University of North Florida ADMINISTRATION & FINANCE Departmental Status Report for Space Committee Meeting Director: Department: Date: Zak Ovadia Campus Planning Design & Construction September 4th, 2013 I. SELECTED ACTIVE PROJECTS NOTE ALL SCHEDULES ARE TENTATIVE 1. Student Assembly Building (Sanctuary): Design and Construction of sanctuary building of approximately 6,500 square feet to serve as a venue for group events. Tentative Schedule: Programming TBD Conceptual Permitting TBD RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification TBD Schematic Design August 2013 Design Development October 2013 Construction Docs. TBD Construction TBD Changes from last month: Fee proposal from consultant, negotiated and accepted. AIA Contract in the works. 2. New Housing Clubhouse Building: Design and Construction of a new Clubhouse to service the housing units in the core campus. Program calls for a 15,000 GSF building to contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450 students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900 students. Tentative Schedule: Programming Complete RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification Complete Schematic Design August 2012 Design Development October 2012 Select CM January 2013 Construction Docs. March 2013 Construction May 2013 to July 2014. Changes from last month: No changes from last month. Project is currently under construction and on schedule. Zak Ovadia 1 3. Elevated Parking Deck at Lot 14: Feasibility, Design and Construction of a new elevated parking deck over part of Lot 14. Consultant will test the feasibility of adding additional parking levels to tie to the existing Fine Arts Garage. Program calls for a minimum of 170 stalls to serve the residential population. Tentative Schedule: Programming August 2013 RFQ for Consultants Completed Short-listing & Interv. Completed Program Verification September 2013 Schematic Design September 2013 Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Baker Barrios Architects was selected as prime consultant. . 6. Aquatic Center Re-purposing for Basketball: Design and construction of basketball courts and general extensive renovations to the Aquatic Center to eliminate the pool. Tentative Schedule: Programming TBD RFQ for Consultants TBD Short-listing & Interv. TBD Program Verification TBD Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Request for Qualification in the process. Submissions due September 9. 7. New Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size pool and diving pool north of the existing Student Wellness Complex. Tentative Schedule: Programming TBD RFQ for Consultants TBD Short-listing & Interv. TBD Program Verification TBD Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Request for Qualification document ready to be published. 8. Skinner-Jones Hall NORTH: Programming and Schematic Design: Programming, Schematic Design, Feasibility Study to re-purpose this building. Program will Zak Ovadia 2 include Skinner-Jones Hall SOUTH as well as other buildings having related departments (Math, Engineering, Health, etc). Tentative Schedule: RFQ for Consultants August 2013 Short List for interview September 2013 Programming November 2013 Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Request for Qualification document published. 9. Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of magnitude cost for providing utility services to a grouping of four buildings. Tentative Schedule: ON HOLD. 10. Development of Greek Village: This project entails the programming and completing a feasibility study to develop 250-bed a Greek Village at Tech. Park Tentative Schedule: Consultant Selection RFQ Released Consultant Selection TBD Programming Feasibility Study Report Due Changes from last month: Zak Ovadia TBD TBD December 2012 NO CHANGES THIS MONTH. Meetings held with fraternities. Revising proposal for sororities. 3