Chapter 10

advertisement
T10.1 Chapter Outline
Chapter 10
Making Capital Investment Decisions
Chapter Organization
 Project Cash Flows: A First Look
 Incremental Cash Flows
 Pro Forma Financial Statements and Project
Cash Flows
 More on Project Cash Flow
 Alternative Definitions of Operating Cash Flow
 Some Special Cases of Discounted Cash
Flow Analysis
CLICK MOUSE OR HIT
SPACEBAR TO ADVANCE
T10.2 Fundamental Principles of Project Evaluation
 Fundamental Principles of Project Evaluation:
Project evaluation - the application of one or more capital
budgeting decision rules to estimated relevant project cash
flows in order to make the investment decision.
Relevant cash flows - the incremental cash flows associated with
the decision to invest in a project.
The incremental cash flows for project evaluation consist
of any and all changes in the firm’s future cash flows that
are a direct consequence of taking the project.
Stand-alone principle - evaluation of a project based on the
project’s incremental cash flows.
Mgt 3040 Y Chapter 10
Slide 2
T10.3 Incremental Cash Flows
 Terminology
 Key issue:
 When
is a cash flow
incremental?
A. Sunk costs
B. Opportunity costs
C. Side effects
D. Net working capital
E. Financing costs
F. Inflation
G. Government Intervention
H. Other issues
Mgt 3040 Y Chapter 10
Slide 3
Incremental Cash Flows
 Sunk Cost - a cost that has already been incurred, cannot
be removed and therefore should not be considered in the
investment decision - the ‘firm has to pay this cost no
matter what’

example in the oil & gas business is the exploration costs
incurred in finding reserves - these are sunk costs and should
not be considered in any evaluation of developing those
reserves
 Opportunity Costs ‘ the most valuable alternative that is
given up if a particular investment is undertaken’ - if a
project results in an opportunity being forgone this benefit
that has been given up should be included in the project
cash flow as a cost - see the text example
 Side Effects - ‘erosion’ - cash flows of a new project that
come at the expense of a firm’s existing projects – these
‘negative’ cash flows should be included
Mgt 3040 Y Chapter 10
Slide 4
Incremental Cash Flows
 Net Working Capital - projects often require investment in
working capital in addition to the investment in longer term
assets e.g. Investment in inventories & receivables.
Important to build in the recovery of this cash investment
at the end of the project.
 Financing Costs - are not included. The financing of the
project is a separate decision - we want to evaluate the
cash flows generated by the assets from the project.
 Inflation - a factor in projects with longer lives. Cash flows
should factor in inflation just as the nominal discount rate
includes inflation premiums. An alternative approach is to
use a ‘real;’ or inflation adjusted discount rate and
calculate future ‘real’ cash flows - adjusted for inflation
(inflation element removed)
Mgt 3040 Y Chapter 10
Slide 5
Incremental Cash Flows
 Government Intervention - where government incentives
result in incremental cash flow - they should be
incorporated into the project cash flow e.g. Grants, tax
credits, subsidized loans, etc.
 Other - after tax incremental cash flow (not after tax
earnings!)
Mgt 3040 Y Chapter 10
Slide 6
Pro Forma Financial Statements & Project Cash Flows – the mechanics
 Projecting the future years operations of the project in the
form o f pro forma financial statements summarize the
relevant project information – these pro forma statements
can then be used to project the cash flows


projected income statement - enable the projection of
operating cash flows
projected balance sheet or balance sheet extracts - enable the
projection of working capital and capital spending
 Project cash flows – use the Cash Flow From Assets
model (similar to ‘mini-firm’ cash flow) in establishing the
incremental cash flow from the project



