III MANAGING CONTRUCTION DISPUTES CALEB DUMISA MOTSA A master’s report submitted as a partial fulfillment of the requirement for the award of degree of Master of Science (Construction Management) Faculty of Civil Engineering Universiti Technologi Malaysia November, 2006 V ACKNOWLEDGEMENT I would like to express my sincere gratitude and grateful appreciations to my supervisor, Dr Rosli Mahamad Zin for his invaluable guidance, advice, encouragement and help throughout the project. Without his advice and constructive ideas this report wouldn’t be successfully accomplished. A special acknowledgement must be given to my sponsor the Common Wealth Scholarship under the Government of Malaysia, for their financial support throughout this project. VI ABSTRACT Construction projects are increasingly complex, resulting in complex contract documents. Complex construction can likewise result in complex disputes. Disputes is inevitable in construction projects which predominantly arise from complexity and magnitude of works, multiple prime contracting parties, poorly prepared and/ or executed contract documents, inadequate planning, financial issues and communication problems. Any of these factors can overturn a project and lead to complicated litigation, arbitration, mediation, time overrun, increased costs and a relationship break down among members of different parties involved. The objectives of this study are to identify the root causes of construction disputes as well as their impact on client’s organization. The methodology of study adopted was through questionnaire survey where the target respondents were clients, consultants and contractors. Based on the analyzed data, there are nine root causes of construction disputes caused by clients, five root causes caused by consultants and four root causes caused by contractors have been identified in the local construction industry. The impact of construction disputes in client’s organization as found in the study are time consuming, cost effective, loss of reputation and sour relationship between stakeholders and also loss of profit and business validity. ADRs were observed as the best method of resolving disputes because they were identified as none time consuming and cost effective. From the findings it can be concluded that construction disputes are a cause of concern in every project and the solution to this problem is to avoid and cautiously manage them for smooth running of construction process, prevention is believed is better than cure. VII ABSTRAK Projek pembinaan masa kini didapati semakin rumit dan kompleks, di mana ini sedikit sebanyak turut menyebabkan dokumen kontrak juga menjadi semakin rumit dan kompleks. Projek pembinaan yang kompleks ini juga menghasilkan pertelingkahan yang kompleks. Pertelingkahan adalah sesuatu yang tidak dapat dielakkan kerana ia pada asasnya timbul disebabkan oleh keadaan kerja yang kompleks serta magnitud kerja-kerja tersebut, selain pengelibatan ramai pihak di dalam sesebuah kontrak, kualiti yang kurang memuaskan dalam penyediaan dan penggunaan dokumen kontrak, perancangan yang tidak mencukupi, isu-isu kewangan serta masalah-masalah komunikasi. Salah satu daripada faktor-faktor tersebut sudah mencukupi untuk menggagalkan sesuatu projek serta menyebabkannya menghadapi proses-proses rumit yang melibatkan perundangan, timbangtara, dan mediasi, di samping menyebabkan kelewatan penyiapan projek, peningkatan kos keseluruhan projek serta menjejaskan hubungan di kalangan pihakpihak yang terlibat dalam projek tersebut. Objektif bagi kajian ini adalah untuk mengenalpasti penyebab utama pertelingkahan di dalam projek pembinaan selain mengenalpasti impaknya terhadap organisasi klien. Metodologi yang digunakan di dalam kajian ini adalah melalui borang soal selidik di mana responden-respondennya terdiri daripada pihak klien, perunding projek serta kontraktor. Berdasarkan kepada datadata yang telah dianalisis, di dalam industri pembinaan tempatan, dikenalpasti terdapat sembilan penyebab utama pertelingkahan di dalam projek pembinaan berpunca daripada pihak klien, manakala lima lagi penyebab utamanya adalah berpunca daripada pihak perunding projek serta empat lagi penyebab utama pertelingkahan di dalam projek pembinaan adalah berpunca daripada pihak kontraktor. Impak pertelingkahan di dalam projek pembinaan bagi organisasi klien yang dikenalpasti melalui kajian ini adalah ianya memakan masa, menelan belanja, hilangnya reputasi dan mengakibatkan hubungan yang renggang di kalangan pihak-pihak yang terlibat, selain mengakibatkan kerugian serta melemahkan perniagaan yang dijalankan. ADR didapati merupakan kaedah yang terbaik untuk menyelesaikan pertelingkahan kerana ia didapati tidak memerlukan masa yang panjang serta kosnya yang efektif. Daripada hasil kajian, boleh disimpulkan bahawa VIII pertelingkahan dalam projek pembinaan adalah sesuatu yang dititikberatkan dalam perkara kajian dan penyelesaian bagi masalah ini adalah dengan mengelakkan pertelingkahan bermula serta langkah-langkah awal untuk menguruskannya agar projek pembinaan dapat dilaksanakan secara lancar, kerana adalah dipercayai bahawa mengelak adalah lebih baik daripada mengatasi. IX TABLE OF CONTENTS CHAPTER 1 2 TITLE PAGE INTRODUCTION 1 1.1 Introduction 1 1.2 Problem Statement 2 1.3 Aim and Objectives 3 1.4 Scope of Research 3 1.5 Project Methodology 3 1.6 Significance of Findings 5 1.7 Summary 5 LITERATURE REVIEW 6 2.1 Introduction 6 2.2 Definition of Dispute 7 2.3 Causes of Disputes in the Industry 8 2.3.1 The Contract Conditions 10 2.3.2 The Design Deficiency 18 2.3.3 The Construction Process 28 2.3.4 The Consumer Reaction 29 2.3.5 Time 33 2.4 Causes of Disputes by Stakeholders 34 2.4.1 Causes of Disputes by Client 35 2.4.2 Causes of Disputes by Consultants 36 2.4.3 Causes of Disputes by Contractors 37 2.5 The Impact of Construction disputes on client organization 39 X 2.6 Methods of Recovery of Disputes 40 2.6.1 Litigation 41 2.6.2 Arbitration 41 2.6.3 Mediation 42 2.6.4 Negotiation 42 2.7 Summary 43 3 RESEARCH METHODOLOGY 44 4 DATA ANALYSIS AND RESULTS 49 4.1 Introduction 49 4.2 Results and findings 60 4.3 Analysis and Discussions 66 4.3.1 Causes of disputes by clients 68 4.3.2 Causes of disputes by consultants 72 4.3.3 Causes of disputes by contractors 75 4.3.4 The impact on client’s organization 79 4.3.5 The most preferred method of resolving disputes 4.5 Summary of findings 81 82 4.5.1 Identify the causes of major contributors of construction disputes 83 4.5.2 Identify the impact of construction disputes in client’s organization 85 4.5.3 The most preferred method of solving disputes 5 CONCLUSIONS AND RECOMMENATIONS 85 86 5.1 Introduction 86 5.2 Conclusions 86 5.3 Recommendations 88 XI REFERENCES 89 APPENDICES 92 XII LIST OF FIGURES Figure No. Title Page 2.1 Causes of disputes in contract condition 17 2.2 Causes of disputes through design deficiency 27 2.3 Causes of disputes by client 35 2.4 Causes of disputes by designers 36 2.5 Causes of disputes by contractors 37 Causes of construction disputes 38 2.7 Project dispute resolution satisfaction 40 4.1 Major causes of disputes caused by clients 71 4.2 Major causes of disputes caused by consultants 75 4.3 Major causes of disputes caused by contractors 77 4.4 Impact of disputes in client’s organization 80 4.5 Major Root causes of construction disputes 83 XIII LIST OF TABLES Table No. Title Page Causes of construction disputes caused by client 4.1 i) Clients Point of View 54 4.2 ii) Consultants Point of View 55 4.3 iii) Contractors Point of View 56 4.4 iv) Overall respondents 57 Causes of construction disputes caused by Designers 4.5 i) Clients Point of View 58 4.6 ii) Consultants Point of View 59 4.7 iii) Contractors Point of View 60 4.8 iv) Overall Respondents 61 Causes of construction disputes caused by contractors 4.9 i) Clients Point of View 62 4.10 ii) Consultants Point of View 63 4.11 iii) Contractors Point of View 64 4.12 iv) 65 Overall Respondents The Impact of Disputes in Clients Organization 4.13 i) Clients Point of View 66 4.14 ii) Consultants Point of View 67 4.15 iii) Contractors Point of View 68 4.16 iv) Overall Respondents 69 4.17 The Most Preferred Method of Resolving Disputes 70 1 Chapter 1 INTRODUCTION 1.1 Introduction to the Problem Construction relationships in the construction industry all over the world have become more increasingly strained as years goes on and on. Working relationships, communications, and contractual commitments are often not carried in good faith. This has led to most developed countries to search for better alternatives on how to manage disputes in the construction industry. Though it has been seen that disputes in the industry is like an un-incurable disease, means are done to fight the problem. In the United Kingdom, for example the standard form of contract that is internationally used to new engineering contracts has been subject to change; whereas, in the United States of America the Disputes Review Boards ( DRB’s) which comprises of three board members to manage disputes in construction sites was introduced. All this exercises undertaken have proved to be successful. Developing countries are still facing this problem and the research on this topic will be on what to do either to improve or avoid and manage disputes in our local construction industry. Alternative dispute resolution is therefore essential for the industry in order to improve its performance. 2 1.2 Problem Statement The construction industry has become very complicated such that political and economic trends are increasing the economic pressure resulting in disputes. Complex construction has brought about complex disputes in the industry. There are so many different types of sources that may lead to disputes and this eventually becomes a burden to the industry in terms of production Great concern has been expressed in the recent years regarding the dramatic conflicts and disputes in the construction industry in the whole world and this has resulted in extensive high costs and time consuming. This is a result of the systems of resolving disputes in the industry. An alternative resolution has been seen as a necessity in the industry. The alternative resolution of disputes should therefore address the causes of disputes within a limited space of time so that the production capacity is not affected in anyways. We have seen stakeholders blaming each other because of problems they come across during the construction process, because of poorly done designs, claims, poor administration and delays and these have been overlooked. There are questions rose on what is it that is actually causing disputes in the industry? And why disputes have become a nature of event in the industry? Disputes and conflicts have gained frequent rise during construction of projects and this needs an involvement of a neutral body to resolve disputes as early as possible. 