Electricity Generation Costs October 2012 Introduction Electricity generation costs are a fundamental part of energy market analysis, and a good understanding of these costs is important when analysing and designing policy. DECC regularly updates estimates of the costs and technical specifications for different generation technologies used in its analysis. Cost data is broken down into detailed expenditure per MW or MWh for the lifetime of a plant, from planning costs right through construction and operating costs to eventual decommissioning costs. These detailed costs are used by DECC to calculate a ‘levelised cost’ for each technology. A ‘levelised cost’ is the average cost over the lifetime of the plant per MWh of electricity generated. These reflect the cost of building a generic plant for each technology, potential revenue streams are not considered1. For the purposes of this report data on the cost of electricity generation has been drawn from Parsons Brinkerhoff (2012) for non-renewables technologies and evidence underpinning the Renewables Obligation and Feed in Tariff scheme for renewable technologies. Based on this detailed cost data, this report presents selected ‘levelised costs of electricity generation’ estimates generated using DECC’s Levelised Cost Model. This report firstly details the methodology and assumptions used in these estimates and discusses some of the limitations of levelised costs estimates. The report then presents selected ‘levelised cost’ estimates generated using DECC’s Levelised Cost Model. The final section of this report also adds a brief explanation of how cost information is used in DECC modelling. It is important to note there is a large amount of uncertainty when estimating the future costs of electricity generation. The levelised costs in this report are not intended to provide any indication of potential future strike prices for the Feed-in Tariff with Contracts for Difference (CfD) being introduced as part of Electricity Market Reform. 1 With the exception of heat revenues for CHP technologies Electricity Generation Costs Explanatory Notes Methodology The levelised cost of electricity generation (LCOE) is defined as the ratio of the net present value of total capital and operating costs of a generic plant to the net present value of the net electricity generated by that plant over its operating life. For further information on how levelised costs are calculated and DECC’s Levelised Cost Model please refer to section 4.2 Mott MacDonald (2010)2 or see Annex 2: Calculating Levelised Costs Data Sources and Assumptions The following data sources and assumptions have been used to calculate the levelised costs estimates presented in this report : • Non-Renewables Data: Underlying data on non-renewable technologies has been provided by Parsons Brinckerhoff. The underlying data and assumptions can be found in the PB (2012) report3. Renewables Data (over 5MW): Renewable technology estimates (for plant size over 5MW) reflect data and evidence underpinning the ‘Government response to the consultation on proposals for the levels of banded support under the Renewables Obligation for the period 2013-17 and the Renewables Obligation Order 2012’ for renewable technologies4. Please note that the estimates for renewables over 5MW have been inflated from 2010 to 2012 prices and heat revenues have been updated to reflect new fuel, carbon, and electricity prices when compared to those published as part of the Government Response to Renewables Obligation.5 Renewables Data (up to 5MW): Renewable technology estimates (for plant size up to 5MW) reflect data and evidence from PB (2012) published as part of the government response to Phase 2A and 2B comprehensive review of feed in tariffs67. • • 2 http://www.decc.gov.uk/en/content/cms/about/ec_social_res/analytic_projs/gen_costs/gen_costs.aspx 3 http://www.decc.gov.uk/en/content/cms/about/ec_social_res/analytic_projs/gen_costs/gen_costs.aspx 4 http://www.decc.gov.uk/assets/decc/11/consultation/ro-banding/5936-renewables-obligation-consultation-thegovernment.pdf This is referred to as the ‘Government Response to the RO’ throughout this report. 5 Please note that the data used to produce these levelised costs is consistent with the data underpinning the Renewables Obligation and figures presented in the Call for Evidence on Onshore Wind 6 http://www.decc.gov.uk/assets/decc/11/meeting-energy-demand/renewable-energy/5381-solar-pv-costupdate.pdf. 3 Electricity Generation Costs • • Fuel and Carbon Prices: DECC’s projected fossil fuel prices and Carbon Price Support. Deployment Scenarios: Future cost estimates are driven by a combination of assumptions of learning rates and global and UK deployment. Please see data sources referenced above for detailed information about deployment scenarios used. In general IEA Bluemap scenarios were the main source for global deployment. Four notable exceptions are; offshore wind, ACT, marine and estimates for renewables technologies under 5MW