ii OCCUPATIONAL SAFETY AND HEALTH IMPROVEMENT AT CASTING PLANT NORASIKIN BINTI HUSSIN A project report submitted in partial fulfillment of the requirements for the award of the degree of Master of Engineering (Industrial Engineering) Faculty of Mechanical Engineering Universiti Teknologi Malaysia APRIL 2010 iv In the name of Allah.the Beneficient,the Merciful and To my beloved mother,father,friends…. v ACKNOWLEDGEMENT First of all, I would like to express my sincere thanks and deepest appreciation to my project supervisor, Assoc. Prof. Dr. Abd. Rahman bin Abdul Rahim from the Faculty of Mechanical Engineering, Universiti Teknologi Malaysia, for his generous advices, guidance, comments, patience, commitments and encouragement given to me in preparing and completing this project report. My special thanks also go to Prof. Ir. Dr. Wahyu Kuntjoro for his willingness to guide and suggest ideas for project analysis in MSC Nastran/Patran, Ir. Haji Zulkifli Mohd Rashid, who have given ideas in design using Solid Edge and AutoCAD system. Mr. Sahadan Abdullah, Managing Director of DSB Casting who provides support and information about DSB Casting. Lastly, I would also like to extend my gratitude to all my friends, colleague’s and those individuals who have contributed, either directly and indirectly towards the successful compilation and completion of this project report. To my parents who always pray for my success, I owe them forever for all they have done. vi ABSTRACT Occupational safety and health issues among workers are gaining prominence in industrial sectors. To ensure that all workers are free from any hazards, preventive actions should be given priority. These hazards can cause accidents and ill health to the workers due to unsafe conditions or unsafe act. This project was carried out at a casting plant. The project have identified the hazard, assess the risk and proposed control measures. Three methods are used to collect data which are questionnaires, interviews and observations. Process with high risk is pouring process due to manual lifting and carrying molten metal. The hot environment cause heat stress, and sand dust can cause silicosis. Trolley was designed to eliminate the need to carry the molten metal during pouring. Finite element analysis was carried out to study the strength of material and suitability of the design. A ventilation system was proposed to reduce the effect of heat stress and mineral dust from the greensand mold. Engineering analysis was carried out during the design of the ventilation system. vii ABSTRAK Isu keselamatan dan kesihatan pekerja adalah sangat penting didalam sektorindustri. Dalam memastikan bahawa setiap pekerja adalah terhindar daripada sebarang risiko bahaya atau kemalangan, langkah-langkah pencegahan perlu diberi keutamaan. Risiko bahaya atau kemalangan ini boleh menyebabkan kemalangan dan masalah kesihatan keatas pekerja disebabkan akta dan persekitaran yang tidak selamat. Kajian ini dilakukan di industri penuangandan adalah untuk mengenal pasti sebarang bahaya atau risiko yang mungkin berlaku serta mencadangkan langkah-langkah keselamatan .Tiga kaedah digunakan dalam pengumpulan data yang mana melalui borang kaji selidik, temuramah dan juga pemerhatian.. Risiko kemalangan yang tinggi adalah proses penuangan bahan logam, ini disebabkan cecair logam panas masih lagi diangkat dengan menggunakan kaedah lama atau secara tradisional. Persekitaran yang panas semasa proses penuangan juga menyebabkan tekanan haba yang tinggi, dan udara yang berpasir, berhabuk serta berdebu boleh menyebabkan radang peparu. Sebagai langkah pencegahan dalam mengurangkan berat yang dialami ketika menuang cecair logam panas ke dalam acuan penuangan troli direkacipta khas untuknya. Untuk mendapatkan ketepatan rekabentuk dan mengenal pasti tahap kesesuain troli sebagai ganti dan juga bahannya, Kaedah Pengstrukturan Elemen diguna pakai bagi tujuan penganalisaan dan pembuktian. Sistem Pengudaraan juga dicadangkan bagi mengurangkan kepanasan suhu dan debu di kawasan penuangan. Sistem pengudaraan ini juga perlu dianalisa untuk mendapatkan ketepatan pengukuran dalam mengurangkan haba panas. viii LIST OF TABLES TABLE NO TITLE PAGE Table 2.1 Likelihood of occurrence 20 Table 2.2 Severity of hazard 21 Table 2.3 Risk matrix 21 Table 2.4 Risk level from risk matrik 22 Table 4.1 Industrial accidents at DSB Casting January 2000 until 50 October 2009 Table 4.2 Data of lost time injury (M/C) 51 Table 4.3 Data of accidents 52 Table 4.4 Background of workers 57 Table 4.5 Types of problem 58 Table 4.6 Number of injuries by job categories 59 Table 4.7 Frequency of accident 60 Table 4.8 Number of workers using PPE 62 Table 4.9 Data for injured body parts 64 Table 4.10 Temperature at pouring area 64 ix Table 4.11 Temperature at furnace 65 Table 4.12 HIRARC of pouring process 66 Table 5.1 Finite element result 74 x LIST OF FIGURE FIGURE NO TITLE PAGE Figure 1.1 Project methodology 6 Figure 1.2 Project report outline 10 Figure 3.1 HIRARC process 42 Figure 4.1 Organization chart at DSB Casting 46 Figure 4.2 Foundry layout 47 Figure 4.3 Machining and fabrication layout 47 Figure 4.4 Casting process flowchart 49 Figure 4.5 Layout of pouring area 53 Figure 4.6 Manual material handling 54 Figure 4.7 Pouring process 55 Figure 4.8 Ventilation system 55 Figure 4.9 Pouring area 56 Figure 4.10 Furnace area 56 Figure 4.11 Pareto diagram on types of problem 58 Figure 4.12 Pareto diagram for numbers of injuries by job categories 59 xi Figure 4.13 Pareto diagram of accident frequency 60 Figure 4.14 Pareto diagram number of workers using PPE 62 Figure 4.15 Layout of pouring area with ambient temperature 64 Figure 5.1 Pouring trolley design 71 Figure 5.2 Methods when using pouring trolley 71 Figure 5.3 Types of Ladle 72 Figure 5.4 Result of stress analysis of pouring trolley 73 Figure 5.5 LEV ducting design 77 Figure 5.6 LEV location 78 Figure 5.7 Location of LEV with respect to ambient temperature 79 xii LIST OF APPENDICES APPENDIX TITLE PAGE A Questionnaire for data collection of the project 84 B Analysis from questionnaire 90 C Mechanical drawing of pouring trolley using solid edge 93 V19 D Mechanical drawing of ventilation system using AutoCAD 98 2002 E Analysis of pouring trolley using Msc Nastran/Patran 100 xiii CHAPTER 1 INTRODUCTION 1.1 Introduction Safety and health has become major issues of every workplace. Industry, government, the public and academia has taken significant interest and put pressure on employers about the importance of safety and health to employees. Both employers and employees must comply with the Occupational Safety and Health Act 1994 and its regulations to avoid risk and accidents in workplace. xiv Safety is vague because to some extent safety is a value judgment, but precise because in many cases, one can readily distinguish a safe design from an unsafe one. The American Heritage Dictionary defines safety as freedom from damage, injury or risk. The Oxford Dictionary defines health as the state of being well, having or showing or producing or functioning well, beneficial and good. Many workers become seriously ill as a result of unsafe and unhealthy working conditions. Occupational accidents are common occurrence. The number of reported accidents has increased sharply in countries where industrial development has been rapid or where reporting systems for accidents have improved. Accident rates remain particularly high in hazardous industries such as manufacturing, mining, construction and forestry. There is a growing awareness too, of the close relationship between working conditions and productivity. The improvement of occupational safety and health is considered an important prerequisite for economic and social development. In response, most governments have taken steps to review policy and legislation. Employers and workers are becoming increasingly aware that safe and healthy working conditions are essential for sustainable growth. It is important to realize that health and safety problems must be solved through the commitment of all concerned. Technical solutions alone cannot lead to concrete improvement. The purpose of this project is to suggest improvement in safety and health at a casting plant. The plant is a ferrous and non-ferrous foundry, and produce variety of casting products. The company has many processes which have safety and health hazards. It is important to implement safety and health policy and program to protect workers. This study will focus on health and safety improvement at the casting plant. xv 1.2 Background of the Project Hazards at a metal foundry depend on the employees job and work station. Employees faced different risk depending on what they did, and where they actually performed their job. Grinders experienced more eye injuries, hot metal workers has more heat injuries, and molders more strains, pulls and tears. Overall, injury rates adjusted for exposure were significantly lower than expected for hot metal workers, and higher than expected for molders. Long term employees experienced lower accident rates. Workplace injuries may be broadly characterized as caused by either organizational or personal factors. Organizational factors include work method, workstation layout and exposure to hazardous noise and materials. Personal factors may include age, experience, occupational stressors and non-work stressors. The foundry was unique in that most jobs and workstations have different type of stressors. Dust is one of the most common hazards likely to be found in foundries. The dust will be in the form of fine respirable particles, and depending on the type of foundry and the processes used, may contain significant amount of silica, lead, or other contaminant. In some metal casting processes, respirable silicous dust is produced as a product of furnaces, moulding sand, knockout and shakeout of casting, fettling and abrasive. Dust including various form of silica containing materials can cause silicosis. Manual material handling is one of health hazard in foundries and major causes of back injury. Moulding and core making may involve the lifting, carrying and stacking of heavy objects. A hazardous task observed in the foundry, which could contribute to low back injuries involves pouring molten metal. Due to the high cost of automating metal pouring operations, small and medium scale foundries still utilize the manual method for pouring. Proper workplace design, using ergonomic principles, will prevent long-term serious injury to xvi workers. The economical benefits are well recognised through increased production and less downtime or lost time through absenteeism. Lighting is important in working area that involved work that need precision, accuracy and detail. Sufficient lighting means sufficient number of lamp in appropriate space. Lighting can also be used to define form, shape and scale of spaces. Usually for accident to occur there are probably some ‘near-misses’, people who work in places where accidents frequency is high tend to work a little slower as a precaution, so there is probably some loss of productivity. Personal injury can affect the productivity for a long period of time. For example, in the coating process sufficient lighting is crucial to obtain a good drying surface finished. 1.3 Research Problem There are two areas selected for studies in this project. The first one is work environment where the employees are exposed to dusts and extreme heat. The second area of study is working condition which is not ergonomic. Example of working condition not ergonomic, are glare and poor material handling causing back injury. xvii 1.4 Methodology The methodology in this research is shown in Figure 1.1. This project begins with searching for a suitable manufacturing company as a case study. Understanding the company profile, activities and manufacturing process is necessary before detail data collection is carried out. Literature review, include past case studies. Metal pouring process is selected for further study. In order to understand the pouring process, visits to the company were made regularly, followed by discussion with the supervisor, and workers to enable a better comprehension about safety hazard and precautions during the pouring process. Information about safety requirements and process is obtained from the company’s document. In problem identification stage, three methods of data collection were used observation, study of factory’s documents and interview. From here hazard identification is carried out after analyzing collected data. Safety hazard with the highest risk are be analyzed and recommendations are made. Recommendation and proposed improvement can reduce risk or avoid in the pouring process. xviii State Company Study Company Operation Identify Areas for Study Literature Review Identify hazards at selected areas Data Collection and Analysis Recommendation and Proposed Solutions Figure 1.1 Project methodology xix 1.5 Objectives The objectives of this project are: i. To identify safety and health hazard and assess risk at the casting plant. ii. To propose improvements. 