PART 1 (OPEN TO THE PUBLIC) ITEM NO. JOINT REPORT OF THE DIRECTORS OF CORPORATE SERVICES AND DEVELOPMENT SERVICES TO : THE LEAD MEMBER FOR CORPORATE SERVICES, MONDAY 16th JUNE 2003 SUBJECT: LIFT PROJECT AFFORDABILITY (version 3b) RECOMMENDATIONS: Lead Member is asked to note the contents of the report, in particular: i) the potential cost of LIFT of up to £ (based on the assumptions herein) ii) the uncertainty of other funding to meet that cost; iii) that any additional requirements, such as additional Social Services facilities (para ) or community space (para ) will push this cost up. Lead Member may wish to consider the level of financial commitment EXECUTIVE SUMMARY: LIFT represents an opportunity to redesign the Council’s interface with the public and to provide services in high-standard accommodation, while transferring the design, build, finance and operating risks to the private sector. It is hoped that synergies of placing various Council and health services in one location will lead to increased and enhanced public use overall. This report gives an update on the estimated cost to the Council of the LIFT project. The cost of accommodation for placing services in LIFT centres, at £184/m2/pa, is substantially greater than the comparable current accommodation cost of £99/m2/pa. However, it is less expensive than the Council undertaking the building programme itself (were there funds available), at approximately £200/m2/pa - and therefore, on the face of it, represents good value for money. (para 3.1) The additional cost to revenue of placing the services in the LIFT centre would be £737,367pa (para 4.4). This cost can be partly addressed by utilising capital receipts received from the sale of land to the LIFT Co and other measures. This would leave an affordability gap of £645,527pa (para 5.3). There is a case for redesign of the LIFT contract for two specific areas where the contract is disadvantageous to the Council. Adressing these issues would reduce the affordability gap to between £334,580pa and £pa (para 6.1). The remaining affordability gap would have to be met by efficiency savings across other Council services, unless it is possible to obtain additional funding by pursuit of grant, credit approval or PFI. BACKGROUND DOCUMENTS: Various working papers and reports. CONTACT OFFICERS: Chris Hesketh; Steve Durbar Tel. Nos. 793 2668; 793 3755 E-mail: chris.hesketh@salford.gov.uk; steve.durbar@salford.gov.uk ASSESSMENT OF RISK: High. The Council will shortly be expected to sign up to a space requirement before the availability of alternative funding can be determined with certainty. SOURCE OF FUNDING: Revenue budget. PFI is also considered as a possible source of funds. LEGAL ADVICE OBTAINED: Not applicable for this report. When appropriate, the LIFT officer working group is advised by a Law & Administration Division representative. FINANCIAL ADVICE OBTAINED: This report has been part-produced by officers of the Finance Division of Corporate Services. WARD(S) TO WHICH REPORT RELATE(S) All KEY COUNCIL POLICIES Budget Strategy Salford Partnership Community Plan 2001 – 2006 Pledge 3 A Clean and Healthy City Annual Library Plan Charlestown and Lower Kersal New Deal for Communities REPORT DETAIL 1. INTRODUCTION 1.1 There are six Salford sites in the first wave of LIFT. There is the potential in the project plan for Salford City Council to locate certain services in four of the sites. This includes one-stop shops at each of the four sites, libraries in three and a Social and Community Services team at one. This report examines the cost consequences of so locating the various services. 1.2 Owing to developments in joint health and social services, there is a reasonable expectation that further Social Services functions could be located at LIFT sites. The potential cost of this is not covered in this report. 2. CHANGES FROM PREVIOUS VERSIONS 2.1 Compared to versions 1 and 2, it is possible to be a little more confident about some of the assumptions in the body of the report, particularly in relation to the Swinton scheme, where work is the most developed. However, nothing is certain until financial close, and the figures should still be taken as being indicative rather than exact. 