Cancer Institute Penn State Milton S. Hershey Medical Center Chris Voros

advertisement
Cancer Institute
Penn State Milton S. Hershey
Medical Center
Hershey, Pennsylvania
Chris Voros
Construction Management
April 17, 2007
April 17, 2007
Chris Voros
Construction Management
Presentation Topics





Project Overview
 Building summary, project team members, and construction sequence
Structural Breadth-Foundation Redesign
 Intermediate, Geopier-reinforced Mat Slab vs. Micropile Foundation System
 30% Weight- 15% Value Engineering, 10% Schedule Reduction, 5% Constructability
Electrical Breadth- Utility Redesign and Energy Impact
 Utility rerouting plan & energy loss study for PSHMC’s East Campus
 30% Weight- 15% Constructability, 10% Value Engineering, 5% Schedule Reduction
Depth Study- Industry Influences on Subcontractor Markups
 Identify factors that impact a subcontractor’s “multiplier” value
 40% Weight- 40% Research
Conclusion, Acknowledgements & Questions
April 17, 2007
Chris Voros
Construction Management
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--30% Weight-15% VE
10% SCH
5% CR
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Structural Breadth
Study:
Intermediate, Geopier-reinforced
Mat Slab versus Deep Micropile
Foundation System
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--30% Weight-15% VE
10% SCH
5% CR
PSHMC Cancer Institute
Hershey, PA
Project Overview
Background & Problem
Statement
Structural BreadthFoundation
Redesign
•
•
Central PA- Karst Topography
Parking Garage Complications
– Piles averaged 20’ deeper
than 70’ predicted average
– Change Order of $600,000
(33% Increase)
– Schedule delayed 36 days
(49% Inflation)
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
Proposal
•
•
•
Avoid possible subsurface issues with finding competent rock
Utilize soil stabilization techniques that will enable a shallow
foundation- Geopier Rammed Aggregate Piers (RAPs)
Break building footprint into three zones for analysis:
– Primary (1), Radiotherapy Vaults (2), Shell Space (3)
April 17, 2007
Chris Voros
Construction Management
--30% Weight-15% VE
10% SCH
5% CR
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
EXISTING PLAN SPECS:
• 387 Micropiles @ 65’ each (8” dia.)
–
–
–
•
•
•
Zone 1 = 233
Zone 2 = 70
Zone 3 = 84
Column Piers & Grade Beams
Slab on Grade (5” to 7”)
36” Slab for Radiotherapy Vaults
Depth StudyPROPOSED LAYOUT SPECS:
Building Respect:
•
916 Geopier RAPs @ 15’ each (30” dia.)
Industry Influences
– Zone 1 = 419
on Subcontractor
Markups
– Zone 2 = 228
Conclusion &
Questions
•
– Zone 3 = 269
Mat Slab Thickness– Zone 1 = 2’-9”
– Zone 2 = 4’-6”
– Zone 3 = 1’-3”
April 17, 2007
Chris Voros
Construction Management
--30% Weight-15% VE
10% SCH
5% CR
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
SCHEDULE ANALYSIS
-Proposed System saves
13% on foundation
Installation sequence
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
2 Week
Reduction
April 17, 2007
Chris Voros
Construction Management
--30% Weight-15% VE
10% SCH
5% CR
PSHMC Cancer Institute
Hershey, PA
CONSTRUCTABILITY ANALYSIS
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
-Existing System Costs• Piles
• Pile Caps, Col. Piers, & SOG
-Proposed System Costs• Geopier RAPs
• Mat Slab
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
