Coherent X-ray Imaging WBS 1.3 CXI Component Status, Cost and Schedule Paul Montanez CXI Lead Engineer/CAM June 3, 2009 CXI Final Instrument Design Review June 3, 2009 1 1 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Outline WBS 1.3 Scope Early Science/CD-4 Deliverables Progress since CD-2 Status Engineering/Design Status Cost & Schedule Performance Critical Path Milestones Risk Identification & Mitigation Safety Summary CXI Final Instrument Design Review June 3, 2009 2 2 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Acronyms PRD Physics Requirements Document ESD Engineering Specifications Document SOW Statement of Work ICD Interface Control Document PDR Preliminary Design Review FDR Final Design Review BAC Budget at Completion BCR Baseline Change Request XRT X-ray Transport Tunnel FEH H5 Far Experimental Hall Hutch 5 CXI Final Instrument Design Review June 3, 2009 3 3 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU WBS 1.3 – Early Science/CD-4 Deliverables WBS 1.3.01 1.3.02 1.3.02.02 1.3.03 1.3.03.01 1.3.05 1.3.05.01 1.3.05.01.01 WBS 1.3.01 1.3.02 1.3.02.01 1.3.04 1.3.04.01 1.3.05 1.3.05.01 1.3.05.01.01 Early Science CXI System Integration & Design CXI X-ray Optics CXI KB System (1 micron) CXI Lasers CXI Reference Laser CXI Sample Environment CXI Room Temperature Environment CXI Sample Chamber & Ion TOF CXI 1 Micron Sample Chamber 1.3.05.01.02 CXI Precision Instrument Stand CXI Precision Instrument Stand -- 1 Micron CXI Detector Stage 1.3.06 CXI Hutch Facilities 1.3.06.01 CXI Hutch Specification 1.3.06.02 CXI Utilities & Hutch Equipment 1.3.07 CXI Vacuum System 1.3.07.01 CXI Vacuum Equipment 1.3.07.02 CXI Vacuum Hardware 1.3.07.02.01 CXI Spools & Bellows 1.3.07.02.02 CXI Vacuum Supports 1.3.08 CXI Installation 1.5 Diagnostics and Common Optics 1.5.02.01 Pop-in Profile Monitor 1.5.02.02 Pop-In Intensity Monitor DCO 1.5.02.03 Intensity-Position Monitor 1.5.03.03 Slit System 1.5.03.04 Attenuators / Filters 1.5.03.05 Pulse Picker Controls 1.6 Controls and Data Acquisition LCLS 2.06.05.02 2.06.02.08 Cornell 2D Pixel Array Detector CXI CD-4 CXI System Integration & Design CXI X-ray Optics CXI KB System (0.1 micron) CXI Coherent Imaging Injector CXI Coherent Imaging Injector CXI Sample Environment CXI Room Temperature Environment CXI Sample Chamber & Ion TOF CXI 0.1 Micron Sample Chamber CXI Ion ToF 1.3.05.01.02 CXI Precision Instrument Stand CXI Precision Instrument Stand -- 0.1 Micron 1.3.07 CXI Vacuum System 1.3.07.01 CXI Vacuum Equipment 1.3.07.02 CXI Vacuum Hardware 1.3.07.02.01 CXI Spools & Bellows 1.3.07.02.02 CXI Vacuum Supports 1.3.08 CXI Installation 1.6 Controls and Data Acquisition Early Science: Early Finish – April 2011 CD-4: Early Finish – January 2012 (B/L Early Finish – May 2011) (B/L Early Finish – November 2011) CXI Final Instrument Design Review June 3, 2009 4 4 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Progress Since CD-2 CXI Engineering/Design staff Added 1 Mechanical Engineer & 1 Mechanical Designer – October 2008 Added 2 Mechanical Engineers & 1 Mechanical Designer – March 2009 Added 1 Mechanical Engineer – April 2009 All documentation completed & released PRDs, ESDs, SOW’s, etc. 1µm Kirkpatrick-Baez mirror system Authorization to proceed with advanced procurement Vendor site-visits Mirror system RFP released, proposals received and vendor selection made April 27, 2009 Award in June 2009 Design Reviews Preliminary Design Reviews completed CXI 1µm Sample Chamber & Reference Laser – March 2009 CXI Detector Stage & 1µm Precision Instrument Stand – May 2009 Baseline vibration data obtained in the LCLS Far Experimental Hall Vertical/Horizontal PSD, 1-100Hz Measured near location