Office of Contract Management and Vendor Services Rio Hondo Community College 3600 Workman Mill Road, A-103 Whittier, CA 90601-1699 Ph: 562/908-3413 & Fax: 562/908-3462 Bid # 2047- Pico Rivera Educational Center Project DSA #03-116946 Addendum # 3 May 16, 2016 To: All Prospective Bidders THE FOLLOWING REVISIONS AND/OR CLARIFICATIONS SHALL BE MADE TO THE BIDDING REQUIREMENTS AND CONTRACT DOCUMENTS. REVISE AND AMEND THE DOCUMENTS FOR THE ABOVE NAMED PROJECT IN ACCORDANCE WITH THIS ADDENDUM. THE BID SHALL REFLECT THESE ADDENDUM CHANGES AND EACH BIDDER SHALL MAKE REFERENCE IN THEIR BID TO THIS ADDENDUM. ALL BIDDING REQUIREMENTS AND CONTRACT DOCUMENTS SHALL APPLY TO THIS ADDENDUM AS ORIGINALLY INDICATED IN THE APPLICABLE PORTIONS OF THE CONTRACT DOCUMENTS, UNLESS OTHERWISE MODIFIED BY THIS ADDENDUM. Acknowledge receipt of this Addendum in the space provided on Document 00210 – Bid Proposal. Failure to do so may result in the bid being deemed non-responsive. The Addendum consists of the following changes: 1. ADMINISTRATIVE ITEMS: 1.1. REPLACE: Section 00210 Bid Proposal with the attached revised Section 00210 Bid Proposal 1.2. ADD: Section 00212 Site Visit Certification 1.3. REPLACE: Section 00300 Agreement with the attached revised Section 00300 Agreement 1.4. REPLACE: Section 00800 Special Conditions with the attached revised Section 00800 Special Conditions 1.5. ADD: Section 01010 Phasing of the Work 1.6. ADD: Section 01010 Phasing of the Work Appendix A RIO HONDO COMMUNITY COLLEGE – Bid #2047 Page 1 of 2 ADDENDUM NO 3 May 16, 2016 2. TECHNICAL SPECIFICATIONS: 2.1. ADD: Audio Visual Standard Specification 2.2. ADD: Exhibit 1 to the scope of work. Contact Jim Wagner at (909) 790-0296 for pricing, delivery and installation for a total of seven classrooms. 3. DRAWINGS: 3.1. ADD: Drawing E001 3.2. ADD: Drawing E008 3.2. ADD: Drawing E202 3.2. ADD: Drawing E203 4. BIDDERS QUESTIONS: RESPONSE TO QUESTIONS FROM BIDDERS The following questions were received as Bid RFIs. Enclosed are responses to each. The followingrevisions and clarifications shall become a part of the Contract Documents upon award of Bid. All bidders are required to incorporate all necessary changes, additions, or deductions into their proposals. 4.1 Q: The Bidders Check List states Item D, Site Visit Certification must be submitted with Bid Proposal. Document was not located in the Project Manual. Is the Site Visit Certification required to be submitted with the Bid Proposal? A: Yes, please see attached Section 00212 Site Visit Certification 5. ENCLOSURES: Enclosures: REVISED Section 00210 Bid Proposal (6 pages) Section 00212 Site Visit Certification (1 page) REVISED Section 00300 Agreement (2 pages) REVISED Section 00800 Special Conditions (8 pages) Section 01010 Phasing of the Work (3 pages) Section 01010 Phasing of the Work Appendix A (2 pages) Exhibit, Audio Visual Equipment List 1 (1 page) Audio Visual Standard Specification (2 pages) Drawing E001 (1 page) Drawing E008 (1 page) Drawing E202 (1 page) Drawing E203 (1 page) END OF ADDENDUM # 3 RIO HONDO COMMUNITY COLLEGE – Bid #2047 Page 2 of 2 ADDENDUM NO 3 May 16, 2016 SECTION 00210 BID PROPOSAL TO: RIO HONDO COMMUNITY COLLEGE DISTRICT, a California Community College District, acting by and through its Board of Trustees (“District"), 3600 Workman Mill Road, Whittier, California 90601. FROM: (Name of Bidder as listed on License) (Address) (City, State, Zip Code) (Telephone) (Fax) (Email) (Name(s) of Bidder's Authorized Representative(s) & Title) RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 BID PROPOSAL PAGE 1 OF 6 SECTION 00210 1.01 Bid Proposal. A. Bid Proposal Amount. Pursuant to and in compliance with the Notice to Contractors Calling for Bids, the Instructions for Bidders and the other documents relating thereto, the undersigned Bidder, having reviewed the Instructions for Bidders and all other Contract Documents and upon compliance with all requirements therein with reference to the submittal of this Bid Proposal, hereby proposes and agrees to perform the Contract including, without limitation, all of its component parts; to perform everything required to be performed; to provide and furnish any and all of the labor, materials, tools, equipment, applicable taxes, and services necessary to perform the Work of the Contract in strict compliance with the Contract Documents and complete in a workmanlike manner all of the Work required for the Project described as: Bid #2047 – Pico Rivera Educational Center at 9515 Haney Street, Pico Rivera, Ca 90660 for the sum of: Total Bid Amount: $____________________________________________ (Total Bid Amount in Figures) _______________________________________________________________ (Total Bid Amount in Words) Allowance Amount: $__90,000.00__ ___ (Total Bid Amount in Figures) Ninety Thousand Dollars__________ (Total Bid Amount in Words) _______ for the sum of: Total Base Bid and Allowance Amount $_______________________________ (Total Base Bid Amount in Figures) _______________________________________________________________ (Total Base Bid Amount in Words) RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 BID PROPOSAL PAGE 2 OF 6 SECTION 00210 B. Acknowledgment of Bid Addenda. In submitting this Bid Proposal, the undersigned Bidder acknowledges receipt of all Bid Addenda issued by or on behalf of the District, as set forth below. The Bidder confirms that this Bid Proposal incorporates and is inclusive of, all items or other matters contained in Bid Addenda. _______ No Addenda Issued (initial) _______ Addenda Nos. _________________ received, acknowledged and (initial) incorporated into this Bid Proposal. C. Alternate Bid Items. The Bidder’s price proposal(s) for Alternate Bid Items is/are set forth in the form of Alternate Bid Item Proposal included herewith. The Bidder acknowledges that the award of the Contract, if at all, shall be in accordance with the Instructions for Bidders. 1.02 Rejection of Bid; Holding Open of Bid. It is understood that the District reserves the right to reject this Bid Proposal and that this Bid Proposal shall remain open and not be withdrawn for the period of time specified in the Call for Bids, except as provided by law. 1.03 Documents Comprising Bid Proposal. The undersigned Bidder has submitted as its Bid Proposal the following: Bid Proposal (00210), List of Subcontractors (00215), NonCollusion Declaration (00220), DIR (00230) and Bid Security (Cash, Cashier’s Check, Certified Check or Bid Bond – 00260),Statement of Bidder’s Qualifications (00240) The Bidder acknowledges that if this Bid Proposal and the foregoing documents are not fully in compliance with applicable requirements set forth in the Call for Bids, the Instructions for Bidders and in each of the foregoing documents, the Bid Proposal may be rejected as non-responsive. 1.04 Award of Contract. It is understood and agreed that if written notice of the acceptance of this Bid Proposal and award of the Contract thereon is mailed or delivered by the District to the undersigned after the opening of Bid Proposals and within the time this Bid Proposal is required to remain open or at any time thereafter before this Bid Proposal is withdrawn, the undersigned will execute and deliver to the District the Agreement in the form attached hereto in accordance with the Bid Proposal as accepted within five (5) working days after notification of acceptance and award. Concurrently with delivery of the executed Agreement to the District, the Bidder awarded the Contract shall deliver to the District: (1) the Labor and Material Payment Bond; (2) the Performance Bond; (3) the Drug-Free Workplace Certificate; (4) Certificates of Insurance evidencing all insurance coverages required to be provided under the Contract Documents; (5) the Certificate of Workers’ Compensation Insurance; and (6) Letter of Assent for Project Labor Agreement. RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 BID PROPOSAL PAGE 3 OF 6 SECTION 00210 The Work under the Contract Documents shall be commenced by the undersigned Bidder, if awarded the Contract, on the date stated in the District's Notice to Proceed issued pursuant to the Contract Documents. Completion of the Work and all Interim Milestones shall be achieved within the Contract Time and Interim Milestones specified in the Contract Documents. 1.05 Notices. All notices or other correspondence shall be addressed to the District and the Bidder at their respective addresses set forth herein. Notices shall be effective only if in writing and in conformity with the requirements for service of notices set forth in the Contract Documents. 