BHP 2012 - Western Electricity Coordinating Council

advertisement

Wes R. Wingen

Manager, Transmission Planning wes.wingen@blackhillscorp.com

March 9, 2012

Mr. David Franklin

Chair, WECC Technical Studies Subcommittee

Southern California Edison

1 Innovation Way

Pomona, CA 91768

409 Deadwood Avenue • PO Box 1400

Rapid City, SD 57709-1400

P: 605.721.2268

F: 605.721.2735

Mr. Enoch Davies

WECC Technical Staff

Western Electricity Coordinating Council

155 North 400 West, Suite 200

Salt Lake City, UT 84103

Re: Black Hills Power 2012 Annual Progress Report

Gentlemen:

Please find attached Black Hills Power’s 2012 Annual Progress Report on significant additions and changes to our system. The projects included in the report have no significant impacts on the

WECC interconnected system. Please contact me if you have any questions or concerns.

Sincerely,

Wes R. Wingen

Manager, Transmission Planning

Enclosure cc: Eric Egge – PCC Representative

Dan Baye – SRWG Representative

TSS Members

WECC Annual Progress Report for Black Hills Power 2012

Minnekhata 230 kV Substation:

The Minnekhata 230 kV substation is required to provide additional 230:69 kV transformation capacity in the southern Black Hills. The station will tap the existing Westhill-Osage 230 kV line approximately 9.7 miles from the Westhill substation and will include a 70 MVA 230:69 kV transformer. Reliability analysis for this project was initially performed as part of the 2008

BHBE LTP Study. Construction on the substation began in 2010 and was placed in-service during the fourth quarter of 2011.

St. Onge 230 kV Substation:

The St. Onge 230 kV substation project was identified to provide additional 230:69 kV transformation capacity in the northern Black Hills. The station will tap the existing Lange-

Lookout 230 kV line approximately 10 miles from the Lookout substation and will include a 150

MVA 230:69 kV transformer. Reliability analysis for this project was initially performed as part of the 2008 BHBE LTP Study. Construction on the substation has been delayed beyond 2014.

Teckla-Osage 230 kV Transmission Line:

The Teckla-Osage 230 kV line will consist of approximately 60 miles of 1272 ACSR ‘Bittern’ conductor on H-frame poles. The line will be constructed to provide needed Common Use

System (CUS) transmission capacity, accommodate projected load growth, and increase Wyodak area stability margins. Reliability analysis for this project was initially performed as part of the

2008 BHBE LTP Study. The Teckla-Osage line construction is scheduled to begin in 2013, and is expected to be complete in 2014.

Osage-Lange 230 kV Transmission Line:

The Osage-Lange 230 kV line will consist of approximately 75 miles of 1272 ACSR ‘Bittern’ conductor on H-frame poles. The line will be constructed to provide needed Common Use

System (CUS) transmission capacity and provide an additional path to the Rapid City load center. Reliability analysis for this project was initially performed as part of the 2008 BHBE

LTP Study as specified in Attachment K to the BHBE OATT. The Osage-Lange line construction is scheduled to begin in 2013. The project is still expected to be complete in 2015.

Reno Junction 200 MW Wind Farm:

The Reno Junction Wind Farm is a proposed generation project consisting of up to one hundred thirty-four (134) GE 1.5 MW wind turbines. The generation project will interconnect to the

Pumpkin Buttes 230 kV substation via a radial 230 kV line. The project has an executed LGIA that is currently under suspension. There are no changes to the status of this project from the

2011 WECC Annual Progress Report submittal.

WECC Annual Progress Report for Black Hills Power 2012

Weston Wind I 250.7 MW Wind Farm:

The Weston Wind I Wind Farm is a proposed generation project consisting of one hundred nine

(109) Siemens SWT-2.3-93 2.3 MW wind turbines. The generation project will interconnect to a new substation on the Wyodak-Osage 230 kV line approximately 6 miles northwest of the existing Osage power plant in Weston County, Wyoming. The customer has completed the

System Impact Study phase, and a Facilities Study Agreement has been tendered. The SIS report for this project was included in the 2011 WECC Annual Progress Report Submittal. The

Facilities Study Agreement was not returned and this project has been deemed terminated/complete.

Download