INTRODUCTION

This report sets out the actual Service achievements against targets for 1999/2000 and provides a summary of the Service Plans for 2000/1.

It covers the full range of I.T. Services, including Development, Operation and Support.

To assist Elected Members, a description of current I.T. Services is provided in the next

Section.

2.

CURRENT I.T. SERVICES

This section summarises current IT Service offerings for information.

Service

Consultancy

Account Support

Software Development

Project Management

Implementation

Training

Service Desk

Research and Develop.

Computer Services

Networking

Small Systems

Role

Advice and planning of IS/IT Strategies, including BPR

Projects

General IT Support for Customers at senior level

Bespoke software and package procurement, tailoring and support

Project planning and control, quality and risk management

Site surveys, specifications, procurement, testing and installation

Training in use and application of products and facilities

First line support for fault rectification, advice and consumables

Research and evaluation of emerging technologies incl.

Prototyping

Management, operation, support and security of computing platforms

Management, operation, support, security of communications networks

Specification, implementation and support of PCs and associated products

CDCS0B058MWRH

Page 3 of 10

3.

ACHIEVEMENTS IN 1999/2000

1999 was the year, which saw the conclusion of the major Year 2000 Compliance Programme for Council I.T. Systems and the launch of one of the most significant Service Strategy

Developments in recent years, in the form of the Information Society Strategy

.

Service Developments

Item

1.

2.

4.

5

3.

6

7

8

9

10

Description

Successful conclusion of the correction and testing of Council Applications and equipment to ensure Year 2000 Compliance, resulting in very minor incidents only.

Active involvement in the development of the Information Society Strategy in which overall Strategy Report approved which provides the foundation for a range of initiatives involving Call Centre, One Stop Shops and Home-working

Models, built on BPR work, new HR Strategies and improved IS/IT Systems

Piloted the Home-working scheme for two software engineers to assess costs and benefits, which resulted in a very positive outcome where both employer and employee confirmed a strong case for these working arrangements. Issue to be tackled as part of Council Strategy in 2000

Concluded EC funded evaluation of Software CASE Tools (CAPELLA Project) and

Received an 83% Evaluation rating from EC on final report on Project Outcomes

Built upon relationships with Members through rollout of Office Automation facilities, SOLAR System and IT Training and Support

Worked in Partnership with a range of Private Sector Providers to develop

Services and Infrastructure including: SOCITM, Oracle, Deloitte and Touche,

Price Waterhouse Coopers, Cable and Wireless, Cisco

Substantially upgraded Network infrastructure, involving major nodes and developed proposals for circuit upgrades to improve capacity, speed, reliability and resilience to cope with future growth in flow of information throughout City

Implemented Enterprise Wide Management System to improve planning, management, support and security of Council Data

Developed a closer working relationship with Education Service involving transfer of ITMS Team to IT Services, contributed to Schools IT Forum and developed a major ICT Strategy for Directorate

Consolidated Environmental Health Directorate’s Network into Corporate

Network

11

12

13

14

15

Updated and re-issued Security and Privacy Policy and resolved major virus threats

Investigated business case for Outsourcing of PC maintenance and Mainframe

Operations

Moved from 3 shift to 1 shift system to improve cost effectiveness of service

Introduced recruitment and retention scheme with very successful results

Continued staff development and training investment resulting in successful achievement of technical accreditations including Microsoft, Cisco, Oracle products and ISEB.

All seven IT Trainers gained ECDL Qualification and Training Service achieved

Test Centre Status by British Computer Society

CDCS0B058MWRH

Page 4 of 10

9

8

7

5

6

4

3

2

1

Item

12

10

11

13

Information Society Developments

Description

Pilot call centre set up July 1999 (Environmental Services – poor performing service in terms of telephone responsiveness), in conjunction with Vertex Data systems. Achieved success in understanding true call volumes. Response rates increased from 17% to between 70-90% in

30 seconds. Potential disruption to ‘back office’ did not materialise as originally feared.

BPR team set up September 1999 in order to develop new business processes, models and system requirements. Expertise and input from Warwick Business School and Manchester

University to develop methodology and operating framework. Achieved considerable success and attracted interest from commercial organisations. Chair set up at Salford University which enables access to research and assistance from students to undertake BPR fieldwork

January 2000 - Information Society staff appointed to develop implementation requirements

Call Centre and One Stop business model, specification, development and outline implementation plan for 2000/01 agreed by Cabinet in February / March 2000

Accommodation requirements for corporate call centre specified February 2000.

