University of North Florida ADMINISTRATION & FINANCE Departmental Status Report for Space Committee Meeting Director: Department: Date: Zak Ovadia Campus Planning Design & Construction April 2, 2014 I. SELECTED ACTIVE PROJECTS NOTE ALL SCHEDULES ARE TENTATIVE 1. Student Assembly Building (Sanctuary): Design and Construction of sanctuary building of approximately 6,500 square feet to serve as a venue for group events. Tentative Schedule: Programming TBD Conceptual Permitting TBD RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification Complete Schematic Design August 2013 Design Development October 2013 Construction Docs. February 2014 Construction TBD Changes from last month: Technical Review meeting was held on March 13. The Project Committee will be meeting the second week in April. 2. New Housing Clubhouse Building: Design and Construction of a new Clubhouse to service the housing units in the core campus. Program calls for a 15,000 GSF building to contain a Convenience Store/Grill, a Multi-purpose Room, a Laundry facility for 450 students, an R/A Graphics Room, a Game Room and a Mail Distribution area for 2,900 students. Tentative Schedule: Programming Complete RFQ for Consultants Complete Short-listing & Interv. Complete Program Verification Complete Schematic Design August 2012 Design Development October 2012 Select CM January 2013 Construction Docs. March 2013 Construction May 2013 to July 2014. Changes from last month: Project is currently under construction and on schedule. There are no issues at this time. Zak Ovadia 1 3. Elevated Parking Deck: Feasibility, Design and Construction of a new elevated parking deck over part of an existing lot south of the FAC. Consultant tested the feasibility of adding additional parking levels to tie to the existing Fine Arts Garage. Program calls for a minimum of 170 stalls to serve the residential population. Currently the design provides over 550 stalls. Tentative Schedule: Programming August 2013 RFQ for Consultants Completed Short-listing & Interv. Completed Program Verification Completed Schematic Design Completed Design Development October 2013 Select CM January 2014 Construction Docs. March 2014 Construction Must be occupiable by January 2015 Changes from last month: President endorsed the selection of Perry-McCall as the CM. . 6. Aquatic Center Re-purposing for Basketball: Design and construction of basketball courts and general extensive renovations to the Aquatic Center to eliminate the pool. Tentative Schedule: Programming TBD RFQ for Consultants TBD Short-listing & Interv. November 2013 Program Verification December 2013 Schematic Design February 2014 Design Development February 2014 Select CM March 2014 Construction Docs. TBD Construction TBD Changes from last month: Eleven CM submissions were reviewed. Three firms will be invited to interview (Danis, Barton Malow, and Clancy & Theys). 7. New Outdoor Swimming Pool: Design and Construction of an outdoor Olympic-size pool and diving pool north of the existing Student Wellness Complex. Tentative Schedule: Programming TBD RFQ for Consultants TBD Short-listing & Interv. TBD Program Verification TBD Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Kick-off meeting was held on February 13. Working on Program Verification and Schematic Design. Zak Ovadia 2 8. Skinner-Jones Hall NORTH: Programming and Schematic Design: Programming, Schematic Design, Feasibility Study to re-purpose this building. Program will include Skinner-Jones Hall SOUTH as well as other buildings having related departments (Math, Engineering, Health, etc). Tentative Schedule: RFQ for Consultants August 2013 Short List for interview September 2013 Programming February 2014 Schematic Design TBD Design Development TBD Select CM TBD Construction Docs. TBD Construction TBD Changes from last month: Meetings with Focus Groups completed. Consultant preparing bubble diagrams. Meeting with Steering Committee is tentatively scheduled for last week in April. 7. Library Learning Commons: Reconfigure First and Second Floors to create a studentcentric learning commons. Co-locate the Help Desk from Bldg. 15, and remodel entry lobby. Tentative Schedule: Programming February 2014 Program Verification March 2014 Schematic Design March 2014 Design Development April 2014 Construction Docs. TBD Construction TBD Changes from last month: Three meetings were held with Library and ITS Staff to review space allocations. The last iteration will be distributed for discussion. A committee meeting is being scheduled for the second week in April with Steelcase. 9. Religious Centers: Engage Civil Engineer to provide a feasibility study and an order of magnitude cost for providing utility services to a grouping of four buildings. Tentative Schedule: NO CHANGE. Zak Ovadia 3 10. Development of Greek Village: This project entails the programming and completing a feasibility study to develop 250-bed a Greek Village at Tech. Park Tentative Schedule: Consultant Selection RFQ Released Consultant Selection TBD Programming Feasibility Study Report Due Changes from last month: Zak Ovadia TBD TBD December 2012 NO CHANGES 4