Unit Strategic Plan 2012/2013 Outcome Assessment Report

advertisement
Unit Strategic Plan
2012/2013
Outcome Assessment Report
Geological Sciences Department
Page 1
AY 2012/2013
Unit Strategic Planning Report
Unit: ____Geological Sciences Department__________
Reporting Authority: _____Dr. Carey Gazis, Chair_____________
Date: _______November 1, 2013__________
A: Please complete the column titled “Outcome Assessment” on your own Unit Strategic Plan. Complete with as much detail as
you can provide.
Strategic Plan for 2012 with Outcome Assessment is attached.
B. Please summarize each of the University’s Five Core Themes from your Unit Strategic Plan Outcome Assessment report.
University Core Theme I (Teaching and Learning) – The outcomes in this area are related to maintaining our programs. The outcome
assessment provides baseline data in enrollments and faculty scholarship. Faculty activity in scholarship is considered to be crucial
for quality instruction. Although our enrollment and scholarship appear strong, our department had to supplement the Goods and
Services budget with ≈$16,000 from our indirect returns from grants.
University Core Theme 2 (Inclusiveness and Diversity) – We do not currently have departmental outcomes in this area in our
Strategic Plan. We will expand into this theme once we have a better idea of the baseline data in the other themes.
University Core Theme 3 (Scholarship and Creative Expression) – Our outcome assessments in this area relate to resource needs for
scholarship, including graduate assistants, a Laboratory/Instrument Technician, and a new Science facility. The assessments indicate
that we are losing quality students to competing programs. We think that this is because we are very late in getting our offers out
Page 2
and the graduate stipends are very low. In addition, we now have evidence of our need for a Laboratory/Instrument Technician: at
least two of our instruments are not operational for more than 20% of the time that we are attempting to operate them. In addition,
faculty members have spent many hours repairing and maintaining instruments. The Science facility, Science Phase II, has been
funded. In our outcome assessment, we have baseline data on proposals for comparison to our productivity once we have occupied
the new building.
University Core Theme 4 (Public Service and Community Engagement) – We were not able to obtain any quantitative data to assess
our outcome in this area.
University Core Theme 5 (Resource Development and Stewardship) – The outcomes in this area relate to two resource needs: a
Laboratory/Instrument Technician and a new Science facility. The outcome assessment related to the Laboratory/Instrument
Technician is the same as that described in University Core Theme 3. Science Phase II has been funded and will be occupied in less
than three years.
Toward which theme(s) did you make progress, and how are students benefitting from this?
We made the most progress towards Themes 1, 3, and 5 because of the funding of Science Phase II. The students are not yet
benefitting from this but will once the building is occupied.
Which theme(s) deserve special attention next year?
Themes 1 and 4 deserve special attention next year. Related to Theme 1, Teaching and Learning, we would like to examine our
programs, particularly our B.A. in Geology, and improve them so that students are better prepared for the work force or graduate
school. In the area of Theme 4, Public Service and Community Engagement, we will work on supplementing the Science Phase II
FF&E budget so that the new building best serves our needs in terms of educational equipment and displays and classrooms.
C. How do you intend to utilize the data gathered this year to assist you in developing stronger programs?
We will use the enrollment data we have been given combined with our internal tracking of students to get a better picture of what
the longer term trends are in our majors. Based on these trends, we will continue to try to increase enrollment in our programs,
particularly in the B.A. Geology, as much as our classes and staffing will allow. Data on research productivity of faculty (peerPage 3
reviewed publications and abstracts) will serve as baseline data and ultimately will help define our expectations for productivity of
the department as a whole. Data related to our need for additional support staff will be gathered and presented to the
administration.
D. Based on your learning from this first year report, what parts of your strategic plan will you modify, add to, or omit for next
year?
Strategic Plan for 2013 with explanation letter is attached.
Page 4
UNIT STRATEGIC PLAN – GEOLOGICAL SCIENCES DEPARTMENT 2012
UNIVERSITY CORE THEME: 1. TEACHING AND LEARNING
UNIVERSITY OBJECTIVE 1.1 Enhance student success by continually improving the curricular, co-curricular, and extracurricular programs.
