Schedule 9 – Part 1 Practical Completion Part 1 – Practical Completion 1 For the purposes of this Schedule 9 only, the South Kirkby Main RCV Facility shall be deemed to be a Non-Acceptance Test Facility and references to New Waste Management Facilities shall exclude the Carrwood Road TLS. 2 Where applicable each New Waste Management Facility and the South Kirkby Main Site shall for the purposes of Practical Completion satisfy the following requirements in accordance with the Works Delivery Plan and all Necessary Consents:a) has been designed and constructed on the relevant Site; b) has had any relevant landscaped areas completed; c) has had any other facilities shown on the appropriate drawings completed; d) all external fencing, gates, security equipment, vehicular and pedestrian accesses have been completed; e) is secure from intrusion and uncontrolled public access; f) all buildings are weatherproof and watertight as appropriate; g) all building services, drains, fire and any security related equipment have been completed; h) all surface water drainage connections have been completed in accordance with the requirements of the land drainage authority and any damage has been made good; i) any foul sewer diversion has been completed; j) all buildings, and the relevant parts of each Site are clean and tidy and all debris and rubbish have been removed; k) all mechanical and electrical installations, plant and equipment have been installed, tested, certified and are safe for use; l) all weighbridges have been calibrated and are operational; m) is entitled to operate lawfully and accept Contract Waste; n) all health and safety systems are operational; and o) all roads and hard-standings required for the delivery of Contract Waste have been constructed and completed including surface dressings, kerbs, drainage and road markings. 07/01/2013 Part 1 Page 1 of 21 Schedule 9 – Part 2 Acceptance Tests Part 2 – Acceptance Tests Acceptance Tests will be carried out using Contract Waste only and no Non-Contract Waste will be processed during the conduct of these Acceptance Tests. The Acceptance Tests shall be carried out in accordance with the agreed Acceptance Test Programme. The Acceptance Tests shall be supervised by the Independent Certifier and the Contractor. 07/01/2013 Part 2 Page 2 of 21 Schedule 9 – Part 2 Acceptance Tests 1. South Kirkby Main Composting Facility 1.1 The Acceptance Test 1.1.1 The Acceptance Test will demonstrate that the South Kirkby Main Composting Facility can process the Composting Input without breaching the Environmental Permit and produce Composted Material in accordance with test 1.1 of Table 1 below. 1.1.2 In order to complete the test in a reasonable period of time the Acceptance Test will be restricted to the processing of four (4) composting tunnels worth of Composting Input over a complete composting cycle using the normal operational Composting procedure as set out in section 2.10.4.1 of the Works Delivery Plan and the Operating Manuals. 1.1.3 Four (4) of the first stage composting tunnels will be filled to their design operating capacities so that the required composting conditions are achieved and maintained throughout the period of the Acceptance Test. The time taken to fill the four (4) tunnels will depend on the delivery rate of Composting Input. 1.1.4 The criteria being monitored or measured are defined in Table 1 below. 1.1.5 The Acceptance Test of the South Kirkby Main Composting Facility shall be deemed passed provided the pass criteria defined in Table 1 below are achieved 1.1.6 Should the pass criteria in test 1.1 of Table 1 below not be achieved then, following modification to the South Kirkby Main Composting Facility, test 1.1 shall be repeated with a duration that shall be agreed with the Independent Certifier. 1.1.7 Should the pass criteria in tests 1.3, 1.4, or 1.5 of Table 1 below not be achieved then, following modification to the South Kirkby Main Composting Facility, that test shall be repeated within the remaining period of the Acceptance Test or the period of the Acceptance Test shall be increased to accommodate the retest as agreed with the Independent Certifier. 