SECONDARY DISTRIBUTION SYSTEM OPTIMIZATION METHODOLOGY AND MATLAB PROGRAM A Project Presented to the faculty of the Department of Electrical and Electronic Engineering California State University, Sacramento Submitted in partial satisfaction of the requirements for the degree of MASTER OF SCIENCE in Electrical and Electronic Engineering by Steve Ghadiri Majid Hosseini FALL 2013 © 2013 Steve Ghadiri Majid Hosseini ALL RIGHTS RESERVED ii SECONDARY DISTRIBUTION SYSTEM OPTIMIZATION METHODOLOGY AND MATLAB PROGRAM A Project by Steve Ghadiri Majid Hosseini Approved by: _________________________________, Committee Chair Turan Gönen, Ph.D. _________________________________, Second Reader Salah Yousif, Ph.D. _________________________ Date iii Student: Steve Ghadiri Majid Hosseini I certify that these students have met the requirements for format contained in the University format manual, and that this project is suitable for shelving in the Library and credit is to be awarded for the Project. _________________________________, Graduate Coordinator Preetham B. Kumar, Ph.D. _________________________ Date Department of Electrical and Electronic Engineering iv ACKNOWLEDGMENTS The authors would like to acknowledge Dr. Turan Gonen, Professor of Electrical Engineering at California State University, Sacramento, for his guidance, supervision, patience, and care in recommending and evaluating this project in the area of Power Engineering at California State University, Sacramento. The authors are also appreciative of Dr. Salah Yousif, Professor of Electrical Engineering at California State University, Sacramento, for his excellent instruction in the area of Power Engineering at California State University, Sacramento, as well as being a reader of this project. The author would also like to acknowledge Dr. Preetham Kumar, Graduate Coordinator, and Professor of Electrical Engineering at California State University, Sacramento, for his guidance and direction in completion of this project. v Abstract of SECONDARY DISTRIBUTION SYSTEM OPTIMIZATION METHODOLOGY AND MATLAB PROGRAM by Steve Ghadiri Majid Hosseini The goal of many utilities is to provide an economically balanced energy delivery system that will provide customers with safe, reliable, and efficient means of power while not subjecting them to over-designs with unjustifiable cost. In achieving that goal, the utility company must rely on system designers to optimize several key parts of their delivery system. The distribution system secondary, e.g., is one of these subsystems, and therefore, it can pose optimization type challenge for the distribution system designers. Arriving at optimal solutions, serves the best interests of the utility and the long-term objectives of the customers and ratepayers. In this paper, the authors analyze many alternative intelligent choices when considering a simplified distribution system selection and show, thru the formulation and Matlab computer programming, how a simple optimization technique can arrive at a standard selection of the system components. Total Annual Cost (TAC) is the reviewed concept, vi and essentially, it reduces to a sum of initial capital investment, maintenance, and operating costs including the costs of system losses. The optimization process is pivotal in minimization of the TAC. Customer loadings are a key part of this selection and have been considered in the program formulation, as well. Matlab program provides the ease in selection of the components and speed in calculation performance to arrive at a most feasible answer among optimized choices. Voltage drop is the constraint in this optimization process, which is usually limited by the utility company’s requirement. _________________________________, Committee Chair Turan Gönen, Ph.D. _________________________ Date vii DEDICATION We dedicate this paper to our family for supporting and inspiring us in this journey. viii TABLE OF CONTENTS Page Acknowledgement ...............................................................................................................v Dedication ....................................................................................................................... viii List of Tables ......................................................................................................................x List of Figures ................................................................................................................... xi Chapter 1. INTRODUCTION ..........................................................................................................1 2. DISTRIBUTION SYSTEM DESCRIPTION .................................................................5 2.1 Distribution System Design Requirement ..............................................................5 2.2 Distribution System Planning Methodology ........................................................7 3. LITERATURE REVIEW .............................................................................................10 3.1 Design Criteria .....................................................................................................10 3.2 Components of Secondary Distribution System .................................................15 3.3 Voltage and Load Criteria ...................................................................................16 3.4 Main Factors ........................................................................................................17 3.5 Changing Paradigm of the Power Distribution System .......................................19 4. OPTIMIZATION METHODOLOGY ..........................................................................24 5. ECONOMIC ESTIMATION AND ANALYSIS .........................................................43 6. NUMERICAL RESULTS ...........................................................................................49 7. CONCLUSIONS ..........................................................................................................64 Appendix A: Matlab Optimization Program for Secondary Distribution System ............68 Appendix B: Instruction for Matlab TAC Program in Distribution System ....................79 Appendix C: Secondary Distribution System Voltage Drop Program ............................83 Appendix D: Distribution System Component Information Background ........................91 Bibliography .....................................................................................................................96 ix LIST OF TABLES Table Page 4.1 Load Data for Book Example 6.1 ...............................................................................39 6.1 Summary of the Runs .................................................................................................53 x LIST OF FIGURES Figures Page 1.1 One Line Diagram of Typical Primary Distribution Feeders .......................................2 3.1 Radial-type Primary Feeders .......................................................................................11 3.2 One Line Diagram of a Typical Distribution System .................................................14 4.1 Flow Chart of Safigianni’s Optimization Process ......................................................25 4.2 Matlab Program Flow Chart .......................................................................................30 4.3 One Line Diagram of Multiple Primary System for JHC ...........................................32 4.4 Typical Residential Area Lot Layout and Service Arrangement ................................33 4.5 Illustration of a Typical Residential Secondary Pattern ..............................................33 5.1 Current Transformer Cost ............................................................................................45 5.2 Historic Cost of Transformers ....................................................................................45 5.3 Current Cable Cost .......................................................................................................47 5.4 Historic Cable Cost ......................................................................................................48 6.1 Transformer Cost Fit into Third Order Model ............................................................51 6.2 Cable Cost Fit into Second Order Model ....................................................................52 6.3 Cable Cost For Different Sizes ...................................................................................52 xi 1 Chapter 1 INTRODUCTION 1. Introduction The power distribution systems, which carry electric energy to even far-flung customers utilizing the most appropriate voltage level, are divided into primary and secondary. The part of the electric utility system, which is between the distribution substation and the distribution transformers, is the primary feeders or primary distribution feeders. The secondary power distribution systems include step-down distribution transformers, secondary circuits, consumer services, and meters to measure the consumer energy consumption. They are single-phase when they serve residential customers and three-phase when they serve industrial or commercial customers. The most commonly used secondary power systems are the radial systems. The general requirements from a secondary power distribution system are that it gives customers as stable a voltage as possible, operate safely and effectively at the minimum possible cost and is well balanced. One line diagram of a typical primary distribution feeder is shown in Figure 1.1 below, as depicted from standard Handbook for electrical Engineers [3]. 2 Figure 1.1 One-line diagram of typical primary distribution feeders. Source: (From Fink, D.G., and H. W. Beaty, Standard Handbook for Electrical Engineers, 11th edition, McGraw-Hill, New York, 1978. With permission.) 3 Unfortunately, the reliability of service continuity of the radial primary feeders is low. A fault occurrence at any location on the radial primary feeder causes a power outage for every consumer on the feeder unless the fault can be isolated from the source by a disconnecting device such as a fuse, sectionalizer, disconnect switch, or recloser. Additionally, the operation and planning of electric power systems involve even a long list of challenging activities, many of which are directly or indirectly related with the optimization of certain objective functions [13]. The complex algorithms can be obtained from the cited references, which have been developed in order to examine whether a radial secondary power distribution system fulfills several criterions. Conductor tapering, network conductors having sufficient thermal short-circuit strength, power flow in each network segment less than the thermal of the conductor used there, acceptable percent voltage drop from the distribution transformer (source node) up to any one of the ends of the network, and adequate fault current to operate the network protection are essential part of this criteria [4]. While we acknowledge those methodologies and we ideally wish to create those features in a comprehensive software program, we are somewhat limited to essential math functions in our Matlab program, and therefore, we recognize that we have no way of implementing all of them in our Matlab program. Use of power flow programs can perhaps facilitate their implementation caption. 4 Switching mechanisms and over current protections are usually associated with the type of configurations and they do not necessarily follow exactly into an optimization program. Additionally, the cost of the over-current protection does not always vary linearly with the size of the system. For simplicity, they have been put aside here as an economical or fault current constraint in our program [6]. Safigianni has shown the methodology behind an elaborate optimization program [4] and [5]. In her program, each stage is analyzed for the constraints by examination. If the result of the above examination is that any of the previously mentioned technical constraints is not satisfied, the program which implements the algorithm suggests a number of alternative solutions concerning transformer changes or conductor replacement combinations or both of them, in order to optimize technically the system operation. This number depends on the load distribution and the conductor types and sizes, which are available for the network construction. Finally, the program estimates economically the alternative technically acceptable solutions and selects the most economical one. The algorithm of Safigianni is an improvement and extension of the algorithm used in her first reference and it is using more constraints, a load flow analysis method to calculate the currents, voltages, economic data, and functions to estimate the resulting technical solutions, which make final results more accurate and reliable. Ultimately, a capable optimization method could expand to power flow modeling of a portion of network. 