1.6 Scope The scopes of this research are: i. Focuses on safety and health improvement at sand casting process only. ii. Cost analysis is not included. iii. All suggestions must not be necessarily implemented by the company. 1.7 Definition of Terms The definitions of the most common terms used in this project are: a) HIRARC means hazard identification, risk assessment and risk control. b) Severity is outcome from an event such as severity of injury or health of people, or damage to property, or damage to environment, or any combination of those caused by the event. xx c) Likelihood is an event likely to occur within the specific period or in specified circumstances. d) Control is the elimination or inactivation of a hazard in a manner such that the hazard does not pose risk to workers who have to enter into an area or work on equipment in the course of scheduled work. e) Redesign means jobs and processes can be reworked to make them safer. For example, containers can be made easier to hold and lift. f) Isolation means if a hazard cannot be eliminated or replaced, it can sometimes be isolated, contained or otherwise kept away from workers. For example, an insulated and air-conditioned control room can protect operators from toxic chemical or extreme temperature. g) Dilution means some hazards can be diluted or dissipated. For example, ventilation systems can dilute toxic gasses before they reach operators. 1.8 Outline of the Report Figure 1.2 illustrates the report outline of this project. This report consists of six chapters. Chapter 1 describes introduction to the project and research problem. This chapter also explains the objectives, scopes, methodology, terms and definitions used in this project. xxi Chapter 2 explains literature review of previous work related to safety and health hazard. These literatures discuss about theory, concept and research method. Chapter 3, explains the methodology used in the project and background of the company. This chapter includes the method used to collect data and identify hazards at the company. The organization chart, company layout and process flow is also discussed in this chapter. Chapter 4 explains data collection and analysis. Risk assessment of sand casting process is also carried out. Chapter 5 discuss the proposed solutions and analysis. This chapter explained the improvement plans proposed to the company. The results from the improvement plan were evaluated and compared with existing condition. Chapter 6 summarize the report and conclusion of the works. Research contribution and recommendations for future works are explained. xxii Introduction to Project (Chapter 1) Literature Review (Chapter 2) Methodology and Company Background (Chapter 3) Data Collection and Analysis (Chapter 4) Proposed Solution and Analysis (Chapter 5) Conclusion and Future Work (Chapter 6) Figure 1.2 Project report outline 1.9 Conclusion This chapter described introduction to the project. Project background, objectives, scopes and methodology are also discussed. The purpose of this project is to identify safety and health hazards in casting plant, and proposed improvements to control the hazard. The literature review is discussed in Chapter 2. xxiii CHAPTER 2 LITERATURE REVIEW 2.1 Introduction This chapter discuss the theory, concept and methodology of the project. Literature review include general safety, risk assessment, sand casting process, and hazards during casting and hazard control. 2.2 Definition 2.2.1 Accident An accident is defined as an unplanned, unexpected occurrence that interferes with or interrupts the orderly progress of work and potentially leads to personal injury or dollar losses. During an accident, a person’s body comes into contact with or is exposed to some object, other person or substance, which is injurious or the movement of a person causes injury or creates the probability of injury (Thomas, 1989). xxiv 2.2.2 Injury An injury may be defined as harmful condition sustained by the body as the result of an accident, it can take the form of an abrasion, a bruise, a laceration, a fracture, a foreign object in the body, a punctured wound, a burn or an electric shock.(Thomas,1989). 2.2.3 Unsafe Act An unsafe act is a violation of an acceptable safe procedure, which could permit the occurrence of an accident. Some unsafe acts are so hazardous that it takes very little action before the occurrence of an accident (Thomas, 1989). 2.2.4 Unsafe Condition An unsafe condition is a hazardous physical condition or circumstances that could directly permit the occurrence of an accident. This could be the result of an unsafe act by someone (Thomas, 1989). 2.2.5 Danger The definition of "danger" includes any existing or potential hazard or condition and any current or future activities. The notion of immediacy has been clarified by specifying that the injury or illness need not follow immediately. Hazard is also clarified by adding the wording "existing and potential" to hazard (OHSAS 18000: 1999). xxv 2.2.6 Hazard Hazard is a sources or situation with a potential for harm in terms of injury or ill health, damage to the workplace environment or a combination of these. (OHSAS 18000: 1999) 2.2.7 Hazard Control The process of implementing measures to reduce the risk associated with a hazard. (OHSAS 18000: 1999) 2.2.8 Risk Risk means a combination of the likelihood of an occurrence of a hazardous event with specified period or in specified circumstances and the severity of injury or damage to the health of people, property, environment or any combination of these caused by the event. (OHSAS 18000: 1999) 2.3 Occupational Safety and Health Act 1994 (OSHA) The Occupational Safety and Health Act 1994 provides a legislative framework to stimulate and encourage high standards of safety and health at work and also promote safety and health awareness and establish effective safety organization through self-regulation. It consists of 15 parts and is an enabling measure superimposed over existing safety and health regulations. xxvi OSHA provisions prevail in the event of any conflict. Unlike the Factory and Machinery Acts 1967 (FMA), OSHA does not go into great detail regarding specific requirements instead it provides statutory guidelines on the duties of employers, employees, manufacturers and suppliers. It provides also for the implementation of industry codes of practice and the making of regulations. OSHA also sets out the framework of policy making body such as National Council for Occupational Safety and Health. A very important aspect of OSHA that departed from the earlier style of legislation is the application of the Act to “persons at work”. This means that many more people who were previously not covered are now embraced by the provision of the Act. 2.3.1 Objectives of OSHA 1994 Objective of OSHA 1994 are i. To secure the safety, health and welfare of persons against risks from work activity ii. To promote an environment which is adapted to physiological and psychological needs iii. To provide the means to progressively replace legislation by a system of regulations and approved industry codes of practice. 2.3.2 Scopes The Act also clearly defines the terms like “employee”, workplace” and “industry” to avoid misinterpretation or confusion among the users. With these clear definitions, the enforcement of the Act becomes more systematic and easy. “Employee” is defined as a person who is employed for wages under a contract of service or in connection with the work of an industry either permanent or temporary. xxvii Where else, “workplace” is defined as premises where person works or premises used for storage of plants substances. Meanwhile “industry” is defined as the public services, statutory authorities or any of the economic activities. Industries that are covered under OSHA 1994 are: 2.4 i. Manufacturing ii. Mining and quarrying iii. Construction iv. Agriculture, forestry and fishing v. Utilities including electricity, gas, water, sanitary services vi. Transport, storage and communication vii. Wholesale and retail trade viii. Hotel and restaurants ix. Finance, insurance, real estate and business services x. Public services and statutory authorities Hazard Identification, Risk Assessment, and Risk Control (HIRARC) The purpose of HIRARC is to provide a systematic and objective approach to assessing hazards and their associated risks that will provide an objective measure of an identified hazard as well as provide a method to control the risk. It is one of the general duties as prescribed under the Occupational Safety and Health Act 1994 (Act 514) for the employer to provide a safe workplaces to their employees and other related persons 2.5 Hazard Identification Hazard identification means the identification of undesired events that lead to the materialisation of the hazard and the mechanism by which those undesired events could occur. The purpose of hazard identification is to highlight the critical operations of tasks, that xxviii is, those tasks posing significant risks to the health and safety of employees as well as highlighting those hazards pertaining to certain equipment due to energy sources, working conditions or activities performed. Hazards can be divided into three main groups, health hazards, safety hazards, and environmental hazards. 2.5.1 Health Hazard An occupational health hazard is any agent that can cause illness to an individual. A health hazard may produce serious and immediate (acute) affects, or may cause long-term (chronic) problems. All or part of the body may be affected. Someone with an occupational illness may not recognize the symptoms immediately. For example, noise-induced hearing loss is often difficult for the affected individual to detect until it is well advanced. Hazards include chemicals (such as battery acid and solvents), biological hazards (such as bacteria, viruses, dusts and molds), physical agents (energy sources strong enough to harm the body, such as electric currents, heat, light, vibration, noise and radiation) and work design (ergonomic) hazards. 2.5.2 Safety Hazard A safety hazard is any force strong enough to cause injury, or damage to property. An injury caused by a safety hazard is usually obvious. For example, a worker may be badly cut. Safety hazards cause harm when workplace controls are not adequate. Some examples of safety hazards include, but are not limited to – i. slipping/tripping hazards (such as wires run across floors); ii. fire hazards (from flammable materials); iii. moving parts of machinery, tools and equipment (such as pinch and nip points); iv. work at height (such as work done on scaffolds); v. ejection of material (such as from molding); xxix vi. pressure systems (such as steam boilers and pipes); vii. vehicles (such as forklifts and trucks); viii. lifting and other manual handling operations; and working alone. 2.5.3 Environmental Hazard An environmental hazard is a release to the environment that may cause harm or deleterious effects. An environmental release may not be obvious. For example, a worker who drains a glycol system and releases the liquid to a storm sewer may not be aware, of the effect on the environment. Environmental hazards cause harm when controls and work procedures are not followed. 2.5.4 Hazard Identification Technique The employer shall develop a hazard identification and assessment methodology taking into account the following documents and information – a) any hazardous occurrence investigation reports; b) first aid records and minor injury records; c) work place health protection programs; d) any results of work place inspections; e) any employee complaints and comments; f) any government or employer reports, studies and tests concerning the health and safety of employees; g) any reports made under the regulation of Occupational Safety and Health Act,1994 h) the record of hazardous substances; and any other relevant information. 