VE CONSIDERATIONS:
• Avoid Subsurface Issues
• Maintain Settlement Tolerances
• Reduce ICRA Impact
• Consider for Children’s Hospital
April 17, 2007
Chris Voros
Construction Management
--30% Weight-15% CR
10% VE
5% SCH
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Electrical Breadth
Study:
High Voltage Utility Relocation
Plan and Distribution Systems Loss
Analysis
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--30% Weight-15% CR
10% VE
5% SCH
PSHMC Cancer Institute
Hershey, PA
Background & Problem Statement
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Four 15kV Feeders service PSHMC:
• Hospital A & B – main hospital
complex (incl. CI and Children’s)
•
Master Plan Goal:
• Carry main ductbank from
substation across Centerview Drive
and split feeders
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
•
Markups
Conclusion &
Questions
Loop A & B – support facilities
(ASB, PG, UPC, Student Housing)
Separate A and B lines into
designated manholes to ease
construction and maintenance
Proposal Goal:
Phase HV installation for Parking
Garage, Cancer Institute and
Children’s Hospital at same time
April 17, 2007
Chris Voros
Construction Management
--30% Weight-15% CR
10% VE
5% SCH
PSHMC Cancer Institute
Hershey, PA
EXISTING LAYOUT SPECS:
Project Overview
Structural BreadthFoundation
Redesign
•
•
•
•
(7) new manholes
3,111LF of duct bank
Loop Feeders- 669’; Hospital Feeders- 832’
3 Road Crossings
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
PROPOSED LAYOUT SPECS:
•
•
•
•
(4) new manholes; (1) Handhole/Pullbox
2,988 LF of duct bank
Loop Feeders- 607’; Hospital Feeders- 777’
2 Road Crossings
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--35% Weight-15% CR
10% VE
5% SCH
PSHMC Cancer Institute
Hershey, PA
Distribution System Line Loss Evaluation
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Sample Calculations:
Voltage Drop (Volts) = [Avg. Amps] * [Resistance]
Average Losses (Watts) = [Avg. Amps]^2 * [Resistance]
Average Losses/ year (kWh) = [Loss Factor] * [Peak Losses] *[8760 hrs/yr]
[1000 W per kW]
Annual Cost of Losses ($) = [$0.0877/kWh] * [Avg. Losses]
(Resistance = 3 Phases @ 0.0222 Ohms/ 1000 ft each)
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--30% Weight-15% CR
10% VE
5% SCH
PSHMC Cancer Institute
Hershey, PA
CONSTRUCTABILITY & COST ANALYSIS
Project Overview
Structural BreadthFoundation
Redesign
-Cost Breakdown• Duct banks (incl. excavation, concrete, backfill)
• PVC Conduit (5” typical)
• Wiring–
3 Phase, 4 Wire Okonite Copper Conductors – 500
kcmil Feeders and #4/0 Ground Conductor
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
OTHER CONSIDERATIONS:
• Phase PG utility installation at same time as CI
•
Consolidate construction costs and overall site impact of layout
•
Construction Savings, Proposed System (incl. EMHs) =
$54,699
•
Yearly Energy Savings, Proposed System = $225 per year
April 17, 2007
Chris Voros
Construction Management
--40% Weight-40% Research
PSHMC Cancer Institute
Hershey, PA
Project Overview
Building Respect:
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
Industry Influences
on Subcontractor Markups
April 17, 2007
Chris Voros
Construction Management
--40% Weight-40% Research
PSHMC Cancer Institute
Hershey, PA
Project Overview

