L1_Cal Int/Comm Bagby/Mulhearn 7.11.05 The L1_Cal Integration and Commissioning team has a new schedule based on the Review Committee’s charge and Dan’s thoughtful explanation of the work we need to complete to meet the charge requirements. Task/Personnel/Status Daily toolbox meetings started today. L1_Cal Schedule Tasks for Review Start Date Personnel (STATUS) H: HOLD S: SCHEDULED U:UNDERWAY D:DONE Infrastructure VLDS cable labeling/bundling PFC labeling/bundling Cable plant hardware and cable installation Transition system installation (1 crate) Robust signal transmission BLS - to - ADF ADF - to - TAB TAB - to - L2/L3 TAB - to - GAB TAB - to - Caltrack GAB - to - L2/L3 GAB - to - TFW SCL - to - ADF SCL - to - GAB/TAB BLS - to - ADF TWG tests connectivity amplitude crosstalk noise floor w/ Transition system Bxing sync w/ hand pulser Pulser analysis program ADF - to - TAB Parity check ATC check Pseudo random data Fully loaded ADF crate (MODIFIERS): Status P:PROMISING July 11 July 11 July 18 July 18 Stone/Rahmi/Cosmin Stone/Rahmi/Cosmin Foglesong/Martinez/Bagby Foglesong/Martinez/Jorge/Edmunds/LB U-P U-P U-P U-P Aug 1 Edmunds/Jorge/Philippe U-P Mulhearn/Rahmi U-P Mulhearn/Mikolaj(2)/Nayeem(3)/Sabine/LB U-B Mulhearn/Cory U-P Mulhearn/Johns S Mulhearn/Mikolaj(2)/Nayeem(3) H Mulhearn/Edmunds/Cory U-N Edmunds/Philippe U-P Mulhearn H July 25 Edmunds/Jorge/Philippe S July 25 Rahmi Unalan/Cosmin Dragoiu Edmunds/Jorge/Philippe Peter Renkel S Mulhearn/Rahmi Mulhearn/Rahmi Edmunds/Mulhearn Edmunds/Jorge/Rahmi U-P U-P S S July 25 July 25 Bagby/Mulhearn 7.11.05 Notes N:NORMAL T:TROUBLE B:BAD D: labels D: labels drawings under review Hinged path panel delivery July 15 g-link error troubleshooting in progress due to g-link errors DONE?? due to g-link errors lower priority, parity works L1_Cal Schedule Tasks for Review Start Date Personnel (STATUS) H: HOLD S: SCHEDULED U:UNDERWAY D:DONE TAB - to - L3 Low BER Run w/ BOT trigger Run in conjunction w/ D0 Bxing sync w/ hand pulser Stable running for hrs Collect first data for L1_Cal Prec. R.O. Comp L1_Cal VS Prec. RO Comp. Analysis (MODIFIERS): Status P:PROMISING Nayeem/Mulhearn/Sabine/Bagby Nayeen/Mulhearn/Sabine Nayeem/Mulhearn/Sabine Edmunds/Jorge Mulhearn/Nayeem/Sabine Mulhearn/Nayeem/Sabine All H S S S H S GAB - to - TFW Test AND/OR terms to TFW Measure latency July 25 Bxing sync of And/Or terms w/ various trig cond. July 25 Check term rates at TFW w/ detector BLS I/P Aug 1 Mulhearn/Cory Edmunds/Mulhearn/Cory Edmunds/Mulhearn/Cory Edmunds/MulhearnCory U-N S S S Controls Verify hardware configuration capability Setup trig conditions w/COOR or sim COOR dial Edmunds/Nayeem(3)/Philippe Alan/Nayeem/Sabine July 11 July 11 July 18 July 18 Monitoring Demonstrate PS V/I monitoring and control Tools/displays for low-level error detection Tools/displays for high-level monitoring (trig. rates) Basic examine which unpacks data Documentation Setup and Operation Meaning of error conditions Savage/Bagby/Roe Roe U-P All U Bagby/Mulhearn 7.11.05 Notes N:NORMAL T:TROUBLE due to g-link errors BOT:Beginning Of Turn due to g-link errors trig file in progress EPICS software required expert tools shifter tools B:BAD Toolbox Meeting Bagby/Mulhearn 7.11.05 Daily 9AM working toolbox meeting in DAB1. Audio bridge available tomorrow. Weekly Schedule Bagby/Mulhearn 7.11.05 July 12 Toolbox Minutes Bagby/Mulhearn 7.11.05 Transition system reviews Stone/Green/Jorge: Cable plant drawings. Anderson/Green: Test card layout. Rahmi/Cosmin: Glenair harness construction. ADFTAB Mike/Rahmi:Successfully ran pseudo random data set from ADFTAB for 2 hours with NO parity errors verifying operation of ATC LVDS connection. Order will be placed for balance of ATCs this week. Toolbox minutes Bagby/Mulhearn 7.11.05 GABTFW Mike/Cory: Successfully downloaded and compiled GAB firmware. Verifying control lines. L2/L3 Nayeem/Sabine: Developing BOT trig file. ORC All: Goal is to obtain ORC for full ADF crate testing.