2.2 The following are changes from versions 1 and 2 of this report:a) All figures are based on the successful bidder’s (Excellcare’s) submissions. b) It is now anticipated that the ‘B’ submission option will be built into the leaseplus agreement. This option involves GPs sub-letting on a PCT headlease and results in a lower unitary charge. c) It is now anticipated that the final leaseplus agreement will be a contract over 25 years, rather than 20, which results in a lower annual unitary charge but commits the Council for a longer period. d) The analysis of space occupied at the Swinton site has been revised. The Council now has less space directly allocated to it, but more indirect space apportioned to it. The net result is favourable. e) Capital receipts re-estimated on latest valuations. f) Subordinated loan effect recalculated over 25 years. g) Core team costs now included. h) Radio mast loss of income now included. i) Community space and New Deal for Communities introduced. 2.3 PCT and Council officers are currently working on detailed analyses of space to be occupied at the non-Swinton sites along the lines of 2.2d) above, so further refinement of the figures will become available. In the interim, less accurate estimates continue to be used. 3. VALUE FOR MONEY 3.1 Table 1 (taken from Appendix A) compares the accommodation cost per square metre of the following:a) current service provision; b) current service provision, after carrying out backlog maintenance to bring the facilities to a good standard; c) provision of the services in new accommodation, purpose-built by the Council; d) providing the services in LIFT centres. Table 1: Cost per square metre Alternative a) b) c) d) Council existing Council addressing backlog maintenance Council new build Library Office One-stop Shop LIFT lease charge Cost £/m2/pa 99.00 106.50 214.00 180.00 186.00 184.00 3.2 It can be seen that the cost per square metre of LIFT is substantially greater than the existing cost of service provision, but roughly equivalent to the Council undertaking the building programme itself (were there funds available). 3.3 Note however that the LIFT building plans do contain a greater proportion of common or circulation space than would be expected of Council buildings. 4. LIFT COST BUILD-UP 4.1 Lease Plus Charge The LIFT scheme is analogous to a DBFO (design, build, finance, operate) PFI scheme – the intention being to transfer the risk in all those areas from the public to the private sector. Rather than owning and operating the building itself, the Council will lease space. The lease plus is a unitary charge, levied monthly, per square metre of space let and in return the Council will receive modern accommodation maintained to a very high standard. The lease plus cost is calculated at £908,935pa. Comparable revenue and capital charges of the existing services are £328,902pa (see Appendix B). 4.2 Pass-Through Costs The Lease Plus Agreement does not provide for the payment of certain accommodation costs, which will have to be met by the lessees. These include furniture and fittings, IT equipment and infrastructure, and ‘soft’ facilities management (FM) services such as cleaning, refuse disposal, security and caretaking. This report considers the effect of these to be cost-neutral, as they have to be provided in current service provision. However, in practice it is expected that there will be an additional cost associated with an upgrade in services. In addition, the Lease Plus Agreement provides for certain costs to be met by LIFT Co initially, but to be ‘passed-through’ to the tenants in the form of a supplement to the lease charge. These costs include insurance, utilities and rates. The invitation to negotiate specified the levels to be used in the bids, but it is likely that the actual charges will be different. Bidders resubmissions are to include more accurate estimates of the likely pass-through costs. It is estimated that there will be an additional cost over existing services of £264,187pa, partly offset by savings of £82,961pa (Appendix C). 4.3 One-Stop Shops The four sites include one-stop shops with associated waiting/information areas. These are at the same time the front desk of both the LIFT building and other Council services. This represents a significant redesign and enhancement of existing Council services at the interface with the public. It is anticipated that the Council will recharge the PCT for the use of this front desk in proportion to the number of enquiries taken. In the absence of any accurate data, this report estimates that the recharges will total 50% of the cost of the space. This has been reflected in the floor area calculations in Appendix B. It should be recognised that this is a very rough estimate. Furthermore, the movement of staff into the LIFT site could result in space savings at the present location of those staff. For the purpose of this report, these recharges and savings are estimated at £40,000pa (see Appendix D). 