which are driven by technical potential for UK deployment8 All estimates are in 2012 real prices. This is in contrast to previously published estimates which were in 2010 real prices. Technology Notes This report will not discuss changes to individual technology estimates from previously published figures. For more information on individual changes please refer to the source material referenced in the Data Sources and Assumptions section above. Estimates for Carbon Capture and Storage (CCS) technologies and Nuclear are shown on a First of a Kind (‘FOAK’) and Nth of a Kind (‘NOAK’) basis. For these technologies with no commercial experience in the UK, FOAK was defined as the first plant within the UK, not including demonstration projects. For these technologies, FOAK costs assume experience has been gained from international and demonstration projects9. The period in which the cost moves from FOAK to NOAK is entirely dependent on the assumed learning rate and the assumed build rate. For nuclear we have assumed a move to NOAK for plants starting development in 2018 onwards. In practice this may occur later than we have assumed. The movement between FOAK and NOAK for CCS is even more uncertain and as such we have only used FOAK estimates in this report. Unless indicated all other estimates presented are NOAK. 7 http://www.decc.gov.uk/assets/decc/Consultations/fits-review/5900-update-of-nonpv-data-for-feed-in-tariff-.pdf 8 Please see Arup 2011 and PB 2012 for FiTs for more details. Please note that reductions in costs for offshore wind are based on technical potential for deployment, if these levels of deployment do not materialise cost reductions would be less pronounced.. 9 All estimates for Carbon Capture and Storage (CCS) presented in this document are intended to illustrate the cost of CCS for a commercial plant. In practice CCS would have be successfully demonstrated first. In order to avoid confusion, we have not included estimates for CCS in the near future to illustrate the need for an initial ‘demonstration’ project 4 Electricity Generation Costs Limitations of ‘Levelised Costs’ Levelised costs estimates are highly sensitive to the underlying data and assumptions used including those on capital costs, fuel and carbon costs, operating costs, operating profile, load factor and discount rates. Future levelised costs estimates are heavily driven by assumptions of global and UK deployment and assumed learning rates (and to a limited extent market effects10). This report captures some of these uncertainties through ranges presented around key estimates (for capex and fuel depending on the estimates). However, not all uncertainties are captured in these ranges and estimates should be viewed in this context. It is often more appropriate to consider a range of costs rather than point estimates. Given these uncertainties, the levelised cost estimates in this report are not intended to provide any indication of potential future strike prices for a particular technology or plant under the Feed-in Tariff with Contracts for Difference (CfD) being introduced as part of Electricity Market Reform. Strike prices will vary according to the length and design of the FiT CfD contract, technology, financing costs and in a few limited cases specific project characteristics. To the extent that project specific cost discovery processes are undertaken, these will form the starting point of any process of setting a strike price, rather than relying on levelised cost data. The levelised cost is a standardised measure of the net present value of lifetime costs divided by generation for a generic plant under each technology. This measure makes no assumptions about how particular generating stations would be financed, or the allocation of risk between parties. A CfD stabilises revenues for a particular generating station at a fixed price level known as the ‘strike price’ over a specified term, at a rate of return which reflects contract duration and design, financing costs, and risk allocation between parties. The levelised cost measure does not explicitly include the financing costs attached to new generating stations11. In most cases this report includes estimates using a standard 10% discount rate (in line with the ‘tradition’ used in reports produced by other organisations) across all technologies. These estimates may be viewed as neutral in terms of financing and risk when comparing across technologies. In practice financing costs of individual projects will vary depending on a range of factors including financing type, project developer, conditions in financial markets, maturity of technology, and risk and political factors. Annex 4 includes levelised cost estimates for renewable technologies using technology specific hurdle rates as was done in previous reports on renewables. Currently uncertainties around the cost of financing nuclear and CCS technologies means technology specific hurdle rate estimates are only provided for renewables in this report. 