INTEGRATION OF SMED AND TRIZ IN IMPROVING PRODUCTIVITY AT SEMICONDUCTOR INDUSTRY KARTIK SREEDHARAAN KUMARESAN UNIVERSITI TEKNOLOGI MALAYSIA INTEGRATION OF SMED AND TRIZ IN IMPROVING PRODUCTIVITY AT SEMICONDUCTOR INDUSTRY KARTIK SREEDHARAAN KUMARESAN A project report submitted in fulfillment of the requirements for the award of the degree of Master of Engineering (Industrial Engineering) Faculty of Mechanical Engineering Universiti Teknologi Malaysia MAY 2011 iii In dedication to my beloved parents and wife iv ACKNOWLEDGEMENT My sincere appreciation and thanks to my supervisor Assoc. Prof. Dr. Muhamad Zameri b. Mat Saman for his supervision, constructive critics and the continuous guidance to furnish this project paper to an accepted quality. I am also indebted to my sponsor Intel Technology Sdn. Bhd. whom has supported me financially throughout my tenure as a post graduate student. Also would like to extend my appreciation to Mr. Ismail Ishak and Mr. TJ Yeoh from Intel KMCO, who provided technical assistance at various occasions throughout this project. Without their continued support and interest, this thesis would not have been the same as presented here. I would take this opportunity also to recognize my parents, wife, family members and friends for their unconditional love and support. Last but not least, none of this would be possible without the blessing and grace of the Almighty God ‘Anbe Sivam’. v ABSTRACT A case study on a test handler’s changeover process was conducted in a semiconductor organization (Intel Technology Sdn. Bhd.). The test handler being a constraint operation in the production supports the testing of two of the mainstream chipset products. Though the test handler is capable to support multiple chipset products but due to the equipment configuration complexity, the changeover process today requires an average 4 hours to fully complete. The long changeover duration degrades the overall productivity especially inability to meet customer demand timely, lower utilization and rising cost issues. These identified issues are potential factors that could impact the sustainability of the organization in long run. This case study focuses on improving the changeover process using techniques from Single Minute Exchange of Die (SMED) and Theory of Inventive Problem Solving (TRIZ). Both the techniques have individual strengths and weakness and thus the focus will be to integrate them to complement each other to enhance the changeover process duration further. Problems in the current process like non standard practices, complex hardware setup and waste activities that plagued today are process were identified and categorized accordingly. Later, appropriate techniques from SMED and TRIZ were proposed to counter these issues systematically. SMED will be used mostly for task simplification while TRIZ will be used for hardware part redesigns and overall process optimization. The end of mind of this study is to achieve a lean and optimized changeover process that can be performed below 30 minutes with no safety, quality or output concerns. vi ABSTRAK Kajian kes ini bertumpu amnya pada pengubahsuaian mesin di Intel Technology Sdn. Bhd yang merupakan pemgeluar cip komputer terbesar di dunia. Mesin yang digunakan di operasi pemeriksaan cip silikon secara automatik ini mampu mengendali pelbagai jenis cip tetapi memerlukan pengubahsuaian tertentu. Proses pengubahsuaian mesin ini boleh memakan masa sehingga 4 jam untuk disiapkan sebelum digunakan balik untuk operasi. Disebabkan ini, organisasi ini mengalami kemerosotan produktiviti and juga kerugian kos-kos lain. Untuk mengatasi masalah ini, teknik-teknik daripada SMED and TRIZ diperkenalkan untuk menyelesaikan isu –isu seperti ketidakselarasan aktiviti dan penukaran alat ganti yang kompleks. Teknik SMED and TRIZ dikaji secara teliti sebelum dicadangkan untuk penyelesaian. Teknik-teknik SMED banyak digunakan untuk mempermudahkan activiti kerja dan teknik-teknik TRIZ banyak berguna untuk mereka bentuk alat ganti yang lebih mudah dan efiksyen untuk ditukar ganti. Cadangan-cadangan ini setelah dilaksanakan dapat membantu mengurangkan masa pengubahsuaian daripada 4 jam kepada 30 minit dengan tiada sebarang masalah kualiti, keselamatan ataupun pengeluaran. vii TABLE OF CONTENTS CHAPTER 1 TITLE PAGE DECLARATION ii DEDICATION iii ACKNOWLEDGEMENTS iv ABSTRACT v ABSTRAK vi TABLE OF CONTENTS vii LIST OF TABLES xii LIST OF FIGURES xiv LIST OF ABBREVIATIONS xviii INTRODUCTION 1.1 Overview 1 1.2 Background of Problems 1 1.3 Statement of Problems and Justification 3 1.4 Objective of Study 3 1.5 Scopes 3 1.6 Significance of Study 4 1.7 Thesis Structure 4 viii 2 LITERATURE REVIEW 2.1 Overview 5 2.2 Lean Manufacturing 5 2.2.1 History and Background 7 2.2.2 Lean Concepts 8 2.2.3 Lean Tools 9 2.2.4 The ‘bright side’ of Lean 10 2.2.5 The ‘Anti’ Lean Sentiment 11 2.3 2.4 2.5 2.6 3 Optimization of Changeover Process 13 2.3.1 Changeover and PM 14 2.3.2 Benefits of Quick Changeover 15 2.3.3 Alternatives to Quick Changeover 15 Single Minute Exchange of Die (SMED) 15 2.4.1 Advantages of SMED 18 2.4.2 Disadvantages of SMED 19 Theory of Inventive Problem Solving (TRIZ) 20 2.5.1 History and Background 20 2.5.2 Conceptual Basis of TRIZ 21 2.5.3 Common TRIZ terminologies 24 2.5.4 Tools in TRIZ field 25 2.5.5 Application and Implementation of TRIZ 28 2.5.6 Shortcomings of TRIZ 29 Summary 31 METHODOLOGY OF RESEARCH 3.1 Overview 32 3.2 Research Objective 32 3.3 Analyzing Research Methods 33 3.4 Description of Research Methods 35 3.4.1 36 Secondary Data Study ix 3.4.2 4 Primary Data Study 37 3.5 Limitation of Research Methods 40 3.6 Summary 41 PROBLEM IDENTIFICATION 4.1 Overview 42 4.2 Background and Justification 42 4.2.1 Low Tester Utilization 43 4.2.2 Drive for Flexible Manufacturing 44 4.2.3 Driving Cost Competitive Advantage 45 4.3 Case Study Company 46 4.3.1 Background 47 4.3.2 KMCO 47 4.4 Product Background 48 4.5 Process Background 50 4.6 Equipment Background 52 4.7 Changeover Process Historical Study 54 4.8 Changeover Process Flow in Detail 55 4.9 Problems and Gaps Identification 85 4.9.1 Pre Changeover Activities 87 4.9.2 Preliminary Soft Setups 88 4.9.3 Hardware Part Setups 90 4.9.4 TIU Replacement 99 4.9.5 PnP Teaching Process 100 4.9.6 Dry Cycling Validation 102 4.9.7 TP Download Phase 105 4.9.8 Standard Unit Validation 106 4.9.9 Wrap Up Activities 107 4.10 Summary 109 x 5 PROPOSED FRAMEWORK 5.1 Overview 110 5.2 Strategy and Execution for Counter Measures 110 5.3 Process Flow Optimization 113 5.3.1 Upfront Setup Improvement Proposals 116 5.3.2 TP Download Improvement Proposals 122 5.3.3 Validation/Calibration Improvement Proposals 125 5.3.4 Post Setup Activities Alignment Proposals 127 5.4 6 Optimizing Hardware Setups phase 130 5.4.1 Proposals to Identify Fungible Parts 132 5.4.2 Proposals to Identify Non Fungible Parts 132 5.4.2.1 Non Fungible Parts With Multi Function 132 5.4.2.2 Non Fungible Parts With Hardware Redesign 133 5.5 Human Dynamic and Procurement Improvement Proposal 135 5.6 Summary 136 RESULT AND DISCUSSION 6.1 Overview 137 6.2 Implementation of Pre Setup phase 137 6.3 Improving of TP Download phase 146 6.4 Improving of Hardware Setup phase 149 6.4.1 Identified ‘fungible’ parts 149 6.4.2 Identified ‘non fungible’ parts 153 6.4.3 Redesigning hardware parts 155 6.4.3.1 Nest redesign 155 6.4.3.2 One turn screw design 162 6.5 Improvement of PnP teaching phase 171 6.6 Improvement of mechanical unit validation 176 6.7 Improvement of standard unit validation 182 6.8 Elimination of wrap up phase 188 6.9 The new optimized test handler changeover process 189 xi 6.10 7 Return of Investment (ROI) analysis 191 6.10.1 Capital and cost savings 192 6.10.2 Total utilization indicator improvement 194 6.10.3 Learner and Efficient Training 196 6.11 Critical Appraisal 197 6.12 Future Recommendation / Studies 198 6.13 Summary 199 CONCLUSION 200 REFERENCES 201 xii LIST OF TABLES TABLE TITLE PAGE 2.1 The seven deadly waste in Lean context 6 3.1 Categories of observations 39 4.1 Physical attributes comparison 50 4.2 Physical attributes comparison to NPI 51 4.3 Hardware parts involve in the changeover 64 4.4 Summary of the changeover process 86 4.5 Problems identified at the pre changeover phase 88 4.6 Problems identified at the preliminary soft setup 89 4.7 Sequence of the contactor chuck replacement 92 4.8 Problems identified during hardware part changes 98 4.9 Problems identified during the TIU replacement phase 100 4.10 Problems identified during the PnP teaching phase 102 4.11 Problems identified during the dry cycling phase 104 4.12 Problems identified during the TP download phase 105 4.13 Problems identified during the standard unit validation 107 4.14 Problems identified during the wrap up activities phase 108 5.1 The 5 pre requisite items and current practice 117 5.2 The ‘Beforehand Cushioning’ proposal 118 5.3 The activity dependency table 119 5.4 Technician idle time 126 5.5 ‘Merging’ technique on identifying NVA activities 127 5.6 The current hardware setup phase 131 5.7 Technician headcount per shift 136 xiii 6.1 Pre setup improvement result 138 6.2 The new ‘End Lot’ process sequence 141 6.3 The TP Download improvement result 146 6.4 The identified ‘fungible’ hardware parts 151 6.5 The identified non ‘fungible’ hardware parts 153 6.6 The steps in changing the ‘nest’ size 158 6.7 The actual changeover steps with new ‘nest’ design 160 6.8 The functionality of the one turn screw 164 6.9 The result of the hardware setup proposals 165 6.10 The time study result of new improved hardware setup 167 6.11 The improvement result of PnP teaching phase 172 6.12 The result of dry cycling phase proposals 177 6.13 The result of the standard unit validation proposals 183 6.14 The result of the wrap up phase elimination 188 6.15 Time study of the overall new optimized changeover process 190 6.16 The actual tool savings by factories for Q3’11 193 6.17 The contribution of TRIZ 197 xiv LIST OF FIGURES FIGURE TITLE PAGE 2.1 General changeover process 13 2.2 Shingo’s original SMED model 16 2.3 Shingo’s conceptual stages and techniques 17 2.4 SMED in Lean context 18 2.5 The 40 Inventive Principal 21 2.6 The 4 element model of TRIZ 23 2.7 The contradiction matrix 26 2.8 Tools in TRIZ field 27 3.1 Research Methodology flow 35 4.1 Breakdown of tester utilization 43 4.2 The corporate utilization goal 43 4.3 Example of demand trend 44 4.4 Cost breakdown of Nebula 45 4.5 Inventory impact analysis 46 4.6 Intel Kulim’s topography 47 4.7 KMCO’s Factory View 48 4.8 Nebula and Nexus sample units 49 4.9 Product roadmap illustration 50 4.10 The process flow 52 4.11 The M4542AD Dynamic Handler 53 4.12 Test module setup 53 4.13 Time trend of conversion from Q2’10 to Q4’10 54 4.14 The generic changeover flow 56 xv 4.15 Generic activities in pre changeover phase 57 4.16 Generic activities in preliminary soft setups 59 4.17 The change of AEPT state 59 4.18 The change of ‘sticky’ tag indicators 60 4.19 The ‘Andon’ light 60 4.20 The use of barricades 61 4.21 Reset temperature in the GUI 61 4.22 Manual turn off by pressing ‘TEMP’ button 62 4.23 Example of change kit box with hardware parts 62 4.24 Complete tool sets 63 4.25 Example of a TIU 67 4.26 Generic flow of TIU replacement phase 68 4.27 Rear of the handler 69 4.28 The ‘Clamper’ button 69 4.29 The position wheels to move the TIU and test head 70 4.30 Docked TIU on test head 71 4.31 Generic flow of PnP teaching phase 72 4.32 The command menu 73 4.33 Starting the teach sequence 74 4.34 Completing the teaching sequence 75 4.35 Existing the PnP teaching phase 76 4.36 Generic flow of dry cycling phase 77 4.37 Generic flow of TP download phase 79 4.38 Change of CTSC environment 80 4.39 TP download status 81 4.40 Choosing STD1 summary 81 4.41 Generic flow of standard unit validation 83 4.42 Generic flow of wrap up activities 84 4.43 Time study of pre changeover activities 87 4.44 Time study of preliminary soft setups 89 4.45 Time study of hardware part changes 91 4.46 Time study of TIU change phase 99 4.47 Time study of PnP teaching phase 101 xvi 4.48 Time study of dry cycling phase 103 4.49 Time study of TP download phase 105 4.50 Time study of standard unit validation 106 4.51 Time study of wrap up activities 108 5.1 The changeover duration factors 111 5.2 The generic proposal model 111 5.3 Extraction of proposal techniques 112 5.4 The generic ‘non optimized’ changeover flow 113 5.5 The ‘serial’ flow of activities 114 5.6 Illustration of ‘segmented’ of TIU phase 120 5.7 The changeover process flow with upfront setup proposals 122 5.8 Segmented TP download phase 5.9 The changeover process flow with TP download 123 improvement proposals 124 5.10 The new aligned post setup phase 129 5.11 The changeover process flow with wrap up phase elimination proposal 130 5.12 Current contactor chuck setup 134 5.13 Current ‘nest’ design 134 5.14 X- pitch blocks 135 5.15 The current screw design 135 6.1 The new pre setup activity flow 142 6.2 Illustration of pre setup phase development 143 6.3 Actual time study of new pre setup phase 144 6.4 Illustration of changeover process change with pre setup phase improvement 145 6.5 TP Download activity breakdown 148 6.6 Illustration of changeover process change with TP download phase improvement 148 6.7 The transfer pick up assembly 150 6.8 The Nebula and Nexus tray difference 150 6.9 The new ‘nest’ design 157 6.10 Old versus new ‘nest’ design comparison 157 xvii 6.11 New chuck (L) and old chuck (R ) comparison 158 6.12 The current X pitch block and screw design 163 6.13 The X pitch block with new screw design 163 6.14 Illustration of hardware setup executed as parallel activity 170 6.15 Illustration of changeover process change with optimized hardware setup 171 6.16 Actual time study of the improved PnP teaching phase 174 6.17 Illustration of PnP teaching phase with activity breakdown 175 6.18 Illustration of the changeover process change with improved PnP teaching phase 175 6.19 The improved dry cycling activity flow 180 6.20 Illustration of the improved dry cycling phase buildup 180 6.21 Actual time study of the improvised dry cycling phase 181 6.22 Illustration of changeover process change with improved dry cycling phase 6.23 182 Activity flow of the improvised standard unit validation phase 186 6.24 Actual time study of the improved validation phase 186 6.25 Illustration of the changeover process change with improvised standard unit validation phase 6.26 187 The new flow of post changeover activities replacing wrap up phase 189 6.27 The new optimized changeover flow 191 6.28 The capital purchase ROI analysis 193 6.29 The cost breakdown analysis (post improvement) 194 6.30 The post improvement utilization analysis 195 6.31 The post improvement technician idling time reduction 196 xviii LIST OF ABBREVIATIONS ABBREVIATIONS FULL NAME AEPT Automated Equipment Performance Tracking ATE Assembly Test Equipment GU Goal Utilization HMLV High Mix Low Volume MA Machine Availability NA Not Available NVA Non Value Added PM Preventive Maintanence SDT Schedule Downtime SPEC Specifications SEMI E10 Semiconductor Equipment and Materials International (E10 is spec) SMED Single Minute Exchange of Die TIU Test Interface Unit TP Test Program TRIZ Theory of Inventive Problem Solving USDT Unscheduled Downtime VA Value Added CHAPTER 1 INTRODUCTION 1.1 Overview This chapter describes a high-level overview of this project. This includes the background of the project, problem statement, objective, scopes and the lastly significance of this project. 1.2 Background of Project The ever-growing technological envelope and the shrinking of product life cycle have ultimately changed the overall face of today’s global economy where trends are more volatile and impulsive with end-customers are more vivid in their choices and selection of products. The ‘ripple’ of these effects has strongly influenced in the semiconductor industries especially manufactures supporting High Mix Low Volume (HMLV) products. It is well noted that the number of transistors that can be placed inexpensively on an integrated circuit has doubled approximately every two years (Gordon Moore, 1965) which precisely describes a driving force of technological and social change in the late 20th and early 21st centuries and the trend has continued for more than half a century and is not expected to stop until 2015 or later. This has directly impacted the once flamboyant semiconductor industries which 2 are now facing competitive pressures to meet the ever-changing demand from end customer and at the same time the challenge in reducing the overall operation cost. Some 3 years ago, when Intel’s Kulim Microprocessor and Chipset Operations (KMCO) mega-factory was erected as the biggest offshore facilities (was then taken over by the mega factory in Vietnam in 2nd Quarter 2010) and ramped-up aggressively for HMLV manufacturing (include assembly and testing), there were 2 main mounting challenges for the factory was; i. To make a breakthrough in the factory process cycle time (time taken to manufacture a product from start of assembly to finish product ship out) ii. To demonstrate a low cost competitive advantage especially when compared against Internal competitors (other Intel factories i.e. Penang, China, Costa Rica and US) and external competitors whom are mostly EMS or other sub-contracted factories The above 2 challenges are linked together by one similar gating issue which is the conservative or the traditional manufacturing flow which focuses on batchbased production that in return produce large inventory build-ups, high storage cost and overall lower equipment utilization. This manufacturing method opposes exactly the concept of Lean Manufacturing which dictates on identifying and eliminating those waste or Non Value Added (NVA) activities in accordance to achieve optimum performance. Lean advocates for continuous flow and manufacturing flexibility of readily adapting to the market shifts (Anthony Inman, 2010). The ability and competency to be flexible is much easier to be said than done as the complexity to design such facility could be both costly and sophisticated especially on long term sustaining. This project will fully focus on the case study of reducing the changeover time for an Automated Testing Equipment (ATE) called the ‘Extreme Test Handler’ in a semiconductor industry by integrating 2 well known problem solving 3 methodologies; the Single Minute Exchange of Die (SMED) techniques together with the Theory of Inventive Problem Solving (TRIZ) principals. 1.3 Problem Statement and Justification Today, the non flexible factory environment practices batch build of products and equipment dedication policy at the Test operation area due the long hours of non-optimized changeover process for the Test Handler which in result causes low equipment utilization, high inventory accumulation, higher cost per unit and the rising cost to purchase new capital equipments. 1.4 Objective The objective of the project is to reduce the changeover duration for a test handler from a current 4.0 hours to 0.5 hours by integrating SMED techniques and TRIZ principals. 1.5 Scopes The scopes of this project will cover as below: i. Only techniques from SMED and TRIZ will be used. All the TRIZ are based only from the ‘Principal’ tools ii. The study is limited only to the chipset products codenamed ‘Nebula Peak’ and ‘Nexus Peak’ iii. The focus area is the Test operation of the company where the focused equipment M4542AD Dynamic Test Handler (Extreme Handler) 4 1.6 Significance of Study The highlights of this project are as below: i. Changeovers or conversion for test equipments such as the Test Handlers are rarely studied or practiced upon compared to other assembly equipments such press, lathe or even conveyor based equipments. This could be due to fact that these types of test equipments are only commonly found at high end semiconductor industries with structural and functional die testing capabilities. Also to note is that this type of equipment are more complex and sophisticated technically to change or redesign. ii. This project explores the opportunity to apply the SMED techniques to perform changeover for the Test Handler and further enhance the shortcoming of the prior techniques by integrating them with TRIZ principals. 1.7 Thesis Structure This thesis consists of 7 chapters. Chapter 1 is the introduction of the project with background, problem statements, objective, scopes and the significance of the study. Chapter 2 presents the literature review on Lean manufacturing, rapid changeover, Single Minute Exchange of Die (SMED) and Theory of Inventive Problem Solving (TRIZ) which also consist the critical analysis of each techniques. Chapter 3 is basically the detail of the methodologies used throughout the project. Chapter 4 focuses on the problem identification in the case study where both qualitative and quantitative data collected are presented. Chapter 5 shows the counter measure proposals with respect to the SMED and TRIZ techniques. Chapter 6 is where the end results are presented together critical appraisals and future study recommendations. Chapter 7 is the conclusion and summary of this project. CHAPTER 2 LITERATURE REVIEW 2.1 Overview This chapter will focus on reviewing and critically analyzing literatures related and relevant to this project. The core objective is to lay out foundation for this project by extracting the significant findings, the opportunities and the shortcomings or gaps highlighted in the studies. 2.2 Lean Manufacturing The term „Lean‟ has derived into multiple different meaning since its introduction during the 20th century. According to Intel‟s Lean Learning Centre (2003), „Lean‟ is an integrated approach in designing and improving work towards a customer focused ideal state through engagement of all people aligned by common principles and practices. Others prefer the simple and basic concept that Lean is to identify and eliminate wastes from every aspect of the business (Levinson and Rerick, 2002). Waste or commonly known as „muda’ in Japanese is defined by Hiroyuki Hirano as „everything that is not absolutely essential‟ (Santos, Wysk and Torres, 2006). Table 2.1 below summarizes the typical 7 deadly waste in Lean context (Liker and Meier, 2006). The term “Lean production” was first introduced in the book titled „The Machine that Changed the World‟ (Womack et al., 1990) and the 6 term Lean Manufacturing flourished naturally after the success of automobile makers Toyota in the 20th century applying Lean in their shop floor. Lean manufacturing focuses on continuous improvement of the manufacturing processes which leads to superior processes that require less human effort, less manufacturing space, less operational capital and less time to make products with fewer defects to precise customer requirements (Marchwinski and Shook, 2003). No Waste Table 2.1: The seven deadly waste in Lean context Description 1 Producing items earlier or in greater quantities than needed by the customer. Generates other wastes, such as overstaffing, Overproduction storage, and transportation costs because of excess inventory. Inventory can be physical inventory or a queue of information. 2 Waiting Workers merely serving as watch persons for an automated machine, or having to stand around waiting for the next processing step, tool, supply, part, etc., or just plain having no work because of no stock, lot processing delays, equipment downtime, and capacity bottlenecks. 3 Transportation Moving work in progress (WIP) from place to place in a process, even if it is only a short distance. Or having to move materials, parts, or finished goods into or out of storage or between processes. 4 Taking unneeded steps to process the parts. Inefficiently processing due to poor tool and product design, causing Overprocessing unnecessary motion and producing defects. Waste is generated when providing higher quality products than is necessary. 5 Excess Inventory Excess raw material, WIP, or finished goods causing longer lead times, obsolescence, damaged goods, transportation and storage costs, and delay. Also, extra inventory hides problems such as production imbalances, late deliveries from suppliers, defects, equipment downtime, and long setup times. 6 Unnecessary Motion Any motion employees have to perform during the course of their work other than adding value to the part. 7 Defects Production of defective parts or correction. Repairing of rework, scrap, replacement production, and inspection means wasteful handling, time, and effort. 7 2.2.1 History and Background The concept of waste being built into jobs can be identified as far back as pre 20th century when Frank Gilbert observed inefficiencies in the brick laying worker‟s repetitive motion of bending and lifting the bricks from ground to the wall. He then improves the task by placing the bricks at wall level which resulted in almost threefold of efficiency improvement. Subsequently, more work and motion study was done including works like The Principles of Scientific Management (Taylor, 1911) which introduced standardization and marked the early example of early lean techniques. Henry Ford continued the focus on waste elimination by developing the mass assembly manufacturing system which startled the world because it exhibited a higher degree than most people would have thought possible with the seemingly contradictory requirements of true efficiency which are; constant increase of quality, great increase of pay to the workers, repeated reduction in cost to the consumer. This brought a new era of mass production in short throughput time with high profit to the manufacturer. By enforcing very strict specification and quality criteria on the manufactured component, he eliminated the requirement for skilled workers almost entirely which help to reduce the manufacturing cost by 60% -90%. Lean manufacturing concept is a generic process management philosophy derived mostly from the Toyota Production System (TPS) which is considered as the cradle of Lean. TPS is renowned for its aggressive focus on the 7 deadly wastes elimination. It all started with in the 20th century when it‟s brain child Toyota, Sakichi Toyoda implemented an improvement to auto-stop the looms when the tread broke in his textile factory which then became the seed for autonomation or ‟Jidoka‟. But then, it was Taiichi Ohno who initiated the Lean school of thought by putting together all the experience, themes and the school of thought into what is known as the Lean Manufacturing. Another industrial revolutionist called Shigeo took Lean to a greater height when he reduce the setup time of the hull assembly on a 65,000-ton super tanker from 4 months to 2 months, setting a new record in shipbuilding (Vardeman et al., 2010). 8 2.2.2 Lean Concepts Lean concepts are not necessarily a tool that we would implement but a state or condition that we would strive for. Some of the commonly used concepts and which are related to changeover are as below: i. Autonomation: Also referred to as jidoka, it is adding human element of being able to identify problems and either stop for correction or selfcorrect before moving onto the next steps ii. Continuous Flow: The ideal state for any process is to move away from traditional batching of work, whether material or information, and flow for continuous, one element at a time. This reduces many types of waste particularly waiting iii. Pull: In order to improve continuous flow and reduce the waste of overproduction, process should be „pull‟ what they need from the previous step in the process and only that triggers new actions iv. PDCA: Plan- Do-Check-Act means that whether solving a problem or building a plan everyone should follow this process to ensure learning and success towards the goal v. Visual Management: Is both a tool and a concept. The ideal state is all employees, operators and management, should be able to manage all aspect of the process at a glance using visual data, signals and guides. vi. Value Added: The Japanese term of waste is known as Muda (Sayer and Williams, 2007) and can be divided into Type-1 muda (Non-value-added but necessary) and Type-2 muda (Non-value-added and not necessary). Value Added task are only those tasks which (1) the customer is willing to pay for, (2) transform the product or service, (3) are done right after first time vii. Waste Elimination: Eliminating waste from the process is the goal of many lean tools and should be an ongoing effort in itself. This comes in form of 7 types of waste best remembered using the acronym TIMWOOD; Transportation, Inventory, Motion, Waiting, Overprocessing, Overproducing and Defect 9 2.2.3 Lean Tools Lean tools are proven practices that help to move closer to the ideal state and are consistent with the Lean Principles. There are various methods and tools to assist the changeover process and help to implement the Lean production systems. Some of the universally accepted tools as per documented by the Association for Manufacturing Excellence are as below: i. 5S: adapted from the Japanese words that start with „S‟ but have been rewritten as Sift, Sweep, Sort, Sanitize and Sustain ii. Error Proofing: Error Proofing is also known as poke-yoke or mistake proofing. It involves redesign of equipment or process to prevent problems from occurring iii. Six Sigma: Method and a set to tools to reduce variations in a process particularly quality using mostly statistical tools. It‟s primary method is DMAIC: Define, Measure, Analyze, Improve and Control iv. Scoreboards: are part of Visual Management of safety, quality, delivery and cost metrics including analysis and action plans use to help shop floor teams to manage their own process v. Layout: An arrangement of work(machines, people, method and material) so that processing steps are sequentially done in next door steps one at a time in order to efficiency, reduce waste and improve communication vi. Kanban: Often in the forms of cards, are signals that a downstream, or customer, process can use to request specific part from the upstream, or supply or process vii. Andon: The andon cord is the ability for an operator to pull a cord that triggers a horn and light which tells their team leader that they need help or support safety, health, and environment viii. Honshin kanri: A strategic planning process to establish strong agreement and align people in a common direction with agreed upon methods to improve 10 ix. Kaizen: Kaizen is a structured process to engage those closest to the process to improve both the effectiveness and efficiency of the process. Its goal often to remove waste and add standardization x. Preventive Maintenance: Simplifying and structuring maintenance activities to prevent problems rather than react to them can increase capacity to improve continuous flow xi. Setup Reduction: The time takes to changeover equipment from one product to the next is a major barrier to continuous flow and setup reduction seeks the reduction or elimination of that time. This is also known as SMED or Single Minute Exchange of Dies xii. Value Stream Mapping: This is structured process helps manager understand the flow of both material and information through their operation and develop plans to move them closer to ideal state The ‘bright side’ of Lean 2.2.4 T Ross & Associates Environmental Consulting Ltd. (2003) mentioned in their report, that Lean production typically represents a paradigm move from conventional “batch and queue” functionally aligned mass production to “continuous flow” product-aligned pull production. This shift requires the implementation of justin-time production principle and employee-involved, system-wide, continual improvement. Several potential outcomes of implementing Lean are identified as follow: i. Reduced Inventory Level: Include raw materials, work-in-progress(WIP), finished product along with associated carrying costs and loss due to damage, spoilage, off-specification etc ii. Decreased Material Usage: Include product inputs, including energy, water, metals, chemicals, etc by reducing material requirements and creating less material waste during manufacturing 11 iii. Optimized Equipments: Capital equipment utilized for direct production and support purposes using lower capital and resource intensive machines to drive down costs iv. Reduce need for Factory Facilities: Physical infrastructure primarily in the form of buildings and associated material demands by driving down the space required for product production v. Increase Production Velocity: The time required to process a product from initial raw material to delivery to a consumer by eliminating process steps, movement, wait times, and downtime vi. Enhance production flexibility: The ability to alter or reconfigure products and processes rapidly to adjust to customer needs and changing market circumstances enabling the implementation of a pull production, just-in-time oriented system which lowers inventory and capital requirements vii. Reduced complexity: Complicated products and processes that increase opportunities for variation and error by reducing the number of parts and material types in products, and by eliminating unnecessary process steps and equipment with unwanted features The ‘Anti’ Lean Sentiment 2.2.5 It has not always been glitz, glamour and glory for Lean as there has been some known and obvious disadvantage of the Lean concepts and the setback from its implementation. Apple Inc has been described as successful giant organization that is known to be „Anti Lean‟ in its business practices. Some of the disadvantages of Lean (Wen Jie and Lang Wood, 2010) could be summarized as: i. Supply Chain Problem because only a small amount of inventory is kept on hand, lean manufacturing depends heavily on suppliers that can provide products for the manufacturing process dependably and without interruption. Problems like employee strikes, transportation delays and 12 quality errors on the part of suppliers can create manufacturing holdups that can be fatal. Vendors may be unable or unwilling to supply parts or products on a tighter schedule or in smaller amounts. These needs can burden suppliers with unprofitable costs and create tensions that ultimately affect the manufacturing process and can cause frequent changes of suppliers, or even difficulties finding suppliers who can provide on the necessary schedule at all ii. High Cost of Implementation of lean manufacturing often means completely dismantling previous physical plant setups and systems. Training employees can be lengthy and acquiring managers experienced in lean manufacturing process can add considerably to company‟s payroll expenses. The purchase of machinery that increases efficiency, and the setup of smaller work cells can add to long-term debt. Small and mediumsized businesses, in particular, may find the cost of changeover to lean manufacturing processes prohibitive iii. Customer Dissatisfaction Problems because lean manufacturing processes are so dependent on supplier efficiency, any disruption in the supply chain and therefore, on production can be a problem that adversely affects customers. Delivery delays can cause long-lasting marketing problems that can be difficult to overcome iv. Requires Close Management where Lean manufacturing requires close management that a lean production system must be constantly monitored to find potential future problems and maintain production efficiency. This close management requires regular communication between line level employees and management. In many organizations, there is a divide between management and workers, resulting in a hesitation to share information. Close management also can run the risk of management being too active in fine-tuning employee tasks, often called "micromanagement" v. Employee Pushback, in some cases, organizations may be culturally resistant to change. Employees may balk at changing how they do their jobs. In some cases, a lean production modification may cause one set of employees to have more work, while reducing the work load on another 13 set. This can trigger resentment and employees who fight the implementation of a lean production system. In some cases, the pushback may come from management. This is especially true in organizations where managers see their organizations as separate "fiefdoms" under the larger organization. Managers sometimes can attempt to sabotage the implementation of a system because of a fear of losing power and control of the department and groups that they head 2.3 Optimization of Changeover Process Changeover or conversion is defined as the need of equipments to support for 2 or more products simultaneously. Figure 2.1 shows a general changeover process and the total elapsed time that is measured from the ramp down period of current product to the time the new product is fully ramped up. Figure 2.1: General changeover process It is necessary to optimize line changeover efficiency especially in a High Mix Low Volume (HMLV) electronics assembly environment before Lean Manufacturing is implemented (Douglas Farlow, 2005). Traditionally, improvements in changeover are approach only through the evaluation and elimination of the Non Value Added (NVA). Studies have shown the existences of the 7 „deadly‟ waste in an inefficient changeover and highlighted the goal of an efficient changeover is to 14 reduce waste specifically transportation and motion (Womack and Jones, 1996). Also Total Productive Maintenance (TPM) has also identified quick change over time as one of it‟s six key principles (Nakagima, 1988). 2.3.1 Changeover and Preventive Maintenance The role of better changeovers to facilitate reducing downtime losses has been widely reported (Klospic and Houser, 1997) including changeovers application in TPM and the 6 big losses. However, there has been little assessment of changeover improvement techniques been applied for maintenance procedures. There are many similarities between activities that happen at changeover and maintenance as summarized below: i. Involve substitution of components ii. Dismantling to gain access iii. Removal of component or assemble iv. Replacement of component v. Adjustment to reinstate the desired level of performance Poor quality of parts can impact changeover and maintenance performance. With better maintenance practice, changeover process can be optimized with the reduction of lengthy downtime due to component damage or the wear and tear situations (McIntosh et al., 1999). Though typically, maintenance and changeovers happens separately at different times frame which increases tool downtime but there are opportunities to integrate changeover and maintenance activity especially for those with low variability high frequency changeover/maintenance scenario. 15 2.3.2 Benefits of Quick Changeover Changeover reduction is an extremely powerful tool which improves a plants ability to provide better utilizing its own assets and improve productivity of employees (Rubrich and Watson, 2004). Also some of the advantages of manufacturers implementing changeover reduction (Feld, 2000) are: i. Improved product quality ii. Work in process (WIP) reduction iii. Reduction in set up costs iv. Improved utilisation of labour and equipment. v. Shorter Manufacturing lead time vi. Quicker response to customer demand 2.3.3 Alternatives to Quick Changeover The following are some of the available options to explore to achieve quick changeover; 2.4 i. Single Minute Exchange of Die (SMED) ii. Group technology/cell formations iii. Design Standardization iv. Mechanization or automation Single Minute Exchange of Die (SMED) Single Minute Exchange of Die or better known as SMED took its first step in 1950‟s as a concept from the brain child of Shigeo Shingo‟s efficiency experiment at Toyo Kogyo Mazda plant in Hiroshima, Japan. It is also worth to note that, it was 16 Dr Shigeo‟s who first initiated the concept of „Defect=0‟ or „poka-yoke’ in 1961 (Vardeman, 2010). Shingo‟s SMED was highly inspired by Taylor‟s Principle of Scientific Management. SMED emphasises that changeover improvements is sought primarily by rearranging internal and external elements where the whole changeover process can be completed below 10 minutes. According to Shingo, an internal activity is something that can be performed only when the tool is stopped or down for production while external activities can be performed in parallel when the tool is up and running production. Figure 2.2 shows the original approach by Shingo‟s to achieving quick changeover while Figure 2.3 shows an enhanced SMED conceptual stages with techniques: Figure 2.2: Shingo‟s original SMED model Shingo‟s 3 Main Stages: i. Stage 1: Separate internal and external activities. ii. Stage 2: Converting internal activities to external where and when possible iii. Stage 3: Engineering, streamlining or standardising all remaining activities so that they can be completed in the fastest possible time Shingo‟s 12 main techniques: 17 i. Using Checklist ii. Perform Function Check iii. Improving Die Transportation iv. Preparing Operation Conditions in Advance v. Function Standardization vi. Using Intermediary Jigs vii. Improving Storage and Transportation for Blades, Dies, etc viii. Implement Parallel Operations ix. Use Functional Clamps x. Eliminating Adjustments xi. Least Common Multiple System xii. Mechanization Figure 2.3: Shingo‟s conceptual stages and techniques By 1980, SMED was ear-marked as one of the most revolutionary concept in manufacturing after it successfully integrated into the Toyota Production System (TPS) when the die punch set up time in the cold forging process was reduced form one hour 40 minutes to just 3 minutes with significant reduction in operating costs 18 and improve in the lead time (Vardeman et al, 2010). SMED became the cornerstone of Lean Manufacturing especially in setup time reduction by waste elimination and enabling smaller batch sizes of lots to be processed, demonstrating JIT and as an element for continuous improvement or „kaizen’ (Karlsson and Ahlstrom, 1996) as shown in Figure 2.4. Figure 2.4: SMED in Lean context 2.4.1 Advantages of SMED According to Shigeo, SMED will help lower the skill level requirements when the tool changeover are quick and simple which in return eliminate the need to hire or train highly skilled workers. As earlier discussed, competitive advantages like quick customer response could be achieved through SMED where rapid changeovers will create a flexible manufacturing environment. Shingo‟s SMED promotes world class manufacturing through delivering outstanding business results and improvement in customer satisfaction levels (Varderman, 2010). Typically improvements in changeover is approached only through the evaluation on the Non 19 Value Added (NVA) steps but through the introduction of SMED as a Lean tool to reduce changeover time, even the Value Added (VA) steps are accessed and waste are eliminated systematically at all levels. Today, SMED can be applied to every situation and urges that everyone would benefit from its principles (Brad McEnroe, 1985) where the main benefits are the introduction of parallel operations and a reduction in wasted adjustments by having fixed numerical settings, using gauges and using referencing plans. Wasted adjustments, can consume up to 50% of set-up times, when not tackled. Besides this, another advantage here is improved employee involvement. Both SMED and Lean by culture welcome employee involvement towards continuous improvement. Employee involvement (Kearney, 1997) is one of the dominant elements of world class manufacturing that can make both small and large companies competitive in the global market. Organization especially shop floors with SMED implemented has shown a positive change in employee‟s attitude where involvement of employee in both problem solving and decision making has yield outstanding results especially in set up time reduction cases. 2.4.2 Disadvantages and gaps in SMED The biggest 2 gaps found in the SMED methods and techniques today are; i. Sustainability – substantial evidence showing that some changeover times has continued to improve, some had stabilized while a few has took a reverse and degraded. The main reason for the degradation in changeover time was due to sustainability issues. Management commitment and continuous focus on changeover reduction are the key enablers on sustainability (McIntosh et al., 2001) ii. Low focus on hardware redesign- SMED does not sufficiently promote some important options, particularly those who seek to reduce the duration of the changeover tasks or eliminate them altogether. This 20 particularly arise when a system in need for a design change for continuous improvement (McIntosh et al., 2000) 2.5 Theory of Inventive Problem Solving (TRIZ) TRIZ (pronounced TREEZ) is the Russian acronym for „’Teoriya Resheniya Izobreatatelskikh Zadatch‟‟ or the Theory of Inventive Problem Solving. TRIZ introduced by Russian engineer and scientist Genrikh Altshuller in 1946, is a problem solving method based on logic and data, not intuition, which accelerates the ability to solve problems creatively. TRIZ also provides repeatability, predictability, and reliability due to its structure and algorithmic approach (Orloff, 2003). This proven algorithmic approach to solving technical problems began when Altshuller studied thousands of patents and noticed certain patterns. From these patterns he discovered that the evolution of a technical system is not a random process, but is governed by certain objective laws. These laws can be used to consciously develop a system along its path of technical evolution - by determining and implementing innovations. One result of Altshuller's theory that inventiveness and creativity can be learned has fundamentally altered the psychological model of creativity. 2.5.1 History and Background TRIZ has an interesting history (Terninko, Zusman & Zlotin, 1998) where after World War II Genrich Saulowitsch Altshuller (1926–1998), at that time a young and talented inventor in the former Soviet Union and a patent examiner for the Russian navy, started to develop the „classical‟ TRIZ as a methodology to create systematic innovations. His research began with comparing patents to analyze how inventors invent. Because of his criticism of the Soviet system, Stalin banished Altshuller to Siberia, where he spent a number years in a labor camp. During this time, he worked intensively on around 200,000 patent analysis and discovered only around 40,000 of the patents are considered to be really worth it to be considered as 21 inventions. For instance, Altshuller extracted the 40 inventive principles as shown in Figure 2.5 below, on which many technical solutions are based on. Furthermore, in the labor camp he met like-minded researchers who were interested in his research, and with them he discussed his ideas. In the following years, Altshuller developed successively TRIZ tools and characteristic terms. Later, as a consequence of glasnost or the openness policy by the Soviet government post 1980s, the TRIZ knowledge grow enormously especially in the Western Hemisphere when several of Altshuller‟s students emigrated to the USA, Scandinavia, Israel and Germany. Figure 2.5: The 40 Inventive principals 2.5.2 Conceptual Basic of TRIZ TRIZ research began with the hypothesis that there are universal principles of creativity (Katie, Ellen and Michael, 2006) that are the basis for creative innovations that advance technology. If these principles could be identified and codified, they 22 could be taught to people to make the process of creativity more predictable. The short version of this is: ‘’Somebody someplace has already solved this problem (or one very similar to it.) Creativity is now finding that solution and adapting it to this particular problem’’. Throughout the 60 years of research the TRIZ community has accumulated wide range of experiences and knowledge of former inventors to help support new inventors when they have to solve primarily technical or technical-economical problems (Martin Moorle, 2005). The 3 fundamental findings of TRIZ are; i. Problems and solutions are repeated across industries and sciences. The classification of the contradictions in each problem predicts the creative solutions to that problem ii. Patterns of technical evolution are repeated across industries and sciences iii. Creative innovations use scientific effects outside the field where they were developed. Problem solving within TRIZ can be described using a four-element model as shown in Figure 2.6: i. The problem-solver should analyze his specific problem in detail. This is similar to many other creative problem-solving approaches ii. He should match his specific problem to an abstract problem(or general problem) iii. On an abstract (general) level, the problem-solver should search for an abstract (general) solution iv. If the problem-solver has found an abstract (general) solution, he should transform this solution into a specific solution for his specific problem. 23 Figure 2.6: The 4 element model of TRIZ During this process, TRIZ can support the problem-solver by accumulating innovative experiences and providing access to effective solutions independent of application area. As there are different TRIZ tools corresponding with different levels of abstraction, this process may vary in the heights of abstraction, and also in the number of loops, which the problem-solver is passing through. For each step the problem-solver can resort to specific TRIZ tools: i. The specific problem can be analyzed and transformed into an abstract solution, for example, through the tool function analysis. ii. The tool contradiction can help to formulate the problem on an abstract level. iii. Afterwards, the inventor can find abstract solutions for the formulated abstract problem, for instance using the tools inventive principles, separation principles or substance- field-modulation. iv. Lastly, the problem-solver can use the tool ideal machine for assessing the found solution concepts and transfer the selected solution concept into a specific solution 24 2.5.3 Common TRIZ terminologies Some of the common TRIZ terminologies are as below; i. Technical System: Everything that performs a function is a technical system. Any technical system can consist one or more subsystems. The hierarchy of technical system spans from the least complex with only 2 elements to a complex with many interacting elements ii. Level of Innovation: Analysis of a large number of patents shows not every invention is equal to its inventive value. There are 5 levels of inventions beginning from Level#1(simple improvement) to Level#5(discovery of a new phenomena). Almost 77% of the patents reviewed showed they belong to either Level#1 and Level#2, and TRIZ could help innovators to elevate to Level#3 or Level#4 iii. Laws of Ideality: States that any technical system throughout its lifetime tends to become more reliable, simple and effective or more ideal. Systems are considered ideal when mechanisms disappeared while the function remains. iv. Contradiction: are situation where improvement of one characteristic, cause another characteristic to deteriorate and mostly a compromised solution are sought. The most effective solutions are solving of technical problems with contradiction. There are 2 types of contradiction; technical contradiction are contradiction happening inside a technical system and the 40 principals are used to resolve them; physical contradiction where 2 opposite properties are required from the same element of a technical system with multiple methods to solve this type of contradictions v. Evolution of Technical System: Altshuller established 8 Patterns or Lines of technical system evaluation namely Life Cycle, Dynamization, Multiplication Cycle, Transition from Macro to Micro, Synchronization, Scaling up and down, Uneven development of parts and Automation 25 2.5.4 Tools in TRIZ field TRIZ offers a comprehensive set of tools to analyze and solve problems in different perspectives. Lev Shulyak has summarized TRIZ tools into 3 different categories as below; i. Principals: the tools to overcome contradiction where consist of generic suggestions for performing an action to, and within a technical system. The 40 Inventive Principles (Figure 2.5) together with the first 20 Contradiction matrix (Figure 2.7) are example of tools from this category. ii. Standards: Are structured rules for the synthesis and reconstruction of technical systems where it helps to combat complex problems. Standards provide 2 functions; a) Standards help to improve and existing system or synthesis a new one and b)Standards are most effective way for providing graphical model of a problem and is called S-field modeling. Altshuller offered 72 Standards divided into 5 classes iii. ARIZ: is the abbreviation Algorithm to Solve an Inventive Problem is the central analytical tool of TRIZ. It provides specific sequential steps for developing a solution for complex problems. The latest version is called ARIZ-85C which contains 9 main steps with a multiple substeps On the other hand, Martin G. Moehrle (2005) in his work on „Framework for TRIZ research‟ summarized that the comprehensive TRIZ toolkit could be structured based on the five field framework. The tool list in TRIZ field is summarized in the Figure 2.8. 26 Figure 2.7: The contradiction matrix 27 Figure 2.8: Tools in TRIZ field 28 2.5.5 Application and Implementation of TRIZ TRIZ has made it presence in many large established organizations around the globe with case real case study has shown the success story. A report from Fortune Magazine (Peter Lewis, 2005), shows how Semiconductor /Electrical companies like Samsung is trains the engineers aggressively in TRIZ to develop new designs and ideas which till date Samsung owns up to 1600 patents in 2005 alone. Besides them, US companies like GE, Intel, Motorola are fast catching up on the TRIZ techniques especially in their respective R&D department to invoke breakthrough ideas. Research below has shown the evolvement of TRIZ in today‟s real world, notably the absorption into the corporate world alongside Lean and Six Sigma (Katie, Ellen and Michael, 2006); i. Entertainment: Applications of TRIZ developed eight families of solutions to solve Singapore‟s automobile traffic on the Sentosa , its entertainment island (aquarium, bird sanctuary, dolphin show, restaurants, music, etc) ii. Warranty cost reduction: Ford used TRIZ to solve a persistent problem with squeaky windshields that was costing several million dollars each year. Previously, they had used TRIZ to reduce idle vibration in a small car by 165 percent, from one of the worst in its class to 30 percent better than the best in class. iii. IT Product development: A manufacturing company doubled the value to the customer of their patient interview system for opticians offices by applying the feedback and self-service principles of TRIZ to the overall product development, and applying the principles of segmentation, taking out and composite construction to the training and support. iv. School administrators: Creativity has been greatly enhanced in situations ranging from allocation of the budget for special education to building 29 five schools with funding only for four, to improving racial harmony in the schools. v. Waste processing: Dairy farm operators could no longer dry the cow manure due to increased cost of energy. TRIZ led the operators to a method used for the concentration of fruit juice, which requires no heat. vi. Dow Chemical Company showed the combined effect of TRIZ with Design for Six Sigma (DFSS) saw the Breakthrough achieved in controlling of monomer residuals, handling of raw materials, and reactor design. The reduction amazed even the project team, when the capital cost of a plant built to the new standard dropped by more than 25 percent, from nearly $110 million to < $80 million. 2.5.6 The Shortcomings and Opportunities in TRIZ As the worldwide appreciation for TRIZ grows, its further development as a science is hindered by a number of factors (Simon Letvin et al.,2010) mainly due the fuzzy boundaries of TRIZ but hardly any scientific association, even the most respected and established one, is able to define with utmost certainty the boundaries of its “subject” science. This in response leads to significant differences in the interpretation of some key concepts, tools and approaches of TRIZ (and in some cases to their corruption). Unfortunately, there are currently no TRIZ textbooks or training programs that are universally accepted by the global TRIZ community. These discrepancies make it difficult to meet an increasingly tangible need for a globally authoritative certification of TRIZ practitioners. Presently, there are several new developments based on “classical” TRIZ, such as I-TRIZ, TRIZplus, TRIZ-OTSM, and some others. Although some of these developments are used by many TRIZ practitioners, they have not yet attained the 30 status of being universally accepted BUT there is already aggressive steps taken by especially the International TRIZ Association together with Altshuller Institute to work on this. Martin G. Moehrle (2005) in his proposal on TRIZ‟s research framework pointed out 5 improvement aspects as below: i. Core– the various TRIZ tools are located in the centre of the framework. How effective and efficient are those tools? What combinations of them are particularly helpful? What theoretical background can be found to enhance the toolkit? What comprehensive process models (see above) should be used under what conditions? ii. Inspiration- some aspects may inspire the development of TRIZ. New scientific knowledge domains and new patented inventions may be assigned to this field of research. What findings, for example, from the field of bionics can be integrated into TRIZ and its tools? Which new inventive principles can be found in patents covering newer technologies like photovoltaic or nanotechnology? iii. Adaptation– TRIZ may be applied in different fields. In a narrow sense, one can think of different technical fields, reaching from classical engineering to software and gen technology. In a broader sense, other fields of application like management, sociological or even psychological problems can be considered (bearing in mind that people are not technical systems) iv. Psychological and sociological contingency–the application of TRIZ and its tools is embedded in psychological and sociological factors. Which personnel types prefer which TRIZ tools? How is this related to the qualification of the people? How should group members be assigned to reach acceptable results with TRIZ tools? v. Integration-several creativity techniques, such as lateral thinking, morphology and CPS have been developed. Furthermore, a lot of quality tools such as FMEA or QFD are being discussed. How could these techniques and tools be combined with TRIZ tools 31 2.6 Summary From the critiques above, it is clear that both the renowned techniques discussed above have numerous advantages and individual strengths alongside with its weakness. This shows the possibility of molding both techniques to complement each other in a changeover process. CHAPTER 3 METHODOLOGY OF RESEARCH 3.1 Overview The purpose of this chapter is to give a concise overview of the research method used throughout this project. This chapter will define the research objectives, methods used and lastly the limitation faced and some recommendations to overcome this setback. 3.2 Research Objective The primary objective of the project is to reduce the overall time taken to complete high frequency-high variability changeover activity for a handler. The following are some of the Research Questions that this project to aims to answer: 33 i. What are the current state and the process flow for the changeover process? ii. Is it possible to reduce the changeover durations using SMED techniques and how much saving is expected? iii. Similarly, is it possible to integrate SMED techniques with TRIZ principals to enhance the changeover reduction time? How much is saving is expected with this method? iv. How to ensure the improved changeover process does not affect Safety, Quality and output delivery? 3.3 Analyzing Research Methods The evolution of research has created an alternative pool of available Research Methods (RM) to suit individual needs. According to Shariff (2004), research methods can be divided into 4 types namely experiment, surveys, observation and secondary data study. In a broader perspective, this could be categorized as qualitative and quantitative based RMs. Qualitative research methods are fields or inquiry that crosscuts disciplines and subject matters. Qualitative researchers aim to gather an in depth understanding of human behaviour and the reason that govern human behaviour. Qualitative researchers normally use four methods for gathering information: i. Direct observation or ‘’gemba’’ ii. Participation in the setting or self-experience (experience survey) iii. In depth interviews, surveys and questionnaires etc iv. Analysis of documents, papers, info or called secondary data study 34 Quantitative research is much more scientific that qualitative approach, and aims to determine a relationship between variables. The objective of quantitative research is to develop and employ mathematical models, theories and/or hypotheses pertaining to natural phenomena. The process of measurement is central to quantitative research because it provides the fundamental connection between empirical observation and mathematical expression of quantitative relationships. Quantitative research is often an iterative process by which evidence is evaluated, theories and hypotheses and refined, technical advances are made. Quantitative research is generally approached using scientific methods such as: i. The generation of models, theories and hypotheses ii. The development of instruments and methods for measurement iii. Experimental control and manipulation of variables iv. Collection of empirical data v. Modelling and analysis of data vi. Evaluation of results Researchers have long debated the relative value of qualitative and quantitative inquiry (Patton, 1990). Russek and Weinberg (1993) claim that by using both quantitative and qualitative data, their study gave insights that neither type of analysis could provide alone. The form of research that combines multiply research methods is usually described as one of convergent methodology, multimethod/multitrait convergent validation or what has been called “triangulation”. Based on the research questions posed earlier, it is best to combine both qualitative and quantitative research methods where the former will be used in at the early stage especially on understanding human behaviour and the interaction with the changeover process. Later, this will be coupled with quantitative techniques to 35 analyse the info and data collected to be presented in a more scientific and empirical way. 3.4 Description of Research Methods used Below are some of the crisp details of the RM that will be used throughout this paper. Figure 3.1 then summarizes the whole process flow. Figure 3.1: Research Methodology flow 36 3.4.1 Secondary Data Study Some of different categories of secondary data study used throughout this project are as below; i. Historical Data: Once the problem statement and focus area has been indentified, the 1st step is to collect, compile, and review and thoroughly analyze the historical data i.e. the time trend taken to complete a changeover process for the equipment in focus. The raw historical data can be collected from the automated database of the company (i.e. MyATM) that stores each event happened on each equipment for a tenure for 26 weeks. The automated system is designed to capture events based on the SEMI E10 standard where each time and operator performs changeover (conversions) the event will be auto-log under the SCHEDULED DOWNTIME bracket. This automated database are ease for retrieval and are more trustworthy than the manual tracking since all activities are not easy to be manipulated and minimum human errors. But nevertheless, it is important to carefully analyze the raw samples and exclude only any known outliers or out of control (OOC) data to ensure the data integrity. The extracted raw data can be presented in either in a periodic line graph or time trend based on week to week and between shift to shift performances. This information is vital to understand the actual scenario versus the target goal especially for the changeover process. The historical trends are important to show obvious gaps and help to estimate the severity of the problem statement ii. Standard Changeover Specification and/or Technician training document: Normally documents like this are stored in both hardcopy by the engineering department and also as a softcopy in the organization‟s database. This is mostly restricted or confidential documents. It is necessary to thoroughly analyze the standard documents; ensure its updated and valid for use. Also, it will help to provide an overview of the changeover require and necessary steps needed currently to ensure a complete conversion. Document the important steps that will be used at later stage for comparison purpose. 37 iii. Literature Review: The next best source of information through previous studies did globally by like-minds that shares interest on similar research area or problem statement. Through critical analysis of related literatures, scenario like „reinventing the wheel‟ could be avoided and help to expand the knowledge gain from the research of others. Good literature review will help to scope the research better and identify opportunities and gaps from other research to explore upon. iv. Changeover Technician Info: This include the information i.e. Name, ID etc of the personnel involve during the changeover process (info normally available thru the operator log book) which will help to understand the qualification or competency level of the technicians. 3.4.2 Primary Data Study Some of different categories of primary data study used throughout this project are as below; i. Direct Observation: Also known as ‘’Gemba’’ by the Japanese and commonly use in the Lean environment. It simply means of going directly to the point of activity and perform a direct observation personally as oppose to the secondary data above. In direct observations, the key point is to „actively‟ observe with no participation in the overall observed activity (or passive involvement). Key objective of any direct observation is to understand the activity, connections and flow besides identifying opportunities in the process to eliminate waste or „muda‟ based on the 7 deadly waste abbreviated as „‟TIMWOOD‟‟. The end-information of a Direct Observation is very important because only then the actual scenario or the current state of i.e. the changeover process could be 38 spelled out correctly before any improvements are implemented. An effective Direct Observation should involve group of individuals from related expertise area i.e. engineering, IE, manufacturing, supervisors and the technicians themselves. Each member will be assigned a role where the team will observe based on the 3 main categories as below in Table 3.1 and through answering the related question with respect to the changeover process. The Direct Observation will be an iterative process where it will be conducted at all 4 shifts during changeover process to understand the impact of variables like time, techniques and competency levels. Also as continuity, the direct observation will be done pre and post improvement implementation. To ease analyzing and to map the direct observation, some of the tools as below will be utilized; a) Top Down Flow Chart Provides an overview of the activities and process flow Helps to focus attention on specific aspects of the process b) Spaghetti Diagram Capturing the flow- of either people or products between stations Ease to identify waste in motion, transportation and inventory c) Process Map Depicts what is happening to the process Useful to identify overproduction, defects, overprocessing and inventory waste Also to ease the process, equipments like sketch board, stop watches and video camera will be used. 39 Table 3.1: Categories of observations Activities Connection Flows What is the expected result of the activity? Will the results be clearly understood? How is the activity structured? Is the sequence determined? Is the timing specific? Is it clear if the expected outcome is not achieved? Is this clear what the upstream activity/process delivers? Can it be easily determined if the need it not met? How the request is made? Is there one way and one way only to make a request? Are the flow paths specific? ( is there only one way?) Are the flow paths simple as possible without excess travel? ii. Are there loops or forks in the process? Does the flow path minimize waiting in queue? Is there any other waste in the flow path? Self-Experience: To ensure a more holistic approach to understand the changeover process better, the method of self experience will be used where the observer will now involve directly in the changeover process or „getting the hands dirty‟ by performing the actual task. This is a more active approach where personal experience on performing changeover i.e. pre improvement and post improvement will allow more understanding of each steps, the time taken and the opportunity to identify the gaps and improvements needed. It is important especially post-improvement implementation to involve personally in the changeover as it is required to understand if the improvement is in place, practical and sustainable before it can be downloaded or done by other floor technicians. Key note for an effective and fruitful self experience is to document all findings, revise and continuously improvise before training others. 40 iii. Informal Interviews: As it was not possible to involve all the „changeover‟ technicians in the direct observations, quick fix to that will be through conducting some informal interview by asking same specific questions to each individual. Interviews with the personnel whom directly involve in changeover could help in mining data and information on the practice, ideas, setbacks and other vital information to help during the improvement stage. 3.5 Limitation or setback of the Research Method used Some of the limitation and setbacks that has been identified based on the research method mentioned above are described as below; i. Information and data bias: Possible if the sample size collected is not sufficient or „skews‟ especially during the direct observation. Data bias is also possible if no proper scrutiny is done based on the interviews outcome. ii. Data Inaccuracy and information misinterpretation: Manual time study, automated data versus manual data, and insufficient reading of previous literatures could potentially deviate to inaccuracy of data and misinterpretation. iii. Time consuming and constraint: Performing interviews and observation for all 4 shifts could be challenging and consume time. The availability of resources and aligning to personnel to conduct the changeover. Indulging in self experience or performing changeover personally would be going for basic training (mostly called Level 1) before being qualified to perform tool conversion. 41 iv. Possibility of human error: Many of the data collected are by human i.e. mapping, time study, process study thus there are high tendency and possibility of errors 3.6 Summary This chapter discussed in depth the methodology that has been used in throughout this project. The research methodology was structured in accordance to collect both quantitative and qualitative data and information. Various different approach and techniques will be use to collect as much sample information to ensure no data integrity or any data bias issue. CHAPTER 4 PROBLEM IDENTIFICATION 4.1 Overview This chapter will describe in detail in the case study untaken for this project. A thorough analysis of the overall changeover process will be covered; including the historical background, justification, current state and last but not least the problems or gaps identified. 4.2 Background and Justification The core objective of this whole project as mentioned earlier is to reduce the overall changeover time for a test handler from current 4 hours to a target goal of 0.5 hours. The motivation behind this project is driven due to the 3 reasons as below: 43 4.2.1 Low Tester Utilization From the historical data collected from early Q2’2010 to the end of Q4’2010, the average equipment (tester) utilization for good production use purpose is only at 70.6% per week where the remaining 30% of the time is lost due to the Non Value Added activities or simply waste in Lean context. Figure 4.1 shows the breakdown of the average tester utilization where almost 8.4%/ week or nearly 14 hours/week is just lost due to changeover activity alone. Figure 4.1: Breakdown of tester utilization Also, a point to note is that the high Repair (downtime) around 10.5%/week and Idling time of 6.5%/week also could be associated due to this ineffective changeover process. Figure 4.2 on the other hand shows the corporate utilization goal which highlights a gap of almost 20% in good utilization time itself. Lower utilization indicates high cost and high cycle time which could be disastrous for the survival of a High Mix Low Volume (HMLV) industry. Figure 4.2: The corporate utilization goal 44 4.2.2 Drive for Flexible Manufacturing Figure 4.3 shows an example of the historical data collected from Q4’2009 to Q4’2010 on the product’s demand trend. Due to ever volatile customer demand, it is challenging in both to predict and support the demands timely. Thus the best counter action is for organizations to be adoptive and also flexible to response quickly to the ever changing customer demand. Figure 4.3: Example of demand trend In actual current scenario, the factory shop floor is non-conducive to practice lean or to drive flexible manufacturing due to the fact of; i. Equipment dedication policy (product family based) at the Test operation area ii. The practice to batch build products from same family iii. The WIP linearity issue from upstream operation always hinders continuous flow of materials to the test operation Thus, to achieve World Class Manufacturing status, all the above elements need to be improved and converted to: i. Continuous flow of both WIP and information ii. Rapid and Quick equipment/process changeover 45 iii. 4.2.3 Lean, flexible and eliminate waste at all levels Driving Cost Competitive Advantage The organization’s target cost of per unit chipset is at $5.44 but the actual effective cost is currently at $6.04. The spike of $0.60 is due to multiple factor but mainly cost by test operation and manufacturing overhead. Test operation is plagued mainly by the high capital purchase with below goal utilization are major reasons behind the higher cost per unit. Figure 4.4 below shows an example of cost breakdown for a chipset product based on the Q1’10 finance analysis. Nebula Cost Breakdown 7 6 Cost ($) 5 4 3 2 1 0 Goal ($) Actual ($) Core yield loss 0.17 0.18 Mfg OH 0.58 0.83 Test 0.38 0.57 Assembly 0.45 0.51 Package 1.44 1.46 Die 2.42 2.49 Figure 4.4: Cost breakdown of Nebula With the incoming of higher production volume and the introduction of new product series (NPIs), the need to purchase new capitals and collaterals arise much quickly. Figure 4.5 shows an example with current scenario of low utilization and 46 high cycle time practice; this could result in additional capital purchase of 1 tester quarter to quarter. Figure 4.5: Inventory impact analysis In summary based on the justification above, an optimized and flexible manufacturing process flow will ensure improvement in productivity and cost which is significant for continuous sustaining and leading the market segments compared to the competitor. 4.3 Case Study Company This case study will be based in Intel Kulim Microprocessor and Chipset Operation (KMCO or KM5) located in Kulim High Tech Park, Kedah DA. Some of the generic information of the case study company is summarized as below: 47 4.3.1 Background of Company When Kulim High Tech Park (KHTP) was launched in 1996, Intel Microelectronics Sdn. Bhd. was the 1st company to setup its facilities beginning with KM1. Till date, Intel has invested more than RM3.7bil with land size of 75 acres in KHTP alone. Figure 4.6 shows the topography of the Intel Kulim layout in KHTP. Today with its significant growth, Intel Kulim has 3 major operating factories (KM1,KM2 and KM5), 1 R&D facility (KM3) and a multi storey office suites (KM6) with a grossing of 3500 employees. Figure 4.6: Intel Kulim’s topography 4.3.2 Kulim Microprocessor and Chipset Operation (KMCO) KMCO is a 250ku square feet factory building erected in year 2006 with the initial plan to be the largest single platform chipset operation factory was mainly to boost the production of some of the already in operation Intel factories in Asia. KMCO as shown in Figure 4.7 started its full operation mid of year 2007 with 1st chipset product code named ‘Cantiga’. Later in year 2008, with changes in business strategy changes and priority rescheduling, KMCO started to support the high volume and high value microprocessor platform when the mobile microprocessor codenamed ‘Penryn’ was ramped up in KMCO to support Intel factory in Chengdu. 48 Today, KMCO is the 2nd largest factory in Intel’s Assembly-Test-Manufacturing (ATM) ring of factories after Vietnam. KMCO is considered as a mix platform factory supporting High Mix Low Volume (HMLV) products as breakdown below; i. High Volume = Microprocessor, demand of 500ku-2Mu/ week ii. Mix Volume = I/O or graphical Chipsets, demand of 200ku-1Mu/ week iii. Low Volume = Others chipsets, demand of <200ku/week Figure 4.7: KMCO’s factory view Due to the mix platform and volume structure, KMCO is considered a pivotal resource for the organization. Nevertheless, with current structure it is herculean challenge for KMCO to meet and deliver quality products with low cost/unit, high tool utilization and lower cycle time. 4.4 Product Background Today though KMCO supports production of 9 different major products with hundreds of sub-line items and with 5 new NPI products in coming, but the focus of this case study will be on 2 of the major chipset products called Nebula Peak and Nexus Peak. 49 Nebula and Nexus as shown on Figure 4.8 are integrated chipset units build to support the main stream microprocessors especially to function for the I/O and graphics. Nebula and Nexus are first of its kind where both the silicon technology and the processes are apparently new to Intel with no prior successor product to refer on. Nebula and Nexus are chipset units built to serve a similar function but to serve a different market segment. Nebula is introduced for the desktop and server market segment while Nexus is for the mobile market segment. Both the products have significant different of market demand and this trend swing quarter to quarter. Nebula Peak Nexus Peak Figure 4.8: Nebula and Nexus sample units From the analysis of the physical attribute, both this product are significantly same in many ways but differ mainly on the package size where Nebula is slightly bigger compared to Nexus due to the nature of use for this product. Table 4.1 shows a summary of the physical attribute difference between these products. Table 4.1: Physical attributes comparison 50 Figure 4.9 shows a graphical illustration of the product roadmap where Nexus and Nebula will be in production till the mid of year 2011 until it is replaced by a more enhanced next generation chipsets codenamed ‘Orio’ and ‘Wicky’ respectively. This products are the followed on chipset units with main difference on the 3D graphics function accelerator. Table 4.2 shows the Orio and Wicky physical attribute compared to Nebula and Nexus. 4.5 Process Background The process that this case study will focus is the Test Operation area. Figure 4.10 shows a full blown process in respect to Nebula Peak and Nexus Peak. Test operation area is considered as one of the most complex and costly operation in a semiconductor process flow. Orio Wicky Figure 4.9: Product roadmap illustration 51 Table 4.2: Physical attributes comparison to NPI Test operation is the area where units undergo ‘Functional’ testing, where the Die Under Test (DUT) are exposed to multiple electrical test instructed by the test programs under extreme temperatures, typically from the range of -5’C (Cold Test) to +115’C (Hot Test). In Lean perspective, the test operation is considered as a Non Value Added phase as the operation does not significantly change the physical attribute of a device but only test to screen out reject. But nevertheless, this is still considered necessary operation as it is needed to screen out silicon failures due to wafer fabrication and mechanical defects due to process and equipments. A test operation normally consist sets of different test sub modules depending on the product it supports. Test modules are a combination of different test equipments like Tester unit, Test handler, Tester Interface unit (TIU) , Station Controller (SC) and product centric Test Programs(TP). 52 Figure 4.10: The process flow 4.6 Equipment Background The equipment in focus for the changeover is called the M4542AD Dynamic Test Handler or also known as the Extreme Test Handler as shown in Figure 4.11. The test handler is part of a test module and an illustration of a test module setup is as shown in Figure 4.12. The test handler together with the tester is operated for electrical testing using device specific test programs and TIU. Developed by Advantest in year 2003 with an average market price around USD $700k to USD$1.5Million. The equipment became an instant hit in semiconductor industry especially for those with Ball Grid Array (BGA), Quad Flip Chip (QSC) and Land Grid Array (LGA) type of packages. The tester handler is able to perform testing from single unit to a maximum of 8 units per execution. The handler has capability of 6000 devices/hour throughput with index time averaging 1.0sec/unit. This tester handler is able to operate at extreme temperature ranging 53 from -60’C to +150’C including room temperature. The Extreme Test Handler is known mainly for 2 reasons; i) motorized pickup arm that automatically adjust its stroke and speed to prevent device from cracking and chipping, ii) the pressure control mechanism that enables constant and uniform pressure to devices. Figure 4.11: The M4542AD Dynamic Handler Figure 4.12: Test module setup In a test module setup, the most complex equipment is the test handler since most operation, process and mechanical movements happen either in or at the 54 handler portion. 95% of a changeover activity is due to the test handler alone with the highest constraint of the hardware part setups. Besides the test module, the other subcomponents are which is indirectly related to this changeover is the Automated Equipment Performance Tracking (AEPT) which is the core tracking system built in the Station Controller. AEPT system collects, analyze and stores every activity occurs at the equipments in a centralize database called the MARS. The AEPT system are designed based on the SEMI E10 standard where the data collected are categorized by Production, Idling, Engineering, Schedule Downtime, Unscheduled Downtime and Non Schedule time. 4.7 Changeover Process Historical Study The corporate goal for allowed changeover duration is 1.1 hour / conversion while the actual average time taken to complete a test module changeover from Nebula to Nexus (or vice versa) is around at 4.0 hours/conversion. Figure 4.13 shows the changeover time trend based on the data collected from Q2’10 to Q4’10. Figure 4.13: Time trend of conversion from Q2’10 to Q4’10 55 The time trend graph can be divided in to 3 phase: a) Ww13 to ww25 this is considered as the infant stage where changeover of the tester handler was relatively new concept, engineers and technicians were slowed trained to be familiar with the equipment. At this phase, changeover average at 5.0 hours/conversion b) Ww26-ww39 this is considered as the intermediate stage. More formal training emphasize for technicians. Minor improvement efforts like optimizing recipe profiling help to save around 15 minutes of changeover time. Changeover average at 4.75 hours/conversion c) Ww40-ww52 better trained and experienced technicians. Also, some improvements in the TP download time. Changeover average at 4.0 hours/conversion. 4.8 Changeover Process Flow in Detail The generic changeover flow is shown in Figure 4.14 and the details of each of the stages are further explained in detail below. a) Pre Changeover Activities – though not part of an actual changeover process but the activities are important and ‘need to happen’ to ensure the equipment ownership is transferred from ‘Production’ to ‘Engineering’. Some of the significant activities involved in this phase are summarized in Figure 4.15. 56 Pre Changeover Activities AEPT Log In Start of Conversion Preliminary Soft Setups Hardware Parts Setup TIU replacement PnP 'Teaching' Process Dry Cycling with Mechanical Units 8 main generic stages involve in the changeover TP download Standard Unit Run Wrap Up Activities AEPT Log Off End of Conversion Changeover Complete Figure 4.14: The generic changeover flow 57 Supervisor forecast and decide on the changeover need Supervisor identifies the available technician from the team Supervisor and technician identify the equipment to be changeover Supervisor communicates to technician on the expectation and other changeover info Supervisor ensure no lots are queued to be processed by the identied equipment in the system (SYSTEM BLOCK) Supervisor communicates to operator complete the last lot and not to load any new lots Once last lot completes, Operator peforms all neccesary activities called 'End Lot' activity The operator performs basic housekeeping at equipment area The operator log off the ID and look for the technician to handover the equipment Figure 4.15: Generic activities in pre changeover phase i. Based on the current WIP level, tool status and /or priority, Supervisor will assess the need for equipment changeover. This is normally done during the early of the shift and/or mid shift hurdle meeting or when triggered by the Manufacturing Integrator ( normally on shipment priority) ii. Once supervisor decides on the need of changeover, he/she will identify an available and qualified technician in the shift to perform the changeover iii. Technician and Supervisor with mutually walk the line and identify an equipment to be changeover 58 iv. Once the equipment has been mutually agreed and identified, the supervisor will communicate with the operator attached to the equipment to complete the last lot process. Normally, supervisor will reassign the operator to another machine once the lot complete v. In the WIP system, supervisor will block or cancel any new lots in queue to be processed for the identified equipment vi. Once the last lot has completed processing at the identified equipment, the operator will proceed with the following end lot process (by sequence); Physical move out last lot End lot process in the system Physical segregation of good and reject units Counting and visual verification Reject unit process include use red tray, bundle tie with bin card Good unit process include preparing partial tray, bundle tray and bin card Documentation on shift tracking sheet Place good units into shipment trolley and push to next station Send the reject units to RIMS room for disposition action vii. Operator will perform basic housekeeping especially on the work bench before handover the equipment to the technician viii. Operator will log off the ID as user and will go look for the technician to inform on the equipment availability for changeover b) Preliminary Soft Setup – are all the activities performed or occurred once the Technician logs in the ID and the AEPT state changes from ‘Production’ to ‘Schedule Downtime- Conversion’. It is considered as the first official changeover phase and is summarized in Figure 4.16. 59 Completion Pre Changeover Activities Technician logs-in ID and change AEPT from 'PROD' to 'SDTConversion' Change 'sticky' tag and/or Barricade work area Perform equipment temperature setup Collect changekit from maintanence room Collect toolset from toolshop Back to equipment area and standby to start hardware changes Figure 4.16: Generic activities in preliminary soft setup phase i. The technician will log in the ID and subsequently change the ‘Automated Equipment Performance Tracking’ or AEPT state from ‘Production’ to ‘Schedule Downtime– Hard Conversion’ as shown in Figure 4.17. TO Figure 4.17: The change of AEPT state ii. As for visual indicator, technician will change or place the ‘sticky’ tag on the equipment as shown in Figure 4.18 and also once the AEPT state is change to Schedule Downtime, the ‘Andon’ lights towered on top of the equipment will automatically change from ‘GREEN’ to ’RED’ light as shown in Figure 4.19. To ensure safety and minimize disturbance, some technician prefers to use barricades as shown in Figure 4.20 around the equipment area. 60 T O Figure 4.18: The change of ‘sticky’ tag indicators Figure 4.19: The ‘Andon’ Light 61 Figure 4.20: The use of barricades iii. Normally, equipments used prior for production will be under extreme temperature which could range from hot temperature (+115’C) or cold temperature of (-5’C). Thus, the next step in this phase is called the equipment cool down/ warm up activity where the equipment temperature will be set to be in the range between 60’C. The technician will need to reset the temperature in the GUI monitor at the front end of the handler as shown in Figure 4.21 and also to manually turn off the ‘TEMP’ button as shown in Figure 4.22. This is an important step to ensure safety of both the technician and the equipment itself. Figure 4.21: Reset temperature in the GUI 62 Figure 4.22: Manual turn off the by pressing ‘TEMP’ button iv. Next, technician will walk to the maintenance room to collect the changeover kit box which contains all the hardware parts that will need to be replaced as shown in Figure 4.23. Figure 4.23: Example of change kit box with hardware parts 63 v. Lastly, the technician will need go to the tool shop to collect the necessary toolset needed for the changeover. Normally toolbox will contains set of hex keys and screw drivers as shown in Figure 4.24. Figure 4.24: Complete tool sets c) Hardware Part Setups- is the 2nd phase of the changeover and considered as the most complex activity that causes the overall bottleneck in the changeover process. There are 12 major hardware parts involve in this changeover and are summarized in Table 4.3. Table 4.3: Hardware parts involve in the changeover No. Hardware Hardware Image Function Changeover detail Name / Qty LD: To pick the Loader/ 1 Unloader pick up heads (4pcs/set) units from input tray to heat plate ULD: To pick units from exit plate move them unloader tray Each pick up head has 1 screw need to be loosened in order to be removed. A total of 4 screws are involved. To remove and replace 64 use hex keys. A total of 8 screws 2 3 4 Loader/ To ensure units are involved before Unloader are pick up in the 4 blocks can be Y-pitch blocks correct Y-axis removed and (4pcs/set) position replaced. Loader/ To ensure units A total of 2 screws Unloader are pick up in are involved to X-pitch blocks correct X-axis remove and replace (2pcs/set) position the blocks. Plate to place and Changeover of the Heat Plate to heat/soak units heat plate involve (1 pc/set) before they are push and lock of 2 moved to the real clamps functional testing To pick up and Loader/ Unloader 5 buffer/exit pick up heads (4pcs/set) transfer unit from This pick up heads heat place pocket can only removed to buffer stage and replaced using and the unloader a special device pick up from the supplied by the buffer to exit supplier plate 6 Loader / Unloader Only 1 screw for Units from the each buffer plates 65 Buffer stage heat plate are need to be loosen for Front & transferred into before it can Rear the front buffer removed and (4pcs/set) stage and transfer replaced them into chamber (test head)To transfer units to the contact arm unit Act as a stopper to ensure the 7 assembly Are removed and Stopper for mechanism of the replaced by input/exit loader and loosen/tightening of assembly unloader of buffer 1 screw for each (2pcs/set) stage to be in stopper correct location and avoid pick up issues Each chucks has 4 clips and in total of 16 clips to be removed. And, this includes removal Contactor 8 Chucks with nest (4pcs/set) To pick up units and replacement of at buffer stage 2 screws for each loader and test the chuck. Before a units at TIU for new chuck is functional test replaced, a thorough cleaning of the pedestal and nest is required. Also to ensure no temperature issues, a temperature 66 calibration is needed. a full greasing is needed especially on the pedestal The exit plate is Is use to store 9 Exit Plate and position (1pc/set) tested units from buffer stage locked by 6 clamps and technician needs to unlock the clips to remove and replace with new plate Prevent condensation from forming on devices when 10 Unsoak Plate performing low (1pc/set) temperature tests, prior to Need to remove 4 screws from each end to replace a new plate transferring the devices to customer trays 11 Transfer pick To pick up empty To replace, need to up assembly trays from buffer loosen 2 screws and (1pc/set) stoker to remove 1air tube input/output stoker Socket 12 To replace, cleaning plate Plate that place technician need to (1pc/set) the surrogate remove 2 clamps cleaning device and replace with 67 (SCD) coupons new plate. which are used to clean TIU pogo pin. This is a run based activity where cleaning is auto performed for every 5000units. d) Replacement Test Interface Unit (TIU) – changing of the interface component that links the test handler to the tester unit. TIUs as shown in Figure 4.25 are usually kept in a separate maintenance area called TIU room with trained technicians dedicated to handle and maintain them separately as they are prone to pin defects and require special ESD-care. Each TIU are uniquely designed based on product characteristic especially on the package size and the pin counts. Figure 4.26 shows a summary of the generic steps involve in a TIU replacement with detail explanations below. Figure 4.25: Example of a TIU 68 Complete hardware part setups Walk from equipment area to TIU room Request and collect TIU Perform pre-physical setup Perform pre-system setup Walk back to equipment area Undock the old TIU Replace with new TIU Perform post-physical setup Collect old TIU and send back to TIU room Perform temperature setting Perform post-system setup Return to equipment area standby for PnP Teaching Figure 4.26: Generic flow of TIU replacement phase i. Technician will need to walk from the tagged equipment area to the TIU maintenance room to request for a product-specific TIU i.e. Nebula Peak ii. TIU maintenance room administrator will review the request item in the auto-tracking system to locate the exact rack the TIU is stored iii. Once the requested TIU is found, administrator will log out the item from the inventory and handover it to the technician iv. Technician will take the TIU and walk back to the equipment area. The technician will place the TIU on the table and walk to the rear of the handler where the current TIU is docked on the test head as shown in Figure 4.27. 69 Figure 4.27: Rear of the handler v. By pressing the ‘Clamper’ button as shown in Figure 4.28, the current TIU will be released from the test head. The pilot lamp will indicate once the TIU has completely released vi. Technician will next rotate the position wheel anti-clockwise to move the TIU and test head in an downward position as shown in Figure 4.29 vii. Technician will next rotate the position wheel anti-clockwise to move the TIU and test head in an outward position viii. Once the test head reaches to the maximum position, the stopper will automatically halt the movement Figure 4.28: The ‘Clamper’ button 70 Figure 4.29 The position wheels to move the TIU and test head ix. Next, the technician will need to press the ‘PB Free’ button located below on the handler to ensure the hydraulic releases the TIU from the test head x. Then the technician will undock the TIU in an upright and by holding the handle xi. Technician will bring this TIU to the front of the handler area where the table is to place this TIU and pick the new TIU xii. Technician will move back again to the rear of the handler, place the new TIU in the correct orientation on the test head and lock it as shown in Figure 4.30 xiii. Next, the technician will need to press the ‘PB Lock’ button located below on the handler to ensure the hydraulic lock the TIU from the test head 71 Figure 4.30: Docked TIU on test head xiv. Once technician validated the TIU is fully secured, then need to rotate the position wheel in clock wise motion until the test head hits the automatic stopper. xv. Then once the ‘Clamper’ button is triggered again, the TIU will be position on the test head and will be auto-locked xvi. Once completed, the technician will turn on the temperature by changing the setting in the GUI monitor from ‘No Temp Control’ to ‘Temp Control’ and press the ‘TEMP’ button to turn on temperature fully. With this step, the equipment heater will ramp the temperature from the current +60’C to a temperature of +115’C ( +/- 5’C) xvii. Technician will next return the undocked TIU back to the maintenance room for maintenance and storekeeping e) Handler Pick and Place (PnP) ‘Teaching’ - is the process step performed by the technician to calibrate settings of the newly replaced hardware parts. Teaching process is required to ensure the contact between the test handlers and the device under test is fully optimized to avoid intermittent temperature fallouts and PnP errors which could cause both quality and reliability issues during real production runs. Figure 4.31 shows the generic flow of this phase with detail explanations as below; 72 Complete TIU replacement activity Walk to EIMS room to collect Standard Units Pre physical setups Actual 'Teaching' Process Temperature Stabilization Pre system setup and configuration Post system setup and configuration Post physical setups Standby to start the Mechanical Unit Validation Figure 4.31: Generic flow of PnP teaching phase i. Technician will go to the EIMS room to collect a tray full of Standard units (only 4 units are needed for the PnP teaching while other for later validation ii. Once back to the equipment area, technician will need to ensure that all mechanical movements of the handler has fully stopped iii. At the front end of the handler’s GUI monitor, from the main operating screen choose to access into the Command menu. iv. In Command Menu option, choose Teaching Mode Setting screen and access into the Teaching Execution Condition files where commands for teaching are set v. Based on the Teaching documented available (prepared by engineer), manual settings are done in the Teaching Stroke Limit screen. The stroke limit refers to the stroke of the contact press to the test socket vi. Next, return to the Command Menu screen and from the dropdown list, choose the Teaching Sequence button as shown in Figure 4.32 73 Figure 4.32: The command menu vii. The technician then places 2 Standard units on the front and rear buffer stage loader respectively viii. On the Teaching Sequence Start screen, technician will need to specify a target teaching unit mode where the units are placed either Contact Front or Contact Rear and once confirmed technician will choose ‘Start Teaching Sequence’ and activate the ‘Teaching Data Registration’ screen as shown in Figure 4.33 ix. Normally before the 1st teaching sequence can be executed, the equipment will wait for the temperature to stabilize before it proceed with the PnP sequence x. In the Teaching Data Registration’ screen, the motor contact point setting is performed and once complete, the ‘Register Teaching Data’ button is selected xi. Technician will repeat the above steps for the remaining units in the buffer stage 74 Figure 4.33: Starting the teach sequence 75 Figure 4.34: Completing the teaching sequence xii. Once all teaching has been completed with sufficient data and high confidence level, the technician will select the ‘Teaching Has Been Completed’ to exit the Teaching Data Registration and the Teaching Sequence screen as shown in Figure 4.34 above xiii. Lastly the technician will select the ‘Operating State’ button to exit the PnP Teaching GUI and return to normal mode to end this process as shown in Figure 4.35 xiv. Technician will then remove the 4 units from the buffer stage xv. Place the units on the tray and send them back to the EIMS room 76 Figure 4.35: Exiting the PnP teaching phase f) Mechanical Unit Validation – is also known as ‘Dry cycling’ phase where the changeover success will be validated using samples of mechanical units or unit’s without any die attached to it. This is a 1st level validation process where the mechanical units will be cycled as per normal process but without the use of the actual test program. The importance of this validation phase is to ensure all the hardware components fixed are operating as per optimum requirement and no intermittent issues or other mechanical or process related issues like stains on die issues. Figure 4.36 shows a generic flow of this phase with detail explanation as below; 77 Completed the PnP Teaching Walk to Tool Shop to collect 5 trays of Mechanical Units Perform prevalidation visual inspection Temperature Stabilization Perform prevalidation physical setup Perform prevalidation system setup Actual Dry Cycling Process Perform postvalidation system setup Perform postvalidation physical setup Standby for TP download Return units back to tool shop Perform postvalidation visual inspection Figure 4.36: Generic flow of dry cycling phase i. Before starting the ‘Dry’ cycling phase, technician will go to the tool shop to request for 5 trays of Mechanical Units ii. Once acquired, technician will return to the equipment area and will begin will the pre-validation visual inspection using the ‘naked’ eyes. This pre-validation inspection is important to ensure all the units are screened through and only defect-free units are cycled in this phase. If any defect units found in this step, technician will need to return the units back to tool shop and collect the replacement units (Note: if prevalidation visual inspection is skipped, any damage found later during post-inspection will be questionable as the root cause will be unknown and delay the overall process) iii. Once visual inspection completed, the technician will proceed with the system setup where from the Operating State in the handler’s GUI, 78 the technician will select the Mechanical Unit Validation option and Click ‘OK’ iv. While waiting for temperature to stabilize, the technician will load in the trays into the input stage and empty trays in the buffer stage and ensure no other units or trays inside the handler v. Once the temperature stabilization done, the handler will start to process the mechanical unit validation where each and every unit will be process as per normal but without the actual testing enabled vi. The quick dry cycling using the 135 units will test the new hardware fixtures and trigger alarm if any parts are malfunctioning vii. During the dry cycling , the handler auto system will capture all the mechanical part functionality in its data log for technician to review if any issue viii. Once all the 135 units have completed the dry cycling, the completion alarm will trigger for technician to end process ix. Technician will remove the 5 trays from handler’s output stage and place them on the work desk x. Then later the technician will screen through the auto log for any failure report ( normally this is done during the cycling itself) xi. Technician will continue to perform the post-validation visual inspection to screen for gross defects like solder ball damage, scratches on die cap or substrate or any foreign residue or stain on the units xii. If any defects are seen through this visual inspection, the technician will relook into the system log file to understand the failure root cause and will have to re-run the whole dry cycling process xiii. Once a 100% pass is obtained, then technician will end the Dry Cycling process by logging off the ‘Mechanical Unit’ validation option and back to Operating State GUI xiv. Technician will collect the units into the tray and send them back to the tool shop 79 g) Test Program (TP) download – is a set of electrical instructions for the equipment to perform required testing to the device under test (DUT). TP are software coding developed by product content experts during the R&D stage and the complexity of a TP depends on the number of test lines. All of the TP developed are confidential as they contain information on product technology and characteristic which are classified as Intellectual Property (IP). A product can have one or many different TPs which depend heavily on the type of product, the testing requirements or purpose. All authorized TPs are stored securely in the centralized database system and TP are retrieve from this database to equipment through a process called TP downloading. In this phase, since Nebula and Nexus have a different TP version, thus each time a changeover is performed; the TP will need to be downloaded before the equipment is handover back to the Production. Figure 4.37 shows a generic flow of this phase with detail explanation as below; Completed Dry Cycling Process Perform TP reset Technician input info into ELI window System will Initialize SC Actual TP download process TIU initialization Standby to start Standard Unit Validation TP download complete Figure 4.37: Generic flow of TP download phase 80 i. Technician will reset the ASTRA framework to basic Station Controller version to enable the TSS nullify the current TP in the equipment database as shown in Figure 4.38 ii. Once complete of current TP reset, turn back CTSC to ASTRA framework iii. Then click on the ‘Initialize Station Controller’ option which will purge all previous TP related info and prepare the a new CTSC screen without any TP downloaded Change Figure 4.38: Change of CTSC environment iv. Once Initialize SC is complete, the system will prompt with ‘Engineering Lot Info’ window which will require technician to input information of TP name, TP version, product/device name etc. Once 81 the required info is correctly input, the system will auto search the TP and start the downloading process v. A window will prompt showing the duration and status of the TP download as shown in Figure 4.39 vi. Once TP download complete, another window will prompt technician to select the Summary Type; options are STD1 or 2A. For changeover or engineering, STD1 is used as shown in Figure 4.40 while 2A for production retest runs Figure 4.39: TP download status Figure 4.40: Choosing STD1 summary 82 vii. Once STD1 summary has been selected, the downloaded TP will be transferred to the Handler system to initialize the TIU ( this is to ensure the TIU is able to communicate with the tester module ) viii. Once the Initialization has complete, CTSC will prompt message that the system is ready for testing and awaiting technician to click ‘Start Testing’ at handler ix. This complete the TP download process h) Standard Unit Validation- is the final validation process of the changeover where samples of good engineering units called Standards (equivalent to good production units) are tested under production environment with actual TP and temperature settings. 1 full tray containing 27 units will be cycled and tested with requirement of 100% yield with no electrical failure rejects. Standard Units are categorized as High Value Inventory (HVI) thus the availability are limited and stored securely in Engineering Inventory Management System (EIMS) locker room with controlled access. The generic flow of this phase is shown in Figure 4.41 with detail explanations as below; i. Technician will use the Standard unit collected earlier during the PnP teaching phase ii. Technician will start off by performing some basic inspection like units orientated correctly inside the tray pocket and no other abnormalities on the STD units iii. Once complete, technician will load this tray into the handler’s input source and on the GUI system, technician will choose Standard Unit Validation option iv. On the CTSC screen, technician will click ‘OK’ and press the ‘Test Now’ button on the GUI screen to begin the validation process v. Equipment will initialize and the temperature will need to stabilize before the validation testing can proceed 83 Completed TP download Perform prevalidation basic inspection Perform prevalidation system setups Actual validation and testing process Temperature Stabilization Perform prevalidation physical setups Perform postvalidation system setups Perform postvalidation physical setups Complete process, return units back to EIMS Standby to Wrap Up changeover activities Figure 4.41: Generic flow of the standard unit validation vi. Once initialization and temperature stabilize, the actual testing will proceed for all the 27 units vii. Units will be tested with good units place into Bin1 and rejects units into Reject tray at the handler viii. Once all units has complete testing, an alarm triggers to indicate all units are in output trays ix. Technician will collect the units back from the output trays x. For STD unit validation, all 27 units should be in the Bin1 output tray, else technician will need to troubleshoot to understand the issue xi. Once validated, technician will clear log and reset the GUI to return to Operating state window xii. Technician will place all units into tray and send back to EIMS room 84 i) Wrap Up Activities - Is the final set of activities to complete the changeover process before the equipment is handover back to production. Figure 4.42 shows a generic flow of this phase and detail explanation as per below; Completed Std Unit validation Perform basic housekeeping Inform supervisor/operator of completion Return change kits and toolsets Change 'sticky' tags to 'UP' Change AEPT state from 'SDTConversion to 'PROD' Completion of changeever Figure 4.42: Generic Flow in Wrap up Activities i. In this last phase, technician will start by performing basic housekeeping activities like cleaning the work desk from the dirt, debris and other waste items from the previous activities. The housekeeping is needed to ensure the work desk is clean and clear during normal production operations ii. Next, technician will rearrange the removed hardware parts back into the change kit box and the toolsets into the tool box. Technician will 85 return the changekits and toolsets to the maintenance room and toolshop respectively iii. On the way, technician will inform the supervisor who sits in the supervisor room or else any operator available to start loading production lots iv. Once back to equipment area, technician will change the sticky tags from ‘Down’ to ‘Up’ v. Once the operator is available or the supervisor has acknowledge the changeover completion, the technician will change the AEPT state from ‘Schedule Downtime-Conversion’ To ‘Production’ and technician will log off his id as user vi. Changeover process is complete and equipment is successfully handover back for Production use 4.9 Problems and Gaps Identification Table 4.4 below shows a general summary of the current changeover process discussed previously and the average duration to complete each of the activity. Thus, there is a changeover gap of 4 hours between the last good run lot to the next good run lot. The impact of this time-consuming changeover has been assessed earlier from the point of utilization, cycle time and cost, thus this justifies the need to improve the current process. The ultimate objective of this project is to reduce the changeover duration by optimizing the processes and activities involved. This is possible by identifying and systematically eliminating waste or non value added activities in each of the current changeover process phase. In the next following discussion, problems and gaps identified at each stage will be highlighted and analyzed in detail. 86 Table 4.4: Summary of the changeover process Sequence No. Activity and Milestone Pre Changeover Activities Details Average Time (minutes) Supervisor communication and alignment with technician End lot process for the last production run Not included in changeover time Official start of changeover process with the change in AEPT 1 Preliminary Soft Setup Activities 2 Hardware Part Setups Tagging of equipment i.e. sticky pad or barricading area Preparation of change kit and toolsets 12 major hardware part setups Bottleneck of the overall changeover process TIU replacement Interface unit that need to be replaced 3 4 PnP 'Teaching' Process 5 Dry Cycling with Mechanical Units 6 TP download 7 Standard Unit Run 8 Wrap Up Activities 6 160 11 Required calibration process each time hardware parts are replaced 9 1st validation process on the hardware part setup Using 5 trays of mechanical units 19 Ensure end of cycle, 100% pass with no mechanical defects Software coding to instruct tester to perform electrical testing 2nd validation performed using good production samples of 1 full tray Validation under real production atmosphere Ensure all units pass with 100% yield Housekeeping and cleaning up work area Official end of the changeover activity by change in AEPT TOTAL 14 15 6 240 Internal Time 87 4.9.1 Pre-Changeover Activities As mentioned earlier, though not an actual changeover phase but the pass over coordination and communication activities that takes place at this phase are equally important. Figure 4.43 shows the generic flow of this phase with the estimated time taken to complete each of the activity. Some of the common problems and gaps observed during this phase are listed in the Table 4.5. 7 minutes 5 minutes 5 minutes 10 minutes 3 minutes 30 minutes •Supervisor finds and identify the technician •Communicate on changeover request •Supervisor and Technican decide and identify of the equipment for changeover •Supervisor communicates with operator to complete the last lot •Assign operator to other equipment upon completion • Ensure no new lots or WIP in queue to be process for the identified equipment •Operator performs end lot process •Include move out lot, reject preparation, documentation etc •Operator performs basic house keeping activities •Operator log off ID as user and passover the equipment to technican •Total EXTERNAL time spent for the Pre Changeover Activites Figure 4.43: Time study of pre changeover activities 88 Table 4.5: Problems identified at the Pre-Changeover phase No # Problems or Gaps Identified Many non standard practices observed especially: Changeover request done on ad-hoc basis across all shifts 1 No proper process to define or identify the equipment for changeover Potential delay of overall changeover process due to; misunderstanding and miscommunication waste in motion, walking and transportation The 13 minutes operator spends for end lot process and 2 housekeeping are actually opportunities for technicians to capitalize in preparing upfront for the changeover. Today technician idle during this period 4.9.2 Preliminary Soft Setups The preliminary soft setup activities are the 1st phase of actual changeover activity that involves 4 sub activities. Figure 4.44 shows a generic flow of this phase and the time taken to complete each of the activity. Based on the multiple observations done, most of the problems identified at this phase are related to NVA practices and are summarized in Table 4.6 below: 89 0.5 minutes 0.5 minute 3.0 minutes 2.0 minute 6 .0 minutes •Technician log in ID as user •Change AEPT state from 'PROD' to 'SDTConversion' • Changing Sticky pad from 'Up' to 'Down' •Barricading work area • Walk to maintanence bay and toolshop to collect changekit and toolsets •Setup to cool down/warm up equipment •Temperature stabilize •Total INTERNAL time spent in Preliminary Soft Setup activities Figure 4.44: Time study of preliminary soft setups Table 4.6: Problems identified at the preliminary soft setup phase Problem Problems or Gaps Identified No # Existence of many non standard practices especially: 1 Different technician /shifts practices different work flow or sequences Some technician practice on deploying barricades around work area while some don’t Potential delay overall phase > 6 minutes 2 Many of the INTERNAL activities practiced today does not VALUE ADD directly to the changeover process especially; 90 Practice of placing barricades/sticky pads Walking to and fro between tool shop/maintenance room and equipment area to collect toolset/change kits If able to remove or performed as EXTERNAL activity, potential able to salvage 3.5 minutes Temperature setting (cool down / warm up) practiced as EXTERNAL activity which delays ~2 minute. Technician idle during this period 3 If able to perform this as a EXTERNAL activity potential reduction of 2.0 minutes 4.9.3 Hardware Part Setups Hardware part setups contribute to the major bottleneck concern in this changeover process. Figure 4.45 shows a summary on the generic hardware parts changed as per practiced today with the average time taken to complete each of the activity. From the table, the major bottleneck part change is the replacement of the contactor chucks and Table 4.7 shows the current changeover flow for this part. Also, the other problems identified at this phase are summarized in Table 4.8: 91 Loader & Unloader Pickup Heads •4 pcs/set • 4.0 minutes/set to replace Loader & Unloader Y-pitch Blocks •4 pcs/set •4.0 minutes/set to replace Loader & Unloader X-pitch Blocks •2 pcs/set •4.0 minute/set to replace Heat Plate •1 pc/set •0.5 minute/set to replace Loader & Unloader Buffer/Exit Pick Up Heads •4pcs/set •8.0 minutes/set to replace Loader & Unloader for Front & Rear Buffer Stage •4pcs/set •4.0 minutes/set to replace Stopper for Input/Exit Assembly •2 pcs/set •2.0 minutes/set to replace Contactor Chucks •4 pcs/set •120.0 minutes/set Exit Plate •1 pc/set •0.5 minute/ set Unsoak Plate •1 pc/set •0.5 minute/set Transfer Pick Up Assembly •1 pc/set •13 minutes/set Soak Cleaning Plate •1 pc/set •0.5 minutes/set Total time for Hardware Changeover = 160 minutes Figure 4.45: Time study of hardware part changes 92 Table 4.7: Sequence of the Contactor Chuck Replacement No Actual Photo(s) Description Time taken(min) Remove all current contactor 1 chucks from the 8 handler Replace the old 2 chucks with the new chucks from the change kit box 3 93 Collect new chucks and 3 arrange 1 accordingly on work desk Clean each chuck with cotton swap 4 dipped with 16 Isopropyl alcohol(IPA) Remove nests 5 from all the 8 chucks Remove all the 6 6 pins from each of the nest 3 94 Again, use cotton 7 swap and IPA to clean each of the 12 nest Use the air gun to 8 dry each of the 4 nest Place all 6 pins 9 back into each of 4 the nest Clean the nests 10 again with cotton swap and IPA 8 95 Remove the contactor components ( 11 4pcs) from each 4 of the chuck and clean them with IPA as well Use the air gun to 12 dry each of the 4 components Fix the contactor 13 components back to the chucks 6 respectively Fix the nest back 14 to respective chucks 8 96 Use clean cloth to 15 wipe residue on the contactor and 4 the chuck Walk to the rear on the handler and place all 16 newly setup 1 chucks at the bottom of the handler Use clean and dry cloth to wipe and 17 clean the internal 4 part of the handler’s chuck With cotton swap, perform 18 greasing to the internal chuck parts 2 97 Clean and grease 19 the contactor 2 chuck calibrator Insert calibrator into each chuck 20 socket to re- 6 calibrate the chuck heads Once calibration done, fix respective 21 contactor chucks 12 to the chuck socket and ensure all clip are locked Total 120 minutes 98 Table 4.8: Problems identified during the hardware part changes Problem Problems and Gaps Identified No# Changeover of the hardware parts are performed without any 1 standardized sequence i.e. replacement of parts in wrong order delaying overall process Some of the hardware components today have similar physical 2 attribute and function, thus might be fungible and does not need to replace Changeover involve many small, delicate and hard to be handled 3 4 parts Changeover involve many screws, bolts and/or fasteners i.e the X and Y pitch blocks requires up to 7 turn to tighten or loosen The overall bottleneck in the hardware part changeover is during 5 the replacement of the contactor chuck which involve many NVA activities like greasing, alignment and calibrations 6 The generic hardware parts design are not fully optimized and need only minor modification to enable as a fungible part 99 4.9.4 TIU replacement Once all the hardware parts have been successfully replaced, the technician will move to the next phase called the TIU replacement. Figure 4.46 shows a generic flow of the TIU replacement that is practiced currently with the time taken to complete each of the activity. 2.5 minutes 3.0 minutes 4.0 minutes 1.5 minutes 11 minutes •Walk from equipment area to TIU room •Request & Collect TIU •Walk back to equipment area •System setup •Undock old TIU activities •Dock new TIU activities • Temperature setting increase from +/-60'c to +/-115'c •Walk from equipment area to TIU room •Return old TIU • Walk back to equipment area •Total Internal time spent at the TIU replacement phase Figure 4.46: Time Study of TIU change phase In the time study flow above, only 3 minutes of the overall 11 minutes is actually spent on the actual TIU change. A list of problems or gaps observed at this phase is summarized in the below Table 4.9 together with its forecasted impacts. 100 Table 4.9: Problems identified during the TIU replacement phase Problem Problems and Gaps Identified No# 1 Only 3 minutes of the 11 minutes spent are used for the TIU replacement while others are NVA activities 2 Almost 4 minutes spent in just walking from equipment to/from TIU room which is a waste in motion practiced Internally 3 Performing temperature setting ( increase from current temp +/- 60’C to +/- 115’C ) INTERNALLY during the TIU replacement are delaying the overall changeover process 4.9.5 PnP Teaching Process This is a requisite step that needs to be performed each time hardware components are replaced. PnP teaching is required to ensure proper contact between the chuck and the device under test. Figure 4.47 shows a generic flow of this phase together with the time taken to complete each of the steps. Table 4.10 summarized the list of problems and gaps identified at this phase. 101 2.5 minutes 1.35 minutes 1.25 minutes 2.2 minutes 0.5 minutes 1.15 minute 8.95 minutes • Collect 1 full tray of Standard units from EIMS room • Pre Physical Setups and validation • Pre system setup and configuration • Include temperature stabilization • Actual Teaching Process • Post system setup & configuration • Post physical setup and validation • Total Internal time spent for PnP Teaching Phase Figure 4.47: Time study for PnP Teaching Phase 102 Table 4.10: Problems Identified during the PnP Teaching Phase Problem Problems and Gaps Identified No# 1 The collecting and returning Standard Units performed as INTERNAL time delays the overall process 2 The temperature turned ON during the TIU replacement step does not serve purpose or required in this PnP teaching phase 4.9.6 Dry Cycling Validation This is the 1st phase of validation involving the mechanical units or units without die. Dry cycling is required to ensure the mechanical parts or movements are functioning as per requirement and are reliable during real production use. Figure 4.48 shows a generic flow of the Dry Cycling and the time taken to complete each of its steps. Table 4.11 summarized the list of problems and gaps identified at this phase. 103 2.5 • Walk to tool shop to collect the mechanical units minutes 2.75 • Pre dry cycling visual validation minutes 0.35 • Pre dry cycling physical setups minutes 1.5 • Pre dry cycling system setups + Temperature stabilization minutes 7.0 • Actual dry cycling process minutes 0.25 • Post dry cycling physical setups minutes 1.0 • Post dry cycling system setup minute 2.75 • Post dry cycling visual validation minutes 2.5 • Walk to tool shop to return the units minutes 20 minutes • Total Internal time spent for Dry Cycling Phase Figure 4.48 Time study of dry cycling phase 104 Table 4.11: Problems Identified during the Dry Cycling Phase Problem Problems or Gaps Identified No# Waste in motion/transportation observed when the technician walks to/from the tool shop to collect the mechanical units. 1 This is practiced INTERNALLY currently and delaying the start of this phase 2 The visual verification using bare eyes are actually causing delay because technician need to perform verification a few times for unclear reject signatures Potential delay in starting the Dry Cycling process due to mechanical units is collected from tool shop fails the pre3 validation inspection i.e. existence of marks, stains etc. Technician need to walk back to tool shop to returns these units and collect replacement unit which are free from defects 4 5 The temperature turned ON during the TIU replacement step does not serve purpose or required in this dry cycling phase The dry cycling process today uses 5 full trays of units and consumes almost 7 minutes to complete. This is a NVA activity but needed only due to validation reasons 105 4.9.7 TP Download Phase The next phase of the changeover is the Test Program (TP) download step. Again the generic steps involve in this phase together with the time taken to complete each step is as shown in Figure 4.49. Table 4.12 summarized the list of problems and gaps identified at this phase. 2.85 minutes 7.0 minutes 4.15 minutes 14.0 minutes • Pre TP download setup • Includes choosing recipe, CTSC reboot etc • Actual TP download duration from server to equipment CTSC • Post TP download Setup • Include system initialization, TIU check etc • Total INTERNAL time spent in the TP download phase Figure 4.49: Time Study of TP Download Phase Table 4.12: Problems Identified during the TP Download Phase Problem Problems and Gaps Identified No# 1 During the Actual TP download duration and TIU initialization, the technician was just idling 2 TP download error due to TIU initialization fail could prolong the process 106 4.9.8 Standard Unit Validation phase This is the final validation run using samples of good production units. This phase is important to ensure the whole changeover of both software and hardware is fully validated before the equipment is released back for the production use. Figure 4.50 shows the generic flow in this phase together with the time taken to complete each of the steps. Table 4.13 summarizes the list of problems identified in this phase. 3.5 minute 3.95 minutes 3.2 minutes 0.95 minutes 1.0 minutes 2.5 minutes 15.0 minutes •Pre-Validation Phsysical setup •Include quick validation and tray load in •Pre-Validation System setup •Include Machine Initialization & Temp Stabilization •Actual Validation Processing •Post-Validation System setup •Post-Validation Physical setup •Walk back to EIMS to return the units •Total Internal time spent in Std Unit run Figure 4.50: Time study of standard unit validation 107 Table 4.13: Problems identified during the standard unit validation Problem No# Problems and Gaps Identified 1 The Std unit collected from EIMS room has physical defects i.e. solder ball defect, stains which cause need for technician to walk back to EIMS room to seek for replacement units which are defect-free 2 Because the temperature was turned ON earlier, it took almost 1.5 minute to re-stabilize the temperature back to 115’C which is needed before the Standard Unit validation can proceed 3 The overall process of Standard Unit validation can be considered as a NVA step but necessary for validation. It takes almost 15 minutes to complete a 1-tray STD unit validation 4.9.9 Wrap Up Activities This is the final phase before the equipment is fully handover back to the production. Some of the generic activities involve this is phase is shown in Figure 4.51. The problems and gaps identified in this phase are listed in Table 4.14. 108 3.5 •Housekeeping activities •Include clean up of the work desk, placing tools and hardware into respective box •Change sticky pad from 'Down' to 'Up' minutes 2.0 •Communication activites •Includes technician looks for supervisor/operator to inform on completion minutes 0.5 minutes •Technician change AEPT state from 'SDT-Conversion' to 'PROD' •Technician log off ID 6.0 minutes •Total Internal time spent during the Wrap Up activities Figure 4.51: Time study of wrap up phase Table 4.14: Problems identified during the wrap up activity phase Problem No# Problems or Gaps Identified 1 The changeover duration is prolonged 4.5 minutes because the technician often changes AEPT state after completing housekeeping and the communication process 2 All of the activities performed as NVA and does not need to be practiced as Internal activity, need to find way to move this activities towards the end of the changeover 109 4.10 Summary In summary, this chapter illustrated 2 points which is the case study and also the problem identification. The data gathered at this chapter will be use for counter proposals and outcome analysis in the next discussions. CHAPTER 5 PROPOSED FRAMEWORK 5.1 Overview This chapter is important as it directly relates to the objective of this project on reducing the changeover process duration by integrating the SMED and TRIZ techniques. The following discussions will focus directly on counter measure proposals for the problems and gaps that were identified previously. 5.2 Strategy and Execution for Counter Measures The root cause of the problems identified earlier can be summarized into 3 main factors namely; i. Human (technician) ii. Equipment (handler) iii. Process Flow The changeover duration today depends on the interaction of these factors as shown in Figure 5.1. In order to systematically counter the problems, an integrated proposal framework consisting both SMED and TRIZ technique will be introduced. 111 As mentioned earlier, both techniques are well renowned with individual strengths and integration of both will compliment the shortcomings to achieve a better optimized process. HUMAN EQUIPMENT PROCESS Figure 5.1: The changeover duration factors Figure 5.2: The generic proposal model Figure 5.2 shows a generic proposal model which will be utilized throughout this chapter. Each identified problem will go through the 3 ‘conceptual’ stages as shown driven by the SMED and TRIZ techniques. A problem will be proposed with 1 or more techniques with to achieve one of the conceptual stages. The techniques proposed can be a generic technique from Shingo’s SMED technique or Altshuller’s TRIZ. Nevertheless, some of the technique proposed will be a combination of both in order to achieve a more enhanced solution. Figure 5.3 shows a flow of the technique extraction from both methodologies. 112 Figure 5.3: Extraction of the proposal techniques In order to systematically execute the proposals, the identified problems will be truncated and categorized into 3 main groups which are; i. Process Flow Optimization – will focus on process gaps which involves identifying and separating elements, eliminating Non Value Added elements, improving parallel activities and streaming some of the tasks ii. Hardware Part Setup Optimization – identifying hardware parts significant to the changeover and improving hardware designs iii. Improving the human dynamic and procurements – are generic elements related to standardization in human practice and documentation 113 5.3 Process Flow Optimization This is the first and foremost counter measure proposal step where the current generic changeover process flow as shown in Figure 5.4 is considered as nonoptimized due to: i. The ‘successive serial’ flow of activity as shown in Figure 5.5 ii. The practice of Non Value Added (NVA) or waste activities iii. The non standardize and /and complex practices All the above 3 elements are induces the process to delay further and also the possibility of both safety and quality issues occurrences. Figure 5.4: The generic ‘non optimized’ changeover flow 114 Figure 5.5: The ‘serial’ flow of activities In order to convert a non optimized process to an optimized and efficient process, the functionality of each phase of changeover will need to be reassessed especially by: i. Identifying individual/group task type ii. Segregating task by value to changeover iii. Minimize, substitute (streamline) or eliminate task iv. Introduce parallel activity execution Each task or activity in the changeover stage can be divided into either External or Internal elements. External activities are those executed without impacting the changeover duration. These types of activities are normally performed offline or during the process of other activities. Internal activities on the other hand are those activities that can be executed or performed with machine/process interrupted and impacting the changeover duration. Internal activities are the major driver of pro-longed changeover duration. Once each of task type has been identified, the next step is to define the functionality of these activities. Each of the External and Internal task can be categorized into 3 main groups; the Value Added (VA) activities, the Non Value Added but required activities and lastly the Non Value Added waste activities. It is 115 important to segregate definitely the Value Added activities which has significant role the changeover as compared to the Non Value Added activities. It is important to note that although most NVA activities are insignificant and deemed as waste to the process but a handful of them are directly part of the requirements, routine or procedures which makes it tougher to be eliminated. Next step is considered important as it will vet the above mentioned categorized activities to achieve a more lean process with lesser serial sequences. In this phase, the activities will be considered to go through either one of more of the following vetting process; i. Moving the easy, simple and low risk Internal task to External Task ii. Eliminate the NVA waste activities iii. Substitute or use engineering solutions to streamline the NVA but required activities iv. For Internal activity which are value added, find ways to minimize or stagger the task involve The last step is actually the end result of the above 3 steps that is the introduction of parallel activity execution. Parallel activities enhance the opportunity to pull-in and perform multiple activities at a single phase. Enabling parallel activity execution will help to truncate the overall changeover and help to restructure the activity sequencing. 116 5.3.1 Upfront Setup Improvement Proposals The first and ‘obvious’ improvement proposal is to introduce a better and standardized upfront setups activities before the actual changeover commences. A proper early preparedness guarantees in the changeover activities reduction and minimizing the overall NVA activities occurrences. In SMED, Shingo’s introduces a Stage 2 technique called the ‘Preparing Operating Conditions in Advance’ where the technique requires certain tasks which are directly related to the changeover to be performed and completed earlier than the current practice. Similarly, in TRIZ this technique is part of Principle No. 10 called ‘Preliminary Actions’ but it expanded the scope by suggesting not only performing an action before it is needed, but it can be perform either fully or partially depending on the situation. Also this TRIZ technique also suggest that to optimize this technique, ensure the objects involve in this action are pre-arranged that they can come into action from the most convenient place without losing time for delivery. The goal of this proposal is to identify all activities that are directly related to the changeover and can be prepared or performed upfront. The advantage of this SMED’s technique is that it will help to convert many of the current Internal elements to External element. From direct observation analysis, the 5 pre requisite kits for this handler changeover are: i. Hardware Change kits ii. 1 set of toolbox iii. TIU iv. 5 trays of Mechanical Units v. 1 tray of Standard Units 117 Table 5.1 shows the current practice of acquiring the 5 pre requisite items during the respective stage therefore increasing the Internal time. The opportunity here is to follow as per SMED and TRIZ technique which is to move this to be part of a standardized upfront setup activity which is compulsory to be done before a changeover commences. To minimize further the NVA waste activities like multiple walking or repeated request submission, per TRIZ’s ‘Beforehand Cushioning’ technique proposal is that technician acquire or prepare more than required part before the start of the changeover. For instance is that technician can collect and prepare more than the required 5 trays of mechanical units as if there is any defect found in the units during the pre validation visual inspection, the technician can quickly replace with the buffer units rather than the need to go back to the tool shop and request for a new set of units. Table 5.2 shows a list of ‘Beforehand Cushioning’ proposal that can be performed during the early setup. Table 5.1: The 5 pre requisite items and current practice Phase Items Task Acquired Element Hardware Setup Soft Setup Internal Tool sets Hardware Setup Soft Setup Internal 3 TIU TIU replacement TIU replacement Internal 4 Mechanical Units Dry Cycling Dry Cycling Internal 5 Standard Units PnP Teaching Internal No. Pre Requisite Item Phase Items required 1 Change kits 2 PnP Teaching and Standard Unit Validation 118 Table 5.2: The ‘Beforehand Cushioning’ proposal Since all the 5 items are located at different areas in the shop floor (except change kits and tool sets are placed together in the tool shop), it will be a challenge for technician to move these items to the equipment area. In order to eliminate multiple walking or waste in motion, the next proposal is to use a trolley or cart that will be able to store and move all items together. This not only minimizes the walking time but also reduce the possibility of mishaps like dropping of units or damaging TIU etc. The use of trolley is inspired by the SMED’s ‘Improving Part(Die) Transportation’ where Shingo reckon this as part of SMED’s stage 2 technique in improving Internal element to External element. To improvise further, as per TRIZ’s ‘Prior Action’ technique suggestion, arranging the 5 pre requisite items in order of usage i.e. change kit box and toolbox on top shelf followed by TIU and last the validation units will help to improve the efficiency. As earlier mentioned, the upfront setup phase can consist of all activities that are related to the changeover and can be performed earlier without jeopardizing the activity flow. Identifying the potential upfront setup activities can be done using the activity dependency mapping as shown in Table 5.3. From the table below, only Soft Setup and TIU replacement stage are potential stand alone activities which can be performed as part of the upfront setup activities. With this assumption, the first streamlining of activity will be combining both this phases and performing them together as ‘External’ activities before the changeover process officially commences. 