION Section Title: Replace “MECHANICAL IDENTIFICATION” with “EQUIPMENT IDENTIFICATION” 22. SECTION 15082, PIPING INSULATION Section 3.03: Under “Service Temp. °F”, remove “Note 5” and replace with “Note 4”. 23. SECTION 15820, DUCTWORK ACCESSORIES Section 1.02.C: Delete the following text: “C. Uniform Building Code (UBC).” Update the subsequent paragraph listing from “D.” to “C.”. 24. SECTION 15830, FANS Section 1.04.D.1.a: Delete the following text “as specified in Section 15936”. Section 1.04.D.1.c: Delete the following text: “if a fire alarm control panel is part of project design.” Section 1.04.D.1.d: Delete the following text: “When no electrical design for smoke control system is indicated, CONTRACTOR shall provide design and installation of the smoke control system.” Page 6 Date: November 6, 2012 ADDENDUM NO. 2 STANDBY GENERATOR AND ELEVATED BUS DUCT REPLACEMENT PROJECT PROJECT NO. ss1018, BID NO. 2528 25. SECTION 15956, PIPING SYSTEMS TESTING Section 1.03.G: Remove “Dispose of testing water off-site in accordance with requirements of federal, state, county, and city regulations governing disposal of wastes in the location of the Project and disposal site.” and replace with “Testing water may be disposed of on-site. Coordinate time, location, amount, and flow rate of disposal with plant staff.” Section 3.05.E.1.b: Remove “trust restraints” and replace with “thrust restraints”. 26. SECTION 16232, SINGLE DIESEL FUELED ENGINE GENERATOR ABOVE 200 KW Section 2.05.C: Add the following text at the end of the section: “6. OWNER and/or ENGINEER shall witness factory acceptance test. a. Verify that all systems functions as required before the formal witnessed test. b. The CONTRACTOR shall bear costs associated with travel for this test including, but not limited to: lodging and meals to witness the test. CONTRACTOR shall pay for travel expenses for air and/or ground transportation for up to three (3) OWNER’s representatives traveling from either the Oakland or San Francisco International Airport to the test site. c. CONTRACTOR shall pay for travel and lodging expenses required for witnessing of any re-testing or delayed testing. d. Costs associated with accommodation of the witness testing at the testing facility shall be paid for by the CONTRACTOR.” 27. SECTION 16430, LOW VOLTAGE SWITCHGEAR Section 2.06.A.1.a: Remove “The test may be observed by the ENGINEER and the OWNER” and replace with “a. Verify that all systems functions as required before the formal witnessed test. b. Tests shall be observed by the OWNER or ENGINEER, or both. c. The CONTRACTOR shall bear costs associated with travel for this test including, but not limited to: lodging and meals to witness the test. CONTRACTOR shall pay for travel expenses for air and/or ground transportation for up to three (3) OWNER’s representatives traveling from either the Oakland or San Francisco International Airport to the test site. d. CONTRACTOR shall pay for travel and lodging expenses required for witnessing of any re-testing or delayed testing. e. Costs associated with accommodation of the witness testing at the testing facility shall be paid for by the CONTRACTOR. f. Tests shall include the Automatic Transfer Control System specified in Section 16433.” CONTRACT DOCUMENTS, VOLUME 3 OF 3, DRAWINGS Page 7 Date: November 6, 2012 ADDENDUM NO. 2 STANDBY GENERATOR AND ELEVATED BUS DUCT REPLACEMENT PROJECT PROJECT NO. ss1018, BID NO. 2528 28. DRAWING 00-G-05, SITE PLAN Refer to Attachment C for modified Drawing 00-G-05. 