DEFENCE OF ABATEMENT FOR DEFECTIVE WORKS MOHAMAD FAIRUZ BIN KIPRAWI UNIVERSITI TEKNOLOGI MALAYSIA DEFENCE OF ABATEMENT FOR DEFECTIVE WORKS MOHAMAD FAIRUZ BIN KIPRAWI A master’s project report submitted in fulfillment of the requirements for the award of the degree of Master in Science of Construction Contract Management. Faculty of Built Environment Universiti Teknologi Malaysia November 2009 iii DEDICATION To my beloved parents, late grandmother, fiancée and my sisters Thank you for your love, support and everything iv ACKNOWLEDGEMENT Highest gratitude and to Allah S.W.T. who give me ideas and physical strength to complete this research. First of all, I would like to express my deepest gratitude to my supervisor, Dr. Nur Emma Mustafa for her patience, guidance, advice and kind assistance in order to complete this research on time. I also would like to express my gratitude to all the lecturers for the Master of Science (Construction Contract Management) course for their patient, commitment and kind advise during the process of completing this master project and course. Last but not least, a token of appreciation goes to my parents, fiancée and sisters for their love, care and support in my life. v ABSTRACT Defective works are one of the major issue in the Malaysian construction industry which have been the main concerned by the industry players, especially the employer. Although everyone in the industry is aware of this problem, the defective building works are still unpreventable and cause a lot of claims and litigation in the industry. In the context of construction law, the little known common law right of abatement can provide an employer with the entitlement, by way of defence to a contractor’s claim, to reduce sums otherwise payable to contractors by asserting that the sum claimed has not been earned. A typical example arises in circumstances where an employer asserts that the value of works claimed by a contractor should be reduced on account of defects in those works. To date, abatement has not achieved the same status as the similar and inter-linked defence of set-off. This common law right to abate will provide an alternative to the employer as a defence for claim for defective works. Unlike set-off, abatement is a common law rights which can be used by all the parties in the industry without having to serve any early notice or need to be stated clearly in the conditions of contract. In view of the above, this study has been conducted and the data are collected using Lexis-Nexis database. Subsequently, related cases are gathered and analysed. There are three main principles of abatement and one principle on measure of damages in abatement has been indentified. Judges will depend on the facts in every single case to award damages based on the principle of abatement. vi ABSTRAK Kecacatan kerja merupakan salah satu isu utama di dalam industri pembinaan di Malaysia yang telah menjadi perhatian utama oleh setiap pihak di dalam industri terutamanya majikan. Walaupun semua pihak mengetahui tentang masalah ini, namun ia masih tetap tidak dapat dielakkan dan telah menyebabkan pelbagai tuntutan dan kes-kes perundangan di dalam industri ini. Di dalam konteks undang-undang pembinaan, abatement, yang merupakan hak yang terdapat di dalam common law, boleh memberikan hak kepada majikan dengan memberi perlindungan daripada tuntutan pihak kontraktor, hak untuk mengurangkan jumlah pembayaran yang sepatutnya dibayar dengan menyatakan nilai kerja yang dituntut di dalam tuntutan yang telah dibuat oleh pihak kontraktor tidak diperolehi. Sebagai contoh, pihak majikan menyatakan nilai kerja yang dituntut telah berkurangan di sebabkan oleh kecacatan pada kerja tersebut. Sehingga masa kini, abatement masih lagi kurang digunakan di mahkamah berbanding dengan perlindungan set-off. Hak abatement akan memberi satu alternatif kepada pihak majikan untuk melindungi hak mereka dalam kecacatan kerja. Tidak seperti set-off, abatement boleh digunakan oleh semua pihak tanpa perlu memberi sebarang notis awal ataupun perlu dinyatakan secara jelas di dalam syarat-syarat kontrak. Berdasarkan yang tersebut, kajian ini telah dilakukan dan data telah dikumpul melalui pangkalan data Lexis Nexis. Kes-kes yang berkaitan telah dikumpul dan dianalisa. Daripada analisa tersebut, terdapat tiga prinsip utama abatement dan satu prinsip berkaitan dengan cara menilai kerugian telah dikenal pasti. Hakim akan bergantung dengan setiap fakta di dalam setiap kes untuk menentukan ganti rugi berdasarkan prinsip abatement. vii TABLE OF CONTENTS CHAPTER I II TITLE PAGE TITLE i DECLARATION ii DEDICATION iii ACKNOWLEDGEMENT iv ABSTRACT v. TABLE OF CONTENTS vii. LIST OF TABLES x LIST OF CASES xi LIST OF ABBREVIATIONS xiii INTRODUCTION 1 1.1 Background of Study 1 1.2 Problem Statement 4 1.3 Objective of the Study 6 1.4 Scope of Study 6 1.5 Significance of the Study 7 1.6 Methodoly of Study 7 DEFECTS 10 2.0 Introduction 10 2.1 Definition 11 2.2 Qualitative Defects 12 2.3 Patent/Latent Defects 13 viii 2.4 Defective Work in Malaysian Standard Form Of Contract 2.4.1 Defective Work Claim During Construction Period 2.4.2 2.6 III 19 Defetcs and Interim Payment 21 2.5.1 The Contractual Position 21 2.5.2 Interim Valuations, Certificate and Payment 21 Conclusions 25 ABATEMENT IN UK CONSTRUCTION INDUSTRY 26 3.0 Introduction 26 3.1 Set-Off 27 3.2 Abatement 28 3.3 Differences Between Set-Off and Abatement 32 3.4 Common Law Right of Abatement of Price 36 3.5 Abatement Under UK’s Housing Grants, Construction And Regenation Act 1996 (HCGRA), Part II 37 3.5.1 Witholding Payment 40 3.5.2 Abatement and Set-Off in Response to the Claim 42 3.5.3 The Adjudicator’s Decision – Abatement and Set-Off in Response 3.6 IV 16 Defect Work Claim During the Defects Liability Period 2.5 15 Consclusion 43 46 PRINCIPLES OF ABATEMENT AND MEASURE OF DAMAGES DUE TO DEFECTIVE WORKS 47 4.0 Introduction 47 4.1 Common Law Right for Abatement 49 4.1.1 Gilbert-Ash (Northern) Ltd v Modern ix Engineering (Bristol) Ltd 4.2 4.3 4.4 4.5 V 49 Measure for Cost of Damages 52 4.2.1 B.R. Hodgson Ltd v Miller Construction Ltd 52 4.2.2 C.A. Dunquemin Ltd v Raymond Slater 54 4.2.3 Mondel v Steel 56 The Rights for Abatement of Price Due to Causes Other Than Defects 59 4.3.1 59 Mellows Archital Limited v. Bell Projects Limited The Rights for Abatement in Cross Action Claim 61 4.4.1 62 Davis v Hedges Conclusion 65 CONCLUSIONS AND RECOMMENDATIONS 66 5.1 Introduction 66 5.2 Summary of Study Finding 66 5.3 Problems Encountered During Study 68 5.4 Further Study 68 5.5 Conclusion 68 REFERENCES 69 BIBLIOGRAPHY 71 x LIST OF TABLES TABLE NO. 5.1 TITLE Summary of study findings PAGE 67 xi LIST OF CASES CASES Anglian Building Products Ltd v W&C French (Construction) Ltd [1972] 16 BLR 1 Barret Steel Buildings Ltd v Amec Construction Ltd [1997] 15-CLD-10-07 Baxall Securities Ltd v Sheard Walshaw Partnership [2002] BLR 100 Bim Kemi AB v Blackburn Chemicals Ltd [2001] All ER (D) 13 Brown v M. Kinally 2 Esp. 278 B.W.P. (Architectural) Ltd v Beaver Building Systems Ltd [1998] 42 BLR 86 C.A. Duquemin Ltd v Raymond Slater [1993] 65 BLR 124; 35 Con LR 147 Davis v Hedges [1871] 6 QB 687 Dawnays Ltd v FG Minter Ltd and Trollope & Colls Ltd [1971] 1 BLR 16 Gilbert-Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] 1 BLR 75 Hamlet v Richardson 9 Bing. 644 Halesowen Presswork and Assemblies Ltd v National Westminster Bank Ltd [1972] AC 785 Hanak v Green [1958] 1 BLR 4 Hargreaves B. Limited v Action 2000 Ltd [1992] 62 BLR 72 Hutchisons v Harris [1978] 10 BLR 19 Jackson v Mumford [1902] 51 WR 91 Macob Civil Engineering Ltd v Morrison Construction Ltd [1999] BLR 93 McGriffin v Palmers Shipbuilding and Iron Co Ltd [1882] 10 QBD 5 Mellowes Archital Ltd v Bell Projects Ltd [1997] 87 BLR 26 Mondel v Steel [1841] 1 BLR 106 xii Multiplex Construction (UK) Ltd v Cleveland Bridge UK Ltd [2006] Adj.L.R.12/20 P&M Kaye Ltd v Hoiser & Dickinson [1972] 1 WLR 146 Riverstone Meat Pty Ltd v Lancashire Shipping Company Ltd [1961] AC 807 Rotterham MBC v Frank Haslam Milan & Co Ltd & M.J. Gleeson (Northern) Ltd [1996] 78 BLR 1 CA Ruxely Electronics and Construction Ltd v Forsyth [1995] 73 BLR 1 Stewart Gill v Horatio Myer [1992] 2 All ER 257 Sunderson v National Coal Board [1961] 2 QB 44 Tate v Latham & Son [1897] 1 QB 502 Tubeworks Ltd v Tilbury Construction Ltd [1985] 30 BLR 67 Yandle & Sons v Sutton, Young and Sutton [1922] 2 Ch 199 Yarmouth v France [1897] 19 QBD 647 xiii LIST OF ABBREVIATIONS AC Appeal Cases All ER All England Law Reports All ER Rep All England Law Reports, Reprint BLR Building Law Reports CLJ Construction Law Journal Con LR Construction Law Reports CLR Commonwealth Law Reports EG Estate Gazette EGD Estate Gazette Digest Exch Court of Exchequer HL House of Lords HGCRA Housing Grants, Construction and Regeneration Act 1996 JCT Joint Contracts Tribunal KB Kings Bench Law Report LGR Local Government Reports LJQB Lae Journal Reports, Queens Bench LR, CP Law Reports, Common Pleas QB, QBD Law Reports: Queen’s Bench Division WLR Weekly Law Report 1 CHAPTER I INTRODUCTION 1.1 Background Of Study Most of the time, a set off in construction arise due to dissatisfaction of one party to another party on the quality of the works carried out. In the historical case of Hanak v. Green,1 the builder asserted he could set off his counterclaims against the claims made by Mrs Hanak due to her dissatisfaction of his work. The analysis made by the Court of Appeal, which agreed with the builder’s assertion, resolved the dispute between Mrs Hanak and her builder. However, the problems of set-off continues to exist in the construction industry where there are claims and counterclaims because the question continues to arise whether one can be set off against the other.2 Originally, there are no common law right at all to set off a counter claim.3 The common law did, however, allow the remedy of abatement. In Oxford Dictionary Of Law, abatement is defined as “ any reduction or cancellation of money payable”. Here, the employer does not seek to set up a cross claim against the contractor’s 1 [1958] 2 WLR 755. Neil F. Jones (1991). “Set-off In The Construction Industry.” Blackwell Science, United Kingdom, pg 1. 3 Ibid. 2 2 claim, but rather alleges that, because of the defects, the contractor’s claim itself is not justified.4 The law in respect of the defence of abatement was recently considered in detail by the English courts in Multiplex Construction (UK) Ltd v Cleveland Bridge UK Ltd.5 After an analysis of the case law on the defence of abatement, Justice Jackson held that the following principles apply: (1) In a contract for the provision of labour and materials where performance has been defective, the employer is entitled at common law to maintain the defence of abatement against claims for payment. (2) The measure of abatement is the amount by which the product has diminished in value due to the actions of the contractor. (3) The method of assessing diminution of value depends on facts of the case. (4) In some cases, diminution may be assessed by comparing the current market value of the construction with the market value that it ought to have had. Otherwise, and as was the case here, the best method was the cost of the remedial works, as the value of the steelworks did not have a market value in the conventional sense, only to the contractor who was obliged to produce the completed stadium; (5) The measure of abatement can never exceed the sum that would have been otherwise due to the contractor. (6) Abatement is not available as a defence to a claim in respect of professional services. 4 Murdoch, J. and Hughes, W. (1992). “Construction Contracts Law and Management.” E & FN Spon, London, pg 336. 5 [2006] Adj.L.R. 12/20 3 (7) Claims for delay / disruption / damage caused to anything other than what the contractor constructed cannot feature in the defence of abatement. The difference between abatement, set-off and counterclaim is all too often misunderstood.6 Abatement is the process of reducing a price or a value on the grounds, for example, that the works have not been properly carried out, incomplete, or not carried out at all.7 By contrast a set-off is a defence to a claim used to reduce or extinguish a claim and is resultant from a party’s breach of contract. However a counterclaim, whilst also results from a party’s breach of contract, may also give rise to an award for damages.8 These distinctions can often be quite important, particularly in the context of the Construction Act in the UK, where it has been held that a set-off may not be made in the absence of a withholding notice.9 A withholding notice will not, however, normally be required for a defence of abatement to be argued. That is to say, if the work is defective, the amount due to the contractor may be reduced correspondingly and thus, in reality, there is no withholding against the proper amount due.10 6 Silver, R. (2008). “Abatement, Set-Off and Counterclaim – What’s the Difference? ” from http://www.silver-shemmings.co.uk/construction-law/abatement-set-off-counterclaim.asp 7 Ibid 8 Silver, R. (2008). “Abatement, Set-Off and Counterclaim – What’s the Difference? ” from http://www.silver-shemmings.co.uk/construction-law/abatement-set-off-counterclaim.asp 9 Brewer, G. (2006). “Legal Case Study: The defence of abatement”. Contract Journal. http://www.contractjournal.com/Articles/2006/11/01/52679/legal-case-study-the-defence-ofabatement.html 10 Ibid. 4 1.2 Problem Statement In the context of construction law, the little known common law right of abatement can provide an employer with the entitlement, by way of defence to a contractor’s claim, to reduce sums otherwise payable to contractors by asserting that the sum claimed has not been earned. A typical example arises in circumstances where an employer asserts that the value of works claimed by a contractor should be reduced on account of defects in those works. To date, abatement has not achieved the same use in courts as the similar and inter-linked defence of set-off.11 In Malaysian construction industry Standard Contract Form, there is no express provision for abatement as a defence to contractor’s claim. Out of three most common used Standard Contract Form (which is Public Work Department 203, PAM Contract 2006 and CIDB Standard Form of Contract for Building Works) only PAM Contract 2006, clearly expressed that entitlement for Employer to set off claim made by Contractor12 under the following conditions: i) The Architect or Quantity Surveyor (on behalf of the Employer) has submitted the Contractor complete details of their assessment of such setoff; ii) A written notice have been given to the Contractor by the Employer specifying his intention to set-off the amount and the gorunds on which set-off is made. Although the defence of abatement has been recognized for at least 150 years,13 its use in the construction field raises one difficulty. This is where the disputed claim rests, not upon a simple assertion by the contractor that money is due, 11 Dolan, S. (2007). “The Common Law Defence of Abatement : A Change of Direction” .from http://www.mhc.ie/news-+-events/legal-articles/220/ 12 See Clause 30.4 of PAM 2006. 13 Mondel v Steel [1841] 8 M & W 858. 