431-SPEC-000112 Revision Effective Date: To be added upon Release Expiration Date: To be added upon Release DRAFT Robotic Lunar Exploration Program Lunar Reconnaissance Orbiter Project Technical Resource Allocations Specification Date Document Generated (06/22/2005) Goddard Space Flight Center Greenbelt, Maryland National Aeronautics and Space Administration CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) CM FOREWORD This document is a Lunar Reconnaissance Orbiter (LRO) Project Configuration Management (CM)-controlled document. Changes to this document require prior approval of the applicable Configuration Control Board (CCB) Chairperson or designee. Proposed changes shall be submitted to the LRO CM Office (CMO), along with supportive material justifying the proposed change. Changes to this document will be made by complete revision. Questions or comments concerning this document should be addressed to: LRO Configuration Management Office Mail Stop 431 Goddard Space Flight Center Greenbelt, Maryland 20771 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) Signature Page Prepared by: Michael Pryzby Spacecraft Systems Engineer Swales / 431 _________ Date Reviewed by: Martin Houghton Mission Systems Engineer GSFC / 599 _________ Date Approved by: Craig Tooley LRO Project Manager GSFC / 431 _________ Date CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) LUNAR RECONNAISSANCE ORBITER PROJECT DOCUMENT CHANGE RECORD REV LEVEL DESCRIPTION OF CHANGE Sheet: 1 of 1 APPROVED BY CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. DATE APPROVED Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) List of TBDs/TBRs Item No. Location Summary CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Ind./Org. Due Date Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) TABLE OF CONTENTS Page 1.0 Introduction .................................................................................................................... 1-1 1.1 Purpose................................................................................................................. 1-1 1.2 Applicable Documents ......................................................................................... 1-1 2.0 Technical Resource and Budget Tracking ................................................................... 2-1 2.1 Definitions............................................................................................................ 2-1 2.1.1 Current Best Estimate .............................................................................. 2-1 2.1.2 Contingency ............................................................................................. 2-1 2.1.3 Allocation ................................................................................................. 2-1 2.1.4 System Margin ......................................................................................... 2-1 2.1.5 Specification ............................................................................................ 2-2 2.2 Margin Progression .............................................................................................. 2-2 2.3 Allocation Approach ............................................................................................ 2-3 2.3.1 Overall Approach ..................................................................................... 2-3 2.3.2 Initial Allocations..................................................................................... 2-4 2.3.3 Reallocations ............................................................................................ 2-6 3.0 Mass Allocation .............................................................................................................. 3-1 4.0 Power allocation ............................................................................................................. 4-3 4.1 Un-switched power allocations ............................................................................ 4-3 4.2 heater power allocations ...................................................................................... 4-4 4.3 switched power allocations .................................................................................. 4-5 5.0 Delta V / Fuel Mass Allocation ..................................................................................... 5-6 6.0 Data Capture Budget ..................................................................................................... 