07/01/2013 Part 2 Page 3 of 21 Schedule 9 – Part 2 Acceptance Tests Table 1 South Kirkby Main Composting Facility Parameters Test Feature being Any specific conditions for tested the facility to ensure that the feature being tested is subject of a valid test 1.1 Throughput of the South Kirkby Main Composting Facility 1.2 Test Process and parameters measured Pass Criteria Throughout the period of the Acceptance Test the South Kirkby Main Composting Facility shall be operated in accordance with the relevant Operating Manuals. The time taken to reach maturity will depend on a number of parameters and it is the role of the Contractor’s composting operator to determine when the composting process has finished. When the Contractor’s composting operator deems that, after maturation, the material has reached a suitable condition, the composted material for each of the four batches shall be sampled using the The South Kirkby Main guidance in BS EN 12579 and the samples shall be tested Composting Facility will be to demonstrate that the South Kirkby Main Composting staffed with the number of Staff Facility can produce Composted Material to achieve: as set out in the relevant Operating Manuals. Staff will a Composted Material compliant for agricultural or have completed the appropriate horticultural use in accordance with the standards defined induction and training process in Table 1 of the Materials and Energy Marketing Plan. prior to the commencement of and after further maturation and screening a Composted Material that meets the product quality aspects of PAS the Acceptance Test. 100:2005 standard and is in accordance with Quality Protocol - Compost (the Quality protocol for the production and use of quality compost from source-segregated biodegradable waste” published by WRAP and the Environment Agency, July 2010). Contribution of Throughout the period of the Tonnage of Composting Input will be recorded and a mass the facility to Acceptance Test the South balance will be compiled detailing the input and output Contract Kirkby Main Composting streams across the South Kirkby Main Composting Facility. Targets Facility shall be operated in Although there is no specific figure for the South Kirkby accordance with the relevant Main Composting Facility the mass balance will be used to determine the contribution of the South Kirkby Main Part 2 07/01/2013 Page 4 of 21 Schedule 9 – Part 2 Acceptance Tests 1.3 Noise levels Operating Manuals. Composting Facility towards: The South Kirkby Main Composting Facility will be staffed with the number of Staff as set out in the relevant Operating Manuals. Staff will have completed the appropriate induction and training process prior to the commencement of the Acceptance Test. The peak noise levels will be recorded at the test points identified in the South Kirkby Acceptance Testing Measurements Points SK-EXT9201 during normal operating conditions whilst the following activities are being conducted: The level of noise generated by the South Kirkby Main Composting Facility will be measured in accordance with the detailed procedure set out in the Acceptance Test Programme. 1.4 Odour Levels while Composting Input is being delivered; while the waste shredder is operating at near operating capacity; and while the loading shovel is filling a tunnel This test will be performed towards the end of the test period for the South Kirkby Main Composting Facility. The biofilter operation will be adjusted to take into account the Household Waste Recycling Target; and the BMW to Landfill Target The level of generated noise will be measured on one occasion at each of the test points on the boundary of the South Kirkby Main Site. The measurements taken at these points, as may be determined by the Environmental Permit, are to ensure that noise levels comply with the requirements of the Environmental Permit. The odour shall be monitored at a number of points on the boundary of the South Kirkby Main Site as may be determined by the Environmental Permit and in accordance with the detailed procedure set out in the Acceptance Test Programme to ensure that odour levels comply with the requirements of the Environmental Permit. Part 2 07/01/2013 Page 5 of 21 Schedule 9 – Part 2 Acceptance Tests 1.5 Bioaerosol Levels the number of tunnels being tested using suitable means, such as temporary baffles, to maintain the residence time at the design levels. The ventilation fans in the unused tunnels shall be configured so as to maintain the expected efflux velocity at the discharge point. If the efflux velocity varies from the predicted velocity no correction factor shall be applied. The odour output from the biofilters will be measured to ensure compliance with the levels of odour set out in the Environmental Permit. The bioaerosol tests shall not be undertaken before the biofilters have been acclimatised and optimised. If required by the Environment Agency as part of the Environmental Permit, bioaerosol levels will be measured at a number of points on the boundary of the South Kirkby Main Site in accordance with the detailed procedure set out in the Acceptance Test Programme. The biofilter operation will be adjusted to take into account the number of tunnels being tested using suitable means, such as temporary baffles, to maintain the residence time at the design levels. The ventilation fans in the unused tunnels shall be configured so as to maintain the expected efflux velocity at the discharge Should the measured odour level from either biofilter be more than above the defined level in the air quality model (in OUe/m3); the potential impact on overall site odour release will be evaluated using the air quality model once all odour measurements required as part of the Acceptance Tests have been completed. Part 2 07/01/2013 Page 6 of 21 Schedule 9 – Part 2 Acceptance Tests point. Part 2 07/01/2013 Page 7 of 21 Schedule 9 – Part 2 Acceptance Tests 2. South Kirkby Main MRF 2.1 The Acceptance Test 2.1.1 The period for the Acceptance Test for the South Kirkby Main MRF shall be two (2) weeks. 