L 2C Learning to Collaborate Project Overview and Management and Progress Report (WP 7) Albert Angehrn & Alicia Cheak, INSEAD Review Meeting – INSEAD, Fontainebleau – 30 March 2007 1 Project Overview, Management & Progress Report (WP 7) Structure of the Presentation 1. Project Overview 2. D7.1 Quality Assurance Plan 3. Management and Financial Report Review Meeting – INSEAD, Fontainebleau – 30 March 2007 2 Project Overview, Management & Progress Report (WP 7) Project Overview Review Meeting – INSEAD, Fontainebleau – 30 March 2007 3 Project Overview, Management & Progress Report (WP 7) L2C: Learning to Collaborate The objective of the project is to address and significantly advance the state-of-the-art (both theory and practice) in two relevant areas: 1. Technology-enhanced learning of Collaboration Dynamics and Competencies Development. 2. Design of Advanced Simulations based on models of human behaviour in different contexts (organizational, group/team and interpersonal). Review Meeting – INSEAD, Fontainebleau – 30 March 2007 4 Project Overview, Management & Progress Report (WP 7) Three Project Outputs A comprehensive online Knowledge Base and active Virtual Learning Community on Advanced Collaboration Dynamics & Technologies (ACDT). ACDT Framework: An eLearning Framework to address the effective development of Collaboration Competencies in the Information Society. ACDT Simulation Games Prototypes: Validated computerenhanced solutions deployable in educational and organizational contexts. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 5 Project Overview, Management & Progress Report (WP 7) Relationship among L2C outputs Review Meeting – INSEAD, Fontainebleau – 30 March 2007 6 Project Overview, Management & Progress Report (WP 7) Mid-Team Review Milestones Milestones Review 1 • Knowledge harvesting, State of the Art review, common concept building among the partners • A set of L2C Simulation Games prototypes • Set up the Knowledge Base • Set up the Virtual Learning Community • Set up the Quality Assurance Plan • Dissemination and Exploitation Plan • Definition of the Evaluation Framework Review Meeting – INSEAD, Fontainebleau – 30 March 2007 7 Project Overview, Management & Progress Report (WP 7) Overview of the L2C Project Phase 1 : Conceptual foundations (M1-6) • Workpackage 1: Knowledge Harvesting and Integration • Workpackage 2: Knowledge Management tools development Phase 2: Prototype development (M7-12) • Workpackage 3: ACDT Framework, Simulation Scenarios and Design Phase 3: Piloting and continuous improvements to the prototypes (M 12-24) Learning to Collaborate • Workpackage 4: Pilots and piloting cycles • Workpackage 6: Embedded, continuous evaluation Phase 4: Deployment and dissemination (M 1-24) Workpackage 5: Dissemination and exploitation Project Management (M 1-24) • Workpackage 7: Project management Review Meeting – INSEAD, Fontainebleau – 30 March 2007 8 Project Overview, Management & Progress Report (WP 7) Simulation Design & Development Process Overview FOUNDATION (WP 1) KNOWLEDGE MANAGEMENT (WP 2) DESIGN & MODELLING (WP 3) PILTING & TESTING (WP 4) Review Meeting – INSEAD, Fontainebleau – 30 March 2007 DEPLOYMENT & DIFFUSION (WP 5) CONTINUOUS EVALUATION (WP 6) 9 Project Overview, Management & Progress Report (WP 7) D7.1 Quality Assurance Plan Review Meeting – INSEAD, Fontainebleau – 30 March 2007 10 Project Overview, Management & Progress Report (WP 7) Project Decision Making Structure Project Steering Project Co-ordinator and AssPC European Commission Committee Technical Co-ordinator Work Package Leaders WP 1 WP 2 ... Project Team Review Meeting – INSEAD, Fontainebleau – 30 March 2007 Technical Committee Exploitation & Dissemination Board WP N Relation with Institutions and others Products 11 Project Overview, Management & Progress Report (WP 7) Three Project Committees Created 1. Project Steering Committee • • To update the strategy of the project, review