of 1µm KB system CXI Final Instrument Design Review June 3, 2009 5 5 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Engineering/Design Status CXI Early Science CXI CD-4 Diagnostics/Common Optics Diagnostics & Wavefront Monitor 1 micron Sample Environment 1 micron KB Reference Laser 0.1 micron KB & Sample Environment, Particle Injector and IToF CXI Engineering/Design staff Armin Busse, Kay Fox, Paul Montanez, William Olson, Michael Ramos, Donald Schafer, Nathaniel Stewart CXI Final Instrument Design Review June 3, 2009 6 6 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Engineering/Design Status (2) Documentation CAD system model documentation hierarchy (CAD Drawing Tree/File Structure) released XRT/FEH H5 beamline layout complete with all available models implemented & updated 26 PRDs/ESDs released, 10 SOWs/ICDs released CXI PHYSICS REQUIREMENTS DOCUMENTS (PRD) & ENGINEERING SPECIFICATION DOCUMENTS (ESD) TOPIC AREA PRD DOCUMENT NO. ESD DOCUMENT NO. CXI Instrument Start-up Plan SP-391-001-16 Physics Requirements for the CXI Instrument SP-391-000-19 CXI Instrument ESD SP-391-000-85 CXI 0.1 micron Sample Chamber SP-391-000-20 SP-391-000-67 CXI Reference Laser System SP-391-000-21 SP-391-000-73 CXI 0.1 micron KB System SP-391-000-24 SP-391-000-64 CXI 1 micron KB System SP-391-000-25 SP-391-000-65 CXI Particle Injector System SP-391-000-26 SP-391-000-75 CXI Detector Stage SP-391-000-28 SP-391-000-70 CXI Ion ToF SP-391-000-30 SP-391-000-68 CXI 0.1 micron Precision Instrument Stand SP-391-000-63 SP-391-000-69 CXI 1 micron Sample Chamber SP-391-001-41 SP-391-001-43 CXI 1 micron Sample Precision Instrument Stand SP-391-001-42 SP-391-001-44 Eng Spec for Hutch 5 of the FEH SP-391-001-36 Eng Spec for the CXI of the FEH SP-391-001-37 Eng Spec for the Common Room of the FEH SP-391-001-40 - Hutch Design Reviewed 30%, 60%, 90% & 100% A/E drawings FEH Hutch construction – June thru December 2009 (LCLS) APP and Risk Identification/Registry complete and up-to-date CXI Final Instrument Design Review June 3, 2009 CXI STATEMENTS OF WORK (SOW) & INTERFACE CONTROL DOCUMENTS (ICD) TOPIC AREA SOW DOCUMENT NO. ICD DOCUMENT NO. 1 micron KB System, Mirror Substrates SP-391-001-51 1 micron KB System Mechanics, Mechanical System SP-391-001-52 1 micron KB System, Mirror Coating SP-391-001-53 1 micron KB System, Mirror Metrology SP-391-001-54 0.1 micron KB System, Mirror Substrates SP-391-001-57 0.1 micron KB System Mechanics, Mechanical System SP-391-001-58 0.1 micron KB System, Mirror Coating SP-391-001-59 0.1 micron KB System, Mirror Metrology SP-391-001-60 CXI Detector Stage Design SP-391-001-68 CXI-DCO ICD SP-391-001-56 - 7 7 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Engineering/Design Status (3) CXI 0.1µm KB system (WBS 1.3.02.01) PRD, ESD & SOWs released Procurement included as an “option” for the CXI 1µm KB contract Delivery November 2010 BAC ≈ $1,400K CXI 1µm KB system (WBS 1.3.02.02) PRD, ESD & SOWs released Prime vendor to provide complete and integrated KB system, including: Figured & Polished Substrates Mirror Mechanics/Manipulators Vacuum chamber and support stand MOU for independent metrology/coating of the substrates LLNL likely candidate based on past experience with LCLS OMS mirrors Secured the services of an optics expert to assist with the evaluation of all procurement documents and to participate as a member of the Proposal Evaluation Committee Procurement Activities Advance Procurement Review – October 2008 (required for advanced procurement authorization) Design Review Report TR-391-003-10 “CXI 1 Micron K-B Mirror System Advanced Procurement Technical Review” Vendor site-visits by CXI staff – Q1 FY09 