10 11 Market effects can include short term imbalanced between the demand and supply for component costs. While financing costs are included implicitly through the choice of discount rate used to produce the levelised cost this is an approximation. 5 Electricity Generation Costs Generation Cost Estimates This section outlines the main results of the analysis of the levelised cost of electricity generation. It focuses primarily on the main technologies likely to be deployed in the UK over the next decade and a half. The Levelised Cost of Electricity Generation is the discounted lifetime cost of ownership of using a generation asset converted into an equivalent unit of cost of generation in £/MWh. This is sometimes called a life cycle cost, which emphasises the cradle to grave aspect of the definition. The levelised cost estimates do not consider revenue streams available to generators (e.g. from sale of electricity or revenues from other sources), with the exception of heat revenues for CHP plant which are included so that the estimates reflect the cost of electricity generation only. A full set of estimates for renewable technologies not covered in the main report can be found in Annex 3. When looking at levelised cost estimates it is important to consider how they have been reported in terms of project timing and what sensitivities (if any) are included. These are discussed in more detail below. Timing Levelised cost estimates can be reported for different time points associated with a project including ‘Project Start’, ‘Financial Close’ and ‘Commissioning’. These are illustrated in Chart 1 below for an illustrative technology. A levelised cost estimate could be reported for ‘project start’, ‘financial close’ or ‘commissioning’ basis and represent the same information but be associated with different years. For example, using the illustrative timings below for ‘Technology 1’. If the levelised cost of this technology was £50/MWh for a project starting in 2012, this would be the same as saying £50/MWh for a project reaching financial close in 2017 (2012 plus the 5 year pre-development period), or £50/MWh for a project commissioning in 2023 (2017 plus the 6 year construction period). It is important to consider this when comparing across technologies. Pre-development and construction timings will vary by technology and therefore estimates reported for ‘project start’ or ‘financial close’ may not represent technologies commissioning in the same year as each other, and vice versa. Please see Annex 1 for key timings for selected technologies. 6 Electricity Generation Costs Chart 1: Illustrative Timings Project Start Financial Close Pre-development Commissioning Construction Operation De-Commissioning 0 10 20 years 30 40 50 Sensitivities Levelised costs estimates are highly sensitive to the underlying data and assumptions used including those on capital costs, fuel and carbon costs, operating costs, load factor and discount rates. As such it is often more appropriate to consider a range of cost estimates rather than point estimates. In order to illustrate some of these sensitivities, ranges of estimates have been shown. The key sensitivities explored are: High and Low capital costs (including pre-development) Unless specified all ‘high’ and ‘low’ estimates reported incorporate ‘high’ and ‘low’ capital costs including ‘high’ and ‘low’ pre-development costs. For non-renewable technologies this is a small change from previously reported estimates which used ‘central’ estimates for pre-development costs throughout. For non-renewables technologies ‘high’ and ‘low’ capital costs include the full range from PB (2012) i.e. both sitespecific variation and uncertainty over future costs12. High and Low fuel and capital costs In some cases, sensitivities which explore uncertainty over both fuel costs and capex costs are provided . These are shown in charts like Chart 2 below. In these cases the thick blocks represent ‘high/low’ sensitivities around capex (including pre-development) costs and the thin 12 For more details on ‘uncertainties’ please see PB (2012). Please note for nuclear technologies there was no basis to distinguish between variation and uncertainty. Non-renewable technologies also include an adjustment for market effects. These do not have a large impact on the cost estimates. 7 Electricity Generation Costs lines represent ‘high/low’ sensitivities around fuel prices on top of the uncertainty around capex (including pre-development) costs. Chart 2: Illustrative Sensitivities 120 100 £/MWh 80 60 40 20 0 Technology 1 Technology 2 Estimates Levelised cost estimates for three cases have been calculated using the DECC Levelised Cost Model. Case 1: projects starting in 2012, FOAK/ NOAK, 10% discount rate13 Case 1 shows the levelised costs for projects starting in 2012 with technologies which have not been deployed in the UK in their current form considered ‘first of a kind’ (FOAK), and those that have been deployed in the UK in their current form considered ‘Nth of a kind’ (NOAK). A 10% discount rate has been used in this case. Table 1 and Chart 3 show the detailed breakdown of the central levelised cost estimates for projects starting in 2012. Table 2 and Chart 4 show the sensitivities around capex and capex and fuel prices for projects starting in 2012. 