MINIMISING CONSTRUCTION DISPUTES NORAZIAH BINTI WAHI A project report submitted in partial fulfilment of the requirements for the award of the degree of Master of Sciences (Construction Management) Faculty of Civil Engineering Universiti Teknologi Malaysia NOVEMBER 2008 iii To my beloved family and friends, Thank you for all your support and guidance iv ACKNOWLEDGEMENTS I am grateful to Allah, the Almighty for making all good things possible. First of all, I would like to express my gratitude to my Supervisor, Associate Prof. Aziruddin Ressang who had patiently read through my drafts, his unfailing supports and contribution of ideas in preparing this dissertation. I also appreciate and deep acknowledge his willingness to motivate, insightful supervision as well as his creative suggestions throughout the course of this research. My appreciation also goes to Tuan Haji Mohd Nazir bin Ismail and all lecturers from the Department of Quantity Surveying, Faculty of Architecture, Planning and Surveying, Universiti Teknologi Mara and Faculty of Civil Engineering, Universiti Teknologi Malaysia, who had given me the benefits of their knowledge and guidance in making constructive suggestions for this research. A grateful acknowledgement is also addressed to Tuan Haji Mohammad Noor Abu Hassan, the senior engineer in Perunding Zar, for his approachable and generous counsel in dispensing the useful sources for this research. My special thanks also go to all those who had agreed to be interviewed, formally or informally and gave me the advantage of their knowledge, views and experience. I am also thankful to my friends for their moral support and encouragement during the preparation of this dissertation. Last but not least, I would also like to extend my sincere and heartiest thanks to my beloved parents and family, who had never failed to give me their encouragement and moral support, thus enabling me to complete this dissertation with pride and satisfaction. v ABSTRACT Construction industry plays an important role in developing Malaysia and it is a major contributor towards realizing Vision 2020. It is totally different from manufacturing industry whereby the same construction team will not be able to produce the same products even though the projects have similar nature of construction. Owing to the complex, disputes between different parts within these interacting fragments is highly foreseeable. This study was conducted to identify the causes and effects of disputes in construction industry, as well as ways to mitigate disputes. Results from the survey conducted indicated that the causes of disputes in general between major parties involved in construction projects are various, with certain considered as major, others considered as quite significant and up to certain extent, some are considered of less significant but nonetheless could still give birth to disputes. Categorically the major effects of disputes are those that concerns time as well as money, while those consequences from the legal terms was also considered significant as the other potential effects of disputes. However, all parties involved do not seem to care much of the potential effects of disputes on their reputation as well on third parties. Dispute can effectively be avoided or mitigated by adopting certain or series of dispute avoidance activities. Although effective, these dispute avoidance approaches does not guarantee anybody full exclusion from experiencing disputes. Of all the dispute avoidance approach suggested the partnering approach was seen as the most effective but probably the hardest to be adopted. The content as well as the outcome of this study was hoped to be able to serve as a source of reference for various participants of construction industry with regards to the matters of disputes in construction industry. vi ABSTRAK Industri pembinaan penting dalam pembangunan Malaysia dan turut menyumbang ke arah pencapaian Wawasan 2020. Sektor pembinaan adalah berlainan dibandingkan dengan sektor pembuatan, dimana produk yang sama tidak dapat dihasilkan meskipun melalui proses pembinaan yang sama. Disebabkan sifat industri itu sendiri yang agak kompleks, pertelingkahan antara pihak ataupun pecahan yang pelbagai serta berinteraksi ini sering terjadi. Kajian dijalankan bagi mengenalpasti punca-punca serta kesan-kesan pertelingkahan yang wujud dalam industri pembinaan, selain daripada mengetengahkan kaedah-kaedah bagi mengelak berlakunya pertelingkahan. Hasil kaji selidik yang dijalankan menunjukkan secara amnya, puncapunca pertelingkahan antara pelbagai pihak dalam industri tersebut adalah pelbagai, yang mana ada antaranya dianggap sebagai punca utama, ada pula dianggap agak penting dan sebahagian pula dirasakan tidak begitu penting sebagai punca pertelingkahan. Dari segi kesannya pula, ianya boleh dikategorikan ke dalam kesankesan yang berkaitan dengan masa dan wang, disamping kesan-kesan yang berkaitan dengan aspek perundangan. Walaubagaimanapun, kebanyakan pihak yang terlibat tidak begitu mengambil berat berkenaan kesan pertelingkahan terhadap reputasi mereka. Pertelingkahan mampu dielakkan dengan mengguna pakai kaedah ataupun kombinasi kaedah-kaedah yang pelbagai. Meskipun berkesan, kaedah-kaedah ini bukanlah jaminan pengecualian sepenuhnya terhadap berlakunya pertelingkahan. Kaedah kerjasama antara dua ataupun pelbagai pihak dilihat sebagai kaedah terbaik namun mungkin yang paling sukar untuk dilaksanakan. Adalah diharapkan, kandungan serta hasil daripada kajian ini dapat digunakan sebagai rujukan bagi pihak-pihak yang terbabit dalam industri pembinaan dari segi perkara yang berkaitan dengan pertelingkahan. vii TABLE OF CONTENTS Chapter I II Contents Page Declaration ii Dedication iii Acknowledgements iv Abstract v Contents vii List of Figure xi List of Tables xii INTRODUCTION 1 1.1 Introduction 1 1.2 Problem Statement 2 1.3 Aim of Study 3 1.4 Objectives of Study 4 1.5 Scope of Research 4 1.6 Significance of Research 5 1.7 Research Methodology 5 MINIMISING CONSTRUCTION DISPUTES 7 2.1 Introduction 7 2.2 Definition of Disputes 8 2.3 Nature of Construction Dispute 9 2.4 2.3.1 Enforceable Promises 9 2.3.2 Technical Matters 10 2.3.3 Legal Matters 10 2.3.4 Entitlement and Magnitude 11 Sources of Disputes 12 viii Chapter Contents 2.5 Page 2.4.1 Inconsistencies of Contract 14 2.4.2 Payment 15 2.4.3 Determination of Contract 16 2.4.4 Variation 17 2.4.5 Lack of Communication 17 Causes of Disputes In General 2.5.1 Causes of Disputes by Stakeholders 2.6 21 2.5.1.1 Clients 22 2.5.1.2 Consultants 24 2.5.1.3 Contractors 26 Effect of Disputes 2.6.1 Effect on Cost and Profitability 2.7 18 28 28 2.6.1.1 Financial Costs 29 2.6.1.2 Hidden Costs 29 2.6.1.3 Reducing Profit Margin 30 2.6.2 Effect on Time 30 2.6.3Effect on Quality 31 2.6.4 Effect on Business and Working Relationship 31 2.6.5 Dispute Escalation (Chain Reaction) 32 2.6.6 Emotional Costs 33 Avoiding Disputes 35 2.7.1 Partnering Approach 35 2.7.2 Clarification of Responsibilities 36 2.7.2.1 Client 36 2.7.2.2Contractor 37 2.7.2.3 Consultant 37 2.7.3 Risk Allocation 38 2.7.4 Increase Ability to Resolve Problems 39 ix Chapter III Contents Page RESEARCH METHODOLOGY 41 3.1. Introduction 41 3.2. Literature Review 41 3.3. Data & Information Gathering 42 3.3.1 Primary Data and Information 3.3.1.1 Questionnaires 42 3.3.1.1.1 Method of Questionnaire Collection 43 3.3.2 Secondary Data and Information 3.4. Data Analysis and Interpretation IV 42 44 44 3.4.1 Frequency Analysis 44 3.4.2 Average Index Analysis 45 3.5. Conclusions and Recommendations 45 DATA COLLECTION AND ANALYSIS 47 4.1. Introduction 47 4.2. Questionnaire Feedback 48 4.3. Analysis and Results 51 4.3.1 Causes of Construction Disputes in General 51 4.3.2 Causes of Construction Disputes by Client 58 4.3.3 Causes of Construction Disputes by Consultant 66 4.3.4 Causes of Disputes by Contractor 73 4.3.5 The Effect of Disputes to Stakeholders in the Construction Industry 4.3.6 Disputes Avoidance in Construction Industry 4.3.6.1 Management Role in Avoiding Disputes 80 89 96 x Chapter V Contents Page CONCLUSION AND RECOMMENDATION 101 5.1 Introduction 101 5.2 Conclusion 102 5.3 Recommendation 104 BIBLIOGRAPHY 106 APPENDIX A 110 xi List of Figure Page Figure 1.1 : Methodology Flowchart 6 Figure 2.1 : Causes of Disputes in General 20 Figure 2.2 : Causes of Disputes Caused by Client 23 Figure 2.3 : Causes of Disputes Caused by Consultant 25 Figure 2.4 : Causes of Disputes Caused by Contractor 27 Figure 2.5 : Effects of Construction Disputes 34 Figure 2.6 : Disputes Minimisation 40 Figure 4.1 : Distribution Percentage of Questionnaire Sampling 48 Figure 4.2 : Distribution of Stakeholders Percentage 49 Figure 4.3 : Respondents’ Years of Working Experience 50 Figure 4.4 : Respondents Awareness on Several Disputes Approach 92 Figure 4.5 : Respondents Practise of Several Disputes Avoidance Approach : Respondents Success in Avoiding Disputes by Practising Several Disputes Avoidance Approach : Management Practise on Several Disputes Avoidance Approach : Management Success in Avoiding Disputes by Practising Several Disputes Avoidance Approach 92 Figure 4.6 Figure 4.7 Figure 4.8 93 97 97 xii List of Table Table 2.1 Table 4.1 Table 4.2 Table 4.3 Table 4.4 Table 4.5 Table 4.6 Table 4.7 Table 4.8 Table 4.9 Table 4.10 Table 4.11 Table 4.12 Table 4.13 Table 4.14 Table 4.15 Table 4.16 Table 4.17 Table 4.18 Table 4.19 Table 4.20 : Research on the Sources of Conflicts and Disputes In Construction Industry : Response Percentage : The Percentage of Respondent Based on Organisation : Tabulation of Respondents’ Years of Working Experience : Client’s point of view (Causes of Construction Disputes in General) : Consultant’s point of view (Causes of Construction Disputes in General) : Contractor’s point of view (Causes of Construction Disputes in General) : Overall Respondents (Causes of Construction Disputes in General) : Client’s point of view (Causes of Construction Disputes by Clients) : Consultant’s point of view (Causes of Construction Disputes by Clients) : Contractor’s point of view (Causes of Construction Disputes by Clients) : Overall Respondents (Causes of Construction Disputes by Clients) : Client’s point of view (Causes of Construction Disputes by Consultants) : Consultant’s point of view (Causes of Construction Disputes by Consultants) : Contractor’s point of view (Causes of Construction Disputes by Consultants) : Overall Respondents (Causes of Construction Disputes by Consultants) : Client’s point of view (Causes of Construction Disputes by Contractors) : Consultant’s point of view (Causes of Construction Disputes by Contractors) : Contractor’s point of view (Causes of Construction Disputes by Contractors) : Overall Respondents (Causes of Construction Disputes by Contractors) : Client’s point of view (The Effect of Disputes to Stakeholders in the Construction Industry) Page 13 48 49 50 51 53 55 56 59 61 62 64 67 68 70 71 74 75 77 79 81 xiii Table 4.21 Table 4.22 Table 4.23 : Consultant’s point of view (The Effect of Disputes to Stakeholders in the Construction Industry) : Contractor’s point of view (The Effect of Disputes to Stakeholders in the Construction Industry) : Overall Respondents (The Effect of Disputes to Stakeholders in the Construction Industry) 83 85 87 1 CHAPTER I INTRODUCTION 1.1 Introduction Construction industry plays an important role in developing Malaysia and it is a major contributor towards realising Vision 2020. The industry contribute 3.3 percent of the countries gross domestic product (GDP) in year 2003 and employs more than 500,000 workers in some 54,500 local companies. In year 2003 more than 3000 local contracts have been awarded to contractor with the total value of RM4.8 billion. The housing and infrastructure project has been the biggest contributor to the construction industry which contributes more than 70% of the total value, Yusof; M.A et al. (2007). Construction is totally different from manufacturing industry where the same products with the same quality are possible to be produced even at a thousand times of its production. In construction, the same construction team will not be able to produce the same products even though the projects have similar nature of construction because there would be differences in regulation, site conditions and market conditions for each project. Global-wise, the construction industry has been identified as a ‘… loosely coupled system … characterized by … particular complexity factors owing to industry specific uncertainties and interdependencies, and inefficiency of operations’ stated by Dubois & 2 Gadde (2002). The separation between the design and construction processes, the fragmentation evident in the management of the construction process by subcontract, and the short term project focus of the contractual relationships between participants results in little incentive or opportunity to improve inter-organizational practices. With respect to this, there are various participants in this industry. These included; clients, regulatory agencies, engineers, quantity surveyors, developers, lawyers, suppliers, contractors, architect and the list goes on. Their obligations and objectives varied, based on their contractual relationship for each projects. Owing to this complex, fragmented nature of this industry, disputes between different parts within these interacting fragments is highly foreseeable. 1.2 Problem Statement Dispute in construction industry may it be in the form of financial , legal or any other form is an important subject that requires attention of the industry ‘players’. Within the scope of the industry itself, disputes most often than not leads to losses may it be in terms of economic, time, market share as well as reputation, and in certain extreme cases may even lead to the downfall of a construction entity. According to Groton (1997); Mitropoulos and Howell (2001), J.G Richard (2006), evidence showed that the amount of disputes on construction projects can be reduced through dispute identification. There are many who believe that conflicts, and therefore disputes, injured business relationships. Many considered that disputes in the construction industry are inevitable stated by Cheung and Suen (2002); Stipanowich (1996), J.G Richard (2006). Thus, it essential that all participants within this very fragmented industry must consider and establish a proper and effective mechanism to minimise disputes, to ensure products of total quality and value can be achieved and delivered. The topic on minimisation construction disputes also dawned from newspaper articles entitled ‘Precinct 11 Housing Project at a Standstill’,published in The STAR 3 Newspaper dated May 8, 2008. It was about the disputes between the Client, Putrajaya Holdings Sdn Bhd (PJH) and the Contractor, Peremba Jaya Sdn Bhd. The disputes has been kept in silence for the last two years. Out of the total of 259 units offered, 211 units or equivalent to 81.5% has been sold. The project was promised to be delivered to the buyers in 2005. The bulk of the project was originally given by Peremba Jaya Sdn Bhd to its subsidiary, Arif Cerah Sdn Bhd who eventually got into financial difficulties in 2005 which causes the project to be stalled. To date Arif Cerah Sdn Bhd has surrendered the land title back to Putrajaya Holdings to resume the work. As a result, customers who have purchased the house by signing the sales and purchase agreement as early as 2003 has been servicing their housing loan repayment to the bank are the victims of the disputes. Furthermore, in relation to these negative impacts or consequences that disputes can bear towards the industry, therefore it is vital that participants or ‘the players’ within this industry adopt a serious attitude towards mastering this subject matter, which in turn would assists them in planning, decision-making and implementation of construction projects. This research, will address as much as possible the issues, facts and ideas regarding the matter of disputes in construction industry and its minimization strategies. 1.3 Aim of Study The aim of this study is to determine the causes of dispute in the local construction industry and to identify strategies to mitigate the disputes. To achieve the above aim, the following objectives have been identified. 4 1.4 Objective of Study In order to achieve the above aims, following objectives have been laid out: 1) To identify the causes for dispute in the construction industry. 2) To study the effect of disputes in the construction industry 3) To identify ways to mitigate disputes in construction. 1.5 Scope of Research With respect to the very vast subject regarding disputes in industry, therefore, this particular work will focus on several types of disputes that are commonly experienced within the industry. Subsequently, the consequences arising from these disputes will also be addressed, and where possible supported with actual case examples. Next, the study will also put forward the strategies to minimize these disputes, based on established ideas from various references, journal, articles, working papers and newspapers. Finally it should also be noted that all the issues, facts, ideas as well as proposal that will be presented in this study will only focused on those related to the scenario of construction industry. 5 1.6 Significance of Research The subject matter of disputes is an important subject that participants within construction industry needs to be aware of, and understands as clear as possible, Thus, this study is presumed to bear the significance of compiling the relevant knowledge regarding the minimizations of disputes whereas the final product (the completed work as a literature) may be used as a source of reference for all who are involved in construction industry or the construction processes to enhance their knowledge on the matter of disputes together with strategies to minimize it. This would subsequently assists everyone involved towards a more calculated planning, implementation and decision-making, by taking into account the potential risks of disputes and ways to resolve it if encountered – in short; of how to adopt a proper and effective strategies to minimize and resolve disputes. 1.7 Research Methodology In order to complete this dissertation, the first and foremost step of the study was identifying research problem which covered the significance, objective and scope of study. Second step is then followed by exploratory research of the literature. Secondary data sources for literature review are gathered from references books, journals, newspaper articles and relevant magazines. These sources provide lots of data that can help to determine the background of the research. Primary data gathered for this study are taken from interviews conducted with the expert in this industry. Questionnaires are also distributed among the participants in construction industry. All the data will analysed using statistical method. Figure 1.1 shows methodology flowchart for this research. 6 Figure 1.1 Methodology Flowchart 7 CHAPTER II MINIMISING CONSTRUCTION DISPUTES 2.1 Introduction H.S Richard (2002) stated that the construction industry has become known as one of the most adversarial and problem-prone, with claims and disputes on construction projects frequently the rule rather than the exception. Cost overruns and schedule delays can be the subject of expensive and protracted claims and litigation, and pose serious risks for all parties to a construction project. Meanwhile according to J.G Richard et al (2006), for decades, the construction industry has been mired in adversarial relationships between owners and contractors Each party’s priorities are unsurprisingly at conflict with the others, establishing a repetitive cycle of hostilities. Construction disputes can begin at any phase of the project from program, design, procurement, during the project, or project close out. The impacts can often have diverse effects on project financing, budget, schedule, quality, maintenance, safety, and client satisfaction stated by F.B Osmond (2003). 8 2.2 Definition of Disputes The oxford dictionary defines dispute as a misunderstanding between two parties, either contractual or non contractual but the fact is there is a misunderstanding between the two it becomes a dispute. Dictionary of Law define disputes as a conflict of claims or rights. Whenever one party to a contract requests something from the other party under the terms of their contract and that request is not complied with; there is a dispute. Meanwhile, the words “disputes” has been defined by Kumuraswamy as situation when a claim or assertion made by one party is rejected by another party and his rejection is not accepted. Tillet G (1991) defines that construction dispute as the incompatibility of two (or more) people’s (or groups’) interests, needs, or goals. As they seek to maximize fulfillment of their own interests, or needs, or achievement of their own bargaining or negotiating through compromise, one party may yield to the other on that which is less important. When this happens, the dispute is usually settled. To conclude disputes in a simplistic way in principle is that it is an event or scenario of which either one or both of the party involve in an agreement failed to deliver the agreed product or outcome. 