2.1.2 The Acceptance Test will demonstrate that the South Kirkby Main MRF can process the MRF Input without breaching the Environmental Permit and produce Reclaimed Materials and Waste Derived Products in accordance with test 2.2 of Table 2 below. Part 2 07/01/2013 Page 8 of 21 Schedule 9 – Part 2 Acceptance Tests Table 2 South Kirkby Main MRF Parameters Test Feature being tested Any specific conditions for the facility to ensure that the feature being tested is subject of a valid test 2.1 Average Throughput The South Kirkby Main MRF Each week of the testing period shall comprise the of the South Kirkby shall be operated in accordance following categories of time. Main MRF with the relevant Operating Planned Operating Time (POT) shall be Manuals with adjustments to 45 hours/week. This is the time when the take into account the quantity of plant would normally be expected to be in MRF Input delivered for the operation including: preparation, startups, purposes of the Acceptance shutdowns and daily maintenance and Test. cleaning. The exact start and finish times The South Kirkby Main MRF will be staffed with the number of Staff as set out in the relevant Operating Manuals. Staff will have completed the appropriate induction and training prior to the commencement of the Acceptance Test. Test Process and parameters measured Pass Criteria which make up POT each week shall be set by the Sub Contractor and written into the detailed testing procedures prior to starting the test. Planned Weekend Maintenance Time (PWMT) shall be 48 hours/week. The exact start and finish times for PWMT each week shall be set by the Sub Contractor and written into the detailed testing procedures prior to starting the test. Planned Idle Time (PIT) shall be the remaining periods in the week which are not covered by POT or PWMT. The throughput over the testing period shall be calculated as follows. AT = TTP/(POT-UIT+EXT) AT = Average Throughput (expressed in tonnes/hours input waste) Part 2 07/01/2013 Page 9 of 21 Schedule 9 – Part 2 Acceptance Tests TTP = Total Tonnes Processed as measured using weighbridge data, with appropriate adjustments for inventory levels at the start and end of the testing period. UIT = Unplanned Idle Time is any time within the specified POT periods when the plant cannot operate solely due to lack of waste in the reception area. For any time to count towards UIT, the plant shall not be cleaned, maintained, prepared, worked on in any manner or awaiting repairs. EXT = Extra Time is any time within the PIT periods when the plant is being operated cleaned, maintained, prepared or worked on in any manner 2.2 Contribution of the South Kirkby Main MRF to Contract Targets The South Kirkby Main MRF shall be operated in accordance with the relevant Operating Manuals with adjustments to take into account the quantity of MRF Input delivered for the purposes of Acceptance Test. The tonnage of MRF Input and both Waste Derived Products and Reclaimed Materials delivered to market will be recorded and a mass balance will be compiled detailing the input and output streams across the South Kirkby Main MRF to determine the contribution of the South Kirkby Main MRF towards: The South Kirkby Main MRF will be staffed with the number of the Household Waste Recycling Target; and Staff as set out in the relevant Operating Manuals. Staff will the BMW to Landfill Target have completed the appropriate induction and training prior to Reclaimed Materials and Waste Derived the commencement of the Products shall be produced to a standard that can be delivered to the markets identified in Acceptance Test. Table 1 of the Materials and Energy Marketing Plan. Part 2 07/01/2013 Page 10 of 21 Schedule 9 – Part 2 Acceptance Tests 2.3 Noise levels The peak noise levels will be recorded at the test points identified in the South Kirkby Acceptance Testing Measurements Points SK-EXT9201 during the test operating hours and under normal operating conditions whilst the following activities are being conducted: 2.4 Odour Levels while MRF Input is being delivered; while the loading shovel is in operation; and while the trommel screen is handling MRF Input. The odour test shall not be undertaken unless the South Kirkby Main MRF ventilation fans are operating. The level of noise