5 Chapter 2 DISTRIBUTION SYSTEM DESCRIPTION 2.1 Distribution System Design Requirement Secondary power distribution systems are used to deliver power to consumers in residential or commercial businesses. We cannot imagine living without efficient constant source of power. The best distribution system is one that will supply adequate power to present and future loads safely and cost effectively. Distribution design engineers choose the best distribution system, when they have considered all the design parts, installation, and the cost. Design needs to be safe, effective, and reliable. Then, at the same time, it needs to be not necessarily cheap, but cost effective. In order to design the best distribution system, the system design engineer must have information concerning the loads and knowledge of the various types of distribution systems that are applicable. The various categories of buildings have many specific design challenges, but certain basic principles are common to all. Such principles, if followed, will provide a soundly executed design. Understanding of the entire component in the power distribution system and their functions are essential for implementing a proper design. The components in such a system are power distribution transformers, primary and secondary conductors, and power poles. For choosing the right component in this system, the most important 6 information is how consumer uses this power. Most important piece of information is the amount of load that consumer will use considering present load and future load given the load value will constantly change both within a day and over time. The future load increase also needs to be considered because the system will not be cost effective if the system need to be replace in 1, 2, or even 10 years. In this paper, we report on the creation of a Matlab program for a simplified residential block, which is illustrative of city development, and it explores a secondary distribution system design that supply an area block with 24 loads. A reasonable load demand could be input for each consumer. The demand assumption relies on average monthly electrical usage for the area with some extra spare capacity (20 percent) for safety before reaching the threshold and of course some extra room for future usage. The program calculates the total annualized cost for the design and then this cost is optimized with transformers, primary system enhancements, service laterals, and service drop secondary conductors. The service is size optimized (or sub-optimized) based on optimized cost and number of pertaining constraints. After the entire initial components’ selection, the program calculates the voltage drop to ascertain, if it is in an acceptable range and if it is not, the design needs to be changed. Conductors can be overhead or underground. In case of overhead conductor, the cost of poles and other component will add to the overall layout cost, and for underground distribution, the cost of trenching, conduits, and pull boxes will have to be added which usually are substantially more. 7 2.2 Distribution System Planning Methodology The costs and reliability of power distribution systems are beginning to receive as much attention as those of power generation and transmission systems. Modern planning of these large-scale and complicated systems relies heavily on computers and mathematical optimization tools [12]. Especially, in the developing countries where the growing power demand provides needs for substantial expansion of power distribution systems, the long-term benefit brought by using computerized optimization tools are tremendous, as compared to widely practiced ad hoc methods involving only local computation. The goal of modern power distribution system planning is to satisfy the growing and changing system load demand during the planning period and within operational constraints, economically, reliably and safely, by making optimized decisions on the following: voltage levels of the distribution network; locations, sizes, servicing areas, loads and building or expanding schedules of the substations; routes, conductor types, loads and building schedules of the sub-transmission lines and feeders; other important issues such as the types and locations of switching devices, load voltage levels, network configuration, and load reliability levels, etc. The optimization problem is usually very complicated, considering the scale of the system and the existence of many interrelated factors. 8 The new approach for the systemized optimization of power distribution systems is presented in Yifan Tang’s paper [12]. In Yifan’s paper the distribution system reliability is modeled in the optimization objective function via outage costs and costs of switching devices, along with the nonlinear costs of investment, maintenance and energy losses of both the substations and the feeders. The optimization model establishes a multi-stage, mixed-integer and nonlinear function, which is solved by a network-flow programming algorithm. A multi-stage interlacing strategy and a nonlinearity iteration method are also designed by him. It is noteworthy to mention that the investment and maintenance costs of the substations and the feeders are fixed costs (zero-order), while their operational costs are variable costs squarely depending on their loads (second-order) [16], making the objective function inherently nonlinear. The need to seriously consider reliability in terms of capital costs in distribution system planning is being recognized, as emphasized recently by an IEEE task force on distribution reliability modeling and applications [17]. Unfortunately, few papers had extensively tackled this problem [18] and [19]. Most of methodology by Yifan Tang is based on the original Dr. Gonen’s work on Optimal Multi-Stage Planning of Power System [21], and Pseudo-Dynamic Planning of Dr. Ramirez-Rosado and Gonen [22]. 9 In this paper, of course for simplicity reasons we do not model reliability in our simple secondary distribution optimization solution, however, when a designer is considering the primary distribution design or a large portion of a city, one needs to account for it. Usually selection of the switching configurations and degrees of redundancy provide a certain level of reliability. Reliability inherently reflects into the overall objective function via outage costs and costs of switching devices, along with the present value of the costs of investment, maintenance and energy losses for both the substations and the feeders. 10 Chapter 3 LITERATURE REVIEW 3.1 Design Criteria Problem formulation and definition is important to arrive at a correct optimized value in a multi- variable equation. There are various yet interrelated factors affecting the selection of a primary-feeder rating [1]. Examples are: 1. Nature of the load connected 2. The load density of the area served 3. The growth rate of the load 4. The need for providing spare capacity for emergency operations 5. The type and cost of circuit construction employed 6. The design and capacity of the substation involved 7. The type of regulating equipment used 8. The quality of service required 9. The continuity of service required There are many methods to design the distribution system and we will not concern ourselves to discuss the other methods in detail here. However, we chose a radial type primary feeder with uniform loading for the simplicity and ease of developing established methodology into a Matlab optimization program. The simplest and the lowest cost, and 11 hence, the most common form of the primary feeder is the radial-type primary feeder as shown in Figure 3.1, as shown below. Figure 3.1 Radial-type Primary Feeders Source: Electric Power Distribution System Engineering by Gonen [1] 12 The main primary feeder branches into various primary laterals, which in turn separate into several sub-laterals to serve all the distribution transformers. Generally, the main feeder and sub feeders are three-phase three-or four-wire circuits and laterals are three or single-phase. The current magnitude is the greatest in the circuit conductors that leave the substation. The current magnitude continually lessens out toward the end of the feeder as laterals and sub-laterals are branched off the feeder, tapering down. Usually, as the expected current value reduces in the service lateral, the size of feeder conductors reduces in the design. However, the permissible voltage regulation may restrict any feeder size reduction, since the thermal capacity of the feeder is also a consideration. The reasons for making a secondary power distribution system radial are the low investment cost, the simplicity of the protection circuits, and the easy control of the power method convenient for radial networks. In this project, we analyzed and concentrated on the three important components of the secondary distribution system. These components are distribution transformers, primary electrical conductors, and secondary electrical conductors. Focus of this paper will be cost effectiveness of the design and optimizing this cost. Cost, reliability, and life of the component will be discussed and these components will be analyzed and chosen mainly based on load demands and voltage drops. Electrical companies are facing very challenging situation, not only the energy price for the consumer need to be reasonably affordable and comparative in value, but the electric supply system also need to be reliable and 13 available constantly. In addition, the electric utility needs to be adapting to the change in load demand continuously. In the older neighborhood, the secondary distribution system is aging and need to be replaced. The cost of components, installation and labor, and maintenance compared to fifty years ago is significantly more, and with all the new technology that consumers use, the demand tends to be significantly higher, also. The design should be efficient and cost effective otherwise it will cost the utility company a lot of money and that extra cost will pass on to the consumer, and consequently, the price of electricity will go up. The operational objectives of a power grid are to provide continuous quality service at an acceptable voltage and frequency with adequate security, reliability, and an acceptable impact upon the environment—without damage to power grid equipment—all at a minimum cost. In Figure 3.2, the direction of arrows indicates the priority in which the objectives are implemented. 14 Figure 3.2 One-line diagram of a typical distribution system Source: Electric Power Distribution System Engineering by Dr. Gonen 15 Quality service that is environmentally acceptable, secure, and reliable, and entails minimum cost is the main objective in power grid operations. However, during the emergency conditions, the system may be operated without regard for the economy and environmental restriction such as the use of high polluting energy source, instead concentrating on the security and reliability of the service for energy users, while maintaining power grid stability. [7] The term continuous service means “secure and reliable service.” The term secure, as it is used here, means that upon occurrence of a contingency, the power grid could recover to its original state and supply the same quality electric power energy as before. Later definitions have been added to signify the innovative technologies in the smart grid arena, such as resiliency, and self- healing characteristics. 3.2 Components of Secondary Distribution System In the design of secondary distribution system, three essential components are distribution transformers, primary conductors, and secondary conductors. Load demand, voltage drop, and voltage fluctuation should be considered and examined for sizing the components because of their effect on both transformers and conductors. Overhead or underground cables will be discussed in brief in this paper since most likely the underground installation requires the trenching and conduit, and therefore, it will be substantially more expensive than the overhead’s cost of the poles and reinforcements. 16 3.3 Voltage and Load Criteria The present and future electrical needs of the consumers must be anticipated by utility companies and system should be planned accordingly. An electric load defines the rate at which the supply system is required to do work [24]. The unit of power measurement is Watt and electric power is the rate at which electric circuit performs work. The electric load power consumption is measured by kilowatt-hour, which the amount of work (1000watt) is done over the period of an hour. The amount of energy per unit time, which should be supplied by the utility, is load. (This is the total energy consumers are using or need in worst-case scenario to run all their electrical equipment such as lights, appliances, motors, etc. This load can be changed depending on time of the day or year. Planning an efficient design requires that a good forecast of load characteristics to be developed. It is very important that the utility can meet this maximum load demand. This maximum load demand is usually determined after review of a residential neighborhood over a year. The total power consumption (household load) for each residential unit is determined, or at least estimated. Then, the total power for that area is calculated. The utility can develop their plan for the size of components when they arrive at the load calculations. Not only the load demand fluctuates hourly, daily, monthly and yearly, but it also can increase and grow over time due to technology changes. Also of importance is estimating how the load may grow over time and at what rate [25]. Usually the new technology brings newer energy efficient devices that should decrease the load demand. 17 However, since we are using more devices the load demand is still higher. In particular, we can refer to the air conditioning loading, the most variable and disproportionally dominant component of bus load, which has brought to older neighborhoods that were not designed or built with it in the designer’s mind [26]. Another example, is super screen televisions that consume increasingly more watts than their older smaller predecessors. It is necessary for utility companies to re-evaluate the existing distribution system frequently to make sure the size of existing component are adequate for the increased loads. Furthermore, one can step in future and explore the frustration felt by homeowners when they may encounter difficulty in charging their electric vehicles all simultaneously, and finding that the neighborhood distribution circuit to be inadequate [10]. 3.4 Main Factors Utility companies consider two factors for load demands when designing a secondary distribution system. These two factors are Diversity factor and Coincident factor. The diversity factor is ratio of sum of the individual demands of the individual loads to maximum demand of the entire system [25]. Maximum individual demand for each customer does not occur at the same time and if all maximum individual demands are added, the result will be much higher than the maximum load of the system. If there was no diversity of the maximum load timing for each customer, then there would be a need for very large system capacity. Hence, the diversity factor is an important economic consideration for electric utilities when designing distribution system [24]. Diversity factor is usually equal to or greater than unity. 18 The coincident factor, the reciprocal of diversity factor, is often preferred because it is a way to describe load characteristics using a value that is usually less than unity [25]. This factor is used to calculate secondary voltage drops. One of the most critical components of the distribution system is transformers. When a transformer breaks and fails, it is noticeable to customers and whole neighborhood. It is hard to replace overhead transformer in timely manner and it is hard to service them. “Hot Spot Area”, or the highest temperature in the winding Area, is the most important factor relating to the loading capacity and aging of an oil-paper-installed distribution transformer. Hot spot temperature and data for life span of transformers are unknown and because of this lack of information transformers are often overrated. However, due to possible over-loading situation in the face of unavailable monitoring techniques, it is still possible that hot-spot temperatures can rise to undesirable levels [27]. In order to maintain transformer ageing within desirable limits, the goal is to keep the maximum hot –spot and top oil temperatures and the current load under allowed limits [28]. The following limits are given in [29]. Hot-spot temperature can range between 120C and 160C and top oil temperature can be between 105C and 115C. Transformers current rating can exceed its typical rating for a short duration by 30 to 100 percent. Distribution Transformers are usually designed for peak efficiency at or near 19 average power level. However, their actual efficiency is dependent upon their loading schedule [30]. 