3 1.3 Aim and Objectives The aim of this study is to identify the best dispute resolution amongst the ones in current use, and objectives of the study will be summarized as follows: i To identify the root causes of construction disputes ii To identify the impact of disputes in the industry iii To identify dispute resolution methods. . 1.4 Scope of Research This research has been carried out with a careful study on data collected mainly on case studies and questionnaire survey exercise. The research was focused on the private and government projects which are faced with the problem of construction disputes. 1.5 Project Methodology The methodology of the project consists of two phases as shown below (Refer to Figure 1.1): i) Phase one Gather information from journals, internet and book .Literature review on causes of construction disputes, the impact in Client’s Organization and methods of dispute recovery. 4 ii) Phase two The second phase of the study was conducting a survey and discussions with relevant stakeholders, data collection from relevant stakeholders, data analysis and discussions, conclusions and recommendations. The flow chart below illustrates the steps of the study (research methodology): Methodology Literature review Conducting a survey Consultation with stakeholders Data analysis & discussions Conclusions and recommendations Figure.1.1: Research Methodology 5 1.6 Significance of Findings This study has identified the root causes of construction dispute caused by the client, designers and contractors. It also covers the impact of construction disputes in a client’s organization and methods of disputes recovery. These factors had been seen as the major factors in affecting production in the industry, thus it is a necessity to manage them or rather to avoid them for the better part of the performance of the industry. 1.7 Summary This chapter covered the introduction to the problem of disputes in the construction industry that has prompted to this study. Moreover it states the aim and objectives, scope, methodology used and the significance of the findings. This project is based on managing construction disputes that has been seen to be affecting the industry’s performance. The results to be obtained from the study will help in improving the production of the industry by means of implementing the decisions obtained from the results of the study. 6 Chapter 2 MANAGING CONSTRUCTION DISPUTES 2.1 Introduction So long as human nature is what it is there will always be disputes, and those disputes what ever their characters are , they must be resolved if society is to exist in a civilized way and this problems must be resolved as quickly, as cheaply and as satisfactory as possible. Conflict resolution is probably the most important area for the future of mankind and the continued existence of the world. Is it good enough to have it served in inadequate manner? “Conflict is seen to be a normal procedure in the construction industry and time has come for professionals to come up with ideas on how to handle the situation to normal. Disputes are almost inevitable in the fulfillment of construction contracts and with those of significant magnitude or time span, the propensity for dispute is greater”. (Hellard, 1987). Research on the causes of conflicts and disputes in the construction industry has therefore seen essential if the industries performance has to improve. Disputes and conflicts are a burden in the industry though there are means of resolving them. The methods are to be up graded if an alternative resolution is neglected. The construction process involves different disciplines to work as a team in a short space of time. It also involves large amounts of money that have to be shared amongst members of the team, and that is where the problem is seen or starts. 7 According to Hellard (1987) types of disputes, conflicts that have been seen in contractual relationship are summarized as follows; i. Time related disputes (delayed processes) ii. Financial matters (claims and payments) iii. Standards of workmanship (designs and manual works) iv. Relationships and people’s conflict in the industry 2.2 Definition of Dispute The oxford dictionary defines dispute as a misunderstanding between two parties, either contractual or non contractual but the fact is there is a misunderstanding between the two it becomes a dispute. “A dispute is defined as a class or kind of conflict, which manifests itself in distinct and justifiable issues. It involves disagreement over issues capable of resolution by negotiation, mediation or third party adjudication.” (Brown et al., 1993) According to Bachner (1988) “a dispute will not exist until a claim is asserted by one party which is disputed by the other party”. At most claims are seen to be one of the causes and this needs an intervention of a neutral body to solve the problem if the other party will dispute the said claim. The designer would not agree when they have made a blander in their designs but there will always put the blame with the contractor, claiming he is failing to do his work. According to Kumaraswarmy and Yogeswaran (1997), “a dispute can be said to exist when a claim or assertion made is made by one party is rejected by the other party and that rejection is not accepted.” They were referring this to the Institution of Civil Engineer’s arbitration procedure. Any misunderstanding between two parties needs an intervention of a neutral body who will not be biased in awarding the decision. If the other party suspects that the award given is biased he then prefers for a better alternative. 8 The alternatives to solve disputes in the industry are becoming more and more expensive in terms of time and financial wise. “It is therefore wise to resolve the conflicts within the industry than involving people who are not well vest about the industry” (Goyal, 1996). Involvement of lawyers and judges has become costly for the participants of the industry, the disputes takes time to be resolved and it is expensive. So a common understanding is essential for the stakeholders in order to avoid disputes. The Oxford dictionary defines Conflict as a dispute or two parties failing to reach a common understanding. For a conflict to be resolved a third party is involved to make the two to reach a common understanding. 2.3 Causes of Disputes in the Industry “Undoubtedly many construction disputes have their origin in the seeds sown by or in, the client’s error” (Hellard, 1987). Under normal circumstances disputes should not occur if there is no common relationship between two parties, there must be a common relationship between the two then a misunderstanding to be fulfilled and the other parties fails to fulfill it then it becomes a dispute. There are five sets of contractual relationships which are common in the construction program. According to Hellard (1987) the relationships are as follows; i. The relationship of the owner to the designer ii. The relationship of the designer to another design specialist(s) iii. The relationship of the owner to the prime contractor iv. The relationship of the prime contractor to its subcontractors and v. The relationship of the prime contractor to suppliers 9 These five basic relationships have been studied over the years by interested individuals as well as professional committees of varied membership from all corners of the industry, along with private and public attorneys, all in potpourri of concerned people. The result of these studies has been the publication and wide usage of standard form contract documents which are published all over the world in different construction industries. “At most each and every government has its own contract form and more than one contracting agency, and each agency, if of any size or self esteem, has its own standard form”(Stipanowich, 1996). Irrespective of the origins, prejudices and ambitions of their authors, all these standard contracts essentially set forth very similar rules and have the same structural format. Most construction contracts are short in themselves, but they incorporate by reference many documents which comprise the total agreement of construction. The study on construction disputes by Hellard (1987) has come up with the following as major factors that causes disputes in the industry; i. ii. iii. The contract conditions • Lack of perfection in the contract documents • Failure to account the cost • The psychology of people in construction The design deficiency • The underground or subsurface problem • Risks • Defective Plans • Methods or Means and specification performance The construction process 10 iv. v. The consumer reaction • The public owner • Warranties Time 2.3.1 The Contract Conditions “The documents referenced as part of the contract typically include a front end boiler plate which sets out the general conditions or rules which are to be followed and the roles of those who will be governed by the rules” (Hellard 1987). The front end and can and usually will include an invitation to bidders, which is a multi paged statement describing very briefly the project and the salient terms and conditions a prospective bidder must fulfill in order to file a responsive bid. The front end will include a bid form for all bidders to use, thus standardizing the responses of all officers so that evaluations can be rapidly and hopefully unerringly made. Strangely enough the bid form frequently does not provide enough room for