5 but rather on architect’s certificate or its equivalent.14 In such circumstances an employer seeking to defend the claim will face an uphill tasks, since it requires the court to be convinced of a substantial possibility that the work has been over certified. It is established that clear evidence will be needed and that vague allegations of defective work will not suffice.15 A claim for set-off may potentially have a wider reach than abatement. Damages claimed as a set-off may concern, for example, the cost of putting right defects in the work, but may also include damages suffered as a consequence of the manner in which the work has been carried out, for example, damages for delay.16 The measure of abatement, on the other hand, must be limited to the difference in value of the work itself as a consequence of the defective work. Additionally, a set-off must be raised by way of a separate cross-claim. An abatement may, however, simply be regarded as a defence to a claim for payment in respect of defective work.17 In the case of C.A. Duquemin Ltd v. Raymond Slater,18 it was explained that abatement entitles the purchaser to deduct the difference between the value of the work and materials at the date supplied and their value if they had not been defective. It does not, however, permit anything other than a deduction against the price. This case however, left open question, particularly in the context of building contracts, as to which work and materials are subject to abatement.19 While abatement has been the subject of debate in the modern construction industry for some time now, it is an important clause to be aware of as it still remains 14 Murdoch, J. and Hughes, W. (1992). “Construction Contracts Law and Management.” E & FN Spon, London, pg 336. 15 Murdoch, J. and Hughes, W., loc.cit. 16 Brewer, G., loc.cit. 17 Ibid. 18 [1993] 65 BLR 124 19 Neil F. Jones , loc. cit. 6 a valuable tool in the armoury of a party who has suffered loss as a result of defective works.20 In view of these issues, this study will try to find what are the principles of abatement and the main criteria on the measure of damages to a defective works in which abatement claim is made as a defence to a claim. 1.3 Objective of the Study The objective of this research is to identify the principles of abatement claim and what are the criteria on the measure of damages on which an abatement claim can be made due to defective works. 1.4 Scope of Study Based on the objective, the approach adopted in this study is based on case law which covers the following areas: a) Only abatement claim cases due to defective works will be discussed in the study b) Court cases referred in this study are mainly from English cases which is reported in Lexis Nexis.. 20 Brewer, G., loc.cit. 7 1.5 Significance of the Study This study is expected to assist the Malaysian construction industry player to understand and give them a brief picture on what abatement is. This will also help them, especially the aggrieved party, the right and option other than set off, to defence themselves from defective works done by the other party. It is also to help the aggrieved party when seeking for damages from the wrongdoer, where he can compare the facts of his case and the fact of cases list down in this study to proceed with his abatement claim. 1.6 Methodology of Study Methodology is important and is a vital guideline on how this study is being carried out systematically to achieve its objective. The stages involved are explained as below. The first stage of this study is establishing the problem statement. This is the preliminary process in determining the issues and problems which is going to be studied. Literature review on documents as book, journals and internet were used to determine the issue. This is to assist the writer to acquire ideas, knowledge and information relating to the topic studied. It is also to help the writer identified issues or problems related to the topic. The next stage is data collection and research design stage. This is the stage where all relevant data and information were collected, mainly through documentary analysis. All collected data and information were recorded systematically. The source of these date were mainly from the English Law Report, Construction Law Report and other law journals. It is collected through the Lexis-Nexis online 8 database. All the cases relating to the research topic will be sorted out from the database. Important cases will be collected and used for the analysis at the later stage. After collecting data, the further stage involved in this study is data analysis and interpretation. In this stage of research, data were analyzed, interoperated and arranged. This process is to convert the data collected to necessary information which will be used for the research. The final stage of this research process is writing up and conclusions. It involves mainly the writing up and checking of the writing. Conclusion and recommendations will be made based on the findings during the stage of analysis. 9 Stage 1 Problems Statement Approach: Literature review • Books, journals, internet sources Fix the research topic Fix the research objective, scope and prepare the research outline Identify type of data needed and data sources Stage 2 Data Collection Research Design Approach: Documentary Analysis • Law Journals, e.g. Malayan Law Journal, Construction Law Report, etc. Stage 3 Stage 4 Analyzing and Interpreting Data Writing-up 10 CHAPTER II DEFECTS 2.0 Introduction Defect has always been an issue in any construction works. In Ruxely Electronics & Construction Ltd. v. Forsyth21, Mr Forsyth discovered that his recently constructed swimming pool was shallower by 9 inches than the specification called for.22 Despite the workmanship and materials conforming in all other respects with the quality requirements of the specifications, the pool was nonetheless, in law, defective.23 Mr Forsyth sued for compensation, however found himself lost on appeal about the correct approach to the assessment of compensation. Mr Forsyth’s complaint about the depth of his pool serves an illustration that defects can encapsulate more than just bad workmanship and materials, and the quality is just one category of defective works.24 It is useful therefore to have a general definition of the term ‘defect’, to understand what is meant by ‘patent’ and ‘latent’ defects and to appreciate the impact of discoverability on the status and legal consequences of defects.25 21 [1995] 73 BLR 1 Kevin Barrett (2008). “Defective Construction Work and The Project Team.” Wiley-Blackwell. United Kingdom 23 Ibid. 24 Ibid. 25 Ibid. 22 11 2.1 Definition So, what is defined by defect? In Tate v. Latham and Son26, defect is defined as ‘a lack or absence of something essential to completeness’. The Tate definition arose in the context of a workman’s compensation claim under the Employer Liability Act 1880. In that case a fence intended to protect the operator was missing from a dangerous piece of machinery, so it was defective.27 Other example of cases which attempt to define ‘defect’ include McGriffin v. Palmers Shipbuilding & Iron Co Ltd.28 where an obstruction protruding from a furnace (but which was not a part of it) did not render the furnace defective; Yarmouth v.France29, where it was decided that a defect in an item of plant included ‘anything which render the plant, etc. unit for the use for which it is intended, when used in a reasonable way and with reasonable care’; and the curious decision in Jackson v. Mumford30, which decided that the word ‘defect’ did not include design defect. The Tate definition is not sufficiently all embracing. After all, building work can be complete but nonetheless defective – and the Yarmouth definition is potentially too wide, as building can be a unit for use, yet not be defective in the sense that someone can be held responsible for its unfitness.31 Further, the Jackson decision should be treated with some caution.32 It was not followed, although, to be fair it was not cited in Baxall Securities Ltd. v. Sheard Walshaw Partnership33, where the Court of Appeal considered that a flaw includes design as well as workmanship.34 So, Jackson ( which concerned the interpretation of an agreement) is, perhaps, one of those cases that should be treated as confined to its own special facts – a recurring judicial euphemism for binding decisions that do not sit easily with established principles or a prior line of authority.35 26 [1897] 1 QB 502 Kevin Barrett, loc.cit. 28 [1882] 10 QBD 5 29 [1897] 19 QBD 647 30 [1902] 51 WR 91 31 Kevin Barret, loc.cit. 32 Ibid. 33 [2002] BLR 1000 34 Kevin Barret, loc.cit. 35 Ibid. 27 12 If the case do not provide a complete definition of the term ‘defect’, then the dictionaries cannot be criticised if they do no better. For example, Oxford Dictionary of Law (6th edition)36 somewhat enigmatically defines ‘defect’ as meaning ‘ a fault or failing in a thing’, without identifying how the fault or fail should be judged. Daniel Atkinson, in his articles published in his web site, defined ‘defect’ as work which fails to comply with the express descriptions or requirements of the contract, including very importantly any drawings or specifications, together with any implied terms as to its quality, workmanship, performance or design. By definition, therefore, defects are breaches of contract by the contractor.37 It is convenient then to return to Mr Forsyth;s pool. The insufficiency of the pool’s depth meant that it did not conform to the specification. The builder was contractually obliged to achieve the requirements of the specification. As he had not done so, he had breach his contract with Mr Forsyth.38 So, in the context of building work, a more useful definition of the term ‘defect’ is simply to say that something that does not conform to the agreed specification is defective.39 2.2 Qualitative Defects Qualitative defects can be categorised in various ways, including: • 36 Work (including design) or materials not of acceptable quality; Oxford University Press (2006). “Oxford Dictionary of Law (6th Edition”. Daniel Atkinson (1999). “Defects” from http://www.atkinson-laww.com/ cases/CasesArticles /Articles/Defects.htm 38 Kevin Barret, loc.cit. 39 Ibid. 37 13 • Work (including design) or materials that are in themselves of acceptable quality, but which nonetheless do not confirm with the specification or the design brief; and • Work that is in complete Builders must complete the agreed work using materials and workmanship conforming to the contractual requirements.40 If they fail to provide anything necessary to bring about the completion in accordance with the contractual requirements then the work is – latent defects excepted – incomplete.41 In this respect the third category (i.e. incomplete work) may encapsulate the first and second categories if the non-conforming work or materials are discovered before completion of the works.42 Defects failing into any of these three categories may give rise to claims against some or all of the project team.43 2.3 Patent/Latent Defects Defects, whether their qualitative nature, may be patent or latent. It is important to be able to decide when a defects is patent and when it is latent. The starting point, in terms of the case law, is Yandle & Sons v. Sutton44, which decided that a defect is patent if it is open or visible to the eye. But later, in Sunderson v. National Coal Board45, a defect was said to be patent if observable, whether or not actually observed.46 40 Kevin Barret, loc.cit Ibid. 42 Ibid. 43 Ibid. 44 [1922] 2 Ch 1999 45 [1961] 2 QB 244 46 Kevin Barret, loc.cit 41 14 Latent defects, on the other hand, are those that are hidden and, as a corollary to Sanderson, not observable. In Baxall Securities v Sheard Walshaw Patnership47 it was explained that whether a defect is latent is determined by reference to the inadequacy of the works or materials: ‘The concept of a latent defect is not a difficult one. It means a concealed flaw. What is a flaw? It is the actual defect in the workmanship or design..’ But when is a concealed flaw in workmanship or design (and for that matter materials) to be regarded as observable even though not actually observed? Sanderson confirms that answering this questions is an exercise that must be approached objectively.48 For example, in Riverstone Meat Pty Ltd v. Lanchashire Shipping Company Ltd49, a case that concerned the carriage of goods by sea, it was decided that defects were not latent if discoverable by the exercise of due diligence.50 In Rotherham MBC v. Fank Haslam Milan & Co Ltd and M.J. Gleeson (Norhern) Ltd51, a building case concerning the suitability of materials, the term latent defect was described as meaning ‘ in its widest sense a … failure in work or materials to conform to contract in a respect not apparent on reasonable examination’.52 In this case it was not appropriate by the specifier or builder at the time of specification or supply, and could not have been ascertained by the customary examination available, that the specified materials suffered from an inherent characteristics that rendered them unsuitable for the purpose for which they had been specified.53 Therefore, the defect was truly latent. Defects are of fundamental importance because: i. they affect the value of work done (and therefore the obligation to pay, or the right to receive payment); ii. they may prevent work being regarded as complete; 47 [2002] BLR 100 Ibid. 49 [1961] AC 807 50 Kevin Barret, loc.cit 51 [1996] 78 BLR 1 CA 52 Kevin Barret, loc.cit 53 Ibid. 48 15 iii. they may entitle purchasers (and sometimes third party) to compensation; and iv. they may even entitle purchaser to terminate the building contract or the appointment of professional consultants. The importance of the distinction between patent and latent defects often depends on the contractual terms.54 For example, it may not be permissible to certify completion if there are patent defects, or it may be that liability for loss is excluded in respect of latent, but not patent, defects.55 Further, whether defects are patent may be relevant to the duty to mitigate loss and may engage the defence of contributory negligence.56 Finally, whether a defect is patent or latent may sometimes be relevant to the commencement of the relevant limitation period.57 2.4 Defective Work in Malaysian Standard Form Of Contract Provisions In Malaysia, it is a common practise for parties involved in a large construction project to adopt Standard Form of Contract as a basis for entering a formal contract. The two (2) most often used Standard Form are PAM and PWD Standard Form of Building Contract. These two standard forms of contracts do specify a number of provisions regarding of defective works which only deal with the defective works during construction period and defect liability period only. 54 Kevin Barret, loc.cit. Ibid. 56 Ibid. 57 Ibid. 55 16 2.4.1 Defective Work Claim During Construction Period Under the PAM 2006 and PWD Form 203A 2007, there are numbers of clauses that governs the quality of contractor’s work and the materials supplied including the rights, duties and obligations of the parties in respect of defects. Under the Materials, Good and Workmanship To Conform To Description, Testing and Inspection Clause 6.1, PAM 2006 and Materials, Goods and Workmanship, Clause 35, PWD 203A 2007, it is clearly stated that all works, materials, goods and workmanship by the contractor shall be of “the respective quality and standards described in the Contract Documents’ and “in accordance with the standard of the workmanship in the industry”. The obligation of the contractor to procure and achieve the specified quality, kind and standard is an absolute one.58 If the contractor fails to do so, he would be in breach of contract unless the Superintending Officer is willing to permit a substitution by way of a variation instruction.59 In the situation where the contract document does not specify, it would be implied in law that the materials or goods will be of good quality and the workmanship will be carried out with proper skill and care (see Young & Marten Ltd v McManus Childs Ltd60. It was also stated under the clause 35.1 PWD 203A 2007 and clause 6.2 PAM 2006, Superintending Officer or Architect also have the rights to request contractor to submit any documentation such as certificates, vouchers or other evidence to proof that the materials and goods complied with the contract. In the event if there is noncompliance by the contractor to submit what has been requested, the Superintending Officer or the Architect may give order to: 58 Lim Chong Fong, “The Malaysian PWD Form of Construction Contract.” Sweet & Maxwell Asia, Selangor, 2004,pp 29. 