29. DRAWING 00-TP-02, TYPICAL DETAILS PIPING Refer to Attachment D for modified Detail P412/Typ. 30. DRAWING 00-TS-04, TYPICAL DETAILS STRUCTURAL Detail S416, Sheet 2 of 3: Remove “180° STD ANCHOR HOOK. HOOK SHOWN ROTATED 90° OUT OF POSITION FOR CLARITY. PLACE HOOK IN PLAN OF WALL.” and replace with “180° STD ANCHOR HOOK. HOOK SHOWN ROTATED 90° OUT OF POSITION FOR CLARITY. PLACE HOOK IN PLANE OF WALL.” Detail S438, Sheet 2 of 2: Remove “MEMBRANE ROOFING” and replace with “COATED FOAM ROOFING”. 31. DRAWING 01-D-03, ELEVATED BUS DUCT SECTIONS, DETAIL, AND PHOTOS Key Note 1: Remove “REPLACE WITH NEW GRADE DH HEX NUTS, TAPPED AFTER HOT-DIPPED ZINC COATING, AFTER RECOATING COLUMNS.” and replace with “REPLACE WITH NEW GRADE DH HEX NUTS, TAPPED HOT-DIPPED ZINC COATING, AND 1 OVERSIZED WASHER EACH AFTER RECOATING COLUMNS.” 32. DRAWING 43-D-01, STANDBY GENERATOR BUILDING NO. 1 PLAN AND SECTION Add Key Note 13 “ELECTRICAL DUCT BANK LOCATION IS APPROXIMATE. FIELD VERIFY LOCATION, ELEVATION, AND SIZE PRIOR TO STARTING WORK.” Key note shall point to the existing 24” electrical duct bank not marked for demolition. 33. DRAWING 43-D-02, STANDBY GENERATOR BUILDING NO. 1 PLAN Key Note 17: Remove “RELOCATE, RE-ANCHOR, AND RECONNECT” and replace with “REMOVE FUEL FROM TANK, RELOCATE, RE-ANCHOR, AND RECONNECT”. Add Key Note 21 “ELECTRICAL DUCT BANK LOCATION IS APPROXIMATE. FIELD VERIFY LOCATION, ELEVATION, AND SIZE PRIOR TO STARTING WORK.” Key note shall point to the existing 24” electrical duct bank not marked for demolition. Page 8 Date: November 6, 2012 ADDENDUM NO. 2 STANDBY GENERATOR AND ELEVATED BUS DUCT REPLACEMENT PROJECT PROJECT NO. ss1018, BID NO. 2528 34. DRAWING 43-S-01, STANDBY GENERATOR BUILDING NO. 1 FOUNDATION PLAN AND SECTIONS General Note 2: Remove “SECTIONS 08320 AND 08710.” and replace with “SECTIONS 08110 AND 08332.” Add General Note 7 “UTILITY PENETRATIONS OF GRADE BEAMS ARE NOT ALLOWED.” “Add Key Note 16 “ELECTRICAL DUCT BANK LOCATION IS APPROXIMATE. FIELD VERIFY LOCATION, ELEVATION, AND SIZE PRIOR TO STARTING WORK.” Key note shall point to the existing duct bank running north/south between column lines 2 and 3. 35. DRAWING 43-S-02, STANDBY GENERATOR BUILDING NO. 1 ROOF FRAMING PLAN, SECTION, AND DETAIL Roof Framing Note 5: Remove “WELD DECK SEAMS WITH 1/2” LONG TOP SEAM WELDS @ 12” OC.” and replace with “WELD DECK SEAMS WITH 1-1/2” LONG TOP SEAM WELDS @ 12” OC.” 36. DRAWING 43-M-01, SCHEMATIC STANDBY GENERATOR NO. 1 FUEL SYSTEM Add an existing leak detector between the supply and return pipe flanges to 43-TNK-001. 37. DRAWING 43-M-02, STANDBY GENERATOR NO. 1 PLAN, SECTION AND SCHEMATIC Add Key Note 16: “PROVIDE A MINIMUM 12” LONG 316 SST BRAIDED HOSE FLEX CONNECTOR CAPABLE OF PROVIDING 1” DIFFERENTIAL MOVEMENT. INSTALL FLEX CONNECTOR MIN 12” ABOVE GRADE. PROVIDE 1-1/2” SST BALL VALVE WITH QUARTER TURN OPERATOR FOR SHUT OFF. INSTALL BALL VALVE BELOW FLEX CONNECTOR.” Key note 16 shall point to the 1-1/2” 1W line that enters the generator room on the east side of the building. Add Key Note 17: “CONTRACTOR SHALL COMPLETELY FILL BOTH FUEL TANKS WITH NEW DIESEL FUEL. REUSE OF FUEL REMOVED FROM EXISTING FUEL TANK IS NOT ALLOWED.” Key note 17 shall point to 43-TNK-001 and 43-TNK-002. 38. DRAWING 00-E-03, SCHEDULES Page 9 Date: November 6, 2012 ADDENDUM NO. 2 STANDBY GENERATOR AND ELEVATED BUS DUCT REPLACEMENT PROJECT PROJECT NO. ss1018, BID NO. 2528 Luminaire Schedule, Item F: Delete the following text: “UL LISTED FOR WET LOCATIONS” Luminaire Schedule, Item W: Delete the following text: “UL LISTED FOR WET LOCATIONS” 39. DRAWING 00-E-06, CONTROL CONNECTION DIAGRAM DEMOLITION AND TEMPORARY CONNECTIONS Key Note 7: Add the following text at the end of the note: “TEST CABLE IN ACCORDANCE WITH SECTION 16950 TO ESTABLISH CONDITION OF EXISTING CABLES PRIOR TO PULLING