3.5 Changing Paradigm of the Power Distribution Systems Over the last twenty years, renewable energy sources have been attracting great attention due to the cost increase, limited reserves, and adverse environmental impact of fossil fuels. In the meantime, technological advancements, cost reduction, and governmental incentives have made some renewable energy sources more competitive in the market. Among them, wind energy is one of the fastest growing renewable energy sources. [11] Solar technology is also developing fast and has much to offer despite the currently high costs. However, to make a significant contribution to bulk electricity generation, a major technology and cost reduction is required. Thin film PV has the potential to deliver cheaper electricity. Currently, commercial interest centers around thin film nano-crystalline hybrid cells and the hetero junction cells based on copper indium di-selenide and cadmium telluride. Both of the latter provide reasonably stable efficiencies and are expected to benefit from improved manufacturing techniques. There is currently a flurry of investment activity in these technologies that includes manufacturing on to glass, and metal and polymer foils. Industry experts confidently expect that the new mass production technologies will deliver cells capable of generating 20 electricity competitively with conventional forms and nuclear perhaps within the next 10 years. [2] Future grid developments undoubtedly will have to accommodate for the integration of renewable energies in the transmission and distribution grid. Due to rapid development of renewable energies and their integration into the grid, the grid codes in many countries have been updated to address the issues related to renewable energy power generation. Differences in various grid codes also stem from regional and geographical conditions, usually based on the experience of operating the power system, acquired by the utility. However, their ultimate goal is to ensure safe, reliable, and economic operation of power system. The main elements in the grid codes include fault ride through requirements, active / reactive power control, frequency / voltage regulation, power quality, and system protection. [9] Power systems have developed over the years to supply a varying demand from a centralized generation sourced from fossil and nuclear fuels, There seems to be a universal agreement that by the end of this century the majority of our electrical energy will be supplied from Renewable Energy (RE) sources. Unfortunately, due to the small sizes of these generators, they cannot connect to the transmission system because of the high cost of high voltage transformers and switchgears. In addition, the transmission system is often a long way away as the geographical location of the generator is constrained by the geographical availability of the resource. Small generators must 21 therefore connect to the distribution network. Such generation is known as distributed or dispersed generation. [2] In traditional power systems power invariably flows from the large centralized power stations, which connect to the EHV network down through the HV and LV systems to distribute power to consumers. In power system with the distributed generation, power may travel from point to point within the distribution system. This unusual flow pattern has some serious implications in the effective operation and protection of the distributed network [35]. It may be concluded that present power systems will gradually have to evolve and adapt so that, in the far future, a managed demand will be supplied from distributed, mostly variable, RE generation. This transformation will be aided by the liberal use of power electronic interfaces capable of maximizing the effectiveness of RE sources, controlling power flows, and ensuring reliability of supply. Additionally, other changing technology changes are affecting the utility planning process. Today, e.g., we have more than 3,300 plug-in vehicles on San Diego roads, and the numbers could grow quickly. However, the challenge for operating utility is not necessarily the number, as much as it is when the vehicles charge. The utility’s goal is to make sure the vehicles are grid integrated, which means that the majority of charging will happen at times of day when the grid has an abundance of energy, and not at times when 22 energy is scarce. With this kind of integration, charging costs and emissions will be lower due to more efficient use of the grid and our generation resources, which will help the utility customers to realize the many benefits of these environmentally friendly vehicles. This concept of effective integration is vital because of the charging capability of each vehicle. Right now most of these vehicles can charge at a rate of about 3 to 7 kilowatts, and some models just entering the market are capable of charging at up to 20 kilowatts or more [14]. Another technique the utility company has in their tool box of solutions is the Conservation Voltage Reduction (CVR) [15]. CVR is a proven technology for reducing energy and peak demand. By more fully utilizing existing distribution automation equipment, smart grid technologies, and communicating with meters and switchable devices, capital purchases can be avoided or delayed. In addition, CVR has the potential to be Energy Efficiency (EE) resource by helping utilities maximize returns while meeting EE goals. Today, technologies exist to change the CVR operating paradigm. Pilot projects based on smart grid technologies and real-time operating systems show energy savings and demand reductions of 3% are possible. In fact, the Pacific Northwest National Laboratory (PNNL) estimated total CVR energy savings in the US alone to be 6,500 MWs or 56,940,000 MWh—or the equivalent of Grand Coulee Dam operating at nameplate capacity for a year [15]. Pilot projects, funded in part with stimulus dollars, are uncovering promising results: Voltage regulation has been a critical part of power system operation since Thomas Edison first lit electric lights over Menlo Park on New Year's 23 Eve in 1880. For many years, electric utility companies initiated load reductions during critical peak load periods by reducing voltages delivered to air conditioners, home appliances and industrial machinery. CVR can be accomplished through a variety of conventional technologies (tapchanging transformers, line drop compensators, generator excitation controls, voltage regulators, line switchable capacitor banks, static VAR compensators, circuit reconfiguration, and load control) enhanced with microprocessor controls and communication packages. The challenge quickly becomes defining specific control schemes, monitoring points, sensor technologies, protocols, triggering mechanisms, etc. Energy is saved by maintaining voltages close to lower thresholds without going below them. If the priority is to regulate end-user voltages, energy consumption is reduced, saving dollars for the end-user. If losses are to be minimized, feeder volts and VARs are regulated, reducing energy, releasing line capacity and saving dollars for the utility company. 24 Chapter 4 OPTIMIZATION METHODOLOGY The dynamic programming technique should be used to optimize the objective function of power distribution system planning. In its simplest sense, dynamic programming can be thought of as an attempt to break large, complex problems into a series of smaller problems that are easier to solve separately. There are number of decision stages in the dynamic programming at each stage and there are several alternate courses of action with each stage. The decision generated by stage one, acts as conditions of the problem for stage two and so on. In other words, at each of the several stages there is a choice of decisions and the decisions, initially taken affect the choice of subsequent decisions. The various rules of decision making can be established after considering the effects of each decision (separately) and the optimum policy for further decisions. The basis of dynamic programming is to select the best amongst the final possible alternative decisions. This process is then repeated, ignoring all those alternatives which do not lead to selected best (optimum). The best sequence of decisions can thus be defined, by repeating the above process. Safigianni’s paper [4] has shown remarkably that the full optimization process depends on optimization of a full multi-objective function. Please refer to the flow chart of the optimization process as shown below. 25 Figure 4.1 Flow Chart of Safigianni’s Optimization Process Role of optimization undoubtedly can be broad and comprehensive, or narrow and specific. For example based on the pioneering earlier works cited by Dr. Gonen, a Nigerian team took it one step further by the use of integer programming technique. 26 (Alternatively, and more comprehensively, one may look at the distribution system sizing to include the reliability of the distribution system as well [13]. Depending on the choice, these many other considerations may do enter into the algorithm formulation. Ultimately, distribution engineers need to present a dynamic approach towards the sustainability of power distribution system using a comprehensive application. The cost of energy losses, substation cost, feeder cost, and outage cost can be developed using dynamic programming technique and a three stage iterative solution with the aim to optimize the outage costs. For example, the three stages of optimization could be carried out to determine, the number of substation sites and exact location, the feeder routes and the load flow in the network, and the outage cost to cover system node reliability evaluation. In our paper, we implemented a method for minimizing Total Annual Cost (TAC) of installing and operating the secondary portion of a three-wire single-phase distribution system in a residential area, as has been elaborated in Dr. Gonen’s Distribution Book. This can be applied to underground or overhead distribution. Similarly, one can apply the optimization techniques to sectors of the power system, ignoring the reliability aspects for the moment (since integer programming is beyond our current solution to the problem). We have formulated and written a MATLAB program for the calculation and we obtained the near optimized results, by using computer math power for speed and accuracy in selecting the most economically justified alternative in a simple residential radial distribution section. 27 The numerical tabulated example run results in chapter 6 are the testimony to this endeavor. A few of these MATLAB computer calculations have been compared with hand formulated calculation, for verification purpose. Results match very well for all practical purposes. The constraint in the program is the degree of voltage drop that system encounters. The distribution system design engineer must of course take the optimum design size calculated and assure the utility with confidence that load is not going to affect the system voltage severely. Sometimes, the design requires upsizing the secondary conductors and occasionally in the existing systems, re-conductoring with bigger size wires will be needed. The aim of the re-conductoring process is the satisfaction of the voltage drop criterion or the protective devices condition, or both of them. Every combination of conductor replacements, which satisfies the above conditions, is a solution to the problem. Theoretically, there are many solutions for a given network but only a few of them are technically acceptable. Our implementation of the Matlab program depended on making some assumptions. The technically acceptable solutions satisfy the given constraints below: 1. A conductor of a bigger size but of the same type must always replace one span conductor. (There are three conductor types: overhead bare lines, underground cables and overhead twisted cables). 28 2. New type conductors must replace old type conductors, which are no longer in use (e.g. XLPE cables replace paper insulated cables). 3. Because of the big replacement cost, the underground cables are the last solution in the reconductoring process and they are replaced if nothing else can be done. Obviously, our approach has to contain simplicity to be programmed with the help of computer program. (Dr. Gonen has added the costs of a uniform residential distribution system in his Distribution book.) It entails dividing the costs into installation costs and operating costs of the distribution system, annualized over the asset life. (It is important to use asset life annualized since different modifications may have different life and it provides a uniform basis for our comparison). We then take a partial differential derivative with respect to each variable, size of the transformer, cross section area of service lateral, and cross area of the Service Drop. Equating each of these equations to zero will yield us the computationally optimal value. However, this value does not necessarily yield to a standard size of transformer or wire, per se. Therefore, we have created a logic ladder where the program ascertains the sizes against the input given values and automatically progresses to the next size. When the transformer is chosen, then the next wire SL will be selected, and then finally SD size will be determined by the program. We have provided the voltage drop as a major constraint where the value obtained will be tested with a logic statement for being over five (5) percent of the value 29 allowed in distribution voltage drop. A sample of the Optimization Program is provided in Appendix A. Furthermore, we have completed this constraint as a separate Matlab program by itself where students can input different distribution problem input data and verify the voltage drop within a sector of a secondary radial configuration. A sample of this program is shown in Appendix C. Of course the extent of introducing a multi objective function with the introduction of reliability parameters, maintenance, protection systems, etc. into our study is beyond the concept of this master’s project, given the wealth of information topics that were collected for these authors,. What we had to reduce, however, was the essential parts of a secondary system that we could grapple with and could introduce it with our simple Matlab programming. The following page flow chart Figure 4.1 shows the concept of our work from the adapted flow chart as shown by Safigianni’s paper [4]. 