2.6 Analyze and Estimate.Risk xxx Risk is the determination of likelihood and severity of the credible accident/event sequences in order to determine magnitude and to prioritize identified hazards. It can be done by qualitative, quantitative or semi quantitative method. A qualitative analysis uses words to describe the magnitude of potential severity and the likelihood that those severity will occur. These scales can be adapted or adjusted to suit the circumstances and different descriptions may be used for different risks. This method uses expert knowledge and experience to determine likelihood and severity category. In semi-quantitative analysis, qualitative scales such as those described above are given values. The objective is to produce a more expanded ranking scale than is usually achieved in qualitative analysis. Quantitative analysis uses numerical values (rather than descriptive scales used in qualitative and semi-quantitative analysis) for both severity and likelihood using data from a variety of sources such as past accident and from scientific research. Severity may be determined by modelling the outcomes of an event or set of events, or by extrapolation from experimental studies or past data. Severity may be expressed in terms of monetary, technical or human impact criteria, or any of the other criteria. The way in which severity and likelihood are expressed and the ways in which they are combined to provide a level of risk will vary according to the type of risk and the purpose for which the risk assessment output is to be used. 2.6.1 Likelihood of an Occurrence This value is based on the likelihood of an event occurring. Assessing likelihood is based on worker experience, analysis or measurement. Likelihood levels range from “most likely” to “inconceivable.” For example, a small spill of bleach from a container when filling xxxi a spray bottle is most likely to occur during every shift. Alternatively, a leak of diesel fuel from a secure holding tank may be less probable. Table 2.0 shows likelihood and ratings. Table 2.0 Likelihood of an occurrence LIKELIHOOD (L) EXAMPLE RATING Most likely The most likely result of the 5 hazard/event being realized possible Has a good chance of occurring and is 4 not unusual conceivable Might occur at sometime in the future 3 Remote Has not been known to occur after 2 many years Inconceivable Is practically impossible and has never 1 occured 2.6.2 Severity of Hazard Severity can be divided into five categories. Severity is based upon an increasing level of severity to an individual’s health, the environment, or to property. Table 2.1 shows severity of hazards. Table 2.1 Severity of hazard SEVERITY(S) EXAMPLE RATING Catastrophic Numerous fatalities,irrecoverable 5 property damage and productivity Fatal Approximately one single fatality or major property damage if hazard is 4 xxxii realized Serious Non-fatal injury,permanent disability 3 Minor Disabling but not permanent injury 2 Negligible Minor abrasions,bruises,cuts,first aid 1 type injury 2.6.3 Risk Assessment Risk assessment is an overall process of estimation the magnitude of risk and deciding whether or not the risk is tolerable. Risk can be presented in variety of ways to communicate the results of analysis to make decision on risk control. For risk analysis that uses likelihood and severity in qualitative method, presenting result in a risk matrix is a very effective way of communicating the distribution of the risk throughout a plant and area in a workplace as shown in Table 2.2. Risk can be calculated using the following formula: L x S = Relative Risk L = Likelihood S = Severity Table 2.2 Risk matrix xxxiii To use this matrix, first find the severity column that best describes the outcome of risk. Then follow the likelihood row to find the description that best suits the likelihood that the severity will occur. The risk level is given in the box where the row and column meet. The relative risk value can be used to prioritize necessary actions to effectively manage work place hazards. Table 2.3 determines priority based on the following ranges: Table 2.3 Risk level from risk matrix 2.7 Sand Casting Process xxxiv Figure 2.0. Outline of production steps in a typical sand casting operation Figure 2.0 shows outline of production steps in a typical sand casting operation. The main generic processes in foundries are listed below; a. Pattern/tool making b. Mould preparation c. Metal preparation d. Metal melting e. Casting f. Removal of castings g. Fettling and finishing h. Heat treatment i. Material handling and packaging. Most founding establishments will involve all or some of the above and many of these processes will involve significant hazards which will require effective management. What follows is a brief description of each process, a general statement about the process, and a list of possible hazards. 2.7.1 Pattern/Making Pattern making is the process of manufacturing the tooling for producing the final component from the metal casting process. Pattern making involves a number of processes which may be hazardous. Woodworking machinery, wood dust, noise, and chemicals are all found in pattern making workshops. The use of epoxy resins and related chemicals is a particular hazard. Potential hazards include woodworking machinery, metalworking machinery, noise, dust, chemical solvents, hand tools, material and manual handling fumes. xxxv 2.7.2 Mould Preparation This is a process by which a mould is formed, by manual or mechanical means. It is a vessel which is the reverse image of the final component into which the molten metal is poured. Moulds and cores are usually made of quartzose sand bonded with clay or other materials such as silicates, resins and isocyanates. The moulding sand is packed around the pattern within a moulding box to form a mould section. The complete mould may consist of an assembly of two or more sections or parts. Potential hazards in mold preparation are moulding machines, dust, noise or vibration, chemical solvents, fumes, manual handling, heat and flames. 2.7.3 Metal Preparation This is the process of segregation and preparation of alloys and scrap prior to the melting process. Metal is prepared and weighed ready for the furnace. Depending on the type of foundry, the metal will include pig iron, metal ingots, and scrap. Sorting out undesirable or unsatisfactory metal will be an important process. Metal containing contaminants such as lead based paint should be excluded as well as items such as porcelain baths. For safety reasons metal being added to a hot furnace must be dry. Potential hazards are sharp edges, hot material, dust, sparks, material manual handling, toxic waste and heavy metal contamination. 2.7.4 Metal Melting This is the process by which metals are melted to a controlled temperature and composition. Metal, which may be steel, stainless steel, iron, aluminium, bronze, brass and various alloys, may be melted by: electric arc, resistance or induction. a cupola furnace using coke; or oil or gas burning furnaces. Molten metal may then be metallurgically processed xxxvi before being transferred to the mould by ladle or other means. Potential hazards in melting are moisture, fumes, explosions, equipment failure and material manual handling. 2.7.5 Casting This is the process of transferring the molten metal into the prepared mould for solidification. The molten metal is poured into moulds by any one of a number of methods depending on the process used but will usually involve a refractory lined steel. When molten metal is poured into sand moulds the sand is subjected to a high temperature (about 1600ºC in the case of steel). This temperature is sufficient to convert some of the quartz in the sand of the mould to cristobalite which is a significant respiratory hazard. Potential hazards are molten metal, latent heat, fumes, dusts, material manual handling, equipment failure, moisture and explosions. 2.7.6 Removal of Castings This is the process of removing the casting from the moulding medium in preparation for fettling and finishing. The process of removing the casting from the mould, is known as knockout or shakeout. The cool casting is removed by knocking it away from the mould by hand or using vibrators or pneumatic tools. Significant noise and dust hazards are created by these processes. Runners, risers and parts of the casting not forming part of the finished article, are removed by knocking or sawing from the casting, which is then ground on a grinding wheel to remove flashes, rough edges and runner remnants. Castings are usually dressed by fettling or abrasive blasting but small items may be rumbled in rotating drums. Potential hazards are noise, dusts, fumes, heat, sharp edges, manual material handling and waste. 2.7.7 Fettling and Finishing xxxvii This is the process of removing excess material from the casting to meet specified dimensions. Fettling and finishing involves a number of different processes depending on the type of foundry. This is an area in which many different types of hazards are found making it an important place to implement proper controls. Potential hazards are noise or vibration, dusts, thermal cutting, fumes, sharp edges, grinding and cutting machine, abrasive cleaning, and mechanical manual handling. 2.7.8 Heat Treatment This is the process of enhancing the metallic structure and physical properties of the component by the use of controlled temperatures. Heat treatment will be used in specialize applications and because it involves heat, the danger from burns and other effects of heat need to be guarded against. Potential hazards are radiant heat, steam, mechanical or manual handling, chemicals, fire, explosions, dust, waste, fume and equipment failure. 2.7.9 Material Handling and Packaging This is the process of handling materials throughout the casting process and the presentation of components for dispatch to meet customer specifications. Potential hazards are manual material handling, sharp edges, lack of traceability and incorrect storage and stacking. 2.8 Accident in Foundries xxxviii Injuries experienced at a metal foundry depended on the employee’s job category, workstation, and length of employment. Employees faced different levels of risk depending on what they did, and where they actually performed their job. The Bureau of Labor Statistics USA estimated a 1992 injury rate for the iron and steel industry of 27.7 nonfatal injuries and illnesses per 100 full-time workers (National Safety Council USA, 1994), compared to a rate of 12.5 for general manufacturing jobs. The foundry recorded 846 accidents between 1980 and 1995, or 75.5 per 100 workers per year. This accident caused 2,251 lost work-days due to injuries, or 2001 per 100 workers. The nominal accident rate was high compared to the 27.7 per 100 workers reported for the iron and steel industry overall in 1992, but this was largely due to high number of mild eye injuries (foreign particles in eyes) recorded for grinders (Terry Dell and Berkhout year). The highest number of injuries involved foreign particles in eyes (40%), strains, pulls and tears (31%), bruises (11%), cuts and puncture wounds (9%), burns and scalds (5%), and broken bones (4%). Particle injuries were obviously more important than any of the other physical injuries recorded in the foundries. 2.9 Types of Dust Dust is one of the most common hazards likely to be found in foundries. The dust can be in the form of fine respirable particles, and depending on the type of foundry and the processes used, may contain significant amount of silica, lead, or other contaminants. i) Respirable Siliceous Dust In some metal casting processes respirable siliceous dust is produced as a product of furnaces, moulding sand, knockout and shakeout of castings, fettling and abrasive blasting. xxxix ii) Furnaces Repeated heating converts the quartz of the firebricks and silica refractory lining furnaces to amorphous silicates of cristobalite and tridymite. Workers maintaining and replacing the refractory material may be exposed to dust containing significant amounts of cristobalite which is highly fibrogenic (causing the disease silicosis if inhaled into the lung). In the past grouting material used to retain the firebricks often contained asbestos but this has now been superseded. A high degree of respiratory protection therefore will usually be required for workers during this process . iii) Moulding Heat from the molten metal in a sand mould produces two reactions. It reduces the sand-containing quartz in the mould to dangerously fine respirable particles and, it converts some into hazardous silicates, such as cristobalite. These forms of silica can cause the lung disease silicosis. This risk varies according to the efficiency of dust control, whether the sand is screened or not, and whether the mould is wet or dry. Some "parting powders", contain a high content of fine silica dust, and should not be used if possible. The use of compressed air to clean dust from moulds is likely to produce airborne respirable dust and should be avoided. iv) Sand Handling Sand will be handled in a variety of ways in the metal casting process, ranging from manual, pneumatic, or conveyors. Each method will produce significant amount of dust some of which contain airborne silica. Appropriate measures must be taken to control dust emissions, or the wearing of personal protection, whenever this occurs. v) Knockout/Shakeout of Castings xl During