Unit Outcomes
Indicators
Expected
Responsible
Key Strategies/
Budget/Resource
Outcome Assessment
Performance
Reporting Unit
Initiatives
Analysis
Level
(Criterion)
Maintain a
department profile
that supports quality
instruction in the
core disciplines of
Geological Sciences
with faculty who are
active in scholarship
Obtain adequate
and stable resource
base to support
classes and basic
operation of the
department
Inquiry-based
projects and
mentored research:
Increase
opportunities for
class and individual
projects that rely on
instrumentation for
data
SEOI scores
Enrollment in
majors
Peer-reviewed
publications and
presentation of
abstracts at
professional
meetings
Dept average
within one standard
deviation of college
average (if below,
can be higher if
above average)
Enrollment steady
to increasing
CWU
Assessment
Department
Geology
department
faculty (activity
reports)
Professional
development in
teaching
Reassigned
workload for funded
grants
Steady to
increasing numbers
for department as a
whole
Amount of indirect
funds and summer
profits used to
support classes and
operation of
department
Amount of time that
each instrument is
not working
$0, Department
operations should
be supported
entirely by goods
and services
budget
Less than 10% of
the time
Percentage of
instrumentationdependent student
projects that have
complete intended
data set
95% or more
Geology
department
secretary
Maintain existing
level of support
including staff and
faculty
Buyout of classes
with grant funding
Use of indirect
returns towards
adjunct faculty
Goods and
Services budget
restored and
brought to $25,000
Department
faculty:
Instrument log
books
Regular
maintenance of
instruments and
performance tests
Geology
department
faculty (mentors
for projects)
Consistent training
of students on
standard operating
procedures for
instruments
New Support Staff
Position:
Laboratory/Instrum
ent Technician for
Geological
Sciences
SEOI baseline data yet
available
Enrollments for 2012-3:
Undergraduate – 74
Post-bac – 1
Graduate – 27
Faculty scholarship: From
Sept. 16, 2012 to Sept 15,
2013 faculty in our
department produced the
following:
• 12 peer-reviewed
publications
• 52 abstracts for
professional meetings
Goods and Services budget
has not increased. In 20122013, ≈$16,000 from the
department indirect account
was used to maintain basic
operation of the department
IRMS ≈30%
ICP-MS ≈20%
Data is hard to collect. At
least one M.S. student (in
REM program) was delayed
in his progress due to a
vacuum leak in the IRMS
7/24/16, p. 5
UNIVERSITY OBJECTIVE 1.1 continued
Employ modern
Percentage of class
science teaching
time in which faculty
methods across the
use alternative
curriculum
modes of teaching
Improve accessibility
of faculty to students
Percentage of time
when classroom is in
same building as
faculty office
Increasing
Geology
department
Professional
development in
teaching
Classroom layout
and flexibility of
space
Science Phase II
facility
From faculty estimates, we
spend ≈47% of our class
time lecturing
Science Phase II has been
funded. We expect that our
percentage of class time
spent lecturing will go down
once we occupy that
building because of
improved teaching space
and equipment
95-100%
Geology
department
secretary
Consolidate
department faculty,
staff, grad students,
and classrooms in
single building
Science Phase II
facility
In 2012-3, 50% of our
classes were not taught
classrooms in the same
building as the instructors
office. Science Phase II has
been funded. We expect to
see department reunited
and teaching in same
building as their offices in
2015
UNIVERSITY CORE THEME: 3. SCHOLARSHIP AND CREATIVE EXPRESSION
UNIVERSITY OBJECTIVE 3.1 Increase the emphasis on and the opportunities for students, faculty and staff to participate in research, scholarship, and
creative expression activities.
Unit Outcomes
Indicators
Expected
Responsible
Key Strategies/
Budget/Resource
Outcome Assessment
Performance
Reporting
Initiatives
Analysis
Level
Unit
(Criterion)
Strengthen
graduate program
through recruiting
and consistent
availability of
competitive
stipends
Average number
of offers made per
assistantship
Timeliness of
assistantship
offers
Less than 1.5
First set of offers
made within two
weeks of
application
deadline
Geology
Graduate
Program
Coordinator
Recruiting at
national meetings
Fifteen graduate
assistantships
including tuition
waivers in base
budget
eleven offers were made for six
assistantships
11/6 = 1.83
This is typical to good compared to
recent years
Increased graduate
stipends to at least
Due to administrative turnover in the
graduate office and uncertainty about
7/24/16, p. 6
$15,000
Improve
productivity of
instrumentation in
Geological
Sciences
Amount of time
that each
instrument is not
working
Less than 10%
of the time
Department
faculty:
Instrument log
books
Reduce faculty
time spent on
instrument
maintenance and
repair
Amount of time
spent repairing
and maintaining
instruments by
tenure-track
faculty
Research
proposals that
represent new
methods of data
collection at CWU
and/or new
collaborations
Less than 2
hours per week
Geology
department:
instrument log
books
Increasing
number
Department
faculty: activity
reports
Expanded
research
capabilities
through improved
facilities and new
instrumentation
Regular
maintenance of
instruments and
performance tests
Hiring of new
support staff
Hiring of new
instrument support
staff in Geological
Sciences
New facilities (e.g.