30 Read the Input Data Calculate Load Obtain the second order polynomials and obtain the derivative equations Calculate Optimum Transformer Size and Distribution Wires Provide a Safe Reserve Margin For Future Growth Formulate Criteria Choose Next Standard Available Transformer Size Block dimensions are asked via queries Input to the Program Standard Lateral Distribution configuration is assumed Calculate Optimum and then Choose Standard Available Service Lateral Size Is the Chosen Standard Size Cost Optimal? Yes No Calculate Optimum and then Choose standard Service Drop available Size Calculate the Voltage Drop Constraint to see Feasibility Is the Voltage Regulation too high? Yes No Print the Optimal Combinations that met the Criteria MATLAB PROGRAM FLOW CHART Figure 4.2 Matlab Program Flow Chart Source Provided by Authors Comments ? Requested 31 We recognize, of course, that the primary and secondary systems can be simple or complex as well. Figure 4.3 below shows an extensive primary system. Typically, in the residential developments, one block of residential area consists of two pole mounted distribution transformers, which feed twelve houses. This design determines the optimal size for transformers, primary conductors, and secondary conductors. The optimization process requires meeting a certain condition and perhaps holding some assumptions as well to do it properly. In this project, we constructed and analyzed the Total Annual Cost (TAC) of initial procurement, installation, and operating cost of secondary distribution system and provided a Matlab computer program to solve for optimum commercially available size of transformer and wires. We also elaborated on the calculation method to minimize TAC and approximately optimize the system the way that will be most efficient. Furthermore, we illustrated thru the program that this minimized design satisfies the voltage drop constraint, and therefore, the voltage dip will not exceed the tolerance criteria. 32 Figure 4.3 One Line Diagram of Multiple Primary System for John Hancock Center Source: (From Fink, D.G., and H. W. Beaty, Standard Handbook for Electrical Engineers, 11th edition, McGraw-Hill, New York, 1978. With permission.) The Following Figure 4.4 shows one section of secondary distribution system which has two transformers, and each is feeding 12 customers (loads). This system is in a straight line design and is expected to have width ‘d’ which makes each section of secondary line (SL) length ‘2d’. If a secondary line is not used every four customer will have one transformer. 33 Figure 4.4 Typical Residential Area Lot Layout and Service Arrangement Source: Electric Power Distribution System Engineering, by Dr. Gonen In this system over head cable or underground cable can be used. If over head cable is used, then the transformers are pole mounted and if the underground cable is used, the transformers are grade-mounted on a concrete slab. The SL and the SD can be either open-wire or triplex cable construction. Pole or underground pad-mounted submersible transformer Pedestal or hand hole (on pole or underground) ST SD SD SD SD SD SD SD SD SD SD SD SD Alley or Near Lot Line Illustration of a Typical Pattern Figure 4.5 Illustration of a Typical Residential Secondary Pattern Source By Authors 34 The following parameters are used in our calculations: ST=transformer capacity, continuously rated kVA Iexc=per unit exciting current (based on ST) PT, Fe=Transformer core loss at rated voltage and rated frequency, kW PT, Cu=transformer copper loss at rated kVA load, kW ASL and ASD=conductor area, kcmil P=conductor resistivity, (Ω- cmil)/ft The following assumptions are made to make the calculation easier and possible: 1. All services are single-phase, three-wire, 120/240V 2. All three wire circuits have perfectly balanced loading 3. The system is energized at all the time 8760 hours per year 4. The annual loss factor is calculated by Fls=0.3*Fld+j0.7*Fld^2 5. All loads have the same power factor (constant) The total cost depends on number of transformer, type and size of conductors, distance and other parameters, which for simplicity and calculation purposes we will make some assumption in our calculation. For calculation of the TAC we need to know the followings: 1. Annual installed cost of transformer and associated protective equipment(ICT) 2. Annual installed cost of triplex aluminum SL cable (ICSL) 3. Annual installed cost of triplex aluminum SD cable (ICSD) 4. Annual installed cost of pole and hardware on it (ICPH) 35 5. Annual operation cost of transformer exciting current (OCexc) 6. Annual operating cost of transformer due to iron losses (OCT, Fe) 7. Annual operating of transformer due to copper losses (OCT, Cu) 8. Annual operating cost of copper loss in a unit length of SL (secondary line)(OCSL) 9. Annual operating cost of copper loss in a unit length of SD (Service Drop)(OCSD) TAC formula has three main variables: Transformer Capacity, Conductor Area of SL (ASL), and Conductor Area of SD (ASD). For minimizing the ATC, we will take three partial derivatives and set each derivative to zero. However, this optimized number is not necessarily a practical one by any means. Since the sizes of materials are usually given in discrete values, we must choose the next size Up or Down, depending on the choice. Here is where our logic selection ladder automatically chooses the next commercial available size, subject to the voltage constraint. MATLAB programs are written for the calculation and getting the result faster and more accurately. Towards the end of this assignment, we will have some examples to test our MATLAB program and compare the result in MATLAB with hand calculation. 36 1. ICT which is the annual installed cost of distribution transformer and associated protective devices is calculated by following formula ICT = (2000 + 58.08 x ST) x i $/transformer ST is transformer rated kVA and is between 15kVA and 100kVA 2. ICSL is annual installed cost of triplex aluminum SL cable is calculated by following formula: ICSL = (480+ 36 x ASL) x i $/1000ft ASL is conductor Area in kcmil. This cost is for 1000 ft of cable, which is 3000 ft conductor. 3. ICSD is annual installed cost of triplex aluminum SD cable is calculated by following formula ICSL= (480+36 x ASD) x i $/1000ft ASD is conductor Area in kcmil. The ICSD and ICSL are alike since in this example the same kind of conductor will be used for both SL and SD 4. ICPH is the annual installed cost of pole and hardware on it. ICPH =1280 x i $/pole 37 5. OCexe is the annual operating cost of transformer exciting current OCexe = Iexc x ST x ICcap x i $/transformer ICcap is total installed cost of primary-voltage shunt capacitor = $5.00 /kvar Iexc is the average value of the transformer exciting current base on ST = 0.015 pu 6. OCTFe is annual operating cost of transformer due to core (iron) losses. OCTFe = (ICsys x i + 8760 x ECoff) x PTFe $/transformer ICsys is the average investment cost of power system upstream toward the generator from distribution transformer = $2,800/kVA ECoff is incremental cost of electric energy (off-peak) = $ 0.015/kWh PTFe is the annual transformer core loss kW = 0.004 x ST 7. OCTCu is the annual operation cost of transformer due to copper losses OCTCu = (ICsys x i +8760 x Econ x FLS) (Smax/ST)^2 x PTCU $/transformer ECon is the incremental cost (on-peak) = $0.02 /kWh Smax is the annual maximum kVA demand on transformer PTCu is the transformer copper loss, kW at rated kVA PTCu = 0.073 + 0.00905 x ST FLS is the annual loss factor 8. OCSLCu is the annual operating cost of copper loss in unit length of SL OCSLCu = (ICsys x i +8760 x ECon x FLS) x PSLCu 38 PSLCu is the power loss in unit of SL at the time of annual peak load due to copper losses kW PSLCu is an R x I^2, and it must be related to conductor area ASL with R = pL/ASL 9. OCSDCu is the annual operating cost of copper loss in unit length of SD OCSDCu = (ICsys x i +8760 x Econ x FLS) x PSDCu PSLCu is the power loss in unit of SD at the time of annual peak load due to copper losses kW PSDCu is an R x I^2, and it must be related to conductor area ASL with R = pL/ASD To find the equation for TAC, the above nine formulas need to be added together. When these formulas are added together (and with some assumption), TAC equation will be reduced to a function of three design variables, TAC = f (ST, ASD, ASL) It has to be noted that many parameter, such as the fixed charge rate i, transformer core and copper losses, installed cost of poles and lines are contained in constant coefficients A to H in TAC function. TAC = A+ B/ST^2 + C/ST + D x ST + E x ASD + F/ASD + G x ASL + H/ASL 39 After substituting the fixed parameter (approximate assumption) we will have; TAC = (6.048*ASD) + (4.32*ASL) + (14.9522*ST) + 374.536*L1*(L1/ASD) + 2141.28*L4*(L4/ASL) + (6589.33*(L12/ST)*(L12/ST)) + (816.9*L12*(L12/ST)) + 1306.24; L1= Max load for 1 costumer L4= Max load for 4 customers La12= Max load for 12 customers From Table (4.1), Class 2, we have: L1=10, L4=6, and La12= 4.4 TABLE 4.1 Load Data for Book Example 6.1, Source: Electric Power Distribution System Engineering Book, by Dr. Gonen 40 Basically, if above loads and the dimensions of SL and SD cable and the size of transformer are known, TAC for secondary distribution system can be calculated. For example if 39 kVA transformer with ASL of 205 kcmil and ASD of 85.4 kcmil are used with above loads the TAC = $4595 /block And if 50 kVA transformer with ASL of211.6 kcmil and ASD of 105.5 kcmil are used with above loads the TAC = $4693 /block And if 50 kVA transformer with ASL of250 kcmil and ASD of 133.1 kcmil are used with above loads, the TAC = $4896 /block Minimizing TAC For minimizing TAC, since TAC is a function of three variable, using TAC equation and taking three partial derivatives will set each derivative equal to zero and it follows; d(TAC) / d(ST) = 0 d(TAC) / d(ASL) = 0 d(TAC) / d(ASD) = 0 The result of above equations that are used henceforth merely serve as indicators of the region that contains the minimum TAC achievable with standard commercial equipment size. The problem is further continued by computing TAC for the standard commercial sizes of equipment nearest to the results of above equations. 41 There are additional criteria which must be met in the total design of the distribution system, whether or not minimum TAC is realized. The further criteria involve quality of utility service. Minimum TAC designs may be encountered which will violate one or more of the commonly used criteria: 1. A minimum allowable steady-state voltage at the most remote service entrance may have been set by law, public utility commission order, or company policy. 2. A maximum allowable motor-starting voltage dip at the most remote service entrance similarly may have been established. 3. Ordinarily the ampacity of no section of SLs or SDs should be exceeded by the designer. 4. The maximum allowable distribution transformer loading, in per unit of the transformer continuous rating should not be exceeded, by the designer. Matlab Programs There are two Matlab program written for TAC. An extra third Matlab program is also provided to calculate voltage drop in a secondary system. The first one is called Optimize-TAC.Rev24 (Appendix A) and it minimizes TAC by asking for loads as inputs. It then calculates the optimized sizes for ST, ASL and ASD, and it finally determines the optimized TAC. In this program not only the 42 optimized sizes of equipment and TAC are calculated, but also, the standard size and TAC for standard size equipment will be picked by the program. The second one (Appendix B) calculates the TAC by asking the three loads and sizes of ST (in kVA), ASL (in kcmil) and ASD (in kcmil), as inputs. It is called TACtotal and it is basically serving as a calculator for arriving at TAC value. The third program (Appendix C) is provided as a courtesy in addition to the other matlab programs so the future students can calculate or analyze a typical secondary system voltage drop. This program is called OnlyVoltageDrop and it queries for the size of transformer, SL, and SD and it then calculates the voltage drop total and by element. Voltage drop is an independent constraint set to alter program calculation in the Optimize-TAC program. However, we felt it will be useful to provide it also independently as a calculator. Copies of each program and program instructions are also attached for your review (in Appendices). Furthermore, the computer program flow diagram was also provided in Chapter 3. 43 Chapter 5 ECONOMIC ESTIMATION AND ANALYSIS We began our master’s project, of course, with the understanding that we will be solving the Secondary Distribution System Optimization problem with the help of computer provided Matlab programming and using a simplified radial distribution as an example. In doing so, we had to gather a more current set of data, which we also verified by a utility company recent purchases for a close approximation and validity of material and labor costs. Similarly, we obtained in place unit cost of these material and equipment with National Construction Estimator (NCE) tabulated book index to arrive at the Total Annualized Cost function. Consequently, several other factors, such as the cost of electricity, capacitors, and transformers had to be revised upward from the figures initially shown in Dr. Gonen’s Distribution System book about three decades earlier. We wanted to compare the efficiency of the transformers to earlier values, as it was not clear to us if significant technological advances have been made in this area. We then provided several linear regressions of Matlab algorithms to be able to categorize choices and result in the final determined values in our Optimization Program. Cost analyzes have been discussed in this paper. The Two Matlab programs that have been provided work out the TAC cost if the input data file is provide in the Matlab 44 folder. The OptimizeTAC program will figure out the best combination of elements when optimized for their size and subject to the voltage constraints and its TAC cost, as shown in Appendix A. This optimization program provides the near optimized cost for the components. It will further reflect the annualized cost for the given design parameters of our distribution system. We have surveyed the L.E Means and National Construction Estimator books to obtain more recent cost data. The cost figures reported are for the mineral insulated aluminum conductors with the steel cores. We had to provide the linear regression function for the obtained data to make sure it would be in that window of 4 to 8 times cost escalation that we had arrived at before. The data is shown in the input Excel sheet that the program reads from. Additionally, we contacted SMUD for transformers and capacitors data, and we obtained their more recent purchases. We have performed linear regression functions on these data as well, to arrive at the best-fit cost for the given size. Across the board, we observed the typical economical values have increased between 4 to 8 times of preliminary Westinghouse number reported by Dr. Gonen in his Distribution book example, page 299. (Refer to Transformer cost in Figure 5.1 and 5.2, shown below retrospectively.) 