operating cash flow
net working capital requirements
capital spending
Mgt 3040 Y Chapter 10
Slide 7
NPV - Incremental Well Case
CAPEX
Year
2002
Net of Royalties
at 20%
Fixed Well
Costs
Variable
Costs
Total Well
Costs
Net Cash
Flow
434940
324220
267000
224280
192240
160200
145340
125730
105120
95440
85260
74580
63400
52720
52720
347952
259376
213600
179424
153792
128160
116272
100584
84096
76352
68208
59664
50720
42176
42176
30000
30000
30000
31000
31500
32000
32000
32500
33000
33500
34000
34500
35500
36000
36500
52500
48000
38000
30000
24000
18500
14500
10000
7500
5000
3000
3000
3000
3000
3000
82500
78000
68000
61000
55500
50500
46500
42500
40500
38500
37000
37500
38500
39000
39500
-300,000
265452
181376
145600
118424
98292
77660
69772
58084
43596
37852
31208
22164
12220
3176
2676
2403190
1922552
-300,000
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
Total
Incremental Price
WI @50%WI Revenues
Production$Cdn/bbl
$
m bbls
m bbls
33
29
25
21
18
15
13
11
9
8
7
6
5
4
4
-300,000
26.36
22.36
21.36
21.36
21.36
21.36
22.36
22.86
23.36
23.86
24.36
24.86
25.36
26.36
26.36
208
16.5
14.5
12.5
10.5
9
7.5
6.5
5.5
4.5
4
3.5
3
2.5
2
2
104
492000
NPV at 15%
NPV at 10%
Mgt 3040 Y Chapter 10
Slide 8
263000
$394,442.02
$505,363.01
755000
116755
T10.4 Example: Preparing Pro Forma Statements
 Suppose we want to prepare a set of pro forma financial
statements for a project for ABC Co. In order to do so, we
must have some background information. In this case,
assume:
1. Sales of 10,000 units/year @ $5/unit.
2. Variable cost per unit is $3. Fixed costs are $5,000 per year.
The project has no salvage value. Project life is 3 years.
3. Project cost is $21,000. Depreciation is $7,000/year.
4. Additional net working capital is $10,000.
5. The firm’s required return is 20%. The tax rate is 34%.
Mgt 3040 Y Chapter 10
Slide 9
T10.4 Example: Preparing Pro Forma Statements (continued)
Pro Forma Financial Statements
Projected Income Statements
Sales
Var. costs
$50,000
30,000
$20,000
Fixed costs
5,000
Depreciation
7,000
EBIT
$ 8,000
Taxes (34%)
Net income
Mgt 3040 Y Chapter 10
2,720
$ 5,280
Slide 10
T10.4 Example: Preparing Pro Forma Statements (concluded)
Projected Balance Sheets
0
1
2
3
NWC
$10,000
$10,000
$10,000
$10,000
NFA
21,000
14,000
7,000
0
Total
$31,000
$24,000
$17,000
$10,000
Mgt 3040 Y Chapter 10
Slide 11
T10.5 Example: Using Pro Formas for Project Evaluation
 Now let’s use the information from the previous example
to do a capital budgeting analysis.
Project operating cash flow (OCF):
EBIT
$8,000
Depreciation
+7,000
Taxes
-2,720
OCF
$12,280
Mgt 3040 Y Chapter 10
Slide 12
T10.5 Example: Using Pro Formas for Project Evaluation (continued)
 Project Cash Flows
0
OCF
Chg. NWC
______
Cap. Sp.
-21,000
Total
______
1
2
3
$12,280
$12,280
$12,280
______
$12,280
Mgt 3040 Y Chapter 10
Slide 13
$12,280
$______
T10.5 Example: Using Pro Formas for Project Evaluation (continued)
 Project Cash Flows
0
OCF
Chg. NWC
-10,000
Cap. Sp.
-21,000
Total
-31,000
1
2
3
$12,280
$12,280
$12,280
10,000
$12,280
Mgt 3040 Y Chapter 10
Slide 14
$12,280
$22,280
T10.5 Example: Using Pro Formas for Project Evaluation (concluded)
 Capital Budgeting Evaluation:
NPV
=
=
-$31,000 + $12,280/1.201 + $12,280/1.20 2 + $22,280/1.20 3
$655
IRR
=
21%
PBP
=
2.3 years
AAR
=
$5280/{(31,000 + 10,000)/2} = 25.76%
 Should the firm invest in this project?