4.4 Net Additional Cost to Revenue Table 2 below demonstrates that the additional accommodation cost of providing the services in the LIFT centres is £737,367pa, compared with existing service provision. Table 2: Additional annual revenue costs Item add add less less less LIFT lease pass-through costs central costs current costs, Council library/office provision Current costs, rates, insurance, utilities savings on current space Net additional cost in LIFT Cost £pa 908,935 264,187 16,108 (328,902) (82,961) (40,000) 737,367 Notes see appendix B see appendix C see appendix H see appendix B see appendix C see appendix D 1.1 Community Space Each of the four sites contains community rooms. It will be necessary to discuss with PCT colleagues how this space might be paid for. Appendix J shows that the total cost of this space amounts to £pa. Pending the outcome of these discussions, no part of this cost has been included in the affordability calculations in this report. In addition, the Douglas Green and Lower Kersal sites, which otherwise have no Council space, contain community space. It is expected that this space can be funded by New Deal for Communities monies for ten years. Negotiations are pending to determine if the Council and PCT can underwrite the cost of this space for the period subsequent to the funded ten years. No part of the potential cost of this has been included in the affordability calculations in this report. 5. MEETING THE COST 5.1 Capital Receipts Capital receipts of £2,001,000 are estimated from the sale of Council properties to provide first phase LIFT sites (see Appendix G). Ways of using these receipts to help fund the additional revenue costs are being investigated. The simplest method would be to amortise this receipt over the 25-year life of the project, in the form of a reduced lease charge. This would result in an amount of £80,040pa to set against the lease charge. Of course, the use of capital receipts in this way would preclude their use to support other capital schemes. 5.2 Subordinated Debt The Council has approved in principle the purchase of £1,800 of shares in LIFT. Potentially more significant financially is the opportunity to make a ‘subordinated loan’ to LIFT Co. Current proposals indicate that the loan on first phase schemes could be £148,000 at an interest rate of 14%, which is substantially higher than other investment opportunities, at a relatively insignificant risk. Appendix E demonstrates that making such an investment could generate £11,800pa to offset against the loan charge. However, as such a loan is not an 'approved investment' of the type undertaken for treasury management purposes, £148,000 of capital receipts would have to be set aside to provide credit cover (diverting resources from other capital projects). 5.3 Affordability Gap Table 3 shows that, after applying capital receipts and investment interest to the LIFT scheme, there would still be a revenue shortfall of £645,527pa to be found from other measures. Table 3: The affordability gap Item less less Net additional cost in LIFT Utilisation of capital receipts Assignment of investment interest Affordability Gap Cost £pa 737,367 (80,040) (11,800) 645,527 6. FURTHER MEASURES 6.1 Negotiation of the lease contract There are two areas where the LIFT contract is disadvantageous to the Council in relation to other partners, these being the non-differential lease charges and the treatment of common space (explained Appendix F). The non-differential lease charge contributes £101,892pa to the cost of LIFT, while the excess of floor space contributes £209,055pa. It appears that the PCT may be amenable to making a payment to adjust the lease cost in respect of the former, although they may be less inclined to accommodate the Council over the second issue. The effect on the affordability gap of a successful negotiation in respect of these items is shown in table 4 below. Table 4: Negotiation Points Item less Affordability Gap Differential lease charge at 11.2% Cost £pa 645,527 (101,892) Notes less Common and circulation space at 15% To be met from grant aid or efficiency savings (209,055) 334,580 6.2 Central Funding It may be possible to secure additional resources in the form of grant aid, credit approvals or PFI funding to help make LIFT affordable. At the moment, no such assistance is evident so this would require a political approach. In 2002, ODPM invited applications for PFI funding to support Joint Service Centres, the nature of which appears to fit with schemes of the nature of LIFT. Unfortunately, the timescale did not, as the deadline for applications was 3 January 2003. It is likely that a similar invitation will be extended later in 2003 for 2004/05 PFI schemes, but this may be too late for phase 1 LIFT schemes. Typically, successful application for PFI credits results in special revenue grant intended to cover the capital costs of the scheme – estimated at 70% of the NPV of the total costs. 