Volume 30, Number 5 Projects on the Brink: Part I — When the Money Stops Flowing by W. Henry Parkman* A. Troubled Market Conditions Jeopardize the Continuity of Construction Projects News reports of stalled construction projects are becoming more and more common in these uncertain economic times. A Dubai developer recently announced that it was shelving plans for what had been described as the world’s tallest skyscraper. Work has stopped on the prominent Chicago Spire project, and the Chicago Sun-Times reported that the main lender to the Spire developer was near collapse. Architects and engineers have filed millions of dollars in lien claims, and the Chicago Spire project site consists of a deep hole in the ground. Work has reportedly been halted on 11 percent of skyscraper projects worldwide, including 29 of 301 skyscraper projects in the United States. * W. Henry Parkman is a partner with Sutherland, resident in its Atlanta office. He has practiced construction law for 24 years, focusing on mediation, litigation, and arbitration of disputes arising from industrial, commercial, heavy-highway, and other complex construction projects. He acknowledges the research assistance of Sutherland associates Eric L. Hurst, Adam D. Nugent, and Laura J. Stipanowich. REPRINT ARTICLE May 2009 Construction of Echelon, a Las Vegas casino resort, was suspended after it had reached twelve stories. Boyd Gaming, Echelon’s developer, indicated that the suspension was expected to last for three or four quarters, while banks are reluctant to lend, and the U.S. economy slows. Many less-prominent projects have been shelved or are at risk of loss of funding. The contraction of the economy presents a “double whammy” to developers and contractors. Both are affected by shrinking of available financing and reduction in property values. Declining real estate values harm developers’ pro formas, and diminish contractors’ traditional security of mechanics’ lien rights. What can participants in the construction industry do to reduce their risk on projects that are in economic jeopardy? This article focuses on the suspension or threatened suspension of projects after a construction contract has been signed and performance has begun and outlines options available to participants on such projects that may mitigate financial losses. B. The Owner/Developer Has Three Basic Choices — Suspend, Terminate, or Complete 1. The Owner May Suspend the Project If the owner/developer loses financing or market conditions undermine the economic Article Reprint Reprinted from the Construction Litigation Reporter. Copyright © 2009 Thomson Reuters. For more information about this publication please visit www. west.thomson.com © 2009 Thomson Reuters construction litigation reporter viability of a project, three basic options present themselves. The owner/developer may suspend the work until financing becomes available/and or market conditions substantially improve. The suspension option requires the owner/developer to evaluate realistically how long it will take for market conditions to improve and/or to locate new sources of funding. Although the owner/developer may be able to negotiate more favorable terms with the prime contractor for the good of the project, negotiation will not alter statutory requirements for filing and perfecting mechanics’ lien claims. Any suspension plan will need to minimize and deal with the mechanics’ lien claims that will inevitably be filed. Some states require a subcontractor or supplier to file a lawsuit to perfect a lien claim within a year of the claim becoming due. If a suspension will last too long, an owner will likely be forced to choose between termination and completion. 2. The Owner May Terminate the Project The owner/developer has the option to terminate an economically-troubled project. The owner/developer should be prepared to deal with the legal fallout from a termination, and weigh that risk against the risk of attempting to continue with a project. The owner/developer should consider its rights against the lender under applicable financing documents. Is the lender justified in suspending or terminating financing under the terms of the loan documents? If not, the developer as borrower should consider traditional legal remedies that may be available, such as breach of contract, misrepresentation, © 2009 Thomson Reuters. This publication was created to provide you with accurate and authoritative information concerning the subject matter covered, however it may not necessarily have been prepared by persons licensed to practice law in a particular jurisdiction. The publisher is not engaged in rendering legal or other professional advice, and this publication is not a substitute for the advice of an attorney. If you require legal or other expert advice, you should seek the services of a competent attorney or other professional. For authorization to photocopy, please contact the Copyright Clearance Center at 222 Rosewood Drive, Danvers, MA 01923, USA (978) 750-8400; fax (978) 646-8600 or West’s Copyright Services at 610 Opperman Drive, Eagan, MN 55123, fax (651)687-7551. Please outline the specific material involved, the number of copies you wish to distribute and the purpose or format of the use. For subscription information, please contact the publisher at: west.legalworkspublications@thomson.com This publication was created to provide you with accurate and authoritative information concerning the subject matter covered; however, this publication was not necessarily prepared by persons licensed to practice law in a particular jurisdiction. The publisher is not engaged in rendering legal or other professional advice and this publication is not a substitute for the advice of an attorney. If you require legal or other expert advice, you should seek the services of a competent attorney or other professional. Construction Litigation Reporter (USPS 747-330) (ISSN 0279-1102) is published monthly, with a combined July - August newsletter and an annual index published in January in addition to the regular January monthly newsletter, for a total of twelve issues published annually. Published and copyrighted by Thomson Reuters, 610 Opperman Drive, P.O. Box 64526, St. Paul, MN 55164-0526. For subscription information: call (800) 221-9428, or write West, Credit Order Processing, 620 Opperman Drive, P.O. Box 64833, St. Paul, MN 55164-9753. Periodical postage paid at St. Paul, MN. POSTMASTER: Send address changes to, Construction Litigation Reporter, 610 Opperman Drive, P.O. Box 64526, St. Paul, MN 55164-0526. Attorney Editor: Marc M. Schneier Customer Service: 610 Opperman Drive, Eagan, MN 55123. Tel.: 1-800-328-4880; Fax: (612) 687-6674. Editorial Offices: Construction Litigation Reporter, 412 Redleaf Road, Wynnewood, PA 19096-1624. Tel. (610) 642-9337 Fax: (610) 642-9375. E-Mail: mschneier@buildinglaw.org; Web site: buildinglaw.org © 2009 Thomson Reuters. GENERAL PHOTOCOPY NOTICE: For authorization to photocopy, please contact the Copyright Clearance Center at 222 Rosewood Drive, Danvers, MA 01923, USA (978) 750-8400; fax (978) 646-8600 or West’s Copyright Services at 610 Opperman Drive, Eagan, MN 55123, fax (651) 687-7551. Please outline the specific material involved, the number of copies you wish to distribute and the purpose or format of the use. 2 © 2009 Thomson Reuters MAY 2009 and/or promissory estoppel, assuming that the facts and law of the applicable jurisdiction support a claim against the lender. Such disputes involve highly factual issues, including the terms and binding nature of loan documents. The law applicable to these disputes varies by jurisdiction. As in any commercial dispute the claimant should consider the solvency of the defendant and weigh the prospect that the defendant may file for bankruptcy. The traditional legal concept of “force majeure” has recently been asserted as a justification for avoiding contractual performance. The well-known developer of the Trump International Hotel and Tower in Chicago claimed in a lawsuit that the lender should delay its effort to collect $40 million that he personally guaranteed because the current economic downturn constitutes a “force majeure,” or an event not within the reasonable control of the borrower. The contract between the owner/developer and the contractor is likely to contain a “Termination for Convenience” clause, under which the owner may terminate the contract for any reason. Such a Termination for Convenience clause, however, requires the owner to pay the contractor’s specified costs of termination. The owner should understand the magnitude of the cash outflow required to settle the contractor’s termination for convenience costs. Such an obligation to fund the contractor’s termination costs may prompt owners to search for a justification to terminate a project for default, instead of for the owner’s convenience. A termination for default will likely meet a challenge from the contractor, leading to a lawsuit or an arbitration. Fighting over whether the termination for default was justified is likely to be expensive, but would allow an owner to avoid an immediate obligation to pay the contractor, as would be the case under a termination for convenience. If the owner terminates a project, it may hope to sell the project or to assign the development rights to the lender or to another developer. If there is no reasonable prospect of having another developer step in, however, the owner will © 2009 Thomson Reuters need to prepare for the cost of “mothballing” the project, to preserve value in the asset while waiting for market conditions to improve. Aside from the cost of “mothballing” a project, owners must keep in mind their obligations to municipalities. A municipality may revoke the building permit if a suspended project is considered to be abandoned. A project that is not properly mothballed may become a nuisance, allowing the municipality to invoke demolition rights. An owner/developer also has the option of a partial termination of a contract, including the right to delete scope by deductive change order. For example, suspension of the Echelon project had a ripple effect on CityCenter, another Las Vegas mega-development. Changing market conditions created an opportunity for the developer to minimize costs of the ongoing CityCenter project. With the contractor’s consent, the developer deleted a major portion of interior work and awarded that work to the contractor whose work had stalled on Echelon. This move was designed to take advantage of better subcontractor pricing, expected in a more competitive market. 