bidder to fulfill in the information required Often the federalize for invitation for bid or request for proposal will require certain information to be listed on the bid form, but no place for the information is provided on the form. Careful review of the bid requirements and the bid form proposed is the first step an owner and its designer should take to avoid construction disputes. Not only the bid requires owner review, but the entire front end proposed by the designer should be examined by the owner. It is not sufficient to assume that a front end is acceptable because it is in common use on hundreds of million dollars in work. A survey has been undertaken to review the problem by the authors and it was found that it contains inherent contradictions, poor English, antiquated provisions, and all types of ambiguity and confusion which can boggle the very best technical and legal minds. Those who are purchasing the construction must read the boiler plate the designer has prepared. Good business would indicate the contract condition be ready after enough 11 time has been given to review the boiler plate by designer and owner before the project goes to bid. This will allow time and alteration. If there is uncertainty in the review’s mind regarding what the rules or general conditions should best be, then a premiere construction consultant, or the largest contractor, or the nearest associated general contractors office should be asked to review the documents. It is common practices that the standard contracts will be In favor of the owner and the exact people who are doing the spade work are at disadvantage. It is therefore essential to have a neutral body to review the contract documents before going on bid to avoid any discrepancies that may occur due to poor documentation. i) The Lack of Perfection in the Contract Documents “Owners, contractors, designers, and every one involved in construction readily recognize and are quick to admit publicly the very obvious fact that a perfect set of contract documents simply does not exist.” ( Hohns, 1979). All drawings in the contract documents somewhere have mechanical drafting errors or lack a needed dimension or detail. Many have errors which stem from the human nature of the designer and draftsman. Not only are human errors, but changes always occurring as projects undergo the design and construction process. Certain selected equipment carefully specified because obsolete something better has come along, but it is bigger or needs more power. There are changes in space usage to accommodate revised owners needs, something unforeseen occurs, the documents and work scopes must be adjusted. The more complex the project, the more ramifications a change has. The shorter the period allowed for design, the more addenda’s that are required, and the more the opportunity for errors. 12 No one man may know or remember every place a certain detail was shown. “The larger the project, the more the people, the drawings, the thoughts, and the ideas consequently, the larger the project the more errors there are” (Hall, 2002). Contract documents are one major origin of disputes. Document errors become the fault of the owner when they cost the contractor un-bid or unforeseeable dollars. Documents errors become the fault of the designer when the judgment of its peers and the custom of the industry the errors are gross and inexcusable. Document errors become liabilities when someone who has a right to rely on the professional is severely hurt or damaged. Punitive damages are staring to be considered as collectible against a professional when the hearer of the facts finds that the professional’s refusal to come to grips with its duties are offensive to any reasonable standards of behavior. ii) Failure to Count the Cost “Dispute continually arises because someone failed to count the cost at the beginning when the cost should have been defined” (Jessup et al., 1963). Few contractors bring claim on projects which come in near or under the construction budgets. Few owners seek liquidated damages when projects are done on time or close to it. If designers are waterproof and the products the designer specified fulfill the sales representative’s claims, disputes are few and far between. Contrary to the opinion of most owners, few contractors are deliberately claim’s conscious. Most supervisory projects personnel who work for the parties on the project have little real knowledge of disputes or what is involved in litigation and arbitration, most of those involved in getting a job done have solved complex problems on a daily basis of face to face confrontation for such a long period of time that they come to believe they know it all. Thus they prefer to argue among themselves and write what they believe are clever letters to establish a record, and most distribute and resent the lawyers. Contractors who have made money on a job usually do not invent claims or pursue spurious claims. Most often, a contractor who is clearly entitled to valid contract 13 adjustment via a claim will ignore the situation if the job has come out well enough to live with. Contractors like to get the job done and get over with. They fancy themselves builders; claims take long to hold their interest. According to Essex (1996) “Disputes arise when the job does not come out well, and too often the reason for this is the failure initially to figure the cost accurately”. This failure to count the cost initially is not confined to just the contractor. It applies to the owner who set out unrealistically to build a factory, as well as the designer who sets out the design it for less than it will really cost either in design or construction. In construction, major dollars and work scopes are calculated and committed in short periods of time. It is common that someone fails to count something, and end up with a price that is too low. What is worse is that most of those in the industry simply do not have the money to pay for their errors. The one with the best intentions can not pay for his error. Ironically, too, it would seem to some observers that those with the money to pay for their errors lack the degree of intention needed to dig deep enough to square the account totally. “In competitive contracting market, contractors work at extremely low mark up levels.” (Glover and Elliot, 2005) Construction is perhaps the zenith in high volume, low markup business. Usually general contractors bid in the public market with a fee of three percent over its estimated cost. Subcontractors of significant figures importance on the project run a five to eight percent fee. Less major subcontractors will mark up labor by forty to sixty percent and carry material at cost. All sorts of pricing systems exist, but all have one common trait: they are too low. This money must carry home office overhead before net profit can be counted. The hardest part is that the dollar have to be collected after all the delays and difficulties involved in retain age, back charges, punch lists, and the like are resolved. Thus, to the contractor boxed in with retain-age and other cash flow problems there is no room to absorb cost overruns. 14 “Construction pricing methods frequently are not to take into account the erection process that will be ultimately required in sufficient detail” (Stipanwich, 1998). The modern designer does not want to tell how a job should be done or prescribe or reveal any sequential restrictions not strength related. Thus million of funds of work are priced under severe time pressure using established unit price calculated from the estimators experience and which to some extent many have been proven in ongoing or recent projects. The failure of a contractor to understand and / or correctly bid or price the work initially is a major reason for disputes. It is compounded by the ever present confident overbearing optimism inherent in all contractors that they somehow are charismatic and can overcome the dilemma of an obvious bid. iii) The Psychology of People in Construction “It was noted earlier that construction is not a science, it is an art. Construction is really people, and the successful contract administrator, or disputant to a contract interpretation or unfortunate occurrence on a project, is well served to know a little about people involved.” ( Hohns, 1979) When traced down to real roots, a construction dispute has just two people involved. They may be very visible to each other and all concerned, or they may not be known to each other and insulted from it all by many layers of other people. The successful disputant is often the one who knows the people in construction and how to meet them and their psychological needs to their immediate benefit and the disputant’s ultimate benefit. What are construction people? A question which provokes different images to everyone. Tough, hard-driving, demanding, strong, ignorant, shrewd, calculating, honest, dishonest, straight shooters are all adjectives applied at times to individual members of the industry, and even though the adjectives are in some cases antonyms, still the people they describe have some commonality. Construction people have certain recognizable traits or makeup to their personalities. They are referred to gregarious people. All want to belong to a crowd. 