9 2.3 Nature of Construction Dispute Murdoch J and Hughes (2000) stated that the first factor defining the nature of a construction disputes is the term of contract. Basically, a contract is an enforceable promise. And the subject of this enforceable promise is the production of a unique, technical artifact, using temporary management system. There are four nature of construction disputes outline by Murdoch J and Hughes as explained below. 2.3.1 Enforceable Promises Building contracts, like any other contract, are concerned with making promises, with the expectation that one can be forced to carry them out. A person who has no intention of doing a thing should not sign a contract recording that there is no such an intention. Of course, it can happen that people enter into contracts that they did not completely intend. A shared mistake is no real problem, as the parties can rectify it by mutual consent. However what sometimes happens is that one party claims, due to oversight or mistake, to have signed a contract that does not accurately reflect his or her attention. If there is a difference of interpretation, then the type contract will be important in term of the way in which it will be interpreted. If it is not a standard form of contract, the principal of ‘contra proferentem’ will prevail. This means that any ambiguity in the contract will be construed against the party who seeks to benefit by exclutions or limitations in it. This will usually, although not always, be the party which put it forward. It is during disagreements about the intentions of contracting parties that such details as notes of telephone conservations, minutes of meetings, correspondence and the like may become relevant. These seek to provide evidence to the parties intentions. However, it will in most cases be too late for the dissenting party to alter the contract. 10 Building contract, as we have seen, are very comprehensive and specific about what is expected of each party, and it is difficult to claim that the obligations arising from entering into such a contract were not properly understood at the time it was made. 2.3.2 Technical Matters Disagreements often arise over technical questions. The technology involved in construction is idiosyncratic, difficult to understand and subject to change. Added to this is any change that may be associated with the technology of the client organization. The use of different and/or familiar techniques is often the causes arguments and disagreements. For example, the nature of the site is often source of contention. While the site itself is clearly visible at ground level, it can hold many surprises once excavation starts. It is not enough merely to look at a site in order to ascertain the site condition. Adequate site investigation is a constant source of problem in the industry. Who responsibility is it? In order to answer that question, one must look at the clauses in the contract. Do they represent what is intended? Once the cause is identified, it is a fairly straightforward matter to allocate blame and with it legal responsibility. 2.3.3 Legal Matters Some disputes are technically simple, and turn on what is the law on a specific point. The law is not infinite. There many day-to-day occurrences that have not previously been decided upon by the courts. There are many spheres of activity not covered by statute. The resolution of a dispute may hinge upon the ascertainment of the law in a previously undefined area. 11 One particular legal problem area arises from the inconsistencies between various contracts. A major problem mentioned by Latham (1994) was the inconsistencies and gaps between the various consultant appointments and the building contract. As a result, most of the bodies who drafts the contracts now seek to produce integrated packages of contracts, rater than a standard form for just one of the relationship. Where a dispute arises under a construction contract, the first means of resolving that dispute in a binding manner is often through a decision of the contract administrator. Until recently, a party wishing to pursue a dispute beyond the contract administrator had two options: either to go to arbitration, if the contract made provision for this, or to begin proceedings in court. 2.3.4 Entitlement and magnitude The rough division of disputes into ‘technical’ and legal is often reflected in two aspects of a claim. The first aspect is that, for any claim to succeed, legal entitlement to the money must first be proven. After this, the magnitude of the claim must be established. Entitlement arises from the legal interpretation of the contract and associated documents. Magnitude then followed as a factual ascertainment of technical data. In consequences, most disputes contain elements of both types of disputes. 12 2.4 Sources of Disputes It is important to identify the sources of dispute in order to prevent or minimise them. According to Cheung et al (2006) the basic factors that drive the development of disputes are identified; these include: 1) project uncertainty; 2) contractual problems; 3) opportunistic behavior. Yate (1998) pinpointed that the main types of construction dispute arising from the contract document include: 1) variations; 2) ambiguities in contract documents; 3) inclement weather; 4) late issue of design information/drawings; 5) delayed possession of site; 6) delay by other contractors employed by the client (e.g. utility companies); 7) postponement of part of the project. In the study by Kumaraswamy and Yogeswaran (1998) it was indicated that the sources of construction disputes are mainly related to the contractual matters, including variation, extension of time, payment, quality of technical specifications, availability of information, administration and management, unrealistic client expectations, and determination. P.M Feniosky et al (2003) stated that the rationale behind the efforts to identify the sources of disputes in construction has been the premise that if the origins of the ‘illness’ can be identified, ways to ‘cure’ the industry from unnecessary litigation can be developed. Fenn et al (1997) had summarized seven different research efforts conducted 13 during the past decade and the sources of disputes in construction projects they have identified which are as listed in the table in the following page: Table 2.1: Research on the Sources of Conflicts and Disputes in Construction Industry Research Author Sources of Conflicts and Disputes in Construction Five areas: unrealistic expectations; contract documents; Bristow 1998 communications; lack of team spirit; and changes Six areas: payment; performance; delay; negligence; quality; and Conlin et al.1996 administration. Seven areas: contract terms; payment; variations; time; Heath et al. 1994 nomination; renomination and information. Six areas; change of scope; change conditions; delay; disruption; Hewit 1991 acceleration; and termination Ten areas; management; culture; communication; design; Rhys Jones 1994 economics; tendering pressures; law; unrealistic expectations; contracts and workmanship Semple et al. 1996 Four areas; acceleration; access; weather; and changes Sykes 1996 Two areas; misunderstandings; and unpredictability [Sources: Fenn et al.1997] Twenty sources of disputes in Sino-Foreign Joint Venture construction projects were identified by H.W C Edwin And C.H.S Henry (2005) which include variations; extension of time; payments; quality of works; technical specification; availability of information; administration/management; unrealistic client expectations; risk allocation; project scope definition; poor communication; difference in ways of doing things; lack of team spirit; previous working relationships; adversarial approach in handling disputes; unfamiliar with local conditions; conflict of laws; jurisdictional problems; lack of local legal system; and unclear contractual terms. 14 Hewit (1991) identified six types of construction dispute; change of scope, change conditions, delay, disruption, acceleration, and termination. According to M.H Jeffery (2002), disputes occur even though the parties involved all are well intended. This often happens because someone “drops the ball” by failing to communicate effectively with another concerning design issues, compensation and payment issues, scope change issues and the like, leading to legal disputes. The increase in the number of participants of different cultural background in the construction value chain means more business interactions and arguments, whether contractual or social, resulting in an increase in the number of construction disputes stated by Kumaraswamy and Yogeswaran (1998). 2.4.1 Inconsistencies of Contract According to C. Keith (1994) some contracts say that certain contract documents shall govern others if discrepancies are found among them; usually in a declining order as follows: 1. Agreement 2. Supplementary or special conditions 3. General Conditions 4. Specifications 5. Drawings In this way, some inconsistencies may be removed in advance, but others in the same document may remain to confound and cause difficulties. If a dispute over a contractual matter arises, it may be worth looking for contractual inconsistencies that touch on the matter in question. Inconsistencies often are the cause of disputes since each party will favor the interpretation that better suits his or her position. 15 The survey done by Sambasivan and Yau (2006) found that the factors of discrepancies in contract document are one of major contribution to the causes of project delay in Malaysia which eventually had cause disputes between contractual parties. According to K.C Iyer et al (2008), the contract language is considered difficult to comprehend and they are therefore a major source of disputes. Besides that, lack of understanding in contract clauses is one of source of dispute (Broom and Hayes, 1997). Lack in clarity of contract clauses has brought lot of disagreement regarding the contractual obligation to the construction practitioners. 2.4.2 Payment Murdoch J and Hughes (2000) stated undoubtedly the most important of all the employer’s express obligations is to pay the contractor the sum of money which forms the consideration for the contract known as the Contract Sum. According to Ameer Ali (2005), payment has been referred as the lifeblood of the construction industry because construction projects involve large capital and take long time to complete. Meanwile, according to S.Samy Vellu (2006), one of the greatest problems encountered by the contractors is payment either late payment, non payment or short payment. The operation of the payment system is not always smooth. This has an adverse effect on the efficiency and stability of the whole industry. A failure of timely payment can result in project delay, reduced profitability and also lead the company to going into liquidation as stated by Ameer Ali (2005). C. Keith (1994) stated that delayed payments probably will result in extra financing cost for a contractor. A contractor may suffer other losses, such as 16 uncollectable cash discounts on materials, because delayed payments. Prolonged to delays in payment cause the even more serious effects of a restricted cash flow such as; 1. Inability to pay bills 2. Lowering of credit rating 3. Discontented staff and workers 4. Liens on the work 5. Financial failure There is no hesitation that, delayed payment or non payment will cause delay to the progress of Works. As a result, this will also lead to the major construction disputes between the client and the contractors. 2.4.3 Determination of Contract Based on PWD Form 203A either party to a contract can terminate or determine the contract under certain circumstances. According to M.L Don (1991) the usual cause for determination is default of one party for reasons set down in the conditions of contract. Other problems experienced when a contract is determine are the area of quality control, which may suffer, and the question of responsibility for partly completed work is always in contention. Bear in mind that, even though there are such provision in condition of contract, determination of contract should be seen as a last resort as there would cause grievance to both contractual parties. As a result, both contractual parties will suffer financial losses and absolutely will also cause delay to the project that lead to construction disputes. 17 2.4.4 Variation Clearly, buildings are so complex as to require changes to be made before they are completed. Additionally, it is rare for design to be completely detailed at the time of tender, a result of this is that changes have to be made in order simply to make the building work. One possible disadvantage of a variations clause is that it may encourage the design team to be less than specific at the time of tendering, in terms of what to be built. The fact that things may be varied as the contract proceeds means that the design team may not have to finalize their design until a very late stage. This is bad practice and should be discouraged as far as possible. K.S Harban Singh (2003) stated the implication of such changes both in terms of the financial aspects and the legal ramifications can be of material significance; this being evidenced by the litany of disputes an claims reaching arbitral forums and the corridors of justice as of recent. To this effect, it can safely said that next to issues pertaining to payment, disputes or claims related statistic in he engineering and construction industry exhibit a tendency for variations related matters to be a major source of contention between the contracting parties. 2.4.5 Lack of Communication S Murali and W.S Yau (2007) stated since there are many parties involved in a project (client, consultant, contractor, sub-contractors), the communication between the parties is very crucial for the success of the project. Proper communication channels between the various parties must be established during the planning stage. Any problem 18 with communication can lead to severe misunderstanding and therefore, delays in the execution of the project. According to M.H Jeffery (2002) a similar dispute may occur when an owners design vision of a project is not communicated effectively to the design team. Perhaps due to an owner’s inexperience, this breakdown may result in an unrealistic project square footage, unnecessary architectural features, and/or finishes that cannot be achieved within budget. According to E.G. Frederick and E.J Nancy (2003) any successful relationship, either personal or professional, relies on good communication between the parties. A construction team is no different. There are many methods of communication- some formal, some informal. In formal communications are necessary to keep the job running smoothly; but if decisions are made or agreements reached, these communications need to be documented. Formal communication should have an organized method that is understood and agreed to by all parties. In this way, each person can feed into another’s system, easily referencing documents as needed. 2.5 Causes of Disputes In General K.S Harban Singh (2003) had identified that a proliferation of disputes arising from conflict and claims in recent years. These reasons can be summarized under following broad categories; 1. Personality clashes between the various parties to the contract and/or member of project team; 2. Differing goals and objectives of the various parties; 3. A prevailing confrontational/adversarial atmosphere; 19 4. Lack of proper communication between the parties; 5. Allocation of insufficient resources; 6. Complexity of the works under the contract; 7. Allocation of inadequate time for the preparation of contracts and their discharge; 8. Workmanship or quality control problems; 9. Lack of proper planning both in terms of physical work and financial aspects; 10. Lack of good faith on part of the parties; 11. Failure to resolve minor differences on an amicable basis 20 The fish bone diagram below Fig. 2.1 shows causes of disputes in general: A prevailing Failure to resolve minor Personality clashes between confrontational/adversarial differences on an amicable the various parties to the atmosphere basis contract and/or member of project team; Lack of proper planning both Differing goals and objectives in terms of physical work and of the various parties; financial aspects DISPUTES Lack of proper communication between the parties; Allocation of insufficient resources Allocation of inadequate time for the preparation of contracts and their discharge; Complexity of the works under the contract Lack of good faith on part of the parties Workmanship or quality control problems 21 2.5.1 Causes of disputes by stakeholder For decades, the construction industry has been mired in adversarial relationships between owners and contractors as stated by Fenn et al. (1997). Each party’s priorities are unsurprisingly at conflict with the others, establishing a repetitive cycle of hostilities. According to Howard et al. (1997), “The owner usually wishes to obtain maximum quality, functionality, and capacity at minimum cost. The contractor, while hoping to develop a satisfied client, must in the long run achieve financial goals that are advanced by expending the minimum resources required to meet a minimum scope of work”. Fenn et al., (1997) states that “as a consequence of building projects in general being complicated, unique ventures erected largely in the open, on ground the condition of which is never fully predictable and in weather conditions that are even less so, it is common for disputes to arise during the course of building operations”. There are many reasons why disputes occur, but in the main they are caused by the failure of one or more members of the building team: • Failure to do their work correctly, efficiently and in a timely manner • Failure to express themselves clearly, or • Failure to understand the implication of instructions. Ashworth (2006) stated disputes between parties, are really in no one’s best interests. Below are some of the main areas where disputes might occur between parties. 22 2.5.1.1 Clients 1. Poor briefing during design stage 2. Changes and variation requirements 3. Changes to standard conditions of contract 4. Interference in the contractual duties of the contract administrator 5. Late payment to contractor 6. Unrealistic expectations of the parties, particularly employers who have insufficient financing to accomplish their objectives (H.W C Edwin and C.H.S Henry 2005). 7. Clients fail to pay variation claim (Cheung et al 2007). 8. Failure to respond in timely manner 9. Inadequate tracing mechanisms for request of information 10. Deficient management, supervision and coordination efforts on the part of the project. 11. Lowest price mentality in engagement of contractors and designers. 12. The absence of team spirit among the participants. 13. Reluctant to check for constructability, clarity and completeness. 14. Failure to appoint a project manager. 15. Discrepancies / ambiguities in contract documents. 23 The fish bone diagram below Fig. 2.2 shows causes of disputes caused by client: Failure to appoint a project manager The absence of team spirit among the participants Interference in the contractual duties of the contract administrator Late payment to contractor Reluctant to check for constructability, clarity and completeness Unrealistic expectations of the parties, particularly employers who have insufficient financing to accomplish their objectives Clients fail to pay variation claim DISPUTES Failure to respond in timely manner Deficient management, supervision and coordination efforts on the part of the project. Poor briefing during design stage Lowest price mentality in engagement of contractors and designers Changes and variation requirements Discrepancies / ambiguities in contract documents. Changes to standard conditions of contract Inadequate tracing mechanisms for request of information 24 2.5.1.2 Consultants 1. Design inadequacies 2. Lack of appropriate competence and experience 3. Unclear delegation of responsibilities 4. Late issue of design information/drawings (Yates,1998) 5. Errors/substantial changes in bills of quantities (Cheung et al, 2007) 6. Variations due to design errors (Cheung et al, 2006) 7. Design and specification oversights, and errors or omissions resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs (M.H Jeffery, 2002). 8. Failure to understand its responsibilities under the design team contract. 9. Late information delivery and cumbersome approach to request for information’s. 10. Incompleteness of drawing and specifications. 25 The fish bone diagram below Fig. 2.3 shows causes of disputes by consultant: Design inadequacies Failure to understand its responsibilities under the design team contract. Errors/substantial changes in bills of quantities Late information delivery and cumbersome approach to request for information’s. Lack of appropriate competence and experience DISPUTES Variations due to design errors Design and specification oversights, and errors or omissions resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs Unclear delegation of responsibilities Late issue of design information/drawings Incompleteness of drawing and specifications. 26 2.5.1.3 Contractors 1. Inadequate site management 2. Poor planning and programming 3. Poor standard of work 4. Delayed payment to subcontractors 5. Fails to proceed works in a competent manner (Cheung et al, 2007). 