59 Ibid. 60 [1969] 1 AC 454 17 (a) Rectify, demolish, reconstruct or remove such materials or goods at the contractor’s own cost.61 (b) Deduct the amount of money of such to rectify, demolish, reconstruct or remove from the money due to contractor.62 There are also provisions that empower the superintending officer or the architect to instruct the contractor to open up for inspection of any work covered up and carry out test on any materials or goods already incorporated in the proposed work or any executed work.63 Clause 6.5 of PAM 2006 and Clause 36.3 of PWD 203A 2007 also expressed that the Superintending Officer of the Architect have the power, in case where the materials, goods and workmanship provided by the contractor are not in accordance to the contract, to instruct the contractor as follow: (a) Removal, demolition and construction64 These are the expressed power of Superintending Officer and Architect to deal with work, materials, goods and workmanship which not in accordance with the contract.65 In PAM 2006, architect has the power to instruct the contractor to remove, demolish and reconstruct the defective work. Similar in PWD 203A where the Superintending Officer has the power to instruct contractor to remove or reconstruct any defective works. Both standard forms require this to be done in writing. Architect or Superintending Officer cannot merely condemn the defective works without ordering removal.66 In the case of Holland Hannen & Cubitts (Northern) Ltd v Welsh Health Technical Servises Orhganisation67, it was 61 See Clause 6.5(a), 6.5(b), 6.5(c), 6.5(d) of PAM 2006 and Clause 36.3 of PWD 203A 2007. See Clause 6.5(e), 6.7 of PAM and Clause 33.0 of PWD 203A 2007. 63 See Clause 35.2 of PWD 203A 2007 and Clause 6.3 of PAM 2006. 64 See Clause 6.5(a), 6.5(b) of PAM 2006 and Clause 5.1(d), 36.3 of PWD 2007. 65 Wong Bi Xia (2009).”Measure Of Damages For Defective Building Works.” Universiti Teknologi Malaysia. Tesis Msc. 66 Wong Bi Xia, loc.cit. 67 [1981] 18 BLR 80. 62 18 held that a notice condemning the windows that installed by the sub contractor are not in accordance with the contract does not create a valid notice as the notice does not require removal of anything by the architect. (b) Acceptance68 With the consent of employer, the architect may in writing to allow contractor to leave all work, materials, goods or workmanship without any removal, demolition or reconstruction to the work.69 However, this acceptance is subject to set off of all cost, loss and expense incurred and suffered by the employer. (c) Variation70 The obligation of the contractor to procure and achieve the specific kind, standard and quality of materials, goods and workmanship is an absolute one.71 If the contractor fails to do so, he will be in breach of contract unless the architect or Superintending Officer is willing to permitting substitution by way of variation order.72 Clause 6.7 of PAM 2006 and Clause 5.3 of PWD 203A 2007 allowed the employer to employ other person or a third party to rectify the works or to make good all the non compliance works by the contractor if he in default in not complying with the Superintending Officer’s or the Architect instruction to remove, demolish, reconstruct or rectify the defective works. All the cost incurred by the Employer including the cost for loss and expense is recoverable from the contractor. This is an addition to the other two remedies which the employer possesses: an action for breach, namely, treating the contract as repudiated at common law and the drastic procedure of determination.73 This clause provide employer with a more practically effective remedy. Its object is to enable 68 See Clause 6.5(e) of PAM 2006. Wong Bi Xia, loc.cit. 70 See Clause 6.1 and Clause 11 of PAM 2006 and Clause 35.1 and Clause 24 of PWD 203A 2007. 71 Lim Chong Fong, loc.cit. 72 Ibid. 73 Sundra Rajoo, “The Malaysian Standard Form Of Building Contract (The PAM 1998 Form).” Malayan Law Journal Sdn. Bhd., Kuala Lumpur. 1994. pp 99. 69 19 the employer to secure the physical performance on the site of the Super Intending Officer’s or the Architect’s instruction when a contractor refuses or neglects to obey the instruction.74 2.4.2 Defect Work Claim During The Defects Liability Period There are also provisions in PAM 2006 and PWD 203A 2007 that governs the contractor’s responsibility for rectifying defect works after the completion of the work. Clause 15 of PAM 2006 and Clause 48 of PWD 203A 2007 specifies that the contractor is responsible for any defect, imperfection, shrinkage or any other default which appears during the Defect Liability Period (DLP). Lord Diplock in P&M Kaye Ltd v Hosier & Dickinson Ltd75 said of Clause 15(2) of the JCT 1963 Form which is equally applicable to these two clauses : “Condition 15 imposes the contractor a liability to mitigate the damage caused by his breach by making good defects of construction at his own expense. It confers upon him the corresponding right to do so. It is a necessary implication from this that the employer cannot, as he otherwise could, recover as damages from the contractor the difference between the value of the works if they had been constructed in conformity with the contract and their value in their defective condition, without first giving to the contractor the opportunity of making good the defects.” Under Clause 15.4 PAM 2006 and Clause 48.1(b) PWD 203A 2007, the Superintending Officer or the Architect is allowed to specify in a schedule of defect any defect, shrinkage, imperfection or any other fault which appear within the DLP and deliver to the contractor not later than fourteen (14) days after the expiry of the D LP. The contractor is obliged, after receiving the schedule, to make good all the defects specified 74 75 Ibid. [1972] 1 WLR 146 20 within 3 months under PWD 203A 2007 or 28 days or within such longer period as may agreed in writing by the Architect as stated in PAM 2006. In the event where the contractor refuse or fail to rectify and make good the defects, Clause 15.4 PAM 2206 entitled the employer to recover the cost of making good defect by employ and pay third party to rectify the defects and this cost shall be set-off by the employer under Clause 30.4. For PWD 203A, under Clause 48.2, the cost will be deducted from any money due or to become due to the contract and failing which such costs will be recovered from the Performance Bond or as a debt due from the contractor. 2.5 Defects and Interim Payment Under the common law, builders are, subject to the doctrine of substantial performance, entitled to be paid only when work is complete unless the contract expressly provides otherwise.76 In practice most building contracts, with the exception perhaps of those of very short duration, expressly include some mechanism for payment on account to the builder.77 Indeed, for most builders, the cash flow generated by payments on account is generally crucial to their solvency. Lord Denning, in the case of Gilbert-Ash (Northern) Ltd v. Modern Engineering (Bristol) Ltd78 famously said: “There must be a cash flow in the building trade. It is the very lifeblood of the enterprise.” This cash flow is so important that the Parliament of United Kingdom intervened in 1996 to provide a mandatory statutory framework for interim payment and 76 Kevin Barret, loc.cit Ibid. 78 [1973] 1 BLR 75 77 21 deductions.79 It is to see that builders are paid on account for the work done as a project progresses, but only if the work is done properly. If there are defects, then work cannot be said have been done properly and so purchasers ought not to be obliged to pay for it.80 2.5.1 The Contractual Position Standard form of contract conditions tend to provide that builders are entitled for payment, including interim payment, only in respect of work properly executed. In this respect the terms dealing with payment amount to a direction to the person charged with valuing the work. For example, in PAM 2006 the architect is obliged to certify for payment only ‘the total value of work properly executed’ and ‘ the percentage of the value of material and goods delivered’.81 Similarly, the Superintending Officer under the PWD 203A 2007 conditions is obliged to certify the estimated total value of the work properly executed and up to 90% of the value of the unfixed materials and goods delivered to or adjacent site intended for the incorporation into the permanent works.82 2.5.2 Interim Valuations, Certificates and Payments Interim valuations, certificates and payments do not amount to an acknowledgement that work is defect free unless the contract provides otherwise in which they rarely do.83 Furthermore, interim certificates do not, unless the contract provides 79 Kevin Barret, loc.cit Ibid. 81 See Clause 30.2 of PAM 2006. 82 See Clause 28.4 of PWD 203A 2007. 83 Kevin Barret, loc.cit 80 22 otherwise, give rise to a ‘temporary finality’ or ‘pay now, sue later’ requirement.84 This is because interim valuations, certificates and payments are usually provisional. This means that the valuer may, unless the contract provides otherwise, adjust interim valuations/ certificates by omitting the value of work previously included and paid for if it is subsequently discovered to be defective.85 The valuer may address such adjustments at the next valuation/ certification, but in any event the purchaser may do so earlier (including after a valuation has been notified or certified, but before the payment of the sum due) if defects are discovered after a valuation or certificate is issued to the builder. The provisional nature of interim valuations and certificates is reflected in the practice of assessing the gross value of all work done up to the valuation date, rather than the value of work done between valuation dates.86 This means that, if that work that has been valued and included in a certificate is subsequently discovered to be defective, the gross value can be adjusted in the next interim valuation or certificate by excluding the defective works from the gross valuation. This will inevitably have an impact on the net payment due.87 Things will get problematic if defects are discovered after a certificate is issued but before payment is made, particularly so if it is disputed that the work in question is defective.88 If this occurs, builders sometimes insist that payment of the certified sum is made, while purchasers usually refuse to pay any more than the true value after taking account of subsequently discovered defects which usually means paying less than the net sum due under the valuation or certificate in question.89 This is especially likely if defects are significant (either individually or collectively) and will result in the builder being substantially overpaid if the full amount certified is paid.90 This desire to avoid payment is all the stronger where purchasers lack confidence in their builder’s ability to repay if the defects are not corrected by the next valuation date. The practice of making 84 Ibid. Ibid. 86 Ibid. 87 Ibid. 88 Ibid. 89 Kevin Barret, loc.cit 90 Ibid. 85 23 deductions from interim payment to reflect the true value of works has led builders to challenge the right to make such deductions. One such challenge met with success. This occurred in Dawnays Ltd v. F.G. Minter and Trollope & Colls Ltd,91 where it was said, in the Court of Appeal, that an interim certificate is the equivalent of cash or a negotiable instrument and therefore must be paid less only permitted deductions (which, under the particular contract in Danways, included only retention, discount and previous payments). Later, however, in GilbertAsh92 the House of Lords took a different view. In this case it was said that: ‘…in construing a contract one starts with the presumption that neither party intends to abandon any remedies for its breach arising by operation of law and clear express words must be used in order to rebut this presumption.’ The effect of this was that the purchaser was allowed to exercise the right ordinarily available at law to set off against certified sums the amount of his cross-claim for breach of contract.93 While there remained some debate as to whether the Gilbert-Ash decision applied only to the particular contract under scrutiny, it is a decision that has been treated since as one of universal applications. The result has been that, in the absence of clear words, the courts have refused to exclude the defences to payment otherwise available at law.94 For example, in NEI Thompson Ltd v. Wimprey Construction UK Ltd,95 a contractual set off clause was held not to exclude the common law right of set off. In United Kingdom, the outcome of Gilbert-Ash was that some publishers of model conditions, notably the JCT, amended some of their sub-contract conditions to limit the right of builders to set off against sums due to their subcontractors. The JCT limited the right of set off to those instances where notice in writing of the intention to set off was given within a stipulated period before the contractual payment date and 91 [1971] 1 BLR 16 Supra No.76 93 Kevin Barret, loc.cit 94 Ibid. 95 [1987] 39 BLR 65 92 24 provided for an adjudicator to determine the validity of the deductions so notified.96 Subsequently, however, the usefulness (to subcontractors) of this mechanism was reduced when the courts made it clear that the defence of abatement was subject to Gilbert-Ash principle and remained available unless clear words excluded it and that words excluding or restricting the right to set off cross claims were not sufficient to exclude the defence of abatement (see Acsim (Southern) Ltd. v. Danish Contracting and Development Co Ltd97 and A.Cameron Ltd v. John Mowlem Plc98 ). The effect of these decisions was that builders retained the right to dispute the value of work done by their subcontractors and also retained the right to pay less than the amount certified if they did so, but denuded the contractual adjudicator of power to determine the validity of the abatement.99 This rendered the pre-1996 JCT adjudication mechanism largely worthless. The position was much the same in the main contract relationship between purchaser and builder. In this respect the Court of Appeal, in C.M. Pillings & Co Ltd v. Kent Investments Ltd,100 could not find nothing in the wording or provisions of the JCT Prime Cost Contract 1967 edition either requiring immediate payment of certified sums where a bona fide dispute as to the correctness of the certificate existed, or making payment of a certified sum a condition precedent to the right to arbitrate the dispute. Likewise it was found that other main contracts with similar wording did not exclude the right to set off certified sums (see R.M. Douglas Construction Ltd. v. Bass Leisure Ltd101 ). The effect of these decisions was that the payer retained the right to adjust the valuation at any time in the absence of clear express contractual provision to the contrary and so could always protect himself from the impact of defects by consequently adjusting the amount of an interim payment right up to the point of payment. 96 Kevin Barret, loc.cit [1989] 47 BLR 59 98 [1990] 52 BLR 24 99 Kevin Barret, loc.cit 100 [1985] 30 BLR 80 101 [1990] 53 BLR 119 97 25 2.6 Conclusion Defects are categorised into two types, which are Qualitative Defect and Patent/ Latent Defects. Under the Malaysian construction Standard Form of Contract, contractor is obliged to carry out and complete the work in accordance to the standard and specification as spelt in the contract. Employer has the right to instruct and require the contractor to repair or rectify any defective or works not up to the specification and standard which occurred during the construction period and Defect Liability Period at contractor’s own cost. Failing to do so, contractor can be held as in breach of contract and Employer have the rights to take action in respecting of the defective works by employing third party to rectify the works which the cost to be borne the main contractor or by setoff and abatement the value of defective works in the interim certificates. 26 CHAPTER III ABATEMENT IN UK CONSTRUCTION INDUSTRY 3.0 Introduction When defects occur as a result of breach of contract or duty, the injured party is entitled to an award of compensation for loss suffered, put simply, a sum of money that recognises and reimburses all of the losses suffered as a result of the breach. Sometimes, however, the injured party may want to enforce performance either as an alternative or in addition to claiming compensation. Obtaining compensation can be achieved in one of three ways: a) The first is a form of judicially recognized self help called abatement. b) The second is another judicially recognized form of self help called set off. c) The third way is by way of an action for damages which is right to commence legal proceedings for an award of compensation. 27 In considering what defences may be available, much depends upon what steps a contractor takes to enforce the claim to payment.100 If the matter is taken to arbitration or to a full trial in court, then those proceedings should deal with all the issues between the parties.101 3.1 Set-Off The remedy set-off is a procedural device that permits the injured party to offset the compensation he claims against money claimed by the alleged wrongdoer under the same or any other contract.102 The right of set-off is not unfettered. It applies only to claims and conterclaims in three situations: • First, where the amounts claimed by each party amount to a liquidated debt or money demand that can be ascertained with certainty at the time of pleading (known as common law set-off) – but a claim for damages will not generally fall into this category.103 • Second, where there is a close and inseparable connection between claim and counterclaim such that it would be manifestly unjust to give judgment on the claim without taking into account the counterclaim (known as equitable setoff). Generally, this requires the claim and counterclaim to arise from connected dealings,104 but the mere existence of two or more contacts between the parties does not itself amount to a connected dealing.105 100 Murdoch, J. and Hughes, W. (1992). “Construction Contracts Law and Management.” E & FN Spon, London, pg 336. 101 Ibid. 102 Kevin Barret, loc.cit 103 See Hargreaves (B) Ltd. v. Action 2000 Ltd [1992] 62 BLR 72 104 See Bim Kemi Ab v. Blackburn Chemicals Ltd [2001] All ER (D) 13 105 See Anglian Building Products Ltd v. W&C French (Construction) Ltd [1972] 16 BLR 1 28 • Third, where the claimant is insolvent, a set-off of mutual dealings is permitted under the Insolvency Act 1986 and the Insolvency Rules 1986. The effect of a set-off is that the court will not permit the enforcement of the claim, even if it is admitted, until the counterclaim has been determined.106 The right of set-off may be excluded or restricted by contractual terms, although in accordance with the Gilbert-Ash principle, clear words are required to affect an exclusion of the right of set-off.107 Where the contract out of which the claim arises is a construction contract for the purposes of the Housing Grants, Construction and Regeneration Act 1996 as in the UK, the right of set-off may be exercised only if notice is given in accordance with that Act. 3.2 Abatement The common law right of abatement is a defence which is generally limited to contracts for sale of goods or for work and materials and can be invoked by a defendant to reduce the value of goods and services supplied by the claimant where, for some reason, the goods and services in fact supplied did not justify the payment of the full agreed price by the defendant.108 So it means the right of the person for whom work is carried out to reduce the price which he has agreed to pay, usually because the work has not been done properly, or has not been completed.109 It is a means of adjusting the sum payable, rather than requiring a separate cross-claim to be brought. Accordingly, abatement goes to the question of what amount becomes “due” under 106 Kevin Barret, loc.cit Ibid. 108 Simon JA Tolson (2004). “ Payment, Abatement and Set-Off” from http://www.fenwickelliott.co.uk/files/docs/articles/html/payment_abatement_setoff.htm 109 Simon JA Tolson, loc.cit. 107 29 the contract and should be considered when preparing the payment notice but not necessarily a withholding notice. Abatement is a common law right to reduce the price or value of work on the grounds that the work is defective or incomplete. Abatement is therefore only available where there are defects in the quality of the works. It cannot be used as a defence to claims for delay or disruption to the works, or claims for damage to other property. Nor can it be used as a defence to payment for professional services, such as design and engineering work or technical and supervisory services.110 The measure of the abatement will be the amount by which the works have diminished in value as a result of the deficient or defective performance. The method of assessing the diminution in value will depend on the facts and circumstances in each case. In some cases, the diminution in value may be determined by comparing the current market value of the item as constructed, with the market value that it ought to have had. In other cases, the diminution in value may be determined by reference to the cost of remedial works111. The right to abate the price does not permit anything other than a deduction against the price. It was confirmed by the Court of Appeal in Mellowes Archital Ltd v. Bell Project Ltd112 that abatement applies only to the subject matter of the contract in question, i.e. the work and goods supplied and then only where the breach results in diminution in value of the subject matter. In this respect it was said that: “It is therefore clear that , for a party to be able to rely upon the common law right to abate the price which he pays for goods supplied or work done, he 110 Herber Smith (2009). “Set-Off and Abatement Under International Construction Contract” from http://www.herbertsmith.com/NR/rdonlyres/2FE9904E-2AE1-4FE5-A615-4777F206A298/11396 /Newsletter4EJune2009.pdf 111 Ibid. 112 [1997] 87 BLR 26 30 must be able to assert that the breach of contract has directly affected and reduced the actual value of the goods or work, the thing itself.” The result in this case was that the purchaser could not abate the price by reference to delay costs. There is some uncertainty as to the extent to which the defence of abatement applies to a professional consultancy contract.113 The importance of abatement is that the alleged wrongdoer must sue for his money if he disagrees that he is in breach or disagrees with the amount deducted, but the court will not order the injured party to pay the sum withheld pending trial (i.e. it will not grant summary judgment) unless it is satisfied that the defendant has no real prospect of successfully defending the claim.114 In Barrett Steel Buildings Ltd v. Amec Construction Ltd,115 it was decided that the cost of remedying defects might be relied upon as the measure of the diminished value. However, that was a case where the court was asked to determine whether the defendant had an arguable defence to the claim (in which case summary judgment had to be refused), so the position may be different on a final determination of the defence. The right to abate does not require the alleged wrongdoer to pay money to the injured party.116 If the abatement extinguishes the price (or any unpaid balance) altogether (as may occur if the cost of remedial works exceed the price or any unpaid balance), the injured party must, if he wishes to recover the balance, bring an action for compensation and prove his entitlement (unless he can set off the balance against money owed to the builder under a different contract).117 113 See Hutchison v. Harris [1978] 10 BLR 19 Kevin Barrett (2008). “Defective Construction Work and The Project Team.” Wiley-Blackwell. United Kingdom. pp 165 115 [1997] 15-CLD-10-07 116 Supra No. 114 117 Supra No. 114 114 31 The common law right to abate the price is one of those rights that the law presumes to be available unless clear words in the relevant contract expressly excluded it. This doctrine has been stated in Gilbert – Ash (Northern) Ltd. v. Modern Engineering (Bristol) Ltd118 as below: “[It] has long been a general principle of law that if one man does work for another, the latter when sued, may defend himself by showing that the work was badly done and that the claim made in respect of it should be diminished. On the same principle, the purchaser of an article sold with a warranty may, when sued for the price, say that there was a breach of warranty and he may set this up in order to diminish or even extinguish the price.” Nevertheless, the decision in Halesowen Presswork v. Westminister Bank119confirms that the presumption may be impliedly rebutted. Further, the right of abatement may expressly excluded or restricted, but it was decided in the Mellowes case that words that exclude the right of set-off did not operate to exclude the right to abate. If the right to abate is expressly excluded, the exclusion will be subject to the requirements of the UK’s Unfair Contract Terms Act 1977, as occurred in Steward Gill Ltd v. Horatio Myer & Co. Ltd.120 In this case, the plaintiff made a contract to provide a conveyor system for the defendant, with payment by installments. The plaintiffs claimed the last 10% but as the conveyor had faults, the defendant wished to set off its claim against the payment. The plaintiff's standard terms provided that customers could not withhold payment because of any "payment, credit, set-off, counterclaim, allegation of incorrect or defective goods or any other reason whatsoever". The Court of Appeal held that the clause was not within s3 but as it restricted remedies it was within s13 (s13(1)(b)). It was subject to the test of reasonableness and reading the clause as a whole, it was too wide and stopped the defendant using a genuine set-off. The clause was therefore 118 [1973] 1 BLR 75 [1972] AC 785 120 [1992] 2 all ER 257 119 32 unreasonable and the plaintiff could not rely on it. However, the defendant may rely on abatement to get his right due to the defective conveyor supplied by the plaintiff because it was already decided in Mellowes case that excluding the right to set-off did not operate to exclude the right to abate for the injured party. 3.3 Differences Between Set-Off And Abatement The rights of set off and abatement are common, but frequently misunderstood. Although at first sight they have many similarities, they are in fact very different and operate in completely different ways. Set-off, which is a form of counterclaim, concerns the deduction of damages caused by a party’s breach of contract. A set-off can be applied to reduce or extinguish payments otherwise due under the contract. Abatement, on the other hand, concerns the common law right to reduce sums otherwise payable by asserting that the sum claimed has not been earned121. Conversely, set-off does not relate to the amount which the supplier is entitled to be paid for the work which he has done, but refers to an entirely separate right which accrues to the purchaser through the supply of what was contracted for, which relates not to the value of what was supplied but, instead, to the consequences of the manner in which it was performed.122 An essential prerequisite for a right of set-off is that the supplier has committed a breach of contract entitling the purchaser to damages. An obvious example of this is a claim for liquidated and ascertained damages, or even unliquidated damages, for delay.123 121 Brewer, G. (2006). “Legal Case Study: The defence of abatement”. Contract Journal. http://www.contractjournal.com/Articles/2006/11/01/52679/legal-case-study-the-defence-ofabatement.html 122 Simon JA Tolson, loc.cit. 123 Ibid. 33 As a matter of principle, abatement involves an argument that goes to the quantification of the sum “due” under the contract, whereas set-off may, if the circumstances exist, constitute a ground for withholding payment of some part of what is “due”. It follows that, in terms of payment notices and withholding notices, an abatement should be raised at the valuation stage and, at the latest, at the time the payment notice is required to be given. Conversely, a set-off is not a matter which relates to valuation and the paying party must therefore ensure that it is protected by an effective and valid withholding notice given at the proper time. An example of case which distinguish the rule of set-off and abatement is Barret Steel Buildings Ltd v. AMEC Construction.124 This case was examined base on DOM 2 sub-contract conditions for use with JCT 81 Design and Build Contract. AMEC were main contractors for the building of a hospital. They had subcontracted the design, supply and erection of the structural steelwork for the building to Barrett. A dispute arose concerning the design of the steelwork which AMEC alleged to be defective. They considered that the steelwork was unfit for its purpose in that the floor slab sagged to an unacceptable degree. Accordingly AMEC advised their sub-contractor of their intention to set-off monies under clause 23.2.1 of the sub-contract, arising from the use of a proprietary self-levelling screed to correct the deflection in the floors. On receipt of this notice, the sub-contractor proposed adjudication and arbitration as provided for in the subcontract. However, a meeting took place one month later which culminated in AMEC notifying Barrett that they had "withdrawn implementation" of clause 23.2.1. Matters were not however resolved and AMEC continued to refuse to pay interim applications for payments. Finally, Barrett