Michael Abbondante Construction Management Presentation Outline Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Question & Answer Michael Abbondante Construction Management PROJECT OVERVIEW Project Overview Name: American Speech Language – Hearing National Headquarters Sustainability Systems Location: Procurement Methods Rockville, MD Function: Office Space Window Efficiency Re-design Size: 137,000 sq. ft. Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management Stories: 5 Stories above grade; 7 Total stories Construction Dates: July 1, 2006 – October 15, 2007 PROJECT OVERVIEW Project Overview Sustainability Systems Procurement Methods Project Team Owner: American Speech Language – Hearing Association Construction Manager: Davis Construction Development Team: Window Efficiency Re-design AtSite Construction Building Architect: Structural Steel Column Re-design Conclusions Boggs and Partners Architecture Structural Engineer: Cagley and Associates MEP Engineer: Q&A Michael Abbondante Construction Management Vanderweil Engineers PROJECT OVERVIEW Project Overview Relevant Background Information Sustainability Rating: Sustainability Systems LEED Silver Rating: 33 – 38 Points Procurement Method: Procurement Methods Window Efficiency Re-design Traditional: Design – Bid – Build Architectural Façade: • Three types of pre-caste concrete walls with metal panels • Glass Curtain wall using seven different types Mechanical System: Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management • (2) 200 ton chillers with condenser and evaporator • (2) Cooling Towers • Four assorted sized Air Handling Units Structural System: • Slab on Grade with C.I.P. Piers, foundation walls, grade beams • Structural steel columns used above grade Sustainability Systems Sustainability Systems Project Overview Problem: Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management • Lack of one standard sustainable building rating system • Multiple rating systems used for different reasons • Which system is most progressive for the future of sustainability Research: • Analysis and comparison of LEED and Green Globes • Industry surveys of owners and contractors on each • ASHA LEED point and Green Globes Point Comparison • University of Minnesota’s courthouse case study analysis Goals: • • Determine rating system aligned with owner’s goals Determine most progressive system to be used in the future Sustainability Systems Project Overview LEED Analysis Certification: Sustainability Systems • 26 – 69 Points Procurement Methods • 4 Levels: • Certification • Silver • Gold • Platinum Window Efficiency Re-design • Scored on: Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management • • • • • • Sustainable Sites Water Efficiency Energy and Atmosphere Materials and Resources Indoor Environmental Quality Innovation and Design Process • Most widely used system Sustainability Systems Green Globes Analysis Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Certification: • 350 – 1000 Points • 4 Levels: • 1 Globe • 2 Globes • 3 Globes • 4 Globes • Scored on: • • • • • • • Project Management: Policies and Practices Site Energy Water Resources, Building Materials, & Solid Wastes Emissions and Effluents Indoor Environment • Distribution began in 2004 by the GBI • ANSI accreditation in 2005 Michael Abbondante Construction Management Sustainability Systems Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management LEED & Green Globes Comparison 80% of Green Globes represented in LEED 85% of LEED represented in Green Globes LEED: • Popularity in industry due to history • System developed by Consensus of those in the USGBC • Vast knowledge of point system required creating a “complexity label” to the system • Points scored solely on completion of project • Can be expensive Green Globes: • • • • New system introduced to the U.S. in 2004 ANSI accredited in 2005 Online system that is considered “simple” Points awarded for not only completion but also design Sustainability Systems Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management Industry Surveys Interviews of Owners & General Contractors • LEED most popular system between both • Most common in industry • Wishing to remain competitive • Many GC’s have LEED certified individuals • Complexity of rating still a concern • Green Globes not well known • Not widely used • Worries of staying power of Green Globes • Simplicity and cost peaked interests Sustainability Systems Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management ASHA Analysis Sustainability Systems Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management ASHA Analysis Sustainability Systems Project Overview University of Minnesota Case Study Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design • LEED focuses primarily on Materials • Green Globes also focuses on “durability” of materials • Green Globes focuses on Energy • No Management or Emission Effluents for LEED scorecard Michael Abbondante Construction Management Sustainability Systems Project Overview Conclusion Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management • LEED currently controls sustainability due to popularity • Green Globes presents more points as well as a simpler system • Green Globes may allow for higher scores and ratings while being the only ANSI accredited system Procurement Methods Procurement Methods Project Overview Problem: Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management • The industry’s lack of progression involving procurement • Lack of knowledge and potential savings of Design - Build • Which projects could greatly benefit from Design - Build Research: • Analysis and comparison of Design – Bid – Build and Design – Build methods • Industry surveys of owners and contractors on each Goals: • Determine procurement method aligned with owner’s goals • Will Design – Build make a strong influence in the future? Procurement Methods Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management Traditional & Design – Build Comparison Traditional: • • • • • Most commonly used system Allows owner involvement in design Separates all aspects of construction Simplifies bid awarding Easily understood Design - Build: • • • • Allows GC to become involved in the design phase Can allow for less change orders and mistakes during construction Hurries schedule Owners feel a loss of control in design phase Procurement Methods Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management Traditional & Design – Case Study