6. Failure to coordinate its subcontractors’ work through effective and timely exchange of shop drawings (M.H Jeffery,2002). 7. Lack of understanding and agreement in contract procurement (Carmicheal, 2002). 8. Delay/ suspension of works. 9. Failure to plan and execute the changes of works. 10. Failure to understand and correctly bid or price the works 11. Reluctance to seek clarification. 12. Inadequate CPM scheduling and update requirements 27 The fish bone diagram below Fig. 2.4 shows causes of disputes by contractor: Delay/ suspension of works Poor standard of work Lack of understanding and agreement in contract procurement Failure to plan and execute the changes of works Failure to coordinate its subcontractors’ work through effective and timely exchange of shop drawings Inadequate site management DISPUTES Reluctance to seek clarification Delayed payment to subcontractors Failure to understand and correctly bid or price the works Poor planning and programming Inadequate CPM scheduling and update requirements Fails to proceed works in a competent manner 28 2.6 Effect of disputes According to Cheung et al (2002), the effects of construction disputes are detrimental; if disputes are not properly managed, they may cause project delays, undermine team spirit, increase project costs, and, above all, damage continuing business relationships. Hall (2000) observed that consequences of the construction disputes will not benefit the stakeholders in the construction project. Iyer et al (2008) states that with the increasing size and complexity in nature of projects the conditions of the contracts also tend to become more complicated, which in turn add to number of disputes to the already existing ones and further delay the settlement of disputes. The delay in dispute settlement has manifold effects as given below. It hampers the project progress if dispute arises during execution stage. 1) It is detrimental to the relationship between owner and contractor. 2) It contributes to the cost and time overruns. 3) It sends bad signals to foreign investors thereby slowing down the national progress. 2.6.1 Effect on Cost and Profitability S Murali and W.S Yau (2007) stated that factors such as inadequate planning by the contractors, improper site management by the contractors, inadequate project handling experience of contractors, and delay in the payments for the work completed directly affect the completion of the project and cause cost overrun. One of the major concerns of construction industry participants regarding the matter of disputes is its effects on the costs or economics of the projects, as well as the 29 financial returns of their effort and investments. The following discuss several key aspects of the effects of disputes towards project costs and participants profitability. 2.6.1.1 Financial Costs According to the study conducted by Harmon (2003), nearly all (99 %), of the major participants in construction industry agreed that disputes occurring during the course of construction result in additional financial costs. Major concerns were also noted by these participants regarding the high cost of litigation. Only those who have not experienced disputes and litigation were not concerned of these costs. 2.6.1.2 Hidden Costs Apart from the burden of financial costs, the study conducted by Harmon, also revealed that majority of the industry participants studied recognized that hidden costs may be incurred if disputes arising during construction are not quickly resolved. Examples of such costs include the diversion of manpower away from the project (or even a new project) in order to prepare for a deposition, trial or arbitration; the time it takes to bring an attorney or consultant up to speed about the project and the dispute; a reduction in bonding capacity; and damage to reputation. There was also a major concern by both contractors and owners of construction projects, that unresolved disputes would hinder their focus on the next or other projects in hand, since available resources may need to be prepared for any eventualities or outcomes from the disputed projects. 30 2.6.1.3 Reducing Profit Margin Disputes can also affect profitability. In today's economy, both the owner and the contractor seek means to increase the value of their dollar-the contractor by increasing profits and the owner by controlling costs. When an owner spends money on adversarial dispute resolution processes, the funds available for rehabilitation, repairs and new construction are reduced. When the contractor spends money for litigation or arbitration, the profitability of the job is lessened. 2.6.2 Effect on Time According to S Murali and W.S Yau (2007), contract-related factors such as change orders (changes in the deliverables and requirements) and mistakes and discrepancies in the contract document result in cost overrun. Mistakes and discrepancies in the contract document can be in scope, deliverables, resources available and allocated, payment terms, achievement of various milestones, and the project duration. In most of the instances, time overrun leads to cost overrun. The effect of disputes on the timing or schedule of construction projects are well documented as stated by Barry & Michael (1987). In most cases, disputes tend to cause delays in most construction projects. Delays in turn may result in various other subeffects which included; ï‚· Prevention of early completion ï‚· Acceleration, which may force additional resources to be contributed ï‚· Lost of productivity and efficiency (idled labor and equipment) ï‚· Rescheduling and resequencing (due to change work orders, stop work notice, and others as such) 31 ï‚· Increase in time-related costs (such as idled equipment rental costs, changes in building materials price, bank interest, utilities charges, insurance and others as such) ï‚· Third party claims, due to damages for delay to construction projects which affect them ï‚· Abandonment of project by contractors and termination of contract. Whenever there are delays, there are disputes as to who should bear the responsibility and the cost. These disputes often lead to an arbitration process by third parties and failure in this process leads to litigation where the disputes are settled by the court. In extreme cases, some projects might be totally abandoned. About 17% of the projects in Malaysia are abandoned (MALBEX, 2005). 2.6.3 Effect on Quality According to Okumbe (2007), quality is defined as “fitness to purpose”, an i.e. delivering product (buildings or physical structures) which gives an appropriate service for which it is intended. The quality of products or services refers to the perception of the degree to which the product or service meets the customers’ expectations (manifested through contract agreement). Quality therefore bears no specific meaning (perceptual, conditional and somewhat subjective attribute) unless related to specific function and/or objects; costs, time, functionality, appearance, aesthetics and others as such. For that matter, any kind of disputes which affects any of these attributes may affects the quality of product to be delivered. 2.6.4 Effect on business and working relationship Cheung et al (2002) stated a continuing relationship is one of the key elements for any organization to strive for. A good relationship is always based on trust, common interests, and respect and requires the effort and commitment of the parties to make it last. 32 As pointed out by Harmon in his work, the effect of disputes on business and working relationship is generally deconstructive in nature. Nearly all participants studied agreed that conflicts adversely affect the parties’ working relationship, whereby; relationship are strained at best; communications limited; and all parties’ involved became suspicious with one another. These, if not properly managed and resolved, will foster hard feelings and may turn into an ‘ugly’ all out war between these parties’ and severe business relationship in a long run. Findings from Harmon’s work also agreed that unresolved disputes are counterproductive to the progress of construction and can bog down a project. A dispute creates a lot of lingering problems beyond the dispute itself for the completion of the project. It kind of sours the relationship among the people, it also makes it more difficult to resolve other problems that come up during the course of the project, and it's divisive and both [parties] are worrying about the fight they are in rather than getting the job done. 2.6.5 Dispute Escalation (Chain Reaction) A dispute may give rise to another or more other disputes. As studied by Harmon, nearly all the participants of construction industry agreed that when disputes are not resolved, they escalate and become protracted and may turn into an all out conflict and become the breeding base for subsequent disputes (especially on projects that involved a lot of parties with varying contributions and varying contracts or subcontracts). 33 2.6.6 Emotional Costs Majority of the participants of construction industry as studied by Harmon also acknowledged that unresolved disputes result in job stress. Conflict is stressful and physically and psychologically draining. The emotional cost can be substantial. People can become so emotionally involved in the dispute rather than focusing in on it. It creates a real personal problem with the people in dealing with it. Relationships start to deteriorate; people around the jobs see that, know there's a problem. It impacts them and their progress. And it can be devastating to a job. 34 Effect of Disputes Financial Costs Cost and Profitability Time Hidden Costs Reducing Profit Margin Quality Business and working relationship Figure 2.5 : Effect of Construction Disputes Dispute Escalation (Chain Reaction) Emotional Costs 35 2.7 Avoiding Disputes Pro-active steps need to be taken by the three (i.e., the owner, design engineer/ construction manager, and contractor) to foster a cooperative attitude among the parties toward the avoidance of disputes. According to Groton (1998), the parties to construction project implement loss prevention and dispute avoidance measures in their own business practices, adopt partnering to promote teamwork, and agree upon dispute resolution procedures for the project. 2.7.1 Partnering approach Cheung et al (2006) stated that the central ideal of partnering is to reduce the adversarial relationship between two parties and to encourage them to work in a cooperative manner. By being open and honest with each other, it is anticipated that the chance of conflict is greatly reduced, resulting in less dispute. Partnering also helps the parties to establish a long term working relationship. According to Richard (2003), partnering is usually achieved by a contract specification that requires the parties to the agreement to observe the fundamental obligations of good faith and fair dealing with each other during the project. Before actual work begins on the project, an independent facilitator conducts a retreat for the parties. This retreat serves three fundamental purposes: (1) to define leadership and management responsibilities; (2) to establish non adversarial methods to identify potential problems and resolve them before they materialize stated by Groton (1998) and (3) to nurture long term relationships built upon reciprocity and trust. As such, partnering 36 reduces future conflict and related expense, enhances project communications, and maintains relationships stated by TJ Stipanowich (1998). As stated in Building (1998), partnering also focuses on dispute avoidance and prevention but, in contrast to a firm-based loss-prevention program, partnering establishes the project protocols for party interaction, problem recognition and solution, and dispute resolution. According to ASFE (1995), when the parties do not adopt a formal partnering agreement, they can apply the loss prevention skills and techniques they use in their own firms to project management function. 2.7.2 Clarification of responsibilities Each party in construction needs to be clear about their tasks and responsibilities. It is important to spell out roles and responsibilities at the beginning of the contract because often parties to the contract are unaware of their rights and responsibilities until problems develop. M.Don (1991) had listed out each stakeholder responsibilities in general: 2.7.2.1 Client Client responsibilities include: 1. Responsible for providing all information necessary to maintain the buildings works in accordance with the approved programme 2. Responsible for the accuracy of all information contained in the agreement relating to the site and warrant the site in some instances 3. Only vary the contract under the conditions set down in the contract 4. Pay the contractor the contract sum as stated in the contract 5. Responsible under the contract for actions of his agent 37 2.7.2.2 Contractor Below are some of the lists of contractor responsibilities: 1. Execute the whole of the works set out in the contract 2. Carry out work in an efficient and professional manner 3. Maintain the approved work programme 4. Execute properly documented variations to the contract 5. Maintain the site in good order and condition and allow access to approved persons 6. Carry out instruction given in writing b authorized persons 7. Carry out work in accordance with local regulations 8. Deliver up the whole of the works on completion, allow the owner to occupy, maintain the works for that period if so specified, and be responsible for defects for a nominated period. 2.7.2.3 Consultant Consultants responsibilities include: 1. Carry out obligations under the terms conditions of respective contracts 2. Prepare designs, contract documents and cost estimates for their specialist functions and co-ordinate with design team 3. be responsible for all aspects of such documents 4. Recommend contractors for specialist trades to act as nominated subcontractors 5. Arrange the testing and hand-over of relevant sections of the work on completion 6. Carry out responsibilities and render the defects liability provisions as they apply to their particular section 7. Assist with post-contract evaluations as required. 38 2.7.3 Risk Allocation Project risk can be defined as an uncertain event or condition that, if it occurs, has a positive or negative effect on at least one project objective, such as time, cost, scope, or quality. M.L Don (1991) recommended that the term “obligations’ should replace the “risks”. He also suggested that there is necessity for clear identification of risk areas and he promoted risk allocation model to determine obligations. MJ Termini (1999) stated that one of the major steps in project risk management is to identify and assess the potential risks in the project. Every project contains some degree of risk; and yet, most project managers are ill prepared when it comes to identifying or adequately addressing potential risks. Meanwhile according to PMI (2004) be successful, the organization should be committed to addressing the management of risk proactively and consistently throughout the project. Risk is manageable, diminishable, transferable or acceptable but not ignorable as stated by M Latham (1994). As a part of a risk management strategy, it is commonly defined through the contractual documents. Usually, a tender document of a construction project is prepared by the contracting party, i.e. the owner, who initiates the project. It is common that the owner tends to contractually pass the responsibility for most of the risks to the contractor under traditional procurement processes stated by JA Rutgers and HD Haley (1996). According to M.E Sameh (2007) project risks are divided into two groups, according to their source, into internal and external. Internal risks are those that are project related and usually fall under the control of the project management team. External risks are those risks that are beyond the control of the project management team. A .Aleshin (2001) stated that ‘‘internal risks are initiated inside the project while external risks originate due to the project environment’’. Internal risks are then divided according 39 to the party who might be the originator of risk events such as owner, designer, contractor, etc. External risks are those initiated at the macro level. 2.7.4 Increase ability to resolve problems M. Panagiotis and H. Gregory (2001) suggested to resolve problems with low solution and disruption costs, in addition to cooperative behavior, the project team must establish effective problem-solving mechanisms. This requires: (1) problem-solving and negotiation skills, and (2) processes and policies to promote fast decision making at the project level, and fast escalation of issues that cannot be resolved on site. When uncertainty is high, a significant investment in such mechanisms may be needed. The development of skills, processes, and relations require significant effort and investment at the beginning of the project, because changes in attitudes and beliefs and learning of new skills and processes are necessary for successful cooperation. 40 Partnering approach Clarification of responsibilities Disputes Minimisation Increase ability to resolve problems Figure 2.6 : Disputes Minimisation Risk Allocation 41 CHAPTER III RESEARCH METHODOLOGY 3.1 Introduction In order to achieve the aim as well as the objectives as outlined earlier in this research, therefore the standard and commonly used research process had been employed. The major step or stages as well as the binding activities within this process from start until completion are discussed further in the following sections. The flowchart diagram (Figure. 1.1) illustrating the process of the research methodology to be used to carry out the study. 3.2 Literature Review This section discuss elaborately on previous work done by others in relation to the subject matter of this particular research. Apart from that, general or established facts which are relevant to this field of study will also be reviewed and presented. Information related to the problem were gathered from reliable sources such as from the internets articles published by relevant and chartered establishment; recent journals both print and digital; working papers and proceedings; court cases; relevant reference books and newspaper articles. 42 3.3 Data & Information Gathering Relevant data and information are gathered to establish links between various subject matter of this research. Apart from that, these data and information would also be applied where possible, in strengthening the facts that were reviewed in the literature or between various literatures. In general, the data that are gathered for this research comprised of both primary and secondary data and information. 3.3.1 Primary Data and Information Two types of primary data and information are gathered for this research. The first of these is obtained through the use of questionnaires, whilst the second is through interviews. These data and information are used to relate real-time experience of respondents with respect to the facts, ideas and statements presented in various literatures, regarding the subject matter of this research. 3.3.1.1 Questionnaires Questionnaires are used to extract as much as possible relevant data and information from predetermined respondents. In general the content of this questionnaire are based on matters that are relevant for this research. Questionnaires were distributed in the state of Kuala Lumpur, Selangor and Klang Valley area. This is due to the fact that most projects are awarded to industry participants that are located or operates within these locations as stated by M. Alias et al. (2007). Sample selection is non-random, thus samples are selected from core participants of construction industry; contractors, clients and consultants. 43 The questionnaire were focused more on causes of disputes caused by each of the following parties; clients, consultants and contractors. These were to enhance the study in coming up with the best results that would benefit the industry in Malaysia and other countries faced with similar problem. The second part of the questionnaire was focusing on the effects of the disputes to organisation in the construction industry. This part of questionnaire would enhance the researcher in identifying the side effects of construction disputes in the industry at large. The final part of the questionnaire was on avoiding construction disputes. This would help in minimising construction disputes in the future and identify the best method to avoid construction disputes. 3.3.1.1.1 Method of Questionnaire Collection A postal questionnaire is considered to be the appropriate method for the analysis survey. The postal questionnaire is selected in view of its clear advantages over other method such as interview that will take longer time to achieve the same size of sample. By using the postal survey, a wider geographical coverage is possible. Moreover, due to time and financial factors, postal questionnaire is the most suitable method to collect the data. Moreover, due to time and financial factors, postal questionnaire is the most suitable method to collect the data. 44 3.3.2 Secondary Data and Information Secondary data and information were used to strengthen certain facts, ideas, figures and statements of primary interest within the scope of this research. Apart from that, secondary resources also had been used to compare, discuss and relate certain findings from the survey conducted through the questionnaires and interviews. The sources of these secondary data and information were various; include the data/information extracts from reference books; relevant journals/working papers, public records and relevant cases or court records such as judgment notes, appeal notes, and others as such. 3.4 Data Analysis and Interpretation After the compilation of responses, all types of data received under different questions had been separated and gathered to answer different research objectives. The data were categorized under different variables to represent the result of the research objectives. Analysis of data according to different objectives was done by using different statistical methods such as frequency analysis and average index analysis. 