12-04-2013 Space Update

advertisement
University of North Florida
ADMINISTRATION & FINANCE
Departmental Status Report for Space Committee Meeting
Director:
Department:
Date:
Zak Ovadia
Campus Planning Design & Construction
December 4th, 2013
I. SELECTED ACTIVE PROJECTS
NOTE ALL SCHEDULES ARE TENTATIVE
1.
Student Assembly Building (Sanctuary): Design and Construction of sanctuary
building of approximately 6,500 square feet to serve as a venue for group events.
Tentative Schedule:
Programming
TBD
Conceptual Permitting TBD
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification TBD
Schematic Design
August 2013
Design Development October 2013
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Consultant has been updating
design based on previous
comments made by the
selection committee. Package
is being prepared to show
President. Design Committee
will be requested to attend a
kick-off meeting soon.
2.
New Housing Clubhouse Building: Design and Construction of a new Clubhouse to
service the housing units in the core campus. Program calls for a 15,000 GSF building to
contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450
students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900
students.
Tentative Schedule:
Programming
Complete
RFQ for Consultants Complete
Short-listing & Interv. Complete
Program Verification Complete
Schematic Design
August 2012
Design Development October 2012
Select CM
January 2013
Construction Docs.
March 2013
Construction
May 2013 to July 2014.
Changes from last month:
Project is currently under
construction and on schedule.
Student Government
requested a Pita Pit. There
are no delay claims at this
time.
Zak Ovadia
1
3.
Elevated Parking Deck: Feasibility, Design and Construction of a new elevated parking
deck over part of an existing lot south of the FAC. Consultant tested the feasibility of
adding additional parking levels to tie to the existing Fine Arts Garage. Program calls
for a minimum of 170 stalls to serve the residential population. Currently the design
provides over 500 stalls.
Tentative Schedule:
Programming
August 2013
RFQ for Consultants Completed
Short-listing & Interv. Completed
Program Verification September 2013
Schematic Design
September 2013
Design Development October 2013
Select CM
January 2014
Construction Docs.
March 2014
Construction
TBD
Changes from last month:
Baker Barrios has completed
a concept package which was
presented to the President.
President was also given a
“Fly-By” to better get a
feeling of the building from
various vantage points. Work
on documents continues.
.
6. Aquatic Center Re-purposing for Basketball: Design and construction of basketball
courts and general extensive renovations to the Aquatic Center to eliminate the pool.
Tentative Schedule:
Programming
TBD
RFQ for Consultants TBD
Short-listing & Interv. November 2013
Program Verification December 2013
Schematic Design
January 2014
Design Development February 2014
Select CM
March 2014
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Interviews with Borelli, HKS
and RDB were held on
Monday Oct. 28. President
endorsed the selection of RDB
as the preferred consultant.
Project Committee is
scheduled to attend a kick-off
meeting on December 10.
Zak Ovadia
2
7. New Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size
pool and diving pool north of the existing Student Wellness Complex.
Tentative Schedule:
Programming
TBD
RFQ for Consultants TBD
Short-listing & Interv. TBD
Program Verification TBD
Schematic Design
TBD
Design Development TBD
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Request for Qualification was
advertised. Shortlisting of 6
firms occurred on November
14. Interviews scheduled for
December 9.
8. Skinner-Jones Hall NORTH: Programming and Schematic Design: Programming,
Schematic Design, Feasibility Study to re-purpose this building. Program will
include Skinner-Jones Hall SOUTH as well as other buildings having related
departments (Math, Engineering, Health, etc).
Tentative Schedule:
RFQ for Consultants August 2013
Short List for interview September 2013
Programming
November 2013
Schematic Design
TBD
Design Development TBD
Select CM
TBD
Construction Docs.
TBD
Construction
TBD
Changes from last month:
Shortlisting meeting was held
on October 17. Interviews of
3 firms were held November
15. Recommendation will be
sent to President for
endorsement.
9. Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of
magnitude cost for providing utility services to a grouping of four buildings.
Tentative Schedule:
NO CHANGE.
10. Development of Greek Village: This project entails the programming and completing a
feasibility study to develop 250-bed a Greek Village at Tech. Park
Tentative Schedule:
Consultant Selection
RFQ Released
Consultant Selection
TBD
Programming
Feasibility Study
Report Due
Changes from last month:
Zak Ovadia
TBD
TBD
December 2012
NO CHANGES
3
Download