BACK THROUGH CONDUIT.” Key Note 8: Add the following text at the end of the note: “TEST CABLE IN ACCORDANCE WITH SECTION 16950 TO ESTABLISH CONDITION OF EXISTING CABLES PRIOR TO PULLING BACK THROUGH CONDUIT.” Key Note 9: Add the following text at the end of the note: “TEST CABLE IN ACCORDANCE WITH SECTION 16950 TO ESTABLISH CONDITION OF EXISTING CABLES PRIOR TO PULLING BACK THROUGH CONDUIT.” Key Note 10: Add the following text at the end of the note: “TEST CABLE IN ACCORDANCE WITH SECTION 16950 TO ESTABLISH CONDITION OF EXISTING CABLES PRIOR TO PULLING BACK THROUGH CONDUIT.” 40. DRAWING 25-E-01, BLOWER BUILDING NO. 1 CABLE BUS ROUTING PLAN Key Note 3: Remove “TERMINATION BOX” and replace with “TAP BOX”. 41. DRAWING 43-E-01, STANDBY GENERATOR NO. 1 POWER AND CONTROL PLAN – 1 Refer to Attachment E, modified Drawing 43-E-01. 42. DRAWING 43-E-02, STANDBY GENERATOR NO. 1 POWER AND CONTROL PLAN – 2 Refer to Attachment F, modified Drawing 43-E-02. Page 10 Date: November 6, 2012 ADDENDUM NO. 2 STANDBY GENERATOR AND ELEVATED BUS DUCT REPLACEMENT PROJECT PROJECT NO. ss1018, BID NO. 2528 43. DRAWING 43-E-03, STANDBY GENERATOR BUILDING NO. 1 LIGHTING AND RECEPTACLE PLAN General Note 3: Remove “UNLESS OTHERWISE NOTED, LIGHT SWITCHES AND RECEPTACLES SHALL BE RECESSED WITHIN THE WALLS AND LIGHTING AND RECEPTACLE CONDUITS SHALL BE EMBEDDED IN THE WALLS AND CEILING WHERE POSSIBLE.” and replace with “UNLESS OTHERWISE NOTED, LIGHT SWITCHES AND RECEPTACLES SHALL BE SURFACE MOUNTED ON WALLS AND LIGHTING AND RECEPTACLE CONDUITS SHALL BE IN THE WALLS AND CEILING WHERE POSSIBLE Add Key Note 2 “MOUNT PHOTOCELL 16’ AFF.” Key note shall point to the photocell approximately centered on the exterior face of the north wall of the building. Change the north west welding receptacle circuit label from “DP-43-10/12/14” to “DP-438/10/12”. 44. DRAWING 43-N-01, STANDBY GENERATOR NO. 1 MONITORING Refer to Attachment G, modified drawing 43-N-01. WE HEREBY ACKNOWLEDGE ADDENDUM NO. 2 AND HAVE REFLECTED THESE CHANGES IN OUR PROPOSAL. _______________________________________ Signature of Bidder and Date Sincerely, Sam Bautista, P.E. Project Manager Page 11 DOCUMENT 00410 BID FORM PROJECT IDENTIFICATION: City of South San Francisco Standby Generator and Elevated Bus Duct Replacement Project Bid Number 2528 _________________________________________________________________________ _________________________________________________________________________ THIS BID IS SUBMITTED BY: _______________________________________________________________________________ (Bidder) _______________________________________________________________________________ (Bidder Address) _______________________________________________________________________________ THIS BID IS SUBMITTED TO: City of South San Francisco 400 Grand Avenue South San Francisco, CA 94080 ARTICLE 1 - BID RECIPIENT 1.01 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents within the specified time and for the price indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents. ARTICLE 2 - BIDDER’S ACKNOWLEDGMENT 2.01 Bidder accepts all of the terms and conditions of the Invitation to Bid and Instructions to Bidders, including without limitation those dealing with the disposition of Bid security. The Bid will remain subject to acceptance for 90 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner. ARTICLE 3 - BIDDER’S REPRESENTATIONS 3.01 In submitting this Bid, Bidder represents that: Bidder has examined and carefully studied the Bidding Documents, the other related data identified in the Bidding Documents, and the following Addenda, receipt of which is hereby acknowledged. November 2012 00410-1 