generated by the South Kirkby Main MRF will be measured and in accordance with the detailed procedure set out in the Acceptance Test Programme. The level of generated noise will be measured on one occasion at each of the test points on the boundary of the South Kirkby Main Site. The measurements taken at these points, as may be determined by the Environmental Permit, are to ensure that noise levels comply with the requirements of the Environmental Permit. The odour shall be monitored at a number of points on the boundary of the South Kirkby Main Site as may be determined by the Environmental Permit and in accordance with the detailed procedure set out in the Acceptance Test Programme to ensure that odour levels comply with the requirements of the Environmental Permit. Part 2 07/01/2013 Page 11 of 21 Schedule 9 – Part 2 Acceptance Tests 2.5 Dust Levels The dust test shall not be undertaken unless the South Kirkby Main MRF ventilation fans are operating. A test shall be conducted to monitor dust levels emitted from the facility if required by the Environmental Permit. Part 2 07/01/2013 Page 12 of 21 Schedule 9 – Part 2 Acceptance Tests 3. South Kirkby Main Residual Waste Treatment Facility 3.1 The Acceptance Test 3.1.1 For the purpose of this Section 3 reference to the South Kirkby Main Residual Waste Treatment Facility includes all stages in the process from reception hall up to and including the pasteurisation process and shall exclude the anaerobic digestion system which includes; the intermediate storage tanks, anaerobic digestion tanks, digestate dewatering system, gas handling systems, effluent treatment system and combined heat and power facilities. 3.1.2 The period for the Acceptance Test for the South Kirkby Main Residual Waste Treatment Facility shall be four (4) weeks 3.1.3 The Acceptance Test will demonstrate that the South Kirkby Main Residual Waste Treatment Facility can process the Residual Waste Treatment Input without breaching the Environmental Permit and produce Reclaimed Materials and Waste Derived Products and AD feedstock/cooked organic fraction in accordance with test 3.1 of Table 3 below. 3.1.4 The South Kirkby Main Residual Waste Treatment Facility shall be tested to demonstrate its compliance with the overall design capacity requirements as set out in section 2.2 of the Works Delivery Plan by operating the facility for a period of time required to process the tonnage of Residual Waste Treatment Input available. 3.1.5 The average hourly throughput rate is calculated in accordance with the following formula: Average hourly throughput rate = ∑(daily tonnage of Residual Waste Treatment Input) ∑(daily operating hours) Where Daily operating hours The daily operating period (hours) taken as the period from the recorded start time until the recorded end time as defined in test 3.1 of Table 3. 3.1.6 Unless agreed with the Independent Certifier, during the period of the Acceptance Test planned maintenance and defect rectification can only be carried out during: the daily operating hours; during the planned daily maintenance and cleaning period (4.5 hours); the weekend non operating periods. 3.1.7 Plant preparation activities such as the preparation of the boiler can be completed outside of the daily operating hours. 3.1.8 The criteria being monitored or measured are defined in Table 3 below. Part 2 07/01/2013 Page 13 of 21 Schedule 9 – Part 2 Acceptance Tests 3.1.9 The Acceptance Test of the South Kirkby Main Residual Waste Treatment Facility shall be deemed passed provided the pass criteria defined in Table 3 below are achieved. 3.1.10 Should the pass criteria in test 3.1 of Table 3 below not be achieved then following modification to the South Kirkby Main Residual Waste Treatment Facility, test 3.1 of the Acceptance Test shall be repeated with a duration that shall be agreed with the Independent Certifier. 3.1.11 Should the pass criteria in tests 3.2, 3.3, 3.5, or 3.6 of Table 3 below not be achieved then following modification to the South Kirkby Main Residual Waste Treatment Facility that test shall be repeated within the remaining period of the Acceptance Test or the period of the Acceptance Test shall be increased to accommodate the retest as agreed with the Independent Certifier. Part 2 07/01/2013 Page 14 of 21 Schedule 9 – Part 2 Acceptance Tests Table 3 South Kirkby Main Residual Waste Treatment Facility Parameters Test Feature being Any specific conditions for tested the facility to ensure that the feature being tested is subject of a valid test 3.1 3.2 Throughput of the South Kirkby Main Residual Waste Treatment Facility AD feedstock preparation using the autoclave Test process and parameters measured The South Kirkby Main Residual Waste Treatment Facility shall be operated in accordance with the relevant Operating Manuals. The tonnage of Residual Waste