Overview on the Development of the Egyptian PPP Program Bassel Shoirah Utilities Sector Officer PPP Central Unit Ministry of Finance “Capacity-Building Workshop on Public Private Partnerships” Intercontinental Hotel Amman, Jordan April 28-29, 2008 Ministry of Finance PPP Central Unit Agenda PPP Program in Egypt PPP Policy Framework – Implementation Main Legal & Commercial Aspects of PPP Transactions Role of the PPP Central Unit Key Problems and Issues Goals and Expectations PPP Pilot Projects 2 Ministry of Finance PPP Central Unit PPP Program in Egypt PPPs are key to the Government’s economic reform agenda and strategy to increase private sector involvement in public services through leveraging private spending against public spending Provide a new source of investment capital for required infrastructure projects Reduce Government sovereign borrowings and associated risks Drive the creation of local long term funding market Utilize efficiencies of private sector in running public services Expand economy and stimulate job creation Increase quality of public services to the Egyptian citizen 3 Ministry of Finance PPP Central Unit PPP Program in Egypt (cont’) Fundamental Aspects of Egypt’s PPP Policy Framework Performance-based contract under which the Private Sector supplies public services over time and is paid by the Public Sector, end user or a hybrid of both. Output is specified by Line Ministries while input is the responsibility of the private sector Under the PPP contract: The Government retains total strategic control on the service The Government secures new infrastructure which becomes Government assets at the end of contract life Project and performance risks are allocated to the party best able to manage or mitigate 4 Ministry of Finance PPP Central Unit PPP Policy Framework Egypt is providing the right environment for implementation Adoption and localisation of international successful PPP models (UK) Provision of Supportive Legislative Environment New Legal Framework for PPP Projects (Draft under finalization for Submission to Cabinet and Parliament) Standard PPP Contracts Standardization of procurement documentation and procedures Creation of regulatory bodies for post contract implementation 5 Ministry of Finance PPP Central Unit PPP Policy Framework (cont’) Implementation Strategy Placing clearly PPP initiative within reform macro fiscal agenda Establishing a PPP Central Unit at Ministry of Finance as well as Satellite Units in Line Ministries Identifying PPP’able projects as part of Line Ministries’ 5 years Strategic Plan Providing legislative framework – PPP Law Developing Tool Kit for implementation of projects 6 Ministry of Finance PPP Central Unit PPP Policy Framework (cont’) Implementation Strategy (cont’) Finalizing budgetary and accounting practices to capture PPP transactions Setting “Best Practice” precedence through pilot projects Arranging for Credit Enhancement mechanisms Stimulating domestic banking sector to offer longer tenors and competitive pricing 7 Ministry of Finance PPP Central Unit Main Commercial & Legal Aspects of PPP Transactions Risk mitigation Availability payments upon acceptance certificate Inflation and interest rate indexation Ministry of Finance support to contractual payments Conflict Resolution techniques Direct Agreement and step-in rights for Funders Compensation for termination/ extra-ordinary events/ direct impact on change of Laws All transactions are in local currency 8 Ministry of Finance PPP Central Unit Role of PPP Central Unit Act as a Public face of PPP initiative in Egypt since June 2006 Establish a national PPP policy framework for implementation Set PPP guidelines and methodologies appropriate to Egypt Draft and issue standard project documents, contracts and PPP laws Coordinate the PPP program and process across Line Ministries, private sector and funding market Report to Ministerial Committee for projects approval and recognize issues that may impede the PPP program Identify PPP able projects as part of Line Ministries’ 5 years strategic plan 9 Ministry of Finance PPP Central Unit Role of PPP Central Unit (cont’) Manage PPP transactions and provide technical and advisory support as well as ensure compliance with legislative framework Supervise Tendering and Performance Monitoring Committees Act as: Center of PPP Expertise, Support and Intelligence Gatherer Center for Capacity Building Central Complaints Resolution Office for PPP Investors 10 Ministry of Finance PPP Central Unit Key Problems and Issues Public perception of PPP's as privatization Resistance to change / Project ownership issues Project screening Bankability of projects Project execution and performance monitoring Local funding accommodating PPP transactions 11 Ministry of Finance PPP Central Unit Goals and Expectations Develop action plan to overcome obstacles and key impediments Share Egyptian experience internationally Acquire academic aspects of PPP project structuring Enhance strategies‘ & setting capabilities of team members Act as a Center of Expertise on a national & regional basis Provide ownership for PPP projects amongst both Public & Private Sectors 12 Ministry of Finance PPP Central Unit PPP Pipeline Projects Social Infrastructure Education