07-LAP Update-TRANSAC-06-19-14 Updated:2014-06-17 13:55 CS

advertisement
Local Area Planning Update – TRANSAC 6-19-14
1
Base Cases
Base Case Status
•
2
Base case study models representing the base
scenarios will be completed for four seasons: Heavy
Summer (HS), Heavy Winter (HW), Light Autumn (LA),
and Light Spring (LSP) for the present and future over
the 15-year planning horizon… 2014, 2019, 2024, and
2029… 16 cases total.
Base Cases
Base Case Status – cont.
•
•
•
3
Existing system configuration will be modeled in 2014
HS, HW, LA and LSP cases; signed projects (GIA’s
EP&C’s, TSR’s, etc.) and budgeted/approved system
improvements are included in 2019 and later cases.
Dispatch may depend on TSR’s.
All heavy loading base cases will be based on a 1/10
load forecast.
All light loading base cases will be based on 65% of
the seasonal peak.
Contingencies
Contingencies to Study
•
•
System normal (N-0), single segment or element
outage (N-1), and selected “credible” double segment
or element outage (N-2) contingency files will be
developed/updated to facilitate simulation runs of the
same system conditions through each base case.
Outages include:
–
–
–
–
4
Lines
Transformers
Buses
Plants (Generation)
Criteria
Study Criteria
•
•
System normal and Outage conditions will be modeled
and studied for adequacy and system security.
Segment or element thermal loads >85% will be noted
under these conditions; loads above 100% of
seasonal limits will be noted as overloads.
– Overloaded segments will be “tripped” per standard relaying
practice (100% - 150% thermal on lines, 125% minimum
thermal on transformers) to check for “cascading” outages;
– Changes in seasonal ratings will be considered.
•
•
5
Emergency ratings do not apply.
Existing OMS or RAS schemes will be considered.
Criteria
Study Criteria – cont.
•
Voltages outside of NWE planning criteria will be
noted (93%, 95%, or 97% low voltage limit depending
on line voltage; 105% high voltage limit).
– Load-serving bus voltages may fall above or below the tabled
value if conditions allow a higher/lower voltage without harm to
NWE or customer equipment.
– Certain equipment ratings may dictate different limits (107% will
be allowed on 100 kV systems where equipment is nameplate
rated 102 kV or higher).
6
State of the System
Studies
System Normal and Outage studies will be
completed on all seasons of the 2014 base
cases to determine the present “state of the
system” as it exists today.
7
Next Steps
Next Steps
•
•
Q3: Analysis of 2014 cases for normal and outage
conditions will be completed for state of the system
review.
Q4-Q5: Complete the analysis of 2019, 2024, and the
2029 cases.
– Verification of new problems
– Uncertainty scenarios
•
•
8
Q5: Prioritize problems using Decision Rules
Q5-Q6: Begin Mitigation Studies
Local Area Planning
Update
Questions?
9
10
Download