15 “The herding instinct is very strong in the industry’s people. All seek and need that sense of acceptance or approval. They have a need to emulate the leaders or their concept of the leaders of the profession. Words like belonging, imitation, loyalty, recognition, superiority, status are descriptive of the human elements of gregariousness. Try to make the other party feel as if he belongs to the pack. Find out the group the other party feels important. Show him how resolution of the dispute will help him achieve or strengthen his membership in the group” (Carmicheal, 2002). The next trait to bear in mind is found when a person feels accepted into a group. Almost always he will turn pugnacious. Now that he is in the group, he wants to fight for its need and to seek recognition from his peer group. Words like aggressive, anger, defiance to rules, competitive, curiosity, hate; hostility describes the pugnacity in people. Give the other party something to fight for or with; perhaps a third person can be blamed some of the dilemma. Use the trait of the other fellow’s pugnacity to advantage. More important perhaps than pugnacity is that everyone has the problem of ego survival. “It is one thing to loose money in a contract problem, but it is a lot to lose face. All people have an idea of themselves which they feel must be defined” (McManamy, 1994). The construction industry is one in which the public and peer knowledge of what everyone is doing is vast. There are few secretes in the industry. Everyone’s prices and problems are known; words travel faster than air. Disputes can often be more easily resolved when all the egos involved can survive. Not only are people typically quickly to protect their self-image, they all want to extend the position they currently hold or claim is theirs. Thus any massage couched in terms of few acquisition, promotion, saving money, or being protected will be heard and every often receive action. Everyone wants space, a better future, and the chance to increase the recognition of one’s self-worth. Appeals to ambitions, goal realization, and increase of power help resolve disputes. The clever disputant deals with its adversary with these ideas considered and brought out. The survival and extension of one’s ego include as well the pleasing of a person. Some people like to enjoy themselves, some like to suffer, others want argue, some like 16 detail, some the big pictures. The successful disputant looks for opportunities to help to help the people on the other side find pleasure in the dispute proceedings. According to Camicheal (2002) Construction disputes and confrontations arise because the people involved have needs. From the contractor’s side the needs are usually money or profit related. The designer has the ideas, his building or design which might be his monument to himself, his reputation, his artistic temperament, his money, his insurance premium, and similar needs. The owners have needs as well; political careers, corporate careers, the need to have the space for a certain day. When something unanticipated or not properly recognized interferes with the fulfillment process, goals and security are jeopardized, communications become strained, and strains seem always to be followed by demands, refusals, other more intense strains, hard, then harder positions, and money losses. Unfortunately or perhaps otherwise, it is not in most people to recognize an error, particularly their own, and say I’m sorry and seek to make amends. In construction most are unable to pay for their mistakes, it is simple too expensive; and alas, those who can afford to pay for the mistakes generally remember lots of others errors by the other party which even if already forgiven somehow must now be reconsidered. Once confronted with a problem too expensive or complicated for ready resolution, the claim or dispute process begins. At this juncture several more typical human traits should be born in mind in addition to those already considered. People are creatures who like order. People do not like chaos. Random thoughts, unconnected conditions and ideas, jumping from this to that tends to confuse and obfuscate the paths necessary for problem solving. Human beings react best to order. Strangely, maybe sadly, people prefer well-ordered lies to chaotic truth. Not only is order important, but personal habits are as well. There is a need in everyone to follow their habits and traditions. Appeal to keeping the law, following moral codes, being an early riser, or obeying the government are often rewarding. People have a need to obey. If a construction problem exists chances are that sufficient 17 research and realism will find people as the root cause. In the quest of profit or career improvement, construction people have been known to be greedy, never satisfied, resentful, quick to cover themselves, quick to improve themselves, legalists one moment, rationalizes next. They are often over their heads, lazy, not inclined to do good, incompetent, yet protected by the needs of others and the system, indifferent, discouraged, surprised, sick, or about to get sick. People are a prime cause of construction disputes, and the only solution to these disputes as well. The rise of society’s present attitudes that everyone has rights has led too much of the activity in disputes. The vast amount of contention and society’s attitude towards one’s right must be viewed from the more mature point that each day is one of the opportunities, not guarantee, a foundational position which seems to be lacking in current thoughts. The fish bone diagram (Fig. 2.1) below shows the causes of disputes through contract documents. Lack of perfection in the contract documents Failure to account the costs Dispute The psychology of people in construction Figure 2.1: Fish bone diagram illustrating the root causes of disputes in contract condition. 18 2.3.2 The Design Deficiency The design deficiency which leads to a major dispute is generally beyond an error of omission. To be significant the design error usually must alter the means, methods, environment, duration, or the conditions of the construction process. Any number of factors can influence this. The most common place in which design errors are made are in the foundations, in the construction of the frame and the enclosure, in the utilization of spaces such as method and materials and the required end result are specified, in project duration, and in connection with related performance by others on which the project in question must at some point rely. Some of the problems are as follows: i) The Underground or Subsurface Problems The cause of underground problem can be generally be traced to the handling, display, and interpretation of subsurface investigations. The location, depth, number, and types of borings or subsurface investigations are established by the engineer who needs the information in the building’s foundation and its construction. Borings are typically done by a drilling contractor usually hired directly by the owner, often on a competitive basis using specifications prepared by the architect, the structural engineer, or a soils engineer. The owner obviously wants to get the most out of the borings and subsurface investigations. These investigations are first used for the design of the foundation; then they are typically offered to the contractor for its use in bidding and constructing the job, and it is in this latter use that the disputes begin. It is well known in the industry that variations in the earth’s composition constantly occur underground. It is also well known that each bidding contractor cannot adequately investigate the site to define the soil characteristics in the time period available for bidding. The owner thus has a problem. It wants to put the risk of the excavation and methods of foundation construction on the contractor. It also wants to buy the project for the best price. And so the dilemma, how 19 can the owner pass its soil boring and subsurface knowledge to the contractors to help keep the bids down by sharing the best soil information available and still pass the risk to the contractor if the work is more difficult or expensive than the borings indicate? The route followed to move this risk over to the contractor is to write a clever specification. The following are the random sample quotations from four different jobs which are typical specification writer ideas of how to make soil characteristics available in order to get the most accurate price and simultaneously put all the risk on the contractor. Hohns (1997) makes an example of a case that took place in New England building of a school with local engineers. Sub surface conditions: • The owner has explored subsurface and the foundation conditions by having authorized the making of borings on site. • The owner makes no representations regarding character or extent of soil, rock or other subsurface conditions and / or utilities to be encountered during work. Surface formations, including water levels, included in reports have been interpreted from completed borings, correctness of which is not guaranteed. • The results of the subsurface investigation are available from the architect. The bidder must make his own deductions of subsurface conditions which may affect methods or cost of construction of the work. Each bidder, before submitting his bid, must visit the site and examine all conditions that may affect his work, and make his own deductions as to subsurface conditions. No claims for damages or other compensation will be considered should the scope or progress of the work be different from the ones anticipated by the contractor. This sample is somewhat peculiar since the borings showed bedrock or boulders and thus the specification almost has to lead to a claim for time and general condition money in addition to the unit price for bedrock excavation. 