applied to the court for summary judgment pursuant to the rules of the Supreme Court Order 14 or, alternatively, for an interim payment 124 [1997] 15-CLD-10-7 34 pursuant to Order 29 Rule 10. In its defence and counter-claim AMEC submitted that they had a good defence to Barrett's claim on three different counts as follows: • They firstly argued that they were entitled to an abatement of the sub-contract price such that any outstanding liability to Barrett would be extinguished, by reference to the diminution in value of the sub-contract works by reason of the defects • Secondly, they argued that they were entitled to set-off the sums for remedial works counter-claimed under clause 23.2.2 of the sub-contract • Thirdly, they argued that payment of the sums claimed in Barrett's applications for payment were not due as the work was not "properly executed" in accordance with the terms of the sub-contract. Barrett argued that AMEC could not maintain a set-off against them because the set-off claim, if it had ever been valid, had been withdrawn by AMEC. They further argued that there was no difference between the so-called abatement as pleaded and the claim to set-off the costs of the remedial works. If the abatement plea was allowed, this would mean that the restrictions on the right of the contractor to raise the set-off as imposed by the sub-contract conditions would be valueless to a sub-contractor. In a fairly sweeping judgement the court held that the sub-contractor was not entitled to payment as claimed. It was held that the DOM 2 conditions did not prevent AMEC from relying on the defence of abatement. AMEC were entitled to plead that the value of Barrett's work was diminished by the cost of the works needed to rectify 35 the defects in it. Interestingly, the court also held that at the same time AMEC would be entitled to claim a set-off of the same costs under clause 23 of the sub-contract based on a claim for damages for breach of contract. If AMEC were successful under both heads they would not be permitted a double benefit. Of further importance, the court held that a defendant in a supply contract, including a building contract, may rely on the cost of remedying defects as a measure of the reduced value of the goods or services provided. In the context of construction, such costs may often be greatly in excess of the original value or price of the work done. The court also recognised that AMEC's third line of defence that the work was not "properly executed" in accordance with the sub-contract was equally valid. Such a claim was not in the nature of a set-off but was a ground of defence similar to but distinct from the common law defence of abatement. It arose under the contract and therefore was not excluded by the set-off provisions of the contract. Finally, and perhaps academically, the court held that AMEC had not withdrawn their claim to a set-off. Notifying that they had "withdrawn implementation" of clause 23.2.1 had not amounted to withdrawal of their claim to a set-off, but merely that they would not implement the claim before the outcome of discussions between the parties was known. 36 3.4 Common Law Rights of Abatement Of Price Generally in the UK, there are two different ways in which laws can be made. The first is statutory law, which is made by Parliament and sets out measures to protect the environment and the public by establishing general rules under which environmental matters are regulated.125 Generally, although not exclusively, breaches of statutory law are crimes and are punished by the courts using criminal sanctions, such as fines, imprisonment or Court Orders. The second system is that of Common Law, which is law made by Judges establishing legal precedents arising from disputes between one person and another. Common law looks at the reasonableness of actions and where actions are judged to be counter to established rights, the Courts can impose civil sanctions such as injunctions, award of compensatory damages and Court Orders. The framework of environmental rights is established under various types of common law, principally the law of tort, but to a lesser extent contract and property. The Employer will not wish to pay the full contract price first and then counterclaim for damages by way of set-off. Apart from the inconvenience of doing so, the legal fees as well as the cost of the remedial works themselves will create a significant adverse cashflow for the Employer.126 He will also increase his exposure to the consequences of the Contractor’s possible insolvency, always a serious consideration in the present economic climate.127 Instead the Employer will wish to deduct the cost of remedial works from the amount due to the Contractor. He has this right at common law to raise a defence of abatement against any action for payment in full by the contractor Slater v. CA Dumequin Ltd128. This right of abatement only applies to defects which are patent at the time payment is due.129 125 Waste Dynamics (2003). “Common Law and Civil Liability” from http://www.wastedynamics.name/images/ No9%20Common%20Law.pdf 126 Daniel Atkinson (1999). “ Defects” from http://www.atkinson-law.com/cases/ CasesArticles/ Articles/Defects.htm 127 Ibid. 128 [1992] 29 CON LR 24 129 Supra No.125 37 It is suggested that the amount by which the Employer might rightfully reduce the amount due to the Contractor is limited to the cost which the Contractor would have incurred in remedying any defect.130 Where the defects are the responsibility of the Contractor and he does not carry out the remedial work within a reasonable time then the Employer is entitled to abate the amount otherwise due to the Contractor, by the amount it would cost the Employer to remedy the defect. This additional liability arises from the Contractor’s further breach of contract in not remedying the defect. 3.5 Abatement Under UK’s Housing Grants, Construction And Regeneration Act 1996 (HGCRA), Part II The Housing Grants, Construction and Regeneration Act 1996, (HGCRA) introduced statutory provisions seeking to regulate the right to withhold payment, and so impacts on the law of set-off.131 Under Section 104, it is stated that the HGRCA only applies to ‘construction contracts’ , these being contracts : 1) For the carrying out of construction operations ; 2) Arranging for the carrying out of construction operations by others ; 3) Providing labour or the labour of others for the carrying out of construction operations. References to construction contracts include agreements to carry out architectural design or surveying work and to provide advice on building, engineering, decoration or landscaping in relation to construction operations. 130 Ibid. Neil F. Jones (1991). “Set-off In The Construction Industry.” Blackwell Science, United Kingdom, pg 47 - 61 131 38 Construction operations are themselves defined in section 105 of the Act and may broadly be summarized as work or work and materials in connection with building and engineering. Agreements purely for the sale of goods do not come within the definition. Certain operations are expressly excluded from the definition of construction operations132 including, by virtue of the Construction Contracts Exclusion Order 1998 (SI 1998 No. 648), certain agreements arising under statute and under the private finance initiative.133 The exclusion order also excludes certain finance and development agreements from the ambit of the HGCRA. Further the HGCRA does not apply to contracts with a ‘residential occupier’ of a dwelling or flat.134Lastly, the HGCRA only applies to agreements in writing.135 (defined in section 107). In relation to construction contracts, it is provided by the HGCRA that: • A party shall have the right to refer disputes to adjudication under a procedure complying with section 108 ; and • A party shall be entitled to stage payments unless the duration of the work is or is expressed to be less than 45 days (section 109); and • The contract shall provide an adequate mechanism for determining what payments become due, when and the final date for payment (section 110); and • The right to withhold payment is restricted to those circumstances where an ‘effective notices’ is given (section 111); and • There shall be a right to suspend performance for non-payment (section 112); and • Pay when paid provisions, except those linked to insolvency, are prohibited (section 113). 132 See Section 105(2), HGCRA 1996 Part II Neil F. Jones, loc. cit. 134 See Section 106, HGCRA 1996 Part II 135 See Section 107, HGCRA 1996 Part II 133 39 Further, where construction contract does not comply with any of these requirements, the relevant provisions of the Scheme for Construction Contracts will apply as if the Scheme were an implied term of the contract.136 The JCT and other bodies have amended their standard forms of contract with the intention that they should comply with the HGCRA.137 Despite this, there is nothing to stop the parties using earlier versions of JCT contracts if they wish.138 To the extent that those earlier version do not comply with the HGCRA, the consequent effect will be that the relevant parts of the Scheme will be implied.139 In addition, in relation to those contracts which do not come within the definition of ‘construction contract’, the parties are free to adopt terms which do not conform with the HGRCA. For these reasons it cannot be assumed that the pre-existing versions of the standard forms of building contract in use prior to the HGCRA will entirely fall into disuse, or that the decisions relevant to them will become entirely redundant. Where party wishes to rely on any of the provisions of the Scheme for Construction Contracts it will have to go through the process of establishing that the contract in question: • Is a construction contract; and • Does not relate to a residential occupier; and • Is in writing; and • Does not conform with a particular requirement of the HGCRA. Adjudicators appointed under the Scheme may find themselves called on to decide on the above matters.140 136 See Section 104 (4), HGCRA 1996 Part II Neil F. Jones, loc. cit. 138 Ibid. 139 Ibid. 140 Neil F. Jones, loc. cit 137 40 3.5.1 Withholding Payment A statutory restriction on the right to withhold payment is conferred by section 111(1) which provides: 1) A party to a construction contract may not withhold payment after the final date for payment of a sum due under the contract unless he has given an effective notice of intention to withhold payment. The notice mentioned in section 110(2) may suffice as a notice of intention to withhold payment if it complies with the requirements of this section. 2) To be effective such a notice must specify: a) The amount proposed to be withheld and the ground for withholding payment, or b) If there is more than one ground, each ground and the amount attributable to it, and must be given not later than prescribed period before the final date for payment.’ Prima facie, section 111(1) does not restrict the right to abate the price (i.e. the value of the measured work) because: 1) It does not expressly do so; and 2) The words of section 111(1), i.e.’ … of a sum due to under the contract…’, arguably allow the paying party the right to contend that there is no sum ‘due’ because of either defective, incomplete or nonconforming work. Support for this proposition may be discerned, by analogy, from the decisions in Acsim v. Danish, Cameron v. Mowlem and Barrett Steel Buildings Ltd v. Amec Construction Ltd (see-Chapter 2). However, there may be an exception to this approach (see section 3.2.2). 41 Assuming, as is likely, that the courts interpret section 111(1) as leaving the common law right to abate intact, the paying party under a construction contract will, in principle, be entitled at any time to exercise the right to abate the price without giving any advance notice of the intention to do so.141 Therefore if defective incomplete or non-conforming work is discovered after the payment notice under section 110(2) is given, and after the last date for giving notice of intention to withhold payment has passed, the paying party may reduce the amount to be paid by reference to the value of the abatement of the price.142 Although it will remain open to the paying party to dispute the sum ‘due’, the receiving party could overcome this by asking the arbitrator to decide the amount due, the date when it was due and whether and effective notice was given in accordance with the contract.143 In principle, therefore, it would appear that the effective notice under section 111(1) will only apply to the withholding of payment by way of set-off. If so, then in order to determine that may be withheld it will be necessary look at the background law, in which case a party wishing to withhold payment will be required to establish that the basis for withholding payment is not prohibited by the contract and is one of the three recognized categories of set-off, and if unable to do so the party withholding payment will be ordered to pay the sum due.144 If the preceding propositions are correct, the HGCRA is procedural in nature, at least in relation to set-off, and does not alter the substantive law concerning abatement or set-off.145 Furthermore, it means that the HGCRA has not addressed the Latham recommendation that set-offs should not relate to any contract other than the one in progress, or the criticism of set-off.146 141 Neil F. Jones, loc. cit. Ibid. 143 Ibid. 144 Neil F. Jones, loc. cit. 145 Ibid. 146 Ibid. 142 42 3.5.2 Abatement And Set-Off In Response To The Claim Under Part 1 of the Scheme, by paragraph 20, the Adjudicator ‘… shall decide the matters in dispute’ and may take into account any other matters … which are matters under the contract which he considers are necessarily connected with he dispute’. If adjudication is commenced in relation to a claim for the value of work done, the employer might respond by alleging that the work is defective. If so, paragraph 20 of the Scheme permits a defects cross-claim to be utilized as a defence against a valuation claim. The defects entitle the paying party to invoke the defence of abatement (see section 1.3) which is necessarily connected with the dispute.147 It was not necessary to give notice of set-off under the pre-April 1998 contracts in order to exercise the right to abate.148 The position is likely to be different, however, where defects are relied on by way of an equitable set-off rather than abatement. In those circumstances the adjudicator should not entertain the defects cross-claim unless it has been the subject of an effective notice.149 Allowing a cross-claim into an adjudication would beg the question of whether it can stand as a counterclaims well as a defence. This is difficult but it is possible that, so far as the cross-claim overtops the original claim, it may constitute a separate dispute so that the adjudicator ought not to make a decision in favour of the counterclaiming party other than by way of dismissing the original claim to the extent that it is extinguished by the cross-claim. 