University of North Florida ADMINISTRATION & FINANCE Departmental Status Report for Space Committee Meeting Director: Department: Date: Zak Ovadia Campus Planning Design & Construction December 4th, 2013 I. SELECTED ACTIVE PROJECTS NOTE ALL SCHEDULES ARE TENTATIVE 1. Student Assembly Building (Sanctuary): Design and Construction of sanctuary building of approximately 6,500 square feet to serve as a venue for group events. Tentative Schedule: Programming TBD Conceptual Permitting TBD RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification TBD Schematic Design August 2013 Design Development October 2013 Construction Docs. TBD Construction TBD Changes from last month: Consultant has been updating design based on previous comments made by the selection committee. Package is being prepared to show President. Design Committee will be requested to attend a kick-off meeting soon. 2. New Housing Clubhouse Building: Design and Construction of a new Clubhouse to service the housing units in the core campus. Program calls for a 15,000 GSF building to contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450 students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900 students. Tentative Schedule: Programming Complete RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification Complete Schematic Design August 2012 Design Development October 2012 Select CM January 2013 Construction Docs. March 2013 Construction May 2013 to July 2014. Changes from last month: Project is currently under construction and on schedule. Student Government requested a Pita Pit. There are no delay claims at this time. Zak Ovadia 1 3. Elevated Parking Deck: Feasibility, Design and Construction of a new elevated parking deck over part of an existing lot south of the FAC. Consultant tested the feasibility of adding additional parking levels to tie to the existing Fine Arts Garage. Program calls for a minimum of 170 stalls to serve the residential population. Currently the design provides over 500 stalls. Tentative Schedule: Programming August 2013 RFQ for Consultants Completed Short-listing & Interv. Completed Program Verification September 2013 Schematic Design September 2013 Design Development October 2013 Select CM January 2014 Construction Docs. March 2014 Construction TBD Changes from last month: Baker Barrios has completed a concept package which was presented to the President. President was also given a “Fly-By” to better get a feeling of the building from various vantage points. Work on documents continues. . 6. Aquatic Center Re-purposing for Basketball: Design and construction of basketball courts and general extensive renovations to the Aquatic Center to eliminate the pool. Tentative Schedule: Programming TBD RFQ for Consultants TBD Short-listing & Interv. November 2013 Program Verification December 2013 Schematic Design January 2014 Design Development February 2014 Select CM March 2014 Construction Docs. TBD Construction TBD Changes from last month: Interviews with Borelli, HKS and RDB were held on Monday Oct. 28. President endorsed the selection of RDB as the preferred consultant. Project Committee is scheduled to attend a kick-off meeting on December 10. Zak Ovadia 2 7. New Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size pool and diving pool north of the existing Student Wellness Complex. Tentative Schedule: Programming TBD RFQ for Consultants TBD Short-listing & Interv. TBD Program Verification TBD Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Request for Qualification was advertised. Shortlisting of 6 firms occurred on November 14. Interviews scheduled for December 9. 8. Skinner-Jones Hall NORTH: Programming and Schematic Design: Programming, Schematic Design, Feasibility Study to re-purpose this building. Program will include Skinner-Jones Hall SOUTH as well as other buildings having related departments (Math, Engineering, Health, etc). Tentative Schedule: RFQ for Consultants August 2013 Short List for interview September 2013 Programming November 2013 Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Shortlisting meeting was held on October 17. Interviews of 3 firms were held November 15. Recommendation will be sent to President for endorsement. 9. Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of magnitude cost for providing utility services to a grouping of four buildings. Tentative Schedule: NO CHANGE. 10. Development of Greek Village: This project entails the programming and completing a feasibility study to develop 250-bed a Greek Village at Tech. Park Tentative Schedule: Consultant Selection RFQ Released Consultant Selection TBD Programming Feasibility Study Report Due Changes from last month: Zak Ovadia TBD TBD December 2012 NO CHANGES 3