13 Please note these estimates should be viewed in the context of the sensitivities and uncertainties highlighted in the text of this report. 8 Electricity Generation Costs Table 1: Levelised Cost Estimates for Projects Starting in 2012, 10% discount rate Central Levelised Costs, £/MWh Gas CCGT Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Costs Carbon Costs CO2 transport and storage Decomm and waste fund Heat Revenues TOTAL LEVELISED COST 0 9 3 0 48 19 80 Coal ASC with FGD 0 22 5 1 28 45 102 Central Levelised Costs, £/MWh Onshore >5 MW 14 E&W 2 79 19 3 104 Onshore >5 MW UK 2 71 17 3 93 Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Costs Carbon Costs CO2 transport and storage Decomm and waste fund Heat Revenues TOTAL LEVELISED COST Coal IGCC Nuclear FOAK Offshore R2 Offshore R3 1 26 7 1 30 56 122 5 55 11 3 5 2 81 4 81 32 1 118 6 91 37 134 Dedicate d biomass >50MW 1 38 14 4 65 122 Dedicate d biomass <50MW 2 52 16 5 41 117 Co-firing Conventi onal 5 5 1 81 92 Biomass Conversi on 2 11 13 1 83 110 Solar250 -5000kW 143 26 169 Table 2: Levelised Cost Estimates for Projects Starting in 2012, 10% discount rate, sensitivities Levelised Costs, £/MWh Central High Capex High Capex and High Fuel Low Capex and Low Fuel Low Capex Levelised Costs, £/MWh Central High Capex High Capex and High Fuel Low Capex and Low Fuel Low Capex 14 9 80 81 Coal ASC with FGD 102 105 100 118 140 93 - - - 58 90 108 72 - - - 78 99 118 73 104 117 145 Gas CCGT Onshore >5 MW E&W Onshore >5 MW UK 104 125 85 Offshore R2 Offshore R3 Solar2505000kW 81 92 118 134 134 156 169 203 Coal IGCC Nuclear FOAK 122 125 Dedicate d biomass <50MW 117 139 Co-firing Conventi onal 93 111 Dedicate d biomass >50MW 122 155 76 165 106 115 160 82 100 108 78 88 92 94 Estimates for onshore wind are shown using average load factors for UK and England and Wales ‘E&W’ Electricity Generation Costs Chart 3: Levelised Cost Estimates for Projects Starting in 2012, 10% discount rate Case 1: Project Start 2012, FOAK/NOAK, 10% discount rate 180 160 140 £/MWh 120 100 80 60 40 20 0 Pre-Development Costs Fuel Costs Capital Costs Carbon Costs Fixed O&M CO2 transport and storage costs Variable O&M Decomm and waste fund Chart 4: Levelised Cost Estimates for Projects Starting in 2012, 10% discount rate, sensitivities Case 1: Project start 2012, FOAK/NOAK, 10% discount rate, sensitivities 250 200 £/MWh 150 100 50 0 10 Electricity Generation Costs Case 2: projects starting in 2018, FOAK/ NOAK, 10% discount rate15 Case 2 shows the levelised costs for projects starting in 2018 assuming that NOAK has been reached for all technologies (with the exception of CCS). A 10% discount rate has been used in this case. Table 3 and Chart 5 show the detailed breakdown of the central levelised cost estimates for projects starting in 2018. Table 4 and Chart 6 show the sensitivities around capex and capex and fuel prices for projects starting in 2018. Table 3: Levelised Cost Estimates for Projects Starting in 2018, 10% discount rate Central Levelised Costs, £/MWh Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Costs Carbon Costs CO2 transport and storage Decomm and waste fund Heat Revenues TOTAL LEVELISED COST Central Levelised Costs, £/MWh Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Costs Carbon Costs CO2 transport and storage Decomm and waste fund Heat Revenues TOTAL LEVELISED COST 15 Gas CCGT 0 8 3 0 48 26 85 Nuclear NOAK 4 50 9 3 5 2 73 Gas CCGT with post comb. CCS FOAK 1 24 4 2 55 4 5 94 Dedicate d biomass >50MW 1 37 14 4 65 121 Gas CCGT retro post comb. CCS FOAK 1 19 4 2 56 4 5 89 Dedicate d biomass <50MW 2 51 16 5 41 115 Coal ASC with FGD 0 21 5 1 28 57 113 Coal ASC with post comb. CCS FOAK 1 47 10 3 37 9 11 116 Coal IGCC 1 26 7 1 30 66 131 Coal IGCC with CCS 1 43 9 2 36 9 11 111 Offshore R2 4 71 28 1 103 Offshore R3 6 76 31 113 Onshore >5 MW E&W 2 76 19 3 101 Onshore >5 MW UK 2 68 17 3 90 Please note these estimates should be viewed in the context of the sensitivities and uncertainties highlighted in the text of this report. 