Prequalification of vendors – December 2008/January 2009 Posted on Federal Business Opportunities (FedBizOpps) website RFP sent to vendors – January 2009 Vendor proposals received – 24 March 2009 Proposal Evaluation Committee Meeting – 9 April 2009 Recommend a vendor to the Source Selection Official on April 27th Award in June 2009 Delivery October 2010 Budget at Completion (BAC) ≈ $1,280K ($970,000 in long lead procurement) CXI Final Instrument Design Review June 3, 2009 8 8 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Engineering/Design Status (4) CXI Reference Laser (WBS 1.3.03.1) PRD & ESD released Successful PDR held March 2009 Design Review Report TR-391-003-19-0 Consider Class 2, 1mW, green laser (initially Class 3R, red) Appropriate signage for laser safety Additional interlocks for equipment protection FDR scheduled for July 2009 Start fabrication drawings No significant design/cost changes since CD-2 Use mechanical designs for the vacuum chamber and 6-DOF alignment stage that have previously sustained reviews Leveraging existing designs (when applicable) reduces our overall engineering/design effort. Additionally, helps to ensure commonality within the LUSI instruments Vacuum chamber cover/laser cover removed/sectioned for clarity Budget at Completion (BAC) ≈ $126K CXI Final Instrument Design Review June 3, 2009 9 9 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Engineering/Design Status (5) Particle Injector (WBS 1.3.04.01) PRD & ESD released Existing Injector design from LLNL CXI will advance the current design Optimization of particle beam throughput Remote operation of equipment SLAC/LLNL Memorandum of Understanding (MOU) signed-off February 2009 “Collaboration on the sample particle injector for the Coherent X-ray Imagining (CXI) instrument” generation or exchange of research and test results, data, and know-how fabrication or exchange of equipment financial or other contributions to activities being undertaken exchange of personnel Physics Level of Effort (LOE) began upon MOU sign-off, engineering to follow as required PDR scheduled for September 2009 BAC ≈ $1,470K CXI Final Instrument Design Review June 3, 2009 10 10 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Engineering/Design Status (6) CXI Sample Chambers (WBS 1.3.05.01.01) 1µm Sample Chamber PRD & ESD released Successful PDR held March 2009 Design Review Report TR-391-003-20-0 Currently addressing PDR “Action Items” Piezo-stage vibration/stability due to stack-up Equipment protection for in-vacuum stages (potential for clashing) FDR “Early Finish” scheduled for September 2009 FDR will be accelerated to July 2009 BAC ≈ $620K 0.1µm Sample Chamber PRD & ESD released PDR scheduled for March 2010 Chamber proper will likely be an integral part of the 0.1µm KB vacuum chamber BAC ≈ $500K CXI Final Instrument Design Review June 3, 2009 11 11 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Engineering/Design Status (7) CXI Precision Instrument Stands (WBS 1.3.05.01.02) 1µm Precision Instrument Stand PRD & ESD released Support /Interface with 1µm Sample Chamber and Detector Stage (in all experimental configurations) Engineering/Design effort, beyond conceptual design, began in March 2009 PDR completed May 15, 2009: Design Review Report TR-391-003-27-0 Determine the effect of lateral seismic loads on rod ends Evaluate potential back-driving of ball screws due to seismic loading and ameliorate any effects FDR scheduled for July 2009 BAC ≈ $240K 0.1µm Precision Instrument Stand PRD & ESD released Support 0.1µm Sample Chamber, Detector Stage and 0.1µm KB System PDR scheduled for April 2010 BAC ≈ $330K CXI Final Instrument Design Review June 3, 2009 