pw://Carollo/Documents/Client/CA/South SF/8376A10/Specifications/Bp3/00410 (Addendum 2) 8376A10 ADDENDA No. _____________ No. _____________ No. _____________ No. _____________ No. _____________ No. _____________ Dated ________________ Dated ________________ Dated ________________ Dated ________________ Dated ________________ Dated ________________ Bidder has visited the site and become familiar with and satisfied itself as to the general, local, and site conditions that may affect cost, progress, and performance of the Work. Bidder is familiar with and has satisfied itself as to all Federal, state, and local Laws and Regulations and Permits that may affect cost, progress, and performance of the Work. Bidder has carefully studied all: (1) reports of explorations and tests of subsurface conditions at or contiguous to the Site and all drawings of physical conditions in or relating to existing surface or subsurface structures at or contiguous to the Site (except Underground Facilities) which have been identified in the Supplementary Provisions and which are described in the Supplementary Provisions as containing reliable “technical data,” and (2) reports and drawings of a Hazardous Environmental Condition, if any, which have been identified in the Supplementary Provisions and which are described in the Supplementary Provisions as containing reliable “technical data.” Bidder has carefully studied (or assumes responsibility for having done so) all additional or supplementary examinations, investigations, explorations, tests, studies and data concerning conditions (surface, subsurface and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or performance of the Work or which relate to any aspect of the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, including applying the specific means, methods, techniques, sequences, and procedures of construction expressly required by the Bidding Documents to be employed by Bidder, and safety precautions and programs incident thereto. Bidder does not consider that any further examinations, investigations, explorations, tests, studies, or data are necessary for the determination of this Bid for performance of the Work at the price(s) bid and within the times and in accordance with the other terms and conditions of the Bidding Documents. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and the written resolution thereof by Engineer is acceptable to Bidder. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for the performance of the Work for which this Bid is submitted. In accordance with Section 1861, California Labor Code, the Bidder states the following as its certification: "I am aware of the provisions of Section 3700 of the California Labor Code which require every employer to be insured against liability for workers' compensation or to undertake November 2012 00410-2 pw://Carollo/Documents/Client/CA/South SF/8376A10/Specifications/Bp3/00410 (Addendum 2) 8376A10 self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the Work." ARTICLE 4 - BIDDER’S CERTIFICATION 4.01 Bidder further represents that This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any agreement or rules of any group, association, organization or corporation; Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham bid; Bidder has not solicited or induced any individual or entity to refrain from bidding; Bidder has not sought by collusion to obtain for itself any advantage over any other Bidder or over Owner; and Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this paragraph 4.01.E: 1. “corrupt practice” means the offering, giving, receiving, or soliciting of any thing of value likely to