The Schoharie Creek Thruway bridge collapse 4A6(1) Structural Design Project By Group 18 David O’Brien Karen McMorrow Clare Whitely Submitted October 23rd 2009 Introduction The Schoharie Creek Bridge collapsed on April 5, 1987, just 30 years after it was constructed. It was a New York State Thruway bridge over the Schoharie Creek near Fort Hunter, in New York State. The bridge operated as a pivotal piece of the 900km stretch of superhighway which allowed New Yorker’s travel around the state with ease. The collapse was caused due to erosion of the foundations and the surrounding footing. Five vehicles fell into the flooded river resulting in the death of 10 people. Design and Construction Construction of the Schoharie Creek Bridge began on February 11, 1953. The truss design bridge was supported with pier frames along with abutments at each end. The pier frames were constructed of two slightly tapered columns with tie beams. The columns were fixed in place within a lightly reinforced plinth positioned on a shallow, reinforced spread footing. The spread footing was to be protected with a dry layer of riprap (rock). The superstructure consisted of two longitudinal main girders with transverse floor beams. The skeleton of the bridge deck (200 millimeters thick) was made up of steel stringers. The 165m long structure had 5 separate spans, each span measuring 30.5m, 33.5m, 36.6m, 33.5m, and 30.5m respectively, along with 4 concrete pier frames which would support the bridges spans along with abutments at each end, 2 were to be erected in the creek with shallow pad footings and two on the banks of the creek. A cross-section of a typical pier with footing is as follows: 112.5' 27.75' 57' 27.75' Symmetrical about C L Deck Stringer at 8'-6" o.c. Floor Beam at approx. 20' o.c. Knee Brace Main Girder Cantilever Floor Beam Ends Bearing 7'-0" sq Column 5'-0" wide X10'-0" deep Tie Beam Column Plinth Reinforcement Plinth Footing Figure 1 - Pier Section ( after "Collapse," 1987 ) Collapse In April 1987, the collapse of the Schoharie Creek Bridge occurred during the spring flood. Rainfall totalling 150mm together with snowmelt produced an estimated 50 year flood. The collapse was triggered by the toppling of pier 3. The main cause of the collapse was the intense scouring of pier three. Scour is the removal of sediment from a streambed caused by erosive action of flowing water. It created a scour hole approximately 3 metres deep and 9 metres of the pier was undermined. The pier fell suddenly into the hole, without any warning signs. This led to spans 3 and 4 also collapsing and falling into the creek. When it collapsed, a car and a tractor and trailer were on the bridge. An additional 3 cars also fell into the gap. 90 minutes later pier 2 and span 2 collapsed. It has been suggested by the National Transport Safety Board (NTSB) that pier 2 collapsed due to a blockage caused by the debris from pier 3 and the 2 spans in the river. This caused the water to be redirected towards pier 2 and also increased the stream velocity. In total 10 people died but only 9 bodies were recovered. The body of the 10th victim was recovered in the Mohawk River in July 1989. Other factors contributing to the failure of The Schoharie Bridge collapse are: The shallow footings used, bearing on soil, could be undermined. The foundation of pier 3 was bearing on erodible soil. The as-built footing excavations and backfill could not resist scour. Riprap protection, inspection and maintenance were inadequate. Also sheet-piles which were used in early construction were removed – if they were present scour may have been avoided. The simple spans were not redundant. Concrete piers did not have enough ductility to permit frame action. Bridge bearings allowed the spans to lift or slide off of the concrete piers. Plinth reinforcement stopped the hinge action of the plinth cracks. Conclusion The collapse of the Schoharie Bridge provided essential information on the design methods to resist scour and appropriate methods of bridge scour inspection. There are many ways in which the collapse could have been prevented. The bridge could have been supported on piles, which would have resisted scour. If this was not possible the sheet piling could have been left in place and along with using more riprap, could have helped protect the pier also. Failure could have also have been avoided by using continuous spans. This could have helped to redistribute the forces between the spans after the failure of pier 3. Another important lesson learned is that appropriate and frequent inspections be carried out on all aspects of the structure, including the underwater features of the bridge. The collapse of the Schoharie Bridge is a reminder to us that during bridge design it is not only the dead and live loads we need to consider but also the hydraulic forces which the foundations and supports are subject to. The Schoharie Bridge is also a reminder of why we need regular inspection and maintenance of the bridges which cross our waterways. References: www.wikipedia.org/wiki/Schoharie_creek Levy and Salvadori, “Why buildings fall down” 2002 Norton. ISBN 0-393-31152-X http://mdl.csa.com/partners/viewrecord.php?requester=gs&collection=TRD&recid=A 20042202158CE&q=Schoharie+bridge+collapse%2Cscour&uid=788423659&setcoo kie=yes http://www.eng.uab.edu/cee/faculty/ndelatte/case_studies_project/Schoharie.htm