Butler Memorial Hospital Butler Memorial Hospital New Inpatient Tower Butler, PA Matthew Geary Mechanical Option Advisor: Dr. William Bahnfleth Butler Memorial Hospital Introduction Building Statistics •Location: Butler, PA •Size: 200,000 sqft Inpatient Addition •Occupancy: Hospital, Surgery, Recovery, & CCU •Cost: 93 Million •Levels: 2 Below Grade, 5 Above Grade •Construction: September 2008 – July 2010 N Aerial View of Property Matthew Geary | Mechanical •Delivery: Design-Bid-Build *Note: The floor above the 3rd floor is the 5th, not the 4th.floor Introduction Butler Memorial Hospital Project Team •Owner: Butler Healthcare Providers •Construction Manager: Turner Construction •Mechanical Contractor: Limbach Facility Services Typical Patient’s Room Matthew Geary | Mechanical North-West Facade Chapel Typical Operating Room •MEP Engineer: HGA Butler Memorial Hospital Building Design Architecture •Exterior Facade •Aluminum & glass curtainwall •Red brick veneer •Roofing Nurses’ Station •Mechanically fastened thermoplastic membrane •Interior •Contemporary vibe •Patient rooms along perimeter •Grand entryway atrium Matthew Geary | Mechanical Entryway Atrium Main Entrance Butler Memorial Hospital Building Design Structural System •Foundation •Concrete caissons & grade beams •Poured concrete foundation walls •Structural Steel System •Wide flange structural steel beams and columns •Columns laterally braced with K frame braces •Composite metal deck with shear studs •3-1/2” concrete topping Exterior Walls Poured Foundation Walls •Wall Construction •6” steel studs, gypsum board on both sides •2” rigid insulation, face brick Matthew Geary | Mechanical Caisson Drilling Structural Steel Electrical System Building Design Butler Memorial Hospital •Entry Service •Feeds from existing hospital •2,500 KVA transformer in mechanical room •3 Phase 480Y/277 V distribution •Electrical Distribution •Electrical rooms on each level deliver 208Y/120V & 480Y/277V •3 Ф 480 V •Heavy equipment, motors, & fans •1 Ф 277 V •Fluorescent lighting Switchboard •1 Ф 120 V •Incandescents, halogens, receptacles, & office equipment •Emergency Power •(2) 800 KW Caterpillar generators Matthew Geary | Mechanical Emergency Generator Original Mechanical System Butler Memorial Hospital Mechanical Overview •Variable air volume w/ reheat •33% outdoor air •(3) rooftop air handlers supply majority of spaces •Loop design, provides redundancy •Served by (2) centrifugal chillers Centrifugal Chiller Primary Rooftop Air-Handler •(2) smaller rooftop air handlers supply OR •Independent of primary system •Served by (1) scroll chiller •(2) 7,200 MBH gas-fired boilers •Radiant panels along perimeter of patient rooms Matthew Geary | Mechanical Cooling Towers Gas Fired Boiler Original Mechanical System Butler Memorial Hospital Air-Side Overview •Primary Rooftop Air Handlers (AHU-1, 2 & 3) Primary Operating Rooms •(3) 62,000 CFM Air Handlers •Serves majority of New Inpatient Tower Mechanical Rooms •Operating Room Rooftop Air Handlers (AHU-4 & 5) •(2) 18,500 CFM Air Handlers •Serves operating rooms and support space Primary Rooftop Air-Handler •Mechanical Room Air Handlers ( AHU-6, 7, & 8) •Serve specialty mechanical rooms Air Handler Diagram Matthew Geary | Mechanical **Note: AHU-8 not shown in diagram •Vary from 4,000 – 5,000 CFM Original Mechanical System Butler Memorial Hospital Chilled Water •Primary Loop (CH-1 & 2) •(2) 400 ton water cooled centrifugal chillers •Serves primary AHU’s 1-3 & Mech. AHU’s 6-8 •Serves as back-up for operating room AHU’s •(2) Primary pumps •(2) VSD Secondary pumps •Operating Rooms Loop (CH-3) 400 Ton Centrifugal Chiller •(1) 120 ton air-cooled scroll chiller •Serves operating rooms and support space (AHU-4 & 5) •Supply CHW temperature at 34°F •(1) Primary pump Matthew Geary | Mechanical Chilled Water Diagram Original Mechanical System Butler