6-7 Appendix A. Abbreviations and Acronyms ................................................................................1 ii CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) LIST OF FIGURES Figure Page Figure 2-1 – Resource Budget Nomenclature .............................................................................. 2-1 Figure 2-2 – Example from MEL Allocation Spreadsheet .......................................................... 2-5 LIST OF TABLES Table Page Table 2-1 - LRO Resource Margin Progression .......................................................................... 2-2 Table 2-2 - LRO Software Margin Progression ........................................................................... 2-3 Table 2-3 - LRO Resource Design Maturity Factors ................................................................... 2-4 Table 3-1 - Spacecraft Mass Allocation - Wet............................................................................. 3-1 Table 3-2 - Spacecraft Wet Mass Allocation - Consumables ...................................................... 3-1 Table 3-3- Spacecraft Dry Mass Allocation ................................................................................ 3-2 Table 4-1- Un-Switched Power Allocations ................................................................................ 4-3 Table 4-2 – Instrument Heater Power Allocations ...................................................................... 4-4 Table 4-3 - Switched Power Allocations ..................................................................................... 4-5 Table 5-1 – Delta V / Fuel Mass Allocation ................................................................................ 5-6 iii CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 1.0 INTRODUCTION 1.1 PURPOSE 431-SPEC-000112 Revision Release Status ( DRAFT) This document will be used to set and trace technical resources for the Lunar Reconnaissance Orbiter. This document will detail the process in which the technical resources are to be managed and controlled. It is expected this document will be a living document over the course of the mission. The document will allocate mass and power. 1.2 APPLICABLE DOCUMENTS The following documents (or latest revisions available) are applicable to the development and execution of this plan: 430-PLAN-000008, 431-PLAN-000005, 430-PG-1410.2.1, GSFC-STD-1000, LRO Program Plan, LRO Systems Engineering Management Plan LRO Configuration Management Plan GSFC Rules for the Design, Development, Verification, and Operation of Flight Systems 431-SPEC-0000091, LRO General Thermal Systems Specification Document 1-1 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) 2.0 TECHNICAL RESOURCE AND BUDGET TRACKING 2.1 DEFINITIONS Figure 2-1 shows graphically the definitions that will be used in this document. Specification Limit System Margin Project Control Spec Contingency More Current Best Estimate (CBE) Allocation Prediction/measurement (bottoms up estimate) Subsystem / Instrument Control Figure 2-1 – Resource Budget Nomenclature 2.1.1 Current Best Estimate CBE is the current prediction or measurement of the resource. If it is a prediction, then it is a bottoms-up estimate. 2.1.2 Contingency Contingency is the reserve amount of resource under the control of the subsystem and is kept as part of the allocation. 2.1.3 Allocation Allocation is the amount of resource assigned to a subsystem that the subsystem is allowed to manage. It equals the CBE plus contingency. 2.1.4 System Margin Margin the resource reserve managed at the system level. It is the difference between the overall resource specification and the assigned allocations. Margin shall be calculated as follows: Margin (%) = (Available resource–Estimated Value of Resource)/Estimated Resource X 100 2-1 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) 2.1.5 Specification Specification is the maximum amount of resources available. 