1.06 Contractor's License. The undersigned Bidder is currently and duly licensed in accordance with the California Contractors License Law, California Business & Professions Code §§7000 et seq., under the following: License Number: Class Expiration Date Class Expiration Date Class Class Expiration Date Expiration Date By executing this Bid Proposal, the Bidder hereby certifies that: (a) it is duly licensed, in the necessary class(es), for performing the Work of the Contract Documents; (b) that such license shall be in full force and effect throughout the duration of the performance of the Work under the Contract Documents; and (c) that all Subcontractors providing or performing any portion of the Work of the Contract Documents shall be so similarly and appropriately licensed to perform or provide such portion of the Work. 1.07 Designation of Subcontractors. In compliance with the Subletting and Subcontracting Fair Practices Act (California Public Contract Code §§4100, et seq.) and amendments thereof, each Bidder shall set forth in the Subcontractors List: (a) the name and location of the place of business of each Subcontractor who will perform work or labor or render services to the Bidder in or about the construction of the Work to be performed under the Contract Documents in an amount in excess of one-half of one percent (0.5%) of the Bidder's Bid Proposal; and (b) the trade and/or portion of the Work which will be performed by each listed Subcontractor. The Bidder shall list only one Subcontractor for each trade and/or portion of the Work as is defined by the Bidder in its Bid Proposal. If a Bidder fails to list a Subcontractor for a portion of the work in excess of one-half of one percent (0.5%) of the Bidder’s Bid Proposal or if the Bidder specifies more than one Subcontractor for the same portion of Work to be performed under the Contract Documents valued in excess of one-half of one percent (0.5%) of the Bidder's Bid Proposal amount, the Bidder shall be deemed to have agreed that it is fully qualified to perform that portion of the Work itself and that it shall perform that portion of the Work. RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 BID PROPOSAL PAGE 4 OF 6 SECTION 00210 1.08 Confirmation of Figures. By submitting this Bid Proposal, the Bidder confirms that it has checked all of the above figures and understands that neither the District nor any of its agents, employees or representatives shall be responsible for any errors or omissions on the part of the undersigned Bidder in preparing and submitting this Bid Proposal. 1.09 Acknowledgment and Confirmation. The undersigned Bidder acknowledges its receipt, review and understanding of the Drawings, the Specifications and other Contract Documents pertaining to the proposed Work. The undersigned Bidder certifies that the Contract Documents are, in its opinion, adequate, feasible and complete for providing, performing and constructing the Work in a sound and suitable manner for the use specified and intended by the Contract Documents. The undersigned Bidder certifies that it has, or has available, all necessary equipment, personnel, materials, facilities and technical and financial ability to complete the Work for the amount bid herein within the Contract Time and in accordance with the Contract Documents. The undersigned Bidder certifies that its bid amount includes funds sufficient to allow the Bidder to comply with all applicable local, state and federal laws and regulations governing the labor and services to be provided for the performance of the Work of the Contract and shall indemnify, defend and hold District harmless from and against any and all claims, demands, losses, liabilities and damages arising out of or relating to Bidder’s failure to comply with applicable law in this regard. By: (Signature) (Corporate Seal) (Typed or Printed Name of Bidder’s Authorized Representative) Title: RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 BID PROPOSAL PAGE 5 OF 6 SECTION 00210 ALTERNATE BID ITEM PROPOSAL Bidder must provide a proposal for each Additive Alternate Bid item set forth herein; failure to do so will result in rejection of the Bid Proposal for non-responsiveness. The proposal price for the Alternate Bid Item shall be exclusive of the base bid proposal amounts in Paragraph 1 of the Bid Proposal. Bidder Name: _________________________________________________________ Additive Alternates Scope of Work: Provide all labor, transportation, miscellaneous materials, equipment, supplies and supervision. Work is to include but not limited to the scope of work outline in the plans and specifications. Alternate Bid Item No. 1 Additive Exhibit 1 Audio Visual Equipment - Total Price _______________________________________________________ ( $ Amount in Words ) By: (Signature) (Corporate Seal) (Typed or Printed Name of Bidder’s Authorized Representative) Title: ____________________________________ END OF SECTION RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 BID PROPOSAL PAGE 6 OF 6 SECTION 00212 SITE VISIT CERTIFICATION I certify that I have visited the site of the proposed work and have fully acquainted myself with the conditions relating to construction and labor. I fully understand the facilities, difficulties, and restrictions attending the execution of the work under contract. I certify under penalty of perjury under the laws of the State of California that the foregoing is true and correct. I fully indemnify RIO HONDO COMMUNITY COLLEGE, The Architect, the Construction Manager, and all of their respective officers, agents, employees, and consultants from any damage, or omissions, related to conditions that could have been identified during my visit(s) to the site. ____________________________________ (Signature of Bidder) ____________________________________ (Typed name of Bidder) _____________________________________ (Typed Company Name of Bidder) SUBSCRIBED BEFORE ME on this ______ day of _______________, 2014 ______________________________________ (Notary Public) My commission expires: _________________ RIO HONOD COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER ADDEDNUM NO.3 05/16/16 SITE VISIT CERTIFICATION 00212 (rev. 04-09-11) PAGE 1 OF 1 SECTION 00300 AGREEMENT THIS AGREEMENT is made this day of , 20 , in the County of Los Angeles, State of California, by and between RIO HONDO COMMUNITY COLLEGE DISTRICT, a California Community College District, hereinafter called the “District” and , hereinafter called the “Contractor”, with a principal place of business located at ______________________________. WITNESSETH, that the District and the Contractor in consideration of the mutual covenants contained herein agree as follows: 1.01 The Work. Within the Contract Time and for the Contract Price, subject to adjustments thereto pursuant to the Contract Documents, the Contractor shall perform and provide all necessary labor, materials, tools, equipment, utilities, services and transportation to complete in a workmanlike manner all of the Work required in connection with the work of improvement commonly referred to as: BID #2047 Pico Rivera Educational Center Project at 9515 Haney Street, Pico Rivera, Ca 90660 Contractor shall complete all Work covered by the Contract Documents, including without limitation, the Drawings and Specifications prepared by the Architect, and other Contract Documents enumerated in Article 5 below, along with all modifications and addenda thereto issued in accordance with the Contract Documents. 1.02 Contract Time. The Work shall be commenced on the date stated in the District’s Notice to Proceed. The Contractor shall achieve Substantial Completion of the Work within SEVENTY-NINE (79) calendar days after the date stated in the District’s Notice to Proceed (see Section 1.01 of the Contract Special Conditions and as otherwise provided in the Contract Documents). 1.03 Contract Price. The District shall pay the Contractor as full consideration for the Contractor’s full, complete and faithful performance of the Contractor’s obligations under the Contract Documents, subject to any additions or deduction as provided for in the Contract Documents, the Contract Price of Dollars ($ ). The Contract Price is based upon the Contractor’s Base Bid Proposal and the following Alternate Bid Items, if any: The District’s payment of the Contract Price shall be in accordance with the Contract Documents. 1.04 Liquidated Damages. In the event of the failure or refusal of the Contractor to achieve Completion of the Work of the Contract Documents within the Contract Time, as adjusted, the Contractor shall be subject to assessment of Liquidated Damages in accordance with the Contract Documents. RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 AGREEMENT PAGE 1 OF 2 1.05 The Contract Documents. The Contract Documents consist of the following: Notice to Contractors Calling for Bids Instructions for Bidders Bid Proposal Subcontractors List Non-Collusion Declaration DIR Bid Bond Agreement Statement of Bidders Qualifications Construction Forms Soils Report 1.06 Civil Engineering Survey Labor and Material Payment Bond Performance Bond Certificate of Workers Compensation Drug Free Workplace Certification General Conditions Special Conditions Labor Compliance Program Drawings Specifications Guarantee Authority to Execute. The individual(s) executing this Agreement on behalf of the Contractor is/are duly and fully authorized to execute this Agreement on behalf of Contractor and to bind the Contractor to each and every term, condition and covenant of the Contract Documents. IN WITNESS WHEREOF, this Agreement has been duly executed by the District and the Contractor as of the date set forth above. DISTRICT CONTRACTOR RIO HONDO COMMUNITY COLLEGE DISTRICT, a California Community College District (Contractor’s License Number) By: By: Vice President, Business Name: Title: (Corporate Seal) END OF SECTION RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 AGREEMENT PAGE 2 OF 2 SECTION 00800 SPECIAL CONDITIONS PART 1 1.01 1.02 Contract Time. A. Substantial Completion of the Work. The Work shall be commenced on the date stated in the Notice to Proceed issued by the District to the Contractor and shall be completed within 65 consecutive calendar days from and after the date stated in the Notice to Proceed (Reference Article 7 of the General Conditions). B. Interim Milestone Completion Dates. Notwithstanding any provision of the Contract Documents to the contrary, Contractor shall sequence and coordinate the work so that portions of the work are completed as required by the Work Segment