45 Current Cost vs. Transformer kVA 14000 12000 Cost ($) 10000 8000 6000 4000 2000 0 10 15 25 37.5 50 75 100 167 100 167 Transformer in kVA Figure 5.1 Current Transformers Cost Source Provided by NCE Historic Cost vs. Transformer KVA 1600 1400 Cost ($) 1200 1000 800 600 400 200 0 10 15 25 37.5 50 75 Transformer in kVA Figure 5.2 Historic Cost of Transformers Source Provided by NCE 46 Surprisingly, capacitor mass production technology has managed to provide relatively lower cost despite the inflation. SMUD purchases reflect cost to be about three to four times the original indicated values. Similarly, the utilities markup for on-peak and off-peak energy generation has been relatively contained due to the competition in a heavily regulated electric market. We suspect that markup to be between three to four times what originally assumed in the reference. Given the approximation that cost of material and labor have at least risen four to six percent a year, Every 12 to 14 years it will be twice the cost. Carrying that methodology forward 36 years, one can reasonably expect the material and prices to have increased by a factor of 6 to 8 times more than original reported in the Distribution Book Since these data were originally taken from the late seventies references, it translate into 4 to 8 times the original estimates. In fact, current cost of transformers and wires support this assertion, and furthermore, the two graphs we have provided above and below (Figures 5.3 and 5.4) sustain this assertion. 47 Current Cable Cost vs. kcmil 12000 10000 Cost ($) 8000 6000 4000 2000 0 41.74 52.74 66.36 83.69 105.6 133.1 kcmil Figure 5.3 Current Cable Cost Source Provided by NCE 167.8 211.6 250 48 Historic Cable Cost vs. kcmil 1600 1400 1200 Cost ($) 1000 800 600 400 200 0 41.74 52.74 66.36 83.69 105.6 133.1 kcmil Figure 5.4 Historic Cable Cost Source Provided by NCE 167.8 211.6 250 49 Chapter 6 NUMERICAL RESULTS Many low voltage distribution networks in the United States are typically a 12 kV primary 120/ 240 secondary system, and in the residential areas they are usually served by single-phase distribution circuit, as shown in Figure 4.5. We performed linear regression data fit into a third order polynomial function based on the transformer cost data we had obtained from the utility company (SMUD in this case) and also the typical construction cost reporting (Means). The data from transformers cost was fit perfectly into a third order polynomial, per earlier book citation [1]. The total variations never exceeded more than about 2 to 4 percent from the data, and that is practically the error margin in the survey in the first place. The conductor data were also consecutively fit into the second order polynomial, as well. Matlab command Polyfit was extremely powerful to help fit data into other polynomial orders. The results are shown in Figures 6.1 and 6.2. The data provided below along with the Figures are the testimony for this data match: 50 Single-Phase Residential Distribution Transformers No Total Rated Load Load Cu Z Mat. Labor OH Total Volt Z Actual I@ 208 V Loss Losses Loss (%) $ $ $ $ Base Ohms X 10 48.1 28.5 176 148 1.900 1100 455 325 1880 240 9.480 0.109 15 72.1 31.9 265 233 1.900 1500 605 445 2550 240 6.325 0.073 25 120.2 53.6 344 290 2.200 2050 730 545 3325 240 4.393 0.051 37.5 180.3 71 462 391 1.800 2650 910 715 4275 240 2.396 0.028 50 240.4 90.1 566 476 1.800 3150 1050 800 5000 240 1.797 0.021 75 360.6 130.5 694 564 2.300 4175 1125 950 6250 240 1.531 0.018 100 480.8 185 864 679 2.000 5747 995 1011 7753 240 0.998 0.012 167 802.9 500 2100 1600 2.100 9000 1125 1513 11638 240 0.628 0.007 Size 51 Transformer Data Vs. Third order model Series1 Series2 Unit Cost ($) 11567 7391 6297 11638 5031 4249 3322 2453 1970 1880 1 2550 2 3 5000 4275 3325 4 5 7431 6250 6 7 8 Transformer Sizes Figure 6.1 Transformer Cost Fit Into Third Order Model Source Provided by NCE Distribution Aluminum Wires in Triplex arrangement for Residential Sectors Wire (Values given are for 1000 ft length) Wire No. Size Rating Resis I (A) R Z DC AC #6 X IZ I2R Mat. Labor Indirect Total Area $ $ & OH $ $ kcmils 26.24 #4 1 140 0.4 0.52 0.3323 2130 1660 1000 4790 41.74 #3 2 155 0.32 0.41 0.2563 2310 1740 1080 5130 52.74 #2 3 185 0.25 0.32 0.1997 2520 1820 1150 5490 66.36 #1 4 210 0.2 0.27 0.1814 2890 1820 1150 5860 83.69 #1/0 5 240 0.16 0.21 0.136 3200 1920 1230 6350 105.6 #2/0 6 275 0.12 0.17 0.1204 4000 2020 1380 7400 133.1 #3/0 7 315 0.1 0.14 0.098 4600 2150 1520 8270 167.8 #4/0 8 360 0.08 0.12 0.0894 5200 2280 1670 9150 211.6 #250 9 450 0.06 0.08 0.0529 6450 2430 1870 10750 250 52 Cable Data Vs. Second Order Model Axis Title 300 200 Series1 100 Series2 0 1 2 3 4 5 6 Series1 7 8 Cable Sizes Figure 6.2 Cable Cost Fit Into Second Order Model Source Provided by Authors Cable Size vs. Cost 12000 10000 Cost $ 8000 6000 4000 2000 0 #4 #3 #2 #1 #1/0 #2/0 #3/0 Cable Size Figure 6.3 Cable Cost For Different Sizes Source Provided by Authors #4/0 #250 53 Table 6.1 --Summary of the Runs (Source Provided by Authors) i=10% Run 1 Run 2 Run 3 Run 4 Run 5 Run 6 Class 1 10,12,18 kVA SL=320ft SD=80ft Class 1 10,12,18 kVA SL=480ft SD=120ft Class 2 4.4,6,10 kVA SL=320ft SD=80ft Class 2 4.4,6,10 kVA SL=480ft SD=120ft Class 3 1.2,1.5, 2.5 kVA SL=320ft SD=80ft Class 3 1.2,1.5, 2.5 kVA SL=480ft SD=120ft ST-kVA 80.94 80.94 38.71 38.71 13.217 13.217 ASL-kcmil 267.19 267.19 133.59 133.59 33.4 33.4 ASD-kcmil 141.7 141.7 78.72 78.72 19.68 19.68 TAC-$ 8127 10447 4750 6005 2254 2626 ST-kVA 100 100 50 50 15 15 ASL-kcmil 300 300 167.8 167.8 41.74 41.74 ASD-kcmil 167.8 167.8 83.69 83.69 41.74 41.74 TAC-$ 8230 10573 4827 6099 2348..5 2766 Total -percentage (%) 6 7.27 6.18 7.45 5.55 6.364 VDT-Transformer 2 2.4 1.9 1.9 1.824 1.824 3 3.845 3.539 4.44 3.365 3.997 0.684 1.026 0.742 1.113 0.3615 0.542 Low Electric Markup , ECoff= 0.015, ECon = 0.02, Power Factor = 0.9 Optimized Standard Voltage Drop VDSL-Service Lateral VDSD-Service Drop 54 Table 6.1 --Summary of the Runs Continued (Source Provided by Authors) i=15% Run7 Run 8 Run 9 Run 10 Run 11 Run 12 Low Electric Markup , ECoff= 0.015, ECon = 0.02, Power Factor = 0.9 Class 1 10,12,18 kVA SL=320ft SD=80ft Class 1 10,12,18 kVA SL=480ft SD=120ft Class 2 4.4,6,10 kVA SL=320ft SD=80ft Class 2 4.4,6,10 kVA SL=480ft SD=120ft Class 3 1.2,1.5, 2.5 kVA SL=320ft SD=80ft Class 3 1.2,1.5, 2.5 kVA SL=480ft SD=120ft ST-kVA 80.48 80.48 38.5 38.5 13.15 13.15 ASL-kcmil 262.4 262.4 131.2 131.2 32.8 32.8 ASD-kcmil 139.16 139.16 77.31 77.31 19.32 19.32 TAC-$ 11968 15387 7016 8866 3350 3901 ST-kVA 100 100 50 50 15 15 ASL-kcmil 300 300 133.1 133.1 41.74 41.74 Optimized Standard ASD-kcmil 167.8 167.8 83.69 83.69 41.74 41.74 TAC-$ 12142 15603 7086 8939 3498 4120 Total -percentage (%) 5.648 7.2719 6.923 7.45 5.55 6.364 VDT-Transformer 2.4 2.4 1.9 1.9 1.824 1.824 VDSL-Service Lateral 2.563 3.845 4.28 4.44 3.365 3.997 VDSD-Service Drop 0.684 1.0264 0.742 1.113 0.3615 0.0542 Voltage Drop 55 Table 6.1 --Summary of the Runs Continued (Source Provided by Authors) i=10% Run13 Run14 Run15 Run16 Run17 Run18 Class 1 10,12,18 kVA SL=320ft SD=80ft Class 1 10,12,18 kVA SL=480ft SD=120ft Class 2 4.4,6,10 kVA SL=320ft SD=80ft Class 2 4.4,6,10 kVA SL=480ft SD=120ft Class 3 1.2,1.5,2.5 kVA SL=320ft SD=80ft Class 3 1.2,1.5,2.5 kVA SL=480ft SD=120ft 82.2 82.2 39.28 39.28 13.39 13.278 ASL-kcmil 281.07 281.07 140.54 140.54 35.134 33.99 ASD-kcmil 149.06 149.06 82.81 82.81 20.7 20.03 8563 10999 4966 6282 2313 3977 ST-kVA 100 100 50 50 15 15 ASL-kcmil 300 300 167.8 167.8 41.74 41.74 ASD-kcmil 167.8 167.8 83.69 83.69 41.74 41.74 TAC-$ 8638 11084 5027 6354 2397 4179 Total -percentage (%) 5.648 7.272 6.182 7.453 5.55 6.364 VDT-Transformer 2.4 2.4 1.9 1.9 1.824 1.824 VDSL-Service Lateral 2.563 3.845 3.539 4.44 3.365 3.997 VDSD-Service Drop 0.684 1.026 0.742 1.113 0.3615 0.5423 High Electric Markup , ECoff= 0.03, ECon = 0.04, Power Factor = 0.9 Optimized ST-kVA TAC-$ Standard Voltage Drop 56 Table 6.1 --Summary of the Runs Continued (Source Provided by Authors) i=15% Run19 Run20 Run21 Run22 Run23 Run24 High Electric Markup , ECoff= 0.03, ECon= 0.04, Power Factor = 0.9 Class 1 10,12,18 kVA SL=320ft SD=80ft Class 1 10,12,18 kVA SL=480ft SD=120ft Class 2 4.4,6,10 kVA SL=320ft SD=80ft Class 2 4.4,6,10 kVA SL=480ft SD=120ft Class 3 1.2,1.5, 2.5 kVA SL=320ft SD=80ft Class 3 1.2,1.5, 2.5 kVA SL=480ft SD=120ft ST-kVA 81.39 81.39 38.91 38.91 13.278 13.278 ASL-kcmil 271.9 271.9 135.95 135.95 33.987 33.987 ASD-kcmil 144.2 144.2 80.11 80.11 20.03 20.03 TAC-$ 12411 15949 7234 9148 3411 3977 ST-kVA 100 100 50 50 15 15 ASL-kcmil 300 300 167.8 167.8 41.74 41.74 Optimized Standard ASD-kcmil 167.8 167.8 83.69 83.69 41.74 41.74 TAC-$ 12549 16114 7341 9276 3547 4179 Total -percentage (%) 5.648 7.27 6.182 7.453 5.55 6.36 VDT-Transformer 2.4 2.4 1.9 1.9 1.824 1.824 VDSL-Service Lateral 2.564 3.845 3.539 4.44 3.365 3.997 VDSD-Service Drop 0.684 1.026 0.742 1.113 0.3615 0.5423 Voltage Drop 57 Table 6.1 --Summary of the Runs Continued (Source Provided by Authors) i=10% Run 25 Run 26 Run 27 Run 28 Run 29 Run 30 Class 1 10,12,18 kVA SL=320ft SD=80ft Class 1 10,12,18 kVA SL=480ft SD=120ft Class 2 4.4,6,10 kVA SL=320ft SD=80ft Class 2 4.4,6,10 kVA SL=480ft SD=120ft Class 3 1.2,1.5, 2.5 kVA SL=320ft SD=80ft Class 3 1.2,1.5, 2.5 kVA SL=480ft SD=120ft ST-kVA 80.94 80.94 38.71 38.71 13.217 13.217 ASL-kcmil 267.19 267.19 133.59 133.59 33.4 33.4 ASD-kcmil 141.7 141.29 78.72 78.72 19.68 19.68 TAC-$ 8127 10447 4750 6005 2254 2626 ST-kVA 100 100 50 50 15 15 ASL-kcmil 300 300 167.8 167.8 41.74 41.74 ASD-kcmil 167.8 167.8 83.69 83.69 41.74 41.74 TAC-$ 8230 10573 4827 6099 2349 2766 Total -percentage (%) 5.6 7.2 6.405 7.854 5.643 6.45 VDT-Transformer 2.4 2.4 1.9 1.9 1.824 1.824 VDSL-Service Lateral 2.479 3.718 3.732 4.795 3.448 4.07 VDSD-Service Drop 0.721 1.0826 0.7721 1.158 0.3705 0.555 Low Electric Markup , ECoff= 0.015, ECon=0.02, Low Power Factor = 0.7 Optimized Standard Voltage Drop 58 Table 6.1 --Summary of the Runs Continued (Source Provided by Authors) i=15% Run 31 Run 32 Run 33 Run 34 Run 35 Run 36 Low Electric Markup , ECoff= 0.015, ECon = 0.02, Power Factor = 0.7 Class 1 10,12,18 kVA SL=320ft SD=80ft Class 1 10,12,18 kVA SL=480ft SD=120ft Class 2 4.4,6,10 kVA SL=320ft SD=80ft Class 2 4.4,6,10 kVA SL=480ft SD=120ft Class 3 1.2,1.5, 2.5 kVA SL=320ft SD=80ft Class 3 1.2,1.5, 2.5 kVA SL=480ft SD=120ft ST-kVA 80.48 80.48 38.5 38.5 13.15 13.15 ASL-kcmil 262.4 262.4 131.2 131.2 32.8 32.8 ASD-kcmil 139.14 139.14 77.31 77.31 19.33 19.33 TAC-$ 11968 15387 7016 8866 3350 3901 ST-kVA 100 100 50 50 15 15 ASL-kcmil 300 300 133.1 133.1 41.74 41.74 ASD-kcmil 167.8 167.8 83.69 83.69 41.74 41.74 TAC-$ 12142 15603 7086 8939 3498 4120 Total -percentage (%) 5.6 7.2 7.206 7.854 5.643 6.45 VDT-Transformer 2.4 2.4 1.9 1.9 1.824 1.824 VDSL-Service Lateral 2.478 3.718 4.53 4.795 3.448 4.07 VDSD-Service Drop 0.721 1.0826 0.772 1.158 0.3705 0.555 Optimized Standard Voltage Drop 59 Table 6.1 --Summary of the Runs Continued (Source Provided by Authors) i=10% Run 37 Run 38 Run 39 Run 40 Run 41 Run 42 Low Electric Markup , ECoff= 0.015, ECon = 0.02, Power Factor = 0.9 Class 1 10,12,18 kVA SL=320ft SD=80ft Class 1 10,12,18 kVA SL=480ft SD=120ft Class 2 4.4,6,10 kVA SL=320ft SD=80ft Class 2 4.4,6,10 kVA SL=480ft SD=120ft Class 3 1.2,1.5,2.5 kVA SL=320ft SD=80ft Class 3 1.2,1.5,2.5 kVA SL=480ft SD=120ft 13.217 13.217 Optimized * * ST-kVA 80.94 80.94 38.71 38.71 ASL-kcmil 267.19 267.19 133.59 133.59 33.4 33.4 ASD-kcmil 141.7 141.29 78.72 78.72 19.68 19.68 TAC-$ 8127 10447 4750 6005 2254 2626 100 100 50 50 15 15 ASL-kcmil 350 300 205 300 66.36 105.6 ASD-kcmil 167.8 Out 83.69 83.69 41.74 41.74 TAC-$ 8230 Of 4827 6099 2349 2626 Standard ST-kVA Voltage Drop Bound Total -percentage (%) 5.37 4.69 7.85 4.27 4.40 VDT-Transformer 2.40 1.90 1.90 1.82 1.82 VDSL-Service Lateral 2.28 2.06 4.80 2.08 2.03 VDSD-Service Drop 0.68 0.74 1.16 0.36 0.54 60 Table 6.1 --Summary of the Runs Continued (Source Provided by Authors) i=15% Run 43 Run 44 Run 45 Run 46 Run 47 Run 48 Low Electric Markup , ECoff= 0.015, ECon = 0.02, Power Factor = 0.9 Class 1 10,12,18 kVA SL=320ft SD=80ft Class 1 10,12,18 kVA SL=480ft SD=120ft Class 2 4.4,6,10 kVA SL=320ft SD=80ft Class 2 4.4,6,10 kVA SL=480ft SD=120ft Class 3 1.2,1.5,2.5 kVA SL=320ft SD=80ft Class 3 1.2,1.5,2.5 kVA SL=480ft SD=120ft Optimized * * ST-kVA 80.48 80.48 38.5 38.5 13.15 13.15 ASL-kcmil 262.4 262.4 131.2 131.2 32.8 32.8 ASD-kcmil 139.14 139.14 77.31 77.31 19.33 19.33 TAC-$ 11968 15387 7016 8866 3350 3901 ST-kVA 100 100 50 50 15 15 ASL-kcmil 350 300 205 300 66.36 66.36 ASD-kcmil 167.8 Out 83.69 83.69 41.74 41.74 TAC-$ 12142 Of 7086 8939 3498 4120 Standard Voltage Drop Bound Total -percentage (%) 5.37 4.70 4.94 4.27 4.40 VDT-Transformer 2.40 1.90 1.90 1.82 1.82 VDSL-Service Lateral 2.28 2.06 1.92 2.08 2.03 VDSD-Service Drop 0.68 0.74 1.11 0.36 0.54 We made sure we run the program for at least several cases. We also subjected the runs to the constraints of at least five (5) percent voltage drop for service lateral, and 10 percent overall. 