NEOMED Research and Graduate Education Building + Comparative Medical Unit Expansion the Northeast Ohio Medical University Campus Rootstown, Ohio Image © <www.neomed.edu> Image © <www.crystaldiagnostics.com> Sam Bridwell, BAE Mechanical Option Advisor: Dr. Freihaut Table of Contents • Introduction • Project Overview Project Overview Construction Management Breadth Existing Systems Proposal Mechanical Depth Electrical Breadth Existing Infrastructure Decision Factors Utility Data Analysis Interconnection Laws and Standards Background Water-side HVAC Proposal Components Screening Utility Interconnect Design Research • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Air-side HVAC Configuration Analyses Design Conditions System Operation Design Objectives Further Expansion Potential Benefits Final Recomendations Table of Contents Project Location • Introduction • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Image © <http://upload.wikimedia.org/wikipedia/commons/thumb/b/b2/Utica_Shale_assessment__01.jpg/220px-Utica_Shale_assessment_-_01.jpg> Utica Shale Region Image © ASHRAE Std. 90.1.5.1.4 Figure B1-1 5A Cool and Moist Table of Contents Campus Map • Introduction • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Image © <http://www.neomed.edu/about/pdfs/neomed-campus-map.pdf> Table of Contents Phase 1 Research and Graduate Education Building • Introduction • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System Image © <http://www.ruhlin.com/highered-neomedrgecmu> • Final Recommendations • Conclusion/Acknowledgements Image © <http://www.neomed.edu/about/pdfs/neomed-campus-map.pdf> Table of Contents Phase 1 Comparative Medical Unit Expansion • Introduction • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System Image © Scheeser Buckley Mayfield LLC • Final Recommendations • Conclusion/Acknowledgements REDI-Zone Image © Scheeser Buckley Mayfield LLC Image © <http://www.neomed.edu/about/pdfs/neomed-campus-map.pdf> Table of Contents The Village • Introduction • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Image © <www.neomed.edu> Image © <http://www.neomed.edu/about/pdfs/neomed-campus-map.pdf> Table of Contents Phase 2 • Introduction • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Image © <http://www.ruhlin.com/highered-neomedhwmec> NEOMED Education and Wellness Center Image © <http://www.neomed.edu/about/pdfs/neomed-campus-map.pdf> Image © <http://www.ruhlin.com/highered-neomedhwmec> Table of Contents Existing Infrastructure • Introduction • Project Overview • Existing Systems • • • • • Existing Infrastructure Water-side HVAC Air-side HVAC Design Conditions Design Objectives Main HW/CW Plant • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System High-Pressure Steam Plant • Final Recommendations • Conclusion/Acknowledgements Image © <http://www.neomed.edu/about/pdfs/neomed-campus-map.pdf> Table of Contents RGE Standalone Utilities • Introduction • Project Overview • Existing Systems • • • • • Existing Infrastructure Water-side HVAC Air-side HVAC Design Conditions Design Objectives • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability Image © Scheeser Buckley Mayfield LLC • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Image © Scheeser Buckley Mayfield LLC Table of Contents RGE Standalone Utilities • Introduction • Project Overview • Existing Systems • • • • • Existing Infrastructure Water-side HVAC Air-side HVAC Design Conditions Design Objectives • Proposal • Depth: Cogeneration Plant Implementation Image © Scheeser Buckley Mayfield LLC • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Image © Scheeser Buckley Mayfield LLC Table of Contents • Introduction • Project Overview Custom RTU’s AHU-1 and AHU-2 50,000 CFM 100% OA • Existing Systems • • • • • Existing Infrastructure Water-side HVAC Air-side HVAC Design Conditions Design Objectives • Proposal • Depth: Cogeneration Plant Implementation AHU-4 8,400 CFM • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements AHU-3 28,000 CFM Table of Contents Custom RTU’s • Introduction • Project Overview AHU-5 85,000 CFM 100% OA • Existing Systems • • • • • Existing Infrastructure