147 Neil F. Jones, loc. cit. See Ascim (Southern) Ltd v. v. Danish Contracting & Development Co. Ltd [1989] 47 BLR 22 149 See Section 1.3 GGCRA Part II, 1996 148 43 3.5.3 The Adjudicator’s Decision – Abatement and Set-Off In Response The Scheme adjudicator is empowered by Rule 20 of the Scheme to decide the matters in dispute. In so doing he may decide that any of the parties to the dispute is liable to make a payment under the contract, and decide when the payment is due and the final date for payment. This power is subject to any effective notice of withholding of payment. Further disputes may arise between the parties after the adjudicator has given his decision on a particular dispute. For example, the adjudicator may order that a payment be made but the paying party may discover defects (or further defects) after the adjudicator has given his decision and, as a result, refuse to pay the amount decided on in the decision.150 The paying party could argue that he is merely abating (this would be the position where he is setting off a defect cross-claim against a valuation claim) or legitimately setting off within the contract (setting off may, however, be difficult because under the Scheme a notice of intention to withhold payment under section 111 will nearly always need to be served before the decision is reached, if it is to be effective in avoiding having to honour the decision itself).151 It is arguable however that the paying party, if he can establish either an abatement or (subject to an effective notice ) a set-off, may be able to resist payment of an adjudicator’s award. There is, however, a further difficulty to be overcome when deploying an abatement of an adjudicator’s decision. Namely the effect of Rule 23 of the Scheme which provides: 1.) In his decision, the adjudicator may, if he thinks fit, order any of the parties to comply peremptorily with his decision or any part of it. 150 151 Neil F. Jones, loc. cit. Ibid. 44 2.) The decision of the adjudicator shall be binding on the parties and they shall comply with it until the dispute is finally determined by legal proceedings, by arbitration (if the contract provides arbitration or the parties otherwise agree to arbitration) or by agreement between the parties’. By virtue of Rule 23 the parties are bound to comply with the decision until the dispute is finally determined. It is difficult to reconcile the concept of abating or setting off against decisions with the strict wording of Rule 23(2). It is arguable that adjudicators’ decisions are not susceptible to abatement or set-off.152 If so an exception may exist to the general rule, mentioned in section 3.1.4, that the paying party has the right to contend that there is no sum due. It is arguable that rule 23(2), properly construed, does not prevent the abatement of an adjudicator’s decision on the basis that the binding nature of the decision is only as to the amount payable subject to the terms of the contract relating to and affecting payment. However this view may prove inconsistent with the decision in Macob Civil Engineering Ltd v. Morrison Construction Ltd,153 which found that decisions are binding even when the adjudicator errs on the facts, law or procedure. It may be that Rule 23(2) is ultra vires (see section 3.2.3)154. Enforcement of the adjudicator’s decision may be sought though the court either by an application under Part 24 of the CPR155 for summary judgment or exceptionally by way of mandatory injunction or an order for specific performance.156 It is anticipated that Part 24 CPR will probably be the more favoured route for enforcement of decisions requiring the payment of money.157 The basis of the application will be that the adjudicator has decided that the sum is due and that any 152 Neil F. Jones, loc. cit. [1999] CILL 1470; 16-CLD-05-07 154 Supra No.151 155 CPR – The Civil Procedure Rules which came into effect on 26 April 1999 156 See Macob Civil Engineering v. Morrison Construction Ltd. [1999] CILL 1470; 16-CLD-05-07 157 Supra No. 151 153 45 defence to payment ‘has no real prospect’ of succeeding until the matter is finally determined by the court or by agreement. The defendant might seek to raise an arguable defence to the claim by relying on a post decision abatement or set-off and arguing that the obligation to pay has been discharged by virtue of the abatement which, in effect, constitutes a form of compliance.158 Post decision abatement or set-off is not expressly inhibited by Rule 20 or Rule 23(2). Alternatively it may argued that the underlying basis of the abatement or set-off justifies the court granting a stay of execution judgment pending the determination of the abatement or set-off as a special circumstance under Order 47 of the Rules of the Supreme Court (expressly preserved by the CPR) or for making a conditional order under Part 24 CPR.159 It is uncertain whether the first of the preceding arguments will succeed. If it does it will be seen as seriously undermining Scheme adjudication, especially as the post-decision abatement or set-off will not finally determine the dispute giving rise to the decision. There is some authority indicating that the second argument will not generally find favour. In the case of B.W.P (Architectural) Ltd. v. Beaver Building System Ltd,160 it was held that the existence of a bona fide counterclaim did not provide sufficient reason for a stay of execution. Further, in Tubeworkers Ltd v. Tilbury Construction Ltd,161 the court, in connection with the old Green Form of subcontract, was unwilling to usurp the function of the adjudicator by granting a stay of execution of judgment. In that case the court accepted that there might be exceptional circumstances to justify the grant of a stay but that the relevant terms of the contract’ must be paramount and take precedence over the court’s discretion under Order 47’. 158 Neil F. Jones, loc. cit. Ibid. 160 [1998] 42 BLR 86 161 [1985] 30 BLR 67 159 46 Whether the terms of Rule 23(2) will be found to override the right to abate or the court’s residuary discretion to grant a stay in exceptional circumstances remains to be seen.162 However, an exceptional circumstances might be found to exist where, for instance, there are competing adjudication decisions as a result of the post decision abatement or set-off being referred to adjudication.163 If one of the parties insisted on payment of decision in his favour without taking account of the decision in favour of the other party that might, assuming the right to abate is found to have been abrogated by Rule 23(2), constitute an exceptional circumstance justifying a stay of execution or a ground for making a conditional order. 3.6 Conclusion The defences of set off and abatement share some similarities. In actual fact, they are very different claims and have their own requirements and methods of application. Care should be taken to ensure that the correct defence is used in the correct context and that the requirements of the Construction Act are followed. The key point to remember is that abatement operates to reduce the contract price, whereas set off is the right to set off another claim against that contract price. 162 163 Neil F. Jones, loc. cit. Ibid. 47 CHAPTER IV PRINCIPLES OF ABATEMENT AND MEASURE OF DAMAGES DUE TO DEFECTIVE WORKS 4.0 Introduction As discussed before, the rule of abatement is a right that exists in common law. This means it is something a defendant can argue even if the contract with the contractor or sub-contractor does not deal with abatement. As abatement is only a defence to a claim, it could be equally argued as part of a counterclaim under the contract i.e. that the contractor has breached a contractual obligation by producing defective works. Over the last 15 or so years this rule has been the subject of debate as the construction industry and the courts attempt to define the rule’s application in today’s industry.165 165 Greg Brownlee (2009), “ Understanding The Rule Of Abatement.” From http://www.cnplus.co.uk/hot-topics/legal/understanding-the-rule-of-abatement/5204633.article 48 Essentially abatement is a defence to a claim for payment by a contractor or sub-contractor. It applies in circumstances where a defendant argues that they are not liable to pay the amount claimed because there are defects in the work for which the payment is sought. If a defendant is able to prove that the alleged defects do exist and that the defects have caused a reduction in the value of the thing constructed, the defendant will only be liable to pay an amount that accounts for this reduction in value. A withholding notice will not, however, normally be required for a defence of abatement to be argued. The notice obligations under the section 111 of the UK’s Housing Grants, Construction and Regeneration Act 1996 are well understood. The consequences of not providing the right notice on time means the party concerned then has a very restricted ability to argue before a tribunal that they are not liable to pay the full amount claimed – however, abatement is an exception. An employer’s right to defend a claim for full payment on the basis that defects have reduced the value of the construction project will override the failure to provide, or properly provide, a Section 111 notice. That is to say, if the work is defective, the amount due to the contractor may be reduced correspondingly and thus, in reality, there is no withholding against the proper amount due. So, in what are the principles which entitled the injured party to establish a defence of abatement of price to a payment claim and how is the value of abatement measured? This chapter will discuss the principles of abatement of price that have been used by the court. In doing this, relevant cases from United Kingdom has been used which are mostly found through Lexis-Nexis database and some are found in books relating to abatement and set-off. After the analyses have been done, there are several principles which have been taken into consideration by the court in accessing and granting an abatement of price. The principles in awarding and measuring the damages in abatement of price which will be discussed as follows: 49 i) Common Law right for abatement ii) Measure for cost of damages iii) The right of abatement of price due to causes other than defects iv) The rights for abatement in cross action claim 4.1 Common Law Right For Abatement An injured party can seek for abatement of defective works through the Common Law right though it is not expressly included in the construction contract. Abatement of price should not be indistinguishable from an award of damages. 4.1.1 Gilbert-Ash (Northern) Ltd v. Modern Engineering (Bristol) Ltd166 The appellants entered into a contract with Bradford Corporation to carry out building work on a market development scheme. The principal contract was in the usual R.I.B.A. Local Authorities (with Quantities) 1963 edition form, clause 27 whereof provided that where the employer's architect had certified sums as due to a nominated sub-contractor the con-JJ tractor was required to pay them over to the sub-contractor within 14 days of certification less only: (i) any retention money provided for by the sub-contract; (ii) any sum to which the contractor might be entitled in respect of delay an the completion of the sub-contract works and (iii) 166 a specified cash discount. [1974] 1 BLR 75, HL 50 The appellants adopted a special sub-contract form for nominated subcontractors which incorporated the principal contract save where its terms differed from the sub-contract form. Clause 14 of the sub-contract form, relating to the payment of sub-contractors differed from clause 27 of the principal contract in that the contractor became liable to pay only when he received the money from the employer and in that it also provided that " if the sub-contractor fails to comply with any of the conditions of this sub-contract the contractor reserves the right to suspend or withhold payment , the contractor also reserves the right to deduct from any payments certified as due .and the amount of any bona fide contra accounts and/or other claims which he, the contractor, may have against the sub-contractor in connection with this or any other contract." The appellants contracted for the steelwork to be done by the respondents as nominated sub-contractors. The work was due for completion by May 17, 1969, but it was not completed until June 12, 1969. The corporation's architect certified the sum of £14,532 as due to the subcontractors but the contractor paid over only £10,000. On the sub-contractors' claim for the balance of £4,532 the appellants relied on clause 14 of the subcontract and counter-claimed for delays and defective work. On the trial of the preliminary issue whether clause 14 effectively excluded the principle laid down in Dawnays Ltd. v. Minter167 , where it was said in the Court of Appeal, that an interim certificate is the equivalent of cash or negotiable instrument and therefore must be paid less only permitted deductions which in this case only retention, discount and previous payment. The sums certified and paid to contractors as due to sub-contractors must be paid over without deductions except as provided for under clause 27 of the principal contract, the official referee held that, albeit the clause had to be 167 [1971] 1 BLR 19 51 narrowly construed, it entitled the contractors to withhold the balance of the amount due pending the determination of their cross claims for unliquidated damages against the sub-contractors for delay and defective work. On appeal, the Court of Appeal reversed that decision. The learned judge, Lord Diplock held that a building contract is an entire contract for the sale of goods and work and labour for a lump sum price payable by installments as the goods are delivered and the work is done. Since the turn of the nineteenth century at least there has been a principle of law which is applicable to contracts of this type, but its effect is the converse of that expounded by the Court of Appeal in the instant case. That principle is stated authoritatively in the judgment of Parke B. in Mondel v. Steel168 who described it as "established" by that date. In so far as it applies to contracts for the sale of goods it has since been incorporated in section 53 of the Sale of Goods Act 1893; in so far as it applies to contracts for work and labour it still rests upon the common law. The principle is that when the buyer of the goods or the person for whom the work has been done is sued by the seller or contractor for the price, stated in the act as below: " it is competent for the defendant, . . . not to set-off, by a proceeding in the nature of a cross action, the amount of damages which he has sustained by breach of the contract, but simply to defend himself by showing how much less the subject matter of the action was worth, by reason of the breach of contract;" From the case above, the principle taken by the court in determining whether a party can take an abatement action in a building contract where there is no expressed provision for abatement stated in the contract is that a building contract is an entire contract of sale of good which permitted action abatement to be taken. 168 [1841] 1 BLR 106 52 4.2 Measure for Cost of Damages The measure of the cost which the injured party suffers is based on the difference between the value of the work and materials at the date supplied and their value if they had not been defective. The court has decided that it is not only the value of material which can be deducted, but also the value of the whole work which has been affected due to the defective work. The other important principle held by the court is that the deduction of price should not exceed the value of the work itself should it not have been defective. 