ice core lab) and
instrumentation
(e.g. SEM)
New Support Staff
Position:
Laboratory/Instrum
ent Technician for
Geological
Sciences
New Support Staff
Position:
Laboratory/Instrum
ent Technician for
Geological
Sciences
Science Phase II
facility
graduate assistantships, 2013 was a
particularly bad year for getting out
timely assistantship offers. The number
of assistantships available to each
department were not known until over
a month after the application deadline.
IRMS ≈30%
ICP-MS ≈20%
Based on a survey of faculty, we
estimate that as a whole, we have
spent 235 hours maintaining or
repairing instruments, well over two
hours for week for the faculty involved.
Members of the department submitted
eight research proposals that represent
new methods of data collection and/or
new collaborations. We expect this
number to go up when we move into
Science Phase II
UNIVERSITY OBJECTIVE 3.2 Increase the external funding received for research, scholarship, and creative expression by faculty, staff, and students.
Unit Outcomes
Obtain staff needed
to sustain a high
level of grant-writing
and research
activity, including
support for the new
analytical
geochemistry
facilities.
Indicators
Amount of time
spent repairing and
maintaining
instruments by
tenure-track faculty
Expected
Performance
Level
(Criterion)
Less than 2 hours
per week
Responsible
Reporting Unit
Geology
department:
instrument log
books
Key Strategies/
Initiatives
Budget/Resource
Analysis
Outcome Assessment
Hiring of new
instrument support
staff in Geological
Sciences
New Support Staff
Position:
Laboratory/Instrum
ent Technician for
Geological
Sciences
Based on a survey of
faculty, we estimate that as
a whole, we have spent 235
hours maintaining or
repairing instruments, well
over two hours for week for
the faculty involved.
7/24/16, p. 7
Expanded research
capabilities through
improved facilities
and new
instrumentation
Research proposals
that represent new
methods of data
collection at CWU
and/or new
collaborations
Increasing number
Department
faculty: activity
reports
New facilities (e.g.
ice core lab) and
instrumentation (e.g.
SEM)
Science Phase II
facility
Members of the department
submitted eight research
proposals that represent
new methods of data
collection and/or new
collaborations. We expect
this number to go up when
we move into Science
Phase II
UNIVERSITY CORE THEME: 4. PUBLIC SERVICE AND COMMUNITY ENGAGEMENT
UNIVERSITY OBJECTIVE 4.1 Enhance the commitment and the level of cooperation between the university and external communities.
Unit Outcomes
Indicators
Expected
Responsible
Key Strategies/
Budget/Resource
Outcome Assessment
Performance
Reporting Unit
Initiatives
Analysis
Level
(Criterion)
Increase and
improve geological
and environmental
science outreach
activities in K-12
schools and
community
Number of K-12
students attending
on-campus
activities
Increasing number
over the course of
five years
Geological Sciences
and CESME:
tracking of oncampus visits
K-12 outreach
events (e.g.
Expanding Your
Horizons) in
collaboration with
CESME
Science Phase II
facility
Outreach events:
Expanding Your Horizons,
Science is Central
Number of K-12 students
not available
UNIVERSITY CORE THEME: 5. RESOURCE DEVELOPMENT & STEWARDSHIP
UNIVERSITY OBJECTIVE 5.3 Ensure the University has human resources necessary to accomplish all university objectives.
Unit Outcomes
Indicators
Expected
Responsible
Key Strategies/
Budget/Resource
Performance
Reporting Unit
Initiatives
Analysis
Level
(Criterion)
Obtain staff to
support instruction
and research that
involves
instrumentation
Amount of time
spent repairing and
maintaining
instruments by
tenure-track faculty
Less than 2 hours
per week
Geology
department:
instrument log books
Hiring of new
instrument
support staff in
Geological
Sciences
Outcome Assessment
New Support Staff
Position:
Laboratory/Instrum
ent Technician for
Geological
Sciences
Based on a survey of
faculty, we estimate that as
a whole, we have spent 235
hours maintaining or
repairing instruments, well
over two hours for week for
the faculty involved.