6.3 Efficiency Savings The LIFT proposals are not cost-saving measures in their own right. The proposals represent an enhancement of library and one-stop provision in the City, at a substantial cost. After other measures to close the affordability gap have been exhausted, the balance can only be met by making efficiency savings in other services as part of the budget exercise. Appendix A: Value for Money Table 1: Comparisons on a Cost per Square Metre Basis Alternative a b c d Council existing Council addressing backlog maintenance Council new build Library Office One-stop Shop LIFT lease charge Cost £/m2/pa 99.00 106.50 214.00 180.00 186.00 184.00 Notes 1) The LIFT cost is the lease charge per square metre of bid B (GP sub-leases, 25year contract). While the cost per sq m is similar to Council build, it should be noted that the LIFT buildings will be less ‘efficient’ than Council buildings in their proportion of circulation space. 2) The Council costs include revenue costs and capital costs. The capital costs have been amortised and include the cost of borrowing. 3) The figures exclude insurance, utilities and rates. See Appendix C. 4) The figures exclude soft FM services, i.e. cleaning, refuse disposal, security & caretaking. 5) The LIFT Lease Plus contract allows the lease charge to be increased each year by RPI. The Council figures would increase each year as running costs increase each year. 6) There are some differences in the Council’s existing costs between this and Appendix B, owing to different sources used. These differences are not material to the overall outcome. Sources Costings of Group Leader (Quantity Surveyors) Working papers of Principal Strategic Property Surveyor LIFT bid submissions Appendix B: Accommodation Cost Projected Additional Revenue Budget Requirements Location Walkden Pendleton Swinton Eccles Total Existing Services library library library offices Existing Area m2 597 860 1,500 650 Current Costs £pa 37,476 68,445 190,992 31,989 3,607 328,902 LIFT LIFT lease area cost m2 £pa 1,104 203,216 1,495 275,077 1,477 271,750 864 158,892 4,940 908,935 Notes 1) For all schemes, the LIFT site includes the additional provision of a one-stop shop and waiting area/information lounge. It is expected (based on Swinton floor area analysis) that these will take up 270m2 of space at each site. However only 50% of this space has been included, as costs will be rechargeable to the PCT in proportion to enquiries handled. There is no data to support this split, so 50% is a very rough estimate. 2) LIFT floor areas include estimates (based on Swinton floor area analysis) of overhead space chargeable to the Council. 3) The LIFT cost is the lease charge of bid B (GP sub-leases, 25-year contract). 4) For the Social Services offices in the Eccles scheme, it is assumed that space reduction down to 8m2 per person will be achieved. 5) The figures exclude insurance, utilities and rates. See Appendix C. 6) The figures exclude soft FM services, i.e. cleaning, refuse disposal, security & caretaking. 7) The LIFT cost figures will be increased each year by RPI. 8) There are some differences in the Council’s existing costs between this and Appendix A, owing to different sources used. These differences are not material to the overall outcome. Sources Working papers of Principal Strategic Property Surveyor SAP GL LIFT bid submissions Appendix C: Pass-Through Costs The figures in Appendixes A and B exclude soft FM services, i.e. cleaning, refuse disposal, security & caretaking. These are assumed to be cost-neutral between Council and LIFT provision. The figures in Appendixes A and B exclude insurance, utilities and rates. These are ‘pass-through’ costs, which LIFTCo will settle, then add on to the Unitary Charge in order to obtain reimbursement from the tenants. Within the LIFT assessment process these were given estimated costs shown as ‘LIFT estimate’ in the table below. However, it is considered that the figure estimated by Council officers and shown as ‘LIFT revised’ is likely to more accurately reflect the actual charge. The table also shows estimated ‘current’ costs. Table C Current £/m2/pa LIFT estimate £/ /pa 5.00 12.00 12.00 29.00 LIFT revised £/m2/pa 7.00 12.00 28.00 47.00 Insurance Utilities Rates Total £/m2/pa £/m2/pa £/m2/pa £/m2/pa 5.00 6.00 12.00 23.00 Floor area* m2 3,607 5,621 Total cost £pa 82,961 264,187 *Appendix B Appendix D: One-Stop Shops a) (Re)charges This section of the report has now been removed. Recharges of one-stop shop space are dealt with in note 1 to Appendix