4.2.1 B.R. Hodgson Ltd v. Miller Construction Ltd (1995) Unreported Hodgson was a specialist subcontractor employed by Miller under a DOM/1 subcontract to carry out floor screeding work. The measured work was valued at £81,195.60, of which Miller had paid £50,947.25. Hodgson issued proceedings for the balance due, being £27,317.85. Miller contended that the work was defective because, contrary to the requirements of the subcontract specification, Hodgson had failed to load the slurry grout on the concrete slabs. Hodgson admitted that it had breached the contract but asserted that the cost of the work omitted was £192.08. Miller contended that the cost of the work omitted was £1,358.00. However, Miller also contended that there should be deducted from the price of the works the sum of £32,407.28 by way of abatement of the price because by reason of the breach the floor was valueless. Hodgson argued that the abatement should, at most, be the sum of £1,358.00, representing the value of the materials omitted. 53 The official Referee decided that there was nothing in the subsequent authorities materially detracting from or adding to the statement of law in Mondel v. Steel169. Further, he held that the abatement was not limited to the cost of the missing grout. The contract was for the laying of a floor, and as it was contended that the absence of the grout made the floor worthless, Miller should have leave to defend. By way of example the judge observed that, in a contract for the construction of a simple reinforced concrete beam in breach of which steel reinforcement was omitted, such that the beam was incapable of being safely loaded, the beam for all practical purposes would be wholly valueless. The judge considered that it would be an odd conclusion if the innocent party, in showing how much less the beam was worth, was limited to establishing only the value of the missing steel. From the above case, the principle took by the court in determining the diminishing value of work in abatement is not only the value of the defective material itself which can be deducted, but also the diminishing value of the work itself due to the defective work. This can be seen in the example given by the judge where it not only the value of the missing materials which can be omitted, but also the diminishing value of the works itself due to the missing materials. This principle can be best applied in the current building defects scenario where most of the time, the Contractor will try to cut corners by not applying or using the specified materials or not following the specification in doing works which can affect the value and the quality of the works. 169 1 BLR 106 54 4.2.2 C.A Dunquemin Ltd v. Raymond Slater170 The arbitrator, in evaluating the cost of abatement, treat it as a form of variation and would value additional work for which no specific rates were available since it was unlikely that the Bills of Quantities would cover the costs of diminishing value involved. He acknowledge that evaluations made in this way could result in ‘excess payments’ indistinguishable from damages in the counterclaim, but wrote that if the various abatements are aggregated and applied to the contract sum that was admissible. He substituted for the £ 41,041.91 award in favour of the contractors to an award of £ 62, 497.00 in favour to the employer. C.A. Duquemin Ltd applied to the court under section 22 and 23 of the Arbitration Act 1950 for the interim award to be remitted to him on the ground that he misconduct the proceedings which resulted in award. The learned Judge Newey held that although the abatement price could result in a ‘Nil’ award or judgment, it could not possibly result the seller being ordered to make a payment to the buyer, since the abatement consists of the difference between the goods as warranted and the value of the goods delivered. The right of abatement is recognized in respect of goods in the Sale Of Good Act 1863, which codified existing common law rules. The provisions of the the 1863 Act have been re-enacted with amendments by the Sale of Goods 1979, which reads: “Where there is a breach of warranty by the seller… the buyer is not by reason only of such breach of warranty entitled to reject the goods, but he may : 170 [1993] BLR 124 55 a) set up against the seller the breach of warranty in diminution or extinction of the price, or b) maintain an action against the seller for damages for breach of warranty.” Section 53(2) states the measure of the damages which the buyer may claim against “the estimated loss directly and naturally resulting in the ordinary course of events from the breach of warranty”. The loss may obviously include the cost of carrying out the remedial works. Section 53(3) deals with the measure of “abatement”; it is “prima facie” the difference between the value of the goods at the time of delivery to the buyer and the value they would have had if they had fulfilled the warranty”. If the value of the goods delivered was “nil” the seller cannot obtain any payment for them from the buyer, but there is no possibility of his being ordered to make a payment to the buyer. Cost of repair cannot be taken into account. Judge Newey held further that the common law applicable to the abatement of claims for damages in respect of supply of goods and the supply of work and materials must originally have been the same and he think that, notwithstanding statutory codification of those applicable goods, they remain the same. He further held the arbitrator should deduct the difference between the value of the work and materials supplied at the date when they were supplied and their value if they had not been defective, but had been in accordance to the contract. the result could have been to reduce the contractors’ claim to nil, but could not have produced what might be described as “negative value”. From the above case, the principle taken by the court in determining the cost diminution value of work in abatement is that it should not exceed the value of the work itself should it not have been defective and in accordance to contract. 56 This is explained under Section 53(3) Sale Of Good Act 1979 where “abatement”; is the difference between the value of the goods at the time of delivery to the buyer and the value they would have had if they had fulfilled the warranty”. If the value of the goods delivered was “nil” the seller cannot obtain any payment for them from the buyer, but there is no possibility of the seller being ordered to make a payment to the buyer due to the diminishing value of the goods. 4.2.3 Mondel v Steel171 The action in this case was based on a special assumpsit on a contract to build a ship for the plaintiff, at a certain rate per ton, and according to a certain specification (setting it out) and the breach assigned was for not building the ship with scantling, fastening and planking which is specified in the specification by reason whereof the ship, in a certain voyage, was so much strained that it became necessary to re-fasten and repaired. The plaintiff lost the use of the ship during the time she was undergoing such repairs. The defendant pleaded that the plaintiff ought not further to maintain his action in respect of the alleged breach of contract, because he the defendant, heretofore, before the Court of Exchequer at Westminster, in an action sought to recover from the plaintiff the sum of 86 pounds 6s 4d, being the balance of the price of the said ship calculated according to the said agreement and which remained unpaid to him. The present defendant also try to recover from the present plaintiff the further sum of 134 pounds 3s 2d, being the value of certain work, labour and materials done and provided for the present plaintiff by the present defendant in and about the said ship, for the extra additional to the work, labour and materials mentioned and included in the said agreement. The whole of 171 [1841]1 BLR 106 57 the pleadings in that action were then set out. The defendant further says that all the said issues were duly joined between him and the present plaintiff and afterwards, at the General Sessions of Assize at Liverpool, before justices of the Court of Common Pleas of the said county palatine of Lancaster, the said issues were then tried by a jury. The jury, in the first trial found that the defendant in this action had committed a breach of the said contract and that the plaintiff was entitled for compensation and damages in respect thereof. Their verdict for the present defendant, for the difference only between the said compensation and damages which they so found the plaintiff in this action was entitled to by reason of the said breach of contract, the amount of the said balance, the value of the said extra and additional work and labour and materials as aforesaid for the sum of 120 pounds only. This was considerably less than the amount of the said balance and the value of the extra and additional work, labour and materials. The defendant further says that the said jury then found all the said issues as aforesaid joined for him, assessed his damages on occasion of the premises in the said action, besides his costs and charges by him in his said suit, to the said sum of 120 pounds. Proceedings were afterwards had in the Court of Exchequer at Westminster and it was considered by the said court that the present defendant should recover against the present plaintiff his said damages of 120 pounds and also 264 pounds for his costs and charges which said judgment still remained in full force and effect, not in the least reversed or made void. However, Judge Park B, in his judgment held that this plea states in substance that the defendant had sued the plaintiff for the balance of the agreed price of the vessel after payment of 3,500 pounds and also for a sum of 134 pounds odd for extra work for work, labour and for goods sold and delivered has been made. This issue was joined and on the trial of the cause, the plaintiff gave evidence in his defence of the same breach of contract alleged in the declaration and insisted that if the amount of compensation to which he was entitled, exceeded or equalled the balance of the price and the value of the extra work, the 58 present plaintiff was entitled to a verdict. If it was less, that he was entitled to a deduction from the amount of both, which is an amount of compensation. The plea proceeds to state (which the Judge assume correctly for the purposes argument though the statement has arisen from mistake) that the learned judge before whom the cause was tried, directed the jury and they found that the present defendant had committed a breach of contract, and was entitled to some compensation. They deducted from the price of the vessel and value of the extra work and the present defendant had judgment for the amount, after such deduction had been made, since the commencement of this suit. The plaintiff demurred to this plea, assigning several causes of special demurrer, which it is not necessary to notice, which in Judge Park B’s opinion that it is bad in substance. He then held that that in all these cases of goods sold and delivered with a warranty, work and labour, as well as the case of goods agreed to be supplied according to a contract, the rule which has been found so convenient is established. It is competent for the defendant, in all of those, not to set-off, by a proceeding in the nature of a cross-action, the amount of damages which he has sustained by breach of the contract, but simply to defend himself by showing how much less the subject-matter of the action was worth, by reason of the breach of contract. For defendant to obtain or is capable of obtaining, an abatement of price on that account, he must be considered as having received satisfaction for the breach of contract, and is precluded from recovering in another action to that extent; but no more. The opinion, therefore, attributed on this record to the learned judge is incorrect and his decision was not warranted by law. All the plaintiff could by law be allowed in diminution of damages, on the former trial, was a deduction from the agreed price, according to the difference, at the time of the delivery, between the ship as she was and what she ought to have been according to the contract. All claim for damages beyond that, on account of the subsequent necessity for more 59 extensive repairs which could not have been allowed in the former action can now be recovered. From the case above, in abatement, the injured party not only can claim for the diminuishing value of the works, but also the cost of repairing the works. This can be seen in the judgment by Judge Park B where he has allowed the plaintiff to recover the cost of repairing the defective ship. In accessing the amount where the injured party can recover in an abatement calim, the court will not only access the diminuishing value of the works, but also the amount of repairing works which have been done to the work. 4.3. The Rights for Abatement of Price Due To Causes Other Than Defects Claim for delay, disruption or damaged caused by anything other than which the contractor has constructed, could not be feature in a defence of abatement. 4.3.1 Mellows Archital Limited v. Bell Projects Limited172 Mellows were subcontractors to Bell under a DOM/1 form of sub-contract. Bell withheld £10,165.49 from the value of the work done because of losses incurred as a result of delay by Mellows. At first instance Judge Wilcox, sitting as an Official Referee, held that Bell’s losses could not be asserted by way of set-off owing to the failure to comply with clause 23.2 of DOM/1. Nonetheless the judge held that the claim for delay was an arguable defence to the interim payment 172 [19917] 87 BLR 26 60 claim, if the delay claim could be characterized not as a matter of set-off but as a matter of abatement. Mellows appealed. The Court of Appeal held that the defence of abatement does not include claims that assert losses attributable solely to delay. In particular, as Lord Justice Hobhouse put it: “It is therefore clear that, for a party to be able to rely upon the common law right to abate the price which he pays for goods supplied or work done, he must be able to assert that the breach of contract has directly affected and reduced the actual value of the goods or work – “the thing itself”. In his judgement, he held that for a party to be able to rely upon the common law right to abate the price which he pays for goods supplied or work done, he must be able to assert that the breach of contract has directly affected and reduced the actual value of the goods or work - the thing itself. In other words any other loss or damage, if it is to be relied upon by way of answer to a claim for the price, has to arise from the principle of equitable set-off. In most contractual relationships there would be no need to draw a distinction between the two types of defence. But under DOM/1 it is necessary to do so. Whilst it may be possible to conceive of a case in which delay has affected the value of the thing itself, the normal effect of breaches of the obligation of timeous performance will be to cause losses to the other contracting party which are consequential upon that breach and therefore can only be relied upon, if at all, under the principle of equitable set-off. In the present case the factual situation is clear. The plaintiff sub-contractor’s claim to be paid the price is based upon the valuation of the goods supplied and work done. Indeed the valuation was the defendant main contractor’s own valuation, and is undisputed. The case of the defendants is that the plaintiffs’ delays caused them serious losses through the prolongation of the head contract, the disruption of their own contractual works and those of other sub-contractors, the need to accelerate other work, and the 61 reduced contribution to their own overhead expenses. Thus, the defendants’ case is based upon financial losses which they say they have suffered as a consequence of the plaintiffs, breaches of their obligations of timeous performance. Subject to the terms of Clause 23, those losses can be relied upon to support an equitable setoff but they cannot justify the legal defence of abatement of the price. In this case, Lord Justice Hobhouse held that the common law right of abatement can only be use where the injured party is able to assert that the breach of contract has directly affected and reduced the actual value of the goods or the work – the thing itself. For breaches of the obligation of timeous performance, the loses to the other contracting can only be recovered by way of equitable sett-off, but not by way of abate the price of the goods and the works. 