the knockout process there are a wide variety of dusts produced of which alumino silicates and alumina are the most common .These processes also liberate fine silica dust into the air and the environment of the foundry. If this dust is inhaled there is a risk of silicosis. Because fine dust is raised from the floor as airborne particles by draughts, people walking over the floor, and movement of vehicles such as forklifts, total dust control is an important item in plant housekeeping and hazard management. vi) Pattern Shop The increased use of particle board in pattern making causes increased levels of wood dust and formaldehyde binders which are both recognised health hazards. vii) Core Making There are a variety of mineral sands used in core making. These can include zircon, chromate, magnesite and alumina silicates. In keeping with good work practices exposure to these dusts should be avoided by the use of appropriate control measures. viii) Metal Melting In this process, dust is generated, which will contain a wide variety of chemicals. These will be carried into the ventilation system where this is installed. If ventilation extraction is not installed, appropriate protective measures must be taken for workers in the area. xli 2.10 Noise Excessive noise is a common hazard in foundries and causes permanent occupational deafness to those exposed. Sources of noise include: i. Metal impacting upon metal (shakeout, core, knockout tumbling, chipping, handling and transport of castings); ii. Exhaust from compressed air operated machines and tools (moulding machines, chipping hammers, grinders, hoists); 2.11 iii. Electric furnaces, ladle heaters; iv. Conveyors; v. Wood saws and other machinery in the pattern shop; vi. Electric arc cutting; vii. Core blowers, sand slingers and high pressure moulding machines viii. Shot blasting. Vibration Grinders, pneumatic chipping hammers, chisels and electrically operated rotary grinders can produce "dead hand" or vibration white finger if used extensively. Where people are exposed to whole or part body vibration the exposure must be controlled within limits that protect them from adverse health effects. The condition usually affects both hands, with the index, ring and middle fingers suffering the most. 2.12 Manual Handling xlii Manual material handling is one of the major causes of severe industrial injury especially for back injury. Previous study about the effects of different mold heights and carrying distances on physiological responses and determine maximum acceptable task frequencies (MAF) for metal pouring. Many of these injuries arise from improper handling of materials. The direct and indirect costs are enormous, and the human suffering associated with low back injuries is immeasurable (Kroemer et al., 2001). In order to control the frequency, severity and tremendous economic losses of these injuries, a variety of research and design guidelines have been proposed (Davis and Stubbs, 1980: Waters et al., 1993; National Occupational Health and Safety Commission, 1995). In the 2004 annual report, Liberty Mutual Research Center for Safety published The Liberty Mutual Workplace Safety Index, which revealed that overexertion, comprising of injuries due to lifting, pulling, holding, carrying or throwing of an object, was the number one cause for workplace injuries in 2002 and ranked among the top five during the preceding years ( Fredericks,) Furthermore, back injuries result in much more lost job time (Chaffin,1987). The total cost of back injuries in the USA in 1991 was reported to be between 50 and 100 billion dollars (National Institute for Occupational Safety and Health,1997). A hazardous task observed in the foundry, which could contribute to low back injuries involves pouring molten metal. However, due to the high cost of automating metal pouring operations, many small scale foundries still utilize the manual method for pouring metal. Karim et al. (1998) conducted a study in a foundry to document energy expenditure while pouring metal at different combinations of mold heights and carrying distance. 2.13 Potential health risk in foundries The potential health risk in foundries are listed below; i. Occupational overuse syndrome (OOS) xliii ii. Cancer iii. Dermatitis iv. Stress v. Fatigue vi. Metal fume fever vii. Vibration white finger viii. Burns ix. Soft tissue injuries x. Lead poisoning xi. Respiratory disease xii. Sprains and strains xiii. Back injuries xiv. Eye injuries xv. Silicosis xvi. Noise-induced hearing loss 2.14 Methods to Control Workplace Hazards All workplace hazards (chemical, physical, etc.) can be controlled by variety of methods. The goal of controlling hazards is to prevent workers from being exposed to occupational hazards. Some methods of hazard control are more efficient than others, but a combination of methods usually provides a safer workplace than relying on only one method. Some methods of control are cheaper than others but may not provide the most effective way to reduce exposures. The most effective method of controlling hazards is to control at the source by eliminating the hazard or by substituting a hazardous agent or work process with a less dangerous one. Some methods to control workplace hazards such as : xliv i) Elimination Elimination of a specific hazard or hazardous work process, or preventing it from entering the workplace, is the most effective method of control. ii) Substitution If a particularly dangerous chemical or work process cannot be completely eliminated, then replace it with a safer substitute. iii) Engineering Controls There are a number of common control measures which are called “engineering controls”. These include enclosure, isolation and ventilation. a) Enclosure If a hazardous substance or work process cannot be eliminated or substituted, then enclosing it so workers are not exposed to the hazard is the next best method of control. Many hazards can be controlled by partially or totally enclosing the work process. Highly toxic materials that can be released into the air should be totally enclosed, usually by using a mechanical handling device or a closed glove system that can be operated from the outside. xlv b) Isolation Isolation can be an effective method of control if a hazardous job can be moved to a part of the workplace where fewer people will be exposed, or if a job can be changed to a shift when fewer people are exposed (such as a weekend or midnight shift). The worker can also be isolated from a hazardous job, for example by working in an air-conditioned control booth. c) Ventilation Ventilation in the workplace can be used for two reasons: (1) to prevent the work environment from being too hot, cold, dry or humid; (2) to prevent contaminants in the air from getting into the area where workers breathe. Generally there are two categories of ventilation: local exhaust ventilation and general ventilation. Whatever the type, ventilation should be used together with other methods of control. iv) Administrative Controls Administrative controls limiting the amount of time workers spend at a hazardous job can be used together with other methods of control to reduce exposure to hazards. Some examples of administrative controls include: a. Changing work schedules (for example, two people may be able to work for four hours each at a job instead of one person working for eight hours at that job). b. Giving workers longer rest periods or shorter work shifts to reduce exposure time. c. Moving a hazardous work process to an area where fewer people will be exposed. d. Changing a work process to a shift when fewer people are working. xlvi v) Personal Protective Equipment Personal protective equipment (PPE) is the least effective method of controlling occupational hazards and should be used only when other methods cannot control hazards sufficiently. PPE can be uncomfortable, can decrease work performance and can create new health and safety hazards. The appropriate use of personal protective equipment (PPE) can reduce injuries and illness (Breish, 1989; LaBar, 1990). According to OSHA statistics, about 12 – 14% of total disabling occupational injuries occurs because workers do not wear appropriate PPE (Breish, 1989). Several types of PPE are recommended or required at the plant a) Side-shield safety glasses are required on the factory floor. b) Safety goggles are worn when cleaning the mould in the moulding department. c) Face-shields are worn while servicing lift-truck batteries or handling water treatment corrosive liquids d) Leather shoes that cover the entire foot are required on the factory floor. e) Boot covers are recommended for painters and the workers who prime raw glass. f) Chemical-resistant gloves are worn when the workers are handling solvents and primers. g) Cut-resistant gloves are worn on the worker’s non dominant hand if a razor blade or utility knife is being used. h) Half-mask respirators with organic vapour cartridges are required when spraying the in-mould urethane coating. i) Hearing protection is mandatory in moulding and painting areas. j) Disposable coveralls are required when spray painting in the paint booth. k) Embossed polyurethane aprons are recommended when priming raw glass. l) Disposable sleeves are recommended for workers priming glass or spraying urethane paints in the moulding department. m) Sleeves also are available for workers using razor blades. n) Employees who have to lean against the metal frame of the clamp in the moulding department are advised to wear knee and elbow pads. xlvii 2.15 Conclusion This chapter is describes literature reviews related to safety and health hazard in foundry. The objective of this review is to understand safety hazard and control in foundry. xlviii CHAPTER 3 METHODOLOGY 3.1 Introduction This chapter discuss on the methodology to collect and analyze data to identify hazards and proposed control measures. The study focus on safety and health hazards in the casting area. 3.2 Justification for the Methodology In identifying the safety and health hazards, a few methods are used. The methods are: i. Questionnaire survey of the workers ii. Interviews with the workers and management iii. Observation and discussion iv. Information from the company xlix 3.2.1 Survey of Workers A survey was conducted by distributing questionnaire to casting plant workers. The responses from the workers are essential in determining the problem. The result of the survey can identify hazard and risk. The questionnaires were distributed to the workers. The workers are allowed to choose more than one answer if necessary. Additional comments from the workers can be stated in the columns provided. A sample of the survey question is shown in Appendix A. 3.2.2 Interviews An interview with workers and administrative staffs of casting plant was carried out. Questions related to safety and health hazards at workplace are asked. The feedbacks are important to obtain first-hand information in hazard identification and risk assessment. 3.2.3 Observation and Discussion Observation is conducted on the pouring process during working hours. Information on current work procedure and safety precautions that were used were obtained. Workers sometimes do not follow standard work procedure because of inconvenience. l Nevertheless, observation alone cannot gain much information. Discussion was made with the officer, supervisor and workers in order to get a better view of work procedures and safety precautions in the pouring process. Three different group of people were chosen for discussion to obtain information regarding safety problems in pouring process. The discussion was mainly about their opinion towards safety in the company. 3.2.4 Information from Company Information from the company is important to support information gathered by observation. The company did not have accident record. Information on safety precautions and work procedures is also important. 