3.4.1 Frequency Analysis Frequency analysis used a tabular form to represent the result of data analysis of frequency of response that respondents gave to the different variables in the questionnaire. The result was tabulated in the form of frequency number and percentages according to total respondents. For graphic result presentation, bar chart and pie chart are used as summaries. 45 3.4.2 Average Index Analysis The result of the data collected will be further summarized by using average index analysis. The average index analysis for each variable was calculated by using the similar classification of the rating scale proposed by Abd. Majid (1997) and Likert Scaling as follows: Average Index = Σ ai.xi Σ xi “Not Important” 1.00 < Average Index (I) < 1.50 “Less Important” 1.50 ≤ Average Index (I) < 2.50 “Moderately Important” 2.50 ≤ Average Index (I) < 3.50 “Very Important” 3.50 ≤ Average Index (I) < 4.50 “Extremely Important” 4.50 ≤ Average Index (I) < 5.00 Average Index 1.00 < Average Index (I) < 1.50 1.50 ≤ Average Index (I) < 2.50 2.50 ≤ Average Index (I) < 3.50 3.50 ≤ Average Index (I) < 4.50 4.50 ≤ Average Index (I) < 5.00 3.5 Rating Scale Insignificant Less Significant Moderately Significant Significant Very Significant Conclusions and Recommendations Based on the results obtained, conclusions and recommendations were developed. Conclusions are drawn based on the findings and analysis of the results from the questionnaire survey in accordance with the research objectives. Specific and practical recommendations were later suggested on factors on how to manage construction disputes for the better performance of the industry in future. Recommendations are also 46 made available to aide for future researches. The next chapter renders the detailed information on the above mentioned statement. 47 CHAPTER IV DATA COLLECTION AND ANALYSIS 4.1 Introduction In this chapter, a detail analysis of data and result will be shown and elaborated by using Frequency Analysis and Average Analysis. Data collected is analyzed and interpreted as presented to achieve the objectives of the study. Conclusion has been derived on the major contributor that causes the construction dispute as the most appropriate measures were made to overcome the dispute occurrences. The data obtained from the questionnaire survey based on the response from client, consultants and contractors to the allocated questions on the construction dispute related issues were analyzed and had been categorized into 4 sections as listed below. a) Analyzed the data collected from clients b) Analyzed the data collected from consultants. c) Analyzed the data collected from contractors. d) Analyzed the data collected from all respondents (Overall). 48 4.2 Questionnaire Feedback There were eighty set of questionnaires distributed to construction participants included clients, consultants and contractor which had been selected randomly within Wilayah Persekutuan Kuala Lumpur, Shah Alam and Klang Valley areas. Out of the total 80 questionnaires, 40 questionnaires were returned with 5 incomplete responses. The remaining 40 questionnaires were unreturned by the respondents. Table 4.1: Response Percentage Number of Questionnaires % questionnaires Returned i) Complete responses 35 43.7 5 6.3 Unreturned 40 50.0 Total Distributed 80 ii) Incomplete responses Figure 4.1: Distribution Percentage of Questionnaire Sampling Distribution of Questionnaire Sampling 44% Completed Questionnaire Incomplete Questionnaire 50% Unreturned 6% 49 The analysis on the questionnaire responses will be done by using the 35 complete responses returned by the respondents. A majority of the questionnaires were returned by the contractors (42.9%), 37% were returned by the consultant and the remaining 7 questionnaires (20%) were gathered from the clients. Table 4.2: The Percentage of Respondent Based on Organisation Stakeholders Number of % questionnaires Contractor 15 42.9 Consultant 13 37.1 Client 7 20.0 Figure 4.2: Distribution of Stakeholders Percentage Distribution of Stakeholders 20% 43% Contractor Consultant Client 37% The table 4.3 displays the characteristic of the stakeholders in terms of years of working experience. Most of the respondents from all three categories of stakeholders were having more than 10 years of working experience. 9 questionnaires were gathered from contractor with more than 10 years experience, 4 contractors with 5 to 10 years experience and only 2 contractors with less than 5 years experience. Whereas for 50 consultant’s profile, 5 consultants are having more than 10 years experience, and both 5 to 10 years and less than 5 years experience having 4 respondents each. 3 respondents from client were having more than 10 years working experience and 3 respondents from 5 to 10 years experience category. Whereas only one respondent from the client profile is having less than 5 years experience. Table 4.3: Tabulation of Respondents’ Years of Working Experience Years of working experience Stakeholders Less than 5 5 – 10 More than 10 Contractor 2 4 9 Consultant 4 4 5 Client 1 3 3 Total respondents 7 11 17 Figure 4.3: Respondents’ Years of Working Experience No. of respondents Years of Working Experience 10 9 8 7 6 5 4 3 2 1 0 Contractor Consultant Client Less than 5 5 – 10 Years More than 10 51 4.3 Analysis and Results 4.3.1 Causes of Construction Disputes in General This section presents first stage of analysis to evaluate and determine the most significant causes of construction dispute in general. There are a total of 11 factors identified as causes of construction disputes in general. These factors are normalized and non bias to any profile of the respondents. The factors will be viewed from four different view point namely client, contractor, consultant and overall point of view. It is important to appreciate the responses gathered from various stakeholders’ perspective as their way of looking at the problem at hand may differ from one another. The significance of each factors in contributing as a cause of disputes in general is ranked based on the average index value. The average index was used to grade the weight of each factor on how much it affected the industry or rather how much it had contributed to the problem. i) Client’s Point of View There are seven respondents for the questionnaire pooled within the client’s profile. Table 4.4 shows the responses of clients on the causes of disputes in general. Table 4.4: Client’s point of view Frequency No. Statement 1. Lack of proper communication between the parties Workmanship or quality control problems. Lack of proper planning both in 2. 3. 1 2 3 4 5 Average Index Rank 0 0 0 2 5 4.714 1 0 0 0 3 4 4.571 2 0 0 1 2 4 4.429 3 52 4. 5. 6. 7. 8. 9. 10. 11. terms of physical work and financial aspects Differing goals and objectives of the various parties Complexity of the Works under the contract Allocation of inadequate time for the preparation of contracts and their discharge Personality clashes between the various parties to the contract and/or member of project team Failure to resolve minor differences on an amicable basis Lack of good faith on part of the parties Allocation of insufficient resources A prevailing confrontational/ adversarial atmosphere 0 0 1 3 3 4.286 4 0 0 3 2 2 3.857 5 0 1 1 4 1 3.714 6 1 0 1 4 1 3.571 7 0 1 3 2 1 3.429 8 0 1 4 0 2 3.429 8 0 2 3 2 0 3.000 10 0 2 4 1 0 2.857 11 The results from Table 4.4 above shows that clients relates two factors as very significant to the causes of construction disputes in general as the average index value exceeds 4.500 level. The first factor is lack of proper communication between parties which scores 4.714 on its average index value. Undeniably, communication breakdown between parties involved in the construction industry may always be regarded as the impetus to construction disputes. The second factor that is considered as very significant is workmanship or quality control problems (average index: 4.571). This is subsequently followed by five factors rated as significant to causes of disputes in general as the average index falls between 4.500 and 3.500 level. These factors are listed based on the significance level as follows: ï‚· Lack of proper planning both in terms of physical work and financial aspects ï‚· Differing goals and objectives of the various parties ï‚· Complexity of the Works under the contract 53 ï‚· Allocation of inadequate time for the preparation of contracts and their discharge ï‚· Personality clashes between the various parties to the contract and/or member of project team It is then tailed by four factors which are observed as moderately significant and less significant to the subject matter. These factors are namely failure to resolve minor differences on an amicable basis, lack of good faith on part of the parties, allocation of insufficient resources and prevailing confrontational/adversarial atmosphere. ii) Consultant’s Point of View Results from the questionnaires gathered from consultant’s point of view are tabled in the following Table 4.5. Total of 13 respondents from consultant profile responds to the questionnaires. Table 4.5: Consultant’s point of view Frequency No. Statement 1. Lack of proper planning both in terms of physical work and financial aspects Lack of proper communication between the parties Workmanship or quality control problems. Complexity of the Works under the contract A prevailing confrontational/ adversarial atmosphere Differing goals and objectives of the various parties Allocation of insufficient resources 2. 3. 4. 5. 6. 7. 1 2 3 4 5 Average Index 0 0 0 5 8 4.615 1 0 0 2 2 9 4.538 2 0 0 1 5 7 4.462 0 0 2 7 4 4.154 4 0 0 4 3 6 4.154 4 0 0 5 6 2 3.769 6 0 1 4 5 3 3.769 6 Rank 3 54 Allocation of inadequate time for the preparation of contracts and their discharge Failure to resolve minor differences on an amicable basis Lack of good faith on part of the parties Personality clashes between the various parties to the contract and/or member of project team 8. 9. 10. 11. 1 2 3 5 2 3.385 8 0 4 4 2 3 3.308 9 0 3 8 2 0 2.923 10 2 3 4 3 1 2.846 11 Table 4.5 illustrates the result from the questionnaire answered by the consultant. These results relay the responses from consultant’s perspective on the causes of disputes in general. Based on the consultant’s point of view out of 11 factors listed, two factors recorded average index value more than 4.500 level which is considered as very significant. Both factors are related to communication issue in the construction industry. These factors are: ï‚· Lack of proper planning both in terms of physical work and financial aspects ï‚· Lack of proper communication between the parties This is then followed by five other factors with average index value lies between 3.500 to 4.500. Being within this range, these factors are regarded by consultant as significant to the causes of disputes in general. The significant factors are listed as follows; ï‚· Workmanship or quality control problems. ï‚· Complexity of the works under the contract ï‚· A prevailing confrontational/ adversarial atmosphere ï‚· Differing goals and objectives of the various parties ï‚· Allocation of insufficient resources 55 iii) Contractor’s Point of View Majority of the respondents to the questionnaires are from contractor profile. The view point from 15 contractors concerning causes of disputes in general are gathered and tabulated in the following table. Table 4.6: Contractor’s point of view Frequency No Statement 1. Lack of proper communication between the parties Complexity of the Works under the contract Lack of proper planning both in terms of physical work and financial aspects Differing goals and objectives of the various parties Allocation of inadequate time for the preparation of contracts and their discharge A prevailing confrontational/ adversarial atmosphere Allocation of insufficient resources Workmanship or quality control problems. Failure to resolve minor differences on an amicable basis Personality clashes between the various parties to the contract and/or member of project team Lack of good faith on part of the parties 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 1 2 3 4 5 Average Index 0 0 1 6 8 4.467 0 0 1 6 8 4.467 0 0 2 6 7 4.333 0 0 6 4 5 3.933 0 2 3 7 3 3.733 5 0 0 9 3 3 3.600 6 1 2 3 6 3 3.533 7 0 3 5 5 2 3.400 8 1 2 6 2 4 3.400 8 2 3 5 3 2 3.000 10 2 4 7 2 0 2.600 11 Rank 1 1 3 4 Results shown in Table 4.6 above illustrate the reactions from the contractor’s point of view on the causes of construction disputes in general. It is worth to note that contractors did not rate any factors as very significant as a cause of construction disputes. 56 However, seven factors with the average index value between 3.500 and 4.500 level are observed to be significant to the cause of construction disputes in general from the contractor’s standpoint. These factors are listed as follows according to the level of significance; ï‚· Lack of proper communication between the parties ï‚· Complexity of the Works under the contract ï‚· Lack of proper planning both in terms of physical work and financial aspects ï‚· Differing goals and objectives of the various parties ï‚· Allocation of inadequate time for the preparation of contracts and their discharge ï‚· A prevailing confrontational/ adversarial atmosphere ï‚· Allocation of insufficient resources iv) Overall Respondents Table 4.7: Overall Respondents Frequency No. Statement 1. Lack of proper communication between the parties Lack of proper planning both in terms of physical work and financial aspects Complexity of the Works under the contract Workmanship or quality control problems. Differing goals and objectives of the various parties A prevailing confrontational/ adversarial atmosphere Allocation of inadequate time for the preparation of contracts and their discharge 2. 3. 4. 5. 6. 7. 1 2 3 4 5 Average Index 5 6 10 10 4 4.543 1 0 0 3 13 19 4.457 2 0 0 6 15 14 4.229 3 0 3 6 13 13 4.029 4 0 0 12 13 10 3.943 5 0 2 17 7 9 3.657 6 1 5 7 16 6 3.600 7 Rank 57 8. 9. 10. 11. Allocation of insufficient resources Failure to resolve minor differences on an amicable basis Personality clashes between the various parties to the contract and/or member of project team Lack of good faith on part of the parties 1 5 10 13 6 3.514 8 1 7 13 6 8 3.371 9 5 6 10 10 4 3.057 10 2 8 19 4 2 2.886 11 Causes of construction disputes analyzed from the cumulative view from client, consultant, and contractors are shown in the Table 4.7 above. Based on the result, it is observed that all stakeholders agreed that communication is the major and the single most important factor that can lead to construction disputes. As show in table above, only one factor records an average index value of exceeding 4.500 level. Lack of proper communication between parties is considered as very significant as a cause of dispute in general as it scores 4.534 in average index value. This is then subsequently followed by the factors regarded as significant with average index value ranges between 3.500 to 4.500 level. There are seven factors classified as significant in contributing to causes of construction in general. These factors are listed as below according to the level of significance. ï‚· Lack of proper planning both in terms of physical work and financial aspects ï‚· Complexity of the Works under the contract ï‚· Workmanship or quality control problems. ï‚· Differing goals and objectives of the various parties ï‚· A prevailing confrontational/ adversarial atmosphere ï‚· Allocation of inadequate time for the preparation of contracts and their discharge ï‚· Allocation of insufficient resources On the other hand, the results show that three factors resulted as moderately significant to the problem at hand. These factors are having average index value in between 2.500 to 3.500. The factors listed below are rather of individualism and human 58 relation in nature and not directly related to the construction work nature. We have to accept the fact that individual involved in construction projects are having different personality and preferences in decision making. Listed below are three factors which are regarded as moderately significant to the cause of construction disputed in general. ï‚· Failure to resolve minor differences on an amicable basis ï‚· Personality clashes between the various parties to the contract and/or member of project team ï‚· 4.3.2 Lack of good faith on part of the parties Causes of Construction Disputes by Client This section discusses the analysis of the questionnaire concerning the causes of construction disputes by client. In order to gather a comprehensive feedback from the stakeholders, feedbacks from each stakeholder profile namely clients, consultants and contractors need to be analyzed. The analysis will focus on the factors that are very significant (average index of exceeding 4.500) and factors that are significant (average index between 3.500 to 4.500). Nonetheless, factors scoring average index lower than 3.500 level is regarded as moderately significant, less significant and very insignificant. These factors too need to be addressed because one way or another, these factors are a legitimate factors contributing to construction disputes. There are a total of 15 factors identified as causes of construction disputes by clients. The significance of each factors in contributing as a cause of disputes by clients are ranked based on the average index value. The average index was used to determine how much it affected the industry or rather how much it had contributed to the problem. 59 i) Client’s Point of View There are seven numbers of respondents attempted all the questions. The results are illustrated as in the Table 4.8 below. Table 4.8: Client’s point of view Frequency No. Statement 1. Late payment to contractor 2. Changes and variation requirements Poor briefing during design stage 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. Failure to respond in timely manner. Lowest price mentality in engagement of contractors and designers. Unrealistic expectations particularly employers who have insufficient financing to accomplish their objectives Fail to pay variation claim Discrepancies / ambiguities in contract documents Failure to appoint a project manager The absence of team spirit among the participants Interference in the contractual duties of the contract administrator Deficient management, supervision and coordination efforts on the part of the project Changes to standard conditions of contract Inadequate tracing mechanisms for request of information 1 2 3 4 5 Average Index 0 0 0 2 5 4.714 1 0 0 0 3 4 4.571 2 0 0 1 3 3 4.286 3 0 0 1 3 3 4.286 3 0 0 1 4 2 4.143 5 0 0 3 2 2 3.857 6 0 0 4 1 2 3.714 7 0 2 1 2 2 3.571 8 0 2 1 3 1 3.429 9 0 1 2 4 0 3.429 9 0 1 3 3 0 3.286 11 0 2 2 2 1 3.286 11 0 2 2 3 0 3.143 13 0 3 1 2 1 3.143 13 Rank 60 15. Reluctant to check for constructability, clarity and completeness 1 1 2 3 0 3.000 15 Clients are always regarded as the top hierarchy in the construction industry. Hence, client always try to avoid as being the culprit or cause of disputes in construction. Two factors which their average index value is above 4.500 level are considered as very significant to the problem at hand. These factors are late payment to contractor (average index : 4.714) and changes and variation requirement (average index : 4.571). Furthermore, based on the average index analysis, the respondents agree that eight factors are significant to the cause of disputes by clients. The average index value ranges between 3.500 and 4.500 level thus pooled as significant. Looking from the client’s perspective, the top eight significant causes of disputes by client are listed as follows based on their level of significance: ï‚· Late payment to contractor ï‚· Changes and variation requirement ï‚· Poor briefing during design stage ï‚· Failure to respond in timely manner ï‚· Lowest price mentality in engagement of contractors and designers. ï‚· Unrealistic expectations particularly employers who have insufficient financing to accomplish their objectives ii) ï‚· Fail to pay variation claim ï‚· Discrepancies / ambiguities in contract documents Consultant’s Point of View The total of 13 respondents from the consultant profile responds to the questionnaire. Table 4.9 below indicates the results of consultant’s point of view on the causes of disputes by clients. 