Transmission Capital Project Updates Transmission Expansion Plan • Sigurd to Red Butte 345 kV line in-service May, 2015 • Permitting activities continue on key segments including Gateway West, Gateway South, Oquirrh – Terminal, and Boardman to Hemingway 2 Main Grid System Reinforcement Projects • On-going reinforcement projects in all states. Projects include: – NERC TPL improvements (N-1, N-1-1) • • • • Reconductoring for higher capacity New substations Substation transformer capacity increases New circuit breakers and bus configurations • Reliability / Voltage improvements – Capacitor banks – Reactors – Synchronous condenser 3 Main Grid System Reinforcement Projects Cont. • Key On-going or Upcoming Projects Include: – – – – – – – – – Goshen Area Load Tripping RAS (ID) Goshen-Jefferson-State Line 161 kV Reconductor (ID) Casper Sub Install 230-115 kV 250 MVA Transformer (WY) Standpipe Substation New 230 kV Sub (WY) Ben Lomond to Parrish 138 kV Line (UT) Union Gap – Add 230-115 kV Capacity (WA) Vantage – Pomona Heights 230 kV line (WA) Sams Valley 500-230 kV New Sub (OR) Snow Goose 500-230 kV New Sub (OR) 4 Generation Interconnection & Customer Driven Projects • PacifiCorp is obligated to interconnect generation customers • The transmission facility additions for interconnections shall maintain or improve the level of system reliability • Qualifying Facility generation interconnection requests continue to be a significant number of the requests moving forward • Network Customer Projects are being constructed to meet actual and studied/forecasted load requirements 5 Generation Interconnection & Customer Driven Projects Cont. • Key On-going or Upcoming Projects Include: – Pavant-Flowell-Fillmore 138 kV Rebuild (UT) – Hurricane West (Purgatory Flat substation) New Delivery Point (UT) – St. George Sub Install 345-138 kV Transformer (UT) – Wallula to McNary 230 kV Line (WA/OR) 6 Local Transmission Reinforcement Projects • Local Transmission and Substation system reinforcement projects are on-going in all states – Projects are identified in the Five Year Area Planning studies – Actual loading levels + forecasted load determines timing of the projects – Projects include: • Substation transformer capacity additions • New substations and load transfers • Transmission line reinforcements to increase capacity • Voltage conversions 7