Treatment Input to the South Kirkby Main Residual Waste Treatment Facility will be taken from weighbridge records with appropriate adjustments for waste inventory levels at the start and end of the test period. The South Kirkby Main Residual Waste Treatment Facility will be staffed with the number of Staff as set out in the relevant Operating Manuals. Staff will have completed the appropriate induction and training process prior to the commencement of the Acceptance Test. The start time for processing of waste on each day shall be recorded as the time the first load of waste is collected by the front end loading shovel for depositing in the waste loading hopper. The entire South Kirkby Main Residual Waste Treatment Facility including the autoclave shall be operational At some stage during the Acceptance Test the AD feedstock produced by the autoclave process will be tested in accordance with the detailed procedure set out in the Acceptance Test Programme to ensure that it is a suitable feedstock for Anaerobic Digestion. The following criteria will be measured: Pass Criteria The end time for processing of waste on each day shall be recorded as the time the last load of waste is collected by the front end loading shovel for depositing in the waste loading hopper. The level of pathogens as defined by the Animal ByProducts Regulations. Plastics content is within the specification for Digestate defined in Table 1 of the Materials and Energy Part 2 07/01/2013 Page 15 of 21 Schedule 9 – Part 2 Acceptance Tests Marketing Plan Glass content is within the specification for Digestate defined in Table 1 of the Materials and Energy Marketing Plan 3.3 AD feedstock preparation using the autoclave bypass line The entire South Kirkby Main Residual Waste Treatment Facility shall be operational excluding the autoclave which shall be bypassed and the autoclave bypass line shall be operational At some stage during the Acceptance Test the autoclave bypass line shall be operated and the suitability of the AD feedstock for Anaerobic Digestion established in accordance with the detailed procedure set out in the Acceptance Test Programme. The following criteria will be measured: The level of pathogens as defined by the Animal ByProducts Regulations. Plastics content is within the specification for Digestate defined in Table 1 of the Materials and Energy Marketing Plan Part 2 07/01/2013 Page 16 of 21 Schedule 9 – Part 2 Acceptance Tests Glass content is within the specification for Digestate defined in Table 1 of the Materials and Energy Marketing Plan 3.4 RDF quality The South Kirkby Main The RDF output shall be sampled and tested in Residual Waste Treatment accordance with Schedule 2 of the Ferrybridge Off-Take Facility shall be operated in Contract. accordance with the relevant Operating Manuals. Part 2 07/01/2013 Page 17 of 21 Schedule 9 – Part 2 Acceptance Tests 3.5 Contribution of the South Kirkby Main Residual Waste Treatment Facility to Contract Targets The South Kirkby Main Residual Waste Treatment Facility shall be operated in accordance with the relevant Operating Manuals. The South Kirkby Main Residual Waste Treatment Facility will be staffed with the number of Staff as set out in the relevant Operating Manuals. Staff will have completed the appropriate induction and training process prior to the commencement of the Acceptance Test. The tonnage of Residual Waste Treatment Input and both Waste Derived Products and Reclaimed Materials delivered to market will be recorded and a mass balance will be compiled detailing the input and output streams across the South Kirkby Main Residual Waste Treatment Facility to determine the contribution of the South Kirkby Main Residual Waste Treatment Facility towards. the Household Waste Recycling Target; and the BMW to Landfill Target Reclaimed Materials and Waste Derived Products shall be produced to a standard that can be delivered to the markets identified in Table 1 of the Materials and Energy Marketing Plan. The quantity of AD feedstock sent to Anaerobic Digestion shall be estimated. There is no requirement to measure the water vapour and exhaust gases given off as a by-product of the autoclave process 3.6 Noise levels The peak noise levels will be recorded at the test points identified in the South Kirkby Acceptance Testing Measurements Points SKEXT-9201 during normal operating conditions whilst the following activities are being conducted The level of noise generated by the South Kirkby Main Residual Waste Treatment Facility will be measured and in accordance with the detailed procedure set out in the Acceptance Test Programme. The level of generated noise will be measured on one occasion at each of the test points on the boundary of the South Kirkby Main Site. The measurements taken at these points, as may be determined by the Environmental