Part 1 (Open to the public) ______________________________________________________________ JOINT REPORT OF THE STRATEGIC DIRECTOR OF HOUSING AND PLANNING AND THE MANAGING DIRECTOR OF URBAN VISION PARTNERSHIP LIMITED ______________________________________________________________ TO THE LEAD MEMBER FOR PLANNING ON 17 JULY 2006 ______________________________________________________________ TITLE: Building Maintenance Programme 2006/07 ______________________________________________________________ RECOMMENDATIONS: That Lead Member for Planning; 1. Approves the £500,000 allocation of funds to responsive repair and essential plant servicing as being the minimum reasonable estimate for these works as described in Section 2.3 and 3.1 2. In light of there being no additional resources currently available, approves the expenditure of £31,000 in respect of additional regular preventative maintenance work necessitated by legislation, good practice guidance and new technology detailed in para 3.2 to be met out of the maintenance budget (note it is anticipated that funding for asbestos management will be met from an additional corporate funding allocation) 3. Notes that there is insufficient funding for all four of the most urgent works required shown Bold in the table to section 3.3., to proceed, but that the lightning conductor repairs works have had to be committed already for H&S reasons. 4. Approves that Crompton House and 196 Station Road boundary walls and fence replacement proceed at this stage. 5. Approves that VMS depot works are deferred until funding for the full cost becomes available. 6. Supports that within the Spending Review the case is made for additional funding to be allocated to the councils maintenance budget. ______________________________________________________________ EXECUTIVE SUMMARY: The building maintenance budget has remained fixed since 1992. The council performs poorly in relation to the national property condition and backlog maintenance performance indicators and it is clear that the council does not allocate sufficient funds to adequately maintain its property portfolio. This year’s maintenance report highlights an intensifying problem. With 80% of the budget being used for responsive repairs / routine maintenance there is now insufficient funds to meet even the most urgent works identified. Previous reports recommending the allocation of additional capital and revenue funding have not been approved, resulting in the current budget being insufficient to meet priority schemes and H&S requirements. ______________________________________________________________ BACKGROUND DOCUMENTS: The City Councils Asset Management Plan Survey Information for the buildings detailed in the report. 1 ______________________________________________________________ ASSESSMENT OF RISK: Medium ______________________________________________________________ SOURCE OF FUNDING: Building Maintenance Revenue Budget 2006/07 ______________________________________________________________ LEGAL IMPLICATIONS: H&S May be compromised with inadequate maintenance budgets ______________________________________________________________ FINANCIAL IMPLICATIONS: Maintenance budget is inadequate to meet current liabilities COMMUNICATION IMPLICATIONS: N/A VALUE FOR MONEY IMPLICATIONS: An inadequately funded maintenance budget gives poor value for money. CLIENT IMPLICATIONS: Occupiers of corporate buildings will express increasing levels of dissatisfaction with the condition of the buildings they occupy. PROPERTY: the condition of the councils building stock will continue to decline. ______________________________________________________________ HUMAN RESOURCES: N/A __________________________________________________________ CONTACT OFFICER: Mr Steven Durbar x3755 / John Dooley x4968 (Urban Vision) ______________________________________________________________ WARD(S) TO WHICH REPORT RELATE(S): All ______________________________________________________________ KEY COUNCIL POLICIES: Procurement Strategy ______________________________________________________________ 1.0 BACKGROUND: 1.1 This report is prepared by Urban Vision in it’s role as provider of professional advice and maintenance management of all non-housing property to the City Council’s Directorates. In addition to dealing with specific building maintenance issues this report for 2006/7 aims to begin the setting up of new processes and protocols to take account of the following recent major changes Re-organisation of City Council Directorates in September 2005 including transfer of buildings and budgets. Replacement of the former combination of individual and centrally held budgets with a system whereby each client Directorate is directly in control of it’s own distinct budget. 