12 12 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Engineering/Design Status (8) Cornell/SLAC detector with variable aperture Detector Stage (WBS 1.3.05.01.03) CXI Detector Stage with Cornell/SLAC detector PRD, ESD, SOWs & ICDs released Cornell detector mechanical design progressing SLAC PPA mechanical engineering completing design for a variable aperture detector Complete assembly by October 2009 to meet LCLS CD-4 Purchase order placed in March 2009 with a local design firm for the mechanical design and drafting of the CXI Detector Stage – CXI was resource limited Move design forward in the schedule Vendor design reviews PDR completed May 15, 2009: Design Review Report TR-391-003-27-0 Explore options to prevent any interference between the detector and valve aperture Consider methods to determine the vibration amplitude of the cantilevered detector Develop plans for the fiducialization of the detector relative to the vacuum chamber FDR – July 2009 BAC ≈ $330K CXI Final Instrument Design Review June 3, 2009 13 13 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Engineering/Design Status (9) CXI Hutch Facilities (WBS 1.3.06.01 & 1.3.06.02) Hutch layout design Raised flooring Storage cabinets, work benches and tool chests Utilities distribution BAC ≈ $350K CXI Vacuum System (WBS 1.3.07.01 & 1.3.07.02) Requirements In general, beamline vacuum better than 10-7 Torr Better than 10-9 Torr for KB Systems – isolation/differential pumping from HV required Preliminary design of a compact, 2 stage, differential pump system complete Vacuum equipment: pumps, valves, gauges, etc. Bellows and Spools Use LCLS support stands where applicable (diagnostics supports/beampipe supports) to leverage existing engineering/design effort PDRs Vacuum Equipment – June 2009 Vacuum Supports – November 2009 BAC ≈ $700K B4C “throttles” & Guard CXI Final Instrument Design Review June 3, 2009 14 14 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Engineering/Design Status (10) Installation (WBS 1.3.08.01) LUSI Installation Coordinator Obtain required installation permits Conduct daily tailgate meeting w/ UTR (University Technical Representative) Conduit to engineering for field installation issues Provide installation status for incorporation into LUSI schedule CXI has a “phased installation” Early Science Diagnostics/Common Optics Reference Laser 1µm Sample Chamber & Precision Instrument Stand 1µm KB System Detector Stage Vacuum Equipment/Hardware/Supports Early Finish – May 2011 CD-4 Diagnostics/Common Optics 0.1µm Sample Chamber & Precision Instrument Stand 0.1µm KB System Particle Injector/IToF Vacuum Equipment/Hardware/Supports Early Finish – January 2012 CXI Final Instrument Design Review June 3, 2009 15 15 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Cost & Schedule Performance 10,000 0 1.3.2 CXI X-ray Optics -10,000 1.3.3 CXI Lasers -20,000 WBS 1.3 COHERENT X-RAY IMAGING (CXI) Cumulative Values March 2009 Status (Cumulative to Date) Engineering / Design $ 4,299,779 Scheduled $ 1,166,955 Proc/Fab/Assy/Test/Instl $ 5,771,806 Performed $ 1,067,834 BAC $ 10,071,585 Actual $ 925,671 Schedule Variance $ (99,121) Cost Variance $ 142,163 -30,000 1.3.4 CXI Coherent Imaging Injector -40,000 1.3.5 CXI Sample Environment -50,000 1.3.6 CXI Hutch Facilities -60,000 -70,000 Engineering / Design 1.3.7 CXI Vacuum System -80,000 Month end March 2009 cumulative schedule variance (-) Proc/Fab/Assy/Test/Instl 43% 1.3.6 CXI Hutch Facilities 2% 57% 1.3.5 CXI Sample Environment 21% 1.3.7 CXI Vacuum System 5% 1.3.2 CXI X-ray Optics 16% 1.3.3 CXI Lasers 2% 1.3.4 CXI Coherent Imaging Injector 54% Month end March 2009 cumulative cost variance (+) CXI