Plan in accordance with start and completion dates. Liquidated Damages. A. Delayed Completion of the Work. Pursuant to Article 7 of the General Conditions, the Contractor shall be subject to the assessment and withholding of Liquidated Damages for failure to achieve Substantial Completion of the Work within the Contract Time as indicated in item 1.01.A, above. Liquidated Damages shall be at the rate of $2,000 per day until Work of Construction Segments IA and IB as defined on Section 01010 is achieved. B. Delayed Final Completion of the Work. Pursuant to Article 7 of the General Conditions, the Contractor shall be subject to the assessment and withholding of Liquidated Damages for failure to achieve Final Completion of the Work in accordance with the Contract Documents. Liquidated Damages shall be at the rate of $2,000 per day until Final Completion of the Work is achieved. C. Delayed Submittals. The per day assessment of Liquidated Damages for Contractor’s delayed submission of Submittals pursuant to Article 4.8.2.1 of the General Conditions is $2,000 per day per Submittal until the required Submittal is submitted. D. Other Milestone Delays. Refer to Appendix A for project milestones and associated liquidated damages E. Cumulative Assessment of Liquidated Damages. If the Contractor fails to timely delivery of the Submittals, fails to achieve Final Completion of the Work Segments as set forth herein, or fails to achieve Substantial or Final Completion of the Work, the Contractor shall be subject to assessment and withholding of Liquidated Damages in the amounts set forth above for each such portion of the Work which is not timely delivered or completed within the time allocated for each portion of the Work. RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 SPECIAL CONDITIONS 00800 PAGE 1 OF 8 1.03 Insurance Insurance Provided By District. Not Applicable. B. Insurance Provided by Contractors/Subcontractors. Pursuant to Article 6.12 of the General Conditions, the Contractor, all Subcontractors and Sub-Subcontractors (except Excluded Parties covered under Article 6.18) shall provide and maintain the following insurance coverage’s, with minimum coverage amounts as set forth below: 1. Workers Compensation Insurance In accordance with limits established by law. 2. Employers Liability Insurance $2,000,000 3. Commercial General Liability Insurance Per Occurrence Aggregate $1,000,000 $2,000,000 Automobile Liability Bodily Injury/Property Damage per Occurrence $1,000,000 Aircraft Liability Insurance (if applicable) Per Occurrence Aggregate $5,000,000 $5,000,000 4. 5. C. Insurance Provided by Excluded Parties. Pursuant to Article 6.18 of the General Conditions, the Excluded Parties shall provide and maintain the following insurance coverage’s, with minimum coverage amounts as set forth below: 1. Workers Compensation Insurance In accordance with limits established by law. 2. Employers Liability Insurance $1,000,000 3. Commercial General Liability Insurance Per Occurrence Aggregate $1,000,000 $3,000,000 Automobile Liability Bodily Injury/Property Damage Per Occurrence $1,000,000 Aircraft Liability Insurance (if applicable) Per Occurrence Aggregate $5,000,000 $5,000,000 4. 5. RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 SPECIAL CONDITIONS 00800 PAGE 2 OF 8 D. Pollution Legal Liability Insurance. Pursuant to Article 6.21 of the General Conditions, the Excluded Parties shall provide and maintain the following insurance coverage’s, with minimum coverage amounts as set forth below: Per Occurrence Aggregate 1.04 $5,000,000 $5,000,000 Drawings and Specifications. The number of sets of the Drawings and Specifications which the District will provide to the Contractor pursuant to Article 2.1.2 of the General Conditions is one (1) set of reproducible specifications with plans which can be downloaded of the website at http://www.riohondo.edu/facilities/RFQ/index.htm Website above is the official record of the bid documents. Contractor is responsible for downloading all drawings, specifications, addendum etc from the above mentioned website. 1.05 Mark-ups on Changes to the Work. A. In the event of Changes to the Work, pursuant to Article 9 of the General Conditions, the mark-up for all overhead (including home and field office overhead), general conditions costs and profit, shall not exceed five percent (5%) of the direct actual costs if the General Contractor performed the work, five percent (5%) if the sub-contractor performed the work, as determined in accordance with Article 9.4 of the General conditions. Sub-contractor overhead and profit shall / will not exceed Five percent (5%) for self performed work and Five percent (5%) for work preformed by others. The foregoing limitation on mark-ups shall apply regardless of the number of Subcontractors, of any tier, performing any portion of such Change to the Work. In addition to the foregoing, Contractor may add a bond premium fee of the actual direct cost of the bond for such Change, not to exceed two percent (2%), of the actual direct costs for performance of the Change and the maximum allowable mark-up for overhead, general conditions and profit. B. Deleted Work: All deductive change order(s) must be prepared pursuant to Contract Documents. Deductive Change Orders must be at a fair cost value to the district and shall credit back all mark-ups to the district along with the actual scope of work. General contractor and all subcontractors shall not be entitled to any profit and overhead on the deducted work. 1.06 Inclement Weather Days. Pursuant to Article 7.4.1 of the General Conditions, the number of Rain Days (including inclement weather) for this Contract is 10-days. Include a critical path activity entitled “Remaining Inclement Weather Days” on the initial Contract schedule. This activity shall have an initial duration of seven (7) work days and shall be the last activity in the schedule prior to the activity entitled “Completion”. All predecessor activities must pass through the RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 SPECIAL CONDITIONS 00800 PAGE 3 OF 8 Inclement Weather day’s activity. The Contractor shall request use of the Inclement Weather Day when a critical path activity has been delayed due to inclement weather. This request must occur in the same month as the inclement weather delay and must be approved by a Change Order. Inclement Weather Delays to non-critical activities will not e considered. If, at completion, there are inclement weather days still remaining, the Completion date shall not be adjusted. If at or near completion, additional inclement weather days are required, the completion date shall be adjusted accordingly by processing a Change Order for a non-compensable time extension. 1.07 District’s Construction Manager. Del Terra 13181 Crossroads Prkwy, N., Ste 540 City of Industry, CA 91746 PART 2 2.0 Construction operations, phasing, execution and Special Provisions This Section supersedes other general conditions where applicable. 2.1 Project Limits. The Contractor will limit its operations to the area included in the Contract Documents. All contractor lay-down, construction work and operations will be limited to the area as as directed by the Construction Manager, Approved by Rio Hondo Program Management Team. 2.2 Hours of Operation Work will be coordinated with Construction Manager & College for minimum disruption to College operations and shall be performed during normal business working hours; Monday to Friday from 6:00 AM to 6:00 PM. All off-hour work or weekend work must be approved by the College through the Construction Manager at least two days in advance. 2.3 Construction Traffic Route Contractor to use pre-determined construction traffic routes as approved by the College. 2.4 Progress Schedule; Contractor Responsibility for Construction Schedule CONTRACTOR shall be responsible for the preparation, submittal and maintenance of Construction Schedules required by the Contract Documents according but not limited to Section 01320, CONSTRUCTION PROGRESS DOCUMENTAION as included in Division 01 of the Bid Documents. All pertinent provisions of the General Conditions apply. RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 SPECIAL CONDITIONS 00800 PAGE 4 OF 8 2.5 Phasing A Work will be performed in such a manner as to minimize impact to normal college operations. Any phase/segment shall be required to be completed according to the approved Milestones Schedule. B Contractor shall submit a “work to complete’ list to the Construction Manager 5 calendar days before the scheduled end of any phase. The Construction Manager and the Architect will comment and add items to the list as necessary. The contractor shall complete the “work to complete” list within 3 days after having received the list from the Construction Manager. The contractor shall request a punch list walk 5 days prior to the scheduled end of any phase/segment. C During the performance of this contract, the college and facilities operations will be ongoing and will remain under normal operations. Work will be permitted during school hours, provided that safe access to and exits from buildings are maintained while facilities remain in use. Temporary fencing with green windscreen shall be erected by the contractor to segregate work areas from all other campus areas. D Contractor shall commence performance of the Contract upon the date specified in the Notice to Proceed and shall furnish sufficient labor, equipment, material, extra shifts and overtime to achieve the required milestones as indicated on Section 01010. 