11 Electricity Generation Costs Table 3: (continued) Central Levelised Costs, £/MWh Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Costs Carbon Costs CO2 transport and storage Decomm and waste fund Heat Revenues TOTAL LEVELISED COST Cofiring Conventional 5 5 1 81 92 Biomass Conversion 2 10 13 1 83 109 Solar2505000kW 104 25 129 Table 4: Levelised Cost Estimates for Projects Starting in 2018, 10% discount rate, sensitivities Gas CCGT 85 86 Gas CCGT with post comb. CCS 94 104 Gas CCGT retro post comb. 16 CCS 89 98 106 127 64 84 Coal ASC with FGD 113 117 Coal ASC with post comb. CCS 116 136 Coal IGCC 131 135 Coal IGCC with CCS 111 141 121 131 155 151 160 63 86 59 82 100 109 88 101 116 127 75 87 Nuclear EPWR NOAK 73 85 Dedicated biomass >50MW 121 153 Dedicated biomass <50MW 115 137 Offshore R2 103 118 Offshore R3 113 132 Onshore >5 MW E&W 101 122 Onshore >5 MW UK 90 109 86 163 158 - - - - 64 65 105 114 80 99 91 98 83 74 Levelised Costs, £/MWh Central High Capex High Capex and High Fuel Low Capex and Low Fuel Low Capex Levelised Costs, £/MWh Central High Capex High Capex and High Fuel Low Capex and Low Fuel Low Capex Levelised Costs, £/MWh Central High Capex High Capex and High Fuel Low Capex and Low Fuel Low Capex 16 Cofiring Conventional 92 93 Solar2505000kW 129 154 107 - 78 88 112 Please note all retrofit estimates are for the retrofit of CCS only and do not include the cost of the base plant. 12 Electricity Generation Costs Chart 5: Levelised Cost Estimates for Projects Starting in 2018, 10% discount rate Case 2: Project Start 2018, FOAK/NOAK, 10% discount rate 140 120 £/MWh 100 80 60 40 20 Pre-Development Costs Fuel Costs Capital Costs Carbon Costs Fixed O&M CO2 transport and storage costs Solar250-5000kW Biomass Conversion Cofiring Conventional Onshore >5 MW UK Onshore >5 MW E&W Offshore R3 Offshore R2 Dedicated biomass <50MW Dedicated biomass >50MW Nuclear NOAK Coal - IGCC with CCS Coal - IGCC Coal - ASC with post comb. CCS Coal - ASC with FGD Gas - CCGT retro post comb. CCS Gas - CCGT with post comb. CCS Gas - CCGT 0 Variable O&M Decomm and waste fund Chart 6: Levelised Cost Estimates for Projects Starting in 2018, 10% discount rate, sensitivities Case 2: Project Start 2018, FOAK/NOAK, 10% discount rate, sensitivities 180 160 140 120 100 80 60 40 20 0 13 Electricity Generation Costs Case 3: Commissioning in 2013, 2015, 2020, 2025, 2030, FOAK/ NOAK, 10% discount rate17 In order to also show the costs of technologies commissioning in the same year Case 3 illustrates the levelised costs for projects commissioning in 2013, 2015, 2020, 2025 and 2030, using a 10% discount rate. Table 5: Projects Commissioning in 2013,2015, 2020, 2025 and 2030, FOAK/NOAK, 10%discount rate, capex sensitivity Levelised Costs, £/MWh Commissioning Year Gas - CCGT Gas - CCGT with post comb. CCS FOAK Gas - CCGT retro post comb. CCS FOAK Coal - ASC with FGD Coal - ASC with post comb. CCS Coal - IGCC NOAK Coal - IGCC with CCS FOAK Nuclear - EPWR FOAK/NOAK Dedicated biomass >50MW Dedicated biomass <50MW Offshore R2 18 Capex High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low 2013 77 76 75 2015 79 78 77 2020 84 82 81 93 90 88 97 94 91 107 104 101 108 106 103 121 117 114 156 123 116 140 118 101 159 140 124 96 85 77 154 122 115 138 116 100 134 118 104 157 124 117 141 119 102 174 153 135 2025 88 87 85 104 94 86 97 89 82 117 113 109 136 116 101 131 127 123 109 111 88 91 79 71 153 121 114 137 115 99 120 105 93 2030 91 89 87 105 95 86 100 90 83 121 117 113 137 116 101 136 132 128 111 111 87 85 73 65 152 120 114 136 115 99 110 96 85 17 Please note these estimates should be viewed in the context of the sensitivities and uncertainties highlighted in the text of this report. 18 We have assumed that Nuclear switches from FOAK to NOAK for projects commissioning in 2029 onwards. 14 Electricity Generation Costs Table 5: (continued) Levelised Costs, £/MWh Commissioning Year Offshore R3 Onshore >5 MW E&W Onshore >5 MW UK Cofiring Conventional Biomass Conversion Solar250-5000kW Capex High Central Low High Central Low High Central Low High Central Low Central High Central Low 2013 129 107 88 115 96 79 94 92 88 110 203 169 145 2015 190 164 145 127 106 87 114 95 78 94 92 88 110 178 149 128 2020 162 139 122 123 103 84 110 92 76 93 92 88 109 149 125 109 2025 138 118 103 121 101 83 108 90 74 93 92 88 109 131 110 96 2030 125 107 93 119 99 81 106 88 73 93 91 88 109 118 100 87 DECC Modelling The estimates outlined in the above sections are intended to provide a high-level view on the costs of different generating technologies. In practice DECC’s electricity market modelling, including for the Updated Energy & Emissions Projections (which uses DECC’s Dynamic Dispatch model), does not use ‘levelised cost estimates’ per se. Instead it models private investment decisions, at the financial close for a project, using the same Capex and Opex assumptions incorporated in the levelised cost estimates reported above; assumptions on investors’ foresight over fossil fuel, carbon and wholesale electricity prices; and the financial incentives from policies e.g. the RO. In order to model the investment decision, the internal rate of return of a potential plant is compared to a technology specific hurdle rate. The starting point for these is Oxera 201119 and other sources20, but these are adjusted to allow for the estimated impact of policies on financing costs (e.g. the impact of CfDs). As these hurdle rates are understood to incorporate an allowance for a return on pre-development costs, pre-development costs are not separately included in the investment decision modelling to avoid double counting. 