Final Instrument Design Review June 3, 2009 16 16 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU CXI Critical Path KB Mirror AWARD & Vendor Design KB Mirror Design/Fabrication Effort Post Vendor Effort and Installation Critical path (thru 1µm KB System) has 9d of schedule contingency KB Mirror Installation Effort CXI Final Instrument Design Review June 3, 2009 17 17 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU CXI Milestones FY08 FY09 FY10 FY11 Preliminary Design Reference Laser – March 2009 1 micron Sample Chamber – March 2009 Detector Stage – May 2009 1 micron Instrument Stand – June 2009 Particle Injector – October 2009 1 micron KB System – September 2009 0.1 micron System – January 2010 Ion TOF – May 2010 CXI Advanced Procurement Review - November 2008 Final Instrument Design Review – June 2009 Final Design Reviews Reference Laser – May 2009 Detector Stage – September 2009 1 micron Sample Chamber – September 2009 1 micron Instrument Stand – August 2009 Particle Injector – February 2010 1 micron KB System – January 2010 0.1 micron System – May 2010 Ion TOF – June 2010 Project Ready for CD-3 - July 2009 Award PO 1 micron KB System – May 2009 0.1 micron System – June 2009 1 micron Sample Chamber – January 2010 Detector Stage – January 2010 1 micron Precision Instrument Stand – January 2010 Receive 1 micron Sample Chamber – April 2010 1 micron Precision Instrument Stand – May 2010 Detector Stage – July 2010 1 micron KB System – September 2010 0.1 micron System – October 2010 Early Science Installation Complete - May 2011 All dates are early finish CXI Final Instrument Design Review June 3, 2009 18 18 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU CXI Milestones (2) Significant recent & near-term CXI Instrument milestones Current schedule (March 2009 data) vs. CD-2 approved schedule (October 2008) Moved FIDR to June 2009 so that subsequent activities allow for the CD-3 Review to occur in July 2009 MS Level L2 L2 L6 L6 L4 L4 L3 L2 Activity Description APPROVED: ADVANCE PROCUREMENT-CXI APPROVED: ADVANCE PROCUREMENT-DCO AWARD: CXI KB 1 System - Long Lead AWARD: CXI KB 0.1 System - Long Lead FIDR - Final Instrument Design Review - CXI COMP: Final Instrument Design Review - CXI PROJECT READY FOR CD-3 APPROVAL COMPLETE: CD-3 REQUIREMENTS Current Oct 2008 Early Finish Early Finish 18-Dec-08 5-Jan-09 24-Apr-09 6-May-09 22-May-09 20-May-09 1-Jun-09 6-Jul-09 3-Jun-09 15-Jul-09 16-Jun-09 29-Jul-09 4-Sep-09 27-Oct-09 30-Oct-09 7-Jan-10 L2: DOE Site Office Authority (COMPLETE/APPROVED) L3: Interface Milestones/Major Events L4: Systems (COMP/RCV) L6: Commitments/Awards (AWARD) CXI Final Instrument Design Review June 3, 2009 19 19 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU CXI Milestones (3) Six month “look-ahead” of CXI Instrument milestones Current schedule vs. CD-2 approved dates (October 2008) 4 PDRs completed to-date CXI Reference Laser CXI 1µm Sample Chamber CXI Detector Stage CXI 1.0µm Prec. Inst. Std. 2 Vendor Contract Awards (KBs) 2 Vendor Preliminary Design Reviews (PDR) – KBs 5 Final Design Reviews (FDR) LCLS – Cornell Detector Packaging CXI Final Instrument Design Review June 3, 2009 MS Level L4 L5 L5 L4 L4 L4 L6 L6 L4 L4 L5 L5 L4 L5 L5 L4 L4 L4 L4 Activity description FDR - Fnl Dsn Review - Cornell Detector Packaging COMP: ESD Released - CXI 0.1um Prec Instr Std COMP: ESD Released - CXI 0.1um SC PDR - Prelim Design Review - CXI 1.0um Prec Inst PDR - Prelim Design Review - CXI Detector Stage FDR - Final Design Review - CXI Ref Laser AWARD: CXI KB 1 System - Long Lead AWARD: CXI KB 0.1 System - Long Lead FIDR - Final Instrument Design Review - CXI COMP: Final Instrument Design Review - CXI