UNIVERSITY OBJECTIVE 5.4 Provide the facility and technology infrastructure and services appropriate to meet the university objectives, while
maximizing sustainability and stewardship.
7/24/16, p. 8
Unit Outcomes
Improve facilities in
support of
scholarship and
instruction
Indicators
Years until new
facility is built
Expected
Performance
Level
(Criterion)
Three
Responsible
Reporting Unit
Facilities
Management
Key Strategies/
Initiatives
Budget/Resource
Analysis
Advocate for
Science Phase II
in state
legislature
Science Phase II
facility
Outcome Assessment
Science Phase II has been
funded and should be built
within three years.
Reunite department
faculty, staff, and
students in a single
building.
7/24/16, p. 9
November 1, 2013
To:
Dr. Kirk Johnson, Dean COTS
From:
Dr. Carey Gazis
Chair, Department of Geological Sciences
Subject:
Strategic Plan for Geological Sciences
Attached is the Unit Strategic Plan for the Department of Geological Sciences. Included is an assessment
of the 2012 Strategic Plan and a modified 2013 Strategic Plan (with differences from the 2012 plan
shown in bold text). The 2013 Strategic Plan is similar to the 2012 plan with the following changes
(colors of budget/resource items are the same as in table):
1. No reduction of current resources, including faculty and staff positions – Same as 2012 Plan. We
were told that our plans could assume that the current resources are available. This strategic plan
includes a row that explicitly states this assumption.
2. Restore and increase department goods and service budget – Same as 2012 Plan, but amount was
changed to reflect what was spent this year on basic goods and services.
3. Lab/instrument technician dedicated to our department – Same as 2012 Plan.
4. New instructional technician dedicated to our department – A new outcome was added to
University Objective 5.3 (Human Resources) to reflect this need. The new support staff position would
serve two purposes: 1) to help our department transition to Science Phase II by archiving our collections,
helping to research and order teaching equipment and supplies, and preparing and moving teaching
equipment and collections; 2) to support our upper-level curriculum by maintaining teaching collections
and assisting with logistics for field trips.
Department of Geological Sciences
(509) 963-2820 voice; (509) 963-2821 fax; cgazis@geology.cwu.edu
400 E. 8th Avenue • Ellensburg, WA 98926-7418 • 509.963-2701 • FAX 509.963-1047
EEO/AA/TITLE IX INSTITUTION • TTD 509.963-3323
5. Increased number of graduate assistantships and higher graduate student stipends – Same as 2012
Plan
6. Science Phase II FF&E budget – Now that Science Phase II has been funded by the state, our focus has
shifted from obtaining funding for Science Phase II to supplementing funding in order to increase the
FF&E budget. Because of the level of funding which was designated, it is likely that we will not have
adequate funds to obtain all of our desired equipment and educational displays. We plan to work with
the CWU Development Office and write external grants in order to supplement the state FF&E budget in
order to maximize the benefits of the new building.
7. Three more new outcomes were added: one to reflect efforts we are making to re-envision our B.A.
Geology degree; a second related to improving our General Education offerings; and a third to articulate
further strategies that we are using to increase opportunities for research. In addition, one outcome
(improve accessibility of faculty to students) was removed. This outcome has been addressed by the
funding of Science Phase II because faculty offices will be in the same building as the majority of our
classes.
8. A number of indicators and strategies have been added to the 2013 Plan.
7/24/16, p. 11
UNIT STRATEGIC PLAN – GEOLOGICAL SCIENCES DEPARTMENT 2013
UNIVERSITY CORE THEME: 1. TEACHING AND LEARNING
UNIVERSITY OBJECTIVE 1.1 Enhance student success by continually improving the curricular, co-curricular, and extracurricular programs.
Unit Outcomes
Indicators
Expected Performance
Responsible
Key Strategies/
Budget/Resource
Level
Reporting Unit
Initiatives
Analysis
(Criterion)
Maintain a department
profile that supports
quality instruction in
the core disciplines of
Geological Sciences
with faculty who are
active in scholarship
Obtain adequate and
stable resource base
to support classes and
basic operation of the
department
Re-envision Geology
B.A. major so that it
serves students with
an interest in careers
in earth science
communication
Increase availability
of General Education
offerings, particularly
courses which are in
high demand
SEOI scores
Enrollment, graduation
rates in majors
Peer-reviewed
publications, presentation
of abstracts at
professional meetings and
external grant proposals
Amount of indirect funds
and summer profits used
to support classes and
operation of department
Enrollment, graduation
rate in Geology B.A.