2.6 Allowances The bidders shall include within the base bid the following allowances. The allowances shall be identified as separate line items in the Contractor’s schedule of values. The allowances are to be used at the College’s sole discretion for work not otherwise shown and/or specified in the construction documents. Work performed under the allowances shall be performed only as directed in writing by Program Management Team, through the Construction Manager. Any and all unused allowance amounts shall be credited to the College by change order and reflected in the Contractor’s final application for payment without any compensation for overhead and profit. ALLOWANCES No. 1 Description Allowance Unforeseen Conditions $ 90,000.00 Total 2.7 $90,000.00 Ancillary Project Conditions Contractor shall provide an itemized scope and work plan to include field notes and shop RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 SPECIAL CONDITIONS 00800 PAGE 5 OF 8 drawings to accomplish each of the ancillary projects listed on Exhibit I above. Estimates of costs must be provided prior to commencement of work. The work will be tracked on a time and materials basis. Owner reserves the option to assign work to others with a Not to Exceed amount of 1% of contract value and at no more than 5% overhead and profit markup on assigned subcontractor. Any allowances not used can be assigned to other allowances or deleted in this contract at no penalty to the College. 2.8 Coordination with other Onsite contractors/trades A. Contractor shall coordinate operations included in various sections of the Contract Documents to help ensure efficient and orderly completion of the work. B. Coordinate scheduling and timing of required administrative procedures with other construction activities to avoid conflicts and help ensure orderly progress of the work. Such administrative activities include, but are not limited to, the following: 1. Preparation of schedules. 2. Installation, relocation and removal of temporary facilities. 3. Progress meetings. 4. Project coordination activities. C. Coordinate all work with other onsite contractors. 2.9 Security Contractor is responsible for Work and Site security from start of construction, date of NTP, to Substantial Completion, whichever comes later. Contractor’s responsibility includes assessment of security needs within and around Site Boundaries and employment of qualified personnel as may be necessary at no additional costs to the College. In case the security personnel is not used all such costs will be credited back to the college at prevailing wages. 2.10 Protection of Persons and Property A. The Contractor shall be responsible for all damages to persons or property that occur as a result of its fault or negligence in connection with the prosecution of this Contract and shall take all necessary measures and be responsible for the proper care and protection of all materials delivered to and from the site and work performed until completion and final acceptance by the College. All work shall be solely at the Contractor's risk, with the exception of damage to the work caused by "acts of God" as defined in Public Contract Code Section 7105(b)(2). B. Contractor shall take, and require all subcontractors to take, all necessary precautions for the safety of workers on the site and shall comply with all applicable federal, state, local and other safety laws, standards, orders, rules, regulations, and building codes to prevent accidents or injury to persons on, about, or adjacent to premises where Work is being performed and to provide a safe and healthful place of employment. In addition to meeting all requirements of OSHA, Cal-OSHA, state, and local codes. Contractor shall furnish, erect and RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 SPECIAL CONDITIONS 00800 PAGE 6 OF 8 properly maintain at all times, as directed by the College or Program Manager or required by conditions and progress of work, all necessary safety devices, safeguards, construction canopies, signs, audible devices for protection of the blind, safety rails, belts and nets, barriers, lights, and watchmen for protection of workers and the public, and shall post danger signs warning against hazards created by such features in the course of construction. C. The Contractor shall erect and maintain, as required by existing conditions and performance of the Contract, reasonable safeguards for safety and protection, including posting danger signs and other warnings against hazards, promulgating safety regulations, and notifying owners and users of adjacent sites and utilities. D. Requirements for Existing Sites. Contractor shall (unless waived by the College in writing): (a) When performing construction on existing sites, become informed and take into specific account the maturity of the students on the site. Contractor shall perform Work which may interfere with school routine before or after school hours, enclose working area with a substantial barricade, and arrange Work to cause a minimum amount of inconvenience and danger to students and faculty in their regular school activities. The Contractor shall comply with specifications and directives of the College regarding the timing of certain construction activities in order to avoid unnecessary interference with school functioning. (b) (c) Provide substantial barricades around any shrubs or trees indicated to be preserved. Deliver materials to building area over route designated by the College through the Construction Manager. Take preventive measures to minimize objectionable dust, noise, or other disturbances. Take preventive measures to prevent disturbing or covering any survey markers, monuments or other devices marking property boundaries or corners. If such markers are disturbed by accident, they shall be replaced by an approved land surveyor or civil engineer and all maps and records required therefrom shall be filed with the County and local authorities, at no cost to the College. All filing and plan check fees shall be paid by Contractor. (d) (e) (f) Provide to the College on request, the Contractor's written safety program and safety plan for each site. E. Covering and Cleaning: Cover and protect the College's property within the project limits, as required to prevent soiling or damage by dust, dirt, water, fumes, or otherwise as deemed necessary by the College or Program Manager. F. Repair or replace any damage to existing structures, improvements and equipment caused by Contractor's operations, at Contractor's expense. G. Repair or replace damaged work with new materials, to restore the damaged areas and surfaces equal to and matching, the conditions which existed prior to damage, or at start of the work of this Contract, at no cost to the College. RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 SPECIAL CONDITIONS 00800 PAGE 7 OF 8 H. Prior to start of work, Contractor, College and Construction Manager shall conduct an on-site inspection of existing conditions and the Contractor shall clearly document and report damaged conditions to the College. Items not reported to the College at time of inspection will be assumed to be result of Contractor's work, whose responsibility it will be to repair or replace those items. Contractors shall include, along with his report to the College, digital, dated photographs. 2.11 Landscape Repair and Additional Scope A. Patch all grass areas damaged by construction vehicles and equipment. Re-sod or hydroseed the area to its previous condition or better under the direction of the Construction Manager or College Maintenance Department. Do not use grass seeds. Replace any sprinklers or irrigation material damaged by construction activities. Upon completion of Work, Contractor shall restore grass areas to its previous conditions before start of construction operations. Prior to commencement of work, Contractor is to identify damaged and non-operational irrigation and landscape elements and report to the Construction Manager. B. Fire-Hydrant Protection: Contractor shall protect all Fire Hydrants in the site vicinity from any kind of damage due to construction activity. C. Contractor shall provide Construction traffic control including flagmen as necessary during deliveries. Contractor to provide flagmen and other traffic control personnel at any other location as may be deemed necessary by the construction manager-for safety of all students, staff and visitors. Contractor will follow pre-determined route for access and exit to the campus and shall direct/park all haul vehicles as directed by the Rio Hondo Program Management Team. END OF SECTION RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER PROJECT Addendum No.3 05/16/16 SPECIAL CONDITIONS 00800 PAGE 8 OF 8 SECTION 01010 PHASING OF THE WORK PART 1 - GENERAL 1.01 A. SECTION INCLUDES Requirements a. Comply with the requirements of Section 0800-2.5. 