the progress of work, update plans and set priorities, to establish and enhance communication with third parties (the participation to international events and conferences included), and to resolve conflicts, whenever necessary. Meetings held: October 10, 2006 Meetings planned: April 15,2007 2. Technical Committee • • General technical implementation issues (technologies adopted, methodologies, validation circumstances, etc.). Review and update the solutions adopted, the technical directions of the project and identification of new solutions. Meetings planned: April 15, 2005 3. Exploitation & Dissemination Board • The Exploitation & Dissemination Board defines the commercialisation and dissemination strategy in accordance with the project sponsors in the individual companies, and possible assigned consultants • Meetings planned: May 2007 Review Meeting – INSEAD, Fontainebleau – 30 March 2007 12 Project Overview, Management & Progress Report (WP 7) Project Steering Committee Members Organization Main representative of each partner for the project INSEAD Albert Angehrn UCSC Federico Rajola UAFM Rainer Marr + Alexander Fliaster OFAI Prof. Robert Trappl OU Siv Vangen SCIL Taiga Brahm IF Ruggero Cesaria ALBA Nikos Mylonopoulos UC Anna Simioni Metis Thanos Giamas FVA Susanna Albertini Alpha Martina Eckert SU Chris Huxham Review Meeting – INSEAD, Fontainebleau – 30 March 2007 13 Project Overview, Management & Progress Report (WP 7) Technical Committee Members Organization Representative (WP Leaders) INSEAD Alicia Cheak UCSC Federico Rajola UAFM Alexander Fliaster OFAI Paolo Petta Metis Thanos Giamas FVA Louis Ferrini Review Meeting – INSEAD, Fontainebleau – 30 March 2007 14 Project Overview, Management & Progress Report (WP 7) Exploitation & Dissemination Board Members Organization Representative (Marketing and Business ties) INSEAD Albert Angehrn UCSC Chiara Frigerio UAFM Alexander Fliaster + Florian Schloderer OFAI Dr. Sabine Payr OU Siv Vangen SCIL Taiga Brahm IF Luigi Buson ALBA Tarsinos Panagiotis UC Mr. Gualtiero Insalac Metis Vassilis Argyroulis FVA Susanna Albertini Alpha Martina Eckert SU Pam Hearne Review Meeting – INSEAD, Fontainebleau – 30 March 2007 15 Project Overview, Management & Progress Report (WP 7) Project Monitoring 1. Progress and Status Reports 1. Bi-annual activity reports 2. Annual cost statements and financial report 3. Auditing of processes Review Meeting – INSEAD, Fontainebleau – 30 March 2007 16 Project Overview, Management & Progress Report (WP 7) Project Coordination and Communication 1. L2C Internal Project Space (www.calt.insead.edu/livinglab/moodle) Responsible partner: INSEAD • • Temporary collaboration platform on moodle for project coordination and communication while the L2C Knowledge Community (Workpackage 2) is under construction. Contains the key/basic tools: chat, forums, wikis, calendar, differential admin and editing rights, online status, email, document upload/download, search function, folders, etc. 2. L2C Website (www.l2c.net) Responsible partner: MeTis • Project website to communicate the project’s objectives and outputs to the general public. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 17 Project Overview, Management & Progress Report (WP 7) Project Coordination and Communication 3. L2C Knowledge Community (http://www.l2c.fvaweb.net/) Responsible partner: FVA • Collaboration platform for L2C partners, consisting of • Knowledge Base: uploading, categorizing, organizing and assessing content generated within the L2C project. Virtual Knowledge Community: collaboration space to facilitate discussion and collaborative work on the research, design, and deployment of L2C simulation games Detailed description of the L2C KC and status will be presented in the WP 2 presentation. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 18 Project Overview, Management & Progress Report (WP 7) Management & Financial Report Review Meeting – INSEAD, Fontainebleau – 30 March 2007 19 Project Overview, Management & Progress Report (WP 7) Annual Management Report for Year 1 The Annual Management Report is officially due on April 15. However, the EC required a draft copy of the report for the first L2C review meeting on March 31, 2007. Status: A draft version of the Annual Management Report from all partners was submitted March 23,2007. A final version will be submitted by April 15, 2007. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 20 Project Overview, Management & Progress Report (WP 7) Management Report: Overall Progress for the Period • Good Interaction and collaboration among the partners. • Key communication and collaboration mediums have been set up. • All the deliverables and prototypes have been delivered. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 21 Project Overview, Management & Progress Report (WP 7) Management Report: Deliverables Submitted for Review (M1-12) Del. No. Deliverable name WP no. Lead Nature Dissem. D7.1 Quality Assurance Plan ACDT Knowledge Harvesting and Integration report Dissemination and exploitation plan ACDT Knowledge Management tools Evaluation plan Technical and pedagogical criteria and metrics ACDT Framework, simulation scenarios and design ACDT Simulation Games prototypes Evaluation report of the first prototypes WP7 MeTis Report R M02 WP1 UAFM Report R M06 WP5 MeTis Report R M06 WP2 FVA R M08 WP6 UCSC Report + prototype Report R M08 WP6 UCSC Report R M08 WP3 OFAI Report R M12 WP3 OFAI Prototype R M12 WP6 UCSC Report R M12 D1.1 D5.1 D2.1 D6.1 D6.2 D3.1 D3.2 D6.3 Review Meeting – INSEAD, Fontainebleau – 30 March 2007 Delivery date 22 Project Overview, Management & Progress Report (WP 7) Management Report: Workpackage Status Planned Start Date Actual Start Date Planned Completion Date Actual Completion Date WP1– Knowledge Harvesting and Integration M1 (Mar 2006) M1 (Mar 2006) M6 (Aug 2006) M7 (Sept 2006) WP2– Knowledge Management Tools Development M5 (July 2006) M2 (Apr 2006) M8 (Oct 2006) M8 (Oct 2006) WP3 – ACDT Framework & Simulation Games Prototypes Development M7 (Sept 2006) M7 (Sept 2006) M12 (Feb 2007) M11.5 (Feb 2007) WP4 – Pilots & Prototyping Cycles M13 (Mar 2007) Has not started yes M24 (Feb 2008) WP5 – Exploitation and Dissemination M7 (Sept 2006) M1 (Mar 2006) M24 (Feb 2008) In progress WP6 – Embedded, Continuous Evaluation M6 (Aug 2006) M 6 (Aug 2006) M23 (Jan 2008) In progress WP7 – Project Management M1 (Mar 2006) M1 (Mar 2006) M24 (Feb 2008) In progress Work Package Review Meeting – INSEAD, Fontainebleau – 30 March 2007 23 Project Overview, Management & Progress Report (WP 7) Management Report: Quarterly Consortium Meetings Date Location Topic 11-12 January 2007 Metis, Athens, Greece 4th Project meeting 14-15 September 2006 UCAC, Milan, Italy 3rd Project Meeting 24-25 May 2006 ALBA, Athens, Greece 2nd Project Meeting 6-7 March, 2006 INSEAD, Fontainebleau, France Kick-off meeting Review Meeting – INSEAD, Fontainebleau – 30 March 2007 24 Project Overview, Management & Progress Report (WP 7) Management Report: Status of Individual Workpackages • • • WP 1, 2 and 3 are now complete. WP 5, 6 and 7 are ongoing. WP 4 will officially start on April 1 (but some initial testing with actual users has already begun) Review Meeting – INSEAD, Fontainebleau – 30 March 2007 25 Project Overview, Management & Progress Report (WP 7) Management Report: Effort Declared in Y1 Current situation Used (Year 1) Budget (Total- Year 1 + Year 2) % WP1 48,12 55,5 86,7% WP2 49,07 52,5 94,5% WP3 48,63 68,5 70,9% WP4 0 76 0 WP5 21,27 65,5 32,5% WP6 14,77 46,5 31,8% WP7 5,45 10,8 50.5% Total 187,31 375,3 49,9% Review Meeting – INSEAD, Fontainebleau – 30 March 2007 26 Project Overview, Management & Progress Report (WP 7) WP Status Analysis & Adjustments Activity completed with minor underspending. Comment: No particular comment. Reallocation: The unspent resource workpackages (namely WP 4). Activity