Comparison Construction Management Fundamentals by Richard Mayo: • Low Bid regulations are firmly entrenched in most government systems for the purpose of promoting fairness • It is easy to justify the selection of a low bidder • Contractors understand the system • There is always resistance to change DBIA Project Analysis: • • • • • • Savings in unit cost of at least 6.1% Construction speed at least 12% faster Overall project delivery at least 35.5% faster Cost growth at least 3.5% less Schedule growth at least 11.4% less Quality equal or better Sustainability Systems Project Overview Industry Surveys Sustainability Systems Interviews of Owners & General Contractors • Owners • Prefer the traditional method Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management • • • • • Owners wish to have an impact on design Understanding by all parties involved Government Restrictions Lack of confidence in Design – Build Savings3 Belief Design – Build allows for GC mark up • General Contractors • Prefer Design – Build; but are at mercy of owners • Would allow for less change orders • improving schedule and costs • GMP allows project savings for both the owner and GC Procurement Methods Project Overview Sustainability Systems Procurement Methods Conclusion • Procurement • Depends on project • Speed • Cost • Owner • ASHA • Inexperienced Owner Window Efficiency Re-design • Non – profit Organization • Cost highly important Structural Steel Column Re-design • Back rent costs • Schedule speed crucial Conclusions • Follow Design – Build Procurement Q&A Michael Abbondante Construction Management Window Efficiency Re-design Window Efficiency Re-design Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Problem: • The energy absorbent windows on the curtain wall are single low energy windows • With a more efficient glass energy may be saved improving long term costs over up front costs • A higher LEED rating may be reached with a more efficient system Research: • EQuest analysis of different windows and their overall effect on energy consumption • R.S. Means and industry analysis of new material costs Goals: • Determine if the energy savings of a more efficient window outweighs the initial costs of the materials • Can more LEED points be attained with the new system? Q&A Michael Abbondante Construction Management Window Efficiency Re-design Project Overview EQuest Window Analysis Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Single Low E Michael Abbondante Construction Management Triple Low E Window Efficiency Re-design Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management Industry Cost Analysis Window Efficiency Re-design Project Overview Conclusion Energy vs. Cost Analysis Sustainability Systems • Triple Low Energy windows • Preserve 5% electrical energy but are 1.5 x more expensive Procurement Methods • LEED • 15% energy increase required for addition of 1 point • 20% energy increase required for addition of 2 points Window Efficiency Re-design Final Conclusion Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management • • • The low energy coating is sufficient Initial costs are extremely high Unless the entire mechanical system were redesigned LEED points could not be scored Structural Steel Column Re-design Structural Steel Column Re-design Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management Problem: • The D.C. metro area is known for its C.I.P. construction • In order to increase schedule speed steel columns were used on above grade levels • Concrete may increase the schedule but will lower initial costs Research: • pcaColumn analysis of equivalent concrete columns to replace the steel columns • ICE estimation of new column costs • Newly estimated schedule based upon C.I.P. Columns Goals: • • • Determine the overall savings of converting to C.I.P. Determine schedule and impact of paying back rent Finalize which method would be more cost effective Structural Steel Column Re-design pcaColumn Analysis Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management Structural Steel Column Re-design Cost Analysis Project Overview Assumptions: Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management Steel: 1” Mineral Fire Proofing Concrete: 4000 psi Square Columns Rebar in Corners Structural Steel Column Re-design Schedule Analysis Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management Structural Steel Column Re-design Project Overview Conclusion Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management • Overall cost of concrete is cheaper than that of steel columns • If back rent of former building is less than $50,000 concrete columns may have been an option to pursue Conclusions Conclusions Project Overview Sustainability Systems Sustainability Systems: • Green Globes is an outstanding system that with the growth of knowledge and popularity may become the official rating system • LEED however controls the market and with “competition” always important it may maintain its overwhelming popularity Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management Procurement Methods: • Owners prefer control, and the ability to affect design while having a simple method that everyone can understand • Design – Build presents many financial and scheduling opportunities, but it will take greater knowledge and use if it is ever going to be popular with owners Conclusions Project Overview Sustainability Systems Window Efficiency Re-design: • Although windows may conserve energy on a project initial costs must always be considered • The initial costs for all of the windows presented are too great for the future energy conservation. While LEED points cannot even be affected by the new systems Procurement Methods Structural Steel Column Re-design: Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management • The columns may present a longer schedule however the initial savings are tremendous • If the project could afford the 66 day delay then perhaps a concrete system would have been economical Conclusions Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management Acknowledgements • The Pennsylvania State University Department of Architectural Engineering • Industry Professionals especially those at: • Davis Construction • Barton – Malow Construction • Fellow Students and Friends • My Family Questions? Project Overview Sustainability Systems Procurement Methods Window Efficiency Re-design Structural Steel Column Re-design Conclusions Q&A Michael Abbondante Construction Management