1.02 RELATED SECTIONS A. Section 01010: Phasing of Work – APPENDIX A – MILESTONES B. Section 01100: Summary of Work C. Section 01040: Project Coordination D. Section 01330: Submittal Procedures E. Section 01320: Construction Progress Documentation F. Section 01500: Construction Facilities and Temporary Controls G. Section 01770: Closeout Procedures PART 2 - PRODUCTS (Not used) PART 3 - EXECUTION 3.01 SUBMITTALS A. 3.02 CONTRACTOR shall submit a Project site logistics plans in accordance with the requirements of this Section. LOGISTICS A. Prior to the issuance of NTP -1, CONTRACTOR shall prepare and submit to Construction Manager, a detailed Project site logistic plan, in same size and scale of Drawings, setting forth CONTRACTOR plan of Work relative to the following items: 1. Haul route in accordance with local ordinances to and from Project site: 2. Identification of any overhead wire restrictions for power, street lighting, telecommunications or cable; 3. Local sidewalk access and street closure requirements; 4. Protection of sidewalk pedestrians and vehicular traffic; RIO HONDO COMMUNITY COLLEGE Pico Rivera Educational Center Addendum No.3 05/16/16 PHASING OF THE WORK 01010-PAGE 1 OF 3 5. Project site fencing and access gate locations; 6. Construction parking; 7. Material staging or delivery areas; 8. Material storage areas; 9. Temporary trailer(s) locations; 10. Temporary service location and proposed routing of all temporary utilities; 11. Trash removal and location of dumpsters; 12. Concrete pumping locations; 13 Crane locations; 14. Location of portable sanitary facilities; 15. Concrete mixer truck washout locations; 16. Traffic control signage; 17. Perimeter and site lighting; 18. Storm Water Pollution Prevention Plan – SWPPP; 19. Stockpile or lay down areas; 20. Security lighting. B. Revised Project site logistic plan may be required by Construction Manager for separately identified phases and segments of Work as set forth in this Section. C. CONTRACTOR is responsible for securing and/or obtaining all approvals and permits from authorities having jurisdiction over the work. PHASING OF THE WORK – GENERAL 3.03 A. CONTRACTOR shall prepare Construction Schedule in order to complete Work and related activities in accordance with phasing plan as established in Appendix “APPENDIX A – MILESTONES”. CONTRACTOR shall include all costs to complete all Work within Milestones or Contract Time. B. OWNER will be seriously damaged by not having all Work completed within Milestones or Contract Time. It is mandatory Work be complete within Milestones or Contract Time. C. The major phases/segments of the work are identified below and shall be followed with the following general guidelines. Phase 1 – Mobilization and issuance of NTP: RIO HONDO COMMUNITY COLLEGE Pico Rivera Educational Center Addendum No.3 05/16/16 PHASING OF THE WORK 01010-PAGE 2 OF 3 Work to start immediately following issue of initial Notice to Proceed “NTP I”. See Milestones 1, 2, 3 and 4; and requirements of Section 01500 and other related Sections. Notice to Proceed “NTP II” shall follow the successful completion of Phase I requirements. Phase 2 – Construction to Substantial Completion: Milestones 5, 6, 7. Construction to start following issuance of NTP Phase 2 is defined as completion of milestones 5, 6, 7. All work to be substantially complete as defined by Article 7.2.2 of General Conditions. Phase 3 - Administrative Closeout: Work includes substantial completion of the overall project and final completion of Work in accordance with Articles 7.2.2 and 7.2.4 of the General conditions, respectively. PHASING OF THE WORK – SPECIFIC 3.05 A. B. CONTRACTOR shall prepare Construction Schedule, and shall the complete following Milestones as shown in Section 01010 – Appendix A: 1. Phase 1: Mobilization – (10) calendar days: Milestones 1 2. Phase 2: Construction – (65) calendar days: Milestones 5, 6, & 7 3. Phase 3: Administrative Closeout – (14) calendar days: Milestones 8 The Contract Time shall be a total of (79) calendar days from date of commencement of Contract Time. END OF SECTION RIO HONDO COMMUNITY COLLEGE Pico Rivera Educational Center Addendum No.3 05/16/16 PHASING OF THE WORK 01010-PAGE 3 OF 3 01010 – PHASING OF THE WORK APPENDIX A – MILESTONES CONTRACTOR shall commence performance of the Contract upon the date specified in the Notice to Proceed and shall furnish sufficient forces, facilities and materials, work such hours, including extra shifts and overtime operations, so as to fully perform the Work in accordance with the following Milestones. Milestone No. 1 Description Schedule Phase 1 – Mobilization: Liquidated Damages Per Calendar Day Start date per Notice to Proceed– NTP: Is established in accordance with Articles 7.1 and 7.2.2 of the General NTP Conditions. No.2 Critical Shop Drawings & Submittals Complete: Is defined as CONTRACTOR prepared Shop Drawings and Submittals that are either critical or near critical to the overall Substantial Completion of the Project. Milestones may include, but not be limited to, Baseline Schedule per Article 7.3, schedule of values per Article 8.2, DSA Deferred Approvals, Steel and Shoring Drawings, Concrete and Piling Approvals, excavation support system drawings, seismic calculations if any , shoring system drawings, or any long lead fabrication/procurement item requiring Shop Drawings. 10 calendar days after the effective date of the NTP No. 3 Baseline Schedule Submitted: Is defined as baseline schedule in compliance with all the 10 Calendar requirements outlined in Article 7.3 and in Division 01 Sections 01320 and 01010 is completed days after the and submitted for CM review and approval. effective date of the NTP-I. No. 4 Completion of Mobilization activities: Is defined as CONTRACTOR mobilization completed, all submittals approved and lead-time items processed for procurement, logistics plan submitted and approved (access, gates, parking, trailer locations, signage), site fencing completed if needed, temporary utilities connections completed (water, electric, phone, sanitation, fire protection), Project signage completed, submit for and obtain all required permits, implementation of Storm Water Pollution Prevention measures, submission of CONTRACTOR Safety , submission of CONTRACTOR Hazard Communication Plan, and obtain approval ACM submittal 10 calendar days after the effective date of the NTP * Milestone date to be determined by CONTRACTOR during development of the Construction Schedule and submitted to the CM for approval. RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER ADDENDUM NO.3 05/16/16 -PHASING OF THE WORK - APPENDIX A - Milestone Description Schedule Liquidated Damages Per Calendar Day No. 5 Phase 2– Construction: Total of 79 Calendar days following Mobilization. No. 6 Substantial Completion for all Classrooms, Admin. Office, Staff Lounge/ Study Room Contract 55 Calendar work: Is established in accordance with Article 7.2.2 of the General Conditions. days after the $2,000.00 effective date of the NTP-I. No. 7 No. 8 79 Calendar days after the Start of Phase 2 Construction, as defined on Item 3.05.A.2 of this Section, stating Architect and effective date CM approved date to start actual demolition and construction activities. of NTP Work completion shall be defined as all work is substantially completed including but not limited to. Substantial Completion for all Exterior of Buildings, Site utilities, Hardscape and Landscape 65 Calendar $2,000.00 Contract work: Is established in accordance with Article 7.2.2 of the General Conditions. days after the effective date of the NTP-I Close out and Final Completion: Is established in accordance with Article 7.2.4 of the General 79 Calendar Conditions. days after the effective date of the NTP. * Milestone date to be determined by CONTRACTOR during development of the Construction Schedule and submitted to the CM for approval. RIO HONDO COMMUNITY COLLEGE PICO RIVERA EDUCATIONAL CENTER ADDENDUM NO.3 05/16/16 -PHASING OF THE WORK - APPENDIX A - EXHIBIT 1 Pico Rivera Audio Visual Equipment List Audio Visual Equipment Brand Hitachi Hitachi Chief Chief BMS Extron Draper Draper Shure Crestron Crestron Crestron Crestron Crestron Crestron Extron ELMO Sony Pakedge Spectrum Industries Panel Crafters Middle Atlantic Extron Middle Atlantic Extron Extron Extron Extron Middle Atlantic Model CP-WX3530WN Lamp and filter kit CMA110 CMS018024S LCDLOCIV PMK350 Screen Mount MX-418D/C SAROS IC6T-W-TEACH DMPS3-200-C DM-TX-200-C-2G-B-T PW-4818DU DM-RMC-SCALER-C MP-B20-B-T 60-1489-01 TT-12i BDP-S1200 S8PE Link Lectern Custom panel Custom shelf RSU 129 AUDD2 26-667-03 26-566-02 26-643-06 26-571-03 MIDHSK Quantity 1 1 1 1 1 1 1 1 1 6 1 1 1 1 1 1 1 1 1 1 1 1 3 1 8 1 1 1 1 Description 1280x800 3700 Lumen projector Lamp and filter kit 8" Ceiling plate Adjustable extension column Projector security mount Key#030 Low profile pole mount kit Manual 16:10 109" diagonal projection screen Mounting clips 18" gooseneck mic Ceiling speakers 3-Series DigitalMedia presentation system Wall plate DM transmitter 90W power pack for DMPS DM receiver and room controller w/scaler Media Presentation Button Panel B20 DSC HD-HD Document camera BluRay player 8 port Ethernet switch with PoE 36" Link lectern w/toe kick, overbridge, and document camera shelf Lectern input panel Custom shelf for BluRay player Extron rack shelf kit 2 RU drawer HDMI Micro Series, MicroDigital™ Ultra-Flexible HDMI Cables MVGA-A M-M, Male to Male 15-pin HD Micro HR with Audio Cables AV RCA, RCA Male to Male Composite Video and Stereo Audio Cables Mini Audio Cables, 3.5 mm Male to Male Stereo Audio Cables Screws, 100 Piece Security w/Washers Note : This equipment list is for one classroom. The audio/visual setup needs to be duplicated for all seven classrooms. Contractor is responsible for ordering equipment, and receivership and installation at seven classrooms. Addendum No.3 05/16/16 Pico Rivera Audio Visual Equipment List v1_0.xlsx Rio Hondo College Classroom Audio Visual Standard Specification The Pico Rivera Education Center will contain 6 classrooms and one computer lab for a total of 7 rooms with AV systems. Equipment to be used: A. Projector: Use Hitachi minimum 3500 ANSI lumen, minimum 1280x800 resolution, HDMI connection, with wired networking. B. Screen: Draper or equivalent with a 16:10 aspect