20 The data regarding the surface characteristics are first defined as information only, not part of the contract documents, even though the information often is printed on the contract drawings or bound into the specification book. It is here that the specification writer goes astray, for those who write and enforce the specification (most the owner or designer) forget or fail to perceive that while they may be the author and the first interpreter of the specifications, the ultimate interpreter is a judge or panel with possibly little acquaintance or sympathy with fancy word scheme for the risk avoidance. There is no question that the ultimate interpreter in recent subsurface dispute has been interpreting the soil disclaimer on the basis of reasonability. The question asked to determine if the disclaimer is reasonable ultimately becomes twofold. The first whether the bidder did anything special to investigate the site, or did it rely only on the information printed or made available with the contract documents. If the bidder dug a test pit, drilled a hole, investigated the subsurface site characteristics in any way, or had previously worked on adjacent sites, and used this special knowledge to price or plan its bid, then regardless of the degree of such separate knowledge, it has become a special bidder. It can be argued that the bidder no longer has the right to claim reliance on the owner’s information, indeed it has not so relied. The bidder who makes any major independent analysis of the subsurface essentially picks up the risk of the excavation. The courts and review boards have generally been ruling in favor of the contractor on the underground claims of added cost. These decisions have involved into common law, where the consensus of the decisions leans strongly toward contractor recovery. Consensus, however, does not guarantee a winner in a horse race any more than it does in a construction dispute. The essential element in this type of claim may well be reasonability and reliance but this does not negate the possibility of the superior ability of either or both parties to persuade each other or the hearer of facts as to who is really right. People often win arguments when they are wrong simply because they know best to argue. Many times the skill of counsel will overcome the letter of the law. 21 ii) Risks The contractor should assess and display its risks to its advantage in any project it prices. The present practice of the typical contractor is sadly deficient in risk defense in comparison to the owners and designers. Usually the contractor makes an estimate on a job consisting of three elements: • general conditions or field overhead • The labor and materials for work the contractor could or may want to do with its own forces, and • The subcontractor work Exposure to assuming responsibility for risk is largely found in the estimate techniques and summaries which make up the element of general conditions. Sensible estimator techniques in this area must be stressed since the estimate often records and binds the thinking of the contractor forever. For example, the usual job specification will set out that all work must be done between 8:00 A.M and 4:30 P.M on a five day wok week. “Thus very obviously no overtime is contemplated, seen necessary, or wanted in the mind of the writer of the contract” (Bachner, 1995). The contractor, however, almost always include an item of overtime in its general conditions. Perhaps it is only the overtime for the concrete finishers which could very well be within the perspective of the writer of the contract, but unfortunately, almost without exception only the word overtime is used in the estimate. According to Goyal (1996) five years later in the construction dispute process the original estimate is produced as part of discovery. The contractor pressing a delay claim suddenly is confronted with the undeniable fact it recognized during the bidding stage that the job could not be timely done without overtime. The contractor has admitted it foresaw the potential of delay without overtime, and the urgency or ease of claim collection can be jeopardized. How much? In one experience in Florida, a $920,000 loss stuck because a contractor had listed large amount for overtime on a no overtime 22 specification and also showed an additional item called contingency of $10,000 on its estimate. The judge said, “You knew it couldn’t be done, you bought the risk.” According to Cheeks (1996) “in the present business world theory of risk minimization, there is no place for a word like contingencies in estimate” All the parties involved, bidder, owner, or engineer, must think out its program and not have contingencies. Contingencies are unidentified but obviously recognized risk. Delay could well be in the definition of contingency. It may never have been in the mind of the person who wrote and qualified the contingency, but the persuadability of other five years later may make it difficult to overcome the connotation of the word contingency, particularly to the ultimate hearer of the facts. Modern contractors who are claim conscious should forget the word contingency. The owner and designer should be just as leery of the word contingency. The five percent override on the base contract price by the typical owner in all its data processing o other displays on the construction budget should not be characterized, discussed, or written as a contingency. Let it be a reserve for upgrades in scope. Avoid the use of words which could mean more than intended. The adversary could well sharp shoot a god claim because of the words used in the planning process. The place to put money for the contingency or overtime in non overtime specifications is in a large fee. Fee is a common word to define markup on the estimate of all field cost to cover the home office overhead and provide a profit. The fee or markup commonly used at bid time is in the range of 2 to 4 percent for the major general contractors. This means that a general contractor with one million dollars overhead must do more than thirty million dollars per year at three percent to break even. Studies of a number of contractors show that the home office costs usually run four and a half percent of the volume, yet the bid markups of these contractors are often for less. There may be no end of good reasons for the difference at bid time but five years later in a major law suit for loss recovery those reasons are generally very hard to recall, and at 23 best the low fee originally charged becomes just another item of persuasion or argument one does not need. Those responsible for estimating, marketing, and buying have to be taught risk analysis and protection. If one adds a contingency fee to the estimate, what does it mean? Management must be aware of risk avoidance maneuvers and instruct its people what to do. Insurance companies are criticized because they go to grate pains to teach the professional designer or manufacture they have insured what to do or not to do. Good business practice are certainly good business. This includes training and coaching. The better one is trained and the more he practices, the better the player becomes and the better the score. The contractor, owner, or the engineer sophisticated enough to increase its fee rather than particularize on paper controversial elements of cost is no more profit minded or guilty of unfair business than if it had based its price on new methods of construction cheaper than those in the in common use and then kept all the savings as added profit for itself. iii) Defective Plans “A major source of disputes in the design deficiencies is that categorized as defective plans” (Hellard, 1997). What are defective plans? Most people involved with plans have a working idea of the definition of this phrase, but in reality no standard exists locally or nationally that precisely describes how to measure the plans for defects. Indeed, everyone who has worked with plans know that no set of drawings is complete or without error. Somewhere dimensions are missing, elevations or grades are in error, a detail is missing, or a detail is shown but not needed. Not only are these types of errors common, but all who work with plans know that drawings can always be refined and upgraded. Plans can always be made better, they can be improved. 24 Thus all plans are to some extent defective and everyone involved in building uses defective plans every day. The question in plan deficiency disputes is when the plans become defective to the point at which undue costs are generated from their use. The usual legal definition is that plans are to be prepared with the normal standard of care found in the profession, but no precise standard exist. The designer has the advantage of its subjective knowledge of the intent of the plans. In some cases pressures from the client will be exerted for degree of performance in excess of the objective intent of the plans. This, plus poorly drawn plans, poorly drawn details, poorly prepared notes on drawings, and poor specifications may reach a point where in the opinion of one’s peers, a level of acceptable performance has not been achieved. In the case of errors of omission from a set of plans, the decision of adequacy on the part of the professional is much easier to make than those which bear on methods or performance levels to be met upon completion. If an engineer omits the exit lights totally, are the plans defective? Does the owner have the right to rely on the boiler plate clauses requiring the contractor to meet all codes to overcome the lack of exit lights? Probably no, but then there is no fixed rule to answer these questions. The solution generally comes from the people genuinely willing to confront such situations daily and work out the answer. This nice sounding method, how ever, is a hope for method of solution at best. It does not work all the time and is completed by the lack of practice measurement. Big dispute can arise from defective plans. Experience has shown that major dollars can be lost by one party to a contract because of a drafting error. Although this type of error can be very expensive it may be common to the profession. In this case, for the question is not the extent of damage but the degree of professionalism used or lacking. Engineers and architects are cautioned not to judge themselves in disputes over plans they have prepared which are called or seemingly are defective. The mature designer will acknowledge the existence of an error and do its utmost to mitigate the resultant costs of correction. The ultimate decision as to whether the designer is responsible for the costs is for someone else to make. The designer must remember, in spite of the noisy and menacing emotions of the moment that it is neither the contractor 25 nor the owner who is the judge of the designer. Their opinions may be temporarily unpleasant but they are opinions, not judgments. “The best reaction for a designer in an errant position is to move forward immediately, calm sensible, and openly to measure and solve the problem and simultaneously to create a record of interested, fair, genuine professionalism with concern for all involved in any obvious overruns” (Paul et al.,2000). The sophisticated designer will never admit responsibility for the error it is a long road from discovery of an error in the design to providing it is the designer’s liability, and many people lose their interest during the journey. “When a dispute over plans arises, the disputant will be forced to establish by the opinion of other plan producers and users that performance which constitutes the standard of care” (Jessup et al., 1963). Those who seek to prove that opinion will often find difficulty in locating peer professionals of sufficient stature willing to offer testimony of a critical nature to a fellow professional. Then, too, the degree of persuasive skills from member to member on the rosters of licensed professionals is greatly variable. Highly credentialed peer critics may be unable to put forth persuasively the arguments and conclusions or withstand cross examination regarding the deficiencies needed to establish the errors and their maker guilty of gross. The tactic to prove negligence or gross error is to seek legal precedence in similar cases previously tried in the courts. The second best tactic is reliance on the opinion of experienced professionals whose integrity has been long established and who are recommended and well regarded on the local scene. The problem of omission is more easily solved since it most often can be quantified in a straightforward manner. The missing exit light costs so many dollars for the fixture, the conduit, the box, the wire, and the panel breaker. Perhaps by being purchased as a change or modification, the fixture will be more expensive than it would have been under the initial bid, but at worst this increase or penalty is relatively minor. 26 The liability, however, can be far in excess of the omission o error. The ancillary costs of a construction problem almost always exceed the direct costs. The owner and the contractor have the right to expect the designer to produce a set of drawing plans which will allow the project to be built. The law says the owner warrants to its contractor that the plans, if followed, will produce the desire results and the project is constructible. Thus if the error by the designer prevents the contractor from reaching its ends, the question of ability and assessment of consequential costs exists. iv) Methods or Means and Specification Performance The last category of deficient design is that the case in which the designer has specified both method or means of construction and the result required and then refuses to accept one of these two requirements. Example of this problem are legion but one that occurs very often is when the designer specifies that a certain waterproof coating be applied in two coats on some exterior surface under stringent conditions. The contractor applies the specified coating exactly the way it should, careful inspection is made by the designer as work proceeds, and then to the dismay of all the waterproof coating leaks contrary to the specifications. Almost without exception, the work is rejected and the contractor told to do it over. The means to accomplish the end result has been specified and followed but the end result does not meet the specification. “The problem, while very simple and obvious in the foregoing illustration, can quickly get very complicated and significant when detailed structural or mechanical sequences are set forth” (Mix, 1994). They are carefully followed, inspected before, during and after construction, all approved, and, lo and behold, big cracks appear in the walls and floors or the fancy heating and cooling system does not heat or cool. The principle is still simple: If the designer tells the contractor how to do something, the designer cannot impose a result beyond the product of the specified means This does not mean that the designer will not try nor does it mean that the contractor can view its responsibility for workmanship lightly. 27 Very often, the architect or engineer in its roll as interpreter of the contract will find itself in the position of imposing the consequence on a contractor of an error for which the designer is as at fault and will ultimately be found responsible. The imposition of the consequence of the error on the contractor can mean penalties beyond all fair play such as financial failure, loss of personal health, even suicide. “Can the contractor recover or pursue punitive damages such a capricious and arbitrarily act by a designer? Again, there is no hard rule, but it would appear that the common law evolvement process is now setting the stage for such punitive” (Horns, 1979). Some recent liberal stats who set the initial trends in law at lower levels have found that failure to act in while fully aware of the consequences even in a contract relationship is really a tort action and punitive damages are assessable. This is still to a great or perhaps total extent curbstone law wishful thinking, but all who use the courts know that today’s jurists are zealous to enforce the tenet that people who pretend to bargain and act toward each other in contract situations in good faith are acting with fraud, duress, and skullduggery should be brought to task. Figure 2.2 shows the causes of disputes through design deficiency: Means & specification performance Risks Dispute Underground or subsurface problems Defective plans Figure 2.2 Fish bone diagram shows root causes of disputes through design deficiency. 28 2.3.3 The Construction Process The next spawning ground for construction disputes is found in the consequences of the construction process. “Many times it can be difficult to differentiate between a design error and the consequence of the process.”(Hohns, 1979) Some items that give rise to dispute in the construction process are failure to plan and schedule adequately, failure to follow a plan and schedule, disagreement over what material is really specified, disputes over what is really an equal, failure to supply adequate manpower, responsibility for lack of adequate subcontractor manpower, equipment changes that cause delay. Changes or modifications of scope that increase consequential costs beyond specified markup, failure by the owner to fulfill its responsibilities on time, failure by the engineer to approve contractor submittals on time, overpayment for work in place, underpayment for work in place, failure to provide temporary heat, hosting, or elevators, lack of performance ability in one of the subcontractors, etc. certainly the list is almost endless, but by trade practice and custom essentially the items thereon relate to someone’s failure to do that which was required by its contract, thus changing the basis expected and / or implied to be available to the extent that the means, environment, conditions, or duration of a project are significantly affected for any member of the process who feels sufficiently aggrieved to file a claim. The construction process dispute is recently being pursued under both contract and tort concepts of law. If a designer who does not have a contract with the contractor does not do its work in the time and manner set forth in the owner-contractor contract or in the time and manner on which the contractor has a right to rely, i.e., duties well established by custom and the standard of care, the designer incurs a very real risk of being sued by the contractor in a tort action. Tort actions bring the added threat of punitive damages. This exposure to the design professional has never really been pursued until the last few years. 29 “The construction process dispute and almost all disputes involving large amounts of money are time related” (Hellard, 1997). Much focus is put on contract time; the contract documents usually set forth a definite number of calendar days or fixed final date for completion. There is at times more than one date in the documents when jobs are to be built in phases or specific milestone portions of completion are necessary. The second focus on time-related consequences is the juggling act an owner goes through when, for example, it develops a $ 100 million program which for the reasons of management is spread over say ten or more separate contracts, all or many of which depend on each other for start, mid job milestones, and interrelated finishes. In this type of situation, the pace of everyone involved can and usually does break down and causes the need for adjustments for delay damages. 2.3.4 The Consumer Reaction The consumer can be any other of variety of people. It can be the owner, private or public, or a corporate body. “The corporate owner in a dispute situation always boils down somewhere to one person who at times is hard to find.” (Hellard, 1987). The word management is the protective umbrella to shield so individuals. The consumer can be a tenant or it can be a purchaser of the building such as a condominium buyer. It can be a user who pays money to come into the building or comes to spend money or go to work. The aggrieved consumer can have no relationship with the contractor, designer, or the owner and still have a reaction to their endeavor Good building can sell images. Bad buildings can provide much press and publicity. In some cases there is no such thing as bad free advertising here and there a problem building or structure can be a blessing. 30 i) The Public Owner The typical public owner, such as the a school board, division of hospitals, or municipal corporation, is not particularly set up or organized to display or assert its reaction to its new building or alteration project if it does not do what it was supposed to do. The adage “out of sight, out of mind” applies for most of the problems experienced as this type of owner takes over and uses a newly constructed facility. The maintenance and occupancy of the building are generally the responsibility of a set of other people other than those who were responsible for its design, creation, and construction. “No one knows who did not do what, or had agreed to do something else, or what ever. It is only infrequently that the designer passes out manuals which say that the building was designed to support such and such or so many kilowatts of electricity were to be consumed, and so on” (Ruskin, 1982). Instead the use of the building is something that is learned by chance by the people who take over and determine for themselves how they think the building should best be used. It is the rare building which is put into use as programmed by the engineer. It has been until recently that any emphasis has been placed on getting the contractor or the designer to pay for its mistakes. The prime move towards this idea has been the staggering cost to repair, replace, or alter a system that does not function acceptably let alone as it purported to. The complexity of today’s installations as far as keeping indoor atmosphere cool, dry, quiet, etc., or treating one’s sewage makes it necessary for an owner who has not been well served by its contractor or designer to pursue one or both for relief. Until some years ago there was a tendency among the design profession to be unwilling to find fault with other members of its profession. More recently, responsible professionals in design are now willing and forced to criticize those among them who have not done the type of design work expected. The same has occurred with contractors. As demands have been made upon the construction industry to produce 31 more and more in a shorter period of time, workmanship has decreased. The tendency of the employees to favor the union hall to his employer has led to a talk of skill, interest, durability, and workmanship in many, many cases. The owner now is unwilling and unable to absorb the results for the design and poor workmanship. ii) Warranties The contract will typically spell out the obligation of the contractors regarding guarantee. The standard form of contract JKR 203 stipulates as follows: The contractor warrants to the owner and the SO that all materials and equipment furnished under this contract will be known unless otherwise specified, and that all work will be good quality, free from faults and defects and in conforming to the contract documents. All work not conforming to these requirements, including substitutions not properly approved and authorized, may be considered defective. If required by the SO, the contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment. If within one year after the date of substantial completion or within such longer period of time as many be prescribed by law or by the terms of any applicable special guarantee required by the contract documents, any of the work is found to be defective or not in accordance with the contract documents, the contractor shall correct it promptly after receipt of a written notice the SO to do so unless the SO has already previously given the contractor as written acceptance of such condition. The owner shall give such notice promptly after discovery of the condition. The courts hold that the warranty means what it says and will enforce the contractor to meet the requirements. “Many problems in warranty come about when the contractor is unable to duplicate the agreement it made with the owner, its suppliers, and its subcontractors the typical national manufacturer of major equipment will offer a warranty for one year 32 from stat up, a period that does not coincide with the agreement between owner and contractor” (Battelle, 1995). Obviously, the owner feels the contractor knew this and should have priced its bid to offer the warranty stated regardless of startup caveats from the manufacturer, but most contractors do not do so and instead a squabble over the warranty periods occurs. The owner has no reason to give in on warranties and if does so, it has been outplayed. Owners, who accept buildings with problems that are known at that time of acceptance, accept the problems as well, unless the problem is noted as an exception. These problems are called patent defects. An unknown defect is called a latent defect and is sometimes wrong that no one could observe or properly realize. In the case of discovery of a latent defect, the owner must give the contractor the opportunity to repair or correct the defect before it can go off and relief in some preferable way. Aggressive contractors do well to press continually for substantial completion certificate, to argue partial occupancy, and constantly fill the atmosphere with a stated willingness to make good all defects in workmanship. The aggressive contractor will simultaneously be careful to vigorously argue verbally that it is responsible for only those defects arising from failure to follow plans and specifications, and request proof of departure each time a defect is raised for correction. Aggressive owners will do well to hold substantial sums of the contractor’s money. Reduced retain age at occupancy generally means increased grief after occupancy. “The high degree of sophistication needed to understand how to run one of today’s projects puts another burden on the owner. Typically owners do not maintain the new building and its components as required by the operator’s manual” (Bachner, 1995). Often, too, no one on the owner’s staff understands the theory of the boiler plant, fan room, or controls. An owner with but a small amount of missed but required maintenance may have needlessly given the aggressive contractor enough muddy water to make the owner attempt to have the contractor perform the correction process of 33 equipment defects so frustrating and lacking in joy that the owner inevitably decides to face the problem itself, and all parties go their separate way. The implied warranty or right of reliance on buildings or parts thereof to do certain things has received a great deal of press and publicity. Certainly the owner or user has a right to pursue recovery of damages if the project does not deliver that which all have a right, stated or not, to expect. The product liability litigation again seems to follow the doctrine of reasonability. The subject of the product’s liability litigation is outside the scope of this text 2.3.5 Time Those involved in a construction problem quickly learn that it is not the hard (or the nuts and bolts) dollars which are important; rather it is in the time related costs that the huge damages arise to all concerned. The owner with the late facility has all sorts of extra costs or losses with which to contend in a delay posture; the contractor suffer the added costs of stretch-out, escalation of wages and other costs, and loss from their liability to focus management on new spheres of work. According to Hall (2000) “time is the key and the use of time is planned by scheduling”. Every construction job requires a schedule. Some require simple bar chart schedule, others require more detailed studies, and some require complex computer produced critical path method or construction manager control system programs. The latter techniques are very popular, and becoming more so to the extent that sophisticated scheduling techniques required for certain types of work. The bar chart is the usual standard when the CPM schedule is not used. Scheduling or proper planning by the contractor on how to handle his job in time will need planning programs. This shall help the contractor to manage his project and finish and complete his jobs on agreed time. This will avoid any dispute that may occur due to delay because of poor planning, poor scheduling by the contractor. Serious 34 disputes have occurred due to delayed works. At most the contractors, they overlook this part of the project stage and they just take it simple and it is the one that causes disputes most. Time needs to be monitored to avoid any conflict between the owner and the client. 2.4 Causes of Disputes by Stakeholders Fenn et al., (1997) states that “as a consequence of building projects in general being complicated, unique ventures erected largely in the open, on ground the condition of which is never fully predictable and in weather conditions that are even less so, it is common for disputes to arise during the course of building operations”. There are many reasons why disputes occur, but in the main they are caused by the failure of one or more members of the building team: • Failure to do their work correctly, efficiently and in a timely manner • Failure to express themselves clearly, or • Failure to understand the implication of instructions. A study carried out by Fenn (1997), Hall (2000) and Carmicheal (2002) have showed and identified the courses of construction disputes that contributed by the various party in construction projects. In this study the authors have decided to classify the events of construction disputes into three categories which are clients, designers and contractors. The causes of construction disputes listed below have been identified by range of party representatives and professionals working in the construction industry. The authors have identified the causes of construction disputes that are caused by client, designer and contractor as follows: 35 2.4.1 Causes of Construction Dispute by Clients Fenn (1997) identified the following factors as causes of construction disputes caused by clients: • Failure to respond in timely manner • Poor communications amongst members of the team • Inadequate tracing mechanisms for request of information • Deficient management, supervision and coordination efforts on the part of the project • Lowest price mentality in engagement of contractors and designers. • The absence of team spirit among the participants. • Reluctant to check for constructability, clarity and completeness. • Failure to appoint a project manager • Discrepancies / ambiguities in contract documents. The fish bone diagram below Fig.2.3 shows causes of disputes caused by clients: Poor communication Failure to respond in time Inadequate tracing mechanism for request of information Deficient management, supervision and Dispute Lowest price mentality in engagement of contractors and Discrepancies in contract documents Reluctance to check for contract ability, clarity and completeness Failure to appoint project manager Fig. 2.3 Fish bone diagram illustrating causes of disputes by client 36 2.4.2 Causes of Construction Dispute by the Consultants Hall (2000) identified causes of construction disputes caused by consultants as they are listed below: • Failure to understand its responsibilities under the design team contract • Over design and underestimating the costs involved • Late information delivery and cumbersome approach to request for information’s • Design and specification oversights and errors or omissions resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs. • Incompleteness of drawing and specifications The fish bone diagram below Fig. 2.4 shows causes of disputes caused by consultants Failure to understand its responsibilities under the design team contract Over design and understanding the costs involved To request for information late information delivery and cumbersome approach Dispute Incompleteness of drawings and specification Design and specification oversight and errors or omissions from specialists Figure 2.4: Fish bone diagram illustrating causes of disputes by consultants. 