Department of Civil, Structural and Environmental Engineering Trinity College Dublin The Schoharie Creek Thruway bridge collapse SS structures project Date of submission: 27th October 2006 Group 18 Cormac Carroll Laura Dowdall Patrick Heck David Steinboim The Schoharie Creek Thruway bridge collapse Introduction On April 5th, 1987, 30 years after it was constructed, two spans of the New York State Thruway bridge over the Schoharie Creek collapsed. Five vehicles fell into the flooded river, killing ten people. Structural History The Schoharie Bridge is part of the 1:90 highway connecting New York to Buffalo. It was constructed during the years 1953 and 1954. It is a 4 pier, 5 span road bridge, totalling 165 metres long. (Figure 1) 112.5' 27.75' 57' 27.75' Symmetrical about C L Deck Stringer at 8'-6" o.c. Floor Beam at approx. 20' o.c. Knee Brace Main Girder Cantilever Floor Beam Ends Bearing 7'-0" sq Column 5'-0" wide X10'-0" deep Tie Beam Column Plinth Reinforcement Plinth Footing Figure 1 - Pier Section ( after "Collapse," 1987 ) Figure 1. Pier Section In 1955, a year after completion the bridge successfully survived a 100 year flood. It is thought that this flood may have had a bearing on the collapse three decades later. In 1957 repairs were carried out on the bridge which included, adding plinth reinforcements to each of the four piers to solve the problem of vertical cracking. It was also noticed that the expansion bearings were out of plumb, the approach slabs had settled, the roadway drainage was poor and the supporting material for west embankment dry stone pavement was deficient. All the above problems were corrected by the end of 1957. On the morning of April 5, 1987 during the spring flood the bridge collapsed. Rainfall totalling 150mm along with snowmelt combined to produce an estimated 50 year flood. Collapse The collapse started with the toppling of pier three, which in turn caused the collapse of spans three and four into the flooded creek. Pier two and span two fell ninety minutes after span three dropped, and pier one and span one fell two hours later. The main cause of the collapse was the intense scouring of pier three. Scour is defined as “the removal of sediment from a streambed caused by erosive action of flowing water”. It created a scour hole approximately 3 metres deep and 9 metres of the pier was undermined. The pier fell suddenly into the hole, without any warning signs, taking span 3 and span 4 down. Sloped Embankment NORTH Riprap Sloped Embankment East Abutment West Abutment Flow PIER 1 100' SPAN1 PIER 2 110' SPAN2 PIER 4 PIER 3 120' SPAN3 110' SPAN4 100' SPAN5 Figure 2 - Schematic plan of bridge ( after "Collapse," 1987 ) Figure 2. Schematic plan of bridge (after “Collapse,” 1987) Figure 3. Effects of Scour on Bridge Piers Causes of failure The collapse of the Schoharie Bridge had many contributing factors, including; Firstly the pier foundations weren’t backfilled appropriately. The cofferdams were removed, when they should have been left in place. The riprap was too light-the specifications called for heavier stones to be used. The foundation of pier 3 was bearing on erodable soil. The bridge was also poorly maintained – the riprap was failed to be replaced when recommended. There was no redundancy in the structure. The spans were not connected together and the bridge bearings allowed horizontal and vertical movement, causing the spans to lift or slide off of the concrete piers. Later modifications of the course of the river directed water downward at the base of pier 3. Also an increase in the hydraulic gradient was caused because the Mohawk River dam downstream was set for winter conditions and was 3 metres lower than in the 1955 flood. Finally the plinth reinforcement prevented “hinge” movement, therefore resulting in sudden failure. How it could have been avoided To begin with, clear design objectives should have been set out from the start. The use of the appropriate size of riprap should have been considered, to help protect the pier. The cofferdam should have been left in place. Thorough maintenance should have been carried out following the 1977 study, in which it was noted that the riprap had been washed away and needed to be replaced. The legislation regarding diver inspections should have been implemented. The bridge could have been supported on piles, which would have resisted scour. Finally, redundancy should have been added to the structure. Conclusion In conclusion, as a result of the Schoharie Bridge collapse, many lessons have been learned and any similar future disasters can hopefully be avoided. References: Levy and Salvadori, “Why buildings fall down” 2002 Norton. ISBN 0-393-31152-X www.wikipedia.org/wiki/Schoharie_creek http://www.eng.uab.edu/cee/faculty/ndelatte/case_studies_project/Schoharie.htm http://mdl.csa.com/partners/viewrecord.php?requester=gs&collection=TRD&recid=A200 42202158CE&q=Schoharie+bridge+collapse%2Cscour&uid=788423659&setcookie=yes