Yes -- the NPV > 0, and the IRR > required return
Mgt 3040 Y Chapter 10
Slide 15
Example: Estimating Changes in Net Working Capital
 In estimating cash flows we must account for the fact that some of the
incremental sales associated with a project will be on credit, and that some
costs won’t be paid at the time of investment.
Estimate changes in NWC. Assume:
1.
2.
Fixed asset spending is zero.
The change in net working capital spending is $200:
0
1
Change
A/R
$100
$200
+100
___
INV
100
150
+50
___
-A/P
100
50
(50)
___
NWC
$100
$300
Mgt 3040 Y Chapter 10
Chg. NWC = $_____
Slide 16
Example: Estimating Changes in Net Working Capital
 In estimating cash flows we must account for the fact that some of the incremental
sales associated with a project will be on credit, and that some costs won’t be paid
at the time of investment. How?
Answer: Estimate changes in NWC. Assume:
1.
2.
Fixed asset spending is zero.
The change in net working capital spending is $200:
0
1
Change
A/R
$100
$200
+100
INV
100
150
+50
-A/P
100
50
(50)
NWC
$100
$300
Mgt 3040 Y Chapter 10
Chg. NWC = $200
Slide 17
Example: Estimating Changes in Net Working Capital (continued)
 Now, estimate operating and total cash flow:
Sales
$300
Costs
200
Depreciation
EBIT
0
$100
Tax
0
Net Income
$100
OCF = EBIT + Dep.  Taxes = $100
Total Cash flow = OCF Change in NWC  Capital Spending
= $100  ______  ______ = ______
Mgt 3040 Y Chapter 10
Slide 18
Example: Estimating Changes in Net Working Capital (continued)
 Now, estimate operating and total cash flow:
Sales
$300
Costs
200
Depreciation
EBIT
0
$100
Tax
0
Net Income
$100
OCF = EBIT + Dep.  Taxes = $100
Total Cash flow = OCF Change in NWC  Capital Spending
= $100  200 
Mgt 3040 Y Chapter 10
0
Slide 19
=  $100
Example: Estimating Changes in Net Working Capital (concluded)
 Where did the - $100 in total cash flow come from?
 What really happened:
Cash sales = $300 - ____
= $200 (collections)
Cash costs = $200 + ____ + ____ = $300 (disbursements)
Mgt 3040 Y Chapter 10
Slide 20
Example: Estimating Changes in Net Working Capital (concluded)
 Where did the - $100 in total cash flow come from?
 What really happened:
Cash sales = $300 - 100
= $200 (collections)
Cash costs = $200 + 50 + 50 = $300 (disbursements)
Cash flow
= $200 - 300 = - $100 (= cash in  cash out)
Mgt 3040 Y Chapter 10
Slide 21
CCA Property Classes (See Chapter 2)
Class
Rate
Examples
8
20%
Furniture, photocopiers
10
30%
Vans, trucks, tractors and computer
equipment
13
Straight-line
22
50%
Leasehold improvements
Pollution control equipment
Mgt 3040 Y Chapter 10
Slide 22
Depreciation on $10,000 Furniture (CCA Class 8, 20% rate)
Year
UCC t
CCA
UCC t+1
1
$5,000
$1,000
$4,000
2
9,000
1,800
7,200
3
7,200
1,440
5,760
4
5,760
1,152
4,608
5
4,608
922
3,686
6
3,686
737
2,949
Mgt 3040 Y Chapter 10
Slide 23
CCA on Assets of $10,000 by year
Year
Class 8
Class 10
Class 22
1
$1,000
$1,500
$2,500
2
1,800
2,550
3,750
3
1,440
1,785
1,875
4
1,152
1,250
938
5
922
875
469
6
737
612
234
Mgt 3040 Y Chapter 10
Slide 24
Example: Fairways Equipment and Operating Costs
Two golfing buddies are considering opening a new driving range, the
“Fairways Driving Range” (motto: “We always treat you fairly at
Fairways”). Because of the growing popularity of golf, they estimate
the range will generate rentals of 20,000 buckets of balls at $3 a bucket