61 We first ran the Matlab program (OptimizeTAC) for class 3 residence customer, as specified in the Table 4.1 (reflecting Table 6.4 of the Dr. Gonen’s Distribution book [1], and as provided earlier here in this paper. The program (OptimizeTAC) reached a solution and gave a 15-kVA transformer with a No. 4 conductor, as the answer. Service Lateral (SL) and Service Drop (SD) were both optimized at a No. 4 conductor (ASL = 41 kcmil). We then ran the program similarly for the Class 2 residences (Table 4.1) and obtained the answer as a 50-kVA transformer, with a No. 2/O conductor (ASL = 133.1 kcmil) for SL and a No. 1 conductor (ASL = 83.69 kcmil) for the SD. In both program runs for Class 1, 2 and 3, the voltage drops were within the specified tolerance limits of 5 percent per component (10 percent total). When we entered the Class 1 data in the program, TAC equation derivative answer is a complex value for the transformer (ST). The imaginary part is probably due to the large maximum load. Long blocks, which will have longer wire lengths, can cause the voltage drop constraint in the program to be violated earlier. That effect is more profound when we lower the tolerance level of the voltage constraint to much below 10 percent. Class 1 data in the program run yielded the answer of a 100-kVA transformer, a No. 300 MCM service lateral (ASL = 300 kcmil), and a No. 3/O conductor (ASL = 167.8 kcmil) for SD. 62 In fact, we ran each of the normal Runs with a 50 percent longer length to see this effect. We did not notice any constraint violations until we increased the lengths to about twice long and Class 1 with high loading showed constraint violations earlier. Alternately, one can reduce the tolerance of the voltage drop in the program to see similar change taking place. We also wanted to test the sensitivity of the program to the higher electricity mark-up cost. We have provided 12 runs under high electric mark-up case (twice the normal value in Runs 13 thru 24). We have also provided an alternate similar run of each case with lower capitalization value to see the results. We replaced the capitalization rate (utility rate of return) to lower (10%) and higher (15%) values to discover program sensitivity to the solution based on the assumed capitalization rate (ὶ ), as tabulated in the above tables, to obtain the utility valuation based upon a conservative long-term policy towards higher capital investment. Finally, we first executed the program with the original runs at power factor of 90 percent and then we lowered the power factor to 70 percent to compare the results. The results do not show that lower power factor exacerbates the voltage drop constraint, which is counter-intuitive to our initial expectations. The reality, however, is that constant energy loads under lower power factor condition will demand higher current, 63 which ultimately result in higher kVA and cause program to choose higher conductor sizes, consequently. However, we have no way of reflecting that in our simple program as we input the Table 4.1 column values. We have to increase the loads proportionately to capture that lowered power factor effect. Higher conductor sizes will undoubtedly affect cost and cause higher TAC for the utility company. We also wanted to show the effect of lowering the Voltage Drop constraint. By setting the constraint to 2.5 percent in SL and SD, and 5 percent overall voltage drop, we force the Matlab program to choose larger size conductors, as it is shown in the Runs 37 to 48. The TAC equation yields complex solution and it results in out-of-bound answers for the longer lengths in Class 1 column data. High loading is the main cause of not reaching solution and ultimately, the designed distribution calls for a revision. 64 Chapter 7 CONCLUSIONS Optimization of the secondary distribution is a tedious process. It first requires an understanding and familiarity of the primary and secondary system to identify the uniqueness (if any) of the system. Based on this layout, demographical expectations and growth anticipated, the system designer can then derive the cost figure for this Primary system. In more sophisticated optimization models, the integer programming and dynamic programming techniques are employed, as they are more appropriate solutions. However, our assignment was confined with use of simple Matlab programming to devise a method to optimize the system secondary, and still account for a constraint, which in this case was the overall voltage drop for the secondary system. We were destined to prove the point using only Matlab programming technique and capability. In our program, the dimension of the blocks, and therefore the lots, are parameters that can be safely changed for sensitivity analysis. The program constraint limit of voltage drop can also be altered for ease of analysis. We have justified our cost structure in chapter 6 (Economic Estimation and Analysis), but those cost data may also be adjusted for fine tuning or sensitivity analysis, as well. Finally, the number of the transformers and radial feeding configuration can be altered without many great obstacles. Of course, the optimization program will have to be accordingly revised to account for the required formulation. 65 With the procedures described above the voltage profile, the conductor thermal capacity, tapering and short-circuit strength and the protective grounding of a radial secondary power distribution system can be examined. If the results of this examination are not satisfactory to the system designer, alternative optimizing technical solutions must be proposed, which concern transformer changes or conductor replacements or both. These solutions are economically estimated and the most economical one is finally adopted. Adjusting for load growth is also challenging for the distribution designers, as it will pose the predicament for the system designers to be more conservative with their initial designs and allow higher equipment rating or better specification to fit into the primary side. Higher protection standards and non-linear nature of many loads cause equipment to fail prematurely, or heat up and result in shorter life due to harmonics. Adding to this challenge will be the integration of renewable Distributed Energy Resources (DER) that will dominate the future distribution grid. Many of these DERs have solid state inverters that will exacerbate the harmonics effect. Furthermore, the planned procedures must provide for some degree of the flexibility from the norm. Electric Cars charging needs, e.g., requires direct upgrade of the transformers and conductors in some neighborhoods distribution systems, and therefore, the concept of effective integration is vital because of the charging capability 66 of each vehicle. Future distribution system engineers and designers undoubtedly are faced with great many challenges and game changes, as well. The loading on the distribution transformers will be significantly increased once the ownership of Plug-In-Hybrid Electrical Vehicle (PHEV) becomes prevalent in our modern society and when the average neighborhood displays a significant presence of these cars. The average electric car will need about 20 to 30 kW-hour of charge for a round trip of about 60 miles. While that is not a huge load by itself, relative to size of transformers and wires, it puts undue burden on the grid [14]. One can imagine that while the early adoption may be low, even only two out of twelve houses owning and charging these electrical vehicles can seriously burden the neighborhood distribution grid. Finally, the new utility tariff and rate structure must be provided by the regulators to provide for the shifting paradigm in the utility industry and its ultimate migration to the Smart grid domain. The purpose of this masters project was to demonstrate that (1) the optimization process is essential between main components of the distribution system, being primary or secondary and (2) the optimization process can be implemented between the main components on the basis of fixed initial cost and operating cost of the system, and even a basic Matlab Program is capable of obtaining solutions to the design problem. Future Smart grid vision is to develop and deploy a more reliable, secure, economic, efficient, safe, and environmentally friendly electric system. It will hinge on optimization of 67 several sub system to attain that goal. Advanced grid technologies will help attaining that goal with the increase in grid efficiency and reliability 68 APPENDIX A Matlab Optimization Program for Secondary Distribution System Instructions for Running the Matlab Optimization Program in Distribution System The following are instruction steps to utilize the Matlab Optimization program: 1. The program is designed to provide the design parameters to the distribution designer who will layout the typical urban area City block. It can easily be modified to use it for bigger acreages available in the agricultural areas as well. This program is constructed with the idea that configuration of distribution system greatly affects the outcome as the layout will determine the efficient means of distribution, and hence, we have assumed a city residential block typically found in the urban areas of most major U.S cities (typically 960 feet long by 330 feet wide). 2. Typically, the utility would like to reduce the voltage drop at the end of the line and hence would bring the distribution high voltage side to the middle of the circuit so that two almost equal strings can service the two sides of the pattern. The utility therefore serves the two strings by the two transformers from the utility Right of Way which service these blocks, by single-phase distribution circuit of the serving electric utility. We provided the input queries for the 69 dimensions of this block as to the length and width, which will have a bearing upon the length of service laterals and service drop conductors serving the neighborhood area. The example in the book has assumed two single-phase transformers serving this block, and each transformer serving power to twelve customers (we have assumed 12 kV primary distributions for these transformers, and 240- volt secondary to customers). [1] 3. The utilities have to justify their cost expenditures to their financial managers and public agencies involved, as the total expenditures will undoubtedly affect the tiered electric rates that ratepayers must pay. Therefore, extra prudence is applied so that the utility is not heavily weighted in the purchase of non-utilized assets. Of course, different assets have different life spans and that is why the utility industry has developed the annualized asset cost to have comparison basis of measuring alternative proposals on an equal footing. When the assets are compared on the basis of their amortized life, it will simplify the job of planning managers to develop the consensus for funding the suitable alternatives. 4. The optimized equations in the program are derived from the absolute maximized or minimized equations to provide the optimal value for the variables. However, the standard sizes available in the commercial market do not render themselves to exact sizes. It is pertinent for a distribution system designer to obtain a standard size that can still provide near optimal value to the 70 utility, minimizing the Total Annualized Cost (TAC) that service utility must burden with. 5. The average load a house may use may greatly depend on the neighborhood demography and its location. Over the past century electricity consumption has increased substantially per capita, mainly due to exponential use of automation in human life in the developed world, while it provides the advances in quality of life. Interestingly, while the utilities seek to dampen the peak power usage to curtail high cost of their spot generation, they have to design their distribution conservatively to accommodate the perceived peak load, even though this equipment may not be fully utilized a great portion of the time. Hence, sizing their equipment for average load is allowed, which is somewhat diversified by the local authorities having jurisdictions. The average household load is also provided thru an input to the program, as different type of residential areas may vary in their demography and their electrical usage. The program calculates the load, sizes the next commercially available transformer, and provides the appropriate sizes for the Service Lateral (SL) and Service Drop (SD) conductors. It then calculates the TAC. 6. Two files are attached with this instruction sheet. One is the Matlab program called OptimizeTAC.m and the other is the Excel input data called TransfDataTryVD24.xls. You would need to save the TransfDataTryVD24.xls in 71 the folder that Matlab works with to be able to import the table values automatically into Matlab. 72 Matlab Optimization Program in Distribution System %This program evaluates the distribution circuit requirements for a block %development and then determines the transformers' size, Service Laterals, %and Service Drops. Block length and widths are inputs given to the program %as specifications as well as the residential load, voltage and power factor. clear all clc foadfile1='TransfDataTryVD24.xls'; %reads data from the first worksheet in sheet=1; %the Excel spreadsheet file named 'foadfile1' and returns the x1range='B10:N17'; % numeric data in array num. subsetA=xlsread(foadfile1,sheet,x1range); A=subsetA; foadfile2='TransfDataTryVD24.xls'; %reads data from the second worksheet in sheet=2; %the Excel spreadsheet file named 'foadfile2' and returns the x2range='B10:N22'; % numeric data in array num. subsetB=xlsread(foadfile2,sheet,x2range); B=subsetB; Lab=input('Enter the spacing for block length Lab in ft: '); Wac=input('Enter the spacing for block width Wab in ft: '); volt=input('Enter the secondary distribution voltage: '); prompt1 = 'What is Max Average Load for each of 12 customers in KVA? '; La12=input (prompt1); prompt2= 'What is the Load for 4 customers in KVA ? '; L4=input (prompt2); prompt3 = 'What is Max Load for 1 customer in KVA? '; L1=input (prompt3); pf=input('Enter the distribution system power factor (pf)cos(Phi): '); %Lab=1*960;Wac=1*330;volt=240;La12=4.4;L4=6;L1=10;pf=0.9; i=0.15; % The utility cost annualized Rate (Capitalization Rate) ICCAP=15;ICsys=8*350;Iexc=0.015;FLD=0.35;ECoff=.015;ECon=.02; % Defining the parameters; XX=2; % No of Transformers YY=12; % No of Customers poles=6; % No. of Poles LotW=Lab/12; % Lot Width LotL=Wac/2; % Lot Length LSL=4*LotW; % Length of SL LSD=0.5*LotL; % Length of SD phi=acos(pf); % Phi Angle (phi) Smin=YY*1.1; % In kVA Aload=YY*La12; if Aload<Smin ST=Smin;ASL=41.74;ASD=26.24; 73 else ST=iscolumn(A(1));ASL=iscolumn(B(12));ASD=iscolumn(B(12));RSL=iscolumn( B(3)); XSL=iscolumn(B(5));RSD=iscolumn(B(3));XSD=iscolumn(B(5));AMP=iscolumn(B (2)); SD1=iscolumn(B(2)); end syms ST positive syms ASL positive syms ASD positive C1=XX*8*(250+7.26*ST)*i; % $/Block-2 trx per block & 12 services per ea. trx C2=XX*8*(60+4.5*ASL)*i*2*(LSL/1000); %Triplex aluminum cable cost for Service Lateral per transformer C3=XX*8*(60+4.5*ASD)*i*YY*LSD/1000; % Service Drop initial cost ($/block) C4=8*160*poles*i; % Cost of Poles $/ block C5=2*Iexc*ST*ICCAP*i; % Capacitors’cost for System energizing and I excitation C6=2*(ICsys*i+8760*ECoff)*0.004*ST; % Cost of iron losses/ upleg of Secondary ($/ block) FLS=0.3*FLD+0.7*FLD^2; Smax=YY*La12; % This is found from Table 6.4 for 12 class 2 customers, per book example PTcu=(0.073+0.00905*ST);% Transformer copper losses Where 15 kVA<=ST<=100 kVA % This is found from (Eq. 6.10) C7=XX*(ICsys*i+8760*ECon*FLS)*(PTcu)*(Smax/ST)^2; %From Eq.6.9, The annual OC of tx copper losses per block RSL=(20.5*(LSL)*2)/(1000*ASL); % RSL=p*L/1000*ASL (Ohm.kcmil/trx.) PSLcu=(((4*L4*1000)/(volt))^2)*(RSL/1000); %PSLcu=((4*L4/volt)^2)*(12.3/ASL)/1000; C8=XX*(ICsys*i+8760*ECon*FLS)*PSLcu; % From Eq. 6.11, annual OC of copper losses in the 4 SLs RSD=(20.5*LSD*24*2)/(1000*ASD); %Rc=p*(LSD/1000)*ASD=68.88/ASD (Ohm.kcmil/block), PSDcu=(((L1*1000/volt))^2)*(RSD/1000); % PSDcu=((Lmax/volt)^2)*(68.88/ASD)*1/1000; C9=(ICsys*i+8760*ECon*FLS)*PSDcu; % From Eq. 6.11, annual OC of copper losses in 24 SDs) TAC=C1+C2+C3+C4+C5+C6+C7+C8+C9; disp(TAC); diff(TAC,ST);ST1=ans; E=ans; ST=vpa(solve(E),5);ST1=ST; diff(TAC,ASL); F=ans; ASL=vpa(solve(F),5);ASL1=ASL; 74 diff(TAC,ASD); G=ans; ASD=vpa(solve(G),5);ASD1=ASD; ST0=ST1; ASL0=ASL1; ASD0=ASD1; disp(ST1); disp(ASL1); disp(ASD1); C01=XX*8*(250+7.26*ST0)*i;% $/Block-2 trx per block & 12 services per ea. trx C02=XX*8*(60+4.5*ASL0)*i*2*(LSL/1000); %Triplex aluminum cable cost for Service Lateral per