ratio.Screen height should be at least 1/6 the distance from the screen to the furthest seat. C. Audio: a. Ceiling mounted speakers b. Appropriate amplifier(s) to power speakers c. Line level audio to feed an assisted listening system D. Instructor Station: Lectern with an included 12U rack space in a locking enclosure, overbridge with a 3 gang and 2 gang cutout for control and input panels, cable paths, and standard 110 AC outlet. E. Signal matrixing and routing: Digital and analog video and audio switcher/scaler with inputs for: a. Digital PC (HDMI, DisplayPort, etc.) b. Two additional HDMI ports c. VGA d. Composite F. Control panel: MPC series from Crestron. Control buttons to be labeled and include functions as required: a. Projector power toggle b. Volume control c. Microphone audio control (separate from program audio) gain up/down/mute d. Source selection: i. Rack PC ii. DVD/Bluray player iii. HDMI Laptop iv. VGA Laptop v. Aux Video vi. Projector Image Mute (separate from audio) G. AV connection panels: a. Wall input panel with appropriate device connection plates as required (HDMI, speaker, control) b. Instructor Station input panel (HDMI, VGA +3.5mm audio, Composite w/ RCA audio, Female XLR, 3.5mm ALS output) H. Wired gooseneck microphone I. Option for future wireless microphone Addendum No.3 5/16/2016 3:39 PM RHC PREC Classroom.docx Page 1 of 2 Rio Hondo College Classroom Audio Visual Standard Specification Room arrangement A. Instructor Station at room front B. Display a. Projection screen at room front mounted with the bottom of the screen at least 40-48” from the floor b. Projector ceiling mounted with a security mount centered to screen C. Speakers ceiling mounted D. Media sources and inputs a. Media sources are located in the equipment rack located in the Instructor Station i. Dedicated owner furnished computer located in rack ii. DVD/Bluray player located in rack iii. Laptop/Doc cam connections (HDMI, VGA + audio) on input panel ontop of Instructor Station iv. Microphone located at Instructor Station E. ALS output located at input panel on top of Instructor Station F. Audio and video signal matrixing/routing equipment is located in the Instructor Station rack G. Control Systems a. Push-button control panel with built-in control system will be mounted on top ofthe Instructor Station b. Control processingequipment is located in the Instructor Stationrack Integration Services A. All equipment, cabling, and accessories required for a fully function classroom AV system B. Labor associated with turnkey engineering, installation, programming, testing, and training C. Coordination with campus project manager D. Documentation and engineering package including as-built system CAD diagrams and manufacturer’s manuals E. User training on classroom system F. 1 year warranty Addendum No.3 5/16/2016 3:39 PM RHC PREC Classroom.docx Page 2 of 2 GENERAL NOTES SYMBOL LIST (ALL SYMBOLS NOT NECESSARILY USED ON THESE DRAWINGS) ALL SYMBOL DESCRIPTIONS ARE SUBJECT TO MODIFICATION AS NOTED ON THE DRAWINGS. VERIFY EXACT LOCATIONS AND HEIGHTS OF OUTLETS WITH ARCHITECTURAL INTERIOR ELEVATIONS PRIOR TO ROUGH-IN. A.F.F. ABOVE FINISH FLOOR A.F.G. ABOVE FINISH GRADE AWG AMERICAN WIRE GAUGE AMP, A AMPERE AF/AT AMP FRAME, AMP TRIP AS/AF AMP SWITCH, AMP FUSE AV AUDIO VISUAL CIRC., CKT. CIRCUIT CB CIRCUIT BREAKER C CONDUIT DENOTES CONDUIT(S) RISING UP. C.O. CONDUIT ONLY MODULAR BUILDING GROUND ROD. SEE DETAIL 3/E-005. CONN CONNECTED DIA DIAMETER EMCS ENERGY MANAGEMENT CONTROL SYSTEM EMT ELECTRICAL METALLIC TUBING EWC ELECTRIC WATER COOLER E-O-L END-OF-LINE CIRCUIT TERMINATOR EF EXHAUST FAN LIGHTING FIXTURE, SURFACE OR PENDANT MOUNTED, ON FLUSH CEILING MOUNTED OUTLET BOX. ER EXISTING EQUIPMENT TO BE REMOVED LIGHTING FIXTURE, RECESS MOUNTED, WITH OUTLET BOX. E EXISTING EQUIPMENT FT. OR ' FEET FA FIRE ALARM FLA FULL LOAD AMPS GFI GROUND FAULT INTERRUPTER GRD GROUND HVAC HEATING, VENTILATING AND AIR CONDITIONING H.,W.,D.,L. HEIGHT, WIDTH, DEPTH, LENGTH HP HORSEPOWER COMBINATION DATA/POWER/AV FLOOR BOX WITH TWO (2) DATA OUTLETS AND ONE (1) DUPLEX RECEPTACLES, EQUAL TO FSR #FL-500P SERIES. PROVIDE 1-1/4"CONDUIT WITH TWO (2) DATA CABLES FROM THE BOX TO THE ACCESSIBLE CEILING SPACE AND ON TO THE RESPECTIVE MDF/IDF. IDF INTERMEDIATE DISTRIBUTION FRAME IN. OR " INCHES COMBINATION DATA/POWER/AV FLOOR BOX WITH FOUR (4) DATA OUTLETS AND TWO (2) DUPLEX RECEPTACLES, EQUAL TO FSR #FL-500P SERIES. PROVIDE 1-1/4"CONDUIT WITH FOUR (4) DATA CABLES FROM THE BOX TO THE ACCESSIBLE CEILING SPACE AND ON TO THE RESPECTIVE MDF/IDF. IG ISOLATED GROUND J-BOX JUNCTION BOX KVA KILOVOLT AMPERES KW KILOWATT LCL LONG CONTINUOUS LOAD L.O. LUGS ONLY LTG, LTS LIGHTING MCB MAIN CIRCUIT BREAKER MDF MAIN DISTRIBUTION FRAME MH METAL HALIDE MCC MOTOR CONTROL CENTER MCM THOUSAND CIRCULAR MILS COMPUTER/DATA PROCESSING SYSTEM - 3/4"C., WITH ONE(1) CAT6 CABLE AS SPECIFIED. D2 - 1"C., WITH TWO(2) CAT6E CABLES AS SPECIFIED. D3 - 1 1/4"C., WITH THREE(3) CAT6E CABLES AS SPECIFIED. D4 - 1 1/4"C., WITH FOUR(4) CAT6E CABLES AS SPECIFIED. MCP MOTOR CIRCUIT PROTECTOR MLO MAIN LUGS ONLY MTD MOUNTED CLOCK OUTLET, ON FLUSH WALL MOUNTED OUTLET BOX, +90" WITH CLOCK. CLOCK SHALL BE WIRELESS GPS BATTERY OPERATED BY PRIMEX OR EQUAL. NEC NATIONAL ELECTRICAL CODE NC NORMALLY CLOSED NO NORMALLY OPENED COMPUTER/DATA OUTLET WITH SINGLE DATA OUTLET CONNECTOR, ON FLUSH IN WALL OUTLET BOX, +18". PROVIDE OUTLET BOX, DATA JACKS, FACE PLATE, ETC. AND 1" CONDUIT TO THE ACCESSIBLE CEILING SPACE UNLESS NOTED OTHERWISE. PROVIDE CAT 6E DATA NETWORK CABLE AS SPECIFIED FROM THE OUTLET TO THE RESPECTIVE MDF/IDF. NIC NOT IN CONTRACT NO. OR # NUMBER PRIMARY OVER 600 VOLTS COMPUTER/DATA OUTLET WITH TWO (2) DATA OUTLET CONNECTORS, ON FLUSH IN WALL OUTLET BOX, +18". PROVIDE OUTLET BOX, DATA JACKS, FACE PLATE, ETC. AND 1" CONDUIT TO THE ACCESSIBLE CEILING SPACE UNLESS NOTED OTHERWISE. PROVIDE TWO (2) CAT 6E DATA NETWORK CABLES AS SPECIFIED FROM THE OUTLET TO THE RESPECTIVE MDF/IDF. PH. OR PHASE PROVIDE FURNISH, INSTALL AND CONNECT PA PUBLIC ADDRESS COMPUTER/DATA OUTLET WITH SEVEN (7) DATA OUTLET CONNECTORS, ON FLUSH IN WALL OUTLET BOX, +18". PROVIDE OUTLET BOX, DATA JACKS, FACE PLATE, ETC. AND 1" CONDUIT TO THE ACCESSIBLE CEILING SPACE UNLESS NOTED OTHERWISE. PROVIDE SEVEN (7) CAT 6E DATA NETWORK CABLES AS SPECIFIED FROM THE OUTLET TO THE RESPECTIVE MDF/IDF. REC, RECEPT RECEPTACLE REF REFRIGERATOR RGS RIGID GALVANIZED STEEL VOICE/DATA OUTLET WITH TWO (2) DATA OUTLET CONNECTORS AND ONE(1) VOICE CONNECTOR, ON FLUSH IN WALL OUTLET BOX, +18". PROVIDE OUTLET BOX, DATA JACKS, FACE PLATE, ETC. AND 1" CONDUIT TO THE ACCESSIBLE CEILING SPACE UNLESS NOTED OTHERWISE. PROVIDE THREE (3) CAT 6E DATA NETWORK CABLES AS SPECIFIED FROM THE OUTLET TO THE RESPECTIVE MDF/IDF. RL RELOCATED EXISTING EQUIPMENT SECONDARY 600 VOLTS AND LESS O INDICATES DEVICE ON SURFACE WALL MOUNTED OUTLET BOX. COMPUTER/DATA OUTLET WITH TWO (2) DATA OUTLET CONNECTORS, ON CEILING MOUNTED OUTLET BOX, FOR WIRELESS ACCESS POINT. PROVIDE OUTLET BOX, DATA JACK, FACE PLATE, ETC. PROVIDE TWO (2) CAT 6E DATA NETWORK CABLE AS SPECIFIED FROM THE OUTLET TO THE RESPECTIVE MDF/IDF. TV TELEVISION TYP TYPICAL U.N.O. UNLESS NOTED OTHERWISE V VOLTS VA VOLT AMPERES WP WEATHERPROOF W WIRE DFCI DISTRICT FURNISHED CONTRACTOR INSTALLED DFDI DISTRICT FURNISHED DISTRICT INSTALLED BLDG. BUILDING IWB INTERACTIVE WHITE BOARD AVC AUDIO/VIDEO CABINET 1P SINGLE POLE 2P DOUBLE POLE 3P TRIPLE POLE 1. PORTIONS OF THESE PLANS HAVE BEEN DERIVED FROM INFORMATION TAKEN FROM ORIGINAL ELECTRICAL PLANS. THE INTENT OF THESE PLANS IS TO PROVIDE COMPLETE AND OPERABLE SYSTEMS. 2. ABBREVIATIONS IT IS THE CONTRACTOR'S RESPONSIBILITY TO VISIT THE SITE AND BECOME THOROUGHLY FAMILIAR WITH ALL THE FEATURES OF THE BUILDING AND SITE WHICH WAY AFFECT THE PROPER PERFORMANCE OF THIS WORK. JUNCTION BOX, FLUSH WALL MOUNTED, +18''. JUNCTION BOX CONCEALED ABOVE ACCESSIBLE CEILING AREA OR MOUNTED ON ROOF. 3. IT IS THE CONTRACTOR'S RESPONSIBILITY TO REFER TO THE DRAWINGS OF OTHER TRADES FOR ADDITIONAL DETAILS AND REQUIREMENTS WHICH AFFECT THE PROPER PERFORMANCE OF THIS WORK. DUPLEX CONVENIENCE RECEPTACLE VERTICAL ON FLUSH CEILING MOUNTED OUTLET BOX, +18". P DUPLEX CONVENIENCE RECEPTACLE VERTICAL ON FLUSH WALL MOUNTED OUTLET BOX, +18". INDICATES WALL MOUNTED OUTLET BOX, TYPICAL. INDICATES CONNECTION TO EQUIPMENT AS REQUIRED, TYPICAL. A E-1 4. RACEWAY ROUTING, DIMENSIONS, AND EQUIPMENT LOCATIONS ARE APPROXIMATE. CONTRACTOR SHALL FIELD VERIFY ALL DIMENSIONS AND EXACT RACEWAY ROUTING TO CONFORM TO FIELD CONDITIONS. PANELBOARD, ADJACENT LINE INDICATES PANEL FRONT. ADJACENT BALLOON INDICATES PANEL DESIGNATION ''A'', SEE DRAWING E-1 FOR PANEL SCHEDULE. DOUBLE DUPLEX (FOUR-PLEX) CONVENIENCE RECEPTACLE ON ONE FLUSH WALL MOUNTED OUTLET BOX TERMINAL CABINET. ADJACENT LINE INDICATES CABINET FRONT. CIRCUIT BREAKER STATIONARY (NON-DRAWOUT) SECONDARY VOLTAGE. EQUIPMENT CABINET. ADJACENT LINE INDICATES CABINET FRONT. ELECTRICAL DOWN TIME MUST BE APPROVED BY THE COLLEGE. CONTRACTOR SHALL MAKE PROVISIONS TO ACCOMPLISH THE WORK OF THIS CONTRACT WITHOUT UNDUE INTERFERENCE WITH COLLEGE OPERATIONS. ALL EQUIPMENT DEVICES, CONDUIT FITTINGS, JUNCTION BOXES, AND CONSTRUCTION LOCATED OUTDOORS SHALL BE WEATHERPROOF. 7. ALL SIGNAL AND FIRE ALARM SYSTEMS TERMINATIONS MADE IN JUNCTION BOXES SHALL BE EXECUTED USING TERMINAL BLOCKS. 8. 9. S SINGLE POLE TOGGLE SWITCH, ON FLUSH WALL MOUNTED OUTLET BOX, +45". INSTALL MULTIPLE SWITCHES UNDER COMMON COVER PLATE. SUBSCRIPT OR SUPERSCRIPT AT SWITCH SYMBOL INDICATES THE FOLLOWING: 2 - DOUBLE POLE 4 - FOUR WAY M - MANUAL MOTOR STARTERS 3 - THREE WAY P - PILOT LIGHT K - KEY OPERATED R - SPDT MOMENTARY CONTACT RELAY SWITCH V - VAPOR PROOF a,b,c,d, ETC. - MULTIPLE SWITCHES WITH IDENTIFICATION OF OUTLET CONTROLLED. 