Goal

Structural BreadthFoundation
Redesign

Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
Approach


Improve Construction Manager and General Contractor
Relationships with their Subcontractors
Identify factors that go into a subcontractor’s “multiplier”the value added above allowable bid package markup
Methodology



Two surveys, one tailored to CM/GC professionals and one
to Subcontractors
Create a “Multiplier Matrix” that predicts a BP multiplier
based on a given set of conditions
Compare and Contrast results from both surveys with respect
to perceived markup determinants
April 17, 2007
Chris Voros
Construction Management
--40% Weight-40% Research
PSHMC Cancer Institute
Hershey, PA
Survey Contents
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
CM/GC
• Anonymous
• Mailed Packet
• Qualitative/ Written
Responses
• Question Base:
– Bid Package vs.
Contract Markups
– Determinants of a BP
Markup
– Company SelfAssessment
April 17, 2007
Subcontractors
•
•
•
•
Anonymous
Online Survey
Quantitative & Qualitative
Question Base:
– Part 1• 10 Questions/Scenarios
• Select impact on multiplier
based on a scale from -3
(decrease) to +3 (increase)
– Part 2• 3 Case Study Analyses
• Assign a markup/multiplier
and provide reasoning
Chris Voros
Construction Management
--40% Weight-40% Research
PSHMC Cancer Institute
Hershey, PA
Project Overview
CM/GC Survey Results
•
Contract Markups: 10% to 20% (incl. OH&P)
Structural BreadthFoundation
Redesign
•
Bid Package Markups: -2% to 8%
– Multiplier factor
Electrical BreadthUtility Redesign
and Energy Impact
•
Self- Assessment
– 90-100% Returning Subs
– 70-90% Repeat Clients
•
Markup Determinants
– Majority are objective/quantifiable
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--40% Weight-40% Research
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Subcontractor Survey Results- Part 1
Relationship-oriented Factors
• Past successes with CM/GC, incl. some of team personnel
• Bad history with company, but none of personnel
• Bad history with CM/GC personnel
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--40% Weight-40% Research
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Subcontractor Survey Results- Part 1
Business-related Factors
• AIA Contract is vague with respect to markup procedures
• CM/GC bid-shops on a regular basis to trim bid to owner
• CM/GC uses “nickel-and-diming” practices on project CO’s
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--40% Weight-40% Research
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Subcontractor Survey Results- Part 1
Regional Factors
• CM/GC is a start-up company
• CM/GC is national firm, but new to region
• Project at bid is a “target of opportunity” (one-shot deal)
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--40% Weight-40% Research
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Subcontractor Survey Results- Part 1
Multiplier Matrix
• Take average value of applicable scenarios and use
Multiplier Impact Scale to determine magnitude of expected
markup
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--40% Weight-40% Research
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Subcontractor Survey Results- Part 2
Case Study #1: Alpha
Construction Company
-Dominant CM/GC moving into
region
Electrical BreadthUtility Redesign
and Energy Impact
Alpha Survey Average = 3.31%
Case Study #2: Beta
Depth StudyContractors
Building Respect:
Industry Influences -Start-up company of
on Subcontractor
experienced principals
Markups
Conclusion &
Questions
Case Study #3: Choice
Management
-Respected CM, by owners and
subs alike
April 17, 2007
Beta Survey Average = 1.6%
Choice Survey Average = 0.1%
Chris Voros
Construction Management
--40% Weight-40% Research
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Survey Comparison:
•
•
•
•
Key deciding factor is Regional Economics (supply vs.
demand, work availability, competition)
CM/GC professionals take an objective view, placing less
emphasis on business relationships
Subcontractors value reputations CM/GC/A/E above other
factors, contradicting CM/GC survey responses
CM/GC companies need to value & actively maintain their
sub relationships in order to minimize BP markups
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
PSHMC Cancer Institute
Hershey, PA
Conclusions & Recommendations
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
Foundation Redesign:
• Consider for Children’s Hospital if Cancer Institute
experiences subsurface issues of same magnitude as
Parking Garage project
High Voltage Utility Relocation:
• Implement proposed layout, which improves on
construction and operation of high voltage distribution
for PSHMC’s new facilities (PG, CI, & Children’s)
Industry Influences on Subcontractor Markups:
• Maintain positive business relationships to improve
company reputation and build respect among
subcontractors
April 17, 2007
Chris Voros
Construction Management
PSHMC Cancer Institute
Hershey, PA
Acknowledgements:
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
-AE and Construction Management Faculty:
Dr. David R. Riley
Dr. Michael J. Horman
Dr. John I. Messner
Professor Parfitt
Professor Holland
-The Penn State Milton S. Hershey Medical
Center
Dick Aradine
Mike Lekey
Centerline Associates
Chris Leyenberger
Array Healthcare Facilities Solutions
Mike Connor
-Gilbane Building Company, Hershey Project
Team:
Dennis Vance
Don Hergenreder
Patrick Hardister
Tom Gutherman
Andrew Notarfrancesco
Marianne Jones-Pichler
John Vicanovick
Dan Munn
April 17, 2007
-Dick Harris, PSU Office of Physical Plant
-Shad Hoover, CMT Labs
-John Masland, ARM Group, Inc.
-Kord Wissman, Geopier Foundation
Company, Inc.
-GeoStructures, Inc:
Mike Perlow
Eric Hilberath
Ed O’Malley
-Davis Construction:
Bill Moyer
David Argentieri
-All the survey participants (anonymous)
…and to My Family and Friends- Thanks!
Questions?
Chris Voros
Construction Management
--30% Weight-15% VE
10% SCH
5% CR
PSHMC Cancer Institute
Hershey, PA
Project Overview
Research Progression
•
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
•
•
Investigate alternative foundation
systems
Compare and contrast each
Research most feasible solution
further– Geopier Rammed Aggregate
Piers (RAPs)
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--30% Weight-15% VE
10% SCH
5% CR
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--30% Weight-15% VE
10% SCH
5% CR
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
--30% Weight-15% VE
10% SCH
5% CR
PSHMC Cancer Institute
Hershey, PA
Project Overview
Structural BreadthFoundation
Redesign
Electrical BreadthUtility Redesign
and Energy Impact
Depth StudyBuilding Respect:
Industry Influences
on Subcontractor
Markups
Conclusion &
Questions
April 17, 2007
Chris Voros
Construction Management
Download