influence the action of a public official in the bidding process; 2. “fraudulent practice” means an intentional misrepresentation of facts made (a) to influence the bidding process to the Owner’s detriment, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and competitive bidding process; 3. “collusive practice” means a scheme or arrangement between two or more Bidders to establish bid prices at artificial, non-competitive levels; and 4. “coercive practice” means harming or threatening to harm persons or their property. ARTICLE 5 - BASIS OF BID Bidder will complete the Work in accordance with the Contract Documents for the Lump Sum Bid Price of: BID FORM Base Bid Item Description Lump Sum Amount 1 Completion of all Work associated with the Contract Documents excluding all work listed on other bid items in table. $____________ November 2012 00410-3 pw://Carollo/Documents/Client/CA/South SF/8376A10/Specifications/Bp3/00410 (Addendum 2) (in figures) 8376A10 2 Drilled concrete piers, specified in Section 02467 $____________ (in figures) 3 4 5 6 Sheeting, shoring, and bracing, or equivalent method for protection of life an limb in trenches and open excavations Preparation and submittal of a written geotechnical report as specified in Section 02260, including field investigations, soil sampling, laboratory testing, and interpretation of the data by a register geotechnical engineer in the State of California for the purpose of shoring design, dewatering and other temporary facilities. Insurance against the risk of tidal wave or earthquake in excess of 3.5 on the Richter scale, deemed an act of God pursuant to California Public Contract Code §7105, to indemnify Owner and Engineer for damage to the Work in an amount of at least 50 percent of Base Bid Items 1 through 4. Lump sum allowance of $75,000 for OWNER’s use on change orders in accordance with Section 01210. $ _____________ (in figures) $ ___________ (in figures) $ ___________ (in figures) $ 75,000______ (in figures) TOTAL LUMP SUM BID PRICE (BID ITEMS 1-6) $ ___________ $_____________________________________ ______________________________________ (in words) (in figures) ARTICLE 6 - TIME OF COMPLETION 6.01 Bidder agrees that the Work will be substantially completed, and, completed and ready for final payment in accordance with Section IX, Article 6 of the General Provisions on or before the dates or within the number of calendar days indicated in the Supplementary Provisions. 6.02 Bidder accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within the times specified above, which shall be stated in the Form of Agreement and modified by the Supplementary Provisions. ARTICLE 7 - ATTACHMENTS TO THIS BID 7.01 The following documents are attached to and made a condition of this Bid: November 2012 00410-4 pw://Carollo/Documents/Client/CA/South SF/8376A10/Specifications/Bp3/00410 (Addendum 2) 8376A10 Bid Form (Document 00410); Required Bid security in the form of cash, a certified or bank check, or a Bid Bond issued by a surety meeting the requirements of Section II, Article 5 of the General Provisions; List of Subcontractors and other individuals and entities required to be identified in the Bid (Document 00434); List of Equipment Manufacturers, (00436); Construction Equipment List (Document 00438); Non-Collusion Affidavit (Document 00456), and; Certification of Drug-Free Workplace Requirements (Document 00458) ARTICLE 8 - DEFINED TERMS 8.01 The terms used in this Bid with initial capital letters or all capital letters have the meanings indicated in the Instructions to Bidders, the General Provisions, and the Supplementary Provisions. ARTICLE 9 - BID SUBMITTAL SUBMITTED