transformer C03=XX*8*(60+4.5*ASD0)*i*YY*LSD/1000; % Service Drop initial cost ($/block) C04=8*160*poles*i; % Cost of Poles $/ block C05=2*Iexc*ST0*ICCAP*i; % Capacitors’cost for System energizing & I excitation C06=2*(ICsys*i+8760*ECoff)*0.004*ST0; % Cost of iron losses/ upleg of Secondary ($/ block) FLS=0.3*FLD+0.7*FLD^2; Smax=YY*La12; % This is found from Table 6.4 for 12 class 2 customers, per book example PTcu=(0.073+0.00905*ST0);% Transformer copper losses Where 15 kVA<=ST<=100 kVA % This is found from (Eq. 6.10) C07=XX*(ICsys*i+8760*ECon*FLS)*(PTcu)*(Smax/ST0)^2; %From Eq.6.9, The annual OC of tx copper losses per block RSL=(20.5*(LSL)*2)/(1000*ASL0); % RSL=p*L/1000*ASL (Ohm.kcmil/trx.) PSLcu=(((4*L4*1000)/(volt))^2)*(RSL/1000); %PSLcu=((4*L4/volt)^2)*(12.3/ASL0)/1000; C08=XX*(ICsys*i+8760*ECon*FLS)*PSLcu; % From Eq. 6.11, annual OC of copper losses in the 4 SLs RSD=(20.5*LSD*24*2)/(1000*ASD0); %Rc=p*(LSD/1000)*ASD0=68.88/ASD (Ohm.kcmil/block), PSDcu=(((L1*1000/volt))^2)*(RSD/1000); % PSDcu=((Lmax/volt)^2)*(68.88/ASD)*1/1000; C09=(ICsys*i+8760*ECon*FLS)*PSDcu; % From Eq. 6.11, annual OC of copper losses in 24 SDs) TAC0=C01+C02+C03+C04+C05+C06+C07+C08+C09; disp(' “Value of TAC0 “'); disp(TAC0); if ST1<=A(1,1) % Secondary Distribution Transformer (ST) Selection Logic ST=A(1,1);XT=A(1,13); 75 disp(ST); elseif ST1<=A(2,1) ST=A(2,1);XT=A(2,13); disp(ST); elseif ST1<=A(3,1) ST=A(3,1);XT=A(3,13); disp(ST); elseif ST1<=A(4,1) ST=A(4,1);XT=A(4,13); disp(ST); elseif ST1<=A(5,1) ST=A(5,1);XT=A(5,13); disp(ST); elseif ST1<=A(6,1) ST=A(6,1);XT=A(6,13); disp(ST); elseif ST1<=A(7,1) ST=A(7,1);XT=A(7,13); disp(ST); elseif ST1<=A(8,1) ST=A(8,1);XT=A(8,13); disp(ST); elseif ST1<=A(9,1) ST=A(9,1);XT=A(9,13); disp(ST); else disp('Provide a different design'); end %ASL=B(k,12);AMP=B(k,2);XSL=B(k,5);RSL=B(k,3); if ASL1<=B(1,12) % Service Lateral Ampacity (SL) Selection Logic ASL=B(1,12);AMP=B(1,2);XSL=B(1,5);RSL=B(1,3); disp(ASL);disp(AMP); elseif ASL1<=B(2,12) ASL=B(2,12);AMP=B(2,2);XSL=B(2,5);RSL=B(2,3); disp(ASL);disp(AMP); elseif ASL1<=B(3,12) ASL=B(3,12);AMP=B(3,2);XSL=B(3,5);RSL=B(3,3); disp(ASL);disp(AMP); elseif ASL1<=B(4,12) ASL=B(4,12);AMP=B(4,2);XSL=B(4,5);RSL=B(4,3); disp(ASL);disp(AMP); elseif ASL1<=B(5,12) ASL=B(5,12);AMP=B(5,2);XSL=B(5,5);RSL=B(5,3); disp(ASL);disp(AMP); elseif ASL1<=B(6,12) ASL=B(6,12);AMP=B(6,2);XSL=B(6,5);RSL=B(6,3); disp(ASL);disp(AMP); elseif ASL1<=B(7,12) ASL=B(7,12);AMP=B(7,2);XSL=B(7,5);RSL=B(7,3); disp(ASL);disp(AMP); elseif ASL1<=B(8,12) ASL=B(8,12);AMP=B(8,2);XSL=B(8,5);RSL=B(8,3); 76 disp(ASL);disp(AMP); elseif ASL1<=B(9,12) ASL=B(9,12); AMP=B(9,2);XSL=B(9,5);RSL=B(9,3); disp(ASL);disp(AMP); elseif ASL1<=B(10,12) ASL=B(10,12); AMP=B(10,2);XSL=B(10,5);RSL=B(10,3); disp(ASL);disp(AMP); elseif ASL1<=B(11,12) ASL=B(11,12); AMP=B(11,2);XSL=B(11,5);RSL=B(11,3); disp(ASL);disp(AMP); elseif ASL1<=B(12,12) ASL=B(12,12); AMP=B(12,2);XSL=B(12,5);RSL=B(12,3); disp(ASL);disp(AMP); elseif ASL1<=B(13,12) ASL=B(13,12); AMP=B(13,2);XSL=B(13,5);RSL=B(13,3); disp(ASL);disp(AMP); else disp('Provide a different design'); end ASL2=ASL; VDSL2=4*1000*(L4/(volt)^2)*2*(LSL/1000)*(RSL*cos(phi)+XSL*sin(phi))*100 ; for k=1:1:13 VDSL3=4*1000*(L4/(volt)^2)*2*(LSL/1000)*(RSL*cos(phi)+XSL*sin(phi))*100 ; if VDSL2<5 break else ASL3=B(k,12);AMP=B(k,2);XSL=B(k,5);RSL=B(k,3); if VDSL3<5 ASL2=ASL3; VDSL2=VDSL3; else ASL3=B(k+1,12);AMP=B(k+1,2);XSL=B(k+1,5);RSL=B(k+1,3); end end end VDSL=VDSL2; if ASD1<=B(1,12) % Secondary Service Drop (SD) Selection Logic ASD=B(1,12);SD1=B(1,2);XSD=B(1,5);RSD=B(1,3); disp(ASD);disp(SD1); elseif ASD1<=B(2,12) ASD=B(2,12);SD1=B(2,2);XSD=B(2,5);RSD=B(2,3); %ZSD=B(2,4); disp(ASD);disp(SD1); elseif ASD1<=B(3,12) ASD=B(3,12);SD1=B(3,2);XSD=B(3,5);RSD=B(3,3); %ZSD=B(3,4); disp(ASD);disp(SD1); elseif ASD1<=B(4,12) ASD=B(4,12);SD1=B(4,2);XSD=B(4,5);RSD=B(4,3); %ZSD=B(4,4); disp(ASD);disp(SD1); elseif ASD1<=B(5,12) 77 ASD=B(5,12);SD1=B(5,2);XSD=B(5,5);RSD=B(5,3); disp(ASD);disp(SD1); elseif ASD1<=B(6,12) ASD=B(6,12);SD1=B(6,2);XSD=B(6,5);RSD=B(6,3); disp(ASD);disp(SD1); elseif ASD1<=B(7,12) ASD=B(7,12);SD1=B(7,2);XSD=B(7,5);RSD=B(7,3); disp(ASD);disp(SD1); elseif ASD1<=B(8,12) ASD=B(8,12);SD1=B(8,2);XSD=B(8,5);RSD=B(8,3); disp(ASD);disp(SD1); elseif ASD1<=B(9,12) ASD=B(9,12);SD1=B(9,2);XSD=B(9,5);RSD=B(9,3); disp(ASD);disp(SD1); else end %ZSD=B(5,4); %ZSD=B(6,4); %ZSD=B(7,4); %ZSD=B(8,4); %ZSD=B(9,4); ASD2=ASD; VDSD2=1000*(L1/(volt)^2)*2*(LSD/1000)*(RSD*cos(phi)+XSD*sin(phi))*100; for j=1:1:9 VDSD3=1000*(L1/(volt)^2)*2*(LSD/1000)*(RSD*cos(phi)+XSD*sin(phi))*100; if VDSD2<5 break else ASD3=B(j,12);SD1=B(j,2);XSL=B(j,5);RSL=B(j,3); if VDSL3<5 ASD2=ASD3; VDSD2=VDSD3; else ASD3=B(j+1,12);SD1=B(j+1,2);XSL=B(j+1,5);RSL=B(j+1,3); end end end VDSD=VDSD2; C1=XX*8*(250+7.26*ST)*i; % $/Block-2 trx per block & 12 services per ea. trx C2=XX*8*(60+4.5*ASL)*i*2*(LSL/1000); %Triplex aluminum cable cost for Service Lateral per transformer C3=XX*8*(60+4.5*ASD)*i*YY*LSD/1000; % Service Drop initial cost ($/block) C4=8*160*poles*i; % Cost of Poles $/ block C5=2*Iexc*ST*ICCAP*i; % Capacitors’cost for System energizing & I excitation C6=2*(ICsys*i+8760*ECoff)*0.004*ST; % Cost of iron losses/ upleg of Secondary ($/ block) FLS=0.3*FLD+0.7*FLD^2; Smax=YY*La12; % This is found from Table 6.4 for 12 class 2 customers, per book example 78 PTcu=(0.073+0.00905*ST);% Transformer copper losses Where 15 kVA<=ST<=100 kVA % This is found from (Eq. 6.10) C7=XX*(ICsys*i+8760*ECon*FLS)*(PTcu)*(Smax/ST)^2; %From Eq.6.9, The annual OC of tx copper losses per block RSL=(20.5*(LSL)*2)/(1000*ASL); % RSL=p*L/1000*ASL (Ohm.kcmil/trx.) PSLcu=(((4*L4*1000)/(volt))^2)*(RSL/1000); %PSLcu=((4*L4/volt)^2)*(12.3/ASL0)/1000; C8=XX*(ICsys*i+8760*ECon*FLS)*PSLcu; % From Eq. 6.11, annual OC of copper losses in the 4 SLs RSD=(20.5*LSD*24*2)/(1000*ASD); %Rc=p*(LSD/1000)*ASD0=68.88/ASD (Ohm.kcmil/block), PSDcu=(((L1*1000/volt))^2)*(RSD/1000); % PSDcu=((Lmax/volt)^2)*(68.88/ASD)*1/1000; C9=(ICsys*i+8760*ECon*FLS)*PSDcu; % From Eq. 6.11, annual OC of copper losses in 24 SDs) TAC2=C1+C2+C3+C4+C5+C6+C7+C8+C9; disp(' “Value of TAC2 “'); disp(TAC2); % The Voltage Drop Constraint is tested on the obtained values % VoltDrop = VDT+VDSL+VDSD; %Zpu=0.02; %Zbase=voltage^2/ST;%Zpu is given in input tables %ZVST=Zpu*Zbase; VDT=1000*(Aload/(volt)^2)*XT*100; % VDT=12*LoadC*ZVST; VoltDrop=VDT+VDSL+VDSD; if VoltDrop>10 % The Voltage Drop Constraint is tested for Optimization disp('"Voltage Drop Too High! -- Provide a different design."'); disp('"VoltDrop in % = "'); disp(VoltDrop); disp(VDT); disp(VDSL); disp(VDSD) disp(TAC2); disp(' “Size of transformer in kVA is = ”');disp(ST); disp(' “Size of ASL “’');disp(ASL2);disp(AMP); disp(' “Size of ASD “');disp(ASD2);disp(SD1); else disp('"VoltDrop in % = "'); disp(VoltDrop);disp(VDT);disp(VDSL);disp(VDSD) disp(TAC2);%disp(ST);disp(ASL);disp(AMP),disp(ASD);disp(SD1); disp(' “Size of transformer in kVA is = ”');disp(ST); disp(' “Size of ASL “’');disp(ASL2);disp(AMP); disp(' “Size of ASD “');disp(ASD2);disp(SD1); end 79 APPENDIX B Instructions for Matlab TAC Program in Distribution System The following are instruction steps to utilize the Matlab TAC program: 1. This program is constructed with the idea that configuration of distribution system greatly affects the outcome as the layout will determine the efficient means of distribution, and hence, we have assumed a city residential block typically found in the urban areas of most major U.S cities. 2. Typically, two transformers from the utility Right of Way serve these blocks, usually by single-phase distribution circuit of the serving electric utility. We assume the secondary distribution system within a City block, as discussed in Appendix A. The block dimensions are according to Figure 4.4 Similar to previous program, it queries for the inputs of Transformer size in KVA, Cable sizes (ASL and ASD) in kcmil, and loads (L1, L4, and La12) in KVA . Values for loads L1, L4, and La12 can be obtained from Table 4.1, or can be any combination of average household load for one (maximum load), four, or 12 customers. Similar to the example in the book, we have assumed 12 kV primary distributions for these transformers, and 240- volt secondary to customers. As before, two single-phase transformers are serving this block, and each transformer serving power to twelve customers [1]. 80 3. The following questions will be asked when program is run: What is ST in kVA? What is ASL in kcmil? What is ASD in kcmil? What is the load for 12 customers in kVA? What is the load for 4 customer in kVA? What is Max load (1 customer) in kVA? Then TAC will be calculated by the program in $/block. Sample Runs What is ST in kVA? 100 What is ASL in kcmil? 300 What is ASD in kcmil? 167.8 What is the load for 12 customers in kVA? 10 What is the load for 4 customer in kVA? 12 What is Max load (1 customer)in kVA? 18 TAC = 7746 ***************************************************** What is ST in kVA? 50 What is ASL in kcmil? 167.8 What is ASD in kcmil? 83.69 81 What is the load for 12 customers in kVA? 4.4 What is the load for 4 customer in kVA? 6 What is Max load (1 customer) in kVA? 10 TAC = 4559 ******************************************************* What is ST in kVA? 15 What is ASL in kcmil? 41.74 What is ASD in kcmil? 41.74 What is the load for 12 customers in kVA? 1.2 What is the load for 4 customer in kVA? 1.5 What is Max load (1 customer) in kVA? 2.5 TAC =2255 82 Matlab Program for Total Annualized Cost (TAC) in Distribution System prompt1 = 'What is transformer rate in kVA? '; %input, program asking for %transformer rate in kVA ST = input (prompt1); prompt2 = 'What is cable size (ASL) in kcmil? '; %input, program is asking for %cable size in kcmil ASL = input (prompt2); prompt3 = 'What is cable size (ASD) in kcmil? '; %input, program is asking for %cable size in kcmil ASD = input (prompt3); prompt4 = 'What is the load for 12 customers in kVA? '; % input, Program is %asking for average load for 12 customer. Table can be used L12 = input (prompt4); prompt5 = 'What is the load for 4 customer in kVA? '; %input, Program is %asking for average load for 4 customer. Table can be used L4 = input (prompt5); prompt6 = 'What is Max load (1 customer) in kVA? '; %input, Program is %asking for average load for 1 customer. Table can be used L1 = input (prompt6); % this formula was driven for the cost (C1-C9)in the report page TAC = (6.048*ASD)+ (4.32*ASL) + (14.9522*ST) +374.536*L1*(L1/ASD) + 2141.28*L4*(L4/ASL) + (6589.33*(L12/ST)*(L12/ST))+(816.9*L12*(L12/ST))+ 1306.24; round(TAC); TAC=ans % TAC is calculated by program 83 APPENDIX C Secondary Distribution System Voltage Drop Program Instructions for Running the Matlab Voltage Drop Calculation Program The following are instruction steps to utilize the Matlab Voltage Drop Program : 1. The program is designed to provide the design parameters to the secondary distribution system designer who has the layout of the typical urban Area City block, found in the urban areas of most major U.S cities (typically 960 feet long by 330 feet wide). 2. It may also be modified to use it for bigger acreages available in the agricultural areas, or as a calculator on the primary system. This program calculates the voltage drop within the Transformer, Service Lateral (SL), and Service Drop (SD). 3. The utility would reduce the voltage drop at the end of the line by bringing the distribution high voltage side to the middle of the circuit, so that two almost equal strings can service the two sides of the pattern. The utility therefore serves the two strings by the two transformers from the utility Right of Way which service these blocks, by single-phase distribution circuit of the serving electric utility. We provided the input queries for the dimensions of this block as to the 84 length and width, which will have a bearing upon the length of service laterals and service drop conductors serving the neighborhood area. The example in the book has assumed two single-phase transformers serving this block, and each transformer serving power to twelve customers (we have assumed 12 kV primary distributions for these transformers, and 240- volt secondary to customers) [1]. 4. The utilities have technical designers who are responsible to keep voltage drop within a tolerance level and at the same time must justify their cost expenditures to their financial managers and public agencies involved, as the total expenditures will undoubtedly affect the tiered electric rates that ratepayers must pay. Therefore, extra prudence is applied so that the utility is not heavily weighted in the purchase of non-utilized assets 5. The load is queried into this program as energy use of a house may greatly depend on the neighborhood demography and its location. The program queries for the single family load, diversified loads, and it then calculates the voltage drops values at the Transformer (ST), Service Lateral (SL) and Service Drop (SD) conductors. It then calculates the Total Voltage Drop for all three in the secondary system. 85 6. Two files are attached with this instruction sheet. One is the Matlab program called VoltageDrop.m and the other is the Excel input data called TransfDataTryVD24.xls. User needs to save the TransfDataTryVD24.xls in the folder that Matlab works with to be able to import the table values automatically into Matlab. 