2,P a,b 2 100 1 VISIT THE SITE PRIOR TO BID AND INVESTIGATE THE EXISTING FIRE ALARM, TELEPHONE, INTRUSION DETECTION, EMS, CLOCK, INTERCOM/PA, TELEVISION AND DATA SYSTEMS EQUIPMENT ON CAMPUS. COORDINATE WITH THE EXISTING SYSTEMS MANUFACTURERS FOR ALL REQUIRED EQUIPMENT MODIFICATIONS, CONDUIT, WIRING AND UPGRADING REQUIRED TO EXTEND THE EXISTING SYSTEMS TO THE NEW MODULAR BUILDINGS. INCLUDE ALL COSTS IN BID. ALL NEW COMPONENTS SHALL BE COMPATIBLE WITH THE EXISTING SYSTEM. 2. PAINT ALL EXPOSED RACEWAYS TO MATCH SURROUNDING SURFACE COLOR. 3. PROVIDE GROUNDING SYSTEM PER DETAIL 3/E005. WHERE METAL RAMPS OR RAILWAYS ARE USED PROVIDE 1#2 BONDING ELECTRODE FROM THE RAMPS AND RAILWAYS TO THE STRUCTURAL STEEL MEMBER OF THE BUILDING. 4. PROVIDE WEATHERPROOF SEALANT AROUND PRECAST CONCRETE PULL BOX COVERS AFTER WORK IS COMPLETED WITHIN BOX. B-5,7,9 J UNDERGROUND CONDUIT STUBOUT, STUB 5'-0'' FROM BUILDING OR WALKWAY, CAP, MARK AND RECORD. E EXISTING CONDUIT. F FIRE ALARM SYSTEM - 3/4"C. WITH FIRE ALARM SYSTEM CONDUCTORS AS SPECIFIED. P PUBLIC ADDRESS SYSTEM - 3/4"C., WITH CONDUCTORS AS SPECIFIED. P2 - 3/4"C WITH CONDUCTORS AS SPECIFIED. TELEVISION SYSTEM - 1"C. WITH CONDUCTORS AS SPECIFIED. ID INTRUSION DETECTION SYSTEM - 3/4"C. WITH CONDUCTORS AS SPECIFIED. AV S PUBLIC ADDRESS/CLASS PASSING SPEAKER, HOUSING AND GRILL, FLUSH WALL MOUNTED, +90". S PUBLIC ADDRESS/CLASS PASSING SPEAKER, HOUSING & GRILLE, FLUSH CEILING MOUNTED. S CLASSROOM AUDIO ENHANCEMENT SPEAKER IN FLUSH CEILING MOUNTED BACKBOX. AV D1 INTRUSION DETECTION SYSTEM MOTION SENSOR, ON FLUSH CEILING MOUNTED OUTLET BOX. ID 1D 2D 1 2D WAP COMPUTER/DATA OUTLET WITH ONE (1) DATA OUTLET CONNECTORS, ON CEILING MOUNTED OUTLET BOX, FOR CEILING MOUNTED PROJECTOR. PROVIDE OUTLET BOX, DATA JACK, FACE PLATE, ETC. PROVIDE ONE (1) CAT 6E DATA NETWORK CABLE AS SPECIFIED FROM THE OUTLET TO THE RESPECTIVE MDF/IDF. P VC1 AUDIO/VIDEO INPUT WALLPLATE EXTRON PVT SW HDMI RGB D ON FLUSH WALL MOUNTED 2-GANG EXTRA 3 1/2" DEEP AT +18" A.F.F. PROVIDE 1"C. TO ACCESSIBLE CEILING SPACE. REFER TO SHEET E-0.2 FOR AV SYSTEM REQUIREMENTS. VC MEDIALINK CONTROLLER EXTRON MLC 104 IP PLUS ON FLUSH WALL MOUNTED 2-GANG EXTRA 3 1/2" DEEP AT +48"A.F.F. PROVIDE 1"C. TO ACCESSIBLE CEILING SPACE. REFER TO SHEET E-0.2 FOR AV SYSTEM REQUIREMENTS. TELEVISION OUTLET ON FLUSH WALL MOUNTED OUTLET BOX, +18" WITH A DUPLEX UNIVERSAL OUTLET CONNECTOR AND A TWISTED SHIELDED PAIR RJ CONTROL JACK. PROVIDE A 1" CONDUIT TO ACCESSIBLE CEILING SPACE. TV THE ATTACHMENT OF THE FOLLOWING MECHANICAL AND ELECTRICAL COMPONENTS SHALL BE POSITIVELY ATTACHED TO THE STRUCTURE, BUT NEED NOT BE DETAILED ON THE PLANS. THE PROJECT INSPECTOR WILL VERIFY THAT THESE ITEMS HAVE BEEN POSITIVELY ATTACHED. THESE COMPONENTS SHALL HAVE FLEXIBLE CONNECTIONS PROVIDE BETWEEN THE COMPONENT AND ASSOCIATED DUCTWORK, PIPING, AND CONDUIT. A. COMPONENTS WEIGHING LESS THAN 400 POUNDS AND HAVE A CENTER OF MASS LOCATED 4 FEET OR LESS ABOVE THE ADJACENT FLOOR OR ROOF LEVEL THAT DIRECTLY SUPPORT THE COMPONENT. B. COMPONENTS WEIGHING LESS THAN 20 POUNDS, OR IN THE CASE OF DISTRIBUTED SYSTEMS, LESS THAN 5 POUNDS PER FOOT, WHICH ARE SUSPENDED FROM A ROOF OR FLOOR OR HUNG FROM A WALL. FBA Engineering Consulting Electrical Engineers 150 Paularino Avenue Suite A120 Costa Mesa, CA 92626 949.852.9995 949.852.1657 (fax) fbaengr.com FBA Job Number: 223.029 LIGHTING FIXTURE RECESSED MOUNTED WITH OUTLET BOX AND REMOTE MOUNTED JUNCTION BOX CONCEALED ABOVE ACCESSIBLE CEILING. PROVIDE FLEXIBLE CONDUIT CONNECTION 6 FT. MAXIMUM LENGTH, 1/2" DIAMETER MINIMUM, FROM JUNCTION BOX TO FIXTURE OUTLET. PROVIDE CONDUCTORS IN CONDUIT, QUANTITY AS REQUIRED FOR INDICATED CIRCUITS AND SWITCHING CONTROLS, #12 (AWG) MINIMUM. COMBINATION DATA/POWER/AV FLOOR BOX WITH SIX (6) DATA OUTLETS AND TWO (3) DUPLEX RECEPTACLES, EQUAL TO FSR #FL-500P SERIES. PROVIDE 1-1/4"CONDUIT WITH FOUR (4) DATA CABLES FROM THE BOX TO THE ACCESSIBLE CEILING SPACE AND ON TO THE RESPECTIVE MDF/IDF. 05-16-2016 Addendum No.3 SHEET INDEX TOP OF BOX TOP OF CONTROL FOR THOSE ELEMENTS THAT DO NOT REQUIRE DETAILS ON THE APPROVED DRAWINGS, THE INSTALLATION SHALL BE SUBJECT TO THE APPROVAL OF THE MECHANICAL/ELECTRICAL ENGINEER. 24" MAX 34" MAX 48" MAX FBA Engineering / Plot Date: 5/11/2016 4:57 PM / Plotted by: Jeff Gomez / Drawing Location: I:\223\029\E001_223029.dwg 6D WEATHERPROOF PUBLIC ADDRESS/CLASS PASSING SPEAKER, HOUSING & GRILLE, FLUSH WALL MOUNTED, +90". WP S 3. MOVABLE EQUIPMENT WHICH IS STATIONED IN ONE PLACE FOR MORE THAN 8 HOURS AND HEAVIER THAN 400 POUNDS ARE REQUIRED TO BE ANCHORED WITH TEMPORARY ATTACHEMENTS. PIPING, DUCTWORK, AND ELECTRICAL DISTRIBUTION SYSTEMS SHALL BE BRACED TO COMPLY THE FORCE AND DISPLACEMENTS PRESCRIBED IN ASCE 7-10 SECTION 13.3 AS DEFINED IN ASCE 7-10 SECTION 13.6.8, 13.6.7, 13.6.5.6, AND 2013 CBC, SECTIONS 1616A.1.23,1616A.1.24, 1616A.1.25 AND 1616A.1.26. AV 1 MEP COMPONENT ANCHORAGE NOTE: PIPING, DUCTWORK, AND ELECTRICAL DISTRIBUTION SYSTEM BRACING NOTE AV 4D TV 1V 2. TEMPORARY OR MOVABLE EQUIPMENT THAT IS PERMANENTLY ATTACHED (E.G. HARD WIRED) TO THE BUILDING SERVICES SUCH AS ELECTRICITY, GAS OR WATER. 2D INDICATES CONDUIT SLEEVE(S) THROUGH WALL ABOVE THE CEILING. NUMBER AND SIZE OF CONDUITS AS NOTED. 2D 1. ALL PERMANENT EQUIPMENT AND COMPONENTS. LIGHTING FIXTURE WITH LAMPS ON NORMAL AND EMERGENCY LIGHTING CIRCUITS, PROVIDE SEPARATE LAMP BALLASTS AS REQUIRED. HOMERUN TO PANEL "B" FOR CIRCUITS 5, 7, 9 WITH COMMON NEUTRAL 7D ALL MECHANICAL, PLUMBING, AND ELECTRICAL COMPONENTS SHALL BE ANCHORED AND INSTALLED PER THE DETAILS ON THE DSA APPROVED CONTRUCTION DOCUMENTS. WHERE NO DETAIL IS INDICATED, THE FOLLOWING COMPONENTS SHALL BE ANCHORED OR BRACED TO MEET THE FORCE AND DISPLACEMENT REQUIREMENTS PRESCRIBED IN THE 2013 CBC, SECTIONS 1616A.1.18 THROUGH 1616A.1.26 AND ASCE 7-10 CHAPTER 6 TO 30. OUTLET ON EMERGENCY LIGHTING CIRCUIT. 1775 Hancock St, Suite 120 San Diego, CA 92110 619.542.1188 619.542.1663 Fax CONDUIT, INSTALLED EXPOSED. 9. PROVIDE NEW TELEPHONE(S), SPEAKERS, DATA OUTLETS, AUDIO/VISUAL SYSTEMS AND CLOCKS IN MODULAR BUILDINGS WHERE INDICATED ON DRAWINGS. EQUIPMENT ANCHORAGE NOTES LIGHTING FIXTURE, SURFACE OR FLUSH MOUNTED AS INDICATED ON FIXTURE SCHEDULE, ON WALL MOUNTED OUTLET BOX, +90". STEM INDICATES WALL MOUNTED OUTLET BOX, TYPICAL. CONDUIT, INSTALLED CONCEALED IN OR UNDER FLOOR OR BELOW GRADE, 3/4"C. MINIMUM. 6. PROVIDE CORE DRILLING OF ALL STRUCTURES AS REQUIRED FOR RACEWAY ROUTING AND DISCOVERED SITE CONDITIONS. 8. WHERE NEW CONDUCTOR(S)/CABLING IS SPECIFIED IN EXISTING CONDUITS CONTAINING EXISTING WIRING THE CONTRACTOR SHALL REMOVE ENOUGH OF THE EXISTING WIRING TO PULL IN NEW PLUS REPLACEMENT OF EXISTING REMOVED. FLUORESCENT LIGHTING FIXTURE, RECESS MOUNTED, WITH OUTLET BOX. CONDUIT, INSTALLED CONCEALED IN WALL OR IN CEILING SPACE. 1/2" C - 2 #12, 1#12(GRD) 3/4" C - 6 #12, 1#12(GRD) 1/2" C - 3 #12, 1#12(GRD) 1" C - 7 #12, 1#12(GRD) 3/4" C - 4 #12, 1#12(GRD) 1" C - 8 #12, 1#12(GRD) 3/4" C - 5 #12, 1#12(GRD) 1 1/4" C - 9 #12, 1#12(GRD) 5. PROVIDE APPROVED WEATHERPROOF SEALANT AROUND ALL WALL PENETRATIONS. SEAL IN A MANNER ACCEPTABLE TO THE ARCHITECT. 7. RECONNECT EXISTING CIRCUITS FOR EQUIPMENT THAT IS TO REMAIN IF DISRUPTED BY WORK PERFORMED UNDER THIS CONTRACT. MAINTAIN CONTINUITY OF ALL FEED THRU WIRING. LIGHTING INSTRUCTORS CONTROL STATION ON FLUSH IN WALL OUTLET BOX, +45". PLAN NOTE CALLOUT. REFER TO CORRESPONDING NOTE ON DRAWING WHERE CALLOUT OCCURS. 13. PROVIDE OZ COMPANY TYPE "DX" EXPANSION/DEFLECTION FITTINGS WITH BONDING JUMPER ON ALL CONDUITS AT ALL BUILDING EXPANSION OR SEISMIC JOINT CROSSINGS. 1. D DETAIL CALLOUT, "C" INDICATES DETAIL, "E-2" INDICATES DRAWING WHERE DETAIL OCCURS. 11. WHERE POSSIBLE ALL RACEWAYS SHALL BE ROUTED CONCEALED IN WALLS AND/OR ABOVE ACCESSIBLE CEILING SPACE. PERFORMANCE NOTES LIGHTING ENTRANCE CONTROL STATION ON FLUSH IN WALL OUTLET BOX, +45". FLUORESCENT LIGHTING FIXTURE, SURFACE OR PENDANT MOUNTED ON FLUSH MOUNTED OUTLET BOX. 10. VERIFY THE EXACT LOCATION OF THE RELOCATABLE BUILDING PANELBOARD WITH THE BUILDING MANUFACTURER PRIOR TO ROUGH-IN. 12. UNLESS SPECIFICALLY SHOWN ON THESE PLANS NO STRUCTURAL MEMBER SHALL BE CUT NEITHER DRILLED NOR NOTCHED WITHOUT PRIOR WRITTEN AUTHORIZATION FROM THE STRUCTURAL ENGINEER AND THE DIVISION OF THE STATE ARCHITECT. E FIXTURE SCHEDULE DESIGNATION: "2" INDICATES FIXTURE TYPE, "100" INDICATES FIXTURE TOTAL WATTAGE. SIGNAL AND/OR FIRE ALARM SYSTEMS SPLICES ARE NOT PERMITTED IN UNDERGROUND PULLBOXES. ALL ELECTRICAL EQUIPMENT INCLUDING PANELS, OUTLET BOXES, CONDUITS, ETC. SHALL BE ANCHORED TO BUILDING STRUCTURE. ANCHORING SHALL BE DESIGNED FOR 1.0 GRAVITY LATERAL ACCELERATION OF THE EQUIPMENT. 1 FINISHED FLOOR APPROACH PARELLEL APPROACH 44" MAX PERPENDICULAR 6. LIGHTING FIXTURE, SURFACE OR FLUSH MOUNTED AS INDICATED ON FIXTURE SCHEDULE, ON WALL MOUNTED OUTLET BOX, +90". STEM INDICATES WALL MOUNTED OUTLET BOX, TYPICAL. 46" MAX 5. 