19 http://hmccc.s3.amazonaws.com/Renewables%20Review/Oxera%20low%20carbon%20discount%20rates%2018 0411.pdf 20 See Annex 4 for further details 15 Electricity Generation Costs Annex 1: Key timings for selected technologies Pre-development Period (years) Construction Period (years) Gas - CCGT 2 3 Gas - CCGT with post comb. CCS FOAK 5 5 Gas - CCGT retro post comb. CCS FOAK 4 4 Coal - ASC with FGD 4 3 Coal - ASC with post comb. CCS FOAK 5 5 Coal – IGCC 5 5 Coal - IGCC with CCS FOAK 5 6 Nuclear - NOAK 5 5 Nuclear - FOAK 5 6 Dedicated biomass >50MW 3 3 Dedicated biomass 5-50MW 4 2 Offshore R1/2 5 3 Offshore R3 6 3 Onshore >5 MW 4 2 Cofiring Conventional 1 1 Biomass Conversion 2 1 Table 6:Central Estimates for project timings for selected technologies Please see assumptions section for details of sources 16 Annex 2: Calculating Levelised Cost Estimates The below figure, demonstrates at a high level how Levelised Costs are calculated. Step 1: Gather Plant Data and Assumptions Capex Costs: -Predevelopment costs -Construction costs* -Infrastructure cost* (*adjusted over time for learning) Opex Costs: -Fixed opex* -Variable opex -Insurance -Connection costs -Carbon transport and storage costs -Decommissioning fund costs -Heat revenues -Fuel Prices -Carbon Costs Expected Generation Data: -Capacity of plant -Expected Availability -Expected Efficiency -Expected Load Factor ( all assumed baseload) Step 2: Sum the net present value of total expected costs for each year NPV of Total ∑ total capex and opex costs n = n Costs (1 + discount rate) n n = time period Step 3: Sum the net present value of expected generation for each year NPV of Electricity ∑ net electricity generation = n (1 + discount rate) n n Generation n = time period Step 4: Divide total costs by net generation NPV of Total Costs Levelised Cost of Electricity = NPV of Electricity Generation Generation Estimate Electricity Generation Costs Annex 3: Additional Estimates for Renewables Technologies This Annex presents estimates for the same Cases described in the main report for additional renewable technologies. Case 1: projects starting in 2012, NOAK, 10% discount rate21 Table 7: Levelised Cost Estimates for Projects Starting in 2012, 10% discount rate Levelised Costs, £/MWh Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Cost Carbon Costs Heat Revenues TOTAL LEVELISED COST Levelised Costs, £/MWh Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Costs Carbon Costs Heat Revenues TOTAL LEVELISED COST Levelised Costs, £/MWh Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Costs Carbon Costs Heat Revenues TOTAL LEVELISED COST 21 Co-firing Standard CHP 62 32 2 63 -57 Hydro Large STORE 2 90 8 6 - ACT standard 7 84 58 24 -27 - Bioliquids 5 21 22 6 272 - Bioliquids CHP 5 21 22 6 272 -14 EfW CHP 95 42 30 -121 -13 EfW 75 36 24 -100 - 102 106 145 325 211 32 35 Geother mal 3 66 14 11 94 Geother mal CHP 3 72 14 10 -55 45 Hydropo wer 516MW 2 110 17 6 134 ACT advanced 8 104 58 13 -23 159 ACT CHP 2 101 67 24 -32 -16 145 Sewage Gas 0 69 18 87 Landfill 3 41 9 9 62 AD CHP 3 67 58 21 -56 -15 78 Solar<4k W 281 29 310 Energy crops (small) 2 52 16 5 96 172 Energy crops (large) 1 38 14 4 82 139 Onshore <15kW 414 49 463 Onshore 1MW<5M W 107 14 121 Biomass CHP 2 63 24 10 119 -35 182 Please note these estimates should be viewed in the context of the sensitivities and uncertainties highlighted in the text of this report 18 Electricity Generation Costs Table 7: (continued) Levelised Costs, £/MWh Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Costs Carbon Costs Heat Revenues TOTAL LEVELISED COST AD < 250kW 134 176 310 AD > 500kW 75 102 -70 107 Hydropo wer <15kW 341 36 377 Hydropo wer 100kW1000kW 162 34 196 Table 8: Levelised Cost Estimates for Projects Starting in 2012, 10% discount rate, sensitivities Levelised Costs, £/MWh Central High Capex High Capex and High Fuel Low Capex and Low Fuel Low Capex Levelised Costs, £/MWh Central High Capex High Capex and High Fuel Low Capex and Low Fuel Low Capex Levelised Costs, £/MWh Central High Capex High Capex and High Fuel Low Capex and Low Fuel Low Capex Levelised Costs, £/MWh Central High Capex Low Capex 19 ACT standard 145 225 Bioliquids 325 378 Bioliquids CHP 211 365 EfW CHP 32 43 EfW 35 40 Geotherm al 94 125 Geotherm al CHP 45 77 245 392 379 61 55 - - 58 72 225 313 210 298 3 21 15 30 59 7 Hydropo wer 516MW 134 149 ACT advanced 159 172 ACT CHP 145 229 Sewage Gas 87 131 Landfill 62 90 Biomass CHP 182 202 AD CHP 78 134 - 190 253 - - 219 164 82 117 129 45 61 62 40 146 163 -53 38 Solar<4k W 310 400 Energy crops (small) 172 194 Energy crops (large) 139 172 Onshore <15kW 463 503 Onshore 1MW<5M W 121 137 AD < 250kW 310 358 AD > 500kW 107 134 - 210 186 - - - 166 248 138 156 117 133 429 100 265 -14 82 Hydropo wer <15kW 377 805 187 Hydropo wer 100kW1000kW 196 393 106 Electricity Generation Costs Case 2: projects starting in 2018, NOAK, 10% discount rate22 Table 7: Levelised Cost Estimates for Projects Starting in 2018, 10% discount rate Levelised Costs, £/MWh Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Cost Carbon Costs Heat Revenues TOTAL LEVELISED