the first year, and that rentals will grow by 750 buckets a year
thereafter. The price will remain $3 per bucket.
Capital spending requirements include:
Ball dispensing machine
Ball pick-up vehicle
Tractor and accessories
$ 2,000
8,000
8,000
$18,000
All the equipment is Class 10 CCA property, and is expected to have a
salvage value of 10% of cost after 6 years.
Anticipated operating expenses are as follows:
Mgt 3040 Y Chapter 10
Slide 25
T10.10 Example: Fairways Equipment and Operating Costs (concluded)
Working Capital
Operating Costs (annual)
Land lease
$ 12,000
Water
1,500
Electricity
3,000
Labor
30,000
Seed & fertilizer
2,000
Gasoline
1,500
Maintenance
1,000
Insurance
1,000
Misc. Expenses
1,000
Initial requirement = $3,000
Working capital requirements
are expected to grow at 5%
per year for the life of the
project
$53,000
Mgt 3040 Y Chapter 10
Slide 26
T10.11 Example: Fairways Revenues, Depreciation, and Other Costs
Projected Revenues
Year
Buckets
Revenues
1
20,000
$60,000
2
20,750
62,250
3
21,500
64,500
4
22,250
66,750
5
23,000
69,000
6
23,750
71,250
Mgt 3040 Y Chapter 10
Slide 27
T10.11 Example: Fairways Revenues, Depreciation, and Other Costs (continued)
Cost of balls and buckets
Year
Cost
0
$3000
1
$3,150
2
3,308
3
3,473
4
3,647
5
3,829
6
4020
Mgt 3040 Y Chapter 10
Slide 28
T10.11 Example: Fairways Revenues, Depreciation, and Other Costs (concluded)
Depreciation on $18,000 of Class 10 CCA equipment
Year
UCC t
CCA
UCC t+1
1
9,000
2,700
$15,300
2
15,300
4,590
10,710
3
10,710
3,213
7,497
4
7,497
2,249
5,248
5
5,248
1,574
3,674
6
3,674
1,102
2,572
Mgt 3040 Y Chapter 10
Slide 29
T10.12 Example: Fairways Pro Forma Income Statement
Year
1
Revenues
$60,000
2
3
4
$62,250 $64,500 $66,750
5
6
$69,000 $71,250
Variable costs
Fixed costs
53,000
53,000
53,000
53,000
53,000
53,000
Depreciation
2,700
4,590
3,213
2,249
1,574
1,102
$4,300
$4,660
Taxes(20%)
860
932
1,657
2,300
Net income
$3,440
$3,782
$6,630
$9,201
EBIT
Mgt 3040 Y Chapter 10
$8,287 $11,501
Slide 30
$14,426 $17,148
2,885
3,429
$11,541 $13,719
T10.13 Example: Fairways Projected Changes in NWC
 Projected increases in net working capital
Year
Net working capital
0
$ 3,000
$ 3,000
1
3,150
150
2
3,308
158
3
3,473
165
4
3,647
174
5
3,829
182
6
4,020
- 3,829
Mgt 3040 Y Chapter 10
Slide 31
Change in NWC
T10.14 Example: Fairways Cash Flows
 Operating cash flows:
Year
0
EBIT
$
0
– Taxes
+ Depreciation
$
0
$
0
Operating
= cash flow
$
0
1
4,300
2,700
860
6,140
2
4,660
4,590
932
8,318
3
8,287
3,213
1,657
9,843
4
11,501
2,249
2,300
11,450
5
14,426
1,574
2,885
13,115
6
17,148
1,102
3,429
14,821
Mgt 3040 Y Chapter 10
Slide 32
T10.14 Example: Fairways Cash Flows (concluded)
 Total cash flow from assets:
Year
OCF
– Chg. in NWC – Cap. Sp. = Cash flow
0
$ 3,000
$18,000
– $21,000
1
6,140
150
0
5,990
2
8,318
158
0
8,160
3
9,843
165
0
9,678
4
11,450
174
0
11,276
5
13,115
182
0
12,933
6
14,821
-3829
-2,108*
20,758
0
$
 * after tax
Mgt 3040 Y Chapter 10
Slide 33
Fairways Cash Flow Example
 Assume a discount rate of 20% - what is the NPV?
 IRR??
 Payback ?
Mgt 3040 Y Chapter 10
Slide 34
Present Value of the Tax Shield on CCA
 Shortcut in establishing future cash flows - using a
formula that replaces the detailed calculation of yearly
CCA
 The formula is based on the theory that the tax shield from
CCA continues in perpetuity as long as there are assets in
that particular CCA class.






