WESLEYAN U N I V E R S I T Y Facilities 170 Long Lan e M i d d l e t o wn , C o n n e c t i c u t 0 6 4 5 7 (860) 685-3476 FAX (860) 685-3101 Date: April 3, 2013 To: Bidders of Record Project: Bid Packages 5, 6, 7 Annual Major Maintenance FY 14 ADDENDUM #3 Bid / Construction Schedule Bids due: April 4, 2013 @ 1:00PM Post bid interview/bid review: April 9, 10, 2013 Selection of successful bidders: April 11, 2013 Construction Start Date: May 28, 2013 Substantial Completion Date: August 1, 2013 Project Completion Date: August 16, 2013 Housing Opens/Students Arrive on campus: August 20, 2013 SPECIAL NOTE: Addendum #3 information shall supersede the information contained in the Contract Documents This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents dated January 4, 2013 and any prior Addenda remain in full force and effect except as modified by the following, which shall have precedence over any contrary provisions in prior Documents. Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may subject the Bidder to disqualification. Alsop House; 301 High Street: Verandah & Verandah Roof Replacement: 1. Correction to the following statement: a. 5. “Unit prices to be revised to reference 2” x 6” joists. Unit price to include cost for removal and disposal of joists to be replaced and material and labor for installation of new joists.” b. Correction to read: “Unit prices to be revised to reference 2” x 10” joists. Unit price to include cost for removal and disposal of joists to be replaced and material and labor for installation of new joists.” c. Revise proposal attached and shall be uploaded to the website. Major Maintenance FY2013/2014 Project Number 2014000000 1 ADDENDUM # 3 4/3/13