Memorial Hospital Condenser Water •(1) Packaged double cell Marley cooling tower •Serves centrifugal chillers (CH-1 & CH-2) •(2) constant speed pumps •(2) VFD radial cooling tower fans Double Cell Marley Cooling Tower Condenser Water Diagram Matthew Geary | Mechanical Original Mechanical System Butler Memorial Hospital Heating Water •(2) 7,200 MBH Gas-fired boilers •Primary Loop •(2) primary pumps •3 way valve controls flow rate and temperature of supply water to secondary loop •Secondary Loop Gas-Fired Boiler •(2) VSD secondary pumps distribute to loads •Distributes to AHU-1:8, terminal boxes, duct heaters, & radiant ceiling panels •Inline booster pumps at coils in AHU’s Matthew Geary | Mechanical Heating Water Diagram Original Mechanical System Butler Memorial Hospital Heating Water •(2) 7,200 MBH Gas-fired boilers 3 Way Control Valve •Primary Loop •(2) primary pumps •3 way valve controls flow rate and temperature of supply water to secondary loop •Secondary Loop Gas-Fired Boiler •(2) VSD secondary pumps distribute to loads •Distributes to AHU-1:8, terminal boxes, duct heaters, & radiant ceiling panels •Inline booster pumps at coils in AHU’s Matthew Geary | Mechanical Heating Water Diagram Butler Memorial Hospital Original Mechanical System Energy Consumption •Receptacles and Lighting: constant loads, unaltered •Fan energy is largest consumer of HVAC energy followed by cooling energy •Improvement Ideas •Reduce fan energy by utilizing DOAS •Reduce outside air •Water side free cooling Matthew Geary | Mechanical Butler Memorial Hospital Mechanical Redesign Goals •Reduce Energy & Life Cycle Costs •Increase Indoor Air Quality •Maintain Redundancy & Reliability •Decrease Carbon Footprint Matthew Geary | Mechanical Butler Memorial Hospital Mechanical Redesign Main Features •Dedicated Outdoor Air System •Semco Pinnacle Unit •Figure 1 •Active Chilled Beams •Flaktwoods/Semco Series IQIC & IQCA •Figure 2 Fig.1 Fig. 2 •Water Side Free Cooling •Increased efficiency with chilled beams •Figure 3 Matthew Geary | Mechanical Fig. 3 Butler Memorial Hospital Mechanical Redesign Advantages •Decreased Energy Costs •Less airflow, less fan energy •Water side economizer reduces chiller hours •Increased Reliability •Constant ventilation ensures high IAQ •Simple throttling valves vs. complicated terminal box controls •No moving parts in chilled beam, easier maintenance •Reduced First Cost •Chillers, Ductwork, Terminal Boxes & Air Handlers Matthew Geary | Mechanical Butler Memorial Hospital Mechanical Redesign Design Loads •Cooling Loads •Primary Air Handler Load – 178 tons •Chilled Beam Load – 138 tons •Heating Loads •Primary Air Handler Load – 3,105 Mbh •Chilled Beam Load – 2,255 Mbh •Ventilation Rate – 38,500 CFM Matthew Geary | Mechanical **Note: Loads are for Primary System only; OR loads not included Mechanical Redesign Butler Memorial Hospital •Air Side •Eliminated (3) primary rooftop AHU •Added (1) 42,000 CFM DOAS AHU •Water Side •Eliminated (2) 400 ton centrifugal chillers •Eliminated original primary and secondary pumps •Added (3) 180 ton screw chillers •Added (3) primary and (3) secondary pumps •Added plate & frame heat exchanger •Added chilled beams Matthew Geary | Mechanical *Note: Secondary system supplying operating rooms was unaffected Butler Memorial Hospital Mechanical Redesign Normal Operation Primary AHU Loop Primary Chilled Beam Loop Matthew Geary | Mechanical Operating Room AHU Loop Butler Memorial Hospital Mechanical Redesign Free Cooling Application Primary AHU Loop Primary Chilled Beam Loop Matthew Geary | Mechanical Operating Room AHU Loop Butler Memorial Hospital Mechanical Redesign Chiller 1 (or 2) Fails Primary AHU Loop Primary Chilled Beam Loop Matthew Geary | Mechanical Operating Room AHU Loop Butler Memorial Hospital Mechanical Redesign PCHWP-1 Fails Primary AHU Loop Primary Chilled Beam Loop Matthew