PowerPoint Presentation (PowerPoint Based)

advertisement
Clemson University’s
Advance Material Research Laboratory
David Anderson
Mechanical Option
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
Building Background
Project Team
Owner:
Architecture Firm:
Contractor:
Landscape Architect:
Interior Designer:
$18.5 Million
Clemson University
IDC Architects
Manhattan Construction
Arbor Engineering
IDC Architects
Completed July 2004
Design-Bid-Build
First LEED Certified Facility
In South Carolina
LEED SILVER
Photo from Google Earth
Photo from Google Earth
Location: Anderson, South Carolina
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
Building Background
Location: Anderson, South Carolina
Occupant: Clemson University
Size: 111, 270 sq. ft.
Occupancy:
Offices
Research Laboratories
Clean Rooms
Conferencing
Laboratory Support
Offices
Shared Spaces/Circulation
Laboratories
Support/Services
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
Existing Conditions
Electrical:
Existing Conditions
Structural:
•(1) 2500kVA Transformer
•(5) 30-112 kVa Transformers
•Steel Construction
•300 kW Diesel Fired Stand-By Generator
•Concrete Slabs
Lighting:
•24” x 48” Fluorescent Fixtures
•T8 and T5 Lamps
•Quad Compact Fluorescents
•Ground: 5” Slab On Grade
•4x4 Welded Wire Fabric
•#4 Bars In Pits and Recesses
•Elevated Floors: 2-1/2” Slab
•1-1/2” Deck
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
Existing Conditions
Mechanical:
•(15) AHU’s
•(3) serve VAV Boxes
Existing Conditions
Mechanical:
•(2) Gas Fired Boilers
•3,348 MBH each
•(4) MAH’s
•(2) Cooling Towers
•375 Ton, 1,125 gpm
•(3) Chillers
•266.6 Ton, 750 gpm
•(1) Electric Boiler
•4,094 MBH
•(3) Energy Recovery Coils
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
Mechanical Redesign
Goals and Objectives: Optimize Ventilation and
Reduce Energy
Proposal:
•Replace CAV/VAV system
•Incorporate Dedicated Outdoor Air
System (DOAS) with Integrated Active
Chilled Beams
Design:
•Total Heat Recovery Incorporated
•Sensible Load Met by Chilled Beams
Mechanical Redesign
Justification:
•Smaller Equipment Sizes,
Reduction of Costs
•Life Cycle Cost Reduced
•More Economical for
Laboratories
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS
Existing Conditions:
Anderson, South Carolina
Outdoor Design DB:
93°F Summer
19°F Winter
Indoor Design DB:
RH:
DPT:
74°F
50%
54°F
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
DOAS
DOAS Configuration
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
DOAS
Chilled Beams
Chilled Beams
Selection of Chilled Beams
Enthalpy Wheel Selection:
Xetex AIRotor 2500
Contamination?
Purged Enthalpy Wheel
•Maintance
Building’s Total Sensible Load:
Qtotal•Ventilation
= 1,139,294 Btu/h
Sensible Load Achieved by DOAS
•Piping
QDOAS= 97,824 Btu/h
•Acoustics
Sensible Load To
Be Met by Chilled Beams
QBeams= 1,041,469 Btu/h
•Coordination
788 Active Chilled Beams
-TROX—DID300@76 W/m2 (7.06 W/ft2)
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
DOAS/Chilled Beams
DOAS/Chilled Beams
AHU Resizing
Annual Cost and Equipment Break Down
Existing
Components
Clemson
AMRL
($)
Proposed
Components
Clemson
AMRL
($)
AHU #
Original
SA(cfm)
Design
OA(cfm)
DOAS Resized OA (cfm)
1
4000
1800
594
Cooling
925,442
Cooling
229,434
2
4500
1800
594
Heating
7,019
Heating
3,354
3
5700
1800
594
4
5200
1800
33%
Pumps
88,394
Pumps
169,355
5
6300
6300
2079
Cooling Tower Fans
Cooling Tower Fans
115,958
6
5800
5550
1832
HVAC Sub-Total
3,332,418
HVAC Sub-Total
587,444
7
5000
400
132
Lights
2,389,184
Lights
2,378,390
Electric Equipment
32% Reduction
3,016,649
Electric Equipment
3,003,020
Non-HVAC SubTotal
5,405,833
Non-HVAC SubTotal
5,381,410
Grand Total
8,738,251
Grand Total
5,968,853
Totals
85000
31150
594
Reduction
10280
DOAS Ventilation Air Based On 20 scfm/person
Air System Fans
1,379,405
932,159
Air System Fans
69,342
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
ASHRAE Standard 90.1-2004
•Office Buildings
Lighting Redesign
Conclusions:
•High Efficient T5
•Less Wattage
•Outputs Similar
Clemson University’s AMRL
•1.32—1.95 W/ sq. ft.
20% Reduction
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
Proposal:
•Remove 40 Watt T8
•Install 32 Watt T5
Proposed:
1.06—1.56 W/sq.ft
Design
Lumens/Lamp
Lumens/L’aire
Watts
Existing
2850
8550
41,155
Proposed
2950
8850
34,243
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
Construction Effects
Mechanical System First Costs:
Existing System:
•Total Cost: $3,024,000
Construction Effects
•Schedule Impacts
•Labor
•Ductwork
Proposed System:
•Beam Cost:
$2,764,000
•Equipment/Labor: $2,894,160
•Total Cost:
$5,658,000
$2,634,000 Increase in First Cost
•System Sizes
•Pumps
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
Conclusions
Acknowledgements
Overall Costs:
•My Family and Friends
System
Existing
CAV/VAV
Proposed
DOAS/
Chilled Beams
Initial Cost
$3,024,000
$5,658,000
47%
Yearly Cost
$8,738,251
$5,968,853
32%
Total First
Year Cost
$11,762,251
$11,626,853
•Faculty and Staff of AE
•Clemson University
•IDC Architects
Clemson University’s
Advance Material Research Laboratory
Presentation Agenda
Building Background
Existing Conditions
Mechanical Redesign
DOAS/Chilled Beams
Lighting Redesign
Construction Effects
Conclusions
Acknowledgements
Questions
Download