Sector Health Sector Educational Medical Facilities General Medical Facilities Utilities Sector Wastewater Treatment Plants Transportation Sector 13 Ministry of Finance PPP Central Unit Education Sector 1800 Public Schools Overview • Location: 27 Governorates • Project Duration : 15 Years 6 Batches of Approx 350 to be tendered over 5 years Timeline • 1st Batch Launch date: November 2007 • Project Awarding date : June 2008 • Schools availability date: 2009 / 2010 Project Structure SP to finance, design, build, furbish & maintain schools, provide non educational services & transfer ownership to government at contract end. 14 Ministry of Finance PPP Central Unit Health Sector Educational Medical Facility - 1 Overview • Location: University of Alexandria • Capacity : 230 Beds • Project Duration : 20 Years Timeline • Launch Date : May 2008 • Project Awarding date : January 2009 • Operation date: December 2011 Ministry of Finance Construction of a new Specialized University Hospital (Al Mowassat) in Alexandria Governorate as: i) Neuro - Center ii) Urology / Nephrology Center Project Structure SP to finance, design, build, equip, furnish, maintain, provide non clinical services & transfer ownership to Government at contract end. PPP Central Unit 15 Health Sector Educational Medical Facility - 2 Overview • Location: University of Alexandria • Capacity : 200 Beds • Project Duration : 20 Years Timeline • Launch Date : May 2008 • Project Awarding date : January 2009 • Operation date: December 2011 Construction of a Gynecology / Obstetrics University Hospital as part of Smouha Medical Complex, as well as a Blood Bank with a capacity of 200,000 bags / year, in Alexandria Governorate Project Structure SP to finance, design, build, equip, furnish, maintain, provide non clinical services & transfer ownership to Government at contract end. 16 Ministry of Finance PPP Central Unit Health Sector General Medical Facilities - 1 Overview • Location: Cairo Governorate • Capacity : 300 Beds - General Hospital 100 Beds - Oncology Center • Project duration : 20 Years Timeline Demolition and Re-construction of Al Abassia Chest Hospital and change scope to a General Hospital, plus a separate building for Oncology Center Project Structure • Launch Date : July 2008 • Project Awarding date : July 2009 • Operation date: December 2011 SP to finance, design, build, equip, furnish, maintain, provide non clinical services & transfer ownership to Government at contract end. 17 Ministry of Finance PPP Central Unit Health Sector General Medical Facilities - 2 Overview • Location: Cairo Governorate • Capacity : 230 Beds • Project duration : 20 Years Demolition and Re-construction of Boulak General Hospital Project Structure Timeline • Launch Date : July 2008 • Project Awarding date : July 2009 • Operation date: December 2011 SP to finance, design, build, equip, furnish, maintain, provide non clinical services & transfer ownership to Government at contract end. 18 Ministry of Finance PPP Central Unit Health Sector General Medical Facilities - 3 Overview • Location: Beheira Governorate • Capacity : 100 Beds / hospital Construction of 3 Central Hospitals • Project duration : 20 Years Project Structure Timeline • Launch Date : September 2008 • Project Awarding date : September 2009 • Operation date: December 2011 SP to finance, design, build, equip, furnish, maintain, provide non clinical services & transfer ownership to Government at contract end. 19 Ministry of Finance PPP Central Unit Health Sector General Medical Facilities - 4 Overview • Location: Cairo Governorate • Capacity : 100 Beds Construction of a Rehabilitation Center • Project duration : 20 Years Timeline Project Structure • Launch Date : September 2008 • Project Awarding date : September 2009 • Operation date: December 2011 SP to finance, design, build, equip, furnish, maintain, provide non clinical services & transfer ownership to Government at contract end. 20 Ministry of Finance PPP Central Unit Health Sector General Medical Facilities - 5 Overview • Location: Alexandria Governorate • Capacity : 100 Beds Construction of Oncology Center • Project duration : 20 Years Project Structure Timeline • Launch Date : December 2008 • Project Awarding date : December 2009 • Operation date: December 2011 SP to finance, design, build, equip, furnish, maintain, provide non clinical services & transfer ownership to Government at contract end. 21 Ministry of Finance PPP Central Unit Utilities Sector Wastewater Treatment Plant - 1 Overview • Location: New Cairo • Capacity : 250,000 m3/day • Project duration : 25 Years Project Structure Timeline • Launch Date : October 2008 • Project Awarding date : September 2009 SP to finance, design, build, operate, maintain plant & transfer ownership to Government at contract end. • Operation date : December 2011 22 Ministry of Finance PPP Central Unit Utilities Sector Wastewater Treatment Plant - 2 Overview • Location: Abo Rawash - Giza Expansion of a waste water treatment plant in Giza Governorate to raise capacity up to 2,000,000 • Capacity : 800,000 m3/day • Project duration : 25 Years m3/day Timeline Project Structure • Launch Date : December 2008 • Project Awarding date : September 2009 • Plant Operation date: December 2011 SP to finance, design, build, operate, maintain plant & transfer ownership to Government at contract end. 23 Ministry of Finance PPP Central Unit Utilities Sector Wastewater Treatment Plant - 3 Overview • Location: Gabal Asfar - Cairo 3rd phase expansion of a wastewater treatment plant with capacity of 500,000 m3/day to raise capacity up to approx. 