on _________________________, 2012 State Contractor License Number _________________________. (If applicable) If Bidder is: An Individual Name (typed or printed): By: (Individual's signature) Doing business as: Business address: Phone Number: ( ) FAX Number: ( ) A Partnership Partnership Name: By: (Signature of general partner -- attach evidence of authority to sign) Name (typed or printed): Business address: Phone Number: ( ) November 2012 FAX Number: ( ) 00410-5 pw://Carollo/Documents/Client/CA/South SF/8376A10/Specifications/Bp3/00410 (Addendum 2) 8376A10 A Corporation Corporation Name: State of Incorporation: Type (General Business, Professional, Service, Limited Liability): By: (Signature -- attach evidence of authority to sign) Name (typed or printed): Title: Attest: (Signature of Corporate Secretary, Acting Secretary or other officer) Business address: Phone Number: ( ) FAX Number: ( ) Date of Qualification to do business is A Joint Venture Joint Venturer Name: By: (Signature of joint venture partner -- attach evidence of authority to sign) Name (typed or printed): Title: Business address: Phone Number: ( ) FAX Number: ( ) Joint Venturer Name: By: (Signature of joint venture partner -- attach evidence of authority to sign) Name (typed or printed): Title: Business address: Phone Number: ( ) FAX Number: ( ) Phone and FAX Number, and Address for receipt of official communications: November 2012 00410-6 pw://Carollo/Documents/Client/CA/South SF/8376A10/Specifications/Bp3/00410 (Addendum 2) 8376A10 (Each joint venturer must sign. The manner of signing for each individual, partnership, and corporation that is a party to the joint venture should be in the manner indicated above.) END OF DOCUMENT November 2012 00410-7 pw://Carollo/Documents/Client/CA/South SF/8376A10/Specifications/Bp3/00410 (Addendum 2) 8376A10 THIS PAGE LEFT INTENTIONALLY BLANK November 2012 00410-8 pw://Carollo/Documents/Client/CA/South SF/8376A10/Specifications/Bp3/00410 (Addendum 2) 8376A10 SECTION 01201 ALLOWANCES PART 1 1.01 1.02 GENERAL SUMMARY A. Section Includes: Cash Allowances. B. Related sections: 1. The Contract Documents are complementary; what is called for by one is as binding as if called for by all. 2. It is the CONTRACTOR’s responsibility for scheduling and coordinating the Work of subcontractors, suppliers, and other individuals or entities performing or furnishing any of CONTRACTOR’s Work. 3. The following Sections are related to the Work described in this Section. This list of Related Sections is provided for convenience only and is not intended to excuse or otherwise diminish the duty of the CONTRACTOR to see that the completed Work complies accurately with the Contract Documents. a. Document 00410 – Bid Form. ALLOWANCE AMOUNTS A. Include the following cash allowance amount in Contract Price: 1. $75,000 for change orders at OWNER’s option. 2. Refer to Document 00410 for inclusion in the Contract Price. B. CONTRACTOR’S cost for products, delivery, installation, labor, insurance, payroll, taxes, bonding, equipment rental, overhead, and profit will be included in change orders authorized by OWNER for expenditure of funds from this allowance. C. Funds will only be drawn from this cash allowance by change order. D. Funds not used will be deleted by change order at the end of the contract. PART 2 PRODUCTS Not Used. PART 3 EXECUTION Not Used. END OF SECTION November 2012 01201-1 pw://Carollo/Documents/Client/CA/South SF/8376A10/Specifications/Bp3/01210 (Addendum 2) 8376A10 THIS PAGE LEFT INTENTIONALLY BLANK November 2012 01201-2 pw://Carollo/Documents/Client/CA/South SF/8376A10/Specifications/Bp3/01210 (Addendum 2) 8376A10