14471 Chambers Rd, Suite 210 Tustin, CA 92780 714.508.1780 714.508.1780 Fax E001 SYMBOL LIST, NOTES AND DETAILS E002 SINGLE LINE DIAGRAM AND DETAILS E003 LIGHTING FIXTURE SCHEDULE AND DETAILS E004 LIGHTING CONTROL DIAGRAM E005 TITLE 24 INDOOR LIGHTING CALCULATIONS E006 TITLE 24 OUTDOOR LIGHTING CALCULATIONS E007 DETAILS E008 PANEL SCHEDULES E100 DEMOLITION SITE ELECTRICAL PLAN E101 OVERALL SITE ELECTRICAL PLAN E102 ENLARGED SITE ELECTRICAL PLAN E103 SITE LIGHTING CALCULATIONS E200 DEMOLITION BUILDING ELECTRICAL PLANS E201 BUILDING LIGHTING PLANS E202 BUILDING POWER PLANS E203 BUILDING TELECOMMUNICATIONS PLANS E301 FIRE ALARM SCHEDULES AND DETAILS E302 BUILDING FIRE ALARM PLANS IDENTIFICATION STAMP DIV. OF THE STATE ARCHITECT OFFICE OF REGULATION SERVICES AC FLS SS DATE THE BRACING AND ATTACHMENTS TO THE STRUCTURE SHALL BE DETAILED ON THE APPROVED DRAWINGS OR THEY SHALL COMPLY WITH ONE OF THE OSHPD PRE-APPROVALS (OPM#) AS MODIFIED TO SATISFY ANCHORAGE REQUIREMENTS OF ACI 318, APPENDIX D. COPIES OF THE MANUAL SHALL BE AVAILABLE ON THE JOBSITE PRIOR TO THE START OF HANGING AND BRACING OF THE PIPE, DUCTWORK, AND ELECTRICAL DISTRIBUTION SYSTEMS. MIN.15" A.F.F. BOTTOM OF BOX OUTLET BOX NOTE: MAINTAIN 30" X 48" CLEAR PARALLEL APPROACH FLOOR AREA AND CONTROLS MOUNTING HEIGHT OVER OBSTRUCTION SCALE: N.T.S. 1 SYMBOL LIST, NOTES AND DETAILS E001 1 14471 Chambers Rd, Suite 210 Tustin, CA 92780 714.508.1780 714.508.1780 Fax 1775 Hancock St, Suite 120 San Diego, CA 92110 619.542.1188 619.542.1663 Fax FBA Engineering Consulting Electrical Engineers 150 Paularino Avenue Suite A120 Costa Mesa, CA 92626 949.852.9995 949.852.1657 (fax) fbaengr.com FBA Job Number: 223.029 FBA Engineering / Plot Date: 5/11/2016 4:46 PM / Plotted by: Jeff Gomez / Drawing Location: I:\223\029\E008_223029.dwg 05-16-2016 Addendum No.3 IDENTIFICATION STAMP DIV. OF THE STATE ARCHITECT OFFICE OF REGULATION SERVICES AC FLS SS DATE PANEL SCHEDULES E008 4 A E007 2 D-17,19 TYPICAL A-14,16 1 B - 4 1 PANEL D-13,15 C - PANEL 5 1 15 1 5 D E007 4 E - PANEL 10 4 A-17,19 21 17 17 D-9,11 9 11 13 15 1 16 D-21,23 1 5 14 23 17 19 14 19 19 5 5 22 5 14471 Chambers Rd, Suite 210 Tustin, CA 92780 714.508.1780 714.508.1780 Fax 22 D-22,24 5 19 E-12 17 P 16 5 P P 24 14 3 16 1775 Hancock St, Suite 120 San Diego, CA 92110 619.542.1188 619.542.1663 Fax 3 12 3 12 12 18 12 14 A-18,20 8 18 8 FBA Engineering 22 Consulting Electrical Engineers 22 9 AV 20 24 9 AV AV 10 20 150 Paularino Avenue Suite A120 Costa Mesa, CA 92626 949.852.9995 949.852.1657 (fax) fbaengr.com 11 D-10,12,14,16 9 12 14 16 18 12 D-18,20 20 FBA Job Number: 223.029 18 13 14 BUILDING ELECTRICAL PLAN SCALE: 1/8" = 1'-0" 2 PLAN NOTES: 1 PANEL SUPPLIED WITH BUILDING. VERIFY EXACT LOCATION WITH MODULAR RESTROOM BUILDING MANUFACTURER'S DRAWINGS. 2 PROVIDE SPLIT WIRED DUPLEX RECEPTACLE CONTROLLED BY THE RESPECTIVE ROOMS LIGHTING CONTROLS IN ACCORDANCE WITH 2013 CEC TITLE 24 SECTION 130.1(C). TYPICAL FOR ALL RECEPTACLES IN PRIVATE OFFICES, OPEN OFFICE AREAS, RECEPTION LOBBY, CONFERENCE ROOMS, KITCHENETTES AND COPY ROOMS. REFERENCE 2/E003 FOR ADDITIONAL REQUIREMENTS. 1 3 1 ALL EXISTING ELECTRICAL OUTLETS, POWER CONNECTIONS, AND ASSOCIATED CONDUIT AND WIRING SHALL REMAIN AS IS UNLESS SPECIFICALLY INDICATED OTHERWISE. 6 1 4 DISCONNECT AND REMOVE THE EXISTING PANEL AND REPLACE WITH NEW RECESSED 24 CIRCUIT PANELBOARD, 225 AMPERE 120/240V.1PH.3 WIRE WITH 100 AMP 2P MAIN CIRCUIT BREAKER, FLUSH MOUNT. RECONNECT EXISTING CIRCUITS AND FEEDER TO REMAIN TO THE NEW PANELBOARD. PROVIDE NEW TYPEWRITTEN CIRCUIT DIRECTORY. 5 CONNECT TO TWO(2) 20 AMP, 1 POLE CIRCUIT BREAKERS IN NEW PANEL WITH 4#12, 1#12 GRD. - 3/4"C. 6 CONNECT TO THE EXISTING FEEDER TAP. WP 7 3 E006 PANEL AV 7 CONNECT TO THE PANELBOARD SUPPLIED WITH THE BUILDING. 8 ROUTE CONDUIT BELOW FLOOR, SAWCUT AND PATCH AS REQUIRED. 8 9 P 1 PROVIDE (N) COMBINATION POWER/DATA/AV FLUSH IN FLOOR BOX FOR CONNECTION TO LECTERN. VERIFY EXACT LOCATION PRIOR TO ROUGH-IN. SEE SYMBOL LIST AND TELECOM PLANS FOR ADDITIONAL REQUIREMENTS. 10 DISCONNECT AND REMOVE THE EXISTING PANEL AND REPLACE WITH NEW RECESSED 30 CIRCUIT PANELBOARD, 225 AMPERE 120/240V.1PH.3 WIRE WITH 100 AMP 2P MAIN CIRCUIT BREAKER, FLUSH MOUNT. RECONNECT EXISTING CIRCUITS AND FEEDER TO REMAIN TO THE NEW PANELBOARD. PROVIDE NEW TYPEWRITTEN CIRCUIT DIRECTORY. 11 CONNECT TO FOUR(4) 20 AMP, 1 POLE CIRCUIT BREAKERS IN NEW PANEL WITH 8#10, 2#10 GRD. - 1 1/4"C. 4 1 1 9 G - 3 5 PANEL AV H - 4 8 05-16-2016 Addendum No.3 1 12 CONNECT TO TWO(2) 20 AMP, 1 POLE CIRCUIT BREAKERS IN NEW PANEL WITH 4#10, 2#10 GRD. - 1"C. 9 P FBA Engineering / Plot Date: 5/11/2016 4:56 PM / Plotted by: Jeff Gomez / Drawing Location: I:\223\029\E202_223029.dwg 1 13 PROVIDE TWO COMPARTMENT SURFACE RACEWAY, FOR POWER AND DATA OUTLETS, WIRING AND CABLE. SURFACE RACEWAY SHALL BE MOUNTED HORIZONTAL AT +18". PROVIDE ALL POWER RECEPTACLES AND DATA OUTLETS AS INDICATED. RACEWAY SHALL BE WIREMOLD 4000 SERIES, STEEL AND IN FINISH AS SELECTED BY ARCHITECT. PROVIDE ALL BENDS, COVERPLATES, OFF-SETS, ETC. FOR A COMPLETE INSTALLATION. 14 PROVIDE VERTICAL TWO COMPARTMENT RACEWAY TO ABOVE THE ACCESSIBLE CEILING. 5 3 PANEL 15 PROVIDE NEW BRANCH FEEDER TAP DUE TO LOAD INCREASE. PROVIDE 3#10, 1#6 GRD. - 2"C. AND CONNECT TO THE EXISTING MAIN FEEDER. INCLUDE ALL COSTS IN BID. AV I - 4 8 1 9 P 1 5 3 PANEL AV J - 4 8 1 9 P 1 3 5 IDENTIFICATION STAMP DIV. OF THE STATE ARCHITECT OFFICE OF REGULATION SERVICES AC FLS SS DATE BUILDING ELECTRICAL PLANS BUILDING ELECTRICAL PLAN SCALE: 1/8" = 1'-0" 1 E202 1 11 12 PROVIDE TWO COMPARTMENT SURFACE RACEWAY, FOR POWER AND DATA OUTLETS, WIRING AND CABLE. SURFACE RACEWAY SHALL BE MOUNTED HORIZONTAL AT +18". PROVIDE ALL POWER RECEPTACLES AND DATA OUTLETS AS INDICATED. RACEWAY SHALL BE WIREMOLD 4000 SERIES, STEEL AND IN FINISH AS SELECTED BY ARCHITECT. PROVIDE ALL BENDS, COVERPLATES, OFF-SETS, ETC. FOR A COMPLETE INSTALLATION. PLAN NOTES: (E)TELEPHONE BACKBOARD/MPOLE 1 PROVIDE DATA NETWORK OUTLET IN WEATHERPROOF OUTLET BOX, +8'-0", FOR CONNECTION TO CCTV CAMERA, TYPICAL. 2 PROVIDE NEW OUTLET BOX, FLUSH IN CEILING, FOR INTRUSION DETECTION SENSOR. RECONNECT TO THE EXISTING INTRUSION DETECTION SYSTEM CONDUIT AND WIRING. PROVIDE VERTICAL TWO COMPARTMENT RACEWAY TO ABOVE THE ACCESSIBLE CEILING. 3 (E)MAIN DISTRIBUTION FRAME "MDF" 5 6 PROVIDE COMPLETE CLASSROOM AUDIO/VISUAL SYSTEM IN ACCORDANCE WITH CLASSROOM AV WIRING. PROVIDE ALL CONDUIT, CABLING AND DEVICES FOR A COMPLETE INSTALLATION. 2D 1V 1 PROVIDE TWO(2) 3"C. SLEEVES FOR VOICE AND DATA NETWORK CABLING. PROVIDE EXPANSION/DEFLECTION FITTINGS AND INSULATED THROAT BUSHINGS ON CONDUIT ENDS. 2D 1V 1D 131D 13V 1D 1 25D 7V 4 10 81D 9V 4 3 2D AP 1 34D 8V 4 3 STUB TWO(2) 3"C. CONDUITS FOR VOICE AND DATA NETWORK CABLING INTO THE ACCESSIBLE CEILING SPACE. 14471 Chambers Rd, Suite 210 Tustin, CA 92780 714.508.1780 714.508.1780 Fax 8 1 1D 1 1775 Hancock St, Suite 120 San Diego, CA 92110 619.542.1188 619.542.1663 Fax 1 4 3 2 2 2D AP 2D AP PROVIDE TWO(2) 3"C. WITH VOICE AND DATA NETWORK CABLING. SAWCUT AND PATCH PAVING FOR INSTALLATION OF CONDUITS. 1D 2 STUB 1 1/2"C. INTO ACCESSIBLE CEILING SPACE. PROVIDE DATA NETWORK CABLING TO MDF AS INDICATED. 10 7D 2D PROVIDE 1 1/2"C. FOR DATA NETWORK AND AV CABLING, SAWCUT AND PATCH FLOOR. PROVIDE 18" X 18" X 8" DEEP W.P. GALVANIZED SHEET STEEL PULLBOX, NEMA 3R, WITH TAMPER RESISTANT SCREWS. PROVIDE LABEL TO READ: "VOICE/DATA". 7D 2D 1V PROVIDE (N)COMBINATION POWER/DATA/AV FLUSH IN FLOOR BOX FOR CONNECTION TO LECTERN. VERIFY EXACT LOCATION PRIOR TO ROUGH-IN. SEE SYMBOL LIST AND POWER PLAN FOR ADDITIONAL REQUIREMENTS. 9 1D 1 15D 5V 1D 2D 1V 2D 1V 6 1D WP 2D AP 1D 7 1 2D AV 8 7D 1 1 7 7D 2D 1V 1 4 9 2D 1V 5 2D AP 2D 1V 1D 7 1 2D 7 1 2D 5 2D 1V 1D 2D FBA Engineering 2 2D 5 AV 3D 3D 2D AV 4D 6 Consulting Electrical Engineers 2D AP 150 Paularino Avenue Suite A120 Costa Mesa, CA 92626 949.852.9995 949.852.1657 (fax) fbaengr.com 6 TO MDF FBA Job Number: 223.029 12D 1D WP 1D WP 11 12 1 BUILDING TELECOMMUNICATIONS PLAN 2 SCALE: 1/8" = 1'-0" PLENUM SPK 18 SPEAKER CABLE (17.5 FT.) PLENUM SPK 18 SPEAKER CABLE (17.5 FT.) FF120 42-120-03 FF120 42-120-03 1 39D,4V 10 PVT PVT SW HDMI RGB D 60-1335-03 HDMI 001 HDMI [F TYPE A] A +18" PROJECTOR MOUNT TO INCLUDE THE FOLLOWING: HOUSED INSIDE PVM 220 IR [2 POLE CS] 002 AUDIO PROJECTOR (NOT INCLUDED IN PVS SYSTEM) RGBHV [HD15-F] LOCAL OUT [HD15-F] AUDIO [F 3.5 JACK] AUDIO [F 3.5 JACK] 8 7 2D 1V PCM 340 UPB 25 PVT OUT [F RJ-45] AUDIO [F 3.5 JACK] RGB 1D WP 1D 39D 4V 6 1 9 2D AV HDMI 2 RS-232 2D AP 5 3 PVS PVS 405SA IP 60-1235-01 1D PLENUM SHIELDED TWISTED PAIR CABLE (50 FT.) 1/2 PLENUM SHIELDED TWISTED PAIR CABLE (50 FT.) 3/4 PVT IN [F RJ-45] 005 AUDIO [5 POLE CS] AUD LINEOUT [5 POLE CS] AUX [3 POLE CS] HDMI [F TYPE A] PLENUM SHIELDED CAT-5 TWISTED PAIR CABLE (15 FT.) PVT IN [F RJ-45] PLENUM RATED MLC IR/RS-232 CABLE (50 FT.) VOICELIFT Rx [F RJ-45] LAN 2 [F RJ-45] PAGING SENSOR [3 POLE CS] LAN 3 [F RJ-45] IR OVER PVT [2 POLE CS] POWER RS-232 [3 POLE CS] PLENUM RATED STP 22 CABLE (OPTIONAL) PLENUM RATED PWR/RS-232/VC POWER CABLE (50 FT.) 05-16-2016 Addendum No.3 2D AV 1 2 PVT PVT SW HDMI D 60-1270-03 HDMI 001 HDMI [F TYPE A] AUDIO [F 3.5 JACK] IR [2 POLE CS] HDMI 002 B (IN FLOOR BOX) 2D AP 5 PVT OUT [F RJ-45] 3 ID HDMI [F TYPE A] 1D AUDIO [F 3.5 JACK] MLC-01 IDF Rx B Tx MLS RS-232 VOICELIFT SYSTEM DISPLAY RS-232 / IR GND +12V OUT PART No. 42-139-02 CONT MOD IR IN PENDANT AND HANDHELD SYSTEM SCP COM E PART No. 42-139-22 COMM LINK B C D GND TWO PENDANTS SYSTEM 1 2 GND A 2D AP 5 1 A PART No. 42-139-01 2D AV 1D 4 6 Rx IR OUT GND ONE PENDANT SYSTEM 20D 2V 7 1 Tx PWR +12V IN 1D 2D 1V M +45" MLC 104 IP PLUS 60-818-03 DIGITAL I/O ID A FBA Engineering / Plot Date: 5/11/2016 4:49 PM / Plotted by: Jeff Gomez / Drawing Location: I:\223\029\E203_223029.dwg 1D 4 6 1 A 29D 3V 7 2D 1V LAN 1 [F RJ-45] ID 1D AMPLIFIED AUD [4 POLE CS] 3 2 3 GND 1D 1D ETHERNET 11D 1V 7 CHARGING STATION 2D 1V 6 1 2D AV 1D 4 1 2 PLENUM RATED STP22 CABLE (NOT INCLUDED IN KIT) 2D AP 5 3 IDENTIFICATION STAMP DIV. OF THE STATE ARCHITECT OFFICE OF REGULATION SERVICES EXTRON VOICELIFT MIC IR RECEIVER 1D 1D WP 1D 1D WP TYPICAL 1 AC FLS SS DATE (E)INTERMEDIATE DISTRIBUTION FRAME "IDF" BUILDING TELECOMMUNICATION PLANS CLASSROOM AV WIRING BUILDING TELECOMMUNICATIONS PLAN SCALE: 1/8" = 1'-0" 1 E203