86 Matlab Program for Voltage Drop in Distribution System %This program evaluates the distribution circuit voltage drop requirements for a block %development and then determines if the constraint threshold is exceeded, based on the transformers' size, Service Laterals, %and Service Drops. Block length and widths are inputs given to the program %as specifications as well as the residential load, voltage and power factor. clear all clc foadfile1='TransfDataTryVD24.xls'; %reads data from first worksheet in sheet=1; %the Excel spreadsheet file named 'foadfile1' and returns the x1range='B10:N17'; % numeric data in array num. subsetA=xlsread(foadfile1,sheet,x1range); %disp(subsetA) A=subsetA; foadfile2='TransfDataTryVD24.xls'; %reads data from the second worksheet in sheet=2; %the Excel spreadsheet file named 'foadfile2' and returns the x2range='B10:N22'; % numeric data in array num. subsetB=xlsread(foadfile2,sheet,x2range); %disp(subsetB) B=subsetB; Lab=input('Enter the spacing for block length Lab in ft: '); Wac=input('Enter the spacing for block width Wab in ft: '); volt=input('Enter the secondary distribution voltage: '); prompt1 = 'What is Max Average Load for each of 12 customers in KVA? '; La12=input (prompt1); prompt2= 'What is the Load for 4 customers in KVA? '; L4=input (prompt2); prompt3 = 'What is Max Load for 1 customer in KVA? '; L1=input (prompt3); ST1=input('Enter the distribution system Transformer Size: '); pf=input('Enter the distribution system power factor (pf)cos(Phi): '); ASL1=input('What is the cross section of SL Line? : '); %AMP=input('What is the ampacity of SL Line? : '); ASD1=input('What is the Cross section size of SD Line? : '); %ASD=input('What is the length of SD Line? : '); %Lab=1*960;Wac=1*330;volt=240;La12=10;L4=12;L1=18;pf=0.9; %ST1=75;ASL1=74;ASD1=43; i=0.1; % The utility cost annualized Rate (Capitalization Rate) ICCAP=15;ICsys=8*350;Iexc=0.015;FLD=0.35;ECoff=.015;ECon=.02; % Defining the parameters; XX=2; % No of Transformers YY=12; % No of Customers poles=6; % No. of Poles LotW=Lab/12; % Lot Width LotL=Wac/2; % Lot Length 87 LSL=4*LotW; % Length of SL LSD=0.5*LotL; % Length of SD phi=acos(pf); % Phi Angle (phi) Smin=YY*1.1; % In kVA Aload=YY*La12; if Aload<Smin ST=Smin;ASL=41.74;ASD=26.24; else ST=iscolumn(A(1));ASL=iscolumn(B(12));ASD=iscolumn(B(12));RSL=iscolumn( B(3)); XSL=iscolumn(B(5));RSD=iscolumn(B(3));XSD=iscolumn(B(5));AMP=iscolumn(B (2)); SD1=iscolumn(B(2)); end %disp(ST1); %disp(ASL1); %disp(ASD1); if ST1<=A(1,1) %Secondary Distribution Transformer (ST) Selection Logic ST=A(1,1);XT=A(1,13); disp(ST); elseif ST1<=A(2,1) ST=A(2,1);XT=A(2,13); disp(ST); elseif ST1<=A(3,1) ST=A(3,1);XT=A(3,13); disp(ST); elseif ST1<=A(4,1) ST=A(4,1);XT=A(4,13); disp(ST); elseif ST1<=A(5,1) ST=A(5,1);XT=A(5,13); disp(ST); elseif ST1<=A(6,1) ST=A(6,1);XT=A(6,13); disp(ST); elseif ST1<=A(7,1) ST=A(7,1);XT=A(7,13); disp(ST); elseif ST1<=A(8,1) ST=A(8,1);XT=A(8,13); disp(ST); elseif ST1<=A(9,1) ST=A(9,1);XT=A(9,13); disp(ST); else disp('Provide a different design'); end %ASL=B(k,12);AMP=B(k,2);XSL=B(k,5);RSL=B(k,3); if ASL1<=B(1,12) % Service Lateral Ampacity (SL) Selection Logic ASL=B(1,12);AMP=B(1,2);XSL=B(1,5);RSL=B(1,3); disp(ASL);disp(AMP); 88 elseif ASL1<=B(2,12) ASL=B(2,12);AMP=B(2,2);XSL=B(2,5);RSL=B(2,3); disp(ASL);disp(AMP); elseif ASL1<=B(3,12) ASL=B(3,12);AMP=B(3,2);XSL=B(3,5);RSL=B(3,3); disp(ASL);disp(AMP); elseif ASL1<=B(4,12) ASL=B(4,12);AMP=B(4,2);XSL=B(4,5);RSL=B(4,3); disp(ASL);disp(AMP); elseif ASL1<=B(5,12) ASL=B(5,12);AMP=B(5,2);XSL=B(5,5);RSL=B(5,3); disp(ASL);disp(AMP); elseif ASL1<=B(6,12) ASL=B(6,12);AMP=B(6,2);XSL=B(6,5);RSL=B(6,3); disp(ASL);disp(AMP); elseif ASL1<=B(7,12) ASL=B(7,12);AMP=B(7,2);XSL=B(7,5);RSL=B(7,3); disp(ASL);disp(AMP); elseif ASL1<=B(8,12) ASL=B(8,12);AMP=B(8,2);XSL=B(8,5);RSL=B(8,3); disp(ASL);disp(AMP); elseif ASL1<=B(9,12) ASL=B(9,12); AMP=B(9,2);XSL=B(9,5);RSL=B(9,3); disp(ASL);disp(AMP); elseif ASL1<=B(10,12) ASL=B(10,12); AMP=B(10,2);XSL=B(10,5);RSL=B(10,3); disp(ASL);disp(AMP); elseif ASL1<=B(11,12) ASL=B(11,12); AMP=B(11,2);XSL=B(11,5);RSL=B(11,3); disp(ASL);disp(AMP); elseif ASL1<=B(12,12) ASL=B(12,12); AMP=B(12,2);XSL=B(12,5);RSL=B(12,3); disp(ASL);disp(AMP); elseif ASL1<=B(13,12) ASL=B(13,12); AMP=B(13,2);XSL=B(13,5);RSL=B(13,3); disp(ASL);disp(AMP); else disp('Provide a different design'); end ASL2=ASL; VDSL2=4*1000*(L4/(volt)^2)*2*(LSL/1000)*(RSL*cos(phi)+XSL*sin(phi))*100 ; for k=1:1:13 VDSL3=4*1000*(L4/(volt)^2)*2*(LSL/1000)*(RSL*cos(phi)+XSL*sin(phi))*100 ; if VDSL2<15 break else ASL3=B(k,12);AMP=B(k,2);XSL=B(k,5);RSL=B(k,3); if VDSL3<15 ASL2=ASL3; 89 VDSL2=VDSL3; else ASL3=B(k+1,12);AMP=B(k+1,2);XSL=B(k+1,5);RSL=B(k+1,3); end end end VDSL=VDSL2; if ASD1<=B(1,12) % Secondary Service Drop (SD) Selection Logic ASD=B(1,12);SD1=B(1,2);XSD=B(1,5);RSD=B(1,3); disp(ASD);disp(SD1); elseif ASD1<=B(2,12) ASD=B(2,12);SD1=B(2,2);XSD=B(2,5);RSD=B(2,3); %ZSD=B(2,4); disp(ASD);disp(SD1); elseif ASD1<=B(3,12) ASD=B(3,12);SD1=B(3,2);XSD=B(3,5);RSD=B(3,3); %ZSD=B(3,4); disp(ASD);disp(SD1); elseif ASD1<=B(4,12) ASD=B(4,12);SD1=B(4,2);XSD=B(4,5);RSD=B(4,3); %ZSD=B(4,4); disp(ASD);disp(SD1); elseif ASD1<=B(5,12) ASD=B(5,12);SD1=B(5,2);XSD=B(5,5);RSD=B(5,3); %ZSD=B(5,4); disp(ASD);disp(SD1); elseif ASD1<=B(6,12) ASD=B(6,12);SD1=B(6,2);XSD=B(6,5);RSD=B(6,3); %ZSD=B(6,4); disp(ASD);disp(SD1); elseif ASD1<=B(7,12) ASD=B(7,12);SD1=B(7,2);XSD=B(7,5);RSD=B(7,3); %ZSD=B(7,4); disp(ASD);disp(SD1); elseif ASD1<=B(8,12) ASD=B(8,12);SD1=B(8,2);XSD=B(8,5);RSD=B(8,3); %ZSD=B(8,4); disp(ASD);disp(SD1); elseif ASD1<=B(9,12) ASD=B(9,12);SD1=B(9,2);XSD=B(9,5);RSD=B(9,3); %ZSD=B(9,4); disp(ASD);disp(SD1); else end ASD2=ASD; VDSD2=1000*(L1/(volt)^2)*2*(LSD/1000)*(RSD*cos(phi)+XSD*sin(phi))*100; for j=1:1:9 VDSD3=1000*(L1/(volt)^2)*2*(LSD/1000)*(RSD*cos(phi)+XSD*sin(phi))*100; if VDSD2<5 break else ASD3=B(j,12);SD1=B(j,2);XSL=B(j,5);RSL=B(j,3); if VDSL3<5 ASD2=ASD3; 90 VDSD2=VDSD3; else ASD3=B(j+1,12);SD1=B(j+1,2);XSL=B(j+1,5);RSL=B(j+1,3); end end end VDSD=VDSD2; % The Voltage Drop Constraint is tested on the obtained values % VoltDrop = VDT+VDSL+VDSD; %Zpu=0.02; %Zbase=voltage^2/ST;%Zpu is given in input tables %ZVST=Zpu*Zbase; VDT=1000*(Aload/(volt)^2)*XT*100; % VDT=12*LoadC*ZVST; %VDSD=1000*(L1/(volt)^2)*2*(LSD/1000*((RSD*cos(phi))+XSD*sin(phi)))*100 ; VoltDrop=VDT+VDSL+VDSD; if VoltDrop>20 % The Voltage Drop Constraint is tested for Optimization disp('"Voltage Drop Too High! -- Provide a different design."'); disp('" VoltDrop in % = "'); disp(VoltDrop);disp(VDT);disp(VDSL);disp(VDSD); disp(' “Size of transformer in kVA is = ”');disp(ST); disp(' “Size of ASL “');disp(ASL2);disp(AMP); disp(' “Size of ASD “');disp(ASD2);disp(SD1); else disp('"VoltDrop in % = "'); disp(VoltDrop);disp(VDT);disp(VDSL);disp(VDSD); disp(' “Size of transformer in kVA is = ”');disp(ST); disp(' “Size of ASL “');disp(ASL2);disp(AMP); disp(' “Size of ASD “');disp(ASD2);disp(SD1); end 91 APPENDIX D Distribution System Component Information Background Conductors For utility companies one of the most expensive components is the conductors. Due to this fact, it is imperative that distribution system engineer and planner choose the most appropriate conductor type and size so that optimum operating efficiency can be realized[38][39]. The designer must come up with best price for a conductor with best conductivity-to-weight ratio and/or strength -to-weight ratio. For necessary ratio designer needs to look at all the factors such as voltage stability of the line, loading of the line, losses of the line, tension load, and environmental factors [40]. For selecting a conductor, technical and financial criteria need to be considered. Not only maximum power transfer, minimum loss and thermal capacity , per the system design specification, but also the price should be take in to account. While choosing a new conductor that has to match or work the existing conductor in the network, it has to be suitable for environmental conditions, as well. Most common conductor materials are Aluminum and copper. Copper is the best conductor and is the base-line reference for conductivity characteristics. On the other hand, the closest alternative for conductivity is Aluminum with less weight. Aluminum conductivity is 61 percent, its weight is 30 percent, and its breaking strength is 43 percent of copper [16]. 92 Because of the breaking strength of aluminum, aluminum conductor is made with strands of high-strength steel in their central core, and the combination is called Aluminum Cable Steel Reinforced or ACSR. ACSR is lighter than copper and has strength and conductivity of copper. At the same time, ACSR has longer life span and it last much longer than conductor usual 40 years. Following figure shows various configuration and size of ACSR conductors. 93 94 Distribution Transformers In the beginning, working power systems used direct current (DC) which carries low voltage and high current. Because of this combination there were a very large voltage drops and power losses especially in long distance distribution. The development of Alternating Current (AC) eliminated above problems and issues and made efficient and cost effective long-distance transmission and distribution a possibility. The first modern transmission was built in 1885 by William Stanley [37]. A simple transformer consist of two set of coil wrapped around a ferromagnetic core. When there is current in primary coil there will be flux created in the core and these flux going troughs the secondary coil create current in secondary circuit. The powers in primary and secondary circuits are identical (for ideal transformer). Because of that if the current goes up in secondary voltage goes down in secondary and if current goes down in secondary voltage goes up in secondary. Voltage ratio of primary over secondary is equal to the ratio of coil turn in primary over the coil turn in secondary (Vp/Vs)=(Np/Ns) , Pp=Ps Vp Primary voltage Vs Secondary voltage Np Number of turn in primary coil Ns Number of turn in secondary coil Pp Power in primary Ps Power in secondary , (Ip/Is)=(Ns/Np) 95 Ip Current in primary Is Current in secondary Distribution Transformers are typically rated up to 500kVA, whereas power transformers maintain rating of over 500 kVA at voltage levels of 69kV or greater [36]. Following page shows some typically rated transformers and associated data. 96 BIBLIOGRAPHY [1] Turan Gonen, “ Electric Power Distribution System Engineering”, Second Edition, 2007. Original by: T.Gonen, "Electric Power Distribution System Engineering", McGraw Hill, 1986. [2] Leon Freris and David Infield, “Renewable Energy in Power Systems”, 2008, Pages 18-19, and pages 240-241. [3] Donald G. Fink and H. Wayne Beaty, “Standard Handbook for Electrical Engineers”, 11th Edition, McGraw- Hill, New York, 1978. [4] Safigianni A.S., “Optimization of a secondary Power distribution system” --Electrical Power and Energy System”, September 2004. [5] Safigianni A., “ Technical optimization of a secondary power distribution system”. Proceedings of the IASTED EuroPES, Rhodes, Greece, July; 2001: p. 430-435. [6] R.Billinton, A.N.Allan, "Reliability Evaluation of Power Systems", Pitman Publishing Limited, 1984 [7] Ali Keyhani, “Design of Smart Power Grid Renewable Energy Systems, 2011”, Published by John Wiley & Sons, Inc. [8] Shirmohammadi D, Hong H W, Semlyen A, Luo G X. A compensation-based power flow method for weakly meshed distribution and transmission networks, IEEE Trans Power Deliv 1988; 3(2):753-62. [9] Bin Wu, Yongqiang Lang, Navid Zargari, and Samir Kouro, “Power Conversion and Control of Wind Energy Systems, 2011 copyright by IEEEE, Inc, Published by John Wiley & Son, Inc., page 20-21. [11] Renewable Energy Policy Network for the 21st Century (REN21), Renewable Global Status Report 2009 Update, available at www.ren21.net. [12] Yifan Tang, Power Distribution System Planning with Reliability Modeling and Optimization, Siemens Power Corporation [13] Modeling and Optimization of Electricity Distribution Planning System Using Dynamic Programming Techniques: A Case of Power Holding Company of Nigeria (PHCN), By: 1Chinwuko C.E., 2Chukwuneke J.L., 2Okolie P.C., and 2Dara E.J. INTERNATIONAL JOURNAL OF MULTIDISCIPLINARY SCIENCES AND ENGINEERING, VOL. 3, NO. 6, JUNE 2012. 97 [14] “Lapping The EV Race”, One utility out Front –Heads off Disruption, Martin Rosenberg, EnergyBiz, The energy web magazine, April 28, 2013. [15] “Time to take a second look at conservation voltage regulation”, Intelligent Utility” a web magazine, where smartgrid meets business and reality, June 6, 2013. [16] M.Ponnavaikko, etc, "Distribution System Planning through a Quadratic Mixedinteger Programming Approach", IEEE Trans. Power Delivery, Vol. PWRD-2, No. 4, October 1987. [17] J. H. Spare, Minutes of Distribution Reliability Applications Task Force, IEEE PES Winter Meeting, January 31, 1994, New York, NY 1973, pp. 348-354. [18] S. Karkkainen, etc, "Statistical Distributions of Reliability Indices and Unavailability Costs in Distribution Networks and Their Use in the Planning of Networks", CIRED 1981. [19] G.Kjolle, L.Rolfseng, E.Dahl, "The Economic Aspect of Reliability in Distribution System Planning", IEEE Trans. Power Delivery, Vol. 5, No. 2, April 1990, pp. 11531157. [20] Westinghouse Electric Corp., "Research into Load Forecasting and Distribution Planning" (Volume l), EPRI Project, 1980 [21] T. Gonen, etc, "Optimal Multi-stage Planning of Power Distribution Systems", IEEE Trans. Power Delivery, Vol. PWRD-2, No. 2, April 1987. [22] I.J. Ramirez-Rosado, T.Gonen, "Pseudo-dynamic Planning for Expansion of Power Distribution Systems", IEEE Trans. Power Systems, Vol. 6, No. 1, February 1991, pp. 245-254. [23] K.Kara, etc, "Multi-year Expansion Planning for Distribution Systems", IEEE Trans. Power Systems, Vol. 6, No. 3, August 1991, pp. 952-958. [24] Adkins, E. M., "Planning and load characteristics," in Electric Transmission and Distribution, Bernhardt G. A. Skrotzki, Ed. Malabar, Florida: Robert E. Krieger Publishing Company, 1954, pp. 387-410. [25] Bayliss, Colin, Transmission and Distribution Electrical Engineering, 2nd Edition, Jordan Hill, Oxford: Newnes, 1996, pp. 849-887. [26] Tomiyama, Katsuyuki, John P. Daniel, and Satoru lhara, "Modeling Air 98 Conditioner Load for Power System Studies,"IEEE Transactions on Power Systems, Vol.13, No.2, ay 1998, pp.1-8. [27] Pylvanainen, Jouni K., Kirsi Nousiainen, and Pekka Verho, "Studies to Utilize Loading Guides and ANN for Oil-Immersed Distribution Transformer Condition Monitoring," IEEE Transactions on Power Delivery, Vol. 22, No. 1, January 2007, pp.201-207. [28] Radakovic, Z., E Cardillo, and K. Feser, "The influence of transformer loading to the ageing of the oil-paper insulation," presented at the XIIIth International Symposium on High Voltage Engineering, Netherlands, 2003. [29] IEC Loading guide for oil-immersed power transformers, IEC Standard 600767- Power transformers-Part 7, Committee draft 14/403/CD, 2001. [30] Yang, Minghao, Yajun Shi, and Jing Zhang, "Efficient Operation Regions of Power Distribution Transformers," IEEE Transactions on Power Delivery, Vol. 19, No.4, October 2004, pp. 1713-1717. [31] R.N.Adams, M.A.Laughton, "A Dynamic Programming /Network Flow Procedure for Distribution System Planning", PICA, [32] J.L.Kennington, R.V.Helgason, "Algorithms for Network Programming", John Wiley & Sons, 1980. [33] D.L.Wal1, G.L.Thompson, J.E.D.Northcote-Green, "An Optimization Model for Planning Radial Distribution Networks", IEEE Trans. PAS, Vol. PAS-98, No. 3, May/June 1979, pp. 1061-1068. [34] T.H.Fawzi, K.F.Ali, S .M.El-Sobki, "A New Planning Model for Distribution Systems", IEEE Trans. PAS, Vol. PAS-102, No. 9, September 1983, pp. 3010-3017. [35] Stanley H. Horowitz and Arun Phadke, “ Power System Relaying”, Third Edition, John Wiley And Sons, Inc., 2007. [36] Turan Gonen, “ Electrical Machines”, Carmichael. California: Power International Press, 1998, pp.101-102. [37] Stephen J Chapman, “ Electric Machinery Fundamentals”, 4th Edition, New York, New York: Mc Graw Hill,2005, pp. 65-67. [38] D. A. Douglass, “ Economic measures of bare overhead conductor characteristics”, IEEE Transaction on Power Delivery, Vol. 3, No.2, April 1998, pp. 745-761. 99 [39] R.E. Kennon, and D. A. Douglass, “ EHV transmission line design opportunities for cost reduction”, IEEE paper 89 TD 434-2 PWRD. [40] Jerry M. Hersterlee, Eugene T. Sanders, and Frank R. Thrash, Jr., “ Bare overhead transmission and distribution conductor design overview”, IEEE Transactions on Industry application, Vol. 32, No. 3, May/June 1996, pp. 709-713.