3. The Owner May Complete the Project Finally, the owner has the option of completing the project with a different lender or a group of lenders. Engineering News-Record recently reported that the Chicago Spire developer is in preliminary discussions with representatives from AFL-CIO Housing Investment Trusts. An incentive for using unions’ pension funds to invest in the Spire project would be the creation or preservation of thousands of jobs over what is anticipated to be five years of construction. Depending on the financial strength of the contractor, the owner should also consider approaching the contractor to act as a lender or to take a partial equity stake in a project. The decline in real estate values makes a contractor’s lien rights less desirable as a security mechanism. The contractor, if in a position to contribute financing, labor, and materials to a project, may be motivated to partner with an owner to 3 construction litigation reporter complete the project, rather than face termination and litigation, with an uncertain ability to recover earned contract funds. Of course, if a contractor is in a position to contribute to the completion of a project, the owner should be willing to modify the contract terms to provide the contractor with an improved security position, a greater “up-side” upon successful completion of the project, and/ or a guaranty of some level of payment, with appropriate collateral. C. How Does The Contractor Respond? 1. The Contractor May Request Evidence that the Owner Has Arranged Sufficient Financing to Pay for the Work If an owner is slow in funding pay applications or if the contractor becomes concerned about the owner’s ability to pay, the contractor should see whether its contract allows the contractor to request evidence of the owner’s ability to fund the remainder of the project. For example, section 2.2.1 of AIA Document A-201 – 1997, “General Conditions of the Contract for Construction,” allows a contractor to seek assurances regarding the owner’s financial arrangements: The Owner shall, at the written request of the Contractor, prior to commencement of the Work and thereafter, furnish to the Contractor reasonable evidence that financial arrangements have been made to fulfill the Owner’s obligations under the Contract. Furnishing of such evidence shall be a condition precedent to commencement or continuation of the Work. After such evidence has been furnished, the Owner shall not materially vary such financial arrangements without prior notice to the Contractor. Pursuant to this clause, if the owner does not furnish evidence that adequate financing is in place, the contractor has the right to suspend its work. Moreover, if the owner fails to provide evidence of its ability to pay, upon seven days’ written notice, the contractor has the right to terminate the contract and to recover payment for 4 work performed and for proven loss, “including reasonable overhead, profit and damages.” Section 14.1.3, AIA Document A201 - 1997. The 2007 edition of section 2.2.1, AIA Document A201, limits the contractor’s right to request the owner to provide evidence that construction financing is in place. The 1997 version allowed the contractor to make such a request, without any showing, after the work commenced. Under the 2007 edition, after work commences, “the Contractor may only request such evidence if (1) the Owner fails to make payments to the Contractor as the Contract Documents require; (2) a change in the Work materially changes the Contract Sum; or (3) the Contractor identifies in writing a reasonable concern regarding the Owner’s ability to make payment when due.” A contractor on a condominium project in Florida demanded assurances from the owner, pursuant to the 1997 version of section 2.2.1, that adequate financing was in place. The owner allegedly did not provide such assurances. After suspending its work for a month, the contractor gave notice that it was terminating its work on the project as a result of, among other things, the owner’s failure to provide evidence of adequate financial arrangements. Later, the contractor assigned its contract and lien rights to its surety, and the owner sued the surety, asserting multiple claims. Goodbys Creek, LLC v. Arch Ins. Co., No. 3:07-cv-947, 2008 WL 2950112 (M.D. Fla. July 31, 2008). The case remains pending. Even without an express contract clause allowing a contractor to require the owner to furnish evidence of adequate financing, the doctrine of anticipatory repudiation may allow a contractor to seek assurances of payment before continuing performance. The Supreme Court of New Hampshire has recently held that a contractor was justified in suspending construction work until the owners supplied adequate assurance of financing the work. McNeal v. Lebel, 157 N.H. 458, 953 A.2d 396 (2008). The McNeal court concluded that the right to demand adequate assurance (as recognized in section 2-609 of the Uniform Commercial Code) is closely related to the implied duty of © 2009 Thomson Reuters MAY 2009 good faith and fair dealing and could be invoked where the contractor was informed that the lender would not be funding additional construction draws. Because the contractor had sufficient grounds “to seek adequate assurance of future performance, which the [owners] did not supply, neither [the contractor’s] request for the escrow of funds, nor his cessation of work pending such assurance was a material breach relieving the [owners] of further obligation under the contract.” Id. at 463, 953 A.2d at 401. 