FTES in General
Education courses
Dept average within one
standard deviation of
college average (if
below, can be higher if
above average)
CWU Assessment
Department
increasing
Maintain existing level of
support including staff and
faculty
Curriculum retreat
Institutional
Research
Enrollment steady to
increasing
Steady to increasing
numbers for department
as a whole
$0, Department
operations should be
supported entirely by
goods and services
budget
Increasing enrollment
reaching total of
approximately 10 per
year
Professional development
in teaching
Geology
department faculty
(activity reports)
Reassigned workload for
funded grants
Academic workload in
grants to buy out
classes
Geology
department
secretary
Institutional
Research
Institutional
Research
Maintain level of research
funding through external
grants
Goods and Services budget
restored and brought to
$30,000
Curricular changes to
emphasize Earth
Systems approach more
Recruiting students who
express an interest in
science communication
Increase on-line
offerings, particularly of
high-demand courses
such as GEOL 302
Additional graduate
teaching assistant so that
class sizes for online
courses can be increased
Allign courses with new
Gen Ed outcomes
Work with student
advising to determine
best timing of Gen Ed
offerings
7/24/16, p. 12
UNIVERSITY OBJECTIVE 1.1 continued
Unit Outcomes
Indicators
Inquiry-based projects
and mentored
research: Increase
opportunities for class
and individual projects
that rely on
instrumentation for
data
Amount of time that each
instrument is not working
Employ modern
science teaching
methods across the
curriculum
Percentage of class time
in which faculty use
alternative modes of
teaching
Percentage of
instrumentation-dependent
student projects that have
complete intended data
set
Expected Performance
Level
(Criterion)
Less than 10% of the
time
Responsible
Reporting Unit
Department faculty:
Instrument log
books
95% or more
Increasing
Geology
department faculty
(mentors for
projects)
Geology
department
Key Strategies/
Initiatives
Regular maintenance of
instruments and
performance tests
Budget/Resource
Analysis
New Support Staff Position:
Laboratory/Instrument
Technician for Geological
Sciences
Consistent training of
students on standard
operating procedures for
instruments
Professional development
in teaching
Classroom layout and
flexibility of space
Science Phase II FF&E,
classroom furniture and
teaching technology,
instrumentation, and
educational displays
UNIVERSITY CORE THEME: 3. SCHOLARSHIP AND CREATIVE EXPRESSION
UNIVERSITY OBJECTIVE 3.1 Increase the emphasis on and the opportunities for students, faculty and staff to participate in research, scholarship, and
creative expression activities.
Unit Outcomes
Indicators
Expected Performance
Responsible
Key Strategies/
Budget/Resource
Level
Reporting Unit
Initiatives
Analysis
(Criterion)
Strengthen graduate
program through
recruiting and
consistent availability
of competitive stipends
Average number of offers
made per assistantship
Less than 1.5
Timeliness of
assistantship offers
Improve productivity of
instrumentation in
Geological Sciences
Amount of time that each
instrument is not working
First set of offers made
within two weeks of
application deadline
Less than 10% of the
time
Reduce faculty time
spent on instrument
maintenance and
repair
Amount of time spent
repairing and maintaining
instruments by tenuretrack faculty
Less than 2 hours per
week
Geology Graduate
Program
Coordinator
Recruiting at national
meetings
Department faculty:
Instrument log
books
Regular maintenance of
instruments and
performance tests
Hiring of new support staff
Geology
department:
instrument log
books
Hiring of new instrument
support staff in Geological
Sciences
Fifteen graduate
assistantships including
tuition waivers in base
budget
Increased graduate
stipends to at least $15,000
New Support Staff Position:
Laboratory/Instrument
Technician for Geological
Sciences
New Support Staff Position:
Laboratory/Instrument
Technician for Geological
Sciences
UNIVERSITY OBJECTIVE 3.1 continued
7/24/16, p. 13
Unit Outcomes
Indicators
Expected Performance
Level
(Criterion)
Responsible
Reporting Unit
Expanded research
capabilities through
improved facilities and
new instrumentation
Research proposals that
represent new methods of
data collection at CWU
and/or new collaborations
Increasing number
Department
faculty: activity
reports
Increase
opportunities for
student research in
Geological Sciences
Number of
undergraduate and
graduate research
projects per year
Increasing number
Department
faculty: activity
reports
Key Strategies/ Initiatives
New facilities (e.g. ice core
lab) and instrumentation
(e.g. SEM)
Work with development
office to leverage
additional funding
New facilities (e.g. ice core
lab) and instrumentation
(e.g. SEM)
Budget/Resource
Analysis
Science Phase II FF&E,
laboratory furniture and
instrumentation
Science Phase II FF&E,
laboratory furniture and
instrumentation
Use of indirect funds and
university student grants
Academic year salary in
grants to buy out classes
UNIVERSITY OBJECTIVE 3.2 Increase the external funding received for research, scholarship, and creative expression by faculty, staff, and students.