2.2 MARGIN PROGRESSION The Systems Engineering team is responsible to identify the mission resources to be allocated and tracked at the project level, as well as to define acceptable resource margins and set up a margin management philosophy based on the various stages of the mission lifecycle phases. Table 2-1 shows the LRO System Engineering resource allocation margin progression as the project development lifecycle proceeds through the various phases of mission development. The resource margins required decrease as the system development progresses to further levels of definition and maturity. The resource margins are taken from GSFC-STD-1000. Resource margin requirements from GSFC-STD-1000 will be calculated by adding the margin plus contingency for any given system or subsystem. Total Margin Progression Pre Phase A Phase A Phase B Phase C Phase D Mass 30% 25% 20% 15% 0 Power (wrt EOL capacity) 30% 25% 15% 15% 10%* Propellant 3 Margin detailed w/ Prop Budget Telemetry and Commands 25% 20% 15% 10% 0 RF Link 3dB 3dB 3dB 3dB 3dB *At launch there shall be 10% predicted power margin for mission critical, cruise and safing operating modes as well as to accommodate in –flight operational uncertainties. Table 2-1 - LRO Resource Margin Progression Table 2-2 shows the LRO System Engineering software margin approach. Mission Phase FSW SRR FSW PDR FSW CDR Ship/Flight Est. Anal. Anal./ Measured Measured Average CPU 50% 50% 40% 30% CPU Deadlines 50% 50% 40% 30% PROM 50% 30% 20% 0 EEPROM 50% 50% 40% 30% RAM 50% 50% 40% 30% 1553 Bus 30% 25% 15% 10% SpaceWire (1355) TBD TBD TBD TBD UART/ Serial I/F 50% 50% 40% 30% Method 2-2 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) Table 2-2 - LRO Software Margin Progression Per the Systems Engineering Management Plan, 431-PLAN-000005, the technical resources should be in draft form by SRR. Therefore, the initial allocations set in this document will be with the margins from Phase A in Table 2-1. At PDR, the margin progression will be at the levels for Phase B. At CDR, the margin progression will be the levels for Phase C. At launch, the margins will be at the levels specified for Phase D. 2.3 ALLOCATION APPROACH 2.3.1 Overall Approach Allocations, per the definition in Section 2.1, consist of the Current Best Estimate (CBE) and the contingency. CBEs are calculated by each subsystem and presented, with any technical detail to the Spacecraft Systems Lead. Depending upon the amount of design maturity in the subsystem, a Design Maturity is designated to the subsystem or to the components within the subsystem. Depending upon the level of Design Maturity, a percent contingency is assigned to the resource and a resource value is calculated. At the Spacecraft Systems Lead’s discretion, some or all of that contingency resource value is allocated to the subsystem. The remaining contingency resource value is maintained as System Margin by the Spacecraft Systems Lead. The sum of the System Margin plus the Subsystem Contingency is used to calculate the overall margin used to meet the progression requirements from Section 2.2. 2.3.1.1 Current Best Estimate Current Best Estimates (CBEs) are estimated or calculated by the subsystems. Estimates are to be provided to the Spacecraft Systems Lead with any assumptions that were made. CBEs range from guesses based on engineering judgment to tested values from flight units. As the design matures, both the fidelity and accuracy of the estimate will increase. The assumptions and calculations behind the CBEs are critical to an effective management of resources. The assumptions and calculations will be documented in the Master Equipment List (MEL). The MEL is a tracking tool used by the Spacecraft Systems Lead. The MEL will track CBEs against allocations from concept to launch. 2.3.1.2 Design Maturity As the maturity of the system architecture increases, the precision of the resource estimates will improve with the method of estimating the resources required. Table 2-3 illustrates the LRO margin factors that will be applied to the system elements as they progress through the various levels of development maturity. These factors will be multiplied against their appropriate estimates to determine a contingency resource value. The Spacecraft Systems Lead will allocate that resource value between the subsystem contingency and system margin. If the CBE is 2-3 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) deemed to be conservative, the Spacecraft Systems Lead may keep a portion of the contingency resource value at the system level, reducing the subsystem allocation. Mass Design Maturity Contingency Allocation % Calculations from sketches/schematics 25 Calculations from preliminary layout 20 Calculations from detailed layout/Major modified unit 15 Calculation from pre-released drawing/Moderate modified unit 10 Calculation from released drawing/Minimum modified unit Actual weight for similar flight hardware/Engineering model Actual weight for flight hardware 5 Power Design Maturity Contingency Allocation % New units containing new technologies or Thermal Control System (TCS) components New units based on existing technology Major modifications to existing units Minor modifications to existing units/New units with engineering models Off the shelf, flight qualified units 20-25 15-20 10-15 5-10 3-5 3 0.5 Table 2-3 - LRO Resource Design Maturity Factors 2.3.1.3 System Margin System Margin is maintained by the Project or Spacecraft Systems Lead. At first glance, the margin would be any resources remaining after the CBE as calculated and the assigned contingency allocation were subtracted from the resource specification. At the system level, specifications will be generated to determine the amount of available resources exist. For mass, it would be the maximum throw weight of the launch vehicle. The System Margin will be distributed, as appropriate, over the design phase of the mission. Distribution of the margin to Subsystem Allocations will require a CCR to this document. The CCR will require formal documentation as to the reason the allocations are to be changed. Most often, trade studies will be requested to show adequate efforts were made to maintain the allocation. Some changes in allocation will be accepted as a trade against cost or schedule savings. 2.3.1.4 Overall Margin System Margin will be combined with the subsystem contingency to determine the overall resource margin. The overall resource margin will be used to show adequate design margin as required by GSFC-STD-1000. 2.3.2 Initial Allocations 2.3.2.1 Spacecraft Initial specifications for the space segment were derived for the following resources. 2-4 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) 2.3.2.1.1 Mass The mission traded different designs regarding a transfer to lunar orbit. The project examined various direct lunar insertion trajectories and phasing loops. The project also traded monopropellant verses bi-propellant verses hybrid propellant systems. Given a Level 1 requirement of using an intermediate class launch vehicle, the best solution was for a mono-propellant system on a direct lunar insertion trajectory. Further analysis has yielded a maximum throw mass for the launch vehicle of 1480 kgs. This mass has set the initial mass specification. 2.3.2.2 Subsystems At approximately the time of the Instrument Accommodations Review, subsystem allocations were set against the appropriate resource specification. The timing was chosen to freeze allocations and show adequate Overall Margin at the start of subsystem and instrument PDRs. The MEL contains CBE for the subsystem and an assigned Design Maturity rating. Spacecraft Systems appropriated the resource contingency value, as appropriate, to maintain adequate Overall Margin per GSFC-STD-1000. The contingency value assigned to each subsystem is also shown in the MEL. LRO MASTER CONCEPT E EQUIPMENT LIST CURRENT BEST ESTIMATE Subsystem (kg) Mechanical 148.00 Design Maturity Rating 7 % 25 Assigned Margin Contingency Allocation (Allocation - CBE) SubSystem SubSystem Subsystem Mass (kg) 37.00 Mass (kg) 185.00 Mass (kg) 37.00 Figure 2-2 – Example from MEL Allocation Spreadsheet 2.3.2.3 Instruments Initial instrument allocations were set from the instrument proposals. Most proposals included contingency. For the initial allocations, the CBE and contingency were accepted as proposed. For those instruments which proposed less than 15% contingency, the instrument contingency was increased to 15% and the allocation was set. The Spacecraft Systems felt it was important to track any variations to the proposed resources. It was understood that the spacecraft would imposed design changes on the instruments. It is in both parties interests to track resource growth against the true cause of it. For spacecraft induced changes like requiring different electrical interfaces, it is important to trade the impacts with regard to all resources (cost, mass, power). For allocation growth due to self-imposed design changes, it is important for the Spacecraft to have insight into major changes and the trades that 2-5 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) decided those changes. Design heritage and maturity was a criteria for instrument selection and deviation from the proposed design should be scrutinized. 