Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
July 3rd, 2013
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Student Assembly Building (Sanctuary): Design and Construction of sanctuary
building of approximately 6,500 square feet to serve as a venue for group events.
Tentative Schedule:
Feasibility Study
Complete
Programming
TBD
Conceptual Permitting TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Consultants presented
preliminary designs on May
31st. Designs were shown to
the President’s Executive
Council. Committee has
reconvened on June 24th. A
recommendation to award the
project to one consultant has
been forwarded to the
President’s office for
endorsement.
2.
Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of
magnitude cost for providing utility services to a grouping of four buildings.
Tentative Schedule:
ON HOLD.
3.
Development of Greek Village: This project entails the programming and completing a
feasibility study to develop 250-bed a Greek Village at Tech. Park
Tentative Schedule:
Consultant Selection
RFQ Released
Consultant Selection
TBD
Programming
Feasibility Study
Report Due
Changes from last month:
Zak Ovadia
TBD
TBD
December 2012
NO CHANGES THIS
MONTH. Meetings held with
fraternities. Revising
proposal for sororities.
1
4.
New Housing Clubhouse Building: Design and Construction of a new Clubhouse to
service the housing units in the core campus. Program calls for a 15,000 GSF building to
contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450
students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900
students.
Tentative Schedule:
Programming
Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Select CM
Complete
Construction Docs.
Complete
Construction
May 2013 to July 2014.
Changes from last month:
Project is currently under
construction. CM firm AJAX
was selected for this project.
Early GMP Package for Utilities
infrastructure was endorsed and
Amendment endorsed. GMP
for the building is currently
being negotiated.
5. Chick-fil-A Build Out: Design and Construction of a new fast food outlet to replace
Sbarro’s on the first floor of Building 8. .
Tentative Schedule:
Programming
Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
Complete
Design Development Complete
Select CM
Complete
Construction Docs.
Complete
Construction
May 2013 to August 2013.
Changes from last month:
GMP was submitted by Batson
Cook and was accepted. Started
construction in early May for
completion at the end of July.
6. Athletics Mini Master Plan: Consultant was engaged to look at Athletics and
Recreation needs over the next 15 to 20 years. This mini master plan will be blended into
the campus Master Plan at the next review period in 2014. .
Tentative Schedule:
Kick-off Meeting
Complete
Interim Presentation
Complete
Final Presentation.
Complete
Changes from last month:
Consultants presented a prefinal Master Plan Report to the
Committee on May 30, 2013.
Based on comments made, the
final report document was
submitted to UNF on July 20.
Copies have been distributed.
Zak Ovadia
2
7.
Aquatic Center Re-purposing for Basketball: Design and construction of basketball
courts and general extensive renovations to the Aquatic Center to eliminate the pool.
Tentative Schedule:
Programming
TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Request for Qualification
document ready to be published.
Awaiting funding..
8. New Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size
pool and diving pool north of the existing Student Wellness Complex.
Tentative Schedule:
Programming
TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Request for Qualification
document ready to be published.
Awaiting funding.
9. Skinner-Jones Hall North Feasibility Study
Completed Projects:









Zak Ovadia
COE&HS Building with DRC, VCS, VCL and OCT
Science and Humanities Building (Biological Sciences)
Science & Engineering Building Remedial Work:
Housing Maintenance Building
Student Wellness Complex – Phase I
Northeast Connector Road and Lot 34 Upgrade
Hayt Golf Learning Center – Women’s Locker Room & Lounge
Programming for Buildings 50, 3 and 4
New Food Service Facility and General Purpose Building: