Impact of Ozone NAAQS Program on Urban Areas Gale Lea Rubrecht In South Coast Air Quality Management District v. EPA, 472 F.3d 882 (2006), clarified, 489 F.3d 1245 (D.C. Cir. 2007), cert. denied, 76 U.S.L.W. 3095 (U.S. Jan. 14, 2008), the D.C. Circuit vacated and remanded the Phase I 8-Hour Ozone Implementation Rule (the Rule) (69 Fed. Reg. 23,951; Apr. 30, 2004) to the U.S. Environmental Protection Agency (EPA). The implications of the decision will be felt in urban areas as states implement the 8-hour ozone national ambient air-quality standard (NAAQS). On remand, areas could be reclassified in a way that would mean sooner attainment dates and more stringent controls for sources of emissions in those areas. The decision will also result in significant emission fees for some sources and additional emission offset and control technology requirements for new sources in some areas unless EPA provides relief in its rule-makings on remand. The decision resolved questions concerning the transition from the 1-hour standard to the 8-hour standard that was promulgated more than a decade ago. For example, the court held that EPA need not wait to impose new standards until existing standards had been achieved. The court established EPA’s authority to revoke a standard as long as adequate antibacksliding measures are introduced. The court held that 1-hour requirements may be retained, even if the controls are not already incorporated into state implementation plans (SIPs). In the court’s words: “The [Clean Air] Act [CAA] placed states onto a one-way street whose only outlet is attainment.” The court also agreed with state and environmental petitioners that 1-hour new source review (NSR) requirements, penalties for “severe” and “extreme” 1-hour areas under § 185(a) of the CAA, contingency plans for failure to attain the 1-hour standard, and 1-hour transportation conformity determinations were all “controls” that could not be withdrawn without constituting impermissible backsliding in violation of the antibacksliding provision found in CAA § 172(e). The court’s conclusions that each of these measures is a “control” and that withdrawing any of them would constitute impermissible backsliding became the subject of a petition for a writ of certiorari filed by industry groups in the U.S. Supreme Court. Although the D.C. Circuit rendered its decision in December 2006, the decision did not take effect until more than eight months later when the mandate issued in August 2007. Meanwhile, EPA and those affected by the decision analyzed its implications. Three months after the decision, EPA addressed some of the implications in a memorandum dated March 19, 2007, and a supplemental notice on proposed rulemaking (SNPR) published on March 22. Nearly ten months after the decision, EPA addressed NSR aspects of the decision in an October 3, 2007, memorandum. In the March 19, 2007, memorandum, William L. Wehrum, then Acting Administrator for Air, ended speculation as to whether the decision would delay the June 15, 2007, deadline for the submission of 8-hour ozone SIPs. Notwithstanding SIP obligations that may change when the court decision is final, EPA “strongly encourage[d]” states to continue to develop and submit 8-hour ozone SIPs by the deadline. With respect to NSR requirements, EPA stated that new NSR permits must, at a minimum, meet current applicable 8-hour requirements. In the October 3, 2007, memorandum, Robert J. Meyers, Principal Deputy Assistant Administrator, found that the court’s ruling “restore[d] NSR applicability thresholds and emission offsets pursuant to classifications previously in effect for areas designated non-attainment for the 1-hour ozone standards.” EPA promised rulemaking to address long-term applicability of 1-hour NSR requirements. NSR requirements are important for any company contemplating building a new or modifying an existing major stationary source. EPA also addressed redesignations in the March 19, 2007, memorandum and asked the Regional Offices to take final action on pending redesignation proposals. EPA stated that for many areas that have 8-hour attainment air quality based on 2004–2006 data, it planned to use its Clean Data Policy to suspend certain SIP requirements as long as areas now meeting the standard remain in attainment for the 8-hour standard. These SIP requirements that EPA has suspended include attainment demonstrations, reasonable further progress plans, and contingency measures. EPA addressed pending redesignation requests again in a March 22, 2007, SNPR (72 Fed. Reg. 13,452). EPA proposed to find that the court decision imposed no impediment to moving forward with pending proposed rules to redesignate areas to attainment, and EPA has in fact moved forward with finalizing redesignations. In the March 22, 2007, SNPR, EPA also cautioned that “it is possible that [areas classified under Subpart 1] could, during a remand to EPA, be reclassified under Subpart 2.” Classification is important for determining attainment dates and control requirements. Areas classified under Subpart 1 are required to achieve attainment of the primary NAAQS “as expeditiously as practicable,” but no later than five years from the date such areas were designated nonattainment, except that EPA may extend the attainment date for a period no greater than ten years from the nonattainment designation date. Attainment deadlines for areas classified under Subpart 2 are set forth in Table 1 of CAA § 181 and range from three to twenty years from the date of designation, depending upon the severity of the nonattainment. EPA may grant up to two one-year extensions if certain statutory requirements are met. The 8-hour ozone designations took effect June 15, 2004 (69 Fed. Reg. 23,858; Apr. 30, 2004). Thus, for areas subject to Subpart 1, the attainment deadline would be June 15, 2009, unless EPA extends the attainment date, whereas for areas subject to Subpart 2, the attainment deadline would be as early as June 15, 2007, for “marginal” areas and June 15, 2010, for “moderate” areas. None of the litigants was happy with the decision, and on March 22, 2007, the parties petitioned the court for panel rehearing or rehearing en banc. The court generally denied the petitions on June 8, 2007. However, the court granted a joint request by EPA and the Published in Natural Resources & Environment Volume 22, Number 4, Spring 2008. © 2008 by the American Bar Association. Reproduced with permission. All rights reserved. This information or any portion thereof may not be copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association. environmental petitioners to limit the scope of the vacatur of the Rule to the extent that the court sustained challenges to it. As a result, implementation of the 8-hour standard may proceed in urban areas in the Northeast and elsewhere classified under Subpart 2. With respect to the antibacksliding provisions, the court said EPA’s determination that CAA § 172(e) supports the introduction of antibacksliding measures was “reasonable.” The court concluded that industry’s interpretation that antibacksliding measures are not required when EPA strengthens, as opposed to relaxes, a NAAQS would have “absurd results,” finding “nothing to suggest that Congress intended such a glaring loophole.” Within one week of the court’s denial of EPA’s rehearing petition, EPA Acting Assistant Administrator Meyers issued a memorandum dated June 15, 2007, addressing the implications of the court’s June 8, 2007, decision. EPA announced it would not make findings of failure to submit SIPs before August 15, 2007. Thus, EPA in effect gave Subpart 2 areas an additional two months to submit their 8-hour ozone SIPs. EPA also found that because the court vacated the Subpart 1 classifications and because SIP submission dates are based on an area’s classification, Subpart 1 areas are not currently subject to the June 15, 2007, submission date for their attainment demonstrations. Following unsuccessful motions for a partial stay of the mandate concerning the antibacksliding provisions, industry groups petitioned the U.S. Supreme Court for a writ of certiorari in September 2007. Issues presented in the petitions include (1) whether the court correctly held that CAA § 172(e) applies to require retention of measures related to a revoked NAAQS that EPA replaced with a more stringent standard, and (2) even if § 172(e) applies, whether the court correctly held that EPA violated its terms. The U.S. Supreme Court denied review on January 14, 2008. Under the Rule, 1-hour nonattainment areas (NAAs) would be constrained only by the NSR requirements for their 8-hour classification. For example, the Washington, DC-MD-VA “severe” ozone NAA had not attained the 1-hour ozone standard as of June 15, 2005, when EPA revoked the 1-hour standard, and was classified as a “moderate” NAA for the 8-hour standard. NSR requires “major” sources to include technology consistent with the lowest achievable emissions rate and to offset any increased emissions with greater reductions elsewhere. A “major” source is defined according to its emission threshold, and the emission thresholds for defining “major” sources in areas subject to only Subpart 1 and in “marginal” and “moderate” NAAs under Subpart 2 are higher than in “serious,” “severe,” and “extreme” areas under Subpart 2. For any “moderate” area, the terms “major source” and “major stationary source” include any stationary source that emits or has the potential to emit at least 100 tons per year, whereas for any “serious,” “severe,” and “extreme” areas, the terms “major source” and “major stationary source” include any stationary source that emits or has the potential to emit, at least 50, 25, and 10 tons per year, respectively. The offset requirement for the ratio of total emission reductions to total emission increase under Subpart 1 is 1 to 1. The offset requirements under Subpart 2 are 1.1 to 1 in “marginal” areas, 1.15 to 1 in “moderate” areas, 1.2 to 1 in “serious” areas, 1.3 to 1 in “severe” areas, and 1.5 to 1 in “extreme” areas. Thus, the Rule would include only stationary sources in the Washington, DC-MD-VA area that emit or have the potential to emit at least 100 tons per year instead of 25 tons per year and would require such stationary sources to have a ratio of total emission reductions to total increased emissions of at least 1.15 to 1 instead of 1.3 to 1. The court rejected this interpretation of the antibacksliding provision in the CAA. A SIP for a “severe” or “extreme” area must require major stationary sources of volatile organic compounds (VOCs) and, unless EPA grants an exemption, nitrogen oxides (NOx) to pay an emission fee if the area fails to attain by its attainment date. The fee is payable for each calendar year beginning after the attainment date and continues until the area is redesignated as attainment. The court determined that the fees continue to apply after revocation of the 1-hour standard. The attainment deadline for the Baton Rouge, Louisiana “severe” 1-hour ozone NAA was November 15, 2005. Because the area did not attain the 1-hour standard by November 15, 2005, any VOC and/or NOx major stationary sources in that area must pay § 185 fees beginning in 2006 until the area is redesignated as attainment. Estimates of those fees for businesses in Baton Rouge range from $65 to $100 million a year. The court’s decision created an enormous amount of uncertainty for urban areas with air quality above the 8-hour standard. Implementation of the standard may proceed in areas classified under Subpart 2, while areas erroneously classified under Subpart 1 are in limbo. EPA has said it plans to issue three regulations in 2008 to address the provisions of the Rule vacated by the decision. Early in 2008 EPA plans to propose regulations to remove the vacated provisions. By summer 2008 EPA plans to propose two regulations to address (1) classification of Subpart 1 areas and 1-hour NSR requirements for antibacksliding and (2) § 185 fees and contingency measures for 1-hour NAAs. Meanwhile, full implementation is delayed while EPA completes rulemakings on classifications, NSR requirements, and § 185 fees. Ms. Rubrecht is a member of Jackson Kelly PLLC, in Charleston, West Virginia, and a member of the editorial board of Natural Resources & Environment. She may be contacted at galelea@ jacksonkelly.com. Published in Natural Resources & Environment Volume 22, Number 4, Spring 2008. © 2008 by the American Bar Association. Reproduced with permission. All rights reserved. This information or any portion thereof may not be copied or disseminated in any form or by any means or stored in an electronic database or retrieval system without the express written consent of the American Bar Association.