• Big Tent Meeting, November 19, 2008, Portland Updated:2012-08-23 16:04 CS

advertisement
Transmission Project Sponsors
Big Tent Meeting
November 19, 2008
Portland, Oregon
Welcome
Darrell Gerrard - PacifiCorp
Order 2004 Sensitive
1
Order 2004 Sensitive
Big Tent Meeting
November 19, 2008
Embassy Suites Hotel – Portland, Oregon
9:00 a.m. – 12:00 noon
Agenda
9:00
Welcome – Darrell Gerrard
Background from July 2008 Session
Goals Supporting Coordination
9:15
TCWG Work Plan- What has been accomplished
since July 2008 – Ben Morris
9:30
Individual Project Updates (By Project Sponsor)
11:30
Next Steps – Darrell Gerrard
11:45
Inputs and Commentary – Sponsor Panel
2
Order 2004 Sensitive
Goals Supporting Coordination

Develop ideas to ensure robust proposals brought to sub-regional &
regional engagement

Avoid duplication of study work and facilities constructed

Ensure efficient use of resources, siting, permitting, environmental

Regional view of transmission requirements necessary long term

NW Transmission Hub concept formulated

Optimize current expansion plans from commercial as well as technical
views

Open and transparent FERC Order 890 compliant planning

Improved certainty of project Phase 2 ratings expected via WECC process
3
Order 2004 Sensitive
Background

Purpose: status update for several proposed projects significant to
Northwest

All projects currently in or will be in WECC Phase 1 Rating Process

Began January 2008 with Transmission Coordinated Work Group (TCWG)

Goal is submission of Phase 1 reports in Q4

Sponsors are reasonably on schedule

Each project sponsor will be submitting an individual Project Phase 1 Rating
report to WECC

Expectations are that projects enter Phase 2 relatively close together in the
fourth quarter of 2008 or Q1 2009
4
WECC Phase 1 and Phase 2
Coordination
Ben Morris - PG&E Consultant
Order 2004 Sensitive
5
Order 2004 Sensitive
Coordination

A number of project sponsors are planning construction in the
Northwest in the 2010-2015 period and the study work is being
coordinated. Their projects have the following characteristics:


Currently in (or soon to be in) WECC Phase 1 Rating process
Planning to submit their Comprehensive Progress Reports in 4Q, 2008 and
1Q, 2009
 Agree to use a common study methodology

Projects that meet such characteristics include:












Walla Walla-McNary (PacifiCorp)
Hemingway-Captain Jack (PacifiCorp)
West of McNary Project (BPA)
I-5 Corridor Reinforcement BPA)
Idaho-Northwest Project (Idaho Power and Others)
Southern Crossing Project (PGE)
Canada-Northwest-California (CNC) Project (PG&E and Others)
CNC Project - Devil’s Gap Interconnection (Avista)
Dry Creek-Coyote (Avista)
Northern Lights Project (TransCanada)
West Coast Cable (Sea Breeze)
The project sponsors have formed the Transmission Coordination Work
Group (TCWG).
6
Order 2004 Sensitive
New Transmission Projects Being Planned in Coordination
Planned Operation: 2010 – 2015
To Edmonton/Heartland
Selkirk Sub
BPA
West of McNary Generation
Integration Project
Spokane Area
Sub and
Converter
NorthernLights
DC
Sea Breeze
WCC
PG&E et. al
CNC Project
Station X
BPA
I-5 Corridor
Station Z
McNary
Big Eddy
PGE
Southern Crossing
PG&E, et. al
CNC Project
PacifiCorp
Walla Walla
NEO
Station
Idaho Power
Hemingway Boardman
Legend:
PG&E (AC or DC)
PGE (500kV)
Capt.
Jack
Idaho Power (500kV)
Avista Corp (230kV)
BPA (500 kV)
NorthernLights (DC)
Sea Breeze WCC (DC)
PacifiCorp/Idaho
Gateway West
Hemingway
PacifiCorp
(500 or 230kV)
PacifiCorp
Hemingway Capt.
Jack
Midpoint
Borah
To SF
Bay Area
To SF
Bay Area
7
Order 2004 Sensitive
Transmission Projects in Regional Planning and/or Phase 1
Planned Operation: 2010 – 2015
Sponsor/
Participants
Project Name
PacifiCorp
Walla Walla to McNary
PacifiCorp
Online
Date
Voltage
Capacity
WECC Milestones *
2010
Single 230kV AC
400 MW
RP Initiated – 11/2007
Ph 1 Initiated -- 10/2008
Hemingway to Capt. Jack
(part of Gateway West)
2014
Single 500kV AC
1,500 MW
RP Initiated – 11/2007
BPA
West of McNary Generation
Integration Project
20122013
Single 500kV AC
and 500kV Sub/
Single 500kV AC
1,500 MW
each
RP Completed – 02/2008
Ph 1 Pending
BPA
I-5 Corridor Reinforcement
Project
2015
500kV Sub/Single
500kV AC
1,500 MW
RP Completed – 03/2008
Ph 1 Pending
Idaho Power and
Others
Hemingway-Boardman
2013
Single 500kV AC
1,300 MW
RP Completed – 05/2008
Ph 1 Initiated – 02/2008
PGE
Southern Crossing
20132014
Single 500kV AC
1,500 MW
RP submitted -- 10/2008
Ph 1 submitted – 10/2008
PG&E and Others
Canada – Northwest California (CNC)
2015
Double 500kV AC
and HV DC
3,000 MW
RP Completed – 11/2008
Ph 1 Initiated – 10/2007
Avista Corp
Avista Interconnection to CNC
- Spokane Area Upgrades
2015
500kV Sub and
local 230kV
upgrades
500 MW
RP Submitted – 11/2007
Ph 1 Initiated – 11/2007
Avista Corp
Dry Creek -Coyote 230 kV
2015
230 kV
500 MW
RP and Ph 1 Initiated in 01/08
TransCanada
NorthernLights
2015
+/- 500 kV DC
2,000 MW
RP Completed – 01/2008
Ph 1 Initiated – 01/2008
Sea Breeze
West Coast Cable (WCC)
2015
+/- 600 kV DC
1,600 MW
Ph 1 - Initiated –
*
RP = WECC Regional Planning Process
Ph 1 = WECC Rating Process: Phase 1
12/2006
8
Order 2004 Sensitive
Transmission Coordination Work Group (TCWG)