Geary | Mechanical Operating Room AHU Loop Butler Memorial Hospital Mechanical Redesign SCHWP-1 also Fails PCHWP-4 & SCHWP-3 can supply either loop Primary AHU Loop Primary Chilled Beam Loop Matthew Geary | Mechanical Operating Room AHU Loop Butler Memorial Hospital Mechanical Redesign Secondary Loop Fails Primary/Secondary AHU Loop Primary Chilled Beam Loop Matthew Geary | Mechanical Butler Memorial Hospital Mechanical Redesign Energy Comparison Primary/Secondary AHU Loop Annual Energy Savings = 3,245 MMBtu Matthew Geary | Mechanical Butler Memorial Hospital Mechanical Redesign Energy Cost Savings Annual Cost Savings = $36,140.00 Matthew Geary | Mechanical Butler Memorial Hospital Matthew Geary | Mechanical Mechanical Redesign Reduced Ductwork Butler Memorial Hospital Matthew Geary | Mechanical Mechanical Redesign Reduced Ductwork Butler Memorial Hospital Mechanical Redesign Chilled Water Distribution Piping •Chilled beams will need chilled water supply •Design Criteria • < 1” – Type L drawn copper • > 1” – Schedule 40 steel •Sizing Criteria • < 2” – Max velocity 4 ft/s • > 2” – Max head 4’/100’ piping Matthew Geary | Mechanical Butler Memorial Hospital Mechanical Redesign Chilled Water Distribution Piping Matthew Geary | Mechanical Butler Memorial Hospital Matthew Geary | Mechanical Mechanical Redesign First Cost Summary Net Savings = $276,906.00 Butler Memorial Hospital Mechanical Redesign Life Cycle Cost Analysis First Cost Savings = $276,906.00 Annual Energy Savings = $36,140 Matthew Geary | Mechanical Butler Memorial Hospital Structural Breadth Proposed Redesign •Elimination of AHU-1 & AHU-3 •Reduced roof dead load in these areas •Resize structural steel •AHU-2 Replaced by DOAS Pinnacle Unit •Located in same area to avoid ductwork penetration issues •Comparable dimensions and weight Matthew Geary | Mechanical Butler Memorial Hospital Matthew Geary | Mechanical Structural Breadth AHU-1 Beam Redesign Butler Memorial Hospital Matthew Geary | Mechanical Structural Breadth AHU-3 Beam Redesign Butler Memorial Hospital Matthew Geary | Mechanical Structural Breadth DOAS Air handler Location Steel Summary **Note: Cost data taken from RS Means Butler Memorial Hospital Matthew Geary | Mechanical Electrical Breadth Electrical Savings = 426 kVA Comparison Summary Butler Memorial Hospital Summary Goals Attained •Reduce Energy & Operation Costs •Saved $277,000 First Costs •Saved $36,000 Operational Costs •Increase Indoor Air Quality •DOAS ensures appropriate amounts of outdoor air •Maintain Redundancy & Reliability •Designed with inherent redundancy in all components •Decrease Carbon Footprint •Decreased emissions of CO2, SO2 & NOx Matthew Geary | Mechanical Butler Memorial Hospital Summary MAE Incorporation •AE 558 Central Heating • Calculating Payback Period •AE 557 Central Cooling •Water-Side Free Cooling •Centralized vs. Distributed Pumping •AE 542 Indoor Air Quality •Improvement of IAQ Matthew Geary | Mechanical Acknowledgments •Butler Healthcare Providers •Turner Construction – Megan Corrie •HGA – Tim Andersen & Michael Woodson •HF Lenz – David Miller •Limbach Facility Services – John Hilf •Semco – Matt Pemberton, Randy Phillips, & Thomas Kitchen ` Butler Memorial Hospital QUESTIONS? Matthew Geary | Mechanical Butler Memorial Hospital Alternate Design First Cost Summary ` Matthew Geary | Mechanical Net Savings = $60,057.00 Butler Memorial Hospital Mechanical Redesign Semco Pinnacle Application Guide Matthew Geary | Mechanical Semco Pinnacle Unit Butler Memorial Hospital Mechanical Redesign Semco Pinnacle Application Guide Matthew Geary | Mechanical Semco Pinnacle Unit Butler Memorial Hospital Mechanical Redesign Semco Pinnacle Application Guide Matthew Geary | Mechanical Semco Pinnacle Unit Butler Memorial Hospital Mechanical Redesign Semco Pinnacle Application Guide Matthew Geary | Mechanical Semco Pinnacle Unit