61 Table 4.9: Consultant’s point of view Frequency No. 1. Statement 2. Changes and variation requirements Late payment to contractor 3. Poor briefing during design stage 4. Unrealistic expectations particularly employers who have insufficient financing to accomplish their objectives Lowest price mentality in engagement of contractors and designers. Discrepancies / ambiguities in contract documents Deficient management, supervision and coordination efforts on the part of the project Inadequate tracing mechanisms for request of information Fail to pay variation claim 5. 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. Failure to respond in timely manner. The absence of team spirit among the participants Interference in the contractual duties of the contract administrator Changes to standard conditions of contract Reluctant to check for constructability, clarity and completeness Failure to appoint a project manager 1 2 3 4 5 Average Index 0 0 0 6 7 4.538 1 0 0 1 5 7 4.462 2 0 0 1 6 6 4.385 3 0 0 3 6 4 4.077 4 0 0 5 5 3 3.846 5 2 0 5 3 3 3.385 6 0 3 4 6 0 3.231 7 2 0 5 5 1 3.231 7 2 2 4 2 3 3.154 9 2 1 5 3 2 3.154 9 2 2 4 4 1 3.000 11 2 2 6 2 1 2.846 12 2 2 6 3 0 2.769 13 3 3 2 5 0 2.692 14 5 3 2 3 0 2.231 15 Rank From the results shown in the table above, it is observed that the result ranges from 4.538 for the highest average index down to 2.231 for the lowest average index. Though the results show wide variation, nevertheless all factors remain as the root cause 62 of construction disputes. Consultants regard changes and variation requirement (average index : 4.538) as a very significant factor as being the cause of disputes by clients. Focus should be given to the factor with average value of exceeding 4.500. However, from the responses, majority of the consultants agree with the five common factors as cause of disputes by the clients. Five factors are listed as significant as the average index lies between 3.500 and 4.500. These factors are shown below in their order of significance: ï‚· Changes and variation requirement. ï‚· Late payment to contractor ï‚· Poor briefing during design stage ï‚· Unrealistic expectation particularly employers who have insufficient financing to accomplish their objectives ï‚· iii) Lowest price mentality in engagement of contractors and designers Contractor’s Point of View Table 4.10 shows the results based on 15 respondents from contractor profile on the causes of disputes caused by the clients. Table 4.10: Contractor’s point of view Frequency No. Statement 1. Late payment to contractor 2. Changes and variation requirements Poor briefing during design stage 3. 4. 5. Lowest price mentality in engagement of contractors and designers. Unrealistic expectations particularly employers who have insufficient financing to 1 2 3 4 5 Average Index Rank 0 0 0 5 10 4.667 1 0 0 0 7 8 4.533 2 0 0 4 6 5 4.067 3 0 0 5 5 5 4.000 4 0 2 5 5 3 3.600 5 63 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. accomplish their objectives Fail to pay variation claim Deficient management, supervision and coordination efforts on the part of the project Inadequate tracing mechanisms for request of information Reluctant to check for constructability, clarity and completeness Failure to respond in timely manner. Discrepancies / ambiguities in contract documents Interference in the contractual duties of the contract administrator Changes to standard conditions of contract The absence of team spirit among the participants Failure to appoint a project manager 1 3 3 5 3 3.400 6 1 2 9 2 1 3.000 7 2 3 5 3 2 3.000 7 2 2 5 6 0 3.000 7 2 4 3 5 1 2.933 10 3 2 5 4 1 2.867 11 1 6 3 4 1 2.867 11 0 8 5 2 0 2.600 13 3 4 5 2 1 2.600 13 4 5 4 1 1 2.333 15 Table 4.10 shows the detail distribution of results from contractor’s point of view on the cause of disputes by clients. The average index resulted within the range of 4.667 down to 2.333. It is observed that two factors are regarded as very significant. Both late payment to contractor with average index of 4.667 and changes and variation requirement with average index of 4.553 are very significant as the cause of construction disputes by client from contractor’s view point. Total of five factors score average index value exceeding 3.500 level and considered as significant. The top five factors listed based on their rank are as follows: ï‚· Late payment to contractor ï‚· Changes and variation requirement ï‚· Poor briefing during design stage ï‚· Lowest price mentality in engagement of contractors and designers 64 ï‚· Unrealistic expectations particularly employers who have insufficient financing to accomplish their objectives. It is interesting to note that both contractor and consultant agreed and shared the view on the significant factors contributing to disputes caused by clients. The five significant factors listed by contractors are observed to be tally with the preceding result listed by consultant. iv) Overall Respondents The overall response on causes of construction disputes by client ranges from very significant to less significance to the problem at hand. This is shown in their average index ranging from 4.600 to 2.514. Inevitably respondents viewed the problem at hand from different view based on their preference and profile. Client observed the matters differently as compared to consultants and the same applies with contractors. This entails that factors affecting different profile in construction industry differs from one another. It also depends on how much that particular factor is affecting that particular profile be it client, consultant or contractor. Table 4.11: Overall Respondents Frequency No. Statement 1. Late payment to contractor 2. Changes and variation requirements Poor briefing during design stage 3. 4. 5. Lowest price mentality in engagement of contractors and designers. Unrealistic expectations particularly employers who have insufficient financing to 1 2 3 4 5 Average Index Rank 0 0 1 12 22 4.600 1 0 0 0 16 19 4.543 2 0 0 6 15 14 4.229 3 0 0 11 14 10 3.971 4 0 2 11 13 9 3.829 5 65 6. 7. 8. 9. 10. 11. 12. 13. 14. 15. accomplish their objectives Fail to pay variation claim Failure to respond in timely manner. Discrepancies / ambiguities in contract documents Deficient management, supervision and coordination efforts on the part of the project Inadequate tracing mechanisms for request of information Interference in the contractual duties of the contract administrator The absence of team spirit among the participants Reluctant to check for constructability, clarity and completeness Changes to standard conditions of contract Failure to appoint a project manager 3 5 11 8 8 3.371 6 4 5 9 11 6 3.286 7 5 4 11 9 6 3.200 8 1 7 15 10 2 3.143 9 4 6 11 10 4 3.114 10 3 9 12 9 2 2.943 11 5 7 11 10 2 2.914 12 6 6 9 14 0 2.886 13 2 12 13 8 0 2.771 14 9 10 7 7 2 2.514 15 The results revealed that the major contributing factor to disputes caused by clients is late payment to contractor from the client (average index : 4.600). This factor is very significant based on overall point of view (average index > 4.500). It affects the progress of the construction and can lead to the inability of the contractor to complete the project which will subsequently results in construction disputes. Changes and variation requirement (average index : 4.543) is the second very significant factor contributing to construction disputes by client. This factor is also regarded as very significant as the contributor to disputes caused by clients. It is then tailed by other factors which are found to be of moderately significant and less significant to the cause of disputes by client as the average index value is below 3.500 level. Followings are the list of top five significant factors observed from overall point of view on causes of disputes by the clients: ï‚· Late payment to contractor 66 ï‚· Changes and variation requirements ï‚· Poor briefing during design stage ï‚· Lowest price mentality in engagement of contractors and designers. ï‚· Unrealistic expectations particularly employers who have insufficient financing to accomplish their objectives 4.3.3 Causes of Construction Disputes by Consultant Being one of the stakeholders under study, consultant is also presupposed to be the culprit of construction disputes. This particular section entails the analysis of the questionnaire concerning the causes of construction disputes by consultant. View from clients, consultants and contractors are gathered to enable a comprehensive analysis on the causes of disputes by consultant. The analysis will focus on the factors with average index of exceeding 4.500 (very significant) and factors with average index score between 3.500 to 4.500 level (significant). Even so, factors scoring average index lower than 3.500 level is regarded as moderately significant, less significant and very insignificant are also under scrutiny as they can be the impetus towards construction dispute caused by consultant . Ten factors were identified as causes of construction disputes by clients. These factors are ranked and sorted based on the level of significance as per responses gathered from the questionnaires. The average index was used to determine how much it affected the industry or rather how much it had contributed to the problem. i) Client’s Point of View 67 There are total of seven questionnaires returned from the client respondent profile. Table 4.12 below indicates the view from the client’s perspective on the causes of disputes contributed by the consultants. Table 4.12: Client’s point of view Frequency No. Statement 1. Late issue of design information/drawing Lack of appropriate competence and experience Over-design and underestimating the costs involved Variations due to design errors 2. 3. 4. 5. 6. 7. 8. 9. 10. Unclear delegation of responsibilities Design and specification oversights, and errors or omissions resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs Incompleteness of drawing and specifications Late information delivery and cumbersome approach to request for information’s Errors/substantial changes in bills of quantities Failure to understand its responsibilities under the design team contract 1 2 3 4 5 Average Index 0 0 0 3 4 4.571 1 0 0 0 4 3 4.429 2 0 0 1 3 3 4.286 3 0 0 2 3 2 4.000 4 0 0 2 3 2 4.000 4 0 0 3 3 1 3.714 6 0 0 3 3 1 3.714 6 0 1 1 5 0 3.571 8 0 0 5 2 0 3.286 9 1 1 1 4 0 3.143 10 Rank Based on the responses from clients as depicted in the table above, the average index scored between 4.571 and 3.143. This implies that client regard eight factors as significant and correspond closely to consultant as the cause of construction disputes. Late issue of design information/drawing is the only factor regarded as very significant to the cause of dispute by consultant (average index > 4.500). Listed below are the top eight 68 ranked factors contributing to construction dispute by consultant from client’s point of view. ï‚· Late issue of design information/drawing ï‚· Lack of appropriate competence and experience ï‚· Over-design and underestimating the costs involved ï‚· Variations due to design errors ï‚· Unclear delegation of responsibilities ï‚· Design and specification oversights, and errors or omissions resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs ï‚· Incompleteness of drawing and specifications ï‚· Late information delivery and cumbersome approach to request for information’s ii) Consultant’s Point of View Looking from the consultant’s point of view, it is observed that consultants tried to apportion the causes of disputes in construction to both contractors and clients. Table 4.13 shows the questionnaire results of causes of disputes by consultants looking from the consultant’s point of view. Table 4.13: Consultant’s point of view Frequency No. 1. 2. 3. Statement Lack of appropriate competence and experience Design and specification oversights, and errors or omissions resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs Late issue of design 1 2 3 4 5 Average Index 0 0 0 6 7 4.538 1 0 0 3 5 5 4.154 2 0 0 5 5 3 3.846 3 Rank 69 4. 5. 6. 7. 8. 9. 10. information/drawings Over-design and underestimating the costs involved Variations due to design errors Incompleteness of drawing and specifications Late information delivery and cumbersome approach to request for information’s Failure to understand its responsibilities under the design team contract Errors/substantial changes in bills of quantities Unclear delegation of responsibilities 0 1 4 6 2 3.692 4 0 1 7 3 2 3.462 5 0 3 4 4 2 3.385 6 0 4 5 2 2 3.154 7 1 3 4 4 1 3.077 8 1 3 5 3 1 3.000 9 2 5 2 4 0 2.615 10 Based on the result above, factors of disputes by consultant from the consultant’s point of view are observed to be of the range from as high as 4.538 down to 2.615. As consultant tend to allot the cause of disputes to other stakeholders, only four factors are observed as being significant from the consultant’s point of view. The top four ranked factors with average value more than 3.500 are listed based on the level of significance are as follows: ï‚· Lack of appropriate competence and experience ï‚· Design and specification oversights, and errors or omissions resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs iii) ï‚· Late issue of design information/drawings ï‚· Over-design and underestimating the costs involved Contractor’s Point of View 70 Responses from 15 respondents from contractor profile are shown in Table 4.14. This is with regards from the contractor’s perspective on the disputes caused by consultants. Table 4.14: Contractor’s point of view Frequency No. Statement 1. Over-design and underestimating the costs involved Lack of appropriate competence and experience Design and specification oversights, and errors or omissions resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs Late issue of design information/drawings Errors/substantial changes in bills of quantities Variations due to design errors 2. 3. 4. 5. 6. 7. 8. 9. 10. Incompleteness of drawing and specifications Late information delivery and cumbersome approach to request for information’s Failure to understand its responsibilities under the design team contract Unclear delegation of responsibilities 1 2 3 4 5 Average Index Rank 0 0 0 5 10 4.667 1 0 0 0 8 7 4.467 2 0 0 2 7 6 4.267 3 0 0 3 6 6 4.200 4 0 0 3 6 6 4.200 4 0 0 4 6 5 4.067 6 0 0 5 8 2 3.800 7 0 1 8 3 3 3.533 8 1 4 6 2 2 3.000 9 3 4 3 4 1 2.733 10 Based on the result represented in the table above, contractors rated the ten factors contributing to construction disputes caused by consultant in between 4.667 and 2.733 level. Consultants and contractors are always regarded as the parties that are closely dealing with each other during the construction period. Concerning disputes caused by 71 consultant, both parties agreed on the top four ranked factors as also shown in the preceding result. However, from contractor’s point of view on the construction disputes caused by consultant, there are eight factors scores above 3.500 level which is considered as significant to the subject matter. These factors are listed as follows: ï‚· Over-design and underestimating the costs involved ï‚· Lack of appropriate competence and experience ï‚· Design and specification oversights, and errors or omissions resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs ï‚· Late issue of design information/drawings ï‚· Errors/substantial changes in bills of quantities ï‚· Variations due to design errors ï‚· Incompleteness of drawing and specifications ï‚· Late information delivery and cumbersome approach to request for information’s iv) Overall Respondents Overall views of the construction disputes caused by consultants are shown in Table 4.15 below. Table 4.15: Overall Respondents Frequency No. Statement 1. Lack of appropriate competence and experience Over-design and underestimating the costs involved Late issue of design information/drawings Design and specification oversights, and errors or 2. 3. 4. 1 2 3 4 5 Average Index Rank 0 0 0 18 17 4.486 1 0 1 5 14 15 4.229 2 0 0 8 14 13 4.143 3 0 0 8 15 12 4.114 4 72 5. 6. 7. 8. 9. 10. omissions resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs Variations due to design errors Incompleteness of drawing and specifications Errors/substantial changes in bills of quantities Late information delivery and cumbersome approach to request for information’s Failure to understand its responsibilities under the design team contract Unclear delegation of responsibilities 0 1 13 12 9 3.829 5 0 3 12 15 5 3.629 6 1 3 13 11 7 3.571 7 0 6 14 10 5 3.400 8 3 8 11 10 3 3.057 9 5 9 7 11 3 2.943 10 The result shows that the average index ranges from 4.486 to 2.943. This indicates that overall perception of client, contractor and consultant differ from one another. However all off the stakeholders seems to agree that the top seven factors listed are of significant as the average index is more than 3.500 level. Nonetheless, all of these factors, if not carefully dealt with will subsequently lead to construction disputes. Followings are the top seven significant factors, from overall point of view concerning construction disputes caused by consultant. ï‚· Lack of appropriate competence and experience ï‚· Over-design and underestimating the costs involved ï‚· Late issue of design information/drawings ï‚· Design and specification oversights, and errors or omissions resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs ï‚· Variations due to design errors ï‚· Incompleteness of drawing and specifications ï‚· Errors/substantial changes in bills of quantities 73 Nevertheless, factors such as late information delivery and cumbersome approach to request for information’s, failure to understand its responsibilities under the design team contract and unclear delegation of responsibilities are regarded as vague area of responsibility between contractor, consultant and client which scored less than 3.500 are ranked as less significant contributor to construction disputes caused by consultants seen from overall perspective. 4.3.4 Causes of Construction Disputes by Contractor It is always believed that contractors are the main culprit in dispute causation in construction industry. Hence, this following section presents the analysis of the questionnaire in relation to the issue of construction disputes caused by contractors. Feedbacks from each stakeholder profile namely clients, consultants and contractors are taken into account to understand the real problem at hand. The analysis is carried out by assigning rank to each factor in view of their average index value. Factors that are very significant (average index of exceeding 4.500) and factors that are significant (average index between 3.500 to 4.500) are the main focus and need to be emphasized to minimize disputes in construction industry. Nevertheless, factors with average index lower than 3.500 level is regarded as moderately significant, less significant and insignificant still need to be highlighted as mutual root cause on the issue of construction dispute caused by consultant. Total of 12 factors acknowledged as causes of construction disputes by contractors. The factors are ranked based on their level of significance according to the average index value. The average index was used to determine how much it affected the industry or rather how much it had contributed to the problem. i) Client’s Point of View 74 There are seven respondents from the client profile involves in the questionnaire survey. Table 4.16 depicts the responses for the causes of construction disputes by contractor from the client’s point of view. Table 4.16: Client’s point of view Frequency No. Statement 1 2 3 4 5 Average Index Rank 1. Delay/ suspension of works 0 0 0 1 6 4.857 1 2. Poor standard of work 0 0 0 2 5 4.714 2 Poor planning and program Fails to proceed works in a competent manner Inadequate site management Delayed payment to subcontractors Inadequate CPM scheduling and update requirements Failure to understand and correctly bid or price the works Lack of understanding and agreement in contract procurement Failure to coordinate its subcontractors’ work through effective and timely exchange of shop drawings Failure to plan and execute the changes of works Reluctance to seek clarification 0 0 0 4 3 4.429 3 0 0 0 4 3 4.429 3 0 0 1 3 3 4.286 5 0 0 2 1 4 4.286 5 0 0 1 4 2 4.143 7 0 0 3 1 3 4.000 8 0 0 3 2 2 3.857 9 0 1 2 3 1 3.571 10 0 1 3 1 2 3.571 10 0 0 5 1 1 3.429 12 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. The results indicated in the table above shows the responses from client’s perspective on the causes of disputes by contractor. There are 12 factors listed as related to disputes caused by contractor. Clients seem to infer that 11 out of 12 factors of construction disputes under study as significantly related to contractors as the average index value are more than 3.500. The top two factors resulted as very significant to 75 construction dispute caused by contractors. The average index result soar above 4.500 level. Listed below are the 11 significant factors of dispute caused by contractor from client’s point of view. ï‚· Delay/ suspension of works ï‚· Poor standard of work ï‚· Poor planning and program ï‚· Fails to proceed works in a competent manner ï‚· Inadequate site management ï‚· Delayed payment to subcontractors ï‚· Inadequate CPM scheduling and update requirements ï‚· Failure to understand and correctly bid or price the works ï‚· Lack of understanding and agreement in contract procurement ï‚· Failure to coordinate its subcontractors’ work through effective and timely exchange of shop drawings ï‚· ii) Failure to plan and execute the changes of works Consultant’s Point of View The result on table 4.17 represents the responses from the consultant’s view point on the causes of disputes by the Contractor. Table 4.17: Consultant’s point of view Frequency No. Statement 1 2 3 4 5 Average Index Rank 1. Delay/ suspension of works 0 0 0 2 11 4.846 1 2. Poor standard of work 0 0 0 4 9 4.692 2 3. Inadequate site management 0 0 0 5 8 4.615 3 4. Poor planning and program 0 0 0 6 7 4.538 4 76 5. 