Group formed to

Establish consistent assumptions/methods for Project Sponsors
 Provide feedback on the Project Sponsor study work
 Explore opportunities for synergies among projects

Activities

Develop consistent assumptions, study scenarios, base cases

Identify and establish consistent assumptions for the analysis of Hubs

Review and comment on Project Sponsor study plans, assumptions,
study results and Comprehensive Progress Report
 Monthly meetings through study completion


Met monthly since January 2008 (next meeting: December 9 conference
call)
Participation – Approximately 30 meeting attendees and more than
80 on the correspondence list


Representatives from Phase 1 projects
Other stakeholders with interest in providing feedback on technical
studies
 Other parties interested in the development of the projects
9
Order 2004 Sensitive
System Parameters

2015 HS Regional Gen/Loads
Region
Alberta
Gen
(MW)
Demand
(MW)
9433
9535
BC
11576
8341
PNW
31818
26305
Idaho
4904
3771
Montana
3252
1843
25479
28521
No. Ca

Projects coordinated within the
TCWG are designed to access
resources in BC, Alberta,
Montana, the PNW and
Northeastern CA/NV
+3000
MW
+2000
MW
+4500
MW
+3000
MW
+1500
MW
10
Order 2004 Sensitive
Project Sponsor/TCWG
Phase 1 Accomplishments

Developed Study Plan

Developed Study Assumptions

Identified the location and capacity of new incremental generation to
be accessed with the proposed projects
 Listed major paths to be monitored and their target flows
 Identified the projects in the WECC Phase II Rating process to be
modeled in the cases
 Established set of critical contingencies to be studied

Developed Base Cases:

Seasonal cases:





2015 Heavy Summer (North-South Flow)
2017 Heavy Winter (South-North Flow)
2011 Light Spring (East-West Flow)
2010 Light Autumn (East-West Flow)
Reviewed and adjusted Load and Generation balance as necessary
11
Order 2004 Sensitive
Project Sponsor/TCWG
Phase 1 Accomplishments (cont’d)

Conducted Studies without and with Project

Power flow
 Transient Stability
 Voltage Stability

A number of transmission projects converge in northeast
Oregon


Evaluated the technical merits of substation where these projects
could potentially terminate
New Substation – NEO Station


Preliminary NEO Station arrangements have been developed and will
evolve during WECC Phase 2
Communicated Study Progress and Results

Each of the Projects has presented the results of their nonsimultaneous rating study work at the TCWG Meeting
 Participated in joint Big Tent meetings
12
Order 2004 Sensitive
TCWG Phase 2 Coordination

Project Sponsors have agreed that TCWG will function as the Phase
2 Project Review Group

No need to have separate review teams for individual projects
 Separate Phase 2 meetings can be held at the Project Sponsors’
discretion

Entities who are not part of the TCWG and have interest in any of
the TCWG projects should contact the Project Sponsor to become
part of TCWG

Coordination Activities


Consistent assumptions
Discuss study results involving system interactions
13
Order 2004 Sensitive
TCWG Phase 2 Coordination

Meetings

Regular monthly meetings



January 21
February 18
TCWG is envisioned to function until the last project completes Phase 2
14
Walla Walla – Mc Nary
Tom Tjoelker - PacifiCorp
Order 2004 Sensitive
Project Overview

Conceptual Major Project Elements
 Walla Walla – Wallula 230 kV Line
 Wallula – Mc Nary 230 kV Line

Potential Bidirectional rating:
 400 MW East-to-West
 400 MW West-to-East

Project Operating Date: Late 2010

Project Website:
MAP
www.pacificpower.net/energygateway.
16
Order 2004 Sensitive
Objectives

Provides up to 400 MW of new transmission capacity both East-toWest and West-to-East