2.3.3 Reallocations Changes to the allocations will be handled per the LRO CM Plan. The reallocation will be addressed as part of a Configuration Control Board (CCB). To expedite the process, it is required that any subsystem requesting a reallocation provide technical documentation supporting the request. Engineering discipline should be applied to show a good faith effort to remain within the allocation. The documentation can include results from trades of mass against cost and schedule. There should also be detail in the new mass estimate. Engineering rigor should be applied in determining the new resource allocation. 2-6 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 3.0 431-SPEC-000112 Revision Release Status ( DRAFT) MASS ALLOCATION The overall Orbiter mass allocation is traced from the Mission Requirements Document (431REQT-000004, requirement # 1.2.10. The Wet Mass Allocation is derived from the Table 5-1, Delta V Allocation. Section 5.0 derives the Delta V allocation and the requisite fuel to perform those delta V maneuvers. The mass of the fuel was subtracted from the LV capability to determine the maximum allowable dry mass. Those allocations are set below. Subsystem Allocation SubSystem Mass (kg) Components L/V Wet Mass Capability 1480.00 Derived Wet Mass Allocation Max Dry Mass Allocation 715.30 764.70 Comments MRD Req’t: 1.2.10 Propellant Budget derived from Delta V budget Remaining mass Table 3-1 - Spacecraft Mass Allocation - Wet The wet mass consumable allocation is derived from the Table 5-1 Delta V Allocation budget. Subsystem Components Consumables Allocation SubSystem Mass (kg) 715.30 Propellant Pressurant 713.0 2.3 Comments Derived from Delta V budget - includes 3 Table 3-2 - Spacecraft Wet Mass Allocation - Consumables The spacecraft dry mass allocation is derived from the launch vehicle “throw mass” less the Wet Mass Allocation from Table 3-2. Any difference between the Max Dry Mass Allocation from 3-1 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) Table 3-1 and the Total Dry Mass from Table 3-3 will be kept as System Margin. The Orbiter Systems team will keep that mass and will distribute it later as justified. Subsystem Components Total Dry Mass Spin balance Weight S/C Bus Subtotal Mechanical Mechanisms Thermal Power ACS PDE Propulsion (Dry Mass) C&DH S Comm Ka Comm Electrical Instruments Subtotal CRaTER Diviner LAMP LEND LOLA LROC Mini RF Allocation SubSystem Mass (kg) 710.3 25.0 595.5 155.1 52.8 32.4 76.2 63.4 16.8 105.8 19.5 12.6 18.5 40.0 89.9 6.4 11.9 5.3 23.2 15.3 19.0 12.6 Comments Concept J Place holder Table 3-3- Spacecraft Dry Mass Allocation 3-2 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 4.0 431-SPEC-000112 Revision Release Status ( DRAFT) POWER ALLOCATION Power consumption is highly mode dependent and can vary with orbital location, bus voltage, and other spacecraft component configurations. Power allocations are to be calculated against a nominal, fully operational orbit average scenario unless otherwise noted. In assessing energy balance against the entire mission, the nominal orbits with Ka and S-Band contacts during nominal measurement operations was the driving phase with respect to power. Spacecraft component power allocations were set against this mission phase, except for heater power. Operational heater power allocations for each instrument/component are based on Beta=90° cold case orbit average predictions plus margin. Survival heater power allocations for each instrument/component are based on Safe-hold orbit average predictions plus margin. 4.1 UN-SWITCHED POWER ALLOCATIONS Subsystem Comm C&DH C&DH ACS ACS ACS ACS Thermal Thermal Power Components TT&C XPDR Stack (Rec) COMM Card C&DH Backplane Reaction Wheels Reaction Wheels Reaction Wheels Reaction Wheels Essential S/C Survival HTRs Prime Essential S/C Survival HTRs Redundant PSE Switched Services S / US USA1 USB1 USC1 USA2 USA3 USB2 USC2 USB3 USC3 DIRECT Table 4-1- Un-Switched Power Allocations 4-3 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Allocation Orbit Avg (W) 11.0 17.6 43.5 7.7 7.7 7.7 7.7 37.5 37.5 44.0 Technical Resource Allocation 4.2 431-SPEC-000112 Revision Release Status ( DRAFT) HEATER POWER ALLOCATIONS Heater powers are sized per the General Thermal Systems Specification Document, 431-SPEC000091. Instrument CRaTER DRLE LAMP LEND LOLA LROC Mini-RF Switched Services S / US C10 C4 C13 B12 C10 C4 C10 C4 C10 C4 C10 C4 TBD TBD Components Operational Heaters Survival Heater Operational Heaters Survival Heater Operational Heaters Survival Heater Operational Heaters Survival Heater Operational Heaters Survival Heater Operational Heaters Survival Heater Operational Heaters Survival