completed with minor underspending. Comment: No particular comment. Reallocation: The unspent resource will be moved to other workpackages (namely WP 4) towards the ongoing development of the knowledge management tools. Activity completed with an under spending of almost 29% under the estimation. Comment: The time allocated for conducting this activity was overestimated given the short time frame for the development of the first version of the 5 different prototypes. Reallocation: The unspent resource will be moved to WP 4 since WP 4 is a natural extension of WP 3 activities, involving pilot testing and further developments to each of the prototypes. Not yet started. Comment: Reallocation: WP5 Ongoing Activity over 2 years, with 32,5% spent in the first year. Comment: We expect to increase our dissemination activities in Year 2 when the prototypes will have been defined, tested and deployed. Reallocation: No reallocation needed. WP6 Ongoing activity over 1.5 years, with 31,8% of effort spent in the first year. Comment: Significant evaluation will start with WP 4. Reallocation: No reallocation needed. WP7 Ongoing activity over 2 years, with 50,5% of effort spent in the first year. Comment: No particular comment. Reallocation: No reallocation needed. WP1 WP2 WP3 WP4 Review Meeting – INSEAD, Fontainebleau – 30 March 2007 will be moved to other 27 Project Overview, Management & Progress Report (WP 7) Management Report: Budget Readjustments for Year 2 Budgeted (in DOW) New Budget diff WP1 55,5 48,12 -7,38 WP2 52,5 49,07 -3,43 WP3 68,5 48,63 -19,87 WP4 76 106,68 30,68 WP5 65,5 65,5 0,0 WP6 46,5 46,5 0,0 WP7 10,8 10,8 0,0 Total 375,3 375,3 0,0 Review Meeting – INSEAD, Fontainebleau – 30 March 2007 28 Project Overview, Management & Progress Report (WP 7) Current Experiences and Insights WP 1: This workpackage has not met any major problem. As the project started in March 2006, M6 which is very important for Workpackage 1 fell in the vacation period in August. Therefore the planning for Workpackage 1 was extended for one additional month to M7. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 29 Project Overview, Management & Progress Report (WP 7) Current Experiences and Insights WP 2: No major problems were encountered. Longer period of development required for KM tools. WP 2 started in M2 instead of M5 (with the allocated resources stretched out over this time period), in order to allow enough time for the design and development of the knowledge management tools. In order to integrate all the features requested by the partners, a few MM were shifted internally from WP 5 to WP 2. Further refinement to the knowledge management tools will take place during the piloting phase in WP 4. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 30 Project Overview, Management & Progress Report (WP 7) Current Experiences and Insights WP 3: Tight development schedule. Five prototypes were under parallel construction within a 6 months period. Translating theory into practice took more time than originally anticipated. The large amount of information about different models and theories of collaboration (from WP 1), and the fact that many of these models/theories do not distinguish clearly the three different levels of collaboration addressed, were the major challenges in the identification of specific dynamics for each of the simulation game prototypes. Initial evaluation of theoretical and design soundness of the prototypes. At the time of reporting for D6.1 Evaluation of the First Prototypes in February 2007, the partners had the design specification (i.e. D3.1) as a point of reference. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 31 Project Overview, Management & Progress Report (WP 7) Current Experiences and Insights WP 3: Early user feedback is key. Initial pilots have been conducted in the form of three tests of three prototypes with three groups of managers (user feedback collection). A reallocation of resources of partners from WP3 to WP4 was undertaken, with WP 4 a natural extension of WP 3. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 32 Project Overview, Management & Progress Report (WP 7) Current Experiences and Insights WP 5: This WP has not faced a major problem. Rich discussions were conducted on how to design an effective website to communicate about project results. They will be integrated in the next project phase. Ideally, communication should start at Day 1. The consortium decided after a communication with our Project Officer that the WP should start M1 and finish in M24. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 33 Project Overview, Management & Progress Report (WP 7) Current Experiences and Insights WP 6: No major problems have been encountered. Strong coordination and planning is key. However, due to the closeness of the evaluation process activities to the evolvement of other WPs, it was essential to reach a strong coordination among WPs to work along together. Because the deliverable was delivered a month before expected, so that it could be considered in the first review meeting, a full evaluation of the working prototypes was not possible. • • The Knowledge Base and Virtual Community dimensions were evaluated from a technical point of view. More detailed and continuous evaluation will continue in WP 4. For the evaluation of the simulation games prototypes, the design specifications were assessed, as represented by the description of the design, pedagogical and implementation guidelines of each of the 5 prototypes currently in development. A more detailed evaluation covering both pedagogical and technical dimensions of the actual prototypes will take place, as planned, during the piloting phase (WP 4). Review Meeting – INSEAD, Fontainebleau – 30 March 2007 34 Project Overview, Management & Progress Report (WP 7) Current Experiences and Insights WP 6: Challenge of development and evaluation at the same time. Finally, it was not always easy to manage partners’ needs and requests of time extensions when they are involved in several evaluation activities. What happened is that an output is evaluated as it is being completed, and that these evaluation activities had to be completed in a very short period of time. This issue will be better managed in WP 4 which spans a year and will allow for more well planned and properly timed evaluation (i.e. corresponding to pilot tests). Review Meeting – INSEAD, Fontainebleau – 30 March 2007 35 Project Overview, Management & Progress Report (WP 7) Current Experiences and Insights WP 7: • No major problems were encountered. However, due to how the project has unfolded, some workpackages required less effort or a longer time frame than had been anticipated. • Some partners were new to EC projects and needed particular support. • The Consortium Agreement took more time than expected due to involvement of legal departments of partner organizations. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 36 Project Overview, Management & Progress Report (WP 7) Financial Cost Statements The Financial Cost Statements are officially due on April 15. However, the EC required a draft copy of the financial report for the first L2C review meeting on March 31, 2007. Status: A draft version of the cost statements from all partners has been submitted. A final version will be submitted by April 15, 2007. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 37 Project Overview, Management & Progress Report (WP 7) Financial Cost Statements The Financial Cost Statements are officially due on April 15. However, the EC required a draft copy of the financial report for the first L2C review meeting on March 31, 2007. Status: A draft version of the cost statements from all partners has been submitted. A final version will be submitted by April 15, 2007. Review Meeting – INSEAD, Fontainebleau – 30 March 2007 38 Project Overview, Management & Progress Report (WP 7) Effort Declared Per Partner M1-6 Reported effort & planned effort for each partner per workpackage (person months) WP1 WP2 WP3 WP4 WP5 WP6 WP7 Name of Partner Report Plan Report Plan Report Plan Report Plan Report Plan Report Plan Report Plan INSEAD 8,65 10 4,65 6 0 16 0 22 0,4 12 0 6 1,65 4 UCSC 5 5 1,2 4 0 3 0 4,5 0,8 4 1,5 7,5 0 0,5 UAFM 4,9 8 0,7 4 0 4,5 0 2,5 0,05 2 0 4 0,05 0,5 OFAI (funded) 1,5 5,5 0 2 0 11 0 3,5 0 2 0 3,5 0 0,5 OU 5 5 0 2 0 2 0 0,5 0,1 2,5 0 3 0,1 0,5 SCIL 2,5 2,5 0 2 0 4 0 3 0 2 0 4 0 0,5 IF 1 1 1 2 0 2 0 5 0,5 3 0 2,5 0,25 0,5 ALBA 2,5 4,5 2,5 3 0 3 0 6 1,5 6 0 4 0,2 0,8 UC 1,1 1 0,5 2 0 2 0 5,5 0 3 0 2,5 0,2 0,5 MeTis 2,5 2,5 4,5 6 0 4 0 12 4 15 0 4,5 0,3 1 FVA 1,81 2 7,84 11,5 0 8,5 0 5,5 0,6 7,5 0 1 0 0,5 Alpha 3,5 3,5 4,35 5 0 7,5 0 5,5 0,2 5 0 0 0,1 0,5 SU 0,75 5 2,4 3 0 1 0 0,5 0,25 1,5 0,05 4 0 0,5 TOTAL 40,71 55,5 29,64 52,5 0 68,5 0 76 8,4 65,5 1,55 46,5 2,85 10,8 Review Meeting – INSEAD, Fontainebleau – 30 March 2007 39 Project Overview, Management & Progress Report (WP 7) Effort Declared Per Partner M7-12 Reported effort & planned effort for each partner per workpackage (person months) WP1 WP2 WP3 WP4 WP5 WP6 WP7 Name of Partner Report Plan Report Plan Report Plan Report Plan Report Plan Report Plan Report Plan INSEAD 1,35 10 1,35 6 16 16 0 22 2,85 12 1,25 6 1,6 4 UCSC 0 5 2,8 4 0,8 3 0 4,5 0,5 4 1,76 7,5 0 0,5 UAFM 1,92 8 2,02 4 1,13 4,5 0 2,5 1,02 2 0,56 4 0 0,5 OFAI (funded) 0 5,5 0,5 2 6,6 11 0 3,5 0 2 0,9 3,5 0 0,5 OU 0 5 2 2 1,2 2 0 0,5 0,9 2,5 0,45 3 0,15 0,5 SCIL 0 2,5 1,35 2 2 4 0 3 1 2 2 4 0.25 0,5 IF 0 1 1 2 2 2 0 5 0,5 3 1 2,5 0 0,5 ALBA 0 4,5 0,5 3 2 3 0 6 1,5 6 2,5 4 0,2 0,8 UC 0 1 0,5 2 1 2 0 5,5 0,4 3 1 2,5 0,1 0,5 MeTis 0 2,5 1,5 6 2,5 4 0 12 4 15 1 4,5 0,3 1 FVA 0,39 2 5,16 11,5 4,9 8,5 0 5,5 0 7,5 0,8 1 0 0,5 Alpha 0 3,5 0,65 5 7,5 7,5 0 5,5 0,05 5 0 0 0 0,5 SU 3,75 5 0,1 3 1 1 0 0,5 0,15 1,5 0 4 0 0,5 TOTAL 7,41 55,5 19,43 52,5 48,63 68,5 0 76 12,87 65,5 13,22 46,5 2,6 10,8 Review Meeting – INSEAD, Fontainebleau – 30 March 2007 40 Project Overview, Management & Progress Report (WP 7) Effort Declared Per Partner M1-12 Reported effort & planned effort for each partner per workpackage (person months) WP1 WP2 WP3 WP4 WP5 WP6 WP7 Name of Partner Report Plan Report Plan Report Plan Report Plan Report Plan Report Plan Report Plan INSEAD 10 10 6 6 16 16 0 22 3,25 12 1,25 6 3,25 4 UCSC 5 5 4 4 0,8 3 0 4,5 1,3 4 3,26 7,5 0 0,5 UAFM 6,82 8 2,72 4 1,13 4,5 0 2,5 1,07 2 0,56 4 0,05 0,5 OFAI 1,5 5,5 0,5 2 6,6 11 0 3,5 0 2 0,9 3,5 0 0,5 OU 5 5 2 2 1,2 2 0 0,5 1 2,5 0,45 3 0,25 0,5 SCIL 2,5 2,5 1,35 2 2 4 0 3 1 2 2 4 0,25 0,5 IF 1 1 2 2 2 2 0 5 1 3 1 2,5 0,25 0,5 ALBA 2,5 4,5 3 3 2 3 0 6 3 6 2,5 4 0,4 0,8 UC 1,1 1 1 2 1 2 0 5,5 0,4 3 1 2,5 0,3 0,5 MeTis 2,5 2,5 6 6 2,5 4 0 12 8 15 1 4,5 0,6 1 FVA 2,2 2 13 11,5 4,9 8,5 0 5,5 0,6 7,5 0,8 1 0 0,5 Alpha 3,5 3,5 5 5 7,5 7,5 0 5,5 0,25 5 0 0 0,1 0,5 SU 4,5 5 2,5 3 1 1 0 0,5 0,4 1,5 0,05 4 0 0,5 TOTAL 48,12 55,5 49,07 52,5 48,63 68,5 0 76 21,27 65,5 14,77 46,5 5,45 10,8 Review Meeting – INSEAD, Fontainebleau – 30 March 2007 41 Project Overview, Management & Progress Report (WP 7) Targets/Plan for Third Semester: Activity WP Resp. Partner Agent Brain Module Implementation 4 OFAl Integration of Brain Module in Agent Prototype 4 INSEAD and AlphaLabs Specification of New Dynamics for Simulation Prototypes (Detailed Scenarios) 4 All Implementation of New Dynamics in Simulation Prototypes 4 INSEAD and Alphalabs Fine-tuning of Pedagogical Material for Simulation Prototypes 4 All Further development of L2C Knowledge Community site 4 FVA Pilot Runs 4 All Evaluation of Users Feedback from Pilot Runs 6 UCSC Production of Effective Communication Material 7 MeTis Review Meeting – INSEAD, Fontainebleau – 30 March 2007 42 Project Overview, Management & Progress Report (WP 7) Thank You for Your Attention Review Meeting – INSEAD, Fontainebleau – 30 March 2007 43