Improves transmission reliability to Wallula area

Provides transmission capacity for new wind resources in Walla
Walla area

Facilitates future interconnection of other regional transmission
projects such as proposed by Avista
17
Order 2004 Sensitive
Conceptual One-Line
18
Order 2004 Sensitive
WECC PHASE Rating Process

Complete Phase I Proposed Rating Report – Feb. 2009

Initiate Phase II Planned Rating - Apr. 2009

Complete Phase II Planned Rating – June 2009
19
Order 2004 Sensitive
Project Update (since July, 2008)

Regional Planning Report issued October 6, 2008

Phase I WECC Rating Process initiated October 9, 2008

Single-circuit performs well

Working with Avista & BPA on potential regional transmission
projects

Double-circuit may be built as part of joint project with Avista

RAS needed for higher wind penetrations
20
Order 2004 Sensitive
Project implementation Schedule

WECC rating studies
2008 - 2009

Permitting and Land acquisition
2008 - 2009

Engineering
2008 - 2009

Construction
Late 2009

Operations
Late 2010
21
Hemingway – Capt. Jack
Tom Tjoelker - PacifiCorp
Order 2004 Sensitive
Project Overview

Conceptual Major Project Elements


Hemingway – Capt. Jack 500 kV
Line
Potential Bidirectional rating:
 1500 MW East-to-West
 1500 MW West-to-East

Project Operating Date: 2014

Project Website:
MAP
www.pacificpower.net/energygateway
.
23
Order 2004 Sensitive
CONCEPTUAL ONE-LINE
HEMINGWAY – CAPT JACK
24
Order 2004 Sensitive
Objectives

Support West side load growth

Address renewable portfolio standards

Potentially facilitates future interconnection of other regional
transmission projects
25
Order 2004 Sensitive
Project implementation Schedule

WECC rating studies
2009

Permitting and Land acquisition
2010 - 2011

Engineering
2010 - 2011

Construction
Late 2013

Operations
Late 2014
26
West of McNary Generation Integration Project
(WOMGIP)
Kyle Kohne - BPA
27
Order 2004 Sensitive
Project Overview




Major Elements

Part 1: Construct a new McNary –
John Day 500 kV transmission line
(~79 mi)

Part 2: Construct a new 500 kV
substation (“Station Z”) near
Goldendale, WA, and a 500 kV line
from Station Z to BPA’s Big Eddy
substation near The Dalles, OR. (~30
mi)
Planned Rating:

West of McNary: 4500MW

West of Slatt: 5500MW

West of John Day: 3450MW
Proposed Project Operating Date

Part 1: 2012

Part 2: 2013
Project Website:

http://www.columbiagrid.org/WMRPoverview.cfm
28
Order 2004 Sensitive
Objectives

Enable BPA to meet Network customer load growth from new
resources and serve point-to-point transmission requests across
multiple congested east-west transmission paths along the
Washington – Oregon border.

Enable BPA to interconnect additional wind generation in Eastern
Washington and Eastern Oregon.

Increase system reliability to serve Portland area load.
29
Order 2004 Sensitive
Project Update (since July 2008)

Regional Planning Completed (February 2008)

BPA plans to initiate the WECC Phase One Rating Process in
January 2009.

Funds approved to begin preliminary design and NEPA work.

Public Involvement effort reinitiated for Part 1 (McNary – John Day).

Both parts of the project will be included in BPA’s Network Open
Season (NOS) process.
30
Order 2004 Sensitive
Project Implementation Schedule


McNary-John Day 500-kV

Project will take approximately 3.5 years from start to energization

Environmental Process / Design – 0.5 years

Material Procurement / Construction – Additional 3 years
Big Eddy-Station Z 500-kV (includes Station Z)

Project will take approximately 5 years from start to energization

Environmental Process / Design – 2 years

Material Procurement / Construction – Additional 3 years
31
I-5 Corridor Reinforcement
Kyle Kohne - BPA
32
Order 2004 Sensitive
Project Overview


Major Project Elements

Construct a new 500 kV Substation
near Castle Rock, WA.

Develop a 500 kV yard at the existing
Troutdale Substation in Troutdale,
OR.

Construct a new 500 kV transmission
line between these substations
(approximately 70 miles).

Alternative: Construct new 500 kV
line between new Castle Rock
substation and Pearl substation
instead
Planned Rating


Proposed Operating Date


South of Allston: Approximately 1300
MW increase
2015
Project Website:

http://www.columbiagrid.org/I5CRPoverview.cfm
33
Order 2004 Sensitive
Objectives

Relieve congestion along the I-5 corridor transmission path south of
Paul Substation.

Enable BPA to meet Network customer load growth from new
resources and serve point-to-point transmission service requests
which impact this path.

Enable BPA to interconnect additional new resources which are
being planned along the I-5 Corridor.

Maintain reliable service to growing loads in Portland and vicinity.

Reduce dependence on existing RAS while maintaining
transmission system reliability.
34
Order 2004 Sensitive
Project Update (since July 2008)

Regional Planning Completed (March 2008)

BPA plans to initiate the WECC Phase One Rating Process in
February 2009.

Funds approved to begin preliminary design and NEPA work.

This project will be included in BPA’s Network Open Season (NOS)
process.
35
Order 2004 Sensitive
Project Implementation Schedule

I-5 Corridor Reinforcement Project

Project will take approximately 6 years from start to energization for
either alternative

Environmental Process / Design – 3 years

Material Procurement / Construction – Additional 3 years
36
Order 2004 Sensitive
BPA Network Open Season Update

Cluster Study results submitted to BPA Marketing on 10/31/08

153 PTSA’s submitted totaling 6,410 MW of transmission requests

WOMGIP and I-5 Corridor Reinforcement are part of the portfolio of
projects for meeting the requests

BPA will host Customer Forum on 11/20/08 to present cluster study
results (http://www.transmission.bpa.gov/customer_forums/)

Commercial Infrastructure Analysis to be completed by 12/31/08

Agency embedded rate determination on portfolio of projects no later than
2/16/09
37
Hemingway to Boardman
Dave Angell - Idaho Power
38
Order 2004 Sensitive
Project Overview


Project Elements

Single 500 kV AC circuit
from Hemingway, Idaho to
Boardman, Oregon

Reactive compensation at
Sand Hollow station
Bidirectional rating:

1300 MW West to East

800/1400 MW East to
West

Project Operating Date:
Summer 2013

Project Websites:
http://www.boardmantohemingway.com/
http://www.idahopower.com/newsroom/projnews/hemingway_boardman/default.htm
39
Order 2004 Sensitive
Objectives

Meet transmission requirements of Idaho Power
Integrated Resource Plans (IRP)
225
MW of northwest resource import

Relieve congested transmission path

Satisfy OATI obligation for transmission service requests

Connect resource centers to load centers (hub and
spoke concept)
Transmission
to forecasted load growth
areas
Transmission to forecasted resources
areas
40
Order 2004 Sensitive
Plan of Service

54 mile 500 kV line from Hemingway to Sand Hollow reactive station.

Sand Hollow – series capacitor size for 50% compensation of line reactance

254 mile 500 kV line from Sand Hollow to Boardman Power Plant

Boardman Power Plant – shunt capacitor bank
41
Order 2004 Sensitive
Project Update (since July, 2008)

Permitting
 Oregon Energy Facility Siting Council Notice of Intent 8/27/2008
 BLM Notice of Intent (NEPA process) 9/11/2008

Comprehensive Progress Report
 West to East
 Hemingway – Boardman 1300 MW
 Idaho to Northwest Path 758 MW
 East to West independent of other northwest projects
 Hemingway – Boardman 838 MW
 Idaho to Northwest Path 1766 MW
 East to West with Gateway West, WOMGIP, Southern Crossing
 Hemingway – Boardman 1400 MW
 Idaho to Northwest Path 2417 MW
42
Order 2004 Sensitive
Project Implementation Schedule
7/2007 – 5/2008

WECC Regional Planning

WECC Phase 1 Rating
2/2008 – 12/2008

WECC Phase 2 Rating
1/2009 – 12/2009

Permitting and Land acquisition
1/2008 – 2011

Engineering
1/2008 – 2011

Construction
2011 – 5/2013

Operation
5/2013
43
Southern Crossing
Philip Augustin - Portland General Electric
Order 2004 Sensitive
Project Overview

Conceptual Major Project Elements
 500kV transmission line (215 miles)
 500/230 kV substations

Potential rating:
 1500 MW (East to West )winter
 1400 MW (East to West )summer

Project Operating Date:
 2013
 2013-2014 if staged

Project Website:
 http://www.oatioasis.com/pge/index.html
 http://www.nwpp.org/tcwg/
Order 2004 Sensitive
Objectives

The Project was initiated in response to Generation
Interconnection Requests for network service.

The Project will increase transmission capacity to PGE’s
service territory by increasing the East to West transfer
capability of the PNW grid

The Project is designed to integrate existing PGE
generation resources (i.e., Boardman and Coyote
Springs) and up to 800 MW of additional renewable and
other resources.
46
Order 2004 Sensitive
Conceptual Plan of Service:
 HVAC facilities from Boardman to
Coyote Springs
 HVAC facilities from Boardman to
Olallie
 HVAC facilities for Bethel to Olallie
 Series compensation between
Boardman to Olallie, and between
Bethel to Olallie
Coyote Springs
Coyote PGE
Coyote Avista
Slatt
McNary
Boardman
Bethel
Olallie
Proposed Wind
Pelton / Round Butte
500 kV
230 kV
PORTLAND GENERAL ELECTRIC CO.
SOUTHERN CROSSING
ONE LINE DIAGRAM
47
Order 2004 Sensitive
Project Update (since July, 2008)

Submitted Regional Planning Project Report to WECC Planning
Coordination Committee and Technical Studies Subcommittee on October
30th for 30 day review.

Studies demonstrate the Project’s effectiveness during heavy load
conditions occurring either in the winter or late spring / early summer.
 The east – west proposed rating was determined using a WECC 2017
Heavy Winter case, and a WECC 2015 Heavy Summer case.
Generation in the Northwest was dispatched to achieve 1,500 MW of
flow on Southern Crossing in the winter and 1,400 MW in the summer
meeting WECC Reliability Criteria.