Heater Allocation Orbit Avg =90° =0° 2.0* 2.0* 2.2 45.6 14.0 31.0 9.1 5.5 12.6 2.0* 2.0* 2.0* 42.0 15.6 45.0 12.8 8.0 43.7 TBD TBD TBD * - Current analysis shows no heater power is necessary Table 4-2 – Instrument Heater Power Allocations 4-4 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 4.3 431-SPEC-000112 Revision Release Status ( DRAFT) SWITCHED POWER ALLOCATIONS Subsystem Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument Instrument/thermal Instrument/thermal C&DH S Comm Ka Comm ACS ACS ACS Prop PDE Prop PDE Prop PDE Prop PDE Prop Prop Mechanisms PDE Mechanisms PDE Thermal Thermal Thermal Thermal Components CRaTER Diviner Diviner Operational Heater (HOLD) Diviner Survival Heater (HOLD) LAMP PRIME LAMP REDUNDANT LEND LOLA LROC LROC Optics Decontamination Mini RF System Instrument Operational Heaters Instrument Survival Heater SSR TT&C XPDR Stack (xmit) Ka Transmitter complement Inertial Measurement Unit Star Trackers Star Trackers PDE Pressure Transducers Prop Valve Actuator Prop Valve CAT BED Prop Heaters Prime Prop Heaters Redundant S/A & HGA Control Electronics S/A & HGA Release & Deploy Gimbal Heaters Prime Gimbal Heaters Redundant Spacecraft Operational Heaters Deployable heaters Switched Services S / US Allocation Orbit Avg (W) B8 C12 C13 B12 C14 B13 C8 B14 C15 A10 B10 C10 C4 A7 A12 C5 A13 B11 A11 B6 A15 A6 B4 B5 A5 B7 C7 C16 B15 C6 B16 5.9 19.6 0 0 4.86 4.86 13.0 39.4 27.6 98.0 7.5 37.5 37.5 48.3 15.3 61.6 33.0 10.3 10.3 37.5 3.2 24.5 16.5 84.3 84.3 44.0 40.0 25.0 25.0 62.5 25.0 Table 4-3 - Switched Power Allocations 4-5 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 5.0 431-SPEC-000112 Revision Release Status ( DRAFT) DELTA V / FUEL MASS ALLOCATION The overall Orbiter mass allocation is traced from the Mission Requirements Document (431REQT-000004, requirement #1.2.10. The given allocation was determined assuming maximum wet mass at liftoff. The Mid-Course Correction (MCC) allocation was determined from the MRD requirements, #1.2.14 and #2.3.1. This assumes a MCC at launch + 24 hours. The station-keeping allocation was determined from the MRD requirement # 1.1.54. The extended mission was derived from the MRD requirement #1.1.90. The delta V for the extended mission is a placeholder while extended mission options are traded. This allocation could be used for contingency if the mission required it. Mission Phase MCC Lunar Insertion – 1st burn Lunar Insertion – All other burns Station-keeping Extended Mission Margin Momentum Unloading Other Total LRO Baseline dV Fuel Mass Comments (m/sec) (kg) 75 52 3, MCC @ L+24 hours 1st insertion burn, finite dV, any launch date, 391 210 20% off-pulsing 535 288 All other insertion burns, finite dV 180 125 20 77 48 8 16 14 713 +/- 20 km altitude, 3 including errors Placeholder only 1326 Ullage, De-spin, Residuals Table 5-1 – Delta V / Fuel Mass Allocation 5-6 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 6.0 431-SPEC-000112 Revision Release Status ( DRAFT) DATA CAPTURE BUDGET TBD 6-7 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation 431-SPEC-000112 Revision Release Status ( DRAFT) Appendix A. Abbreviations and Acronyms Abbreviation/ Acronym C&DH CBE CCB CCR CDR CM CMO COMM CPU Delta V EEPROM Est. FSW GSFC HGA HTR I/F Kg LRO LV MCC MEL MRD PDE PDR PROM Prop PSE RAM Rec RF S/A S/C SRR SSR TBD DEFINITION Command & Data Handling Current Best Estimate Configuration Control Board Configuration Change Request Critical Design Review Configuration Management Configuration Management Office Communication Central Processing Unit Delta Velocity Electrically Erasable Programmable Read Only Memory Estimate Flight Software Goddard Space Flight Center High Gain Antenna Heater Interface Kilogram Lunar Reconnaissance Orbiter Launch Vehicle Mid-Course Correction Master Equipment List Mission Requirements Document Propulsion Deployment Electronics Preliminary Design Review Programmable Read Only Memory Propellant Power System Electronics Random Access Memory Receive Radio Frequency Solar Array Spacecraft Systems Requirement Review Solid State Recorder To Be Determined A-1 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE. Technical Resource Allocation TT&C UART W Xmit XPDR 431-SPEC-000112 Revision Release Status ( DRAFT) Tracking, Telemetry, & Commanding Universal Asynchronous Receiver / Transmitter Watt Transmitter Transponder A-2 CHECK WITH RLEP DATABASE AT: https://lunarngin.gsfc.nasa.gov TO VERIFY THAT THIS IS THE CORRECT VERSION PRIOR TO USE.