COMP: Committee Approval - CXI 1.0um SC COMP: Committee Approval - CXI 1.0um Prec Instr FDR - Final Design Review - CXI 1.0um Prec Instr RCV: CXI Ref Laser COMP: Committee Approval - CXI Detector Stage FDR - Final Design Review - CXI 1.0um SC FDR - Final Design Review - CXI Detector Stage PDR - Vendor Design Review CXI KB 1 Sys PDR - Vendor Design Review - CXI KB 0.1 Sys 20 20 Current Early Oct 2008 Early Finish Finish 1-Apr-09 16-Feb-09 2-Apr-09 7-Apr-10 1-May-09 4-Jan-10 15-May-09 7-Dec-09 15-May-09 16-Mar-09 21-May-09 27-Apr-09 22-May-09 20-May-09 1-Jun-09 6-Jul-09 3-Jun-09 15-Jul-09 16-Jun-09 29-Jul-09 13-Jul-09 8-Sep-09 3-Aug-09 9-Mar-10 11-Aug-09 17-Mar-10 31-Aug-09 5-Aug-09 7-Sep-09 7-Jul-09 10-Sep-09 6-Nov-09 21-Sep-09 21-Jul-09 22-Sep-09 18-Sep-09 1-Oct-09 5-Nov-09 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Risk Identification & Mitigation Risk Identification/Registry complete and up to date as per “LCLS Risk Management Plan” PMD 1.1-002-r4 3 (of 17) risks retired prior to CD-2 9 (of 17) risks retired since CD-2 KB Mirror Systems Vendor can’t meet 0.1µm mirror specifications – Technical Vendor can’t meet 1µm mirror specifications – Technical No vendor willing to bid on 1µm mirrors – Technical & Schedule No vendor willing to bid on 1µm mirror mechanical system – Technical & Schedule No resident experience designing mirror mechanical system – Technical & Schedule 45˚ KB configuration – Technical Sample Chambers Custom piezo-stages for Sample Chambers cannot be made – Technical & Schedule Cornell detector Last minute changes to detector design – Technical & Schedule Detector Stage Custom linear translation stage for CXI Detector Stage – Technical Outstanding risks relate to Procurement – As discussed by Tom in his introduction (2X) Delivered KB mirror systems don’t meet specifications (2X) Particle injector Interfaces with adjacent beamlines CXI Final Instrument Design Review June 3, 2009 21 21 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Safety LUSI Hazard Analysis Report (PM-391-001-34) complete Safety issues are considered at every stage of the design, fabrication and installation process Safety considerations (some examples) Ionizing Radiation Hutch walls will comply with SLAC Radiation Safety memo RP-RPG-080606-MEM-01 Hutch PPS Pressure/Vacuum Vessel Safety Compliant with 10CFR851 Approved vacuum procedures Seismic Safety Designs compliant with: Seismic Design Specification for Buildings, Structures, Equipment, and Systems, SLAC-I-720-0A24E-002-R002 Mechanical Interlocks for equipment protection Engineered solutions that prevent potential “pinch-points” with moving machinery Hoisting and Rigging Positioning of devices that require use of the FEH H5 overhead crane shall be performed only by qualified personnel with an approved lift plan. Laser Safety CXI Reference Laser, Class 2, 1mW Appropriate signage CXI Final Instrument Design Review June 3, 2009 22 22 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Summary CXI designs are mature and concepts are based on proven developments made at FLASH and SR sources CXI scope is stable and has not changed since CD-2 Long Lead Procurement Committee evaluation of vendor proposals for the 1µm KB system occurred on April 9, 2009 Procurement recommendation on April 27, 2009 Contract award expected in June 2009 0.1µm KB system is an “option” included in the 1µm KB system RFP Critical Path schedule contingency is 9d – continuously monitored Most major risks associated with the KB mirror systems have been retired Remaining KB risks will be addressed during design/manufacture and testing FIDR is being held now as a prerequisite for the CD-3 review in July 