CLECO POWER, LLC TRANSMISSION SERVICE FACILITIES STUDY OASIS REQUEST 73408102 FOR CLECO POWER LLC, WHOLESALE ENERGY SERVICES OASIS 73408102 Facilities Study TABLE OF CONTENTS 1. PROJECT SUMMARY 3 1.1. Background and Project Need 3 1.2. Scope Summary 3 1.3. Summary of Work to Be Performed 3 1.4. Cost Summary 3 1.5. Schedule Summary 4 2. SAFETY REQUIREMENTS 4 3. GENERAL ASSUMPTIONS 4 4. SCOPE OF WORK 5 4.1. Substations 5 4.1.1. IP Mansfield 5 4.1.2. Mansfield 6 4.2. Lines 4.2.1. Mansfield – IP Mansfield 6 6 5. COST 7 6. SCHEDULE 7 6.1. IP Mansfield Substation Additions 7 6.2. Procurement of Property Adjacent to Mansfield Substation 7 6.3. Engineer and Procure Material and Equipment 8 6.4. Construction 8 7. COST AND SCHEDULE RISK ASSESSMENT 8 8. STUDY QUEUE 8 9. ATTACHMENTS A. IP Mansfield 9 B. Mansfield 10 Issued by: Transmission Services Issued on: February 16, 2010 Page 2 OASIS 73408102 Facilities Study 1. PROJECT SUMMARY 1.1. Background and Project Need A System Impact Study was performed to determine the availability of transfer capability across Cleco Power LLC’s Transmission System to accommodate OASIS Request 739408102 for 2.8MW of yearly Network Integration Transmission Service (“NITS”) beginning April 1, 2010 up to 25MW of NITS ending January 1, 2019. Cleco Power Wholesale Energy Services (“Transmission Customer”) is requesting to interconnect a new 138kV interconnection to the IP Mansfield substation on the Cleco Power Transmission System. 1.2. Scope Summary The System Impact Study identified transmission constraints occurring between the Mansfield and Wallace Lake substations. Based upon the application for the OASIS request this is expected to occur in 2014. The limiting element is the IP Mansfield - Mansfield 138kV line for loss of the Dolet Hills - Southwest Shreveport 345kV line. The addition of a 6Ω reactor in series with the IP Mansfield - Mansfield line is required to reduce the flows below 100% for the stated contingency. The need for these facilities will be re-studied during the fall of 2012. 1.3. Summary of Work to Be Performed Construct facilities within the IP Mansfield substation to provide an interconnection point for the new Transmission Customer 138kV line. Acquire property and construct facilities necessary for the installation of a 6Ω reactor at the Mansfield substation. The line relay panel at the IP Mansfield substation will need to be replaced in conjunction with the reactor installation at the Mansfield substation. 1.4. Cost Summary The estimated cost of the initially required facilities at the IP Mansfield substation is $26,000. The only includes the bus extension. The Transmission Customer is responsible for this cost. Issued by: Transmission Services Issued on: February 16, 2010 Page 3 OASIS 73408102 Facilities Study The estimated cost of the line relaying replacement at the IP Mansfield substation required in conjunction with the reactor installation at the Mansfield substation is $60,000. Cleco Power is responsible for this cost. The estimated cost for the additions to the Mansfield substation to accommodate the 6Ω reactors and associated equipment is $2,981,000. Cleco Power is responsible for this cost. No cost estimate has been made for any facilities beyond the bus extension since these facilities are the responsibility of Transmission Customer. 1.5. Schedule Summary The requested in-service date is April 1, 2010. This date is not achievable. It is estimated that the work within the IP Mansfield substation could be completed within three (3) months of project authorization. The reactor addition at the Mansfield substation is not required to be in service until the end of 2013. Property acquisition, engineering, and equipment procurement would begin in early 2013 to meet the end of year completion date. 2. SAFETY REQUIREMENTS Safety is a priority with Cleco Power and safety will be designed into all substations and lines. All facilities will be designed with the utmost safety for personnel in mind for construction, operation, and maintenance of the equipment. All employees working directly or indirectly for Cleco Power shall adhere to all rules and regulations outlined within the Cleco Power’s Safety Manual. Cleco Power requires safety to be the highest priority for all projects and all company and contract employees must follow all applicable safe work procedures. 3. GENERAL ASSUMPTIONS It is assumed that a minimal amount of time will be required by Transmission Customer to approve this project which would enable Cleco Power to proceed with the necessary tasks as defined in the Scope of Work and be able to complete the project as per the schedule described below. Assumptions have been made in developing estimates without performing site visits, surveys, and soil borings. During the preliminary engineering phase these tasks will be completed and could have an impact on estimates and schedule. Issued by: Transmission Services Issued on: February 16, 2010 Page 4 OASIS 73408102 Facilities Study All costs above represent good faith estimates in today’s dollars and are based on existing data and could change considerably after detailed engineering analysis. Price escalation for work in future years has not been included. 