Presented preliminary WECC Phase 1 study results to TCWG

Begun critical issues analysis work for proposed ROW

Signed a Memorandum of understanding with Idaho Power Co.
48
Order 2004 Sensitive
Generation Dispatch Studied
BC - NW (WEST)
CUSTER
BC - NW (EAST)
WANETA
NELWAY
WEST OF CASCADES - NORTH
BOUNDARY
(944 MW)
CHIEF
JOE
(2447 MW)
MONROE
WEST OF NOXON
GRAND COULEE
(6850 MW)
SOUTH OF BOTHELL
SOUTH OF RAVER
Upper Columbia
Generation
WA
--
ROCKY
REACH
(1240 MW)
ECHO
LAKE
CAB
GORGE
(230 MW)
BELL
RAVER
I-5 cooridor
Generation
--
OLYMPIA
BENEWAH
NORTH OF
HANFORD
SCHULTZ
PAUL /
CENTRALIA
(1370 MW)
VANTAGE
MOSCOW
Mid Columbia Generation
++
LOW
MON
(932MW)
HANFORD
MIDWAY
N. OF JOHN DAY (500KV
ONLY)
BEAVER
(534 MW)
LIT
GOOSE
(932 MW)
DWORSHAK
(476 MW)
HATWAI
ASHE
(1200 MW)
LOW
GRANITE
(932 MW)
ALLSTON
LOLO
SOUTH OF
ALLSTON
ROSS
THE
DALLES
KEELER
WEST OF
HATWAI
WALLA
WALLA
JOHN DAY
(2563 MW)
Lower Columbia Generation
++
McNARY
(1169 MW)
ENTERPRISE
ROUNDUP
PEARL
OSTRANDER
SLATT
HELLS
CANYON
(450 MW)
LAGRANDE
BUCKLEY
BOARDMAN BOARDMAN
(420 MW)
(540 MW)
OXBOW
(220 MW)
BROWNLEE
(730 MW)
WEST OF MCNARY
MARION
GRIZZLY
OR
WEST OF CASCADES SOUTH
IDAHO TO
NORTHWEST
LANE
PDCI
ALVEY
BURNS
ONTARIO
L E G E N D:
345KV
DC
230KV
500KV
115-161KV
CALDWELL
SOUTH OF GRIZZLY
SUMMER
LAKE
DIXONVILLE
49
Order 2004 Sensitive
Phase 1 Study Load Assumptions
Heavy Winter 2017
Name
AGC Status / Area Slack
PGE
TOTAL
NORTHWEST
Slack output: 614 MW
Gen MW
Max Gen MW
Load MW
2,603
3,673
4,284
30,685
48,144
33,258
Heavy Summer 2015
Name
AGC Status/ Area Slack
PGE
TOTAL
NORTHWEST
Slack output: 527 MW
Gen MW
Max Gen MW
Load MW
2,451
3,673
4,330
32,995
48,182
30,021
50
Order 2004 Sensitive
Phase 1: Preliminary Impacts existing paths observed
Winter all lines in service
Path Name and Number
Pre-Project
Summer all lines in service
Post-Project
Pre-Project
Post-Project
West of Cascades South (E-W)
7814
6870
6902
5972
Pacific DC Intertie (N-S)
-963
-963
2167
2167
California Oregon Intertie (N-S)
-1474
-1119
3368
3329
South of Allston (N-S)
-1118
-1237
1296
1149
North of John Day (N-S)
-1300
-1261
6446
6528
West of Slatt (E-W)
1547
844
4185
3313
West of McNary (E-W)
1475
1159
2459
2158
51
Order 2004 Sensitive
Project implementation Schedule
Task Name
Duration
WECC Phase 1 &
Regional Review
• Comprehensive Progress
Report (CPR)
-Identify the non-simultaneous
and known
interactions of the project
• CPR reviewed by PCC & TSS
membership
• Informal reports are presented
at TSS
meetings
• Letter to TSS and PCC
requesting
Phase 2 Status
WECC Phase 2
• Identify the simultaneous transfer
capability for project
• Address mitigations for any
adverse impacts to existing system
Start
12 months
Q1
2008
24 months
Q1
2009
Finis
h
2008
Q1
Q2
Q3
2010
2009
Q4
Q1
Q2
Q3
Q4
Q1
Q2
Q3
Q4
Q4
2008
Q4
2010
52
Order 2004 Sensitive
Project implementation Schedule

WECC Phase Rating Process
 Phase
1 Comprehensive Progress Report December 2008
 Phase 2 Rating Report
Fourth Quarter 2010
2009
Task Name
Duration Start
WECC Phase 3
•Definitive commercial
agreements
•Preliminary Engineering
•EFSC permitting process
•Land Acquisition
• Engineering
• Procurement
• Construction
• Release To Operation
2010
2011
2012
2013
2014
Finish Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Q2
2013
or
54 to 72
months
2013 –
Q1 Q2
2009 2014
53
Canada / Pacific Northwest to Northern California
Transmission Project
Stakeholder Meeting, Portland, November 19, 2008
Steve Metague - PG&E
54
Order 2004 Sensitive
Project Overview
To Edmonton/Heartland
Selkirk Sub