2009 Replanning of LUSI WBS 1.3 (CXI) due to ARRA funding and general scheduling enhancements in process Pending BCR #2009-05-02: CXI Omnibus Replanning CXI is on track to support an accelerated schedule CXI Final Instrument Design Review June 3, 2009 23 23 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU CXI Final Instrument Design Review June 3, 2009 24 24 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Cost & Schedule Performance Rpt Period 03-31-2009 WBS Level 1 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 2 3 3 3 3 3 3 3 3 3 4 5 6 3 01 02 03 04 05 06 07 08 4 5 Description 6 LUSI PROJECT MAJOR ITEM OF EQUIPMENT (MIE) PROJECT MANAGEMENT X-RAY PUMP PROBE (XPP) COHERENT X-RAY IMAGING (CXI) CXI System Integration & Design CXI X-ray Optics CXI Lasers CXI Coherent Imaging Injector CXI Sample Environment CXI Hutch Facilities CXI Vacuum System CXI Installation X-RAY CORRELATION SPECTROSCOPY (XCS) DIAGNOSTICS & COMMON OPTICS CONTROLS AND DATA ACQUISITION Budgeted Cost Work Work Scheduled Performed 7,695,241 2,198,852 1,997,352 1,166,955 718,488 36,625 42,869 87,096 151,386 44,823 85,668 0 749,956 1,099,369 482,757 7,411,597 2,198,852 1,938,851 1,067,834 718,488 37,042 37,031 89,654 140,794 33,758 11,068 0 704,405 1,012,930 488,725 Cumulative to Date Actual Variance Cost Work Schedule Cost 7,283,784 2,236,294 1,900,817 925,671 725,710 12,647 34,596 8,849 109,257 30,599 4,014 0 717,545 1,045,338 458,119 -283,644 0 -58,500 -99,121 0 417 -5,838 2,558 -10,592 -11,065 -74,600 0 -45,551 -86,439 5,968 127,813 -37,442 38,034 142,163 -7,222 24,394 2,435 80,805 31,537 3,159 7,055 0 -13,141 -32,408 30,606 Run Date: 4/20/2009 8:22:53 AM At Complete Perf. Indices Latest Revised SPI CPI Budgeted Estimate Variance 0.96 1.02 42,606,624 1.00 0.98 5,355,823 0.97 1.02 5,784,211 0.92 1.15 10,071,585 1.00 0.99 1,494,270 1.01 2.93 2,676,178 0.86 1.07 125,726 1.03 10.13 1,514,990 0.93 1.29 2,205,693 0.75 1.10 354,534 0.13 2.76 691,149 1,009,045 0.94 0.98 7,227,371 0.92 0.97 6,786,963 1.01 1.07 7,380,671 42,478,811 5,393,265 5,746,177 9,929,422 1,501,492 2,651,784 123,291 1,434,185 2,174,156 351,375 684,094 1,009,045 7,240,512 6,819,371 7,350,065 127,813 -37,442 38,034 142,163 -7,222 24,394 2,435 80,805 31,537 3,159 7,055 0 -13,141 -32,408 30,606 CXI month end March data BCWS BCWP ACWP SPI CPI CXI Final Instrument Design Review June 3, 2009 25 25 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Cost & Schedule Performance – WBS 1.3 2.5 2. CPI SPI 1.5 1. .5 . Cum thru OCT_08 NOV_08 DEC_08 JAN_09 FEB_09 MAR_09 APR_09 MAY_09 JUN_09 FY08 1.3 COHERENT X-RAY IMAGING (CXI) JUL_09 AUG_09 SEP_09 Cum thru FY09 BCWS $ 638,854 $ 51,078 $ 73,891 $ 53,939 $ 77,193 $ 104,320 $ 167,681 $ 172,643 $ 156,025 $ 146,533 $ 216,564 $ 213,275 $ 187,733 $ 2,249,266 BCWP $ 639,127 $ 50,812 $ 63,178 $ 31,307 $ 80,170 $ 83,243 $ 119,997 $ - $ - $ - $ - $ - $ - $ 864,595 ACWP $ 642,280 $ 47,657 $ 53,406 $ 32,777 $ 35,725 $ 45,686 $ 68,141 $ - $ - $ - $ - $ - $ - $ 811,845 CV $ (3,153) $ 3,156 $ 9,773 $ (1,470) $ 44,445 $ 37,557 $ 51,856 $ - $ - $ - $ - $ - $ - $ 52,751 SV $ (50,539) $ 2,978 $ (21,077) $ (47,684) $ - $ - $ - $ - $ - $ - $ (30,359) 50,546 $ (10,712) $ (22,632) $ CPI 1. 