6. 7. 8. 9. 10. 11. 12. Fails to proceed works in a competent manner Inadequate CPM scheduling and update requirements Failure to coordinate its subcontractors’ work through effective and timely exchange of shop drawings Delayed payment to subcontractors Failure to plan and execute the changes of works Reluctance to seek clarification Failure to understand and correctly bid or price the works Lack of understanding and agreement in contract procurement 0 0 2 7 4 4.154 5 0 0 3 6 4 4.077 6 0 0 5 4 4 3.923 7 0 0 6 4 3 3.769 8 0 0 8 2 3 3.615 9 0 2 4 6 1 3.462 10 0 3 5 3 2 3.308 11 0 5 4 3 1 3.000 12 The responses from consultant shows that top four causes of disputes by contractor are related to the management of the project during construction namely delay/suspension of works, poor standard of works, inadequate site management, poor planning and program and fails to proceed works in competent manner. These factors are rated as very significant as the average index value is more than 4.500. However, from the consultant’s point of view, there are total of nine factors which scores above 3.500 for the average index. These factors are considered of being significant to the problem at hand and need to be emphasized to minimize or avoid construction disputes. Listed below are the top four very significant factors followed by five significant factors of disputes caused by contractor from consultant’s point of view. ï‚· Delay/ suspension of works ï‚· Poor standard of work ï‚· Inadequate site management ï‚· Poor planning and program ï‚· Fails to proceed works in a competent manner ï‚· Inadequate CPM scheduling and update requirements 77 ï‚· Failure to coordinate its subcontractors’ work through effective and timely exchange of shop drawings ï‚· Delayed payment to subcontractors ï‚· Failure to plan and execute the changes of works iii) Contractor’s Point of View A total of 15 respondents from contractor profile attempted the questionnaires. Table 4.18 shows the result of contractor’s point of view on the cause of disputes by contractors. Table 4.18: Contractor’s point of view Frequency 1 2 3 4 5 Average Index Delay/ suspension of works Failure to coordinate its subcontractors’ work through effective and timely exchange of shop drawings Poor planning and program 0 0 0 8 7 4.467 1 0 0 1 7 7 4.400 2 0 0 1 7 7 4.400 2 Poor standard of work Fails to proceed works in a competent manner Inadequate site management Inadequate CPM scheduling and update requirements Delayed payment to subcontractors Lack of understanding and agreement in contract procurement Failure to understand and correctly bid or price the works Failure to plan and execute the changes of works 0 0 5 5 5 4.000 4 0 0 5 5 5 4.000 4 0 1 4 6 4 3.867 6 0 3 6 4 2 3.333 7 0 5 4 4 2 3.200 8 1 2 7 3 2 1 4 5 4 1 3.000 10 1 5 6 2 1 2.800 11 No. Statement 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 3.200 Rank 8 78 12. Reluctance to seek clarification 1 5 8 1 0 2.600 12 Contractors tried to condone that they are the major contributors to construction disputes. From the contractor’s point of view, clients and consultants are also the culprit of construction disputes. Table 4.18 illustrates the factors contributing to construction disputes by contractors observing from the contractor’s point of view. The result shows that contractors agree to only six factors are that are considered as significant to the cause of disputes by contractors. These factors scores exceeding 3.500 level for the average index. However, as expected there is no factor regarded as very significant by the contractors to the subject matter as no average index value exceeding 4.500 recorded. This shows that contractors try to rebuff that they are the cause of construction dispute. Followings are the top six significant factors listed based on their level of significance. ï‚· Delay/ suspension of works ï‚· Failure to coordinate its subcontractors’ work through effective and timely exchange of shop drawings ï‚· Poor planning and program ï‚· Poor standard of work ï‚· Fails to proceed works in a competent manner ï‚· Inadequate site management iv) Overall Respondents The overall respondent’s results shown in Table 4.19 summarize the overall view from consultant, client and contractors on the disputes caused by the contractor. Table 4.19: Overall Respondents Frequency No. Statement 1 2 3 4 5 Average Rank 79 Index 1. Delay/ suspension of works 0 0 0 11 24 4.686 1 2. Poor planning and program 0 0 1 17 17 4.457 2 3. Poor standard of work Inadequate site management 0 0 5 11 19 4.400 3 0 1 5 14 15 4.229 4 0 0 7 16 12 4.143 5 0 1 8 14 12 4.057 6 0 3 10 14 8 3.771 7 0 5 12 9 9 3.629 8 1 7 13 8 6 3.314 9 1 7 14 8 5 3.257 10 1 6 17 5 6 3.257 10 1 7 17 8 2 3.086 12 4. 5. 6. 7. 8. 9. 10. 11. 12. Fails to proceed works in a competent manner Failure to coordinate its subcontractors’ work through effective and timely exchange of shop drawings Inadequate CPM scheduling and update requirements Delayed payment to subcontractors Failure to understand and correctly bid or price the works Lack of understanding and agreement in contract procurement Failure to plan and execute the changes of works Reluctance to seek clarification Table 4.19 shows the overall view from all stakeholders regarding disputes caused by contractors. From the average index value analysis, we can deduce that all stakeholders agrees on the top eight factors as significant to the problem at hand with average index value surpass 3.500 level. On top of that, only one single factor agreed by clients, consultants and contractors as very significant to the cause of disputes by contractor which is delay or suspension of works. This factor scores an average value of 4.686 which is above 4.500 thus considered as very significant. The followings are top eight significant factors of disputes by contractors from stakeholder’s perspective: ï‚· Delay/ suspension of works ï‚· Poor planning and program 80 ï‚· Poor standard of work ï‚· Inadequate site management ï‚· Fails to proceed works in a competent manner ï‚· Failure to coordinate its subcontractors’ work through effective and timely exchange of shop drawings ï‚· Inadequate CPM scheduling and update requirements ï‚· Delayed payment to subcontractors Inevitably factors that score below 3.500 on average index analysis which is regarded as moderately significant still need to be put in view as these factors in one way or another may also lead to construction disputes. It is observed that these factors are of pre-construction in nature. Listed below are the factors which are moderately significant to the subject matters. ï‚· Failure to understand and correctly bid or price the works ï‚· Lack of understanding and agreement in contract procurement ï‚· Failure to plan and execute the changes of works ï‚· Reluctance to seek clarification 4.3.5 The Effect of Disputes to Stakeholders in the Construction Industry Undeniably construction disputes have an impact on all stakeholders that can be classified in terms of project deliverables, financial impact, project quality, human resources and also relationship between the stakeholders. The effects of construction disputes on stakeholders are analyzed based on the questionnaires responses. These responses taking into account views from all stakeholders’ profile. There are 13 effects identified and become the subject of study. The analyses are carried out by raking out the effects according to the average index value accordingly. It is unavoidable that disputes may arise in the construction industry. Nonetheless disputes that are of minor in nature can be settled impartially, harmoniously and quickly to move forward to the larger objective of performing the physical construction effectively. 81 i) Client’s Point of View Table 4.20: Client’s point of view Frequency No. Statement 1. Delay to the project completion Increase in time-related costs (such as idled equipment rental costs, changes in building materials price, bank interest, utilities charges and insurance) Effects on the costs or economics of the projects, as well as the financial returns of construction parties effort and investments Affects the quality of product to be delivered Lost of productivity and efficiency (idled labor and equipment) Abandonment of project and termination of contract Additional financial costs especially high cost of litigation Cost for a deposition, trial or arbitration preparation Diversion of manpower away from the project costs Third party claims, due to damages for delay to construction projects which affect them. Damage to reputation of the parties involved Cause job stress (emotional costs) to parties involved A reduction in bonding capacity 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 1 2 3 4 5 Average Index 0 0 0 1 6 4.857 1 0 0 0 2 5 4.714 2 0 0 1 1 5 4.571 3 0 0 3 4 4.571 3 0 0 2 2 3 4.143 5 0 0 2 3 2 4.000 6 0 0 2 3 2 4.000 6 0 0 3 2 2 3.857 8 0 1 3 3 0 3.286 9 0 1 4 1 1 3.286 9 0 2 2 2 1 3.286 9 0 2 3 2 0 3.000 12 0 2 4 1 0 2.857 13 Rank 82 in business Table 4.20 above shows the result gathered from the client’s point of view on the effect of construction disputes to the construction industry. Clients rated four major effects of construction disputes as very significant. These effects are classified based on their average index value of exceeding 4.500 level and considered as a very significant effect to construction industry. The effects of disputes to the industry are listed as follows according to the level of significance. ï‚· Delay to the project completion ï‚· Increase in time-related costs (such as idled equipment rental costs, changes in building materials price, bank interest, utilities charges and insurance) ï‚· Effects on the costs or economics of the projects, as well as the financial returns of construction parties effort and investments ï‚· Affects the quality of product to be delivered Subsequently, out of 13 effects identified, trailing the very significant effect discussed above, four are found to be only as the significant effect of construction disputes to the construction industry from the client’s point of view. These effects scores average index value hovering between 3.500 to 4.500 level. Followings are the significant effect of disputes to constriction industry. ii) ï‚· Cost for a deposition, trial or arbitration preparation ï‚· Lost of productivity and efficiency (idled labor and equipment) ï‚· Abandonment of project and termination of contract ï‚· Additional financial costs especially high cost of litigation ï‚· Cost for a deposition, trial or arbitration preparation Consultant’s Point of View 83 Table 4.21 shows the responses from 13 respondents from consultant profile. Table 4.21: Consultant’s point of view Frequency No. Statement 1. Delay to the project completion Lost of productivity and efficiency (idled labor and equipment) Affects the quality of product to be delivered Effects on the costs or economics of the projects, as well as the financial returns of construction parties effort and investments Increase in time-related costs (such as idled equipment rental costs, changes in building materials price, bank interest, utilities charges and insurance) Additional financial costs especially high cost of litigation Diversion of manpower away from the project costs Cost for a deposition, trial or arbitration preparation Abandonment of project and termination of contract Third party claims, due to damages for delay to construction projects which affect them. Damage to reputation of the parties involved A reduction in bonding capacity in business Cause job stress (emotional costs) to parties involved 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 1 2 3 4 5 Average Index 0 0 1 2 10 4.692 1 0 0 1 3 9 4.615 2 0 0 1 4 8 4.538 3 0 0 1 4 8 4.538 3 0 0 1 6 6 4.385 5 0 0 2 5 6 4.308 6 0 0 2 7 4 4.154 7 0 0 3 6 4 4.077 8 0 3 3 2 5 3.692 9 0 0 7 3 3 3.692 9 1 2 5 5 0 3.077 11 1 3 4 5 0 3.000 12 1 4 4 4 0 2.846 13 Rank 84 Based on the result depicted in Table 4.20 above, consultants rated four effects of disputes under study as very significant as these effects exceeding 4.500 level for the average index value. This result shows that consultants agreed with clients on the top most effect which is delay to the project completion as a very significant effect of construction disputes. Listed below are the four very significant effects of disputes from consultant’s perspective. ï‚· Delay to the project completion ï‚· Lost of productivity and efficiency (idled labor and equipment) ï‚· Affects the quality of product to be delivered ï‚· Effects on the costs or economics of the projects, as well as the financial returns of construction parties effort and investments On top of that, based on the questionnaires answered by the consultants, the result shows that the following six effects are regarded as significant effect of construction disputes. ï‚· Increase in time-related costs (such as idled equipment rental costs, changes in building materials price, bank interest, utilities charges and insurance) ï‚· Additional financial costs especially high cost of litigation ï‚· Diversion of manpower away from the project costs ï‚· Cost for a deposition, trial or arbitration preparation ï‚· Abandonment of project and termination of contract ï‚· Third party claims, due to damages for delay to construction projects which affect them. This is then tailed by three effects under study listed by the consultant as moderately significant as an effect of construction disputes to the construction industry. These effects are seen as more towards human relation in nature. ï‚· Damage to reputation of the parties involved 85 ï‚· A reduction in bonding capacity in business ï‚· Cause job stress (emotional costs) to parties involved iii) Contractor’s Point of View Table 4.22: Contractor’s point of view Frequency No. 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. Statement Delay to the project completion Effects on the costs or economics of the projects, as well as the financial returns of construction parties effort and investments Lost of productivity and efficiency (idled labor and equipment) Diversion of manpower away from the project costs Increase in time-related costs (such as idled equipment rental costs, changes in building materials price, bank interest, utilities charges and insurance) Affects the quality of product to be delivered Abandonment of project and termination of contract Additional financial costs especially high cost of litigation Cost for a deposition, trial or arbitration preparation Third party claims, due to damages for delay to construction projects which affect them. Cause job stress (emotional costs) to parties involved 1 2 3 4 5 Average Index Rank 0 0 1 2 12 4.733 1 0 0 0 6 9 4.600 2 0 0 2 2 11 4.600 2 0 0 1 5 9 4.533 4 0 0 3 5 7 4.267 5 0 0 3 6 6 4.200 6 0 0 4 4 7 4.200 6 0 0 5 5 5 4.000 8 0 1 7 5 2 3.533 9 1 2 6 2 4 3.400 10 1 2 7 2 3 3.267 11 86 12. 13. A reduction in bonding capacity in business Damage to reputation of the parties involved 1 4 6 3 1 2.933 12 2 4 4 5 0 2.800 13 It is interesting to note that from the Table 4.22 above, contractor rated delay to project completion is the most significant effect of disputes to the construction industry. This fact fully supports the responses given by both clients and consultants in the earlier Table 4.20 and Table 4.21. Listed below are four very significant effects of construction disputes with reference to contractor’s point of view. These effects posted an average index value exceeding 4.500 level. ï‚· Delay to the project completion ï‚· Effects on the costs or economics of the projects, as well as the financial returns of construction parties effort and investments ï‚· Lost of productivity and efficiency (idled labor and equipment) ï‚· Diversion of manpower away from the project costs Subsequently, the result shows that consultant rated the following five effects under study as significant to the effect of construction disputes. Generally, contractor regards financial impacts on the project and quality of the works as significant with average index value lies between 3.500 to 4.500. Listed below are the significant effects of construction disputes from consultant’s point of view. ï‚· Increase in time-related costs (such as idled equipment rental costs, changes in building materials price, bank interest, utilities charges and insurance) iv) ï‚· Affects the quality of product to be delivered ï‚· Abandonment of project and termination of contract ï‚· Additional financial costs especially high cost of litigation ï‚· Cost for a deposition, trial or arbitration preparation Overall Respondents 87 The overall result gathered from all stakeholders are listed and sorted in Table 4.23 below. Table 4.23: Overall Respondents Frequency No. Statement 1. Delay to the project completion Effects on the costs or economics of the projects, as well as the financial returns of construction parties effort and investments Lost of productivity and efficiency (idled labor and equipment) Affects the quality of product to be delivered Increase in time-related costs (such as idled equipment rental costs, changes in building materials price, bank interest, utilities charges and insurance) Diversion of manpower away from the project costs Additional financial costs especially high cost of litigation Abandonment of project and termination of contract Cost for a deposition, trial or arbitration preparation Third party claims, due to damages for delay to construction projects which affect them. Cause job stress (emotional costs) to parties involved Damage to reputation of the parties involved 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 1 2 3 4 5 Average Index 0 0 2 5 28 4.743 1 0 0 2 11 22 4.571 2 0 0 5 7 23 4.514 2 0 0 4 13 18 4.400 4 0 0 4 13 18 4.400 4 0 1 6 15 13 4.143 6 0 0 9 13 13 4.114 7 0 3 9 9 14 3.971 8 0 1 13 13 8 3.800 9 1 3 17 6 8 3.486 10 2 8 14 8 3 3.057 11 3 8 11 12 1 3.000 12 Rank 88 13. A reduction in bonding capacity in business 2 9 14 9 1 2.943 13 Table 4.23 shows the cumulative thoughts from clients, consultants and contractors point of view on the effect of construction disputes on the construction industry. Base on the results above, all stakeholders agreed that the whole 13 effects under study are rated as moderately significant, significant and very significant effect of disputes to the construction industry. This is shown in their average index which scores above 2.500 level. None of the effect under study is regarded as less significant or insignificant (average index < 2.500). Top three effects which score an average index exceeding 4.500 level are observed as a very significant effect of construction disputes. It covers the issue of deliverables of the project in terms of meeting the completion date, overall impact on the financial issue and efficiency of the resources. List of very significant effect of construction disputes are as follows. ï‚· Delay to the project completion ï‚· Effects on the costs or economics of the projects, as well as the financial returns of construction parties effort and investments ï‚· Lost of productivity and efficiency (idled labor and equipment) This is then subsequently followed by effects that scores average index ranging between 3.500 and 4.500. These factors are lumped as significant effect of disputes to the industry. Out of five effects regarded as significant, four effects are directly related to financial impact on the stakeholders. Inevitably shareholders are more sensitive towards the effects that are of financial in nature. Followings are the details on the effect of disputes to the construction industry from overall point of view. ï‚· Increase in time-related costs (such as idled equipment rental costs, changes in building materials price, bank interest, utilities charges and insurance) ï‚· Diversion of manpower away from the project costs 89 ï‚· Additional financial costs especially high cost of litigation ï‚· Abandonment of project and termination of contract ï‚· Cost for a deposition, trial or arbitration preparation Nonetheless, factors listed below are clustered together as moderately significant effect of construction disputes. Though these factors are considered as only moderately significant, they still carried some weight to the effect of construction disputes and worth looking into. Somehow or other, these effects would pinch the stakeholders and bring in negative impact to the construction industry. General view of the effects listed below suggests that these effects are inclined towards human resources related issues such as job stress, reputation and bonding. Details of moderately significant effect of disputes to construction industry are as follows. ï‚· Third party claims, due to damages for delay to construction projects which affect them. ï‚· Cause job stress (emotional costs) to parties involved ï‚· Damage to reputation of the parties involved ï‚· A reduction in bonding capacity in business 4.3.6 Disputes Avoidance in Construction Industry In general dispute can be avoided or minimised the least by employing certain or a set of dispute avoidance activities. Among the activities that had been proposed or identified in various literatures included the following: i) Early negotiation ii) Pre-contract reviews iii) Risk audits iv) Training v) Compliance audits 90 vi) Better planning vii) Partnering approach viii) Allocation of risks ix) Proper selection of contracts Within the context of this particular study, three parameters were tested on respondents regarding this matter. These parameters included: i) Respondents awareness or knowledge regarding several disputes avoidance methods or approaches that have been implemented elsewhere (such as in the United Kingdom). The irony of this parameter is to coarsely visualized construction industry participants knowledge on several suggested approach in avoiding disputes, and their alertness on the options available to them in avoiding disputes. Bear in mind that, that the most successful are usually those who keep themselves always up-to-date with the current knowledge and practices. ii) Respondents practise of several disputes avoidance methods or approaches that have been implemented elsewhere, and of which they are aware or have knowledge of. This parameter is essentially to coarsely visualized construction industry participants, level of adoption of the disputes avoidance approaches that they are aware of. The philosophical idea of this parameter is that – Those who practice knows better than those who merely preach. iii) Respondents success in avoiding disputes based on their real time experience applying these disputes avoidance approaches within their respective trades. This is essentially to review the real time effectiveness of these suggested dispute avoidance approaches that have been experienced by respondents. 