119 Table 5.3: The activity dependency table Soft Hardware TIU PnP Dry TP Standard Wrap Setup Setup replacement Teaching Phase download Unit run Up Activity Soft Setup x Hardware Setup TIU replacement PnP Teaching X x Dry Phase X x x x TP download Standard Unit run Wrap Up Activity x X x x x x X x x x x x The biggest available opportunity to perform the Soft Setups and TIU change is during the Pre Changeover phase which currently involves all communication and coordination activities performed as External element. As highlighted earlier, the technician practically idles from the moment the supervisor confirm the changeover till the completion of the end lot process by operator before the equipment is handover to the technician. This interim idling period will serve as the execution opportunity for the new proposal of performing Soft Setups and TIU change as External task. Before this can be executed, the current Soft Setup and TIU change activities need to be re-evaluated again to ensure only the Value Added activities are practiced per the new upfront setup proposal. The 3 significant activities from current Soft Setup phase that need evaluation are: i. The practice of placing ‘DOWN sticky’ tags before the changeover starts. This though considered as a NVA activity but is required as part of visual factory indicator. Nevertheless, this can be practiced as External element rather than Internal if performed during the Pre Changeover phase 120 ii. Placing barricades around the equipment area is not a common practice but still performed by some as measure of safety. Propose to eliminate this activity with justification that changeover are low safety risk with no major hardware overhaul iii. Technician performing equipment temperature setup (i.e. cool down temperature to ~60’C) before hardware setup can commence; is also another opportunity to convert from current Internal to External. Optimize the operator’s end lot period to parallel perform this. Using TRIZ’s ‘Segmentation’ technique, the TIU change phase can be fragmented as shown in Figure 5.6. The technique proposed is useful for separating Internal and External activities where in this case, the segmentation will also help to identify the NVA activities inside the TIU change phase. The current activities can be segmented into 4 sections are per the color coding below: Figure 5.6: Illustration of ‘segmented’ TIU phase i. Segment 1: Collecting TIU as an internal activity can be rescheduled and be made part of the compulsory upfront setup activities as earlier mentioned. Thus, this can be eliminated. ii. Segment 2: Consist of 4 activities which require 3 minutes to complete. These are the only VA activity of this phase and thus cannot be eliminated. Nevertheless, all these 4 activities are Independent activities where they can be performed without the concern of its predecessors outcome. In other words, these activities can be eliminated from this phase and performed together in parallel during the upfront setup. iii. Segment 3: Technician normally performs equipment temperature setting (increase from room temperature to hot temperature of 115’C) post 121 hardware replacement. From observation, the temperature setup as early after TIU replacement delays all the subsequent activities (i.e. Temperature Stabilization) as the correct temperature setting of 115’C is only needed during the Standard Unit validation before the equipment is handover back to Production. In other words, performing temperature setup is a NVA activity in this phase and the subsequent phases thus proposal is to move this activity to be part of the Standard Unit validation’s system setup activity. iv. Segment 4: Returning the old TIU back to TIU room for store keeping is a NVA activity and does not need to perform during the changeover time. This is logical and thus proposal is to keep the old TIU and all items returning practice can be accumulated and performed towards the end of changeover process as External time. With the above proposals, it is clear that the current TIU change phase not only could be practiced as a standalone activity during the upfront setup phase but also truncate the whole activities as the NVA steps can be eliminated. Other minor improvement proposals which will be part of the TRIZ’s ‘Prior Action’ technique are the upfront setup of empty JEDEC trays inside the handler. The pre physical setup during validation phases are delayed mostly due to the fact of needing technician to insert new trays into the input and buffer stage of the handler before the actual process can commence. With new proposal, technician will load in empty trays into the buffer stocker as part of the upfront setup activity. Figure 5.7 shows a generic summary of the changes in the changeover process with the above counter measure proposals. The most significant changes will be reduction of changeover phases and duration with more activities performed in parallel during the upfront setup phase. 122 Figure 5.7: The generic changeover process flow with upfront setup proposals 5.3.2 TP Download Improvement Proposals The TP download phase is a dependent Internal activity that can only be performed once the new TIU has been properly replaced and setup. It is a requirement today that technician will need to ensure the correct Test Program has been downloaded into the test modules before returning the equipment back to the Production ( in order to minimize Production Downtime). Due to this requirement, improving and optimizing this phase is equally important. Using TRIZ’s ‘Segmentation’ technique again, the major activities that make up the TP Download phase can be shown as in Figure 5.8. The 5 major activities can be divided into 2 segments i. Dependent Tasks ii. Independent Tasks 123 Figure 5.8: Segmented TP download phase The dependent task of the TP download phase can be described as activities that require manual interaction from the technician especially on instructions and parameter input to the system in selecting and downloading a current TP. During this period, the equipment or the handler will be idling with no other activities allowed to take place as machine is awaiting or analyzing the instruction. Thus, dependent activities will remain as ‘Internal’ elements with no significant changes. The independent task of the TP download phase is utmost unique compared to other activities as per the observation. The 2 activities listed as Independent tasks are actual activities that run on the ‘background’ or known as passive activities. As observed, once the correct parameter and setting has been done by the Technician, the system will auto-start the TP download from the centralized server into the equipment database and subsequently continue with the system initialization process with the new TIU docked. From the data analyzed, the 11 minutes of Independent activities execution is an opportunity to perform other setup in parallel. From the current changeover process, the only activity that can be performed in parallel during the TP Download phase is the Hardware Part Setup activities which is mutually exclusive and does not interrupt the download or the initialization process. In SMED, Shingo suggested the ‘Parallel Execution’ technique as the basis to streamline activities to achieve process optimization. 124 For better enhancement, the actual TP download duration of current 7 minutes can be further reduced if the current 100MB public network cables are substituted with the new broader and efficient 1GB network cables. Besides to expedite TP reset and SC switch, if the current Station Controller’s Memory (RAM) and processor (CPU) are upgraded to a better and higher speed units. This system and network upgrade will require high cost but will able to salvage 50% of the current duration. Though the new proposals above did not directly minimize the Internal time of the TP Download stage but the proposal of executing Hardware Part Setup will help to reduce the overall Internal time. Figure 5.9 shows an illustration of the changeover process with TP download now reschedule to be the first Internal time activity of the changeover with Hardware Part Setups performed in parallel when the actual download process takes place. Figure 5.9: The changeover flow with TP Download improvement proposal 125 5.3.3 Validation/Calibration Improvement Proposals As highlighted during the problem identification phase, the validation practices in the current changeover process is a major setback in achieving a quicker and leaner conversion. Almost 18% or 43 minutes is spent on performing the PnP Teaching, mechanical and standard unit validation. The most significant similarity between these 3 stages are that there are inter dependent on each other where PnP Teaching is dependent of the Hardware Setup and all previous setup while Mechanical unit validation is dependent on PnP Teaching and all previous setups and lastly Standard Unit Validation is all fully dependent stage. This ultimately shows that all these 3 stages can only be executed in a typical serial show as currently practiced. This condition limits much of the improvement proposals but nevertheless, the real optimization opportunity is actually the activities embedded inside this phases. Both Mechanical unit and Standard Unit validation have very similar steps especially on the requirement of performing Pre Validation Visual Inspection. This step is required to ensure only good and reject free units are tested during the process to eliminate ‘noise’ factor during actual validation. The practice of performing Pre Validation VI as Internal element currently can be opt to be performed upfront especially during the period technician idle or when machine is busy processing. From observation and data collected, an average technician idle time during each phase is summarized in Table 5.4. To reduce the Internal time spent for the Pre Validation VI, proposal is for Technician to perform the Pre VI for all 5 trays of mechanical units during the PnP Teaching phase while capitalized the idling time during Mechanical Unit validation to perform the VI for the 1 tray of Standard Units. This can be linked back to both Preparing Operation Condition in Advance and Prior Actions techniques from SMED and TRIZ respectively. To help improve the Visual Inspection’s efficiency and reduce the duration, the proposal is to introduce magnifier scope at work desk for technician to perform the Visual Inspection. The magnifier scope will replace the current bare eyes inspection which is both time 126 consuming and error prone. Introducing a scope is part of the SMED’s ‘Mechanization’ technique where Shingo suggest improvising manual work with the help of better efficient tools. Table 5.4: Technician idle time The validation phases are also ‘plagued’ by NVA or waste activities like the act of returning the units back to respective room once the validation complete and this is performed as Internal time. As suggested earlier, all practices of retuning kits and items will be standardized as a post setup activities which will be performed only when the changeover complete as External elements. In TRIZ, this is called the ‘Taking Out’ technique where elements that are not needed are vetted out from the process. The validation of using 5 full trays or 135 mechanical units contributes to the long validation period with each tray requires 1.5 minutes to complete. Standard unit validation using 1 tray takes around 3.2 minute to complete. As validations are NVA, the proposal will be to streamline both activities by either: i. Reduce the Mechanical Unit samples but remain Standard Units samples ii. Eliminate Mechanical Unit validation and combine together with the Standard Unit validation with higher sample quantity 127 iii. Eliminate Mechanical Unit validation and combine together with the Standard Unit validation with same sample quantity iv. 5.3.4 Eliminate both validation phases Post Setup Activities Alignment Proposals As highlighted during the early phases, those activities categorized as NVA and waste which cannot be directly eliminated or embed part of other phase will be proposed to be aligned and performed towards the end of the changeover process. Using TRIZ ‘Merging’ technique, all the NVA activities identified throughout the changeover process is listed in Table 5.5 below. Table 5.5: ‘Merging’ technique on identifying NVA activities No. Post Setup Activity Phase Activity practiced Task Element 1 Returning TIU back to the TIU room TIU replacement Internal 2 Returning Mechanical Units to the toolshop Dry Cycling Internal 3 Returning Standard Units Standard Unit validation Internal 4 Return changekit and toolsets Wrap Up Activity Internal 5 Housekeeping and changing 'sticky' tag Wrap Up Activity Internal 6 Changeover completion communication Wrap Up Activity Internal From earlier discussion, the reason behind the pro-long duration of the Wrap Up activity phase is because all the NVA activities are performed as Internal element with AEPT state change performed towards the end of the flow. To ensure all these 128 NVA activities are captured as External element, the proposal is to first complete the changeover and log off the AEPT system before performing all the activities listed above. In other words, applying the TRIZ’s ‘Do it the other way’ technique, the current flow of the Wrap Up activity phase is inverted or mirrored with AEPT system setup performed first followed by the other activities. Below is the proposed sequence for the new post setup phase: i. AEPT change state from ‘SDT-Conversion’ to ‘PROD’ ( log as official completion of changeover process) ii. Housekeeping activities i.e. cleaning of the work desk, area around the equipment iii. Inform supervisor/operator on the changeover completion and equipment readiness for process iv. Change the ‘sticky’ tag from ‘DOWN’ to ‘UP’ v. Re-arrange all hardware parts into the change kit accordingly vi. Re-arrange all tools back into the toolbox vii. Place the change kit box and toolbox on the trolley viii. Ensure the TIU and the units ( standard and mechanical) are also on the trolley ix. Push trolley to respective room to returns the parts accordingly The new proposed flow is illustrated as shown in Figure 5.10 while the new changeover process with the proposed elimination of Wrap Up phase and the new NVA activities aligned towards the end of the changeover as External elements as shown in Figure 5.11. 129 Current Wrap Up Phase Proposed ‘Invert’ flow of Post Setup Change AEPT state from 'SDT-Conversion to 'PROD' Perform basic housekeeping Perform basic housekeeping Return change kits and toolsets Inform supervisor/operator of completion Inform supervisor/operator of completion Change 'sticky' tag to UP Change 'sticky' tags to 'UP' Rearrange changekit and tools into respective boxes and on trolley Change AEPT state from 'SDT-Conversion to 'PROD' Rearrange all items including TIU and units on trolley Figure 5.10: The new aligned Post Setup phase 130 Figure 5.11: The changeover process flow with wrap up phase elimination proposal 5.4 Optimizing Hardware Setups phase The next important proposal will fully focus on the Hardware Setup phase. This phase as mentioned earlier has the longest duration to complete and causes the bottleneck to the changeover process. Unlike other phases, the Hardware Part Setup activities are most directly related and significant to this changeover. Currently there are 12 hardware parts replaced during the changeover and it takes almost 160 minutes to complete a whole set of hardware setup. Table 5.6 illustrates the current hardware setup flow and the time taken to complete each of the part. The current non standardized and non optimized hardware setup delays the overall changeover process. Based on the problems identified earlier, the current hardware parts can be divided into 2 different categories as below; 131 i. Generic ‘fungible’ parts ii. Generic ‘non fungible’ parts In the following discussions, the counter measures proposed will target mainly on the items below; i. Identify the ‘fungible’ and non ‘fungible’ parts ii. Identify the non ‘fungible’ parts that are multi function iii. Identify the non ‘fungible’ parts that can be redesign Table 5.6: The current hardware setup phase 132 5.4.1 Proposal to Identify Fungible Parts In this part of the proposal, the plan is to identify the ‘fungible’ or generic component that is common for both the Nebula and Nexus configuration. By using SMED’s ‘Function Check’ and TRIZ’s ‘Universality’ technique, the current 12 hardware parts from both configuration can be compared to analyze the difference in physical and function. Generic ‘fungible’ hardware parts from both configurations will have the exact same physical appearance and form function. Then by using TRIZ’s ‘Taking Out’ technique, the identified fungible parts can be segregated from the other non fungible hardware. This will be quickest method to optimize the number of hardware parts needed to be setup. 5.4.2 Proposal to Identify Non Fungible Parts A non fungible hardware part from both configurations will have similar function but significant physical difference thus a challenge in optimizing the hardware setup further. For the non fungible hardware parts, the proposals will focus 2 main goals; i. Identify the non fungible hardware which is multifunction ii. Identify opportunity to redesign hardware parts 5.4.2.1 Non Fungible Parts With Multi Function Using SMED of ‘Function Standardization’ technique with TRIZ’s ‘Local Quality’ technique, the proposal is to identify the non fungible hardware part with different physical appearance but has the capability to perform dual function for both 133 configuration. Normally the hardware parts that fall under this category are those involve in low risk mechanical movements with no significant impact to quality and safety. 5.4.2.2 Non Fungible Parts with Hardware Redesign A hardware part will be considered for redesign if the current setup involves many complex steps or consist of NVA activities. In the problems highlighted the 2 hardware parts which above concern is the Contactor Chuck and the X-pitch blocks. The contactor chucks are discussed earlier is the main bottleneck of the hardware part setup involving 21 steps which included many NVA activities like cleaning, greasing, alignment and calibration which consume 120 minute for 4 chucks setup. The current contactor chuck setup is shown in Figure 5.12 below where the only difference between both configuration’s chuck is the ‘nest’ used which is unique to Nebula and Nexus width size. The function of the ‘nest’ is to clamp the DUT when testing is being performed. The current ‘nest’ design is as shown on Figure 5.13. Thus, using the TRIZ’s ‘Dynamization’ technique, the proposal will be to consider a redesign on the current rigid ‘nest’ to be more adaptive as inspired by a screw wrench or a flexible bed. The new design will allow the ‘nest’ to be flexible and adjustable based on the different width size. The intention of this whole design is to allow technician to perform a rapid setup without the need to perform all the complex activities with reduce duration. Also to consider is that the new design will fit into the current production environment with no safety and quality concern. 134 Figure 5.12: Current contactor chuck setup Figure 5.13: Current ‘nest’ design The X-pitch blocks is one of the 5 hardware parts which are fastener -based Today it takes almost 4 minute to complete a setup with each block requires up to 7 turns to either tighten or loosen. The current snapshot of the X-pitch block is shown in Figure 5.14 with it’s current screw design shown in Figure 5.15. The X-pitch block is located deep inside the handler, thus to remove and replace this part under a confine area is challenging and time consuming. The proposal is per SMED’s technique of ‘One Turn Screw’ method where new design will focus on established a more efficient and simple screw with 1 turn design. This together with other techniques will be explored to perform both simple and complex design changes to the current hardware setup if there is a need for improvement and with boundary conditions like safety, quality and cost. 135 Figure 5.14: X-pitch block 5.5 Figure 5.15: The current screw design Human Dynamic and Procurement Improvement Proposal The final proposal focus will dive into the improvements on the human dynamics and the process documentation. This though considered as basic requirements but are often neglected or overlooked. Though not part of the initial scope, this will be covered to ensure a full blown improvement implementation takes place to ensure sustainability. Table 5.7 shows the current technician ratio and status per shift. The table clearly shows though the technician ratio per shift meets goal but the competency is questionable. To ensure align and standardization, all technician both certified and non certified will need to go through the refresher training and those non certified will need to assess immediately. The training will include both theoretical and practical as technician will need to be familiar with both parts. A qualified senior staff or engineer will need evaluate each and every of the technician to ensure standardization in assessment and only the qualified are allowed to perform the 136 changeover. SMED puts high focus on human development and thus a comprehensive training and assessment will be the core for a better changeover sustainability. Table 5.7: Technician headcount per shift Shift A B C D Technician Non In Actual headcount Certified headcount goal Certified progress 6 6 2 3 1 6 6 3 1 2 6 7 4 2 1 6 8 4 3 1 All the above mentioned proposals once validated will need to be documented in either control specification or as training package. The standardized and organized document will ensure proper flow of information without any discrepancies. A checklist will be useful for technician to quickly refer during a changeover and ensure no steps are skipped or missed. Also, better business processes need to be enforce during the changeover request from supervisor to technician. An efficient business process will eliminate the ad hoc and unstructured request which is prone to miscommunications. 5.6 Summary This chapter has highlighted all the counter measures per SMED and TRIZ techniques in response to the problem identified earlier. The proposal focused on process improvement, hardware setup optimization and lastly on the human dynamics and procurements. The outcome of these proposals will be analyzed in the next chapter. CHAPTER 6 RESULTS AND DISCUSSIONS 6.1 Overview In this chapter, the outcome of the counter measures proposed earlier will be thoroughly analyzed and discussed. The results or outcome are purely based on empirical data analysis and engineering decision like Design of Experiments (DOEs), real time experience, structured brain storming session and cycle runs among others but not limited to. All the below information below are based on the 13 weeks (Dec’2010 to Feb’2011) data collection. This chapter will also include the Return of investment (ROI) analysis based on the implemented outcome. 6.2 Implementation of Pre Setup phase The whole initial intention of introducing this new Pre Setup phase was to enable the elimination of the Preliminary Soft Setup phase and to enhance further the Pre Changeover activities. In other words, the new Pre Setup phase streamlines activities from both phases by improving the upfront pre-setup activities which automatically converts the ‘Internal’ tasks to become ‘External’ tasks. Besides that, the introduction of this phase also helps to move the whole TIU replacement phase 138 from an ‘Internal’ stand alone phase to an ‘External’ activity performed in parallel with other Pre Setup activities. Table 6.1 shows the list of current, proposed and the actual implementation status for this Pre Setup phase. All the proposal were accepted and were able to be implemented successfully expect 1 proposal of acquiring 2 TIU board instead one the typical 1 board as a precautionary measure incase the TIU fail during the initialization session (during TP download). This proposal was rejected because as TIU are controlled and high value collateral items, the engineering team suggest to limit 1 TIU per transaction to avoid any misuse or damage to the part. Table 6.1: Pre setup improvement result No 1 Current Proposal Implementation Status All the changeover All these items will be Accepted- Is the parallel required items i.e. part of the upfront setup activity where while waiting Change kits, toolbox, activity requirement. the last lot to complete, the TIU, Mechanical Upon identifying the technician will go to get the Units and Standard equipment for necessary items. This Units are collected or changeover, the reduce the technician idle prepared during the technician will start to time during the early stage changeover duration prepare this items and help to convert the as ‘Internal’ tasks ‘Internal’ tasks to ‘External’ tasks 2 Technician needs to Introduce the practice of Accepted – The already walk multiple times using a trolley to place available 3-tier ergo trolley between the and move all the items in the shop floor can easily equipment to together. This improves place all the 5 major items respective rooms each the waste in motion and and can be moved easily time to collect the transportation. Also required items help to improve safety 139 of the technician and the items 3 Some technician Remove this activity as Accepted- There is no practice placing it is a NVA waste safety concern by removing barricades before start activity this task, changeover of changeover and activity is allowed to be this is practice as an performed without the need ‘Internal’ task during to barricade the work area the Preliminary Soft Setup phase 4 Changing ‘sticky’ tags These are NVA but Accepted- The temperature and performing required activities, setup will now be part of temperature setup proposed to change this the end lot process activity (warmup/cooldown) activity ownership to while changing the ‘sticky’ are part of the operator before the tag (from ‘UP’ to ‘DOWN’) technician’s role equipment is handover will be part of pre during Preliminary to the technician. changeover housekeeping Soft Setup phase activity done by operator. which is practiced as Though this activities ‘Internal’ activities prolong the operator’s activity but it reduce the overall ‘Internal’ time 5 Before performing the To minimize the pre- Accepted- When operator is validation run, validation physical busy performing the final technician will need setup during each housekeeping activities, perform pre- validation run, propose technician can perform this validation physical to ensure enough empty clear/load in empty trays setup that include trays are pre-loaded into into buffer stocker. This clear old trays from the buffer stocker will help to minimize reject stocker and load before hand ‘Internal’ time during trays to buffer stocker Standard Unit and Dry 140 Cycling phase 6 7 TIU replacement is TIU replacement Accepted- During the ‘end performed as an activities are lot’ process once operator ‘Internal’ phase once independent activities has clicked ‘End Summary’, all the hardware parts thus propose to perform the technician in parallel have been replaced is during the Pre-Setup will start the TIU activity replacement activities Technician collect 1 To minimize walking Rejected – TIU boards are TIU board each time time and delaying the High Value and controlled during a changeover overall process, suggest collaterals thus to avoid any and if any failure with technician to collect 2 misuse and potential TIU board need to TIU boards instead of 1 damage, only 1 TIU walk back to TIU during the Pre Setup transaction is allowed per room for replacement preparation time. Furthermore, placing 2 TIUs on the trolley are not encouraged 8 The Pre Changeover Eliminate these phases Accepted – New phase and Preliminary Soft and streamline all the called the Pre Setup will be Setup phase are 2 non activities into 1 single introduce where all the standardized activities phase activities from the current 2 practiced today phases will be performed as ‘External’ task and subsequently eliminate both phases Table 6.2 shows the new ‘end lot’ process and its activity sequence that operator will need to comply before the equipment is handover to the technician for changeover. The new flow included an extra step where operator will perform the equipment temperature cool down (or warm up) before starting ‘end summary’ action. The equipment temperature will cool down (warm up) by itself while operator will continue to perform the units segregation thus the temperature setup is a parallel activity. 141 Table 6.2: The new ‘End Lot’ process sequence No. 1 New ‘End lot’ Process Move out lot from the Move out lot from the handler to handler to the table the table Counting and visual 2 verification 3 4 Current ‘End Lot’ Process Counting and visual verification End lot process in system End lot process in system Physical segregation of good Equipment temperature setup and bad units (cool down/ warm up) 5 Good unit shipment process 6 Bad units reject process Tracking sheet 7 documentation Physical segregation of good and bad units Good unit shipment process Bad units reject process Send good units to next 8 station and reject to RIMS Tracking sheet documentation room 9 Nil Send good units to next station and reject to RIMS room Figure 6.1 shows the new Pre Setup activity flow which combines all activities from 3 different phases namely; Pre Changeover, Preliminary Soft Setup and TIU replacement phase into one single standardized phase. In this new phase, parallel activity execution occurs at least 3 times especially during: i. Operator prepare to complete lot while supervisor ensures no lot’s queue in the system awaiting to be processed by the identified equipment and in parallel technician is already preparing the changeover kits and required items ii. When operator is busy performing end lot process, the equipment temperature is being automatically setup (cool down/warm up) and the technician will proceed to replace the TIU 142 iii. When Operator is busy performing housekeeping , the technician will clear all old trays inside the handler and replace with new trays in the buffer stocker 1. Supervisor forecast and decide on the changeover need 3. Supervisor and technician identify the equipment to be changeover 5.The operator ensure the last lot complete processing succesfully 2.Supervisor identifies the available technician from the team and passdown on requirement/expectation 4a.Supervisor ensure no lots are queued to be processed by the identied equipment 4b. Technician start to i.e changekits, TIU, tools, mechanical and std units 6a. The operator perform all neccesary end lot process include temperature setup (cool down/ warm up) 6b. Once end summary complete, technician will proceed with the TIU replacement phase 7a. The operator performs basic housekeeping include change 'sticky' tag 7b. Technician will clear the old trays and replace with new trays inside the handler 8. The operator log off his/her ID and handover the equipment to technician 9. Technician log in the ID and AEPT change from 'PROD' to 'SDT- Conversion' Figure 6.1: The new pre setup activity flow Figure 6.2 shows the development of the Pre Setup phase and the scheduling of parallel activities. Figure 6.3 shows a more clear breakdown and time study of the newly implemented Pre Setup phase. 143 Figure 6.2: Illustration of the pre setup phase development 144 •Supervisor finds and identify the technician •Communicate on changeover request and expectation •Supervisor and Technican decide and identify of the equipment for changeover •Supervisor communicates with operator to complete the last lot • Ensure no new lots or WIP in queue to be process for the identified equipment •Technician proceed to prepare the requires kits, tool, and units for later changeover and place near equipment area •Operator performs end lot process including temperature setup ( external step) • Technican will proceed with TIU replacement activity •Operator performs basic house keeping activities including changing 'sticky' tag • Technician will clear old trays and replace new trays in buffer stocker •Operator log off ID as user and passover the equipment to technican •Total EXTERNAL time spent in the new Pre-Setup phase 7 minutes 5 minutes 7 minutes 10.5 minutes 3 minutes 32.5 minutes Figure 6.3: Actual time study of the new pre setup phase Figure 6.4 illustrates the actual change in the changeover process flow with the introduction of the new Pre Setup phase and the elimination of the Preliminary Soft Setup and the TIU replacement phase. 145 Figure 6.4: Illustration of changeover process change with pre setup phase In summary, the introduction of this Pre Setup phase has been an advantage to the overall changeover process by not only reducing the duration but also helped to streamline the initial 3 phases into one single phase. The new phase is lean as all the activities are performed as ‘External’ task while those NVA waste activities are eliminated. 146 6.3 Improvement of the TP Download phase There is no much significant improvement on duration reduction of the TP Download phase and all activities 5 major activities will remain as current ‘Internal’ element. The major proposal on system and network upgrade was rejected by the management due to budget and resource constraint but these improvements are on the long strategic plan for year 2012. Nevertheless, with the ‘trimming’ of the TIU change phase and moving it to be part of the Pre Setup phase, the TP Download stage will now move up the sequence to be first changeover process. The unique characteristic of this TP download phase is that though all 5 major activities need to be performed as ‘Internally’ but almost ¾ of the activities duration are background process or autorun in the background. This characteristic identified as an opportunity earlier will be used to perform Hardware Setups which will be illustrated in detail later. Table 6.3 shows the current practice, proposal and the implementation status for this phase. Table 6.3: The TP download improvement result No 1 Current Proposal Today TP download Implementation Status TP download phase is Accepted- Is the most only dependent on the logical solution that once TP activity of the TIU replacement phase logs in the ID as user, will changeover after the thus proposal is to move start off by performing the completion of Dry this phase to be the new TP download activity. Cycling phase. 1st activity of the Technician will use all the Technician idle changeover process. info provided by the is practiced as the 6 th 147 almost 10 minutes supervisor before choosing during this phase the correct ‘recipe’ and downloading the TP 2 During the 2nd half of Since the actual Accepted – In average the the TP download download and TIU TP download and TIU phase which is during initialization are initialization takes around the actual TP background process, 11 minutes to complete, thus download and TIU suggestion is for to minimize idle time, the initialization step, the technician to start technician can start to technician idles performing hardware perform hardware part setup during this period as part setup without interrupting the most activity as download/initialization system setup or process machine time 3 The actual TP Faster and quicker TP Rejected – This change download takes in download is possible if consume cost and resources average 7 min to the current network beyond the budget. But the complete from server cable of 100MB can be network cable upgrade will database to the CTSC switch and replaced be performed during the with the 1G whole factory migration in Q4’11 Figure 6.5 shows the activity breakdown of the current TP download phase with the latest completion duration. With the TP download phase moved to be the 1st changeover activity, the process flow of the changeover changed significantly and is illustrated in Figure 6.6. 148 Figure 6.5: TP download activity breakdown Figure 6.6: Illustration of changeover process change with TP download phase improvement 149 6.4 Improving of Hardware Setup phase The next important improvement proposal to analyze is the optimization of the hardware part setup. The success of this improvement implementation will determine the overall success of reduction the changeover duration. Today, in total 12 hardware parts are replaced and setup during a changeover with duration of 160 minutes. The outcome of the Hardware Setup improvement can categorized into 3 categories as below: 6.4.1 i. Identifying the ‘fungible’ hardware parts ii. Identifying the ‘non fungible’ hardware parts iii. Redesigned or modified hardware parts Identified ‘fungible’ parts Based on the experimentation and observation, there are 4 components per today’s hardware parts which are naturally fungible or common to both configuration. These hardware parts are similar in both physical appearance and in functionality thus they are not required to be replaced. The 4 hardware components identified are; i. Loader/Unloader Pickup Head ii. Loader/Unloader Y-pitch Conversion Blocks iii. Loader/Unloader Buffer/Exit pick up heads iv. Stopper for Input/Exit assembly 150 Besides these 4 components, another hardware part that is not naturally ‘fungible’ but is able to perform dual function is the Transfer Pick Up Assembly component which was identified through the TRIZ’s ‘Local Quality’ technique. This hardware part is used to pick up the empty trays from buffer stocker to the exit stocker. An illustration of the Nebula and Nexus Transfer Pick Up Assembly component is shown in Figure 6.7 below. The most significant physical difference between both configurations is the number of suction cups placed on this component where Nebula will have 2 cups and Nexus with 1 cup. The suction cups count corresponds directly to the empty pocket in the respective configuration trays as shown in Figure 6.8 below. Nebula Nexus Figure 6.7: The transfer pick up assembly Figure 6.8: The Nebula and Nexus tray difference 151 The DOE performed with 3000 units for 20 cycles showed that the Transfer Pick Up Assembly designed for Nexus is able to function for both configuration as the single suction cup is able to lift trays from both configuration without any major concern and the risk assessed is low as the hardware functions only to transfer empty trays without units. With this new implementation, the technician can salvage 13 minutes and exclude the complex step to setup this part. Table 6.4 summarizes the list of identified ‘fungible’ parts that can be excluded from the hardware setup list. Table 6.4: The identified ‘fungible’ hardware parts No. Hardware Name Hardware Snapshot Function Status LD: To pick the units from input tray to heat plate 1 LD and UD pickup head Generically fungible thus ULD: To pick not required units from exit to be changed plate to move to unloader tray Qty: 4 pcs/set To ensure units 2 LD and UD are pick up in Generically Y-pitch correct position fungible thus conversions in Y-axis not required blocks Qty: 4 pcs/set to be changed of 8 screws 3 LD and UD To pick up and Generically 152 buffer/exit transfer unit fungible thus pick up from heat place not required head pocket to be changed exchanger to buffer stage and from buffer to exit plate Qty: 4 pcs/set To ensure the assembly Stopper for 4 Input/exit assembly mechanism Generically buffer and exit fungible thus to be in correct not required location and to be changed avoid pick up issues Qty: 2 pcs/set Generically Transfer 5 Pick Up Assembly To pick up non fungible empty trays but propose from buffer to use the stoker to Nexus design input/output as standard stoker part for both configuration Qty: 1 pc/set and need not to be replaced 153 6.4.2 Identified ‘non fungible’ parts All the remaining hardware that does not fit into the above 2 category will be listed as non ‘fungible’ as these parts though similar in function but significant physical difference that requires it to be replaced each time. Table 6.5 shows a summarized non ‘fungible’ list of the remaining hardware parts. Table 6.5: The identified non ’fungible’ hardware parts No. Hardware Name LD and ULD 1 X-pitch conversion Hardware Snapshot Function To ensure units pick up units in correct X-axis Qty: 2 pcs/set To place the DUT and also to 2 Heat Plate heat/soak units which improve the cycle time Qty: 1pc/set To place units from 3 LD and UD heat plate and front/rear transfer them into buffer stage chamber ( test head) Qty: 4 pcs/set 154 To pick up units at 4 Contactor Chucks buffer stage loader and test the units at TIU for functional test Qty: 4 pcs/set Only used for cold test to remove 5 Unsoak plate moisture from the units before moving out Qty: 1 pc/set To place the tested units from Buffer stage 6 7 Exit Plate Qty: 1 pcs/set Socket Plate that place the Cleaning SCD surrogate 155 Plate cleanin device coupon . SCD coupon to clean TIU pogo pin. Every 5000units run, need to perform cleaning. Different due to coupon size Qty: 1 pc/set 6.4.3 Redesigning Hardware Parts From the proposals highlighted earlier, the 2 hardware parts that was considered for redesign or modification is the Contactor Chuck and the X-Pitch Conversion blocks. The details of the hardware redesign are explained as below; 6.4.3.1 Nest redesign The current contactor chuck setup involves 21 steps and takes 120 minutes to complete. As highlighted earlier, the only difference between Nebula and Nexus contactor chuck is the ‘nest’ which again differs only by the width size. Thus, out of 21 steps performed, the only value added step in this setup is the replacement of the ‘nest’ on the chucks but when each time a nest is replaced, other NVA activities like cleaning, greasing and calibration is needed to be performed as well which delays the overall process. Besides this, the fixing and replacement of the chucks and the nest involve many small and delicate parts which is hard to be handled in addition to many screws and fasteners as well. 156 To counter this, the new proposal was to use engineering solution to design a new nest which will have the ability to adjust it’s width size depending on the configuration. Also, the new design nest will not require technician to dismantle the whole chuck as currently practice which will help reduce overall setup of the time. Using TRIZ’s ‘Dynamization’ technique, a new nest was designed and is as shown in Figure 6.9 below where new ‘adjuster clips or clampers’ are introduced to allow the width size adjustment. The new design model is adjustable and flexible to support both configuration with technician needs only to move the clips either inwards (Nexus) or outwards (Nebula) by adjusting the screw position. Table 6.6 shows the steps involve in changing the ‘nest’ size using a standard hex key. The clips are fabricated only to move in this 2 pre-defined positions with each screw can only be loosen/tighten in 3 turns. Figure 6.10 shows a side to side comparison between the old and new nest while Figure 6.11 shows a comparison of the chucks. The new ‘nest’ design was put under exhaustive and extreme testing for 20 cycles of 3000 unit to fully validate its reliability and durability. Since the core design and material use to build the hardware are similar, thus no concern from safety, quality and reliability. With this new ‘nest’ design, the whole 21 steps involving multiple complex and NVA activities can be truncated to a generic 6 quick steps as illustrated in Table 6.7. This new design demonstrated the advantage of using the TRIZ technique in identifying specific solutions from general problem. 157 Figure 6.9: The new ‘nest’ design Figure 6.10: Old versus new ‘nest’ design comparison 158 Figure 6.11: New chuck (L) and old chuck (R ) comparison Table 6.6: The steps in changing the ‘nest’ size Step 1 Illustration Description The Nebula contactor with default ‘nest’ size setting ( the clampers are ‘outward) 159 Use the standard hex key to ‘loosen’ the screws 2 3 Once loosen, use fingers to push the clips inwards 4 Tighten the screws back into position using the hex keys The Nexus contactor chuck 5 and ‘nest’ ready to be used 160 Table 6.7: The actual changeover steps with the new ‘nest’ design Step 1 Illustration Description Technician picks the hex key 161 2 Technician adjust the contactor chuck’s position from bottom opening of the handler 3 Technician loosen the screws for each of the individual nest from bottom opening of the handler 4 Manually push the clips to either inwards or outwards 162 5 Technician tighten the screw back into position 6 Technician completes task and return the contactor chucks to position 6.4.3.2 One turn screw design The next proposal will focus on performing a simple design change on the X pitch converter part which is a non ‘fungible’ part that need to be replaced. It takes currently 4 minutes to remove and replace a pair of this part during a changeover. The long duration is mainly caused by the motion of tightening and loosening of the screw that need to be performed using both the fingers and the screw driver. In average, a technician needs to turn 7 complete cycles to either loosen or tighten a screw for to remove or replace this part. Figure 6.12 shows an example of the current X-pitch component together with its screw thread. In SMED, Shingo suggest to minimize the need for adjusts and the use of fasteners altogether. 163 Thus, the new proposal is to redesign the screw-type used for this part using the Shingo’s model of 1 turn screw. A low cost design of a 1 turn screw was fabricated for the X pitch conversion as shown in Figure 6.13 where with this new design it is forecasted the hardware replacement time can be reduced to half at it takes only 1 turn for each of the screw to tighten or loosen without the need for any tools i.e. screwdrivers. Table 6.8 shows an illustration of removing and replacing a X-pitch conversion using this 1-turn screw proposal. Figure 6.12: The current X-pitch conversion block and screw design Figure 6.13: The new X-pitch conversion block with the new screw’s thread 164 Table 6.8: The functionality of the one turn screw Step Illustration Description Current X-pitch 1 conversion in place in the handler Technician use 2 2 fingers to loosen the 1 turn screw The 1 turn screw has loosen, remove the X 3 pitch conversion and replace a new one with the same method With the above implementations, Table 6.9 summarizes the Hardware Part setup’s current, proposal and implementation status. Table 6.10 summarizes the average time study of the new optimized hardware part setup. The new result shows the hardware part setup now can be completed below 11 minutes compared to the 160 minutes previously. Figure 6.14 illustrates the parallel execution of the hardware setup when the TP download and TIU initialization is in progress. Figure 165 6.15 shows the actual changeover process flow and duration with the new optimized hardware part setup changes. Table 6.9: The result of hardware setup proposals No 1 Current Proposal Technician changes 4 of the hardware are all the12 hardware identified to be generic parts/components in design thus are during a changeover applicable for both Implementation Status Accepted –The 4 parts; Pickup Head handler configuration and does not need to be Loader/Unloader Loader/Unloader Y pitch conversions replaced Loader/Unloader Buffer/Exit plate pick up heads Stopper for Input/Exit assembly Have been validated to be generic for both Nebula and Nexus thus does not need to be replaced 2 Technician changes The ‘Transfer Pick Up Accepted – DOE performed the Transfer Pick Up Assembly’ part with 30x cycle run showed Assembly component designed for Nexus the Nexus ‘Transfer Pick Up as part of the could actually serve Assembly’ used in Nebula hardware replacement purpose for both configuration able to activity configuration thus transfer empty trays without remain this as the any issue especially standard part that does dropping of trays or not need to be replaced intermittent pick up issues. Thus this will now be part of 166 the fungible hardware part that does not need to be replaced 3 The longest duration The new ‘nest’ design Accepted – DOE performed activity is the will allow technician to with 30x cycle run showed replacement of the do quick adjustment the new ‘nest’ design able to contactor chucks without the need to perform equivalent to the which also involve remove the whole current design without any many NVA task like chuck and perform the safety, quality or reliability cleaning, wiping, whole NVA activities issues. Also, the technicians greasing and are more pleased with this alignment calibration new design as it saves time and resources 4 The X-pitch block Use new design of 1- Accepted- New 1-turn screw used today use screw turn screw to minimize design able to perform methodology where the effort to similar to current design but technician need to loosen/tighten the part able to reduce the time taken turn at least 7x to to loosen/tighten the part loosen/tighten the part 5 Hardware part setup Propose to perform Accepted- With the new is performed as the Hardware setup as a optimized hardware 2nd activity in the parallel activity during changeover plan and since changeover flow once the TP download phase this phase is independent of the preliminary soft as both activities are the TP download, then it can setup and equipment independent of each be executed in parallel temperature setting is other without any impact to the done changeover 167 Table 6.10: The time study result of new improved hardware setup No Pre- Hardware Part / Snapshot Post- Improvement/ Improvement/ Time(Min) Time(Min) LD/ULD pick up head 1 Fungible thus not Replaced replaced 4.0 minutes/set LD and UD Y-pitch conversions blocks 2 Fungible thus not Replaced replaced 4.0 minutes/set LD / ULD X-Pitch Blocks Replaced 1.0 minutes/set 3 but reduced Replaced duration due 4.0 minutes/set to 1-turn screw 4 Replaced Heat Plate Replaced 168 0.5 minutes/set 0.5 minutes/set LD and UD buffer/exit pick up head 5 Fungible thus not Replaced replaced 8.0 minutes/set LD and UD front/rear buffer stage 6 Replaced Replaced 4.0 minutes/set 4.0 minutes/set Stopper for Input/Exit Assembly 7 Replaced Fungible thus not 2.0 minutes/set replaced 169 8 Replaced Contactor Chucks 120.0 minutes/set Fungible but need manual adjustment 4 minutes/set Exit Plate 9 Replaced Replaced 0.5 minutes/set 0.5 minutes/set Unsoak Plate 10 Replaced Replaced 0.5 minutes/set 0.5 minutes/set Fungible if use 11 Replaced 13.0 minutes/set Transfer Pick Up Assembly the Nexus’s design head 170 Soak Cleaning Plate 12 Replaced Replaced 0.5 minutes/set 0.5 minutes/set 160 TOTAL TIME (minutes) 11 Figure 6.14: Illustration of the hardware setup executed as parallel activity 171 Figure 6.15: Illustration of changeover process change with the optimized hardware setups 6.5 Improvement of PnP ‘Teaching’ Phase This as earlier mentioned is a required step to adhere whenever hardware especially when pick up heads or contactor chucks are replaced where the ‘Teaching’ process will calibrate the hardware settings to perform at optimum condition during actual production runs. Though not many significant improvements were proposed in this phase, but with the new improved changes to other phases, it will indirectly impact this process phase from its current state. As both Dry Cycling phase and Standard Unit validation are dependent on the completion of PnP ‘Teaching’, thus there will be no sequence change from the current flow. As earlier identified, the 2 opportunity in the PnP 172 phase to be analyzed are the reduction in setup time and also the opportunity to perform parallel activity during the actual PnP machine process time. Table 6.11 shows the current, proposal and the implementation status in the PnP ‘Teaching’ phase. Figure 6.16 shows the actual time study of the new PnP Teaching phase with improved duration compared to the current practice. Figure 6.17 shows the breakdown of the PnP activity and its respective duration. The figure also shows the implementation Pre VI activity from Dry Cycling phase as a parallel activity during the actual Teaching process. Figure 6.18 shows the latest change in the changeover flow with the improvement in the PnP Teaching phase. Table 6.11: The improvement result of PnP teaching phase No 1 Current Proposal Proposal Status Before the start of the As part of the early pre Accepted – This proposal activity, the setup activity, the has been implemented as technician need to technician has clear old part of the new Pre Setup clear the trays from trays and ensure buffer phase activity which is the input and reject stoker is filled with new performed in parallel during stoker and ensure trays operator’s housekeeping correct trays are activity. With this new placed inside the practice, the Pre Validation buffer stoker physical setup duration will be reduced 2 Only 4 Standard Units Suggest Technician to Accepted with condition- are used for the PnP collect >1 tray units Technician will acquire 2 ‘Teaching’ phase and from EIMS so that the full trays instead of 1 tray the setup is slightly extra units can be since partial trays or units delayed because directly used during the are not allowed in the EIMS technician need to PnP ‘Teaching’, the process but since Standard 173 transfer the 4 units Technician does not Unit are controlled items from the current full need to perform thus acquiring 2 trays are tray to another empty multiple transfer based on availability The system needs to If Temperature Setup Accepted – PnP Teaching stabilize the step in the TIU phase does not require temperature before replacement phase can temperature thus the actual PnP been move to be part of eliminating the temperature Teaching can begin the Standard Unit setup will help to minimize Validation activity, thus lost time during the actual no temperature setting process trays before transferring the units to the handler’s PnP 3 or stabilization occur during PnP Teaching phase 4 Technician idle Propose for technician Accepted – To minimize during the actual PnP to start performing the Technician idle time and Teaching process pre validation visual Internal time during Dry awaiting it to inspection of the 5 tray Cycling phase, this proposal complete mechanical units during will be accepted. The pre- this period validation visual inspection will be performed during this idle period. Also, the proposal to use the 3x magnifier to perform inspection is also approved to ease the visual inspection 5 Technician perform Find quicker way or Rejected – Since there are PnP ‘Teaching’ as eliminate the need to still hardware parts replaced part of the perform PnP Teaching and also the ‘nest’ manually requirement each time as they new optimized adjusted, it is still necessary 174 Hardware parts are hardware part setup to perform the PnP replaced minimizes the required Teaching. And no number of parts to be engineering data to proof replaced, potentially the risk is low low risk • Pre Physical setups and validation • Pre system setup and configuration • Actual Teaching Process • Pre Validation VI of Mechanical Units • Post system setup and configuration • Post physical setup and validation • Total 'Internal' time spent for the new improvized PnP Teaching Phase 0.75 minutes 0.75 minutes 2.2 minutes 0.5 minutes 0.75 minute 4.95 minutes Figure 6.16: Actual time study of the improved PnP teaching phase 175 Figure 6.17: Illustration of the PnP teaching phase activity breakdown Figure 6.18: Illustration of the changeover process flow change with the improved PnP teaching phase 176 6.6 Improvement on the Mechanical Unit Validation Phase This is the first validation phase on ensuring a correct and successful changeover before the equipment is handover to the production. Today technician needs about 20 minutes to complete this dry cycling phase and it’s been highlighted that this is a NVA activity but required per process today. The proposal to eliminate and streamline this phase has been rejected as there the data collected for changeover the last one quarter is still insufficient to show that validation process can be eliminated. This proposal will be put on hold for now and pursued when enough empirical data is available to assess the risk. Nevertheless, the proposal to reduce the mechanical unit sample in this phase has been agreed and the new process is to perform with 1 full tray of mechanical units instead of 5 full trays. This has significantly help to reduce the overall duration of the dry cycling phase. On the other hand, to minimize the technician idling time, the Standard Unit pre validation post inspection will be performed in parallel the actual dry cycling process is in progress. The introduction of the 3x magnifier to technician to perform visual inspection has helped to improve efficiency and speed up the process as well. All the other improvements proposed earlier were accepted and successfully implemented and this is summarized in Table 6.12 below. Figure 6.19 shows the new optimized flow for this Dry Cycling phase per the improvement implementation. Figure 6.20 illustrates the buildup of new optimized Dry Cycling phase while Figure 6.21 shows the actual time study collected based on these improvements. Figure 6.22 illustrates the changeover process flow and duration change with the optimized Dry Cycling phase. 