C= total capital cost of the asset which is added to the pool
d= CCA rate for that asset class
Tc =company’s marginal tax rate
k = discount rate
S = salvage or disposal value of the asset
n = asset life in years
PV of tax shield on CCA = (CdTc)/d+k *(1+.5k)/1+k Sdtc/d+k*1/(1+k)n
Mgt 3040 Y Chapter 10
Slide 35
Alternative approaches in calculating OCF
Let:
OCF = operating cash flow
S
= sales
C
= operating costs
D
= depreciation
T
= corporate tax rate
Mgt 3040 Y Chapter 10
Slide 36
Alternative Approaches in Calculating OCF (concluded)

The Tax-Shield Approach
OCF
shield

(S - C - D) + D - (S - C - D)  T
=
(S - C)  (1 - T) + (D  T)
=
(S - C)  (1 - T) + Depreciation x T
……cash flow w/o dep’n plus dep’n tax
The Bottom-Up Approach
OCF

=
=
(S - C - D) + D - (S - C - D)  T
=
(S - C - D)  (1 - T) + D
=
Net income + Depreciation
…..start with accounting net income plus
dep’n
The Top-Down Approach
OCF
=
(S - C - D) + D - (S - C - D)  T
=
(S - C) - (S - C - D)  T
=
Sales - Costs – Taxes
…..start at top of income statement – leave
out non cash flows
Mgt 3040 Y Chapter 10
Slide 37
Example: A Cost-Cutting Proposal
Consider a $10,000 machine that will reduce pretax operating costs
by $3,000 per year over a 5-year period. Assume no changes
in net working capital and a scrap (i.e., market) value of $1,000 after five years.
For simplicity, assume straight-line depreciation. The marginal tax
rate is 34% and the appropriate discount rate is 10%.
Using the tax-shield approach to find OCF:
OCF
=
(S - C)(1 - T) + (Dep  T)
=
[$0 - (-3,000)](.66) + (2,000  .34)
=
$1,980 + $680 = $2,660
The after-tax salvage value is:
market value - (increased tax liability) = market value - (market value - book)  T
= $1,000 - ($1,000 - 0)(.34) = $660
Mgt 3040 Y Chapter 10
Slide 38
Example: A Cost-Cutting Proposal (concluded)
The cash flows are
Year
OCF
Capital spending
Total
0
-$10,000
-$10,000
1
2,660
0
2,660
2
2,660
0
2,660
3
2,660
0
2,660
4
2,660
0
2,660
5
2,660
+660
3,320
0
$
….key point here is the project economics are driven by a reduction
in operating costs – depicted as positive cash flow for the project
Mgt 3040 Y Chapter 10
Slide 39
Evaluating Equipment with Different Lives
 The goal is to still maximize net present value but when
system/equipment have different lives or time frames we
need to establish what the ‘equivalent annual cost’ (EAC)
is
 The equivalent annual cost is the present value of a
project’s costs calculated on an annual basis (think
annuity!)
 PV of costs = EAC * annuity factor
EAC = PV of costs/Annuity factor
Annuity factor = (1-present value factor)/r
(1-(1/1+r)t )r
Mgt 3040 Y Chapter 10
Slide 40
Example: Setting the Bid Price
The Canadian Forces are seeking bids on Multiple Use Digitizing Devices (MUDDs). The contract
calls for4 units per year for 3 years. Labor and material costs are estimated at $10,000 per
MUDD.
Production space can be leased for $12,000 per year. The project will require $50,000 in new
equipment which is expected to have a salvage value of $10,000 after 3 years. Making MUDDs
will require a $10,000 increase in net working capital. Assume a 34% tax rate and a required
return of 15%. Use straight-line depreciation to zero.
Increases
in NWC
Capital
spending
Total
= cash flow
0
– $10,000
– $50,000
– $60,000
1
OCF
0
0
OCF
2
OCF
0
0
OCF
3
OCF
10,000
+ 6,600
OCF + 16,600
Year
0
Operating
cash flow
$
Mgt 3040 Y Chapter 10
Slide 41
Example: Setting the Bid Price (continued)
 Taking the present value of $16,600 in year 3 ( = $10,915 at
15%) and netting against the initial outlay of – $60,000 gives
Year
0
Total
cash flow
–
$49,085
1
OCF
2
OCF
3
OCF
The result is a three-year annuity with an unknown cash
flow equal to “OCF.”
Mgt 3040 Y Chapter 10
Slide 42
T10.19 Example: Setting the Bid Price (continued)

