802.16 Project Planning Committee (PPC): Session #67 Closing Plenary Report
IEEE 802.16 Presentation Submission Template (Rev. 9)
Document Number:
IEEE 802.16ppc-10/0005r1
Date Submitted:
2010-05-13
Source:
Jose Puthenkulam E -mail: jose.p.puthenkulam@intel.com
Project Planning Committee Chair
Venue:
Bangalore, India
Base Contribution:
None
Purpose:
802.16 Project Planning Committee Session #67 Closing Plenary Report of activities
Notice:
This document does not represent the agreed views of the IEEE 802.16 Working Group or any of its subgroups . It represents only the views of the participants listed in the “Source(s)” field above. It is offered as a basis for discussion. It is not binding on the contributor(s), who reserve(s) the right to add, amend or withdraw material contained herein.
Release:
The contributor grants a free, irrevocable license to the IEEE to incorporate material contained in this contribution, and any modifications thereof, in the creation of an IEEE Standards publication; to copyright in the IEEE’s name any IEEE Standards publication even though it may include portions of this contribution; and at the
IEEE’s sole discretion to permit others to reproduce in whole or in part the resulting IEEE Standards publication. The contributor also acknowledges and accepts that this contribution may be made public by IEEE 802.16.
Patent Policy:
The contributor is familiar with the IEEE-SA Patent Policy and Procedures:
< http://standards.ieee.org/guides/bylaws/sect6-7.html#6 > and < http://standards.ieee.org/guides/opman/sect6.html#6.3
>.
Further information is located at < http://standards.ieee.org/board/pat/pat-material.html
> and < http://standards.ieee.org/board/pat >.
4/11/2020 2
• PPC Meeting Room was Sigma II/III
• Timeslots and Agenda this week:
– Tue: AM1 : 9-11AM; AM2 : 11:15AM-1PM
• Comment resolution on M2M Study Report and M2M PAR & 5C
• Future Project Study Items
– Wed: AM1 : 9-11AM;
• Comment resolution on M2M Study Report and M2M PAR & 5C
• Future Project Study Items
– Wed: AM2 : 11:15AM-1PM
• Joint session with GRIDMAN
• Discuss any PAR issues
– Thu: AM1 : 9-11AM; AM2 : 11:15AM-1PM
• Finalization of M2M Study Report
• Finalization of M2M PAR & 5C for WG Approval
• Finalization of Plans for future Project Study items
– Hierarchical Networks, Coexistence with other legacy Wireless systems
4/11/2020 3
– C802.16ppc-10/0033 – Study Report comments
– C8021.6ppc-10/0032 – PAR & 5C comments
– C802.16ppc-10/0034 – Recommendations for new study item
– C802.16ppc-10/0035 – New study item for Coexistence enhancement for legacy of other wireless technologie
4/11/2020 4
• Discussion on the GRIDMAN PAR and M2M PAR Potential
Overlap Concerns
– Two-way Group calling
– Protocol for Group Management
– Priority Access
– Data Services (short packet and normal packet)
– MAC Protocol Operation Overlap (For example: faster connection setup time/maintenance, )
– M2M applications in emergency situations
– Operational portion (ex: provision of services) of the GRIDMAN based reconfigured network
• Intent to address the overlap concerns in the respective System requirement documents and ensure close co-ordination
4/11/2020 5
4/11/2020
Study Items Description Project Target TimeLine
M2M
First Phase: New requirements for massive number of devices to be connected over 16
Networks.
Later Phase: More Advanced M2M capabilities
Study Item started: Mar 2010
WG PAR Approval: May 2010
EC PAR Approval: Jul 2010
TG Start: Sep 2010
Std Completion: Jul, 2012
TBD
Hierarchical Networks
Same RAT: Extensions to Advanced Air
Interface (802.16m) for multi-tier deployments
802 Multi-RAT: Advanced network topologies offering high capacity at low cost
Client Collaboration: Co-operation amongst clients
Study item started: May 2010
WG PAR Approval: Sep 2010
EC PAR Approval: Nov 2010
TG Start: Jan 2011
Std Completion: TBD
Co-existence with non-
802 TDD systems Co-existence with non-802 TDD systems.
Example: TDS-CDMA, TD-LTE
Study item started: May 2010
WG PAR Approval: Sep 2010
EC PAR Approval: Nov 2010
TG Start: Jan 2011
Std Completion: TBD
6
Study Items Description Project Target TimeLine
Enhanced QOE
Improved quality of experience for mobile internet applications
Ultra High Speed Networks
(>1-5Gbps)
Advanced MIMO, Higher Order Modulation,
Higher Bandwidths, Multicarrier
Green RAN Energy savings at Client and Network
WG PAR Approval: 2011
EC PAR Approval: TBD
TG Start: TBD
Std Completion: TBD
WG PAR Approval: 2011
EC PAR Approval: TBD
TG Start: TBD
Std Completion: TBD
WG PAR Approval: 2011
EC PAR Approval: TBD
TG Start: TBD
Std Completion: TBD
4/11/2020 7
• Motion 1: To Approve the 802.16ppc-10/0002r7 as the M2M Study Report
– Moved: Kerstin Johnsson
– Second: Vibhor Julka
– Approved with Unanimous Consent
• Motion 2: To Approve the 802.16ppc-10/0003r4 as the M2M PAR and 5C and submit it for WG approval
– Moved: Kerstin Johnsson
– Second: HanGyu Cho
– Approved with Unanimous consent
• Motion 3: To Approve initiation of study reports for Hierarchical Networks and Co-existence with non-802 TDD systems and issue call for contributions towards the July meeting
– Moved: Shilpa Talwar
– Seconds: Huiying Fang
– Approved with Unanimous consent
4/11/2020 8
– Moved:
– Second:
4/11/2020 9