COST Levelised Costs, £/MWh Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Costs Carbon Costs Heat Revenues TOTAL LEVELISED COST Levelised Costs, £/MWh Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Costs Carbon Costs Heat Revenues TOTAL LEVELISED COST 22 Co-firing Standard CHP 1 62 32 2 63 -56 Hydro Large STORE 2 102 9 - ACT standard 7 80 55 23 -24 - Bioliquids 5 20 21 5 264 - Bioliquids CHP 5 20 21 5 264 -14 EfW CHP 93 42 30 -121 -14 EfW 74 36 24 -100 - 104 117 140 316 302 30 34 Geother mal 3 64 14 11 92 Geother mal CHP 3 70 14 10 -55 42 Hydropo wer 516MW 2 123 17 6 148 ACT advanced 8 100 55 12 -21 154 ACT CHP 2 96 63 23 -28 -16 140 Sewage Gas 66 18 84 Landfill 3 40 10 9 61 AD CHP 3 64 59 21 0 -15 131 Solar<4k W 204 28 231 Energy crops (small) 2 51 16 5 97 171 Energy crops (large) 1 37 14 4 83 139 Onshore <15kW 414 49 463 Onshore 1MW<5M W 107 14 121 Biomass CHP 2 62 23 9 119 -35 180 Please note these estimates should be viewed in the context of the sensitivities and uncertainties highlighted in the text of this report 20 Electricity Generation Costs Table 9: (continued) Levelised Costs, £/MWh Pre-Development Costs Capital Costs Fixed O&M Variable O&M Fuel Costs Carbon Costs Heat Revenues TOTAL LEVELISED COST AD < 250kW 134 176 310 AD > 500kW 75 102 -3 174 Hydropo wer <15kW 341 36 377 Hydropo wer 100kW1000kW 162 36 196 Table 10: Levelised Cost Estimates for Projects Starting in 2018, 10% discount rate, sensitivities Levelised Costs, £/MWh Central High Capex High Capex and High Fuel Low Capex and Low Fuel Low Capex Levelised Costs, £/MWh Central High Capex High Capex and High Fuel Low Capex and Low Fuel Low Capex Levelised Costs, £/MWh Central High Capex High Capex and High Fuel Low Capex and Low Fuel Low Capex Levelised Costs, £/MWh Central High Capex Low Capex 21 ACT standard 140 217 Bioliquids 316 367 Bioliquids CHP 302 355 EfW CHP 30 41 EfW 34 38 Geotherm al 92 123 Geotherm al CHP 42 74 237 387 371 19 53 - - 56 69 224 303 210 289 59 -1 14 29 58 5 Hydropo wer 516MW 148 164 ACT advanced 154 166 ACT CHP 140 220 Sewage Gas 84 126 Landfill 61 90 Biomass CHP 180 199 AD CHP 131 185 - 184 244 - - 217 215 89 113 124 43 59 60 39 144 161 3 93 Solar<4k W 231 297 Energy crops (small) 171 193 Energy crops (large) 139 170 Onshore <15kW 463 530 Onshore 1MW<5M W 121 144 AD < 250kW 310 369 AD > 500kW 174 208 - 209 184 - - - 240 187 139 155 118 132 425 98 264 52 149 Hydropo wer <15kW 377 852 185 Hydropo wer 100kW1000kW 196 415 105 Electricity Generation Costs Case 3: Commissioning in 2013, 2015, 2020, 2025, 2030, NOAK, 10% discount rate23 Table 11: Projects Commissioning in 2013,2015, 2020, 2025 and 2030, NOAK, 10%discount rate, capex sensitivity, £/MWh Commissioning, £/MWh Co-firing Standard CHP Hydro_LargeSTORE ACT standard Bioliquids Bioliquids CHP EfW CHP EfW Geothermal Geothermal CHP Hydropower 5-16MW ACT advanced ACT CHP Sewage Gas Landfill 23 Capex Central Central High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low 2013 103 104 230 149 73 380 327 315 368 314 301 44 33 22 41 36 31 157 116 70 111 69 19 142 128 79 176 163 132 235 149 62 132 88 62 91 62 40 2015 103 108 226 146 72 375 323 310 363 309 296 44 32 21 40 36 30 143 106 65 96 58 13 147 132 81 173 161 130 231 147 61 131 87 62 90 62 40 2020 104 117 218 141 70 367 316 303 355 302 289 42 31 20 39 34 29 124 93 58 76 44 6 159 144 87 168 155 125 222 141 59 127 85 60 90 61 39 2025 104 122 214 138 68 366 314 302 353 300 288 41 30 19 38 34 28 122 92 58 73 42 5 164 149 89 164 152 122 217 138 57 125 84 60 89 61 39 2030 104 122 209 133 64 365 314 301 351 299 286 40 30 19 38 33 28 120 90 57 70 40 4 164 149 90 160 147 118 211 132 53 124 83 59 89 61 39 Please note these estimates should be viewed in the context of the sensitivities and uncertainties highlighted in the text of this report 22 Electricity Generation Costs Table 11: (continued) Commissioning, £/MWh Biomass CHP AD CHP Solar<4kW Onshore <15kW Onshore 1MW<5MW AD < 250kW AD > 500kW Hydropower <15kW Hydropower 100kW-1000kW Energy crops (small) Energy crops (large) Amalgamated Wave Tidal stream shallow Tidal stream deep Tidal range 23 Capex High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low Central High Central Low High Central Low High Central Low 2013 206 185 165 118 62 22 400 310 248 503 463 429 137 121 100 358 310 265 134 107 82 805 377 187 394 196 106 196 174 157 174 141 134 2015 204 184 164 148 92 53 346 269 216 512 463 429 139 121 99 362 310 265 167 137 112 820 377 187 400 196 106 195 173 156 173 140 133 2020 201 182 162 185 93 93 287 224 181 535 463 423 146 121 98 371 310 263 212 177 151 860 377 185 419 196 105 193 171 155 171 139 132 2025 199 180 161 183 93 93 252 198 160 559 462 413 152 121 96 381 310 261 218 177 150 902 377 181 439 196 103 193 171 155 170 138 132 194 168 163 133 164 147 130 283 229 172 2030 198 179 160 182 93 93 230 181 147 585 462 404 159 121 94 392 310 259 223 177 149 947 377 177 459 196 101 192 170 154 169 138 131 160 144 146 120 143 128 114 283 229 172 Electricity Generation Costs Annex 