Water-side HVAC Air-side HVAC Design Conditions Design Objectives • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Image © Scheeser Buckley Mayfield LLC Design Conditions Table of Contents • Introduction • Project Overview • Existing Systems • • • • • Existing Infrastructure Water-side HVAC Air-side HVAC Design Conditions Design Objectives • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability Image © BR+A Consulting Engineers Image © BR+A Consulting Engineers • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Image © BR+A Consulting Engineers Table of Contents Design Objectives • Introduction • Project Overview • Existing Systems • • • • • Top-Notch Quality of Facility Existing Infrastructure Water-side HVAC Air-side HVAC Design Conditions Design Objectives • Proposal 24/7 Availability for Staff and Researchers Image © <http://www.transactbookkeeping.co.uk/images/reliability.jpg> Image © <http://microinnova.com> • Depth: Cogeneration Plant Implementation Independence and Reliability of Building Systems • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System Flexibility for Future Changes and Campus Expansion • Final Recommendations • Conclusion/Acknowledgements Image © <http://davegreenwald.com> Image © <http://www.laborcosting.com> Table of Contents Considerations Made • Introduction • Project Overview • Existing Systems High Air Turnover, Need for Energy Recovery Multi-Phase, Multiple Bids Complex Controls and Metering • Proposal • Decision Factors • Proposal Components Distance to Existing Utilities Strict Technical Requirements Environmental Impact Ease of Maintenance • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability Goal of Long-Term Growth and Development Strict Project Delivery Timeline Cost Impact Efficiency • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Atypical Building Systems Built to Benefit not only Students and Researchers but Entire Regional Community Table of Contents • Introduction • Project Overview Proposed Alternatives Breadth 1: Power Interconnect & Black Start Capability Depth: Cogeneration Plant Implementation • Existing Systems Breadth 2: Alternate Project Delivery System • Proposal • Decision Factors • Proposal Components • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Image © <http://www-tc.pbs.org> Image © <http://www.fhwa.dot.gov> Image © <http://www.epa.gov> Campus Utility Data Table of Contents Electric Demand by Month • Introduction Kilowatt Hrs • Project Overview • Existing Systems • Proposal M onth Dollars $/kwh Temperature Year 823,121 $62,575.46 $0.076 74° Thermal/Electric Demand Ratio By Month • Depth: Cogeneration Plant Implementation • • • • • Utility Data Analysis Screening Configuration Analyses System Operation Further Expansion • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements 1,800 1,600 1,400 1,200 1,000 kW 800 600 400 200 0 Electric Price by Year $0.090 $0.080 $0.070 $0.060 $/kWh $0.050 $0.040 $0.030 $0.020 $0.010 3.50 3.00 2.50 2.00 1.50 1.00 0.50 0.00 $0.000 FY 03 FY 04 FY 05 FY 06 FY 07 FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 FY 14 Month Month Gas Price by Year Thermal Demand by Month Month 12,000 $12.00 10,000 $10.00 8,000 $8.00 MBH 6,000 $/MMBTU $6.00 4,000 2,000 $4.00 0 $2.00 $0.00 FY 03 FY 04 FY 05 FY 06 FY 07 FY 08 FY 09 FY 10 FY 11 FY 12 FY 13 FY 14 Month Month Table of Contents System Selection Site Data Collection • Introduction • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • • • • • Utility Data Analysis Screening Configuration Analyses System Operation Further Expansion • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements 1. How many hours per year does the facility operate? (hours) Or, ask about operating schedule - day/week, hours/day 2. What is your average power demand during operation? (kW), or 3. How much electricity do you use in a year, kWh? 4. What is your facility's primary thermal load (i.e., DHW, steam/HW space heating, process steam, cooling, etc.) 5. What is your average thermal demand? (MMBtu/hr), or 6. How much fuel (gas/oil/etc) do you use in a year? (MMBtu/yr, Therms/yr, etc.) 7. What is your current fuel price? ($/MMBtu) 