BPA
West of McNary Generation
Integration Project
Project steering team: Avista
Corp, BCTC, PacifiCorp,
PG&E
3000 MW North to South

South to North rating to be
determined
Project Operating Date: late
2015
BPA
I-5 Corridor
Station Z
Project Website:
http://www.pge.com/canada/
McNary
Big Eddy
PGE
Southern Crossing
PG&E, et. al
CNC Project
PacifiCorp
Walla Walla
NEO
Station
Idaho Power
Hemingway Boardman
Legend:
PG&E (AC or DC)
PGE (500kV)
Capt.
Jack
Idaho Power (500kV)
BPA (500 kV)
PacifiCorp/Idaho
Gateway West
Hemingway
PacifiCorp
(500 or 230kV)
Avista Corp (230kV)

PG&E et. al
CNC Project
Station X
Potential Bidirectional rating:

NorthernLights
DC
Devil’s Gap
Sea Breeze
WCC
PacifiCorp
Hemingway Capt.
Jack
Midpoint
Borah
To SF
Bay Area
NorthernLights (DC)
Sea Breeze WCC (DC)
Cottonwood
To SF Bay Area
Today’s presentation:

Project Plan of Service.

Summary of WECC Phase 1 N-S rating results.

Schedule for S-N WECC Phase 1 and WECC Phase 2 rating.

Overall Project Schedule.
55
Order 2004 Sensitive
Project Objectives

Enhance access to significant incremental renewable resources in
Canada and the Pacific Northwest.

Improve regional transmission reliability.

Provide market participants with beneficial opportunities to use the
facilities.

Use WECC’s open stakeholder planning process.
56
Order 2004 Sensitive
Plan of Service

Initial Plan of Service:
 HVAC facilities from Selkirk-Devil’s GapNEO Station
 HVDC facilities from NEO Station to
Collinsville with possible third terminal at
Cottonwood
 HVAC facilities from Collinsville to Tracy
 Voltage support at the interconnecting
substations
 Remedial Actions – tripping of generation
scheduled on the project for outages of the
project facilities

Project is dependent on other projects to be
installed in the 2010-2015 period. Such
projects:
 accommodate CNC Project Sponsors’ use
of CNC, or
 increase AC system strength to support AC
to DC conversion at the terminal stations
57
Order 2004 Sensitive
WECC Phase 1 Rating Process Update

Regional Planning Report completed and submitted – November 2007.

WECC Phase 1 has been coordinated with the Transmission Coordination Work Group (TCWG).

Three generation scenarios were developed to support delivery of 3000 MW of renewable
resources in British Columbia, the Pacific Northwest, or Northern California/Nevada:
 3000 MW of renewable generation from BC
 CNC project loaded to 3000 MW south of Selkirk
 1500 MW of renewable generation from both BC and the Pacific Northwest
 CNC project loaded to 3000 MW south of the NEO Station
 1500 MW of renewable generation from both BC and Northern California/Nevada
 CNC project loaded to 3000 MW south of the Cottonwood Area Substation.

2015 Heavy Summer base case has been used modeling the system with and without the CNC
Project.

The WECC Phase I rating studies conducted to establish a north-to-south rating show:
 The initial Plan of Service is viable.
 Rating for the project segments is 3000 MW, N-S.
 Other proposed projects at Neo Station needed to support the HVDC terminal.
 Other proposed projects at Cottonwood needed to support the potential HVDC terminal.
 Generation tripping of power scheduled on CNC (up to 3000 MW) is required for CNC facility
outages.
58
Order 2004 Sensitive
WECC Rating Process Next Steps

Phase 1 Comprehensive Progress Report (CPR)
 Project Sponsors to e-mail the draft to Stakeholders for comment
by12/1/2008.
 Stakeholders include TCWG members and Big Tent attendees who
request a draft copy.
 Stakeholder comments requested by 12/10/2008.
 Final CPR and request to move to Phase 2 will be submitted to WECC by
12/16/2008.

Project sponsors are scheduled to initiate the WECC Phase 1 rating process
to establish a south-to-north rating in January 2009
 Studies will be coordinated through the TCWG.

Project sponsors expect to initiate the WECC Phase 2 rating process 60-days
after submitting the Phase 1 CPR to WECC (mid-February).

Entities wanting to participate in the WECC Phase 1 (S-N) or Phase 2 (N-S)
process should join the TCWG through the Northwest Power Pool website:
http://www.nwpp.org/tcwg/
 Please copy Ben Morris at benmorris@astound.net
59
Order 2004 Sensitive
WECC Rating Process Activities

Previous activities
 Initiated Regional Planning 12/16/2006.
 Submitted Regional Planning Report 11/1/2007.
 Completed load and resources, technical feasibility and economic screening
analysis. Reports posted on project website 11/1/2007.
 Initiated Phase 1 Rating Process 10/31/2007.
 WECC Phase 1 Rating Process Stakeholder Meetings
 January 24, 2008
 July 18, 2008
 Today
 TCWG monthly meetings.