2. The Contractor Can Pursue Legal Remedies The typical response of a contractor to the owner’s failure to pay is to assert the traditional legal remedies of breach of contract and to file lien or bond claims. Contractors have also utilized other theories, such as promissory estoppel, to assert claims against lenders, even in the absence of a direct contract. For example, another contractor’s request for assurances of adequate financing prompted a bank to provide the contractor with a letter confirming that the bank was committed to financing the project. Suitt Construction Co. v. Hill, 150 P.3d 335 (Kan. App. 2007) (unpublished opinion). After the owner had drawn down all available loan amounts, the owner filed for bankruptcy. Based on the commitment letter, the contractor asserted a promissory estoppel claim against the bank. The court rejected that claim, however, because the bank’s letter merely committed to financing the project, but did not require the bank to pay the contractor directly. A contractor who is terminated because the owner cannot or will not pay has available legal remedies for breach of contract. That remedy for material breach or wrongful termination by the owner, however, may have little value if the owner/developer has become insolvent or is on the brink of bankruptcy. A contractor on a terminated project also has available statutory lien rights, the traditional security for a contractor when the owner “goes bust.” The contractor’s lien remedy may turn out to be hollow, however, if the pre-construction assumed values for the project greatly ex- © 2009 Thomson Reuters ceed the current true value of the real estate. A project that is terminated mid-stream will be less attractive to buyers, with less opportunity for satisfaction of a contractor’s lien claim. 3. The Contractor, Stuck in the Middle, Will Have to Deal with Subcontractor Lien Claims If a contractor is terminated because funding has become unavailable, the contractor will not only have to assert its rights against the owner, it will have to defend subcontractor lien and payment bond claims and lawsuits to perfect. Lien claims of subcontractors and suppliers usually represent the first wave of legal filings, indicating that a project may be on shaky economic ground. The terms of the subcontract and the applicable law are vital to developing the best defense, especially if the owner’s funding is slowing or stopping. Analysis is needed to see what subcontract terms the contractor may use to defeat or to delay the subcontractor claims. Many states will enforce a “pay-when-paid” or “pay-if-paid” provision in the subcontract, if receipt of payment from the owner is stated as a condition precedent to the contractor’s obligation to pay the subcontractor/supplier. The following questions should be addressed. Does the contractor have an obligation to keep the project property free and clear of lien claims? If the lien claims are a direct result of the owner’s failure to pay funds earned by the contractor and its subcontractors/suppliers, is the contractor relieved of the obligation to satisfy or to bond off subcontractor/supplier lien claims? Does the contractor have flow-down provisions in its subcontracts? If the contractor is terminated for convenience, the contractor should likewise be able to terminate the subcontracts/purchase orders for convenience and pass on these termination costs to the owner. If the owner does not or cannot satisfy its obligations to pay applicable termination for convenience costs, the contractor will likely have to defend lawsuits brought by unpaid subcontractors and suppliers. 5 construction litigation reporter 4. Instead of Adopting an Adversarial Posture, the Contractor May Be Better Off by Teaming with the Owner to Maintain the Viability of the Project Because of the possible inadequacy of their legal remedies, contractors on troubled projects should be open to the option of teaming with the owner, in the interest of keeping the project viable. Perhaps the owner could avoid termination or suspension of the project if the contractor agreed to act as a lender or to provide labor and materials in exchange for receiving an equity stake in the project. Of course, any contractor that increases its risk for the good of the project should receive a higher priority and/or improve its security for the increased indebtedness. Under a teaming approach where the contractor contributes money, labor, and/or materials, it will be necessary to modify the contract terms to reflect the different arrangement and to assure a fair (and secure) return upon successful completion of the project. One challenge to be faced by a contractor under this scenario is how to keep major subcontractors and suppliers on board. Unless major subcontractors and suppliers receive funding and/or better security positions, they are likely to stop work and file lien claims. 6 D. Modify Contract Terms to Minimize Risk on Future Projects Most of the contracts utilized on the projects jeopardized because of current economic conditions were prepared, reviewed, and signed without consideration of what has been described as a “financial tsunami.” Now that what was unforeseen has occurred, participants in the construction industry should modify their contracts to better allocate risks and rewards on future projects. Contract terms to be reviewed include the right to request assurance of adequate financing; payment guaranties; and rights and remedies for convenience terminations. In contract negotiation, contractors and owners should address the risk of lender default and contemplate ways the contractor may improve its security if the owner needs the contractor to contribute financing, labor, and/or materials to complete the project. The breadth of the topic of this article has required somewhat cursory treatment of the relevant issues. The author hopes, however, that the options explored may allow industry participants to mitigate losses resulting from the reduced flow of financing for construction projects. © 2009 Thomson Reuters