3.3 Research Procedures 3.3.1 Data Analysis The primary method used for data analysis is the survey. Questionnaires were distributed to 33 workers, (30 male and 3 female) at casting plant. The questionnaires listed questions on hazards in the casting plant. The workers are exposed to various hazards at any workstation in the casting plant and they can identify safety hazards. li In this study, the questionnaire was divided in to 6 areas, background of workers, types of accidents, health problem, personal protective equipment, manual handling and heat stress. The main objective is to get information on safety and health hazard among workers at casting plant. Charts will be used to analyze the questionnaire. Once safety and health hazard has been identified, brainstorming and discussion will be held to determine possible solutions to improve safety and health condition at casting plant. The secondary method used for data analysis is by referring to guidelines for hazard identification, risk assessment and risk control (HIRARC). The purpose of this guideline is to provide a systematic and objective approach to assessing hazards and their associated risks to provide an objective measure of identified hazards as well as to provide methods to control risk. 3.3.2 Planning and Conducting HIRARC The purpose of HIRARC is to identify all factors that can cause harm to employees. Figure 3.1 shows the flowchart of HIRARC process. lii Classify work activities Review Consultation Review Identify hazards Review Risk assessment Prepare risk control action plan (if necessary) Implement Figure 3.1 HIRARC process HIRARC process requires four simple steps; a) Classify work activities b) Identify hazard liii c) Conduct risk assessment (analyze and estimate risk from each hazard), by calculating or estimating: d) i. Likelihood of occurrence ii. Severity of hazard Decide if risk is tolerable and apply control measures (if necessary). 3.3.3 Risk Analysis This objective is to identify safety and health hazard during pouring process at pouring workstation and to determine risk control. The steps to conduct risk analysis are; a) Choose the work station to conduct risk analysis. The pouring workstation at casting plant is selected. b) Prepare a list of potential hazard for the workstation to be studied. Table 2.1 and Table 2.2 shows the severity of hazard and likelihood of occurrences. c) Prepare a risk analysis work sheet to record potential hazards. d) Carry out analysis. 3.4 Conclusion This chapter has explained the methodology applied in the project and the sequence to carry out the analysis. The casting plant does not have a proper safety management system. It is important to improve the company's safety condition to prevent accidents. liv CHAPTER 4 DATA COLLECTION AND ANALYSIS 4.1 Introduction This chapter discuss data collection and data analysis at casting plant. Data will be analyzed in tables and chart to ease the understanding. After data analysis, safety hazards can be identified and suggestion for improvement can be made. 4.2 Data Collection Data in this project is obtained from questionnaires that been given to the workers and interview with management. Some information is gathered by observation. Background of casting plant where this case study was carried out is explained. lv 4.2.1 Case Study Background 4.2.1.1 Casting plant Casting plant is a ferrous and non-ferrous foundry and started its operation in January 1994. The building is located on 40,000 square feet land in Bandar Darulaman Industrial Estate, Kedah. Casting plant is involved in casting of products such as agriculture machinery parts, manhole cover, waterworks/valve, heavy machinenery parts and replacement parts for industrial used. In 1999 casting plant has diversified its operations to include fabrication works, general engineering and machining. 4.2.1.2 Casting plant Organization Figure 4.1 shows the organization chart of casting plant. The company has two main departments, administration and production department. Production at casting plant has two sections; factory and foundry. Each department is managed by one manager. Each manager reports to the managing director. This project will focus on foundry section. The foundry section has 33 personnel, 30 male and 3 female staffs. lvi Managing Director Director Administration Sales & Purchasing Dept Production Account Dept HR Dept Factory Manager Foundry Manager Machining & Fabrication Sectioning Foundry Section Figure 4.1 Organization chart at casting plant 4.2.1.3 Casting Plant Plant Layout The total land area of this company is 40,000 square feet. The foundry area 25,150 square feet and the rest is fabrication area. The foundry area has three major departments; moulding, pouring and shakeout. lvii Figure 4.2 Foundry layout Figure 4.3 Machining and fabrication layout lviii 4.2.1.4 Process Flow Chart of Casting Plant Figure 4.4 shows the process flowchart for casting at casting plant. In casting plant has three main activities; pattern making, prepare mold and core and pouring process. In the sand casting process, pattern is made in the shape of the desired part. The pattern is typically made of wood, plastic, or metal. Basically, sand casting operations use silica sand (SiO²) as mold material and making core. In sand mixing machine, sand is mixed together with natrium silicate for mould making and core. CO2 are using to harden the mold and core. Next, the mold must be coated and dried before pouring molten metal into mold. Coating is to avoid air and moisture trapped in the mold. Molten material is poured in the pouring cup, which is part of the gating system that supplies molten material to the mold cavity. After solidification, the casting is shaken out of its mold, and the sand and oxide layers adhering to the casting are removed by sand blasting. Casting product is cleaned by blasting with steel short. The casting subsequently may be heat treated to improve certain properties required for its intended service use; these processes are important, particularly for steel castings. Finishing operations may involve machining and grinding to obtain final dimensions. Inspection is an important final step and is carried out to ensure that the casting meets all design and quality control requirements. lix Figure 4.4 Casting process flowcharts 4.2.2 Casting Plant Safety Report Casting plant safety report shows accident record from January 2000 until October 2009, data of medical certificate and accident data in 2009. lx 4.2.2.1 Accident Reports from January 2000 until October 2009 Accidents at workplace can happen if the procedures or rules are not followed. Statistics of accident starting from January 2000 until October 2009 shows that the number of accidents at casting plant decreased every year. Total numbers of accidents in 2000, 2004 and 2007 are high compared to other years. Table 4.1 shows the statistic of accidents at casting plant from January 2000 until October 2009. The company should take necessary actions to reduce the accidents rate and also to ensure safety at workplace. The results from the analysis done at the factory, several factors that contribute to accident are machine, splashed molten metal and unsafe work method: Table 4.1 Industrial accidents from January 2000 until October 2009 NO. OF CASES/ ACCIDENTS MONTH 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 January 1 0 0 1 0 0 1 0 0 1 February 0 0 1 2 1 0 0 1 0 0 March 2 0 0 1 0 1 2 0 1 0 April 1 0 1 0 1 0 1 1 0 2 May 0 1 1 0 1 0 0 1 0 0 June 0 0 2 0 2 0 1 2 0 0 July 2 0 1 0 1 0 0 1 0 1 August 0 1 1 0 1 0 0 1 2 0 September 0 1 1 0 1 0 0 1 1 1 October 1 0 0 1 3 1 0 2 1 November 1 0 0 0 0 1 0 1 1 December 2 0 0 0 0 1 0 1 0 TOTAL 10 3 8 5 11 4 5 12 6 5 lxi 4.2.2.2 Total Lost Time Injury Table 4.2 show the data of loss time injury based on medical certificate of workers. Year 2000 and 2007 shows increasing trend with 15 days medical certificate. From year 2001 until 2006 (except 2004) data shows that medical certificate was less than 10 days. The medical certificate was given to workers when they got injured during working days. TOTAL (DAYS) 2000 15 Table 4.2 Data of lost time injury (M/C) YEAR (JAN – DEC) 2001 2002 2003 2004 2005 2006 2007 4 10 5 11 4 8 15 2008 6 4.2.2.3 Data of Accidents in 2009 Table 4.3 shows data of accidents at for 2009. Table 4.1, shows one case in at January and Table 4.3 described the type of accident. On 21st January, worker 2 was injured because flying splinter to hit his face whiles making pattern of mold. There were two cases in April involving worker 27 and worker 15. Worker 27 was working at the pouring process, but his foot was injured when his nail was crushed. Workers 15 got injured when flying particles hit his stomach and hand. In September, Worker 33 was working at shakeout injured his right hand thumb when he wanted to lift the casting product. lxii DATE WORKER 21-Jan Worker 2 6-Apr Worker 27 23-Apr Worker 15 3-Sep Worker 33 Table 4.3 Data of accidents M/C JOB INJURED MACHINED (DAYS) PART INVOLVED 1 Pattern Face injured Cutting saw Maker (flying wood splinter) 2 Pouring R/L foot No machine (nail crushed) involved 1 Pouring Flying No machine particles on involved stomach and hand 1 Shakeout R/H thumb No machine ( nail portion involved crushed) 4.2.3 Indoor Air Quality (IAQ) Monitor Indoor air quality equipment, are used for monitoring indoor air environment such as temperature, humidity, gases including carbon dioxide, ammonia, carbon monoxide, and chlorine. IAQ monitor are used at buildings that are served by a common ventilation and/or air conditioning system. Figure 4.5 shows the layout of the pouring area. The IAQ measurement data was taken based on the layout. The pouring area are divided into two sections; pouring process with 64 points and furnace with 24 points. The data for one location at pouring process was taken three times in two minutes duration and distance point to point is 5 feet (y-axis) and 4.5 feet (x-axis). The data for one location at the furnace was taken three times in two minutes duration and distance point to point is 3.5 feet (y-axis) and 4feet (x-axis). The indicator for each point in Figure 4.5; for example A#8 means pouring process location A at point 8 and F#1 means furnace area at point 1. The red circle shows that casting plant placed three fans at pouring process and one fan at furnace. lxiii All sample data were taken using Indoor Air Quality Monitor as shown in Appendix C. Figure 4.5 Layout of pouring area. lxiv 4.2.4 Questionnaires There are 25 questions in the questionnaire form. Thirty-three forms were distributed to all workers in all departments. The questionnaires are categorized in three categories, work background, workplace environment and work safety. All feedbacks from the questionnaire will be discussed in data analysis. 4.2.5 Observation Figure 4.5 until Figure 4.10 shows the work environment at pouring area. Figure 4.5 shows the manual material handling. The height of is mold 15 cm from the ground. Figure 4.6 Manual material handling lxv Figure 4.7 Pouring process Figure 4.8 Ventilation system lxvi Figure 4.9 Pouring area Figure 4.10 Furnace area 4.3 Data Analysis 4.3.1 Analysis of Questionnaire lxvii 4.3.1.1 Work Background Table 4.4 shows background of workers such as gender, age, race, education, working experience, smoking status and safety training. All results are described in Appendix B. Table 4.4 Background of workers BACKGROUND ( WORKER CHARACTERISTICS ) CHARACTERISTICS MALE Number of Workers Age ( years ): Min Max Race: Malay Indian Education: Primary Secondary College / IKM Experience in Occupation: < 1 years 1 ‐ 5 years 6 ‐ 10 years > 11 years Smoking Status: Yes No Received Safety Training: Yes No 4.3.1.2 Workplace Environment FEMALE 30 3 27 32 50 35 29 1 1 2 1 24 1 2 5 0 0 5 18 0 2 1 7 0 2 0 27 0 10 20 1 2 lxviii Workplace environment is the second questionnaire. There have Seven types of hazards are asked: back injury, hot environment, dust, poor ventilation, lighting, noise and chemical hazard. All data from questionnaire are analyzed and summarized in Table 4.5. Back injury is main problem because they need to lift and carry heavy object such as the mold. The second problem is hot environment especially at pouring process and furnace, followed by dust and poor ventilation. Other problems are lighting, noise and chemical hazard. Table 4.5 summarized the hazards. Problems Back injury Hot environment Dust Poor ventilation Lighting Noise Chemical hazard Table 4.5 Types of problem Number of workers Number of workers ( 33 workers) ( in percentages) 30 27 25 18 10 5 3 90.91% 81.82% 75.76% 54.55% 30.30% 15.15% 9.09% Figure 4.11 Pareto diagram on types of problem lxix Table 4.6 shows the number of injuries by job categories. There are seven job categories which are hot metal works, mold making, coating, shakeout, sand casting, coremakers and grinders. Mostly accident occurs at hot metal works and mold making. Table 4.6 Number of injuries by job categories Job categories Number of workers (Accident/Injury) ( 33 workers) Hot metal work Molders Coating Shakeout Sand blasting Coremakers Grinders Pattern makers Heat treatment 17 13 8 7 6 4 4 2 1 Figure 4.12 Pareto diagram for number of injuries by job categories lxx Table 4.7 shows the number of frequency of accident. This data extracted from Table 4.7.The highest number of injuries occurs at hot metal works followed mold making and shakeout, coating, grinders and coremakers Table 4.7 Frequency of accident Number of workers Frequency of injured Hot metal work Molders Shakeout Coating Grinders Coremakers Sand blasting Pattern makers Heat treatment 1x 2x 3x~5x 6x~10x >10x 1 1 1 1 1 1 2 1 1 2 1 1 1 1 1 3 0 0 2 3 0 2 0 1 0 1 0 1 1 0 0 0 0 0 0 0 11 7 5 4 2 1 1 0 0 Figure 4.13 Pareto diagram of accident frequency lxxi Workplace environment is the second categories in the questionnaire. There were seven types of health hazards which are back injury, hot environment, dust, poor ventilation, lighting, noise and chemical hazard. 