1.07 1.18 .96 2.24 1.82 1.76 1.15 SPI .93 .99 .86 .58 1.04 .8 .72 .92 CXI Final Instrument Design Review June 3, 2009 26 26 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Cost & Schedule Performance – WBS 1.3 $2,400,000 $2,300,000 $2,200,000 CUM BCWS $2,100,000 CUM BCWP $2,000,000 $1,900,000 CUM ACWP $1,800,000 CUM EAC $1,700,000 $1,600,000 $1,500,000 $1,400,000 $1,300,000 $1,200,000 $1,100,000 $1,000,000 $900,000 $800,000 $700,000 $600,000 $500,000 Cum thru OCT_08 FY08 BCWS $ CUM BCWS $ BCWP 1.3 COHERENT CUM BCWP X-RAY ACWP IMAGING (CXI) CUM ACWP 689,666 $ NOV_08 266 $ DEC_08 73,891 $ JAN_09 53,939 $ FEB_09 MAR_09 APR_09 77,193 $ 104,320 $ 167,681 $ MAY_09 - $ JUN_09 - $ JUL_09 - $ AUG_09 - $ SEP_09 - $ Cum thru FY09 - $ 2,249,266 689,666 $ 689,932 $ 763,823 $ 817,761 $ 894,954 $ 999,274 $ 1,166,955 $ 1,339,597 $ 1,495,622 $ 1,642,155 $ 1,858,720 $ 2,071,995 $ 2,259,728 $ 639,127 $ 50,812 $ 83,243 $ 119,997 $ - $ - $ - $ - $ - $ - $ $ 639,127 $ 689,940 $ 753,118 $ 784,425 $ 864,595 $ 947,838 $ 1,067,834 $ - $ - $ - $ - $ - $ - $ 642,280 $ 68,141 $ - $ - $ - $ - $ - $ - $ $ 642,280 $ 689,937 $ 743,343 $ 776,119 $ 811,845 $ 857,530 $ 925,671 $ - $ - $ - $ - $ - $ - EAC $ 642,280 $ - $ - $ - $ - $ - $ - $ 2,215,462 CUM EAC $ 642,280 $ 689,937 $ 743,343 $ 776,119 $ 811,845 $ 857,530 $ 925,671 $ 1,142,696 $ 1,340,046 $ 1,577,991 $ 1,822,984 $ 2,086,408 $ 2,367,153 47,657 $ 47,657 $ CXI Final Instrument Design Review June 3, 2009 63,178 $ 53,406 $ 53,406 $ 31,307 $ 32,777 $ 32,777 $ 80,170 $ 35,725 $ 35,725 $ 45,686 $ 45,686 $ 68,141 $ 27 27 864,595 811,845 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Expanded CSSR – by CAM CA Mgr 3B Pa ul Mo nta ne z 1.3.01 CXI System Integration & Design 1.3.02.01 CXI KB System (0.1 micron) 1.3.02.02 CXI KB System (1 micron) 1.3.03.01 CXI Reference laser 1.3.04.01 Coherent Imaging Injector System Integ and Desig 1.3.05.01 CXI Room Temperature Environment 1.3.06.01 CXI Hutch Specification 1.3.06.02 CXI Utilities & Hutch Equipment 1.3.07.01 CXI Vacuum Equipment 1.3.07.02 CXI Vacuum Hardware 1.3.08.01 CXI Installation Phase CA Mg rT o ta ls : CXI Final Instrument Design Review June 3, 2009 Cumulative to Date Actual Budgeted Cost Cost Variance Work Work Work Schedule Cost Scheduled Performed Performed 718,488 15,262 21,363 42,869 87,096 151,386 33,756 11,068 67,813 17,855 0 1,166,955 718,488 15,261 21,781 37,031 89,654 140,794 33,758 0 11,068 0 0 1,067,834 28 28 725,710 2,159 10,488 34,596 8,849 109,257 30,599 0 4,014 0 0 925,671 At Completion Budgeted 0 -7,222 1,494,270 -1 13,102 1,394,889 418 11,292 1,281,289 -5,838 2,435 125,726 2,558 80,805 1,514,990 -10,593 31,537 2,205,693 2 3,159 54,255 -11,068 0 300,279 -56,745 7,055 296,819 -17,855 0 394,330 0 0 1,009,045 -99,121 142,163 10,071,585 Latest Revised Estimate 1,495,800 1,398,631 1,286,948 125,735 1,469,327 1,985,784 54,231 96,024 297,627 397,378 1,008,185 9,615,670 Variance -1,530 -3,742 -5,659 -9 45,664 219,909 24 204,255 -807 -3,049 861 455,915 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Control Accounts & Work Packages – by WBS L2 WBS WBS 1.1 WBS 1.2 WBS 1.3 WBS 1.4 WBS 1.5 WBS 1.6 Total CXI Final Instrument Design Review June 3, 2009 Control Work Accounts Packages 6 12 $ 18 47 $ 11 60 $ 19 44 $ 11 46 $ 20 299 $ 85 508 $ 29 29 Value 5,355,823 5,784,211 10,071,585 7,227,371 6,786,963 7,380,671 42,606,624 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU P3 Files Milestones – by WBS L2 CXI Final Instrument Design Review June 3, 2009 30 30 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Labor/Non-labor Split – WBS 1.3 LABOR NON-LABOR $4,509,729 45% WBS $5,561,856 55% TYPE BUDGET 1.3 COHERENT X_RAY IMAGING (CXI) CXI Final Instrument Design Review June 3, 2009 LABOR $ 5,561,856 NON-LABOR $ 4,509,729 31 31 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Split by Phase – WBS 1.3 Engineering / Design $ Proc/Fab/Assy/Test/Instl $ CXI Final Instrument Design Review June 3, 2009 32 32 4,299,779 5,771,806 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU Procurements and Dollars – WBS CXI Final Instrument Design Review June 3, 2009 33 33 Paul Montanez, P.E. montanez@SLAC.Stanford.EDU