Accommodation made available September 2000. Installation work began.

In house delivery of call centre began May 2000. ACD evaluated and implemented July /

August 2000. Performance maintained at 70% despite busiest period of year. Call centre staff fully endorse call centre methodologies.

Work to develop requirements for Revenues & Benefits call handling began December 1999, with analysis of processes and IT requirements undertaken by BPR team and assisted by

Salford / Manchester Universities and Warwick business school.

Organisational structure and grading requirements for call centre began June 2000.

Consultation process completed August 2000 with no adverse comments. 30 revenues & benefits staff expressed interest in joining call centre, with only nine post being available in

1 st tranche of development

Proposals to set up Customer Service Division enacted September 2000 to ensure development of clear focus on outward customer service delivery.

Tools and technologies to assist delivery of call centre and future Customer Service Centres being evaluated, including CRM

Training programme for call centre developed August 2000, (for delivery September).

Evaluation of development programme including NVQ, and Certificate / Diploma in Call

Centre Management underway.

Integration of Revenues & Benefits into corporate call centre on target for go live October

2000. Recruitment and selection process underway September 2000

Initial BPR began in Housing Services Directorate (Repairs) July 2000

CDCS0B058MWRH

Page 5 of 10

15

16

14

17

18

19

High-level BPR analysis to develop corporate priorities and requirements for future rollout to all services. Report due October / November 2000

Web content manager post created September 2000 (in process of appointment)

Pilot One Stop Shop launched in Little Hulton launched in December 1999.

Specification for future Customer Service Centres developed February 1999. Site analysis and impact of other developments began July 1999, with assessment of potential locations.

Successful bid for EC funds to develop secure e-commerce facilities. Project begins

October 2000, and lasts for 18 months.

Contributed to National CITU Working Groups throughout Year to develop models for Call

Centre and Customer Service Centre operations

System Developments and R & D Projects

Item

6

7

4

5

2

3

1

11

12

8

9

10

Description

Assistance in procurement of integrated package system for Housing Service. Severe contract performance difficulties with supplier led to contract termination. Procurement process restarted in 2000.

Assistance in procurement and implementation of integrated corporate financial system (SAP)

Assistance in procurement of package system to replace SOSCIS (OLM Care first)

Implementation

of Microsoft Outlook facilities where installations have covered 60 Members and 1245 Officers, and 45 Members and 1508 officers trained

Development of City Council public and private Internet/Intranet Web Site

Initial pilot work on Back Office/ Front Office Systems to enable planned Call Centre

Operation

Development of System to manage Council reports and minutes (SOLAR)

Introduced CD / COLD output facilities thereby considerably reducing paper consumption

Migrated services from Oracle Version 6 to 7 thereby providing improved facilities to users

Implemented upgraded NUMA Processor platform for Council Tax

Upgraded Operating System for Cash Receipting thereby reducing support costs

Installed additional 7 Virtual Private Networks (VPN) enabling new sites to enter Voice

Communications Network thereby reducing rental and call costs

CDCS0B058MWRH

Page 6 of 10

Configuration Developments

Item

1

2

3

4

Customer Training

Description

Additional PC’s installed

Additional Peripherals installed (Printers, Scanners etc)

Additional servers Installed

Additional Devices Networked

Units

650

400

20

140

8.

9

10

11

12

13

4.

5.

6.

7.

Item

1.

2.

3.

There was a very significant increase in the number of delegates trained during 1999/2000.

The target set was 1650 delegate days, which was substantially exceeded with a final total of

2029 being delivered:

Description

Word

Excel

Intro to Computers

Intro to Windows

Access Database/Data-Ease Database

Intro to DTP

Intro to Internet

Key Board Skills

Microsoft Office Overview

Microsoft Outlook

Power-point Presentations

Word-Perfect

NVQ Training

Customer Satisfaction Results

10

33

458

88

38

21

(No. Delegates Days)

305

204

538

120

173

6

35

Customer Satisfaction Results for 1999/2000 were:

Service

Software Development

IT Service Desk

Very Satisfied

31

55

Overall response (%)

Satisfied Quite Satisfied

45

35

16

8

Service Performance Targets

Dissatisfied

8

2

Respondents

36

54

Actual performance against plan for day- to- day service targets was:

Item

1

2

3

4

Aspect

Systems Development

Operations

Technical Support

Infrastructure

Target

70% of deliverables on time

98% availability of On –Line Services

95% of faults responded to within published target times

Not exceed 2% down time for infrastructure for single location

Actual

72%

99.2%

90%

0.5%

CDCS0B058MWRH

Page 7 of 10

4.

PLANS FOR 2000/2001

It is intended to build on the good work done in 1999, in developing Services and infrastructure. Some of the more notable plans for 2000/1 include

:

Strategic Developments and Service Improvements

6.

7

8

1.

2.

3.

4.

5.

Item Description

Improve Project Management through introduction of PRINCE 2 Standard and

MS Project 98 Tool

Improve Customer Support through the introduction of a Service Management

System operated by the I.T. Service Desk

Develop an I.T. Drop-In/Learning Resource Centre including new training courses and media, to improve I.T. Training Facilities

Develop the European Computer Driving License Scheme in order to improve I.T. competency within the City Council

Carry out extensive Business Process Re Engineering (BPR) Projects to facilitate the introduction of the City Council’s Customer Contact Strategy

Develop home-working initiative for Development Staff

Update IT Skills Plan and develop database to better match demand/supply

Restructure of Data Communications, Voice Communications and small Systems

Units to create Network Service Group

Implement ICT Strategy for Education and Leisure Service 9

Item

6

4

5

2

3

1

7

8

9

Information Society

Description

Consolidate corporate call centre in Elmstead and begin process of developing generic working to manage peaks and troughs in demand across the two services

Conduct security and risk assessment and assess countermeasures required

Develop tools, technologies and referral protocols for front and back office, including on-line information requirements

Finalise specification for CRM and determine implementation strategy

Finalise high level BPR analysis and report on implementation proposals and priorities for rollout to other services for 2000/01/02

Develop key PIs (and SLAs)

Agree staff development plans and strategies to ensure skills upgrade and retention

Analyse site requirements for future Customer Service Centres

Develop scope for E-Commerce strategy

Consult and agree implementation plan/ rollout priorities for call centre and Customer

CDCS0B058MWRH

Page 8 of 10

11

12

10

13

14

Service Centre

Begin work to bid for Charter Mark in call centre

Develop protocols for Tele-working to release accommodation at Elmstead

Assess business case for extended opening hours

Develop benchmarks for customer feedback / satisfaction

Consult / develop E-Commerce tools with EC partners

Major I.T. Systems and Infrastructure Developments

Customer

Housing Services

Chief Executive

Social Services

Finance Service

Education and Leisure

Corporate

Project

HS2000 Replacement Procurement

HMIS Archiving

Crime and Disorder GIS

SOSCIS Replacement

Grants

SRB Package Implementation

Council Tax Migration/development

NNDR Feasibility

Cash Receipting Feasibility

Document Management (Major Upgrade to ICLipse System)

Leisure Management System

Automated Libraries

Document Management

SEN Support Information System

Implement Peoples Network within Libraries Service

Council Members System (SOLAR)

SAP Implementation

Further develop Enterprise Management System to manage PCs and servers

Upgrade circuits from 2mb to 155 mb to improve response times of network

Develop Printing Strategy to Improve Services

Consolidate Batch Scheduling across all hardware platforms

CDCS0B058MWRH

Page 9 of 10

Major R and D Projects

Project

Office Automation –continued roll out and expansion of facilities

Internet /Intranet Development Work

E. Commerce

Video Conferencing

Portal Development/Back Office Development/Customer Tracking

Microsoft 2000 product set

Java Technologies

Digital TV Facilities

SQL Server 7 Platform

Digitisation of Images

Palm Tops/Mobile Devices

Thin Client

Instigate voice over IP for Data and Voice Communication Integration

Development of GIS systems throughout City Council

Major BPR Projects

Project

Council Tax/Benefits (Call Centre)

Environmental health (Call Centre)

Housing Repairs

On-Line Procurement

Customer Contact Strategy (Call Centre / Customer Service Centres

Service Performance Targets

The following Service Performance Targets have been set for this year:

5

6

4

1

2

3

Item Service

All Services

Development

Operations

Technical Support

Technical Support

All Services

Target

80 % Customer Satisfaction Rating

70 % Adherence to Project Delivery and Budget Tolerances

98 % Availability of On-line Services throughout the year

95 % of reported faults responded to within published standards

Not to exceed 2 % downtime for infrastructure and hardware platforms for a single location throughout year

75 % achievement of published Service Improvement Plans

CDCS0B058MWRH