Planned activities
 WECC Phase 1 Draft Comprehensive Progress Report (CPR) out for comment –
12/1/2008.
 Stakeholder comments requested by 12/10/2008.
 Final CPR and request to move to Phase 2 to be submitted to WECC by
12/16/2008.
 Initiate the WECC Phase 1 rating process to establish a south-to-north rating in
January 2009.
 Initiate the WECC Phase 2 rating process – 2/2009.
 Complete WECC Phase 2 rating process – Q3/2010.
60
Order 2004 Sensitive
Basic Elements of Conceptual Project Schedule
Task Name
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
FEASIBILITY
ANALYSIS
PROJECT
PERMITTING
PROJECT DESIGN
PROJECT LAND
ACQUISITION
PROCUREMENT OF
MATERIALS
CONSTRUCTION
RELEASE TO
OPERATION
Note: This conceptual project schedule was prepared based on preliminary information without the benefit of route screening, preliminary engineering or other tasks
necessary to finalize a detailed schedule. The timeframes set forth herein may change as the result of pre-application studies.
61
Avista Corporation 500/230 kV Interconnection
with the Proposed
Canada / Pacific Northwest to Northern California
Transmission Project
Scott A. Waples - Avista Corporation
Order 2004 Sensitive
Project Overview

PG&E-CAN
500 kV Line
Major Project Elements:
Westside
230-115 kV

500/230 kV interconnection at
Devil’s Gap
 230 kV Phase Shifting
Transformers
 2-230 kV interconnections to the
Spokane Area 230 kV Grid

Devil’s Gap
500-230-115 kV
Potential Bidirectional rating:

500 MW

Project Operating Date: 2015

Project Website: NWPP.org/tcwg/
Sunset
230-115 kV
Beacon
230-115 kV
Major Highways
Existing 230 kV
Proposed 230 kV
Existing 115 kV
63
Order 2004 Sensitive
Objectives and Resources

The Avista interconnection to the PG&E Canada to Northern
California 500 kV Project will provide up to 500 MW of access from
the “Main Stem” Project to the Avista transmission system, providing
access to renewable resources in the Northwest and Canada.

The interconnection will also provide access to the “Main Stem” 500
kV Project for resources, including renewables, located within the
Avista service territory.

The project may also allow Avista to integrate some of its existing
thermal resources to its loads over its own transmission, and may
allow for additional imports of economy energy into the Avista
system.

Potential wind resources that may require export capacity from
various locations on the Avista system include, but are not limited to,
wind farms near Spokane, Othello and Clarkston, Washington, as
well as Grangeville and Lewiston, Idaho. Avista presently has 10
pending interconnections.
64
Order 2004 Sensitive
Project Update (since July, 2008)

Avista has completed the technical study work to support the WECC
Regional Planning / WECC Phase I Rating submittal as projected in
July. The studies indicate that the interconnection is feasible and
that there are no adverse impacts to neighboring systems from this
interconnection.

Avista anticipated a joint Regional Planning / Phase I submittal for
the study work, and a first draft of this report was provided to the
TCWG at its October 23, 2008 meeting in Portland, Oregon. TCWG
recommended that the draft report be split into two submittals.
Avista has incorporated comments received at the TCWG meeting
into the Regional Planning Report and has submitted that report to
WECC. Comments on the report are due December 12, 2008. The
Phase I report should be submitted to WECC within the next six
weeks.

Avista is also working with other PG&E Project Teams (Permitting
and Public Affairs) for the PG&E Canada to California project.
65
Order 2004 Sensitive
Project implementation Schedule

WECC Regional Planning
December, 2008

WECC Phase I Rating studies
December, 2008

WECC Phase II Rating studies
2009

Permitting and Land acquisition
2013-2014

Engineering
2013-2014

Construction
2014-2015

Operations
2015
66
Avista Corporation 230 kV Dry Creek –
(Walla Walla – NEO ) –
Coyote Springs Transmission Project
Scott A. Waples - Avista Corporation
Order 2004 Sensitive
Project Overview

Major Project Elements:


Dry Creek (Walla Walla – NEO) Coyote
Springs 230 kV Line

Project Operating Date: 2015

Project Website: NWPP.org/tcwg/
Potential Bidirectional rating:

500 MW
Dry Creek
Walla Walla
Boardman/CS II
WA
OR
Major Highways
Proposed 230 kV
68
Order 2004 Sensitive
Objectives and Resources

The interconnection will allow Avista access to other renewable
resources in the Northwest as well as in Canada.

The project may also allow Avista to integrate some of its existing
thermal resources to its loads over its own transmission, and may
allow for additional imports of economy energy into the Avista
system.

Potential wind resources that may require export capacity from
various locations on the Avista system include, but are not limited to,
wind farms near Spokane, Othello and Clarkston, Washington, as
well as Grangeville and Lewiston, Idaho. Avista presently has 10
pending interconnections.
69
Order 2004 Sensitive
Project Update (since July, 2008)

Avista has begun the technical study work to support the WECC
Regional Planning and WECC Phase I Rating submittals. The
studies that have been completed indicate that the interconnection is
feasible and that there are no adverse impacts to neighboring
systems from this interconnection. The project may require phase
shifting transformers as well as series compensation. The project
may, at a future date, also interconnect at the NEO Station.