91 The elaborate response as gathered from the questionnaires from the respondents were transformed into percentage count respective of each groups as well as the cumulative percentage of all respondents from all these groups. The following formula was used to obtained the percentage value: Assume; X = Respondents indicating YES as their answer NX = Number of respondents indicating YES as their answer Y = Respondents indicating NO as their answer NY = Number of respondents indicating NO as their answer Therefore; % X = [NX / (NX + NY)] × 100% These responses are represented for ease through the use of bar charts as shown in Figure 4.4 - 4.8. From the study conducted, it was obvious that majority of the respondents are either aware or have been practising certain or a set of dispute avoidance activities and this is evident since about 88% of the total respondents who filled and returned the survey questionnaire, answered the questions regarding this matter. Figure 4.4: Respondents Awareness on Several Disputes Approach 92 Respondents Awareness on Several Dispute Avoidance Approach % Respondents 100 Clients Only 90 Consultants Only 80 Contractors Only 70 All Respondents 60 50 40 30 20 10 0 Early Pre-contract Risk Audits Negotiation reviews Training Compliance Audits Proper Contract Selection Type of Dispute Avidance Approach Figure 4.5: Respondents Practise of Several Disputes Avoidance Approach Respondents Practise of Several Disputes Avoidance Approach % Respondents 100 Clients Only 90 Consultants Only 80 Contractors Only 70 All Respondents 60 50 40 30 20 10 0 Early Negotiation Precontract reviews Risk Audits Training Compliance Audits Type of Dispute Avoidance Approach Proper Contract Selection 93 Figure 4.6: Respondents Success in Avoiding Disputes by Practising Several Disputes Avoidance Approach Respondents Success in Avoiding Disputes by Practising Several Dispute Avidance Approach % Respondents 100 90 80 Clients Only 70 Consultants Only 60 Contractors Only 50 All Respondents 40 30 20 10 0 Early Pre-contract Risk Audits Negotiation reviews Training Compliance Audits Proper Contract Selection Type of Dispute Avoidance Approach i) Early Negotiation Based on the survey conducted, 83% of the respondents were aware that early negotiation can be employed to avoid disputes, while the remaining was not aware of it. Of those whom are aware of it, only 79% are actually practising early negotiation to avoid disputes. Of these, clients seem to be practising it the most, while contractors the least, of the three groups surveyed. In terms of the result of practising early negotiations, 78% of those who practise it agree that it helps them in avoiding disputes. ii) Pre-contract Reviews The result from the survey, showed that Pre-contract reviews is a dispute avoiding activity, which respondents are most familiar with, whereby 89% respondents indicated that they were aware of it. All the clients that responded indicated their awareness of this approach, while only 80% of the contractors have the awareness on the use of pre- 94 contract reviews in avoiding disputes. Although, most of the respondents are aware of this method, only 68% of them actually practise it, of which consultants practise it the most and contractors the least. In percentage terms only slightly more than half (58%) of the contractors actually practise it. Of those who are aware of it, 76% agreed that precontract reviews does helps them to avoid disputes, and consultants was the group that that benefited the most by this method, while surprisingly clients was the least benefited by this method. iii) Risk Audits Of all the disputes avoidance method presented in the survey, conducting risk audits was the second least method that respondents are aware of, whereby only 77% are aware of it’s benefit in avoiding disputes. Similar to the former, clients was the group that was most aware of this method, and similarly contractors the least. Furthermore, only 59% of those whom are aware of this method actually practise it. Clients were the most that practise it while again contractors were the least. However, those who conducted risk audits indicated that this method seems to significantly give positive results in terms of its ability to avoid disputes whereby 88% of those whom practise it successfully avoided disputes as far as their response was concerned. Surprisingly all those contractors whom had practised this method indicated its success in avoiding disputes, while for clients this method might not suit them fully as only 75% of the clients actually benefited from this method. iv) Training Providing continuous training for human resources is one of the method which most respondents are seems to be well aware of. Of this, consultants were the group which was most aware of this method, while contractor was the least. However, only 73% of those whom are aware actually implemented or provided continuous training for their human resources. Both consultants and contractors whom are aware of the importance of continuous training were equally the most active in this matter, while client 95 was the least. In terms of its success in avoiding disputes, 77% of the respondents that employed continuous training for their human resources acknowledged its effectiveness in avoiding disputes. Surprisingly all clients whom applied this approach acknowledged its effectiveness in avoiding disputes. However, this approach does not seems to benefit contractors greatly, since only 67% of those whom practised this approach obtained positive results in terms of avoiding disputes. v) Compliance Audits On compliance audits, 80% of the respondents indicated their awareness on this approach in avoiding disputes. All clients whom responded indicated their awareness, while contractors were the group that showed the least awareness. Of those whom were aware of this approach, only 71% had implemented or used this approach, of which clients was the group which showed the greatest adoption of this approach as compared to the other groups, while contractors adopted or implemented it the least as far as the percentage counts showed. In terms of its effectiveness in avoiding disputes, only 70% of those whom implemented it considered it as effective. Most (83%) of clients acknowledged the effectiveness of this approach in avoiding disputes. However, only 50% of those contractors whom had implemented this approach acknowledge its effectiveness, while the other half does not think that this approach is effective in their quest to avoid disputes. vi) Proper Selection of Contracts It was also suggested in certain literatures that the simplest method of dispute avoidance can be adopted as early as when anything had not happen yet, that is during the contract selection stage. The irony of this method is that, only contracts which are feasible and possible with the least if not zero risks of problems at all are selected to be undertaken. In relations with this study, most (85%) of those respondents whom are involved in construction contracts procurements indicated their awareness of the potential use of this approach in avoiding disputes. However, only 48% of those whom are aware 96 of it actually adopted this approach in their effort to avoid disputes. Clients seem to be adopting it actively (80%) as compared to both consultants (33%) and contractors (44%) respectively. In terms of its effectiveness in avoiding disputes, only 64% of those whom adopted this approach seem to agree on it effectiveness and contractors agreed the most (75%) on its effectiveness while clients were the least (50%). The possible reason that most contactors acknowledged its effectiveness in avoiding disputes might be due to the fact that contractors are usually the one that had to bear most of the risks in construction projects, which makes them vulnerable towards encountering potentially disputable circumstances. Therefore, by adopting proper selection of contracts, contractors can properly study their options and feasibility before undertaking any projects. This may present them with the chance to avoid undertaking construction projects that are too risky or beyond their realistic ability to deliver. 4.3.6.1 Management Role in Avoiding Disputes Such had been discussed in various literatures as well previous studies by others, the role of individuals or teams that are involved in the management of construction projects is significantly essential in avoiding disputes. Manager needs to think, decide and implement policies, business plan and strategies that may enable disputes to be avoided. Among the approach as suggested in various literatures, that required active participation on the management part included; better and thorough planning; partnering approach; and risks allocation among construction projects participants. 97 Figure 4.7: Management Practise on Several Disputes Avoidance Approach Management Practise on Several Disputes Avoidance Approach % Respondents 100 90 80 70 Clients Only 60 Consultants Only 50 Contractors Only 40 All Respondents 30 20 10 0 Better and thorough Partnering approach Risk allocation planning Type of Dispute Avoidance Approach Figure 4.8: Management Success in Avoiding Disputes by Practising Several Disputes Avoidance Approach Management Success in Avoiding Disputes by Practising Several Disputes Avoidance Approach % Respondents 100 90 80 70 60 Clients Only 50 Consultants Only 40 Contractors Only 30 All Respondents 20 10 0 Better and thorough planning Partnering approach Risk allocation Type of Dispute Avoidance Approach 98 i) Better and Thorough Planning of Construction Projects Based on the response collected from the survey, most (78%) of the respondents that are involved in the management of construction projects indicated that they had adopted this approach in construction projects that they undertook. Contractors seems to be the group that was most active (83%) in adopting this approach, while clients was the least active (67%) in pursuing this approach. However, it should be noted that the number of respondents in the clients group that are involved in the management of construction projects are fairly small (as far as this survey was concerned) as compared to those who had responded from the contractors group, thus the small percentage value might not reflect the true adoption of the real population of clients of construction projects in general. In terms of its effectiveness, 90% of the respondents whom are involved in the management and adopted this approach, acknowledged the effectiveness of this approach in avoiding disputes in the construction projects that they undertook. All of the clients and consultants that responded agreed to the effectiveness of this approach, while only 80% of the contractors agreed. However, since the number of respondents coming from the clients side is relatively smaller as compared to both the consultants and contractors group, therefore the 100% agreement coming from the clients side may still be disputed. But as whole, better and thorough planning is still significantly important in part of the management for the purpose of avoiding disputes. ii) Partnering Approach Regarding the partnering approach, response from the survey indicated that this was the least practised or adopted approach in avoiding disputes. Only 44% of the respondents whom are involved in the management of construction projects actually adopted this approach. Only 50% of the respondents that are involved in the management of construction projects from the contractors group adopted this approach, and this was actually the highest percentage among the three groups comparatively, whereby both clients and consultants showed an even lower percentage of adaptation of this approach. The reason for this sporadic lack of partnering among participants of construction 99 projects might be too many and maybe too complex to be pinpointed within this work, but several possible reasons that are suggested included; incoherent interest and business objectives fuelled by business competition; lack of trusts; ineffective communications and negotiation skills; non-symbiotic interactions among participants and industry players; and, human ego. Although this approach was the least practised by all, it instead seems to be the most effective approach in avoiding disputes, whereby all of the respondents who practised it regardless of which groups, considered it to be effective in avoiding disputes. It is suggested that the reason for this, might be that partnering provides a platform to which participants or partners can stand side by side in planning, implementing and coordinating works, processes and procedures in relation with the projects undertaken, as well as providing a healthy, transparent and coherent platform for resolving issues regarding projects that are undertaken by the partnership, thus potentially avoiding disputes from emerging. iii) Risk Allocation From the survey conducted, 74% of the respondents that are involved in the management of construction projects adopted the risks allocation approach in managing and implementation of the construction projects being undertaken. This approach seems to be adopted mainly (75%) by both consultants and contractors alike, while clients are the least (67%) to adopt this particular approach. However since the number of respondents from the clients group was comparatively smaller than the other groups (with respect to this study), thus this percentage might not reflect the real scenario within the general clients group regarding this approach. In terms of effectiveness, 75% of those whom adopted this approach acknowledged its effectiveness in avoiding disputes. All of the respondents from the clients group whom adopted this approach agreed on its effectiveness, while contractors showed the least percentage (67%) of those whom agreed that this approach was effective. It is suggested that, the reason for this, might be due to the fact that clients are in a more superior position to allocate risks to those (contractors) whom are delivering their intended products. Therefore, contractors are burdened with the tasks to allocate these risks further onwards to other participants and this might be 100 where things might be sticky, since obviously others are happier to be burden with only the smallest risks or not at all and potentially would try to evade from being burdened by any risks. Thus the inability to fully allocate risks further and appropriately might force contractors to heap those unintended risks and making themselves vulnerable towards circumstances where disputes might emerge. For consultants, allocating risks among other participating consultants of a construction project might be easier, but there is a possibility that risks might be harder to be allocated on the shoulders of contractors as they had enough risks to think of thus may only allow minimum allocation on them, thus potentially creating a situation of insufficient risks allocation, resulting in the inability to avoid disputes from occurring. 101 CHAPTER V CONCLUSION AND RECOMMENDATION 5.1 Introduction This is the last chapter of the study which will conclude all the study that had been carried out. It included the literature review and findings of the field study that carried out in Chapter IV. Conclusion will be made based the objectives that had been outlined in the first chapter. 5.2 Conclusion Objective 1: To identify the causes for disputes in the construction industry From the research, in general terms, lack of communication and workmanship or quality control problems are the most important cause of disputes among parties involved in construction projects. However, disputes that arise from clients are mainly due to late payment to contractors as well as changes and variation requirement. From consultants point of view, changes and variation requirement from clients was considered as the main cause of 102 disputes. For contractors, they too considered late payment as well as changes and variation requirement, as two of the main causes of disputes arising from clients. With respect to consultants, clients considered the late issue of design information/drawing as the major cause of disputes by consultants. Between consultants alike, the most common causes of disputes among is lack of appropriate competence and experience. From contractor’s point of view, the most common causes of disputes by consultants is over-design and underestimating the costs involved. With respect to contractors, from clients points of view the main causes of disputes by contractors are delay or suspension of works and poor standard of work. Consultants instead highlighted four main causes of disputes by contractors which included; delay or suspension of works; poor standard of work; inadequate site management; and, poor planning and program. Contractors instead seem to disagree that most of the causes of disputes arises from their part of the deal. Of all the causes under study, only some were regarded by contractors to be possibly assigned to them. These included; delay or suspension of works; failure to coordinate its subcontractors’ work through effective and timely exchange of shop drawings; poor planning and program; poor standard of work; failure to proceed works in a competent manner; and, inadequate site management. Objective 2: To study the effect of disputes in the construction industry On the effect of disputes towards construction projects participants, as far as clients are concerned, the four major effects of disputes on them included; delay to the project completion; increase in time-related costs; effects on the costs or economics of the projects; and, effects on the quality of products (projects) to be delivered. For consultants, the major effects of disputes included; delay to the project completion; lost of productivity and efficiency; effects on the quality of products (projects) to be delivered; and, effects on the costs or economics of the projects. 103 The major effects acknowledged by contractors included; delay to the project completion; effects on the costs and economics of the projects; lost of productivity and efficiency; and, diversion of resources. Conclusively in general, disputes without any doubt do bear effects on all parties concerned. Categorically the major effects of disputes are those that concerns time as well as money, while those consequences from the legal terms was also considered significant as the other potential effects of disputes. Objective 3: To identify ways to mitigate disputes in construction. Finally, dispute can effectively be avoided or mitigated by adopting certain or series of dispute avoidance activities. These included; implementing early negotiation; conducting pre-contract reviews; conducting risks audits; conducting continuous training to enhance the quality and readiness of the relevant workforce to deal with disputable circumstances; conducting compliance audits to ensure every details matches what was planned; adopting better and thorough planning; subscribing to partnering approach; proper and realistic allocation of risks among participants; and, proper selection of contracts to be undertaken. Although effective, these dispute avoidance approaches does not guarantee anybody full exclusion from experiencing disputes. This might be due to inappropriate disputes avoidance measures being adopted (just like subscribing cough syrup to treat muscular pain problems), as well insufficient measures or approaches being adopted (just like using 1 liter of petrol and a cup of water in the radiator to travel a thousand miles), since an approach may at its best tackle certain causes of disputes but not the others. Of all the dispute avoidance approach suggested the partnering approach was seen as the most effective but probably the hardest to be adopted since its’ adoption would first require a successful establishment of partnership among parties involved and a right partner is never easy to find. However, for those who can’t afford a right partner, there is still a list of other adoptable approaches that are just as effective as the partnering approach in avoiding disputes. 