1.2 The Urban Vision role is complimentary to the Strategic Asset Management Planning function of the Housing and Planning Directorate both in terms of the medium and long term property strategy and also the monitoring of overall property maintenance condition and “maintenance backlog” within the Asset Management Plan. This report draws on Asset Management information in order to inform and make recommendations to the Housing & 2 Planning Directorate. Similar reports have been presented to other property occupying directorates. 1.3 The major challenge facing all Directorates is the decline in “real terms” of revenue maintenance budgets over a long period of time and the consequent building up of a significant maintenance backlog in those areas where external or other additional funding has not been available. The recent re-allocation of previously central budgets to Directorates has not altered the overall resource situation, but it does make clear to each Directorate how critical the situation now is in certain areas. 1.4 As set out in previous annual maintenance programmes and reports the effect of overall shortfalls is to greatly reduce amounts available for planned major repairs and replacements. This is due to responsive repair and basic plant servicing being a “first call” on budgets. Additionally, increases in the scope of servicing work imposed by legislation and the effects of many years inflation have increased costs, such that only a small and rapidly declining amount remains for planned works. 1.5 It is proposed in future years that following discussion between Urban Vision officers and Directorate officers regarding the maintenance priorities, budget availability and resultant advice, a formal report of this type will be put to each Directorate detailing the maintenance situation and recommendations for the planned programme of works. A further report would confirm the final agreed budget and programme which a Directorate wishes to proceed with. Directorates need to consider and decide on the general level of delegation to be given to Urban Vision in terms of discretion to manage agreed programmes within budgets and the reporting and control protocols they require to be in place. 2.0 PROPERTY AND BUDGET DETAILS Set out below are the essential statistics and facts in summarised form in respect of each building group within this Directorate. It should be noted that Housing and Planning Directorate holds the corporate office portfolio, which provides office accommodation for all directorates. Additionally the Directorate is responsible for other miscellaneous operational buildings and the management of the non operational estate. 2.1 Particular care should be taken with the “backlog maintenance” figures given below which are for basic maintenance works only. They are taken from an inspection generally on a 5 yearly basis and are the estimated cost of maintenance works due over the following 5 years. In reality for operational or other reasons clients may require much more extensive works – but the figures given are indicative of the general condition of that group in accordance with relevant guidance on work priorities. Building Group Civic Centre Complex and Other Corporate and Operational bldgs Housing Shops / Parades of Shops Misc and Industrial Directorate Total / Average Number of Buildings Floor area (m²) GIA Backlog (£) 37 48,675.95 2,243,214. 54 N/A N/A 48,675.95 Excluded see Inv Estate Strategy Comment 2,243,214. 2 Markets plus industrial estates 93 - 2.2 The above statistics alone do not give the complete picture in terms of determining the true requirement for maintenance work or making appropriate decisions. The information set out below will explain and interpret some of the more salient points. 3 Civic Centre Complex Comprising the Former Swinton Town Hall, Phase 2 Building, Unity House, Innovation House, Elmstead House and Crompton House. There are many complex issues involving on-going office re-location projects as well as plans for operational changes, however this report concentrates on maintenance aspects only. With respect to the former Swinton Town Hall a number of specific works are proposed. It must be borne in mind that the building still has its original roof coverings, timber windows and heating pipework which are approaching 70 years old. In terms of performance, efficiency and costs to keep in repair then clearly these elements are far from ideal but are generally sound in that they can be made to last for some time yet. The more modern Phase 2 and Unity House buildings whilst being generally sound externally have far more complex heating and ventilation systems which tend to have continuing performance and maintenance problems. Past reports have highlighted the major issues with the original system to the Phase 2 building whilst the original main cooling plant to Unity House is likely to require replacement in the medium term. Many other interior aspects are being attended to within office re-location schemes although considerable areas will remain to be addressed. Elmstead House is generally sound but its heating system fed via the former Police Station plant room