4.3.1.3 Work Safety Third categories in the questionnaire are work safety and focused on safety hazards and personal protective equipment (PPE). PPE is important to protect workers from any accidents. Table 4.8 shows seven types of PPE such as safety boots, gloves, goggles, mask, apron, ear protection and face shield. Most workers wear safety boots at the plant Table 4.9 shows the data for parts of body which are in accidents are injured. There are nine job categories: pattern markers, molders, core makers, coating, hot metal works, shakeout, grinders, sand blasting and heat treatment. Nine parts of body frequently injured are head/hair, face, eye, nose, ear, finger, hand, body and leg. The data shows that most workers obtain have injury at the head, body and hand at hot metal work. lxxii Table 4.8 Number of workers using PPE PPE Number of workers using PPE Safety boot 33 Gloves 12 Googles 11 Mask 3 Apron 2 Ear protection 1 Face shield 0 Figure 4.14 Pareto diagram on the number of worker using PPE lxxiii Table 4.9 Data for injured body parts Number of workers Part of Hot Pattern Core Sand Heat body Molders Coating metal Shakeout Grinders makers makers blasting treatment injured work head/ 0 1 0 0 15 1 1 1 1 hair face 1 1 1 1 2 5 1 2 0 eye 1 3 1 1 0 25 0 6 0 nose 0 4 1 0 0 25 0 4 0 ear 0 7 1 0 0 15 0 1 0 finger 1 8 4 6 10 5 2 3 0 hand 1 16 4 9 15 5 3 5 1 body 0 4 4 0 15 4 4 0 0 leg 0 8 4 5 8 2 1 1 0 4.3.2 Analysis of Indoor Air Quality Monitor All temperature measurements were taken using Indoor Qir Quality Monitor as summarized in Figure 4.15, Table 4.10 and Table 4.11. The range of temperature was classified into four different colours; red for hot temperature above 43ºC, green for temperature above 42ºC, blue for temperature above 41ºC, and purple for temperature below 40ºC. The results show that purple indicate low temperature of less than 40ºC because closes with window and fan (see Figure 4.5). lxxiv Figure 4.15 Layout of pouring area with ambient temperature Table 4.10 Temperature at pouring area LOCATION & POINT AT POURING #1 #2 #3 #4 #5 #6 #7 #8 DSB_A 34.45 35.20 35.50 36.15 36.65 37.05 37.45 37.88 DSB_B 31.05 39.30 39.55 40.05 40.85 41.25 41.65 41.95 DSB_C 42.00 42.35 42.65 42.50 42.35 43.00 43.00 43.10 DSB_D 42.80 42.80 42.90 43.10 43.00 43.50 43.30 43.40 DSB_E 42.05 42.40 42.60 42.70 42.80 42.90 43.00 43.00 DSB_F 42.45 42.55 42.65 42.70 42.70 42.70 42.75 42.75 DSB_G 42.30 42.40 42.55 42.60 42.65 42.70 42.75 42.80 DSB_H 41.55 41.80 41.85 41.90 42.00 42.10 42.20 42.25 lxxv Table 4.11 Temperature at Furnace LOCATION & POINT AT FURNACE F# 1 F#2 F#3 F#4 F#5 F#6 F#7 F#8 41.80 41.80 41.93 42.10 42.20 42.35 42.85 43.00 F#9 F#10 F# 11 F#12 F#13 F#14 F#15 F#16 43.55 43.30 43.10 42.45 42.60 42.70 43.25 43.65 F#17 F#18 F#19 F#20 F#21 F#22 F#23 F#24 43.50 43.25 42.85 42.50 42.40 42.30 42.00 42.10 4.3.3 Analysis of Observation using HIRARC The purpose of HIRARC is to identify all the factors that may cause harm to employees and others. Figure 3.1 shows the flowchart of HIRARC process. Table 4.12 shows the HIRARC pouring process which is determined potential hazard, severity, likelihood and risk of each activity at pouring process. At the pouring process have three major activities; prepare the molten metal, scooped perlite and poured into furnace to remove foreign particles and poured molten metal into mold solidification. The indicator of colour red and yellow showed in Table 2.1 until Table 2.4. lxxvi Table 4.12 HIRARC of Pouring Process No Activity 1. Prepare the molten metal 2. Scooped perlite and poured into furnace to remove foreign particles 3. Poured molten metal into mold for solidification Potential Hazard Severit y Like lihood Risk 1. Sharp edge from scrap 2 4 8 2. Sparks / dust from furnace 3 5 15 3. Toxic waste 4 2 8 4. Heavy metal contamination 3 3 9 5. Splash from molten metal 4 3 12 1. Extreme heat and temperature 2 5 10 2. Fumes from furnace 3 4 12 3. Explosions while equipment failure 5 2 10 1. Sparks hot metal 3 5 15 2. Back injury while poured 3 5 15 3. Dust 3 4 12 4. Fumes from molten metal 3 4 12 5. Explosion 5 4 20 6. Leg injury while mold failure 3 4 12 7. Hand injury while carry weighted into mold 3 5 15 lxxvii 4.4 Problem Identification After data collection and analysis casting plant has two main hazards. i. Working condition not ergonomic which can cause back injury and hand injury due to poor material handling while pouring. ii. 4.5 Poor ventilation which cause employees to be exposed to dust, fume, glare and heat. Summary From data collection and analysis, pouring area has two main hazards which are material handling and ventilation. There is no mechanized material handling to minimize back injury. At pouring area, the workers exposed to dust, fume, glare and extreme heat due to insufficient ventilation. lxxviii CHAPTER 5 PROPOSED SOLUTIONS 5.1 Introduction This chapter discussed proposed solutions to control health hazards at pouring area. 5.2 Proposed Solution To ensure that the hazards identified can be controlled, two proposed solutions are developed for the each of the hazards. i. Poor material handling – the main cause of this problem is the workers have to use manual handling during pouring of molten metal. Replacing manual material handling with pouring trolley and can minimize back injury. The pouring trolley can carry molten metal up to 35kg – based on Finite Element Analysis. lxxix ii. Poor ventilation system – the can cause too much dust, smoke and heat at pouring area especially around the furnace. Install ventilation system at pouring area to minimize heat and dust. 5.2.1 Proposed Solution for Manual Handling Manual material handling has been known to be one of the prime causes of back injury. Many of these injuries arise from improper handling of materials. The direct and indirect costs are enormous, and the human suffering associated with low back injuries is immeasurable (Kroemer et al., 2001). In order to control the frequency and severity injuries, a pouring trolley has been proposed to replace manual handling. 5.2.1.1 Pouring Trolley Design. Pouring trolley can be used at the casting plant to replace manual pouring. Figure 5.1 shows the design of pouring. The material selected for the pouring trolley is carbon steel. The steel has good mechanical properties and cost effective. The dimension of this part is 1000 mm L x 500 mm W x 750 mm H. The height of the trolley is at the waist of the workers according to ISO Std 7250, Body Human Measurement. The width of trolley is based on length and width of the mold. The design require a table to place the mold which is 15cm (see Figure 5.2).the Figure 5.2 shows the technique to pour the molten metal using the trolley. lxxx The ladle is the same one currently used at the company. (Figure 5.3).Different size of ladle can be used with the trolley for weight range between 35 kg to 70 kg. Tungsten inert gas welding (TIG) is used to fabricate the pouring trolley.TIG welding is suitable especially for thin metals. The cost of the inert gas makes this process more expensive but provides welds with very high quality and surface finish. The advantages of using pouring trolley is that the workers do not need to bend their body while pouring molten metal into the mold, The workers only need to stand, hold the ladle and turn to the left/ right simultaneously. After that, the workers can move ladle and pour or again until the molten metal is finished.This way back pain can be reduced. Figure 5.1 Pouring trolley design lxxxi Figure 5.2 Methods when using pouring trolley. Figure 5.3 Types of ladle 5.2.1.2 Analysis of Pouring Trolley lxxxii The design of the pouring trolley is analyzed using MSC Patran Version 2005 The pouring trolley is analyzed using static analysis. The model consists of carbon steel angle iron 20 mm by 20 mm width and 3 mm thickness.. The dimension of the pouring trolley is 1000 mm length and 500 mm width and750 mm height. First step is to prepare the model geometry and then define the materials, define the properties of the elements, mesh the geometry, and then apply the constraints and loads (see Appendix F. Figure 5.4 Result of stress analysis of pouring trolley design Figure 5 shows the stress analysis for the pouring trolley. Load is placed in the middle of the trolley and gradually increased until it reached the point of failure. lxxxiii Table 5.1 Finite element result PROPERTIES IN NASTRAN LOAD (kg) FORCE (N) MAX. STRESS (N/mm²) MAX. DEFORMATION (N/mm²) YIELD STRENGTH (255 N/mm²) 35 350 @ 175 121 4.63 PASS 45 450 @ 225 156 5.95 PASS 55 550 @ 275 191 7.27 PASS 65 650 @ 325 226 8.59 PASS 70 700 @ 350 242 9.24 PASS 75 750 @ 375 261 9.91 ‘ FAIL ‘ 85 850 @ 425 296 11.23 ‘ FAIL ‘ 95 950 @ 475 331 12.55 ‘ FAIL ‘ 100 1000 @ 500 347 13.2 ‘ FAIL ‘ 200 2000 @ 1000 693 26.4 ‘ FAIL ‘ Table 5.1 shows the finite element analysis of the pouring trolley using MSC/Patran. This analysis starts with minimum load of 35 kg. To ensure a safe design, maximum stress should be less than yield strength of carbon steel. The analysis start with 35 kg weight and the maximum stress is 121.Tis trolley can support load range until 70 kg. The pouring trolley start to fail when the load exceed 75 kg. 5.2.2 Local Exhaust Ventilation System lxxxiv 5.2.2.1 Calculation and Analysis of Local Exhaust Ventilation System All calculations of the ventilation system are based on Ductulator, English and SI Metric units. The Ductulator is an accurate, easy-to-use calculating device that aids in the design layout of air handling systems, sizing of ducts and reviewing the existing duct. With a single setting, the dimensions of any duct size problem may be read directly from the face of the Ductulator. Conversion of units, English-to-metric, or vice versa, is accomplished by setting-up reading on the scales of one unit system, reversing sides of the Ductulator, and reading the converted values from the scales of the other unit. Ductulator English Units required air volume in CFM (outer blue and red bands) is first established With only one of the four following factors known, the other three are found from a single setting of the Ductulator. i. Friction in inches of water per 100’ of duct............... (inner blue band) ii. Desired velocity in feet/minute (FPM) in round duct...(inner red band) iii. Round duct diameter (inches)............................... (window) iv. Dimensions for rectangular ducts (inches).............. (green band) Procedure: With the friction per 100’ of duct known, set this friction (inner blue band) opposite required CFM (outer blue band). The resulting velocity in round duct (inner red band) coincides with established CFM in outer band. Round duct diameter is indicated in window by arrow. Various equivalent rectangular duct sizes are read from green bands. Calculation for ventilation system based on Ductulator following below; Dimension of space 45’ x 49’ x 15’ = 33075 ft³ lxxxv Ventilation standard for: Factory + Process + Heat = 10 air change/hour Ventilation Air : Volume x 10 Ac/hr = 330750 ft³/hr = 5521.5 ft³/min Six inlet @ 920 cfm/each The required ventilation is 920 cfm from 6 inlets. The location of the inlet must be very close to the source of contaminants. 5.2.2.3 Design of Local Exhaust Ventilation System Using AutoCAD 2002 Based on calculation and analysis, The local exhaust ventilation require with six inlets with 920 cfm/each. The LEV is capable to remove odors, fumes, dust and heat from an enclosed occupied space. Such exhaust may be of the natural variety or may be mechanical by means of roof or wall exhaust fans or mechanical exhaust systems. Figure 5.14 shows the plan view of local exhaust ventilation system and Figure 5.15 shows the front view with the dimension. Each inlet will suck out air 920 cfm. Initially, two inlets will remove air 920 cfm through the duct with 10.inch’ diameter ducting pipe. Initially and at the second stage at pouring process, the air will flow out through duct size of 12.inch’ diameter ducting pipe because the air inside is flowing at1840 cfm. The duct size at second stage is bigger than the first one because of increasing volume of air 1840 cfm. The third stage is at the furnace area where the duct size is 12.inch’ diameter. Each inlet at the furnace will remove 920 cfm of air and will be joined together with air inlet from pouring area. The lxxxvi total volume of ventilation air is 5520 cfm and passing through the duct size of 16’ inch diameter and 18’inch diameter passing through the exhaust fan with capacity 5520 cfm. Figure 5.5 LEV ducting design lxxxvii Figure 5.6 LEV location Figure 5.16 shows the design of local exhaust ventilation system at pouring area. The location of LEV is based on data collection and analysis. The LEV inlet is installed at area where the temperature is above 43°C. lxxxviii Figure 5.7 Location of LEV with respect to ambient temperature. 