B. b) Savings on existing use The one-stop shops do represent a service enhancement and growth item. However, it is assumed that the relocation of staff from existing locations will result in some accommodation savings at those locations. A notional saving of £40,000pa, in line with earlier versions of this report, is used herein. Appendix E: Calculation of Additional Interest on LIFT Subordinated Loan Loan Interest Base Int RPI Interest Receivable £ 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Total Average 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 20,720 £148,000 14.0% 4.0% 2.5% Less Interest at Normal Rate £ 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 5,920 Additional Income NPV £ £ 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,800 14,439 14,087 13,743 13,408 13,081 12,762 12,451 12,147 11,851 11,562 11,280 11,005 10,736 10,474 10,219 9,970 9,726 9,489 9,258 9,032 8,812 8,597 8,387 8,183 279,498 11,180 £11,180 represents the average extra annual income (at current costs) that would be generated by placing £148,000 investment in LIFT Co at 14% for 25 years, as compared with an investment elsewhere at 4%. Appendix F: Non-differential lease charge and common space a) Differential Lease Charges The cost to LIFT Co of constructing and maintaining certain complex spaces (such as specialist health theatres) is greater than simpler spaces (such as offices). Equitably, this difference would be passed on to lessees by differential charges depending on the type of space let. However, instructions from Partnerships for Health for LIFT projects nationally are that the unitary charge is to be applied equally to all spaces within the buildings. Work done by Salford PCT suggests that the effect of this will be that Salford City Council pays more than would otherwise be the rate for its space and effectively subsidises other lessees by 11.2% of its lease cost. The cost of this is £101,892pa, incorporated into the lease charge. b) Common and Circulation Areas (Overhead Space) Because of the nature of their respective buildings, the PCT normally expect the proportion of overhead space (toilets, corridors etc) in new build to be about 30% of gross internal floor area, while Salford City Council would expect only about 15%. Current findings suggest that the sample-bid LIFT designs incorporate a proportion of 38%. As the cost associated with this space is absorbed into the unitary charge, this means that the Council would effectively be paying for a space provision it would not have had to make had the building been a Council-purpose-only design. The cost of an extra 23% of space is £209,055pa, incorporated into the lease charge. It is not now expected that it is viable for the PCT to consider rebating the Council for this space. Appendix G: Estimated Capital Receipts Site Swinton Eccles Walkden Pendlebury Total Estimated Receipt Comment £ 1,100,000 268,000 198,000 In dispute. 435,000 Own estimates of library plus police building. Car park excluded because of potential issues 2,001,000 Over 25 years, equivalent to £80,040pa. Note Valuation negotiations are still proceeding. At sites where the anticipated value of the total receipt is least certain, a figure has been included which is lower than the Council ultimately expects to receive. Appendix H: Central Costs Core Team A MAST LIFT Central Project Team is to be created to support the LIFT Strategic Partnering Board and local partners generally. The budget for 2003/04 is £345,100, to be funded by the partners. The accepted option for apportioning the budget results in a cost of £6,858 to Salford City Council in 2003/04. Future commitment is certain but costs are as yet unspecified. For the purpose of this report, future costs are anticipated to remain the same ie £6,858pa. Telephone Masts The Council has a contract worth £pa to allow telephone masts on the current Lancastrian Hall site. Originally, it had been assumed that the masts would be transferred to another Council building so that the Council would retain the income. It is now anticipated that the masts will be replaced on the new LIFT building and LIFTCo will gain the benefit of the income of £9,250pa. (There is no Appendix I) (There is no Appendix I) Appendix J: Community Space Projected Costs Location LIFT area base m2 LIFT area incl overhead Walkden Pendleton Swinton Eccles 200 160 160 160 Total 680 LIFT lease cost £pa Notes 1. Overhead space is included in the proportion of that applicable at the Swinton site. 2. Space at Douglas Green and Lower Kersal is not included. It is anticipated that there may be a cost to the Council (and PCT) after the ten years’ of New Deal funding expires.