4.4 The Rights For Abatement In Cross Action Claim The injured party has the rights to claim for abatement of price although all the payment due to the other party has been paid by him. This principle will not apply if he had set the cause of action is the breach of contract that cause of action existed before and was independent of the payment and the only question is, whether the plaintiff is precluded from recovering by reason of his not having set up that breach of contract in defence to the former action it up, and either failed to substantiate it, or obtained an inadequate reduction where his right of action would have been extinguished. But not having done so, his right of action remains. 62 4.4.1 Davis v Hedges173 CASE stated on appeal from the County Court of Oxfordshire, holden at Oxford. The action was brought to recover the sum of 42l. 19s. 6d., being damages sustained by the plaintiff for the improper performance of certain work agreed to be done by the defendant for the plaintiff at his house, Burford, Oxon, under a building contract, and for not performing the work according to certain specifications and also for removing certain partitions and appropriating certain materials. After the opening of the plaintiff's case, it was stated to the judge that the defendant had brought an action in the Court of Common Pleas against the plaintiff for the recovery of the price of the work under the contract, and had recovered the whole amount. It was, however, contended on behalf of the plaintiff that he was not in any way prejudiced in the present action, which was one for damage for the nonfulfillment of a contract, by the fact that the defendant had brought a previous action against him in a superior court, to recover the price of the work done, the improper performance of which was the subject-matter of the present case: in other words, that the plaintiff either could not, or in the alternative was not bound to set off the subject-matter of the present action in and to the previous action of the defendant, but could now bring his cross action. The judge decided the contrary, and no suited the plaintiff. Judge Hannen in his judgement said that the plaint was for damages for the non-performance and improper performance of certain works which the plaintiff 173 [1871] 6 QB 687 63 had employed the defendant to execute. The defence set up was, that the defendant had sued the plaintiff for the price of the work now alleged to have been improperly done, and that the plaintiff had settled by paying the whole amount then sued for; and as the plaintiff might have given the non-performance and defective performance now complained of in evidence, in reduction of damages, the plaintiff was precluded from bringing a cross action for that which he might have availed himself of as a defence to the former suit. The county court judge decided in favour of the defendant, holding that all the damages now sued for might have been used in reduction of damages in the former action, and that for anything which might have been so used no cross action could be maintained. Judge Hannen’s opinion that the decision by the country judge was erroneous. His judgement was held by referring to the particular point decided in Mondel v. Steel 174was, that a person who has in fact obtained, in an action brought against him, an abatement of the price of work done, by reason of a breach of contract in its execution, is not precluded from suing for special damage resulting from the breach of contract; but it leaves undecided the question whether he was bound to obtain the abatement in the action in which he was a defendant, or might recover it as damages in a cross action. The expression of Parke, B., which was a good deal relied on in the argument, that "to the extent that he obtains, or is capable of obtaining, an abatement of price, he must be considered as having received satisfaction for the breach of contract," has reference to the facts of the case in which the plaintiff did claim and did obtain an abatement. It is clear that before any action is brought for the price of an article sold with a warranty, or of work to be performed according to contract, the person to whom 174 [1841]1 BLR 106 64 the article is sold, or for whom the work is done, may pay the full price without prejudice to his right to sue for the breach of warranty or contract, and to recover as damages the difference between the real value of the chattels or work, and what it would have been if the warranty or contract had not been broken. He held that there must be a new trial. Judge Lush, in the second judgement by referring to Hamlet v. Richardson175 and Brown v. M'Kinally176 held that in the present case, the cause of action is the breach of contract; that cause of action existed before and was independent of the payment; and the only question is, whether the plaintiff is precluded from recovering by reason of his not having set up that breach of contract in defence to the former action. If he had set it up, and either failed to substantiate it, or obtained an inadequate reduction, his right of action would have been extinguished. But not having done so, his right of action remains. 4.5 Conclusion Having analyzed and reviewed all the cases above, it has been noticed that the judge will evaluate the diminishing value of works based on the principle sets in the Sale of Good Act in which it is just not the value of defective material will be taken consideration, but also the diminishing overall value of the work itself caused by the defective works. 175 176 9 Bing. 644 2 Esp. 278 65 Abatement, although was not specifically expressed in the conditions of construction contract, is still a valid defence for a claim since it is acknowledged in the common law under the Sale of Good Act. This right cannot be denied and the injured party in the construction contract can use their rights to claim for abatement in works if there are defects or works which are not in accordance to the specification and contract. However, claim for damages due to delay, disruption or damaged caused anything other than which the contractor has constructed cannot be raised as a defence of abatement. From the principle of abatement in the UK above, the Malaysian construction industry may also adopt the principle of abatement as a defence for defective works. This is due to the concept where a construction contract is also governed by the common law under the Sale of Goods Act. There is also provision under clause 59 in Malaysian Sale of Goods Act 1957 to give the right for the injured party to abate the price, which reads: “ Where there is a breach of warranty by the seller, or where the buyer elects or is compelled to treat any breach of condition on the part of the seller as a breach of warranty, the buyer is not by reason only of such breach of warranty entitled to reject the goods; but he may- (a) set up against the seller the breach of warranty in diminution or extinction of the price; or (b) sue the seller for damages for breach of warranty 66 CHAPTER V CONCLUSIONS AND RECOMMENDATION 5.1 Introduction The title of this study is defence of abatement in defective works. As mentioned in introduction, the objective of this study is to find the principles of abatement claim and what are the criteria on the measure of damages which abatement claim can be made due to defective works. This chapter would also discuss the problems encountered during the preparation of this study and the recommendation for further study. 5.2 Summary of Study Findings Overall, the objective of this study has been achieved through the literature review and the documentary analysis of law cases. The principles of abatement claim and what are the criteria on the measure of damages which abatement claim can be made due to defective works have been identified and is summarized in Table 5.1 67 Table 5.1: Summary of study findings Item Description Findings 1 Principles of Abatement Findings a. Rights of abatement under Common Law • Gilbert-Ash (Northern)Ltd v Modern Engineering Ltd • The injured party have the right of abatement under the Sale Of Good Act although the rights was not expressed in the condition of contract b. Rights for abatement for damages other than defective works • Mellows Archital Ltd v Bell Projects Ltd • Claim for delay, disruption or damaged caused by anything other than which the contractor has constructed, could not be feature in a defence of abatement. c. Rights for abatement in cross action claim • Davis v Hedges • The injured party have the rights to claim for abatement of price although all the payment due to the other party have been paid by him This principle will not apply if he had set the cause of action in the breach of contract that cause of action existed before and failed • 2 Measure of Damages a Measure of diminution value in defective works • B.R. Hodgson Ltd v. Miller Construction Ltd (1995) Unreported • C.A Dunquemin Ltd v. Raymond Slater • Mondel v Steel Findings • • The measure of the cost which the injured party suffers is based on the difference between the value of the work and materials at the date supplied and their value if they had not been defective. It is not only the value of material which can be deducted, but also the value of the whole work which has been affected due to the defective work. 68 5.3 Problems Encountered During Study The main problem encountered during preparing this study is the lack of reference source due to the geographical location. As a part time student located in Sarawak, it is difficult for us to source for books and journal for reference due to lacks of books in our State library. The other problem encountered is the time constraint. In the two month period given, writing has been executed in a very quick manner, particularly during data collection process. If there is more time and source available, this study can be done in a more comprehensive way. 5.4 Further Studies For further research on abatement, it is suggested that a study on whether the application of abatement of price based can be taken as an action based on our local common law and construction law. 5.5 Conclusion Abatement is the common law right in which a party can institute to assert his or her rights. Although this right is not expressly stated in most of the standard forms of contract, however due to the nature of construction which also governed by the Sale of Goods Act, this right has become available to be use and utilized. In set-off, notice have to be served earlier before action of set-off can be took. This is expressly stated in the conditions of contract whether used in the UK’s construction industry of our Malaysian construction industry. The 69 uniqueness of abatement is that the injured party would not have to serve any notice for them to take the defence of abatement for a claim. Abatement have to be distinguish from set-off. The value of works which will be diminish should not exceed the amount of the work itself should the work is not defective. This principle is different with set-off where the value which is going to be set-off can be more than the value of the work itself. In assessing an abatement claim, judges will took into consideration only to the value of defective material and value of the work due to the defective material as an amount to be deducted from a claim. There is a wide potential in abatement which may be utilized by the construction industry in protecting their rights in contract. Damages due to defective works are the common problems faced by our construction industry today and abatement may become one of the effective defence in claim for the damages due to defective works. 69 REFERENCES Brewer, G. (2006). “Legal Case Study: The defence of abatement”. Contract Journal, Retreive 15 July 2009, from http://www.contractjournal.com/Articles/2006/11/01/52679/legal-case-studythe-defence-of-abatement.html. Daniel Atkinson (1999). “Defects”Retreive 15 July 2007, from http://www.atkinsonlaww.com/ cases/CasesArticles /Articles/Defects.htm Dolan, S. (2007). “The Common Law Defence of Abatement : A Change of Direction” . Retrieve 18 July 2009 from http://www.mhc.ie/news-events/legal-articles/220/. Greg Brownlee (2009), “ Understanding The Rule Of Abatement.” Retrieve 18 July 2009 from http://www.cnplus.co.uk/hot-topics/legal/understanding-the-ruleof-abatement/5204633.article Herber Smith (2009). “Set-Off and Abatement Under International Construction Contract” Retrieve 18 July 2009 from http://www.herbertsmith.com/NR/rdonlyres/2FE9904E-2AE1-4FE5-A6154777F206A298/11396 /Newsletter4EJune2009.pdf John Parris (1993). ”Construction Law Digest”. BSP Professional Books. Oxford. Kevin Barrett (2008). “Defective Construction Work and The Project Team.” WileyBlackwell. United Kingdom 70 Lim Chong Fong, (2004). “The Malaysian PWD Form of Construction Contract.” Sweet & Maxwell Asia, Selangor. Murdoch, J. and Hughes, W. (1992). “Construction Contracts Law and Management.” E & FN Spon, Great Britian. Neil F. Jones (1991). “Set-off In The Construction Industry.” Blackwell Science, United Kingdom Silver, R. (2008). “Abatement, Set-Off and Counterclaim – What’s the Difference? ” Retrieve 2 August 2009 from http://www.silver-shemmings.co.uk/ construction-law/abatement-set-off-counterclaim.asp. Simon JA Tolson (2004). “ Payment, Abatement and Set-Off” Retrieve 2 August 2009 from http://www.fenwickelliott.co.uk/files/docs /articles/html/ payment_abatement_setoff.htm Sundra Rajoo, “The Malaysian Standard Form Of Building Contract (The PAM 1998 Form).” Malayan Law Journal Sdn. Bhd, Kuala Lumpur. Wong Bi Xia (2009).”Measure Of Damages For Defective Building Works.” Universiti Teknologi Malaysia. Tesis Msc. 71 BIBLIOGRAPHY Legal Research Board (2004). “Contracts Act 1950 (Act 136), Contracts (Amendment) Act 1976 (A 329) & Government Contracts Act 1949 (Act 120)”. International Law Book Services, Selnagor. Legal Research Board (2003). “Sale Of Goods Act 1957 (Act 382)”. International Law Book Services, Selnagor. R Pettigrew (2005). “Payment Under Construction Contracts Legislation”. Thomas Telford, Great Britian.