5.3 Summary This chapter has discussed the proposed solutions to reduce hazards at the casting plant. The use of pouring trolley can minimize back pain . The installation of local exhaust ventilation can reduce extreme heat and dust from the sand casting process. lxxxix CHAPTER 6 CONCLUSIONS AND FUTURE WORKS 6.1 Introduction This chapter discuss conclusions of this project. The first part summarizes the project and the second part is recommendation for future works. 6.2 Conclusion This project study health hazards at casting plant, namely manual handling and heat stress. This project started with review of the literature, questionnaire survey and observation at the casting plant to identify health hazards. The first objective of the project is to identify health hazards and assess risk and develop control measures. Data collections are done through survey, observation and indoor air temperature measurement, data analysis, two problems were identified which are manual handling and heat stress. Two proposed safety improvements were developed. Pouring trolley xc was recommended to replace manual pouring to minimize back pain. This pouring trolley can also increase productivity. Local exhaust ventilation was recommended based on Indoor Air Quality Monitor data and analysis. The result showed that the temperature at pouring area is around 43.40ºC and a ventilation system is needed to replace the fan and suction fan. Local exhaust ventilation can reduce heat as well as dust. The use of pouring trolley and installation local exhaust ventilation can improve health and safety at the casting plant. 6.3 Recommendations for Future Works In this project, the focus on safety and health improvement is at sand casting process only. Future works should be directed to other improvement strategies and create a better working environment. The following are recommendations for future work; i. Study on the possibility of automating the pouring process. ii. Conduct a comprehensive audit for the casting plant. iii. Carry out force analysis for all manual operations. iv. Study on bio-mechanics of the workers. xci REFERENCES 1. Tycho K. Fredericks, Anil R. Kumar, Sadat Karim, An Ergonomics Evaluation of a Manual Metal Pouring Operation, 2008, 182-192. 2. Guidelines for Hazard Identification, Risk assessment and Risk Control (HIRARC), Department of Occupational Safety and Health , Ministry of Human Resources, Malaysia, 2008. JKPP DP 127/789/4-47. 3. Karim, S. Fredericks, Physiological cost of manual metal pouring operations. 1998, 29-33. 4. Itasca , National Safety Council (1994), Accidents Facts. 5. Farhang A.K and Michael S.B, Comfort of personal protective equipment, Applied Ergonomics , Vol.26, 1995,195-198. 6. Tasneem Abbasi, S.A. Abbasi, Dust Explosions- Cases, causes, consequence and control. 7. Chaffin, D.B, Manual material handling and the biomechanical basis for prevention of low back pain in industry.1987, 989-996. 8. Gettysburg College (February 2, 2007)., Personal Protective Equipment Program. 9. Purdue University (February 14, 2003)., Personal Protective Equipment(PPE) Policy. 2-5. 10. Breish, S. B, What is ahead? , Dec 1989, 48-52. 11. Ames Health and Safety Procedures and Guidelines (2004), Chapter 33- Personal Protective Equipment (PPE) Hazard Assessment and Selection (REDACTED).2-24. 12. T.Myers, AIbaretta, Investigation of the Jahn Foundry and CTA Acoustics dust explosions: similarities and differences , 2009,1-6 xcii 13. Conita H.S Lam. Appropriate Personal Protective Equipment for Isolation, Speakers Abstracts/ International Journal of Antimicrobial Agents 26S (2005) S1-S63, page S44. 14. Kroemer. K.H.E, 2001, Ergonomic: How to Design for Ease and Efficiency. Prentice Hall, Inc, New. 15. Terry Dell and Jan Berkhout, Injuries at a Metal Foundry as a Function of Job Classification, Length of Employment and Drug Screening. 16. Anne Marie Feyer, Ann M. Williamson, David R. Cairns, The Involvement Of Human Behaviour In Occupational Accidents: Errors In Context. 17. D.Garddner, J.A. Cross, P.N. Fonteyn, J.Carlopio, Mechanical Equipment Injuries in Small Manufacturing Business. 18. Robert. S. Dungan , nikki H. Dees, The Characterization Of Total And Leachable Metals In Foundry Molding Sands. 19. Karen A. Brown, Workplace Safety: A Call for Research. 20. Angela S.Blair, Dust Explosion Incidents and Regulations in the United States 21. H-w Kuo, C L Chang, J S Lai, F C Lee, B V Chung, C J Chen, Prevalence of and Factors Related to Pneumoconiosis among Foundry Workers in Central Taiwan. xciii APPENDIX A DSB CASTING SDN BHD QUESTIONNAIRE FOR DATA COLLECTION OF THE PROJECT xciv Thesis title: OCCUPATIONAL SAFETY AND HEALTH AT A CASTING PLANT A. LATAR BELAKANG PEKERJA NAMA: JANTINA : LELAKI BANGSA : MELAYU PEREMPUAN INDIA UMUR: 18 ‐ 20 TAHUN 21 ‐ 30 TAHUN 31 ‐ 40 TAHUN 45 TAHUN KEATAS 5 ‐ 10 TAHUN 10 TAHUN KEATAS LAMA BEKERJA: KURANG 1 TAHUN 1 ‐ 5 TAHUN Tahap pendidikan sekolah rendah sekolah menengah kolej / university / politeknik tidak bersekolah Lain‐ lain : Adakah anda dilindungi Insuran? YA TIDAK Adakah anda merokok? YA TIDAK B. JENIS KEMALANGAN 1. Terangkan bahagian yang anda bekerja dan xcv lakukan. membuat pattern membuat campuran green sand / silica sand membuat dan menyediakan mold membuat dan menyediakan core memanaskan mold menyediakan cecair besi panas menuangkan cecair besi panas kedalam laddle menuangkan cecair besi panas kedalam mold mengeluarkan mold melakukan sand blast prosess heat treatment prosess grinding Lain‐ lain : 2. Adakah anda pernah mengalami kemalangan/kecederaan di tempat kerja sepanjang anda bekerja. YA TIDAK 3. Jika YA, berapa kali anda mengalaminya? 1 kali 2 kali 3 ‐ 5 kali 5 ‐ 10 kali lebih 10 kali tidak ingat kerana terlalu kerap berlaku setiap hari kadang‐ kadang 4. Jika YA, di bahagian kerja manakah yang anda mengalaminya? Penuangan (pouring) Moulding Grinding coremakers Lain‐ lain : 5. Jika penuangan (pouring) ,bahagian anggota yang mana pernah anda mengalami kecederaan xcvi kaki mata tangan anggota badan muka Lain‐ lain : 6. Jika moulding , bahagian anggota yang mana pernah anda mengalami kecederaan tangan dan jari hidung mata anggota badan Lain‐ lain : 7. Jika grinding ,bahagian anggota yang mana pernah anda mengalami kecederaan mata telinga anggota badan tangan dan jari muka Lain‐ lain : 8. Jika penuangan coremakers ,bahagian anggota yang mana pernah anda mengalami kecederaan tangan dan jari hidung mata anggota badan Lain‐ lain : 9. Jenis kemalangan / kecederaan yang pernah anda alami. cecair besi panas jatuh semasa menuang ke dalam mold Percikan besi cecair panas dari furnace semasa sedang mengacau xcvii di furnace Percikan besi cecair panas dari furnace semasa berdiri berhampirannya Percikan besi cecair panas dari furnace semasa menuang ke dalam ladle tersepak / terpijak cecair besi panas tangan /kaki / badan melecur akibat cecair besi melecur akibat dari gas / api semasa untuk panaskan mold jatuh akibat tersepak wire gas sakit mata disebabkan serpihan pasir / habuk telinga berdengung akibat bising dari prosess sand blast jatuh akibat tersepak wire gas mold jatuh menghempap kaki / tangan pattern jatuh menghempap kaki/ tangan kelukaan pada jari akibat mata pisau/ mata gergaji ketika memotong untuk membuat pattern pengsan akibat panas sesak nafas / hidung tersumbat disebabkan habuk percikan besi dari grinding machine Lain‐ lain : C.MASALAHKESIHATN 10. Adakah anda mempunyai masalah kesihatan? ADA TIADA 11. Jika ADA, sila jelaskan. sakit belakang sakit pinggang pening / sakit kepala pedih mata sesak nafas / asma sakit jantung darah tinggi kencing manis sakit leher sakit tekak / xcviii lenguh‐lenguh badan sakit sendi Lain‐ lain : bibir kering gatal‐gatal di tapak tangan pedih ulu hati 12. Merujuk kepada soalan diatas, berapa kali kah anda mengalami nya? tidak ingat kerana terlalu 1 kali kerap berlaku setiap 2 kali hari kadang‐ 3 ‐ 5 kali kadang 5 ‐ 10 kali lebih 10 kali 13. Berapa kalikah anda menjalani ujian kesihatan dalam setahun? tidak ingat kerana terlalu 1 kali kerap berlaku setiap 2 kali hari kadang‐ 3 ‐ 5 kali kadang Lain‐ 5 ‐ 10 kali lain : lebih 10 kali D. ALAT KESELAMATAN 14. Adakah anda mengetahui akan kepentingan pemakaian alat / pakaian keselamatan? YA TIDAK 15. Adakah anda memakai pakaian / alat keselamatan semasa anda bekerja? YA TIDAK 16. Jika YA, apakah alat keselamatan yang anda gunakan semasa anda bekerja. safety boot googles apron gloves mask xcix ear protection face shield Lain‐ lain : 15. Jika TIDAK, sila jelaskan mengapa? 16. Adakah anda selesa dengan pakaian keselamatan yang disediakan? YA TIDAK 15. Jika TIDAK, sila jelaskan mengapa? c APPENDIX B ANALYSIS FROM QUESTIONNAIRE ci Question 1: Gender Only 8% are females and the rest of them are males. This is because most of the work that has to do needs energy and caution. Men are much better than women in this case. Three women are suitable placed at core making area and doing the same work repetitively for the whole day compared to men. Question 2: Age Most of the employees are in the range of 27 to 50 years old. There are 25% in the range of fewer than 30 years old, 36% in the range of 31 to 49 years old and 4% in the range of more than 50 years old. Question 3: Race At DSB Casting only 8% are India and the rest of them are Malay. The 8% India are 2 women and men. Question 4: Education Mostly of workers in level secondary school with 26 workers and the rest primary 20 and 5m workers have certificate foundry from college Instituted Kemahiran MARA. Question 5: Experience in Occupation They have 70% worker have above six years working experienced, and the rest 15% for less than five years and above 10 years. Mostly workers at DSB Casting start working at age 25 years old until their resign. Question 6: Smoking Status Only 90% of workers no smoking and the rest is smoker. Question 7: Received Safety Training Only 12 workers got safety training in year 1997 and after that no safety training for workers. Twenty-two person did not have any safety training because their start working 1999. cii APPENDIX C MECHANICAL DRAWING OF POURING TROLLEY USING SOLID EDGE V19 ciii civ cv APPENDIX D MECHANICAL DRAWING OF LOCAL EXHAUST VENTILATION SYTEM USING AUTOCAD 2002 cvi cvii cviii APPENDIX E ANALYSIS OF POURING TROLLEY USING MSC NASTRAN/PATRAN cix The step to analyzed pouring trolley are explained following below; Step 1: Create the Geometry There is no need to sketch the pouring trolley drawing because the drawing has already been drwn using Solid Edge V19. Figure 5.4 shows the geometry of pouring trolley imported from Solid Edge V19. Figure 5.4 Geometry element Step 2: Define the Mesh Element Define a mesh element and follows; i. Under the ELEMENTS menu; click CREATE; click MESH; click CURVE; click BAR2. Then select the trolley structure located at each side and click APPLY, and then the Figure 5.5 will show a beautiful mesh on trolley. cx Figure 5.5 Mesh element Step 3: Define the Material Properties Define new material description and its properties (see Figure 5.6): ii. Under the MATERIAL PROPERTIES menu; click NEW; click NAME and put material property 302_Stainless_Steel. iii. Click ISOTROPIC. Click MANUAL INPUT; click LINEAR ELASTIC; A menu appears where LINEAR ELASTIC parameters can be entered; type 193000 on the command line for Elast Modulus and type 0.25 on the command line for Poisson Ratio; click OK. Figure 5.6 Material Element Step 4: Define the Properties of the Element Define property element as follows (see Figure 5.7 and Figure 5.8): cxi i. Under the PROPERTIES menu; click PROP. SETS BY; click NAME as LFrame-5 and press Enter. Click INPUT PROPERTIES; type L-Frame -1 on the command line [Section Name]; type 302_Stainless_Steel as a Material Name; type <1, 1, 1,> on the command line Bar Orientation. ii. Click BEAM LIBRARY; click L Shape; type 20 on the command line W (width); type 20 on the command line H (height); type 3 on the command line t (thick);click APPLY; click OK. Figure 5.7 Properties element Figure 5.8 Properties L-frame Step 5: Apply the Constraint cxii Create a pinned support condition, and apply it to the four nodes on the base of the trolley structure as follows; i. Under the LOADS/BCs menu; click on four nodes at base structure. This fixed the x and y degrees of freedom since their values are 0; click OK (see Figure 5.9) Figure 5.9 Boundary condition element Step 6: Apply the Load Create a Load Case definition as follows: i. Under the LOADS/BCs menu; click FORCE. The force will apply at the critical point.. Click the node at middle and type -175 on the command line load and press the Enter key; click OK. (see Figure 5.10) cxiii Figure 5.10 Load element Step 7: Run the Analysis Lastly, run the analysis. The Figure 5.11 shows the step run analysis. i. Under the ANALYSIS menu; click ANALYZE; click Trolley1; click TRANSLATION PARAMETERS. Figure 5.11 Initial analysis of trolley design cxiv Step 8: Analysis the Result The Figure 5.12 shows the step to run the result. The result analysis is shown in Figure 5.13. i. Under the RESULTS menu; click CREATE-QUICK PLOT; select DEFAULT,A1:STATIC SUBCASE; select Fringe Result as BEAM STRESSES, COMBINED; select Deformation Result as DISPLACEMENT, TRANSLATIONAL. ii. Click VON MISES and result is displayed in Figure 5.13. Figure 5.12 Stress analysis of pouring trolley design cxv DISPLACEMENT VECTOR POINT ID. TYPE R3 T1 T2 T3 R1 R2 cxvi 1 G 1.568496E-02 -8.884762E-03 -5.080979E-02 3.088074E-05 - 7.384489E-03 5.329281E-05 2 G -4.514838E-03 -9.128695E-03 -4.201461E-02 3.717214E-05 - 6.036044E-03 9.083922E-05 3 G -2.120618E-02 -8.702318E-03 -3.328001E-02 3.039605E-05 - 4.687598E-03 2.522518E-05 5 G -2.078333E-02 -1.619747E-02 -1.921013E+00 4.437195E-06 1.023476E-04 -5.102341E-06 6 G -2.074328E-02 6.199344E-03 2.724707E-02 -2.152166E-05 6.094828E-03 3.532276E-02 -3.762795E-05 6.199692E-03 4.339705E-02 -2.151056E-05 4.639475E-03 -9.434270E-05 8 G -4.844332E-02 5.881423E-03 -1.190370E-04 9 G -7.650035E-02 7.123372E-03 -9.719852E-05 11 G -3.259622E-02 -2.015395E-02 -4.628090E+00 4.685089E-06 2.062554E-04 -1.168873E-05 14 G -4.096796E-01 2.978127E-03 -7.403460E-04 -1.456054E-05 2.199092E-04 -1.897302E-04 15 G -2.505981E-01 1.183500E-03 -1.164328E-02 -5.356326E-06 - 1.570359E-03 -2.851177E-04 17 G -9.856840E-02 6.870046E-04 -1.024386E-02 -4.722080E-06 - 1.416903E-03 -1.498444E-04 18 G -2.178669E-04 2.850365E-04 -3.647083E-03 -3.407311E-06 - 4.635729E-04 -1.457101E-05 20 G 8.756898E-03 7.735272E-05 3.304133E-04 -1.909648E-06 9.970662E-05 -7.285931E-06 21 G 23 G 0.0 0.0 0.0 0.0 0.0 0.0 3.792720E-01 -4.235925E-03 -4.245300E-03 2.027745E-05 - 3.279264E-04 1.652024E-04 24 G 2.398621E-01 -1.713814E-03 8.225420E-03 8.175672E-06 7.835360E-03 6.831543E-06 1.482552E-03 3.051797E-04 26 G 9.242187E-02 -9.660599E-04 1.361531E-03 1.593638E-04 cxvii 27 G -2.984942E-03 -3.881328E-04 2.153053E-03 4.727405E-06 4.260351E-04 1.354791E-05 29 G -9.640392E-03 -1.036488E-04 -1.097667E-03 2.587516E-06 - 1.215902E-04 6.776451E-06 30 G 32 G 0.0 0.0 0.0 0.0 0.0 0.0 6.345974E-01 -4.316262E-03 -4.736545E-03 2.087397E-05 - 4.024069E-04 1.794377E-04 33 G 3.945341E-01 -1.712580E-03 1.438863E-02 8.425656E-06 1.342465E-02 6.860043E-06 3.967938E-03 4.652647E-06 2.432376E-03 3.055826E-04 35 G 1.534469E-01 -9.524553E-04 2.222679E-03 1.595777E-04 36 G -2.613887E-03 -3.781517E-04 7.059533E-04 1.357279E-05 38 G -1.480830E-02 -1.000940E-04 -1.476206E-03 2.514131E-06 - 1.795433E-04 6.786393E-06 39 41 G G 0.0 0.0 -6.607168E-01 0.0 0.0 0.0 0.0 2.978920E-03 -7.561909E-04 -1.456387E-05 2.159287E-04 -1.911784E-04 42 G -3.948740E-01 1.183490E-03 -1.773275E-02 -5.359364E-06 - 2.509030E-03 -2.851583E-04 44 G -1.531415E-01 6.868471E-04 -1.560746E-02 -4.722452E-06 - 2.243459E-03 -1.498642E-04 45 G 1.841426E-03 2.849119E-04 -5.311208E-03 -3.406639E-06 - 7.203798E-04 -1.457019E-05 47 G 1.469798E-02 7.730399E-05 8.248095E-04 -1.908702E-06 1.754447E-04 -7.285095E-06 48 50 G G 0.0 0.0 0.0 0.0 -1.727681E-03 -3.566413E-03 0.0 1.104540E-01 0.0 6.600470E-07 6.649723E-07 -7.530754E-07 53 G -3.661147E-04 -3.564492E-03 1.776200E-01 6.230040E-07 - 1.030903E-05 -7.443236E-07 56 G -3.227335E-01 1.353743E-03 -1.468820E-02 2.084334E-05 - 2.039694E-03 -2.901830E-04 cxviii 59 G 3.171729E-01 -1.913446E-03 1.132265E-02 -2.251766E-05 1.957464E-03 3.112375E-04 1 MSC.NASTRAN JOB CREATED ON 23-APR-10 AT 12:27:56 APRIL 23, 2010 MSC.NASTRAN 9/23/04 PAGE 11 DEFAULT 0 SUBCASE 1 FORCES OF SINGLE-POINT CONSTRAIN T POINT ID. TYPE T1 T2 T3 R1 R2 R3 21 G -3.688019E+01 -8.658800E-02 8.889962E+01 3.401706E+01 - 2.412615E+03 2.448416E+00 30 G 3.722671E+01 9.397615E-02 8.614161E+01 -4.519904E+01 1.381623E+03 -2.277207E+00 39 G 5.924539E+01 7.894738E-02 8.669475E+01 -4.344424E+01 2.466862E+03 -2.280547E+00 48 G -5.959192E+01 -8.633553E-02 8.826402E+01 3.399220E+01 - 3.599511E+03 2.448135E+00 1 MSC.NASTRAN JOB CREATED ON 23-APR-10 AT 12:27:56 APRIL 23, 2010 MSC.NASTRAN 9/23/04 PAGE 12 0 1 MSC.NASTRAN JOB CREATED ON 23-APR-10 AT 12:27:56 APRIL 23, 2010 MSC.NASTRAN 9/23/04 PAGE 13 DEFAULT 0 SUBCASE 1 STRESSES IN BEAM ELEMENTS AM) STAT DIST/ (CBE cxix ELEMENT-ID GRID LENGTH S-MAX 0 S-MIN SXC SXD SXE SXF M.S.-T M.S.-C 1 1 0.000 4.069868E-01 5.200676E-01 -5.930145E-01 2.400245E-01 5.200676E-01 -5.930145E-01 2 1.000 -8.054476E-02 -6.245694E-02 9.340624E-02 -5.716529E-02 9.340624E-02 -8.054476E-02 0 2 2 0.000 -8.054476E-02 -6.245694E-02 9.340624E-02 -5.716529E-02 9.340624E-02 -8.054476E-02 3 1.000 -5.680763E-01 -6.449816E-01 7.798269E-01 -3.543551E-01 7.798269E-01 -6.449816E-01 0 3 3 0.000 1.820531E+01 -2.194369E+01 -2.363878E-01 2.146140E+01 2.146140E+01 -2.194369E+01 5 1.000 -6.331388E+01 7.363113E+01 -4.038732E-02 -7.436462E+01 7.363113E+01 -7.436462E+01 0 4 5 0.000 -6.331388E+01 7.363113E+01 -4.038732E-02 -7.436462E+01 7.363113E+01 -7.436462E+01 6 1.000 2.020381E+01 -2.495509E+01 1.556131E-01 2.397041E+01 2.397041E+01 -2.495509E+01 0 5 6 0.000 2.548371E-01 -6.611006E-01 2.142699E-01 3.861427E-01 3.861427E-01 -6.611006E-01 8 1.000 1.317709E-02 -1.567267E-02 -1.437187E-04 1.550644E-02 1.550644E-02 -1.567267E-02 0 6 8 0.000 1.317709E-02 -1.567267E-02 -1.437187E-04 1.550644E-02 1.550644E-02 -1.567267E-02 9 1.000 -2.284829E-01 6.297553E-01 -2.145573E-01 -3.551298E-01 6.297553E-01 -3.551298E-01 0 7 cxx 9 0.000 7.887415E+01 5.771891E+01 -9.028694E+01 5.667327E+01 7.887415E+01 -9.028694E+01 11 1.000 -1.212929E+02 -8.708267E+01 1.355088E+02 - 8.790418E+01 1.355088E+02 -1.212929E+02 0 8 11 0.000 -1.212929E+02 -8.708267E+01 1.355088E+02 - 8.790418E+01 1.355088E+02 -1.212929E+02 1 1.000 7.508926E+01 5.462256E+01 -8.580467E+01 5.402517E+01 7.508926E+01 -8.580467E+01 0 9 6 0.000 -4.880721E+01 -3.533889E+01 5.324588E+01 -3.551950E+01 5.324588E+01 -4.880721E+01 14 1.000 -2.685832E+01 -1.942482E+01 2.846526E+01 - 1.967481E+01 2.846526E+01 -2.685832E+01 0 10 14 0.000 -2.685832E+01 -1.942482E+01 2.846526E+01 - 1.967481E+01 2.846526E+01 -2.685832E+01 15 1.000 -4.909431E+00 -3.510760E+00 3.684641E+00 - 3.830120E+00 3.684641E+00 -4.909431E+00 0 11 15 0.000 -4.556433E+00 -3.500793E+00 3.426510E+00 - 3.517337E+00 3.426510E+00 -4.556433E+00 17 1.000 7.593354E+00 5.308337E+00 -1.029072E+01 5.253495E+00 7.593354E+00 -1.029072E+01 0 12 17 0.000 7.593354E+00 5.308337E+00 -1.029072E+01 5.253495E+00 7.593354E+00 -1.029072E+01 18 1.000 1.974314E+01 1.411747E+01 -2.400796E+01 1.402433E+01 1.974314E+01 -2.400796E+01 0 1 13 MSC.NASTRAN JOB CREATED ON 23-APR-10 AT 12:27:56 APRIL 23, 2010 MSC.NASTRAN 9/23/04 PAGE DEFAULT 14 cxxi 0 SUBCASE 1 STRESSES IN BEAM ELEMENTS (CBE AM) STAT DIST/ ELEMENT-ID GRID LENGTH S-MAX S-MIN 18 0.000 SXC SXD SXE SXF M.S.-T M.S.-C 1.641637E+01 1.171301E+01 -2.025756E+01 1.162079E+01 1.641637E+01 -2.025756E+01 20 1.000 3.617637E+00 2.489609E+00 -5.841051E+00 2.368038E+00 3.617637E+00 -5.841051E+00 0 14 20 0.000 3.617638E+00 2.489609E+00 -5.841051E+00 2.368039E+00 3.617638E+00 -5.841051E+00 21 1.000 -9.181118E+00 -6.733767E+00 8.575459E+00 - 6.884734E+00 8.575459E+00 -9.181118E+00 0 15 3 0.000 4.684231E+01 3.339751E+01 -5.433645E+01 3.368222E+01 4.684231E+01 -5.433645E+01 23 1.000 2.537717E+01 1.783902E+01 -3.010486E+01 1.818559E+01 2.537717E+01 -3.010486E+01 0 16 23 0.000 2.537717E+01 1.783902E+01 -3.010486E+01 1.818559E+01 2.537717E+01 -3.010486E+01 24 1.000 3.912024E+00 2.280527E+00 -5.873264E+00 2.688955E+00 3.912024E+00 -5.873264E+00 0 17 24 0.000 3.533267E+00 2.294182E+00 -5.610172E+00 2.347614E+00 3.533267E+00 -5.610172E+00 26 1.000 -8.648341E+00 -6.541023E+00 6.445472E+00 8.144774E+00 -8.648341E+00 0 18 8.144774E+00 - cxxii 26 0.000 -8.648341E+00 -6.541023E+00 8.144774E+00 - 6.445472E+00 8.144774E+00 -8.648341E+00 27 1.000 -2.082995E+01 -1.537623E+01 2.189972E+01 - 1.523856E+01 2.189972E+01 -2.082995E+01 0 19 27 0.000 -1.773256E+01 -1.313750E+01 1.840794E+01 - 1.300074E+01 1.840794E+01 -1.773256E+01 29 1.000 -4.812584E+00 -3.828590E+00 3.855976E+00 - 3.659899E+00 3.855976E+00 -4.812584E+00 0 20 29 0.000 -4.812586E+00 -3.828588E+00 3.855976E+00 - 3.659902E+00 3.855976E+00 -4.812586E+00 30 1.000 8.107374E+00 5.480334E+00 -1.069599E+01 5.680925E+00 8.107374E+00 -1.069599E+01 0 21 1 0.000 7.568437E+01 5.424486E+01 -8.685814E+01 5.451892E+01 7.568437E+01 -8.685814E+01 32 1.000 4.075219E+01 2.894489E+01 -4.743562E+01 2.929512E+01 4.075219E+01 -4.743562E+01 0 22 32 0.000 4.075219E+01 2.894489E+01 -4.743562E+01 2.929512E+01 4.075219E+01 -4.743562E+01 33 1.000 5.820019E+00 3.644929E+00 -8.013093E+00 4.071315E+00 5.820019E+00 -8.013093E+00 0 23 33 0.000 5.896005E+00 3.987474E+00 -8.276185E+00 4.056457E+00 5.896005E+00 -8.276185E+00 35 1.000 -1.366602E+01 -1.017480E+01 1.379704E+01 - 1.007025E+01 1.379704E+01 -1.366602E+01 0 24 35 0.000 -1.366602E+01 -1.017480E+01 1.007025E+01 1.379704E+01 -1.366602E+01 1.379704E+01 - cxxiii 36 1.000 -3.322805E+01 -2.433706E+01 3.587027E+01 - 2.419695E+01 3.587027E+01 -3.322805E+01 0 25 36 0.000 -2.806955E+01 -2.060933E+01 3.005347E+01 - 2.047013E+01 3.005347E+01 -2.806955E+01 38 1.000 -7.517944E+00 -5.782425E+00 6.894378E+00 - 5.616424E+00 6.894378E+00 -7.517944E+00 1 MSC.NASTRAN JOB CREATED ON 23-APR-10 AT 12:27:56 APRIL 23, 2010 MSC.NASTRAN 9/23/04 PAGE 15 DEFAULT 0 SUBCASE 1 STRESSES IN BEAM ELEMENTS (CBE AM) STAT DIST/ ELEMENT-ID GRID LENGTH S-MAX 0 S-MIN SXC SXD SXE SXF M.S.-T M.S.-C 26 38 0.000 -7.517944E+00 -5.782425E+00 6.894378E+00 - 5.616424E+00 6.894378E+00 -7.517944E+00 39 1.000 1.303366E+01 9.044481E+00 -1.626472E+01 9.237286E+00 1.303366E+01 -1.626472E+01 0 27 9 0.000 -7.609445E+01 -5.505439E+01 8.401315E+01 -5.523432E+01 8.401315E+01 -7.609445E+01 41 1.000 -4.116262E+01 -2.975978E+01 4.459405E+01 - 3.000954E+01 4.459405E+01 -4.116262E+01 0 28 41 0.000 -4.116262E+01 -2.975978E+01 4.459405E+01 - 3.000954E+01 4.459405E+01 -4.116262E+01 42 1.000 -6.230782E+00 -4.465168E+00 4.784764E+00 5.174947E+00 -6.230782E+00 0 29 5.174947E+00 - cxxiv 42 0.000 -6.326369E+00 -4.777972E+00 5.433078E+00 - 4.794712E+00 5.433078E+00 -6.326369E+00 44 1.000 1.278407E+01 9.060158E+00 -1.613225E+01 9.005212E+00 1.278407E+01 -1.613225E+01 0 30 44 0.000 1.278407E+01 9.060158E+00 -1.613225E+01 9.005212E+00 1.278407E+01 -1.613225E+01 45 1.000 3.189452E+01 2.289829E+01 -3.769759E+01 2.280514E+01 3.189452E+01 -3.769759E+01 0 31 45 0.000 2.677256E+01 1.919695E+01 -3.192199E+01 1.910472E+01 2.677256E+01 -3.192199E+01 47 1.000 6.099747E+00 4.284502E+00 -8.627434E+00 4.162956E+00 6.099747E+00 -8.627434E+00 0 32 47 0.000 6.099747E+00 4.284502E+00 -8.627434E+00 4.162956E+00 6.099747E+00 -8.627434E+00 48 1.000 -1.457307E+01 -1.062795E+01 1.466712E+01 - 1.077881E+01 1.466712E+01 -1.457307E+01 0 33 18 0.000 1.945773E+00 1.686835E+00 -1.027576E+00 1.538611E+00 1.945773E+00 -1.027576E+00 50 1.000 1.828843E+00 1.606609E+00 -8.982642E-01 1.453112E+00 1.828843E+00 -8.982642E-01 0 34 50 0.000 1.828843E+00 1.606609E+00 -8.982642E-01 1.453112E+00 1.828843E+00 -8.982642E-01 27 1.000 1.711913E+00 1.526383E+00 -7.689528E-01 1.367612E+00 1.711913E+00 -7.689528E-01 0 35 45 0.000 2.951922E+00 2.510175E+00 -1.423238E+00 2.361910E+00 2.951922E+00 -1.423238E+00 cxxv 53 1.000 2.967912E+00 2.526057E+00 -1.443837E+00 2.372428E+00 2.967912E+00 -1.443837E+00 0 36 53 0.000 2.967912E+00 2.526057E+00 -1.443837E+00 2.372428E+00 2.967912E+00 -1.443837E+00 36 1.000 2.983902E+00 2.541938E+00 -1.464437E+00 2.382946E+00 2.983902E+00 -1.464437E+00 0 37 15 0.000 4.030636E-01 1.130419E-01 -3.486743E-01 3.338062E-01 4.030636E-01 -3.486743E-01 56 1.000 1.756456E-04 -2.314391E-04 6.536594E-06 2.113419E-04 2.113419E-04 -2.314391E-04 0 38 1 MSC.NASTRAN JOB CREATED ON 23-APR-10 AT 12:27:56 APRIL 23, 2010 MSC.NASTRAN 9/23/04 PAGE 16 DEFAULT 0 SUBCASE 1 STRESSES IN BEAM ELEMENTS (CBE AM) STAT DIST/ ELEMENT-ID GRID LENGTH S-MAX S-MIN 56 0.000 SXC SXD SXE SXF M.S.-T M.S.-C 1.756456E-04 -2.314391E-04 6.536594E-06 2.113419E-04 2.113419E-04 -2.314391E-04 42 1.000 -4.027123E-01 -1.135048E-01 3.486874E-01 -3.333835E-01 3.486874E-01 -4.027123E-01 0 39 24 0.000 -4.734231E-01 -1.320486E-01 4.094436E-01 -3.921993E-01 4.094436E-01 -4.734231E-01 59 1.000 -9.816792E-04 2.883108E-03 -6.812462E-04 -1.516332E-03 2.883108E-03 -1.516332E-03 0 40 cxxvi 59 0.000 -9.816792E-04 2.883108E-03 -6.812462E-04 -1.516332E-03 2.883108E-03 -1.516332E-03 33 1.000 4.714597E-01 1.378148E-01 -4.108061E-01 3.891666E-01 4.714597E-01 -4.108061E-01 1 MSC.NASTRAN JOB CREATED ON 23-APR-10 AT 12:27:56 APRIL 23, 2010 MSC.NASTRAN 9/23/04 PAGE 17 0 1 MSC.NASTRAN JOB CREATED ON 23-APR-10 AT 12:27:56 APRIL 23, 2010 MSC.NASTRAN 9/23/04 PAGE 18 cxxvii cxxviii cxxix