4: Estimates for Renewables Technologies using technology specific hurdle rates This annex shows estimates using technology-specific ‘discount’ or ‘hurdle’ rates24 for renewable technologies, in line with the approach used in reports on renewables levelised costs commissioned by DECC and its predecessor departments in recent years. The starting point for these rates is Oxera 201125 along with other sources26. These are adjusted to allow for the estimated impact of policies on financing costs (e.g. the impact of the Renewables Obligation, Feed in Tariffs and Energy Market Reforms). Case 4: renewable projects commissioning in 2013-16, 2020, 2025, 2030, NOAK, technology specific hurdle rates27 Table 12: Projects Commissioning in 2013,2015, 2020, 2025 and 2030, NOAK, technology specific hurdle rates, capex sensitivity Commissioning, £/MWh Co-firing Standard CHP Hydro_LargeSTORE ACT standard Capex Central Central High Central Low 2013 109 83 224 145 73 2015 108 86 221 143 72 2020 106 88 200 132 68 2025 106 91 196 128 66 2030 106 92 191 124 62 24 Please note that hurdle rates are themselves uncertain and likely to vary between projects and financing structures/providers. 25 http://hmccc.s3.amazonaws.com/Renewables%20Review/Oxera%20low%20carbon%20discount%20rates%2018 0411.pdf 26 Please see Arup 2011, Government Response to the RO and the following Feed in Tariff Impact Assessment for more details: 2a: Impact Assessment: Government response to consultation on Feed-in Tariffs Comprehensive Review Phase 2A: Solar PV Tariffs and cost control: http://www.decc.gov.uk/en/content/cms/consultations/fits_rev_ph2a/fits_rev_ph2a.aspx 2b: Impact Assessment: Government Response to Consultation on the Comprehensive Review Phase 2B - on Feed-in Tariffs for anaerobic digestion, wind, hydro and micro-CHP installations: http://www.decc.gov.uk/en/content/cms/consultations/fits_rev_ph2b/fits_rev_ph2b.aspx 27 Please note these estimates should be viewed in the context of the sensitivities and uncertainties highlighted in the text of this report. 24 Electricity Generation Costs Table 12: (continued) Commissioning, £/MWh Dedicated biomass >50MW Dedicated biomass 5-50MW Offshore R2 Offshore R3 Onshore >5 MW E&W Onshore >5 MW UK Bioliquids Bioliquids CHP Cofiring Conventional Biomass Conversion EfW CHP EfW Geothermal Geothermal CHP Hydropower 5-16MW ACT advanced ACT CHP 25 Capex High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low Central High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low 2013 176 134 125 160 132 111 193 169 148 125 105 86 112 93 77 391 331 317 383 319 304 94 92 88 111 74 60 45 56 50 44 357 252 137 328 216 84 114 103 65 205 189 151 301 185 67 2015 174 133 124 158 131 110 177 155 136 231 198 172 124 103 85 111 92 76 386 326 312 378 314 299 94 92 88 111 73 58 44 55 50 43 322 228 125 288 187 69 117 106 67 202 186 148 296 181 65 2020 166 128 120 150 125 106 138 121 107 188 161 139 112 94 78 100 84 70 374 318 305 366 305 291 93 92 88 110 62 49 36 47 42 36 254 181 101 213 135 44 120 109 69 186 171 137 270 167 63 2025 158 124 117 142 119 102 110 97 86 146 125 108 110 92 77 99 83 68 369 315 303 360 302 289 93 92 88 110 61 48 35 47 42 36 176 128 75 132 80 20 124 113 71 171 157 126 247 154 59 2030 157 123 116 141 118 101 101 88 78 116 100 87 108 91 75 97 81 67 368 315 302 358 301 287 93 91 88 110 60 47 34 46 41 36 137 102 63 94 55 9 124 113 71 166 153 122 240 148 55 Electricity Generation Costs Table 12: (continued) Commissioning, £/MWh Sewage Gas Landfill Biomass CHP AD CHP Solar<4kW Solar250-5000kW Onshore <15kW Onshore 1MW<5MW AD < 250kW AD > 500kW Hydropower <15kW Hydropower 100kW-1000kW Energy crops (small) Energy crops (large) Amalgamated Wave Tidal stream shallow Tidal stream deep 26 Capex High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low High Central Low Central High Central Low High Central Low 2013 128 86 61 89 61 39 233 206 179 143 69 16 305 238 192 165 138 119 461 425 394 126 111 92 399 340 285 148 115 84 635 302 153 314 160 90 215 187 166 192 150 142 2015 118 79 57 89 61 39 231 204 177 170 101 52 288 208 151 150 117 92 469 425 394 128 111 92 392 332 280 179 145 116 647 302 153 320 160 90 213 186 165 191 150 141 2020 114 77 55 85 58 38 221 196 172 213 146 99 271 174 126 138 100 79 490 424 388 134 111 90 403 332 278 230 190 159 678 302 152 334 160 89 205 180 161 183 145 137 2025 113 76 55 84 58 38 211 189 167 201 140 96 253 154 114 127 88 71 512 424 379 140 111 88 397 320 268 227 183 154 711 302 149 349 160 88 198 175 158 176 141 134 216 202 185 150 187 167 147 2030 112 76 55 84 58 38 210 188 166 199 139 96 238 142 107 117 80 65 535 423 371 146 111 86 409 320 266 233 183 153 746 302 146 366 160 86 197 174 157 175 141 134 166 167 153 126 150 135 119 Electricity Generation Costs Table 12: (continued) Commissioning, £/MWh Tidal range 27 Capex High Central Low 2013 2015 2020 2025 218 165 126 2030 218 165 126 © Crown copyright 2012 Department of Energy & Climate Change 3 Whitehall Place London SW1A 2AW www.decc.gov.uk URN 12D/383