The PV annuity factor for 3 years at 15% is 2.283. Setting NPV = $0,
NPV = $0 = – $49,085 + (OCF  2.283), thus
OCF = $49,085/2.283 = $21,500
 Using the bottom-up approach to calculate OCF,
OCF = Net income + Depreciation
$21,500 = Net income + $50,000/3 = Net income + $16,667
Net income = $4,833
 Next, since annual costs are $40,000 + $12,000 = $52,000
Net income = (S - C - D)  (1 - T)
$4,833 = (S  .66) - (52,000  .66) - (16,667  .66)
S = $50,153/.66 = $75,989.73
Hence, sales need to be at least $76,000 per year (or $19,000 per MUDD)!
Mgt 3040 Y Chapter 10
Slide 43
Example: Setting the Bid Price -another example
Background: Suppose we also have the following information.

1.
The bid calls for 20 MUDDs per year for 3 years.

2.
Our costs are $35,000 per unit.

3.
Capital spending required is $250,000; and
depreciation = $250,000/5 = $50,000 per year

4.
We can sell the equipment in 3 years for half its original cost: $125,000.

5.
The after-tax salvage value equals the cash in from the sale of the
equipment, less the cash out due to the increase in our tax liability
associated with the sale of the equipment for more than its book value:
Book value at end of 3 years = $250,000 - 50,000(3) = $100,000
Book gain from sale = $125,000 - 100,000 = $25,000
Net cash flow = $125,000 - 25,000(.39) = $115,250

6.
The project requires investment in net working capital of $60,000.

7.
Required return = 16%; tax rate = 39%
Mgt 3040 Y Chapter 10
Slide 44
Example: Setting the Bid Price (continued)

The cash flows ($000) are:
0
1
OCF
2
$OCF
$OCF
3
$OCF
Chg. in NWC
- $ 60
+ 60
Capital Spending
- 250
______
______
+115.25
- $310
$OCF
$OCF
$OCF +
175.25
Find the OCF such that the NPV is zero at 16%:
+$310,000 - 175,250/1.163
=
OCF  (1 - 1/1.163)/.16
$197,724.74
=
OCF  2.2459
OCF
=
$88,038.50/year
Mgt 3040 Y Chapter 10
Slide 45
Example: Setting the Bid Price (concluded)
If the required OCF is $88,038.50, what price must we bid?
Sales
$_________
Costs
700,000.00
Depreciation
EBIT
50,000.00
$_________
Tax
Net income
24,319.70
$ 38,038.50
Sales = $62,358.20 + 50,000 + 700,000 = $812,358.20 per year, and
the bid price should be $812,358.20/___ = ________ per unit.
Mgt 3040 Y Chapter 10
Slide 46
Example: Setting the Bid Price (concluded)
If the required OCF is $88,038.50, what price must we bid?
Sales
$812,358.20
Costs
700,000.00
Depreciation
EBIT
50,000.00
$ 62,358.20
Tax
Net income
24,319.70
$ 38,038.50
Sales = $62,358.20 + 50,000 + 700,000 = $812,358.20 per year, and
the bid price should be $812,358.20/20 = $40,618 per unit.
Mgt 3040 Y Chapter 10
Slide 47
Download