Avista has formally approached PacifiCorp to see if this project and
the PacifiCorp Walla Walla – McNary (NEO) project might be able to
utilize a common right-of-way or common transmission structures,
and the two companies are now engaged in such discussions.

Avista will be hosting a kickoff meeting for the WECC Regional
Planning and Phase I Study efforts for this project in the near future.
Please stay tuned!
70
Order 2004 Sensitive
Project implementation Schedule

WECC Regional Planning
January, 2009

WECC Phase I Rating studies
January, 2009

WECC Phase II Rating studies
2009

Permitting and Land acquisition
2013-2014

Engineering
2013-2014

Construction
2014-2015

Operations
2015
71
NorthernLights
Connecting Alberta and the Pacific Northwest
Russ Hantho – Bill Hosie
TransCanada Corporation
Order 2004 Sensitive
NorthernLights Overview

HVDC transmission line
connecting the Edmonton
area with northern Oregon

3000 MW line design
capacity

2000 MW bidirectional
capacity

900 miles

$2.2 billion (‘08$), 2000 MW
initial capacity

Edmonton
AB
BC
SK
Calgary
Operational in 2015
Spokane
WA
Buckley
MT
ID
OR
NorthernLights
AC or DC Connectors
Converter
Project web site:
http://www.transcanada.com/company/northernlights.html
73
Order 2004 Sensitive
NorthernLights

Creates a bi-directional intertie between Alberta and the Pacific
Northwest

Enhances regional resource reliability (AESO’s 2007 Market
Roadmap)

Improves regional transmission reliability

Enhances regional wind capacity factors through geographic
diversity

Provides market participants with beneficial opportunities to use the
facilities

Provides opportunities for markets to access large scale renewable
energy resources – wind, hydro, IGCC with sequestration & nuclear
74
Order 2004 Sensitive
Generation Potential in Alberta
75
Order 2004 Sensitive
NorthernLights Project Progress

Transmission Planning & WECC
Participation
at NTAC, RMATS, Columbia
Grid and NTTG
WECC Regional Planning Process 2007
WECC Path Rating Process
76

BPA Interconnection Agreement

INL Study

Alberta Corridor Analysis

AESO Open Houses
76
Order 2004 Sensitive
Alberta Interconnection
Milo
To
Buckley
77
Order 2004 Sensitive
Buckley Area Interconnection
“Buckley New”
78
Order 2004 Sensitive
Project Update (since July, 2008)

Edmonton to Calgary System Developments
 40 open houses between June and December 2008 held
by the AESO with TransCanada participation

Phase 1 Comprehensive Progress Report tabled with
TCWG Monday for comment
 Schedule to submit to the WECC December 1, 2008

Phase One Studies
 2000 MW bidirectional power flow, reactive margin and
stability studies
 Results are all within reliability criteria standards
79
Order 2004 Sensitive
Project implementation Schedule

WECC rating studies
2009

Permitting and Land acquisition
2009 - 2012

Engineering
2009 - 2012

Construction
2012 - 2015

Operations
2015
80
West Coast Cable
Juan de Fuca Cable 2
Triton North Cable
Triton Central Cable
Triton South Cable
Sea Breeze Pacific - RTS Projects
81
Order 2004 Sensitive
82
Order 2004 Sensitive
Juan de Fuca Cable 2
2013
+/- 300 kV DC VSC
1,100 MW
RP – submitted
11/2008
West Coast Cable (WCC)
2015
+/- 600 kV DC
1,600 MW
Ph 1 – Initiated
12/2006
+/- 300 kV DC VSC
+/- 150 kV DC VSC
+/- 300 kV DC VSC
2,200 MW
550 MW
2,200 MW
3 RP’s – submitted
11/2008
Triton Central
Triton North
Triton South Cables
2014
2016
2017/2019
83
Order 2004 Sensitive
84
Order 2004 Sensitive
SBP-RTS Projects

West Coast Cable  In Phase 1 – Power Flow runs completed
 Stability runs in process

Juan de Fuca Cable 2
Triton North Cable






▀ Triton Central Cable
▀ Triton South Cables
Regional Planning reports - for all studies have been completed
and are currently being submitted.
Phase 1 – Power Flow cases have been run in PowerWorld using the
TCWG agreed upon 2015 HS TCWG Base Case
Have been converted to PTI format.
ABB has confirmed models and has verified conversions.
Models are available on the NWPP Website.
85
Order 2004 Sensitive
Questions?
86
Order 2004 Sensitive
Next Steps and Timelines for TCWG

Joint Big Tent Meeting
Nov 19, 2008

Submit Phase 1 CPR to PCC and TSS (Project Sponsor)

Phase 2 Studies (Project Sponsor and TCWG)
Dec 2008 and on

TCWG will be used for Phase 2 study reviews
Dec 2008 and on
Q4 2008
87
Order 2004 Sensitive
Q&A
Order 2004 Sensitive
Inputs and Commentary
Sponsor Panel
89
Download