3,000,000 m3/day • Capacity : 500,000 m3/day • Project duration : 25 Years Timeline Project Structure • Launch Date : January 2009 • Project Awarding date : September 2009 • Plant Operation date: September 2012 SP to finance, design, build, operate, maintain plant & transfer ownership to Government at contract end. 24 Ministry of Finance PPP Central Unit Utilities Sector Wastewater Treatment Plant - 4 Overview • Location: Helwan • Capacity : 500,000 m3/day • Project duration : 25 Years Project Structure Timeline • Launch Date : January 2009 • Project Awarding date : September 2009 SP to finance, design, build, operate, maintain plant & transfer ownership to Government at contract end. • Plant Operation date: September 2012 25 Ministry of Finance PPP Central Unit Utilities Sector Wastewater Treatment Plant - 5 Overview • Location: 6th October city - Giza • Capacity : 450,000 m3/day • Project duration : 25 Years Project Structure Timeline • Launch Date : October 2008 SP to finance, design, build, operate, maintain plant & transfer ownership to Government at contract end. • Project Awarding date : April 2009 • Plant Operation date: April 2012 26 Ministry of Finance PPP Central Unit Utilities Sector Wastewater Treatment Plant - 6 Overview • Location: Nahia - Giza • Capacity : 200,000 m3/day • Project duration : 25 Years Project Structure Timeline • Launch Date : October 2008 SP to finance, design, build, operate, maintain plant & transfer ownership to Government at contract end. • Project Awarding date : April 2009 • Plant Operation date: April 2012 27 Ministry of Finance PPP Central Unit Transport Sector Cairo / Alexandria free road Port Said / Matrouh free road Overview • Length : Cairo / Alex 162 kms Link to Coastal Road 25 kms Alex / Matrouh 280 kms Port Said / Alex 285 kms • Description: Connection of all of Egypt’s Mediterranean Ports • Project duration : 20 Years Timeline • Launch Date : June 2008 • Project Awarding date : January 2009 Project is to build & upgrade existing roads and transfer to free roads Project Structure SP to finance, design, build, operate & maintain road & transfer ownership to Government at contract end. • Project Operation date: June 2012 28 Ministry of Finance PPP Central Unit Transport Sector Railway Project -1 Overview • Location: Cairo / 10th of Ramadan City • Length: 77 km • Description: Double track line • Project duration : 20 Years Timeline The Project is to Double the current line from Ain Shams to El- Roubaky (45 km) & Build a new line from ElRoubaky to 10th of Ramadan City (32 km) Project Structure • Launch Date : August 2008 • Project Awarding date : January 2010 Ministry of Finance SP to finance, Upgrade existing tracks & stations, Construct new tracks & stations, Operate, Maintain & transfer ownership to Government at contract end. PPP Central Unit 29 Transport Sector Railway Project - 2 Overview • Location: Alexandria / Borg El Arab • Length: 50 km • Description: Double track line • Project duration : 20 Years The Project is to Double the current line from Alexandria to Borg El-Arab (50 km) Project Structure Timeline Under Due-Diligence SP to finance, Upgrade existing tracks & stations, Construct new tracks & stations, Operate, Maintain & transfer of ownership to Government at contract end. 30 Ministry of Finance PPP Central Unit Transport Sector Maritime Projects Overview •Description: Investment opportunities include: • New container terminals Location • Multi purpose terminals • Sokhna, Damietta • Liquid bulk terminals • Alexandria & Dekhela • General cargo terminals • Port Said – East Ports • Vessels bunkering • Tugging and marine services • Stevedoring • Value added activities and services Timeline Under Due-Diligence • Shipyard, Ship repair 31 Ministry of Finance PPP Central Unit Transport Sector River Transport Project - 1 CAI / Damitte 240 km. CAI / Alex. 220 km. Overview CAI / Aswan 960 km. •Description: Developing river transportation fleet Aswan / Wadi Halfa 350 km. • 4 main routes: •Cairo / Alexandria 220 km •Cairo / Damietta 240 km •Cairo / Aswan 960 km •Aswan / Wadi Halfa 350 km These routes multiple creates development opportunities, commercial centers, & services added value services & also the fleet Timeline could serve commercial Under Due-Diligence transportation to Sudan. 32 Ministry of Finance PPP Central Unit Transport Sector River Transport Project - 2 •Description: Developing new river ports terminals • 7 main ports: •Upper Egypt •Sohag River Port •Assiut River Port •El Tebeen River Port •Kena River Port •Delta •El Nahda River Port •El Nahda Port Extension •Meat Ghamr River Port Timeline Under Due-Diligence 33 Ministry of Finance PPP Central Unit Thank You Contact Details: PPP Central Unit Ministry of Finance Tel: +202 23421283 +202 23421284 Fax: +202 23421283 / 84 ext. 6152 e-mail: pppcentralunit@mof.gov.eg Web: pppcentralunit.mof.gov.eg 34 Ministry of Finance PPP Central Unit