has become unreliable and problematic. Crompton House was re-roofed (following long standing problems) in 2005 but its original windows require replacement at major cost. The boundary wall has become dangerously unstable and requires immediate re-building at a cost of approximately £15,000. In addition work is urgently required to its electrical mains – although the remainder of the building not yet re-wired to modern standards is likely to be covered by office re-location projects. Due to the poor condition of lightning conductors at the Civic centre generally works to Phase 2 and Unity House have been commenced as a maintenance commitment – with other major works remaining to be addressed. Other Core Office Accommodation sites These comprise Turnpike House Complex, Minerva House and Burrows House. Taken together with the Civic Centre this is a very large area of office space – which taking average likely future maintenance costs would require a maintenance budget considerably larger than the current one. A large percentage of the space has been relatively recently acquired or refurbished by externally funded initiatives - but the ongoing maintenance costs for external items, heating systems and decoration etc will be considerable. Of the many items currently or shortly requiring attention then the replacement roof to the Turnpike House Vehicle Maintenance Building is by far the most urgent. Other Corporate and Operational Buildings. Proposed works to a number of other buildings are recommended – along with the recommended additional servicing items suggested in 3.2 below to all buildings. In respect of building such as Irlam Council Offices and Encombe Place Offices then a decision is required as to whether maintenance works can be avoided by re-location of services, although clearly some works cannot be postponed for a long period. Investment Estate Buildings Due to their age and nature of their construction (asbestos cement roofs etc) then many industrial buildings are ready for major external refurbishment. Although generally let with tenants responsible for repair then a number of vacant etc units require external repair and decoration. To address this issue Urban Vision is developing a investment estate strategy which will include recommendations to address maintenance out of improved income generation. 4 2.3 Existing Budget 2006/07 Summarised Existing Budget Details 2006/7 – Responsive / Planned split Building Group Civic Centre Complex Other Corporate and Operational Housing Shops Misc and Industrial Directorate Total 3.0 Total existing budget – previously with shared Corporate budget. £630,000 Amount estimated for responsive repair and essential plant servicing to existing level £120,000 £250,000 £60,000 £70,000 £500,000 Remainder for any planned replacements or extended service £130,000 PROPOSALS AND RECOMMENDATIONS 3.1 Responsive Repairs and essential Plant Servicing It is recommended that the above amounts comprising minimum reasonable estimates for Responsive Repair and Plant Servicing be allowed within relevant budgets for 2006/7. Due to the nature of responsive repair and the aim to minimise these budgets then it cannot be guaranteed that they will meet all possible requirements. The areas covered by existing service contracts are Service of Oil and Gas Heating Systems Air Handling and Air Conditioning Water system treatment and monitoring and anti-legionella. Fire alarm and Emergency Lighting Lift Servicing. Electrical testing 3.2 Additional Preventative Maintenance It is recommended that there be additional resources (or discussions leading to agreement as to priorities) in respect of additional regular preventive maintenance work necessitated by Legislation, Good Practice guidance and new technology as summarised below. Figures are global amounts for all Housing and Planning) buildings unless stated otherwise. £5,000 in respect of Lightning Conductor Regular Maintenance £12,000 in respect of Service Contract to all electrically operated, roller shutter and similar doors under relevant legislation. £6,000 in respect of additional funding to ensure all 5 yearly electrical tests can be completed. £30-40,000 for Type 2 asbestos surveys plus all managerial changes to meet Asbestos Management Regulation Requirements Surveys and works to complete works required to ensure all glazing complies with safety requirements £8,000. It should be noted that a corporate allocation to deal with asbestos surveys is anticipated 3.3 Programme Maintenance It is recommended that as far as possible a programme of works be carried out to maintain or restore all buildings such that they are in the appropriate and safe condition for their purpose. In order to begin to deal with the maintenance backlog it is recommended that the projects in the following table are those most in need of being addressed over the next year – together with a budget estimate of likely cost, totalling £1.022m. The most urgent works are highlighted in bold and total £164,000. It must be understood there is always a risk that other projects may become more urgent or unforeseeable defects emerge during routine works such that priorities may need to be amended. 