Unit Outcomes
Obtain staff needed to
sustain a high level of
grant-writing and
research activity,
including support for
the new analytical
geochemistry facilities.
Expanded research
capabilities through
improved facilities and
new instrumentation
Indicators
Expected Performance
Level
(Criterion)
Responsible
Reporting Unit
Key Strategies/
Initiatives
Budget/Resource
Analysis
Amount of time spent
repairing and maintaining
instruments by tenuretrack faculty
Less than 2 hours per
week
Geology
department:
instrument log
books
Hiring of new instrument
support staff in Geological
Sciences
New Support Staff Position:
Laboratory/Instrument
Technician for Geological
Sciences
Research proposals that
represent new methods of
data collection at CWU
and/or new collaborations
Increasing number
Department faculty:
activity reports
New facilities (e.g. ice core
lab) and instrumentation
(e.g. SEM)
Work with development
office to leverage
additional funding for
Science Phase II
Grant-writing to leverage
matching funds for
instruments
Science Phase II FF&E,
laboratory furniture and
instrumentation
7/24/16, p. 14
UNIVERSITY CORE THEME: 4. PUBLIC SERVICE AND COMMUNITY ENGAGEMENT
UNIVERSITY OBJECTIVE 4.1 Enhance the commitment and the level of cooperation between the university and external communities.
Unit Outcomes
Indicators
Expected Performance
Responsible
Key Strategies/
Budget/Resource
Level
Reporting Unit
Initiatives
Analysis
(Criterion)
Increase and improve
geological and
environmental science
outreach activities in
K-12 schools and
community
Number of K-12 students
attending on-campus
activities
Increasing number over
the course of five years
Geological
Sciences and
CESME: tracking of
on-campus visits
K-12 outreach events (e.g.
Expanding Your Horizons)
in collaboration with
CESME
CESME Teaching
Assistant
Classrooms and
educational displays in
Science Phase II facility
Maintain teaching
assistantship for CESME
UNIVERSITY CORE THEME: 5. RESOURCE DEVELOPMENT & STEWARDSHIP
UNIVERSITY OBJECTIVE 5.3 Ensure the University has human resources necessary to accomplish all university objectives.
Unit Outcomes
Indicators
Expected Performance
Responsible
Key Strategies/ Initiatives
Level
Reporting Unit
(Criterion)
Budget/Resource
Analysis
Obtain staff to support
Amount of time spent
Less than 2 hours per
Geology
Hiring of new instrument
New Support Staff Position:
instruction and research repairing and maintaining week
department:
support staff in Geological
Laboratory/Instrument
that involves
instruments by tenureinstrument log
Sciences
Technician for Geological
instrumentation
track faculty
books
Sciences
Obtain staff to provide Amount of time spent
Less than 1 hour per
Geology
Hiring of new instructional
New Support Staff
support for
by tenure-track faculty
week
department
support staff in Geological
Position: Instructional
instructional
archiving collections
faculty
Sciences
Technician for Geological
collections and
and researching and
Sciences
supplies and to assist ordering educational
in transition to
supplies
Science Phase II
UNIVERSITY OBJECTIVE 5.4 Provide the facility and technology infrastructure and services appropriate to meet the university objectives, while
maximizing sustainability and stewardship.
Unit Outcomes
Indicators
Expected Performance
Responsible
Key Strategies/ Initiatives
Budget/Resource
Level
Reporting
Analysis
(Criterion)
Unit
Improve facilities in support
of scholarship and
instruction
Reunite department in a
single building.
Years until new
facility is built
Two
Facilities
Management
Work with development office
to leverage additional
funding for Science Phase II
Grant-writing to obtain
matching funds
Science Phase II FF&E,
laboratory furniture,
instrumentation,
educational displays and
equipment
7/24/16, p. 15
Download