8. How much do you pay for fuel annually? (Dollars/yr) 9. What are the CHP Fuel Costs? ($/MMBtu) 10. What is your average electricity price? ($/kWh) 11. How much do you pay for electricity annually? (Dollars/yr) 12. What is the efficiency of your existing boiler(s)/thermal equipment? (decimal) 13. What is the efficiency of your existing chillers? (kWh/ton) CHP System Net CHP Power, kW 1,084 CHP System Specs C CHP Electric Efficiency, % (HHV) 36.8% CHP system specs C CHP Thermal Output, Btu/kWh 3,854 CHP system specs C CHP Thermal Output, MMBtu/hr CHP Power to Heat Ratio 0.89 CHP system specs C Calculated based on CHP power output and thermal output CHP Availability, % 98% 90 to 98% Incremental O&M Costs, $/kWh Thermal Utilization, % Total Installed Costs, $/kW 4.2 $0.019 90% $2,335 CHP system specs C Amount of available thermal captured and used - typically 80 to 100% CHP system specs C 8,760 1,084 9,369,859 Space Heating 6.01 51,922 $7.850 $405,770 $7.850 $0.077 $712,509 0.90 0.60 GE Jenbacher Reciprocating Engine RGE HW Boiler RGE Chiller Based on Recip Engines Based on Gas Turbines Thermal Output, MMBtu/hr 0.34 2.64 3.85 10.67 24.47 52.62 76.42 141.33 Net Capacity, kW 50 600 1,000 3,300 5,000 10,000 20,000 45,000 System A B C D E F G H Heat Rate, Btu/kWh 12,637 9,896 9,264 8,454 11,807 12,482 10,265 9,488 Net Electrical Efficiency, % 27.0% 34.5% 36.8% 40.4% 28.9% 27.3% 33.2% 36.0% 6,700 4,392 3,854 3,233 4,893 5,262 3,821 3,141 Thermal Output, Btu/kWh 0.34 2.64 3.85 10.67 24.47 52.62 76.42 141.33 Thermal Output, MMBtu/hr 80% 85% 85% 85% 100% 100% 100% 100% Thermal Output for Cooling (single effect) 50% 50% 50% 50% 90% 90% 90% 90% Thermal Output for Cooling (double effect) 80% 78% 79% 70% 69% 70% 69% Total Efficiency, % Incremental O&M, $/kWh $0.0240 $0.0210 $0.0190 $0.0126 $0.0123 $0.0120 $0.0093 $0.0092 Total Installed Costs, $/kW $2,900 $2,737 $2,335 $1,917 $2,080 $1,976 $1,518 $1,248 Image © <http://site.ge-energy.com/prod_serv/products/recip_engines/en/type3.htm> Table of Contents System Sizing • Introduction • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • • • • • Utility Data Analysis Screening Configuration Analyses System Operation Further Expansion • Breadth 1: Power Interconnect and Black Start Capability $/kwh Yearly Average $/MMBTU Spark Gap kW MBH λD Temperature FY 14 $0.069 $4.51 $15.69 1565 1800 1600 1400 1200 1000 kW 800 600 400 200 0 September, 1697 December, 1435 • Conclusion/Acknowledgements 80 12000 70 60 8000 Degrees F 40 6000 2014 4000 2013 2000 Month 2014 2013 August, 2882 2014 Cooling Months July August September 1,689 1,627 1,697 254 193 262 5087 3858 5240 424 322 437 avg. (non-cooling) kW avg. (cooling) kW Avg. Cooling MBH Avg. Cooling Tons 30 2014 20 2013 10 0 Month Month June total kW cooling power (kW) cooling load (MBH) cooling load (Ton) 50 September, 4815 0 • Breadth 2: Alternate Project Delivery System • Final Recommendations 14000 10000 MBH 8418 1.58 0 Temperature Thermal Demand for Sizing Electric Demand for Sizing 1,435 236 4,728 394 Table of Contents Configurations • Introduction • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • • • • • Utility Data Analysis Screening Configuration Analyses System Operation Further Expansion Year-Round Cooling Heating Cooling Heating • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Image © Cleaver Brooks Product Literature Image © Trane Product Literature Image © AERCO Product Literature Makeup Table of Contents Configuration Analysis • Introduction • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • • • • • Utility Data Analysis Screening Configuration Analyses System Operation Further Expansion • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Plant Configuration Results Table of Contents Cogeneration System Schematic 1772 MBH 3544 MBH Hi-pressure (60 PSI) Steam Load Exhaust • Introduction Condensate From Load • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • • • • • Once-Through HRSG 1747 MBH 206 gpm 1969 MBH Generator Utility Data Analysis Screening Configuration Analyses System Operation Further Expansion • Breadth 1: Power Interconnect and Black Start Capability Low Water