5 Building Category CIVIC CENTRE COMPLEX Building Works Old Town Hall Refurbish Toilets West Wing Old Town Hall Decorations and flooring to corridors Restore corridor etc rooflights Phase 2. Lightning Conductor repair works External decoration (windows) – south facing higher priority. Decorations and flooring to stairs, corridors and lobbies Improve fire exit route to main staircase Upgrade all toilets as carried out to GF central toilets 2005 Unity House Suspended ceilings, lighting and carpeting to Ground and First Floor if required to match standard applied to Second Floor. Work to common parts including corridor doorsets and toilets. Crompton House Replace all original external aluminium windows. Boundary wall rebuild Plant and Engineering Works Old Town Hall Replace emergency light fittings Elmstead House. Provide new self –contained boiler plant and boiler house within Elmstead boundary to replace system via original Police Station boiler and pipework link. Estimated Cost £25,000 £15,000 £9,000 £25,000 £60,000 £32,000 £3,000 £65,000 £90,000 £12,000 £120,000 £15,000 £7,500 £40,000 Replacement of major parts to Air Conditioning / ventilation systems generally beyond scope of Responsive Repair Budget. £15,000 Crompton House. Work to electrical mains and full testing. £35,000. 6 OTHER CORE OFFICE SITES Building Works Turnpike House Complex VMS Building Roof replacement VMS – internal and external decoration in association with above VMS Replace remaining original windows Main office block replacement original steel windows Main Office Block – externally insulated main roof should be of very long life expectancy but leakages put this in doubt, Report may be required on possible options. £120,000 £9,000 £8,000 £150,000 £not known. Plant and Engineering Works Turnpike Main Office Building. Lift Installation major refurbishment. Turnpike Inspection Office Boiler replacement and associated plant Minerva House North Side. Boiler plant replacement Irlam Council Offices . electrical safety works. Pendleton House. Upgrade Fire Alarm and electrical mains. Not yet known. £5,000 £20,000 £3,500 £9,000 OTHER CORPORATE AND OPERATIONAL BUILDINGS Building Works Encombe Place Offices Roof, high priority external wall repairs and external decoration £33,000 Registry Office, “Kingslea”. Renew boundary fencing Refurbish Male Toilet £3,000 £2,000 Pendleton House Internal Decoration etc to common areas £12,000 Wesley St Offices Internal and external decoration Salford Quays Operations Tower. External repair and decoration 196 Station Road. Re-build boundary fence £10,000 £10,000 £4,000 Plant and Engineering Works No significant individual works. Nil HOUSING SHOPS This budget only includes an amount in respect of responsive repair. A survey has recently been completed and submitted to Housing and Planning Directorate in respect of the overall maintenance condition of the shop estate. INDUSTRIAL BUILDINGS Building Works In respect of Industrial Estates and Buildings at Broadway, Choir Street, Girton Street, Muslin Street and Neil Street then an amount has been estimated for external repairs and fencing – excluding roof replacement. Discussion and a decision is required in respect of how to proceed if any works are required. Amounts for replacement of asbestos roof areas and rainwater goods at Broadway and Muslin Street are in addition. Excluded see comment re investment estate strategy . Plant and Engineering Works No significant works. Nil 7 4.0 FINANCIAL IMPLICATIONS 4.1 Eighty percent of the budget (£500,000) is required to meet responsive repairs and routine maintenance. 4.2 Quite clearly, with only £130,000 available for planned works (or extended services) there are severe financial implications in terms of any programme of works, which would address the substantial existing backlog – which in 2005 was £2.2M for buildings in Housing and Planning control. (excluding investment estates and housing shops) Works in most need of being addressed over the next year identified in section 3 are estimated to cost £1.022M and of these the most urgent are estimated to cost £164,000 It must also be noted that there is additional preventative maintenance required for H&S reasons which is estimated will cost £31,000 (excluding asbestos surveys 4.3 4.4 4.5 Whilst other directorates who hold buildings for their own occupation may allocate additional funds for maintenance from other budgets the situation for Housing and Planning is somewhat different. As stated in 2.0 above Housing and Planning hold property occupied by other directorates, consequently it may not be appropriate for Housing and Planning to adopt this approach. Malcolm Sykes Bill Taylor Strategic Director Housing and Planning Managing Director (Urban Vision) 8