104 5.3 Recommendation With respect to the findings as well as the conclusions drawn out from this study, several practical recommendations are worth forwarded for possible implementation. The first and most obvious is that all parties involved in construction projects must step up their effort and gives more emphasis on the issue of communication, workmanship and planning, and should make an effort to adopt methodologies which can bear improvements for them in these matters, since these were regarded as by all participants as some of the most common causes of disputes. Both communication and workmanship issues may be improved through continuous training, since training might provide those relevant workforces with the necessary skills upgrade and enhancements that are vital in delivering professional and high quality performance in executing projects at hand. The ability to plan instead can’t be enhance nor improve by mere training. Planning in its true nature is not as easy as spelling the word; it is indeed a delicate skill that require years of experience and intuition before near perfection. Therefore it is recommended that planning teams should be made up or guided by those with sufficient experience and good track record in order to come up with the best possible plan. Secondly, it is recommended that clients should adopt methodologies which may limit the need for changes till the least as possible if not at all, since changes and variations requirements coming from clients were acknowledged to be one of the major causes of disputes. One such approach might be by adopting early and comprehensive planning of project to be undertaken, since a well constructed plan may eliminate the need for changes and variations unless any real unexpected circumstances appears such as natural disaster or other beyond control events. Even so, a thoroughly produced plan should include a sub-plan of action against any unexpected eventualities. Contractors in the other hand, since they are most of the time burdened with nearly all of the blame, therefore may need to press even more effort into approaches that 105 might improve their standings in various dispute causing aspects. Since the option of approaches that can be choose and implemented are rather broad, all they might need is the desire to apply or use it. Finally it is also recommended that for future works, the relationship between the psychological sides of participants with the various practiced policy by governing or authoritative institutions, be investigated and its potential impacts and consequences (especially those related to the cause and effect of disputes) be addressed. The essence of this recommendation is that certain policies such as selective award of contracts which lacks justified credentials, may result in so-so mentality that do not enhances their actual competencies, and in long run may affect the whole industry players image at global arena hence limiting their global marketability. 106 BIBLIOGRAPHY Feniosky Pena-Mora, Carlos E.Sosa, D,Sean McCone (2003), Introduction to Construction Dispute Resolution, MIT/Prentice Hall Series on Civil, Environmental, and Systems Engineering, Pearson Education, New Jersey. Hellard, R. Baden (1988) , Managing Construction Conflict, Longman Scientific& Technical, Long Group UK Limited, England Allan Ashworth (2006), Contractual Procedures in The Construction Industry, Fifth Edition, Pearson Education Limited, England. Keith Colier (1994), Managing Construction The Contractual Viewpoint, Delmar Publisher Inc.,New York. K.S Singh Harbans (2003), Engineering and Construction Contracts Management: Post-Commencement Practice, LexisNexis Business Solutions, Singapore. Don McLagan (1991), An Introduction to Building Contracts, The Law Book Company Limited, Sydney, Australia. John Murdoch and Will Hughes (2000), Construction Contract: Law and Management, Third Edition, Spon Press, London. John Murdoch and Will Hughes (1992), Construction Contract: Law and Management, E & FN Spon, , London Bramble, Barry B. and Callahan, Michael T., (1987), Construction Delay Claims, Wiley Law Publications, John Wiley & Sons, Inc., Canada 107 John L.Riches and Christopher Dancaster (2004), Construction Adjudication, Second Edition, Blackwell Publishing, Oxford UK Frederick E.Gould and Nancy E.Joyce (2003), Construction Project Management, Second Edition, Prentice Hall, New Jersey. Micheal P.Reynolds (2002), The Expert Witness:In Construction Disputes, Blackwell Science Ltd, UK Alexandar Bevan (1992), Alternative Disputes Resolution, Sweet& Maxwell, London. Andrew A.L Tan (1996), Project Management in Malaysia: A Comprehensive Approach for Successful Management of Property Development Projects from Inception until Completion, Synergy Book International, Kuala Lumpur. K.S Singh Harbans (2002), Engineering and Construction Contracts Management: Law and Principles, LexisNexis Business Solutions, Singapore. C.H Teoh (1992), Arbitration in Construction Disputes, Longman Malaysia Sdn. Bhd, Selangor Darul Ehsan. Simon Roberts and Micheal Palmer(2005), Disputes Processess: ADR and the Primary Forms of Decision-Making, Second Edition, Cambridge University Press, New York. Maxwell J. Fulton (1989), Commercial Alternative Disputes Resolution, The Law Book Company Limited, Sydney. G. Tillet, (1991) Resolving Conflict: A Practical Approach. Sydney, Australia: Sydney Univ. Press. 108 Edwin H. W. Chan and Henry C. H. Suen,(2005), Disputes and Dispute Resolution Systems in Sino-Foreign Joint Venture Construction Projects in China, Journal of Professional Issues in Engineering Education and Practice @ ASCE Sai-On Cheung, Henry C. H. Suen and Tsun-Ip Lam, (2002) Fundamentals of Alternative Dispute Resolution Processes in Construction, Journal of Construction Engineering and Management. J. Richard Cheeks, (2003) Multistep Dispute Resolution in Design and Construction Industry, Journal of Professional Issues in Engineering Education and Practice @ ASC. Hewit, (1991),Winning Construction Disputes—Strategic Planning for Major Litigation. London, U.K.: Ernst and Young. Sai On Cheung and Tak Wing Yiu (2006), Are Construction Disputes Inevitable?, IEEE Transactions on Engineering Management, Vol.53, No.3 Sai On Cheung and Kenneth T.W. Yiu,(2007) A study of construction mediator tactics—Part I: Taxonomies of dispute sources, mediator tactics and mediation outcomes, Building and Environment 42, 752–761 D. J. Yates, (1998), Conflict and Dispute in the Development Process: A Transaction Cost Economic Perspective [Online]. Available:http://business2.unisa.edu.au/prres/Proceedings/Proceedings1998/Papers/Yates 3Ai.PDF 1998 Ameer Ali (2005) A “Construction Industry Payment and Adjudication Act” – Reducing Payment -Default and Increasing Dispute Resolution Efficiency. 109 Y.B. Dato’ Seri S.Samy Vellu, Speech By YB Dato’ Seri S Samy Vellu, Minister Of Works,Malaysia At The Offical Launch Of The PAM Contract 2006, Minister Of Works, Malaysia, Grand Ballroom, Hotel Maya, Kuala Lumpur, page 3 Kamaruddin, Master Builders Association Malaysia (MBAM) Project Management Institute Standards Committee (2004). A Guide to the project management body of knowledge. Stipanowich, T. J. (1998), The multi-door contract and other possibilities. Ohio St. J. On Disp. Resol., 13, 303–328. Building success for the 21st century, (1998), A guide to partnering in the construction industry.’’http://www.adr.org/guides/ partnering_guide.html.. American Arbitration Association, New York Association of Soil and Foundation Engineers @ ASFE (1995). Loss prevention through project management, Professional Firms Practicing In The Geosciences, ASFE, Silver Spring, Md. F.B., Osmond, (2003), Charting a Successful Dispute Resolution, AACE International Transactions M.H Jeffery, (2002), Ineffective Communication : Common Cause of Construction Disputes, ABA Lehal NotesVol.13, No.2 J.G Richard and Gibson G.E, (2006), Quantification of Costs for Disputes Resolution Procedures in the Construction Industry, Journal of Professional issues in Engineering Education and Practice. 110 APPENDIX A MINIMISATION CONSTRUCTION DISPUTES QUESTIONNAIRE SURVEY Section I: Company and Respondent Profile Please fill in the blank space or tick in the box where appropriate. 1. Respondent Name : ___________________________________ 2. Company Name :____________________________________ 3. Type of Job/ Position: ____________________________________ 4. Working Experience: Less than 5 years 5 years to 10 years 10 years and above 5. Type of Organization. Client Consultant Contractor 111 APPENDIX A Causes of Construction Disputes Construction Industry Section II Please indicate your opinion for the following causes of construction disputes Indicator, 1: Insignificant 2: Less Significant 3: Moderately Significant 4: Significant 5: Very Significant A. Causes of construction Disputes in General 11) Personality clashes between the various parties to the contract and/or member of project team 12345 2) Differing goals and objectives of the various parties 12345 3) A prevailing confrontational/adversarial atmosphere 12345 4) Lack of proper communication between the parties 12345 5) Allocation of insufficient resources 12345 6) Complexity of the works under the contract 12345 7) Allocation of inadequate time for the preparation of contracts and their discharge 8) Workmanship or quality control problems 12345 12345 9) Lack of proper planning both in terms of physical work and financial aspects 12345 10) Lack of good faith on part of the parties 12345 11) Failure to resolve minor differences on an amicable basis 12345 112 APPENDIX A Causes of Construction Disputes among Stakeholders in the Construction Industry B. Causes of construction Disputes by client 1) Poor briefing during design stage 12345 2) Changes and variation requirements 12345 3) Changes to standard conditions of contract 12345 4) Interference in the contractual duties of the contract administrator 5) Late payment to contractor 12345 12345 6) Unrealistic expectations particularly employers who have insufficient financing to accomplish their objectives 12345 7) Fail to pay variation claim 12345 8) Failure to respond in timely manner 12345 9) Inadequate tracing mechanisms for request of information 12345 10) Deficient management, supervision and coordination efforts on the part of the project 12345 11) Lowest price mentality in engagement of contractors and designers. 12345 12) The absence of team spirit among the participants. 12345 13) Reluctant to check for constructability, clarity and completeness. 12345 14) Failure to appoint a project manager 12345 15) Discrepancies / ambiguities in contract documents. 12345 113 APPENDIX A Causes of Construction Disputes among Stakeholders in the Construction Industry C. Causes of construction disputes by consultants 1) Over-design and underestimating the costs involved. 12345 2) Lack of appropriate competence and experience 12345 3) Unclear delegation of responsibilities 12345 4) Late issue of design information/drawings 12345 5) Errors/substantial changes in bills of quantities 12345 6) Variations due to design errors 12345 7) Design and specification oversights, and errors or omissions resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs 12345 8) Failure to understand its responsibilities under the design team contract 12345 9) Late information delivery and cumbersome approach to request for information’s 10) Incompleteness of drawing and specifications 12345 12345 114 APPENDIX A Causes of Construction Disputes among Stakeholders in the Construction Industry D. Causes of construction disputes by contractor 1) Inadequate site management 12345 2) Poor planning and program 12345 3) Poor standard of work 12345 4) Delayed payment to subcontractors 12345 5) Fails to proceed works in a competent manner 12345 6) Failure to coordinate its subcontractors’ work through effective and timely exchange of shop drawings 7) Lack of understanding and agreement in contract procurement 12345 12345 8) Delay/ suspension of works 12345 9) Failure to plan and execute the changes of works 12345 10) Failure to understand and correctly bid or price the works 12345 11) Reluctance to seek clarification 12345 12) Inadequate CPM scheduling and update requirements 12345 115 APPENDIX A The Effect of Disputes to Organisation in Construction Industry Section III Please rate the following statements on the scale from 1 to 5, where 1 is least severe where 5 is the most severe. 1 2 3 4 Least Severe 5 Most Severe 1) Effects on the costs or economics of the projects, as well as the financial returns of construction parties effort and investments 12345 2) Additional financial costs especially high cost of litigation 12345 3) Diversion of manpower away from the project costs 12345 4) Cost for a deposition, trial or arbitration preparation 12345 5) A reduction in bonding capacity in business 12345 6) Damage to reputation of the parties involved 12345 7) Abandonment of project and termination of contract 12345 8) Delay to the project completion 12345 9) Third party claims, due to damages for delay to construction projects which affect them. 12345 10) Increase in time-related costs (such as idled equipment rental costs, changes in building materials price, bank interest, utilities charges and insurance) 12345 11) Lost of productivity and efficiency (idled labor and equipment) 12345 12) Affects the quality of product to be delivered 12345 13) Cause job stress (emotional costs) to parties involved 12345 116 APPENDIX A Minimisation of Disputes in Construction Industry Section IV A. DISPUTE AVOIDANCE In general, dispute can be avoided or be minimized the least, by employing certain or a set of dispute avoidance activities. 1. Early negotiation is considered as one of the most used method for avoiding disputes. a) Are you or your company aware that early negotiations can be employed to avoid disputes? Yes No If Yes, please proceed to question 1 b), if No, please proceed to question 2. b) Have you or your company ever used early negotiations in order to avoid disputes? Yes No If yes, please proceed to question 1 c), if No, please proceed to question 2. c) Does early negotiation helps you or your company avoids disputes? Yes No If No, please specify the reason/s: ________________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________ 117 APPENDIX A 2. Pre-contract reviews are another most used method for avoiding disputes. a) Are you or your company is aware that pre-contract reviews can be employed to avoid disputes? Yes No If yes, please proceed to question 2 b), if No, please proceed to question 3. b) Have you or your company ever conducted pre-contract reviews in order to avoid disputes? Yes No If yes, please proceed to question 2 c), if No, please proceed to question 3. c) Do conducting pre-contract reviews help you or your company avoids disputes? Yes No If No, please specify the reason/s: ________________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________ 3. Conducting risk audits are another method for avoiding disputes. a) Are you or your company is aware that risk audits can be employed to avoid disputes? Yes No If yes, please proceed to question 3b), if No, please proceed to question 4. 118 APPENDIX A b) Have you or your company ever conducted risk audits in order to avoid disputes? Yes No If yes, please proceed to question 3 c), if No, please proceed to question 4. c) Do conducting risk audits help you or your company avoids disputes? Yes No If No, please specify the reason/s: ________________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________ 4. Another method that can be employed to avoid disputes is by providing continuous training for your human resources, especially those involved directly in construction projects. Essential trainings to enhance skills included; communication and negotiation skills, leadership skills, teambuilding, specific skills such as legal knowledge, codes and specifications, record keeping and file management, and other skills that are important in ensuring smooth running of construction projects. a) Are you or your company is aware that continuous training has an effect in avoiding disputes? Yes No If yes, please proceed to question 4 b), if No, please proceed to question 5. 119 APPENDIX A b) Have you ever involved in or provides continuous training that can assist you or your human resources in avoiding disputes? Yes No If yes, please proceed to question 4 c), if No, please proceed to question 5. c) Do the trainings that you received or your company provided help you or your company’s human resources to avoid disputes? Yes No If No, please specify the reason/s: ________________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________ 5. Disputes can also be avoided by conducting compliance audits, to ensure intended quality can be achieved. a) Are you or your company is aware that disputes can be avoided through conducting regular compliance audits? Yes No If yes, please proceed to question 5 b), if No, please proceed to question 6. b) Have you or your company ever conducted or involved in compliance audits in order to avoid disputes? Yes No If yes, please proceed to question 5 c), if No, please proceed to question 6. 120 APPENDIX A c) Do conducting compliance audits help you or your company to avoid disputes? Yes No If No, please specify the reason/s: ________________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________ 6. In part of the management, dispute can be avoided through thorough and better planning, for example by ensuring that contract documents are clear and precise. a) Are you involved in the management or the management teams of construction projects? Yes No If yes, please proceed to question 6 b), if No, please proceed to question 7. b) Do you or your teams exercise thorough and precise planning in any of the construction projects that you or your teams undertook? Yes No If Yes, please proceed to question 6 c), if No, please proceed to question 7. 121 APPENDIX A c) Does the thorough and precise planning exercised help you or your team to avoid disputes? Yes No If No, please specify the reason/s: ________________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________ 7. In terms of project management, disputes can be avoided by utilizing project and business structure which lessen the risks of disputes. The best approach suggested is through employing the partnering approach. a) Are you involved in the management or the management teams of construction projects? Yes No If yes, please proceed to question 7 b), if No, please proceed to question 8. b) Do you or your company employ the partnering approach in the construction projects that you or your company undertook? Yes No If Yes, please proceed to question 7 c), if No, please proceed to question 8. 122 APPENDIX A c) Does the partnering approach you or your company employed help you or your company to avoid disputes? Yes No If No, please specify the reason/s: ________________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________ 8. Risk allocation is another method of which disputes can be avoided, especially in part of the management. The proper and acceptable allocation of risks based on the principle of action-consequences relationship among the parties involved in any construction projects can be implemented so each of the party involved will be more proactive in avoiding disputes. a) Are you involved in the management or the management teams of construction projects? Yes No If yes, please proceed to question 8 b), if No, please proceed to question 9. b) Do your company and its partners implement risk allocation as a way to avoid disputes? Yes No If Yes, please proceed to question 8 c), if No, please proceed to question 9. 123 APPENDIX A c) Does the risk allocation being implemented by your company help to avoid disputes? Yes No If No, please specify the reason/s: ________________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________ 9. It was also suggested that disputes can also be avoided by proper selection of construction contracts itself, meaning, select contracts with the least possibility of problems. a) Are you or your company is involved in procuring construction contracts? Yes No If yes, please proceed to question 9 b). b) Are you or your company is aware that disputes can be avoided through proper and thorough selection of construction contracts? Yes No If yes, please proceed to question 9 c). c) Do you or your company properly or thoroughly select construction projects to be undertaken? Yes No If yes, please proceed to question 9 d). 124 APPENDIX A d) Does the selecting of proper construction contracts help you or your company avoids disputes? Yes No If No, please specify the reason/s: ________________________________________________________________________ ________________________________________________________________________ ________________________________________________________________________ THANK YOU FOR YOUR COOPERATION