Permit, are to ensure that noise levels while Residual Waste comply with the requirements of the Environmental Treatment Input is being Part 2 07/01/2013 Page 18 of 21 Schedule 9 – Part 2 Acceptance Tests 3.7 delivered, while the pre-sort MRF and autoclave are in operation, while the loading shovel is in operation. Odour Levels - In order to ensure that the bioResidual scrubbers have achieved Waste stable operation this test shall Treatment not be commenced until after Facility the first week of the throughput test has been completed. The ventilation fans shall be operating normally during the conduct of the odour test. whilst Residual Waste Treatment input is being stored on the floor of the reception hall the bag opener shall be operating normally. Odour Levels - The ventilation fans shall be Autoclave operating normally during the Building conduct of the odour test. In order to ensure that the bioscrubbers have achieved stable operation this test shall not be commenced until after the first week of the Permit. The level of odour shall be assessed whilst the autoclave is venting into the condenser with the remainder of the South Kirkby Main Residual Waste Treatment Facility processing Residual Waste Treatment Input. The odour shall be monitored at a number of points on the boundary of the South Kirkby Main Site as may be determined by the Environmental Permit and in accordance with the detailed procedure set out in the Acceptance Test Programme to ensure that odour levels comply with the requirements of the Environmental Permit. Should the monitoring at all points not be completed on a single autoclave vent cycle then the test shall cover additional autoclave cycles as necessary. The level of odour release shall be measured at two stages of the autoclave cycle: 1. Whilst the autoclave is venting into the condenser with the remainder of the South Kirkby Main Residual Waste Treatment Facility processing Residual Waste Treatment Input. 2. During the autoclave cook phase with the remainder of the South Kirkby Main Residual Part 2 07/01/2013 Page 19 of 21 Schedule 9 – Part 2 Acceptance Tests throughput test has been completed. Waste Treatment Facility processing waste The odour output from the AD and autoclave bioscrubbers and the pre-sort MRF carbon filter will be measured individually to ensure compliance with the levels of odour set out in the Environmental Permit. Should the measured odour level from any of the bioscrubbers/carbon filters be more than above the defined level in the air quality model (in OUe/m3); the potential impact on overall site odour release will be evaluated using the air quality model once all odour measurements required as part of the Acceptance Tests have been completed. Odour Levels The ventilation fans shall be – Reception operating normally during the Hall conduct of the odour test. The measurements will be taken whilst at least 50% of the Residual Waste Treatment Input expected during that day is on the floor in the Reception Hall. The odour output from the carbon filter will be measured to ensure compliance with the levels of odour set out in the Environmental Permit. Should the measured odour level from any of the carbon filters be more than above the defined level in the air quality model (in OUe/m3); the potential impact on overall site odour release will be evaluated using the air quality model once all odour measurements required as part of the Acceptance Tests have been completed. the bag opener shall be operating normally. Part 2 07/01/2013 Page 20 of 21 Schedule 9 – Part 3 Post Anaerobic Test Part 3 - Post Anaerobic Digestion Test 1. Introduction 1.1 The Anaerobic Digestion system will take several months to commission and establish steady state operations. The Parties agree and acknowledge that this test does not form part of the Acceptance Tests required for the South Kirkby Main Residual Waste Treatment Facility to receive a Completion Certificate (and this test does not need to be undertaken for the Contractor to achieve the Full Service Commencement Date and the step up to the Unitary Charge). The Contractor shall undertake this test at an appropriate time during the Full Service Period and the results passed to the Council. 1.2 This test will be conducted to demonstrate that the Anaerobic Digestion system is performing as expected by generating Digestate that meets the market requirement defined in the Materials and Energy Marketing Plan. 1.3 Once the Anaerobic Digestion system has achieved a steady state, the Digestate produced over a 24 hour period will be sampled and tested. The test results will be compared with the market requirements defined in the Materials and Energy Marketing Plan. The sampling methodology and the detailed tests to be carried out will be defined in the Acceptance Test Programme. Part 3 07/01/2013 Page 21 of 21