4. SCOPE OF WORK 4.1. Substations 4.1.1. IP Mansfield The substation is located within the International Paper plant site and servitude was granted to Cleco Power for the substation. Transmission Customer is required to obtain permission from the mill to locate their new facilities within the substation. Cleco Power will own and maintain the short bus extension as well as the new meters. Transmission Customer will be responsible for the engineering, procurement, construction, ownership, and maintenance of all other facilities. General Extend the main bus to accommodate a new terminal. Transmission Customer will be required to install a 2000A disconnect switch, switch stand and a 2000A gas circuit breaker. Transmission Customer will also be required to install appropriate grounding and extend the duct system to accommodate the new GCB as well as perform necessary site work. Relaying Transmission Customer will be required to install Cleco Power approved step distance line relaying for the line. Cleco Power will incorporate the GCB into the existing bus differential scheme. When the reactor is installed at the Mansfield substation the existing line relay panel associated with the Mansfield-IP Mansfield line will need to be replaced with advanced relays required to provide line protection with and without the reactor in service. Metering Cleco will install high accuracy four quadrant meters for delivery point metering. Transmission Customer will be required to incorporate high accuracy metering CTs in the GCB. High accuracy metering PTs are already in place Issued by: Transmission Services Issued on: February 16, 2010 Page 5 OASIS 73408102 Facilities Study SCADA A RTU is already located at this substation. All communications circuits are already in place. 4.1.2. Mansfield Cleco Power will engineer, procure, construct, own, and maintain the new facilities associated with the reactor installation. General Purchase approximately three (3) acres of property adjacent to the substation Perform site work and install fencing Extend the ground grid Extend the cable duct system Install a new dead end tower for the IP Mansfield line Install new bussing to accommodate the reactor Install a 6Ω 1200A reactor Install six (6) 2000A disconnect switches and switch stand Install two (2) 2000A gas circuit breakers Install appropriate grounding and duct system to accommodate the GCB Install three (3) high capacitance CCVTs on the IP Mansfield line Move the carrier relaying CCVT and wavetrap to the new line termination, location. Relaying Move the existing line relay panel from the present circuit breaker to the new gas circuit breaker. Install a bus differential panel to protect the reactor and associated circuit breakers and bus. Install necessary control cable Metering None needed SCADA Connect control and indication for new GCBs to the existing RTU 4.2. Transmission Lines 4.2.1. Mansfield - IP Mansfield General In 2013, dead end the line on the new dead end tower at the Mansfield substation and jumper to the reactor bus. Issued by: Transmission Services Issued on: February 16, 2010 Page 6 OASIS 73408102 Facilities Study 5. COST IP Mansfield Substation (initial) Cost Item Bus extension Metering Engineering review Total Estimated Cost (installed) $10,000 $10,000 $6,000 $26,000 The Transmission Customer is responsible for this cost. All other facilities located beyond the bus extension at this location are the sole responsibility of the Transmission Customer. IP Mansfield Substation (2013) Cost Item Line relay panel installed Estimated Cost (installed) $60,000 Cleco Power is responsible for this cost. Mansfield Substation (2013) Cost Item Property and site work Engineering, material and labor Total Estimated Cost (installed) $400,000 $2,581,000 $2,981,000 Cleco Power is responsible for this cost. 6. SCHEDULE 6.1. IP Mansfield Substation Additions It is estimated that within three (3) months of authorization, Cleco Power can extend the bus and have the new meters installed and be ready for service. This schedule assumes that outages can be obtained from the mill and on the Wallace Lake line. 6.2. Procurement of Property Adjacent to Mansfield Substation Procurement of the property adjacent to the substation would begin in early 2013 and would be completed by mid-year. Issued by: Transmission Services Issued on: February 16, 2010 Page 7 OASIS 73408102 Facilities Study 6.3. Engineer and Procure Material and Equipment at the Mansfield Substation This phase would also begin in early 2013 and be completed by mid-year. 6.4. Construction at the Mansfield Substation Site work and construction would begin late summer 2013 and be completed prior to the end of the year. 7. COST AND SCHEDULE RISK ASSESSMENT Risk Material/equipment Contractor labor Comment Increase in cost of steel and aluminum Increase in labor cost Permitting Wetlands and other permitting Outages Delay in obtaining an outage from the mill and on the Wallace Lake line to extend the bus Obtaining servitude from the mill to add additional facilities at the IP Mansfield substation Servitude Impact Could significantly affect cost estimates Could moderately affect cost estimates Could significantly affect cost and schedule Could significantly affect schedule Could prevent the new delivery point from being established at this location 8. STUDY QUEUE OASIS No. 71847922 71956063 72310136 72805097 1352934 73436331 72981623 Issued by: Transmission Services Issued on: February 16, 2010 MW 162 203 580 45 54 25 75 Begin 04/01/2009 10/01/2008 01/01/2010 03/01/2010 06/01/2010 01/01/2010 01/01/2010 End 12/31/2018 10/01/2020 01/10/2040 01/01/2041 06/01/2015 01/01/2011 01/01/2020 Page 8 OASIS 73408102 Facilities Study ATTACHMENT A Issued by: Transmission Services Issued on: February 16, 2010 Page 9 OASIS 73408102 Facilities Study ATTACHMENT B Issued by: Transmission Services Issued on: February 16, 2010 Page 10