177 Table 6.12: The result of dry cycling phase proposals No 1 Current Proposal Proposal Status Before the start of The 5 trays of units are Accepted – As the proposal Dry Cycling phase, collected earlier allow the task to be Technician will walk together with the tool converted from ‘Internal’ to back to the tool shop sets during the Pre ‘External’ and save the to collect 5 trays of Setup phase duration of 2.5 minutes Incase of any pre Suggest technician to Accepted – Mechanical visual validation fail, collect >5 trays of units units are not controlled or Technician will need ( or atleast an extra 1 limited collaterals, thus go back to tool shop tray of units) as buffer Technician are allowed to to get replacement inhand that technician collect 6 trays of units per units can replace immediately transaction during the Pre mechanical units 2 Setup phase 3 Technician will need Eliminate the need for Rejected – No changes to perform pre technician to perform allowed to the current validation visual pre validation visual business process and tool inspection before the inspection by requesting shop admin R&Rs. start of the Dry the tool shop’s admin to Cycling phase inspect, check and store only good mechanical units for use Eliminate the need to Rejected - The Pre VI are perform pre-validation required to ensure only VI steps as this is NVA defect free units are tested during the dry cycling Move the ‘Internal’ Accepted- This task can be practiced Pre VI during practiced as an ‘External’ the Dry Cycle phase to activity when it is an ‘External’ task performed in parallel during 178 the actual PnP Teaching process 4 Technician perform Suggest to use the Accepted – The use of the the both pre and post readily available 3x 3x magnifier to perform VI using bare or diopter or magnifier visual inspection are much ‘naked’ eye placed at each work quicker and efficient. Able inspection desk to reduce the inspection duration and improve the reject identification 5 Technician need to This activity can be Accepted – This has been clear all the trays performed part of the agreed to be part of the Pre from input/exit Pre Setup activity Setup steps and reduce the stocker and place new pre validation physical trays into the buffer setup stocker 6 Before Dry Cycling Temperature is not Accepted- Dry Cycling process can needed for Dry Cycling process does not need commence, the thus temperature setting temperature and with this equipment can be eliminated. activity eliminated, able to temperature need to Move the temperature save the Internal time spent stabilize setting in TIU during temperature replacement phase to stabilization Standard Unit Validation 8 Technician idle Opportunity for Accepted- Opportunity to during the actual Dry Technician to perform reduce the ‘Internal’ during Cycling process parallel activity during the Standard Unit validation this period and phase recommended to perform the Pre VI for the 1 tray of Standard Units 179 9 10 Technician will Suggest to perform the Rejected – Standard Unit perform Post VI and Post VI during the validation can only ensure all units are Standard Unit validation commence upon 100% defect free period which can save confirmation that all units before officially ‘Internal’ tine are 100% defect free with ending the Dry Cycle all mechanical units Phase working in order Upon completion of Keep the units aside on Accepted – Eliminate the the dry cycling phase, the trolley and return ‘Internal’ task and waste in Technician will together towards the end motion arrange units into tray of the changeover and return them back to the tool shop 11 Current changeover Eliminate the need for Rejected - Dry Cycling is process requires the Dry Cycling validation needed as the ‘gate’ process validation data from as this is a NVA but to identify any abnormality Dry Cycling with required task with the changeover setup 100% defect free Streamline the Dry Rejected – Mechanical units from 5 trays. Cycling phase function damage to Standard Units And this validation with the Standard Unit are too risky and costly. process delays the validation phase so can Also both phase have overall changeover eliminate the Dry significant different Cycling phase function Minimize the no. of Accepted with condition – units or trays used for Dry Cycling phase reduced the Dry Cycle phase from 5 full trays to 1 full from current 5 trays to 1 tray with condition if any tray failure found first time, once issue fix, the revalidation will need to be performed with 5 full trays 180 Perform prevalidation system setup Perform prevalidation physical setup Perform postvalidation system setup Actual Dry Cycling Process Perform postvalidation physical setup Perform postvalidation visual inspection Figure 6.19: The improved dry cycling activity flow Figure 6.20: Illustration of the improved dry cycling phase buildup 181 •Pre dry cycling system setups •Pre dry cycling physical setups •Actual dry cycling process •Post dry cycling physical setups •Post dry cycling system setup •Post dry cycling visual validation •Total 'Internal' time spent in the new improvised Dry Cycling Phase 1.0 minutes 0.2 minutes 1.5 minutes 0.15 minutes 1.0 minute 0.5 minutes 4.35 minutes Figure 6.21: Actual time study of the improvised dry cycling phase 182 Figure 6.22: Illustration of changeover process change with the improved dry cycling phase 6.7 Improvement of the Standard Unit Validation This is the last phase of the validation before the equipment can be officially handover back to the production. This phase is also considered critical as the outcome of the standard unit run determines the full completion of the changeover. As highlighted earlier, the proposal to eliminate or streamline the validation phases were rejected due to insufficient data support. Also, as Standard Unit validation uses only 1 full tray, no further sampling reduction is allowed. Nevertheless, some of the earlier implemented upfront setup and parallel activities has contributed in reducing the overall duration of this validation phase. The summarized outcome of this phase is listed in Table 6.13 below; 183 Table 6.13: The result outcome of standard unit validation No 1 2 Current Proposal Proposal Status Standard units are Standard Units are Accepted – This has been collected before the prepared upfront before part of the Pre Setup PnP Teaching phase the changeover starts activity to convert the begins during the Pre Setup Internal time to External phase task In case of any pre Suggest Technician to Accepted with condition- visual validation fail, collect >1 tray units Technician will acquire 2 Technician will need from EIMS so that if full trays instead of 1 tray go back to EIMS there is any Pre VI since partial trays or units room to get failed units, they can be are not allowed in the EIMS replacement units directly swapped and process but since Standard used for the Standard Unit are controlled items Unit run thus acquiring 2 trays are based on availability 3 Technician will need Eliminate the need for Rejected – No changes to perform pre technician to perform allowed to the current validation visual pre validation visual business process and EIMS inspection before the inspection by requesting admin R&Rs. start of the Standard the EIMS’s admin to Unit phase inspect, check and store only Standard units for use Eliminate the need to Rejected - The Pre VI are perform pre-validation required to ensure only VI steps as this is NVA defect free units are tested during the Standard Unit Move the ‘Internal’ Accepted- As this Pre VI practiced Pre VI during validation is only for 1 tray, 184 the Standard Unit phase thus will be done in parallel to an ‘External’ task during the actual Dry Cycling phase 4 Technician perform Suggest to use the Accepted – The use of the the both pre and post readily available 3x 3x magnifier to perform VI using bare or diopter or magnifier visual inspection are much ‘naked’ eye placed at each work quicker and efficient. Able inspection desk to reduce the inspection duration and improve the reject identification 5 Technician need to This activity can be Accepted – This has been clear all the trays performed part of the agreed to be part of the Pre from input/exit Pre Setup activity Setup steps and reduce the stocker and place new pre validation physical trays into the buffer setup stocker 6 Temperature setting is Move this activity to be Accepted- Correct performed part of the part of Standard Unit temperature (115’C) is TIU replacement run validation needed during the Standard activities Unit run but not needed for PnP Teaching and Dry Cycling phase. Temperature setup in Standard Unit run can be performed as a parallel activity when they pre physical setup is performed 10 Upon completion of Keep the units aside on Accepted – Eliminate the the dry cycling phase, the trolley and return ‘Internal’ task and waste in Technician will together towards the motion arrange units into tray end of the changeover and return them back 185 to the EIMS room 11 AEPT state change is AEPT state changed is Accepted – As long all the from ‘SDT- performed once units passed with no rejects Conversion’ to Standard unit validation and the supervisor agrees. ‘PROD’ is performed complete as part of the All other NVA like towards the end of the post system setup housekeeping can be Wrap Up activity performed upon completion phase 12 Current changeover Eliminate the need for process requires the Standard Unit validation validation is needed as the validation data from as this is a NVA but ‘gate’ process to identify Standard Unit with required task any abnormality with the 100% pass of all the Rejected - Standard Unit changeover setup units tested And this Streamline the Dry Rejected – Mechanical validation process Cycling phase function damage to Standard Units delays the overall with the Standard Unit are too risky and costly. changeover validation phase so can Also both phase have eliminate the Dry significant different Cycling phase function Use a different TP for Rejected – to avoid many Standard Unit validation noise or variables in the which is shorter in shop floor and also to download time and standardize the TP use. quicker to execute during the actual validation process . Figure 6.23 shows the new activity flow for the Standard Unit Validation phase while Figure 6. 24 show the actual time study taken to complete this validation phase based on the new improvements while Figure 6.25 shows changeover flow and duration change with the new optimized Standard Unit validation phase. 186 Perform prevalidation system setups including Temperature Setup Perform prevalidation physical setups Actual validation and testing process Perform postvalidation system setups Perform postvalidation physical setups Figure 6.23: Activity flow of the improvised standard unit validation phase •Pre-Validation System setup •Machine init and Temperature setting •Pre-Validation Physical Setup •Actual Validation Processing •Post-Validation System setup •Post-Validation Physical setup •Total Internal time spent in the improved Standard Unit run 3.0 minute 1.0 minutes 3.2 minutes 0.95 minutes 1.0 minutes 9.1 minutes Figure 6.24: Actual time study of the improvised validation phase 187 Figure 6.25: Illustration of changeover process change with new improvised standard unit validation phase 6.8 Elimination of Wrap Up phase The last phase of the current changeover process is the elimination of Wrap Up activities phase which consists mostly NVA activities to the actual changeover. As indicated in the proposal phase, the major change to occur at this phase is the reverse flow of the activities where technician will log off the AEPT state change upon completion the Standard Unit validations and thus officially complete the changeover process. All the other NVA activities removed from previous stages will be accumulated with the other Wrap Up phase activities and performed together as 188 External elements. The new phase will be known as Post Changeover activities with no impact to the changeover duration. Table 6.14 summarizes the new changes to the changeover process by the elimination of the Wrap Up phase. Figure 6.26 shows the new Post Changeover activities ‘mirrored’ from the Wrap Up Activity phase while Figure 6.27 shows the changeover process flow with the elimination of Wrap Up activity phase. Table 6.14: The result outcome of the wrap up phase elimination No 1 Current Proposal Proposal Status The AEPT state Technician to perform Accepted – AEPT state change is performed AEPT state change as change will be move to be st towards the end of the the 1 activity of the part of the Standard Unit Wrap Up Activity phase validation phase and performed part of the Post System Setup activity 2 The Wrap Up phase Eliminate this phase and Accepted – Changeover of the changeover perform all this official end process will be consist activities like activities together with the Standard Unit validation housekeeping, the returning of the and once it complete, the cleaning, arranging parts once AEPT state equipment will be ready to and post has change. be handover back to communication production. All the other NVA activities will be performed in this new phase called the Post Changeover phase 189 Change AEPT state from 'SDT-Conv' to 'PROD' Perform basic housekeeping Inform supervisor/operator of completion Rearrange all items including TIU and units on trolley Rearrange changekit and tools into respective boxes and on trolley Change 'sticky' tag to UP Send all items back to respective rooms Figure 6.26: The new flow of post changeover activities replacing wrap up phase 6.9 The New Optimized Test Handler Changeover Process With all the above improvement and implementation, the whole changeover process structure has changed significantly to be more optimized and lean with lesser duration to complete. Table 6.15 shows the actual time study based on the average data collected for the whole of Q1’2011. Figure 6.27 shows the new optimized changeover process flow. Thus from the data above, it is clear that the new changeover process duration is 32 minutes compared to the 240 minutes previously. Besides that, the number of stages and phases has significantly reduce with more parallel activities are executed. 190 In summary, the techniques proposed has enabled to reduce the changeover duration to 32 minutes and achieving the objective. The benefits and other ROIs will be analyzed in the following discussions. Table 6.15: Time study of the overall new optimized changeover process 191 Figure 6.27: The new optimized changeover flow 6.10 Return on Investment (ROI) analysis With the new improved and optimized changeover process, the benefits and advantages of achieving this can be summarized through the ROI analysis: 6.10.1 Capital and cost savings The ability to convert the equipment rapidly has helped the organization to response to the volatile market demand more systematically. With this new changeover process, the factories will eliminate the tool dedication policy and also 192 maximize the equipment utilization due to low conversion downtime. The impact of this can be analyzed through the cost benefit analysis as shown in Figure 6.28. The ROI analysis shows the capital tool saving or eliminating the need to purchase new equipments with this improvement. It is estimated at least 1 tool purchase can be eliminated in Q3’2011 for the case study factory which is about USD $ 1.5M in savings as shown on Table 6.16. Besides, the other minor savings can be materialized by the equipment collaterals savings especially in kits, TIU, pogo pins among other with an estimated sum of USD $50,0000. With the reduction in capital and collateral purchase together with a better overall utilization, the cost per unit at Test operation was able to be reduced to a grossing USD $ 0.25 and exceeding the goal target. With this the overall cost per unit was able to be reduced to almost USD $0.30 as shown in Figure 6.29. Though there was some minor expenditure on the R&D and re-designing of the hardware parts, but since the cost is below USD$1k, thus it is negligible in the overall finance analysis. In summary, the optimized changeover has brought in positive cost and capital ROI for the overall organization. 193 Figure 6.28: The capital purchase ROI analysis Table 6.16: The actual tool saving by factories for Q3’11 Q3'11 Available Inventory Pre Post factory(KMCO) 9 10 9 Factory B 7 8 6 Factory C 3 3 3 Total 19 21 18 Case Study 194 Figure 6.29: The cost breakdown analysis (post improvement) 6.10.2 Total Utilization Indicator Improvement The impact to the overall utilization can be analyzed from the total good production utilization and from the idling duration of the technician itself. Figure 6.30 shows an example of an actual utilization study based on before and after improvement of the changeover. The data collected post improvement though slightly below the corporate goal but it showed significant improvement compared to previous actual data in Q4’11. 195 Figure 6.30: The post improvement utilization analysis A huge reduction in both downtime and also idling can be demonstrated due to the improvements in changeover process. With further enhance and fine tuning, the utilization and exceed the expectation of the corporation’s goal target. On the other hand, the significant reduction in the technician’s idling time can be shown in Figure 6.31. The new improved and compress changeover able to minimize a technician idle time below 1 minute in order to achieve a changeover in 196 30 minutes. There are still a few minor idling instances in the new changeover and more analysis will be done to reduce this further to an ideal goal of ‘zero’ idling. T O Figure 6.31: The post improvement technician idling time reduction 6.10.3 Leaner and Efficient Training The new improved and implemented process is now well documented into both official specification (spec) called the ‘Standard Work Instruction’ module where technician will be trained and assessed based on this latest changes. All the current certified technicians will also undergo refresher training to ensure all shift technicians are aligned and standardized on the practice. The new and simplified process has truncated the duration of the training from 8 hours class to a 3 hours 197 class including of both theory and practical. With a more lean and efficient training, more technicians are to be trained and disseminate quickly to the production shifts. 6.11 Critical Appraisal The SMED and TRIZ techniques used to optimize the changeover in this case study helped to significantly reduce the duration from an average of 4 hours to ½ hour. If understanding the actual contribution of TRIZ in this changeover optimization, the Table 6.17 shows the forecasted changeover duration changes of using a single changeover technique like SMED alone compared with an integrated technique of SMED and TRIZ. The table clearly shows the major contribution of TRIZ especially in hardware designing and also process segmentation. Table 6.17: The contribution of TRIZ Duration No. Changeover Status (minutes) 1 Pre Improved changeover 240 Improvement with SMED 105 2 3 techniques only Improvement with SMED + TRIZ 32 techniques Nevertheless, as per Shingo’s SMED goal, a changeover is considered successful only if the whole setup can be completed below 10 minutes thus the new improved changeover in this case study can’t be considered as fully optimized and successful. Though, the 3 value added process in this changeover can be completed in 14 minutes but the remaining 18 minutes due to NVA like calibration and validation gates the whole process optimization. 198 Also, the available TRIZ principals and SMED techniques are aligned mostly to hardware and process improvement but lesser focus or tool proposed for areas like software, IT or network computing which is also part of most processes today. Due to this, the TP download phase cannot be fully optimized. Though many of the identified problems and proposed /implemented solutions are common sense and logical at basic but the introduction of SMED and TRIZ techniques helped solving problems in a standardized and structured manner. The most important element that was less focused in this case study was the human factor improvement the continuous motivation and training to the personnel ensures a better process sustainability and further enhancement. 6.12 Future Recommendation / Studies Some of the suggested recommendation and studies for the future are: i. Continue to pursue improvements to reduce the current test handler changeover to below 10 minutes by; a. Eliminating the validation and calibration phases with more empirical data b. Reducing the TP download phase c. Improve the hardware setup further especially the non ‘fungible’ parts by redesign or eliminate the NVA activities ii. Apply the TRIZ principles and SMED techniques suggested in this case study for any other applicable semiconductor based equipment iii. Extend the scope of TRIZ by introducing the other advance TRIZ tool’s like Standards and ARIZ 199 6.13 Summary This chapter covered the results and outcome based on the earlier proposed counter measures. Though many was accepted and implemented, but a handful of proposal were rejected due to current circumstances. Nevertheless, the outcome of the optimized changeover met and aligned with the initial objective. CHAPTER 7 CONCLUSION This project focused on a changeover case study where the non optimized process affected the organization from both cost and productivity point of view. The equipment, a test handler consists of 8 major changeover steps with average completion duration of 4 hours. The hardware part setups and the non standardized process was the major gating issue of the changeover. Thus, to counter the issues and gaps identified, the techniques from both SMED and TRIZ was introduced and integrated into the changeover process. Solutions included redesigning hardware parts and rescheduling the process sequence help to minimize the ‘Internal’ time and eliminate the Non Value Added (NVA) activities. One of the major breakthroughs was redesigning a hardware part which helped to reduce the setup time from an initial 120 minutes to a staggering 4 minutes using a TRIZ and SMED concept. With the implementation of the other improvement proposals, the changeover duration was successfully reduced from the current 4 hours to ½ hour with no safety and quality concern. The case study showed the integration of these techniques helped to achieve a better optimized changeover process. The improved changeover resulted in cost, capital and resource benefit for the organization. Nevertheless, there are still room for future consideration and improvement that can be explored upon. In summary, the integration of SMED and TRIZ techniques helped to successfully improve the changeover process for a test handler in a semiconductor industry from 240 minutes to 30 minutes. REFERENCES Anderton, J. (2009). Quick Changes. Canadian Plastic. January/February 2009, 29-30. Angeles, Rolly S. (2009). World Class Maintenance Management – The 12 Disciplines. Central Books Supply Inc. Association for Manufacturing Excellence (2009). Sustaining Lean: Case Studies in Transforming Culture. New York: Productivity Press. Farlow, D. (2005). Efficient Line Changeover. SMT magazine, March 2005, 4445 Fey, V., and Rivin, E (2005). Innovation on Demand: New Product Development using TRIZ. Cambridge University Press. Karlsson, C., and Ahlsrrom, P.(1996). Assessing changes towards lean production, International Journal of Operations & Production management. 16 (2), 24-41. Kearney, W. (1997). A proven receipt for success: the seven elements of work class manufacturing, National Productivity Review. 16, 67-76. Lev, S. (2009). Introduction to TRIZ. Altshuller Institute Online. Levinson, W., & Rerick, R. (2002). Lean Enterprise: A Synergistic Approach to Minimizing Waste. Milwaukee, WI: ASQ Quality Press Liker, J.K, and Meier, D (2006). The Toyota Way Fieldwork: A Practical Guide for Implementing Toyota’s 4Ps. United States: The McGraw- Hill Companies. 202 Lotter B., and Wiendahl H.P.(2009). Changeable and Configurable Assembly systems. Springer. McIntosh, R.I., Culley, S.J., Mileham A.R., and Owen, G.W. (2000). Critical Evaluation of Shingo’s SMED Methodology. International Journal of Production Research. 38(11), 2377-2395. Taylor and Francis Ltd. McIntosh, R.I., Culley, S.J., Mileham A.R., and Owen, G.W.( 2001). Changeover improvement a maintenance perspective. International Journal of Production Economics. 73( 2), 153 – 168. Taylor and Francis Ltd. Mann, D (2001). TRIZ: The Theory of Inventive Problem Solving. 10(2), 123125. Blackwell Publishing Ltd. Martin G. M. (2005). What is TRIZ? From Conceptual Basics to a Framework of Research. Creativity and Innovation Management, 14, 3-13. Moxham, C., and Greatbanks, R. (2001). Prerequisites for the implementation of the SMED methodology: A study in a textile processing environment. IJQRM. 18 (4 ), 404-414. Taylor and Francis Ltd. Nakajima, S. (1988). Introduction to TPM. Cambridge , MA : Productivity Press. Orloff. M (2003). Inventive Thinking Through TRIZ: A Practical Introduction. Berlin: Springer. Reik, M.P., and McIntosh, R.I. (2006). Formal Design for Changeover Methodology. A Case Study. Proc. IMechE, Part B. 220(528),1237-1247 Ross & Associates Environmental Consulting, Ltd. (2003). Lean Manufacturing and the Environment: Research on Advanced Manufacturing Systems and the Environment and Recommendations for Leveraging Better Environmental Performance. United States: Environmental Protection Agency. 203 Santos, J., Wysk, A.R., Torres, M.J. (2006). Improving production with lean thinking. New Jersey: John Wiley & Sons, Inc. Shingo, S. (1984). A Revolution in Manufacturing: The SMED system. Cambridge , MA : Productivity Press. Simon, L., and Vladamir, P (2009). TRIZ Body of Knowledge. International TRIZ Asscociation (MA TRIZ), Alshuller Institute, 1-9. Sousa R.M., and Lima R.M (2009). An Industrial Application of Resource Constrained Scheduling for Quick Changeover. Proc. IEEM, 189-193. Taylor, B.W. (2006). Introduction to Management Science. (9th ed.). Virginia: Prentice Hall. Van, J. V. (2001). Transport Developments Support Fast Changeover In High Volume SMT production. SMT magazine, May 2004, 66-69. Van Goubergen, D., and Landeghem, H.(2002). Rules for Intergrating fast changeover capabilities into the new equipment design. Flexible Manufacturing. Elsevier Science Ltd. Vardeman, S. B.(2010). The Impact of Dr. Shingo on Modern Manufacturing Practices. IE 361. Utah State University. Whitney D.E., (2004). Mechanical assemblies – their design, manufacture and role in product development. Oxford University Press. Womack, P.J., Jones, T.D., Roos, D. (1990). The Machine that Changed the World: The Story of Lean Production. New York: Harper Perennial. Womack, P.J., Jones, T.D. (2003). Lean Thinking. New York: Free Press. Yyes, D.G (2006). SMED reduces changeover time : A case study in a 204 food industry. Food Engineering and Ingredients, November 2006, 32-34. www.altshuller.com www.intel.com www.leanlearningcenter.com www.ross-assoc.com/lean www.trizland.com 205