Flow Shutdown • Conclusion/Acknowledgements Pressure Control Valve Steam Separator L Exhaust 1772 MBH L Low Water Level Shutdown Once-Through HRSG 1747 MBH 206 gpm 1969 MBH Generator 3145 MBH Excess Steam Valve Lo-pressure (10 PSI) Steam Load Condensate From Load Image © <http://www.davegreenwald.com> Water Level Control • Breadth 2: Alternate Project Delivery System • Final Recommendations High-Temperature Water Steam System 10 psig Maximum Relief Pressure Valve Engine Engine Once-Trough Steam Generator Air Eliminator Circulating Pump Low Water Flow Shutdown Circulating Pump Existing Cooling Tower Load Balancing Condensor Condensate Tank Condensate Pump Image © <http://inproheat.com/sites/files/imagecache/product_nodeview/products/pic-onceThrough-zz_0.jpg> Table of Contents Further Expansion • Introduction • Project Overview • Generator Sizing Accommodates Expansion • Fit out of 4th Floor • AHU Humidifiers • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • • • • • Utility Data Analysis Screening Configuration Analyses System Operation Further Expansion • Breadth 1: Power Interconnect and Black Start Capability • Locate Additional Plant Capacity in NEW Building • Lap Pool • Hydrotherapy Pool • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Image © <http://www.neomed.edu/about/pdfs/neomed-campus-map.pdf> Table of Contents State Interconnect Laws and Standards • Introduction • Project Overview • Existing Systems Ohio has very “DG-Friendly” Policies • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Interconnect Laws and Standards • Utility Interconnect Design • Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations Disconnect Switch at discretion of Utility No Generation System Size Limit for Interconnection Net Metering mandated for all IOU’s; No Generation System Size Limit • Conclusion/Acknowledgements Image © EPA Clean Energy-Environment Guide to Action Image © EPA Clean Energy-Environment Guide to Action Table of Contents Generation and Utility Parallel Operation Schematic • Introduction • Project Overview T-1C 1000 kVA 12.47KV Primary to 480/277V, 3p, 4W Secondary • Existing Systems • Proposal T-1R 2000 kVA 12.47KV Primary to 480/277V, 3p, 4W Secondary Overcurrent Relay Overcurrent Relay Voltage Regulator Ground Overvoltage Relay G1 848kW 480V Voltage Regulator • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Interconnect Laws and Standards • Utility Interconnect Design • Black Start Capability N.C. 1600A Undervoltage/ Overvoltage Relay Lockout-Trip • Breadth 2: Alternate Project Delivery System Under-Frequency Relay Current Unbalance Relay Directional Overcurrent Relay Overcurrent Relay Automatic Synchronizer N.C. 4000A Undervoltage/ Overvoltage Relay Lockout-Trip Under-Frequency Relay Current Unbalance Relay Directional Overcurrent Relay Overcurrent Relay • Conclusion/Acknowledgements CMU Switchboard RGE Swithboard 3000 A 3000 A Automatic Synchronizer Undervoltage/ Under-Frequency Overvoltage Relay Relay Overcurrent Relay Current Unbalance Relay Current Unbalance Relay Reverse Power Relay Lockout-Trip G2 848kW 480V Overcurrent Relay Govenor Loss of Excitation Relay • Final Recommendations 3000 A 3000 A Undervoltage/ Under-Frequency Overvoltage Relay Relay Automatic Synchronizer 1600 A Ground Overvoltage Relay Reverse Power Relay 1600 A Lockout-Trip Govenor Loss of Excitation Relay Automatic Synchronizer Table of Contents Project Delivery Methods Multiple-Prime • Introduction • Project Overview • Existing Systems Owner NEOMED • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Background • Research • Potential Benefits Construction Manager Ruhlin MEP Engineer BR+A MEP Engineer Scheeser Buckley Mayfield Architect Ellenzweig X 22 Interior Design Schumacher Design • Final Recommendations • Conclusion/Acknowledgements Architect/Interiors TC Architects Civil/Structural Engineer The GPD Group Trade Contractor - X 22 Table of Contents Project Delivery Methods Single-Prime/GC Single-Prime/GC Construction Manager @ Risk • Introduction • Project Overview Owner NEOMED • Existing Systems Owner NEOMED Owner NEOMED • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability General Contractor Ruhlin MEP Engineer BR+A Architect Ellenzweig MEP Engineer BR+A • Final Recommendations • Conclusion/Acknowledgements MEP Engineer Scheeser Buckley Mayfield X 22 MEP Engineer Scheeser Buckley Mayfield Interior Design Schumacher Design MEP Engineer Scheeser Buckley Mayfield Civil/Structural Engineer The GPD Group Trade Contractor - X 22 Architect/ Interiors TC Architects Construction Manager Ruhlin Interior Design Schumacher Design Other Consultants - Interior Design Schumacher Design Architect/ Interiors TC Architects Architect/ Interiors TC Architects Architect Ellenzweig Architect Ellenzweig • Breadth 2: Alternate Project Delivery System • Background • Research • Potential Benefits MEP Engineer BR+A Construction Manager Ruhlin Civil/Structural Engineer The GPD Group Trade Contractor - Civil/Structural Engineer The GPD Group X 22 Trade Contractor - X 22 Table of Contents Research Results U.S. Building Projects (351) • Introduction Univariate Results • Project Overview 23% Construction Management at Risk • Existing Systems • Proposal 33% Design-Bid-Build 44% Design Build • • • U.S. Building Projects (351) • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability 28% Light Industrial 8% Multistory Dwelling • Breadth 2: Alternate Project Delivery System 24% Simple Office 18% Complex Office 5% Heavy Industrial 17% High Technology 50% CMR and DB delivered on-time or early 50% DBB more than 4% late CMR,DB Quality > DBB Quality Multivariate Results U.S. Building Projects (351) • Background • Research • Potential Benefits • • 28% AREA < 5,000 m2 • Final Recommendations 33% 5,000 m2 < AREA < 15,000 m2 • Conclusion/Acknowledgements 25% 15,000 m2 < AREA < 35,000 m2 13% 35,000 m2 < AREA • U.S. Building Projects (351) Image © Journal of Construction Engineering and Management Nov/Dec 1998 • 22% COST < $600/m2 26% $600/m2 < COST < $1,000/m2 19% $1,000/m2 < COST < $1,400/m2 13% $1,400/m2 < COST < $1,800/m2 19% $1,800/m2 < COST DB < CMR DBB Delivery Method significant influence on construction speed, some influence on total delivery speed Delivery Method single biggest influence on schedule growth Project Delivery Method biggest influence on every metric overall, matched only by Facility Type Table of Contents Project Benefits Schedule Slippage • Introduction • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Background • Research • Potential Benefits • Final Recommendations • Conclusion/Acknowledgements Images © the Ruhlin Group, NEOMED University Table of Contents Project Benefits • Introduction Disputes • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Background • Research • Potential Benefits • Final Recommendations • Conclusion/Acknowledgements Images © the Ruhlin Group, NEOMED University Table of Contents • Introduction • Project Overview • Existing Systems • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Final Recommendations Based On Analyses Breadth 1: Power Interconnect & Black Start Capability Depth: Cogeneration Plant Implementation Breadth 2: Alternate Project Delivery System Table of Contents • Introduction Acknowledgements Chris Schoonover Principal - Scheeser Buckley Mayfield, LLC • Project Overview Brian Ault • Existing Systems Blaine Wyckoff Jim Freihaut Mechanical Engineer - Scheeser Buckley Mayfield, LLC Director of Campus Operations- Northeast Ohio Medical University Asst. Dir. of Campus Operations- Northeast Ohio Medical University Professor of Architectural Engineering – Penn State Rob Leicht Asst. Professor of Architectural Engineering – Penn State Tim Warren President - JDB Engineering, Inc. Tom Leary Executive VP/DOP - JDB Engineering, Inc. Ari Tinkoff Managing Director/Principal - BR+A Consulting Engineers Scott Walthour Managing Principal – Arium AE Chris Elgin Structural Engineer - GPD Group Diet Mt. Dew Carbonated Soft Drink – PepsiCo Inc. Steam Internet-based gaming platform – Valve Corporation • Proposal • Depth: Cogeneration Plant Implementation • Breadth 1: Power Interconnect and Black Start Capability • Breadth 2: Alternate Project Delivery System • Final Recommendations • Conclusion/Acknowledgements Jim Rankin