37 2.4.2 Causes of Construction Disputes by Contractors Carmicheal (2002) identified causes of construction disputes caused by contractors as follows: • Inadequate contractors management, supervision and coordination • Delay/ suspension of works • Failure to plan and execute the changes of works • Failure to understand and correctly bid or price the works • Lack of understanding and agreement in contract procurement • Reluctance to seek clarification • Inadequate CPM scheduling and update requirements Below is fish bone diagram Fig. 2.5 showing the root causes of construction disputes caused by contactors. Inadequate contractor’s management, supervision and coordination Failure to plan and execute the changes of works Delay / suspension of works Reluctance to seek clarification Dispute Inadequate CPM scheduling and update requirement Failure to understand and correctly bid or price the works Lack of understanding and agreement in contract procurement Fig. 2.5 Fish bone diagram illustrating causes of disputes by contractors Design Deficiency Defective plans Construction Process Contract Conditions Lack of perfection in the contract documents The underground or subsurface problems Failure to count the cost Risks The psychology of people in construction Root causes of disputes No damage for delay contract clause Poor communication Time related problems Reluctance to seek for clarification Over design and underestimating costs Incompleteness of drawings Failure to respond in timely manner Changes Dispute Discrepancies in contract documents Delayed works Caused by Consultants Reluctance to check for constructability Caused by Clients Poor scheduling Caused by Contractors Figure 2.6: fish bone diagram showing root causes of construction disputes 39 2.5 The Impact of Construction Disputes on Client’s Organizations Problems of construction disputes impacts on all stakeholders which may lead to an inequitable mode of project delivery such as reduce the margins, increased costs and even reduced the quality and levels of service. Most disputes are of a minor nature and are settled quickly, fairly and amicably by the building team. From time to time, however, more serious the issues come into dispute. When this happens, the building team should make mean to reach a fair settlement by negotiation. If this fails, it becomes necessary to use one or more of the dispute resolution mechanisms available and these are mediation, arbitration and litigation. When the above mentioned methods of dispute recovery fails, the out come of the results will be only winning or losing of one of the parties. Hall (2000) observed that consequences of the construction disputes will not benefit the stakeholders in the construction project. Therefore the impact of construction disputes into client organizations can be summarized as follows: • Additional expense in managerial and administration • Possibility of litigation cases • Loss of company reputation • Loss of profitability and perhaps business viability • Time delays and costs overruns • Extended and / or more complex award process • Loss of professional reputation • Diminution of respect between parties and deterioration of relationship and break down in cooperation • High tender prices • Rework and relocation costs for men, equipment and materials 401 2.6 Methods of Recovery of disputes “Some conflicts and disputes are not avoidable, proper management of conflict will ease the impact it has on the construction process, but resolution must follow quickly. Dispute can be resolved by either using informal such as negotiation and alternative resolution methods (ADR) or formal resolution methods such as mediation, arbitration and litigation.” (Whitfield, 1994). Cheung, et al., (2000) in their reviewed paper on project dispute resolution satisfaction classification through neural network. They have classified the dispute resolutions into five different stages. The diagram bellow illustrates the stages Litigation Line of increasing cost and Antagonism Binding resolution e.g. Arbitration Non-binding Resolution e.g. Mediation, Mini-trial and Adjudication Standing Neutral e.g. Dispute resolution Adviser, Dispute Review board Negotiation Favorable DRS Adverse DRS Figure 2.7: Definition of Project dispute resolution satisfaction 412 2.6.1 Litigation On any given construction project, disputes among the various parties are virtually guaranteed. In large measures, this is because the construction industry is not particularly well integrated and the opportunities for conflict between the many participants at all stages of the design and construction development are numerous, even on relatively small projects. Litigating these disputes before a judge and jury is expensive. Legal costs are not always predictable and the parties do not always anticipate or quantify the time and costs directly attributable to tying up key staff members in discovery, hearings, depositions, preparing or answering interrogatories, meeting with lawyers, testifying, and reconstruction of project files. Litigation also risks irreparably damaging the relationship between the parties and causes them to substantially relinquish control over the outcome of the dispute. Alternative forms of dispute resolution (ADR), intended to reduce or eliminate some of the undesirable consequences of litigation, have come into more practice. According to Essex (1996), in response to the increasing levels of litigation experienced in the early 1990s, the U.S. construction industry looked to the alternative means of resolving disputes. Grouped under the term Alternative Dispute Resolution (ADR) methods, they include arbitration, negotiation, mediation, mi-trials, and rent-ajudge and dispute review boards 2.6.2 Arbitration Organizations such as the American Arbitration Association in the U.S. have provided means for binding and non-binding forums to hear and resolve grievances. Such organizations provide listening of individuals qualified in selected areas of 423 expertise, from which the parties may choose one or more arbiters for a specified dispute. A disadvantage of this approach is that arbitration, like litigation, is usually started too late, takes too long to reach resolution, and costs too much. It does little to dispel the adversarial relationship which develops before the process can be implemented. “The resolution of a specific dispute withstanding, the outcome may further erode the relationship between the parties throughout the remainder of the project” (Bancher, 1988) 2.6.3 Mediation Mediation is a widely used technique wherein the parties continue their negotiation with the assistance of a mediator. The mediator serves at the request of the disputing parties and facilitates, but does not dictate the negotiation. The process may involve joint meetings as well as sequences of separate meetings with each party. According to Bachner (1988) “The mediator undertakes to clarify each party’s concept of each of the facts given, priorities and positions; loosen rigid stances, explores alternative solutions, and seeks trade-offs”. The mediator is an agent of reality, never an advocate for either side. The outcome is either a resolution of the dispute or step towards other recourses. 2.6.4 Negotiation “Negotiation is a voluntarily pre-hearing or mandatory pretrial” (Smith et al., 1996). It is generally an extension of the parties’ earlier negotiations, but is conducted by their newly appointed representatives or attorneys. If unsuccessful, such negotiations may also continue as a final attempt pretrial under the direction of a trial judge. However, any settlement or resolution is only achieved by agreement of the parties. 434 Although this method can avert a trial, its success depends on the attitudes and expertise of the representatives. If these individuals happen to be opposing attorneys, they must be dedicated to the success of their mission. Otherwise, they might as well be in court. 2.7 Summary This chapter covered the root causes of construction disputes from their sources. Performance at its best is a result of collaborative team work, if there is none it becomes very difficult to achieve the intended goal. The misunderstanding of the contract document can cause serious dispute among members of the team, thus it is wise to understand the contracts contained in the document. Researchers have observed that designs deficiency has caused problems in the industry, this is because most of the drawings are deficient. Moreover they have observed that construction disputes have a serious effect in the client’s organization, it is therefore necessary to manage disputes to improve production in the industry without delays and cost overruns. 5 Chapter 3 RESEARCH METHODOLOGY 3.1 Introduction The primary research objective is to identify the root causes of construction disputes. The study of this research was contacted in two phases, the first phase being collecting or gathering information and the second phase was collecting data from relevant parties involved in the industry. The research methodology goes as follows: 3.2 Phase One Information related to the problem were gathered from reliable sources which in this case were from the internet; this were most on recent journals published on maters related to causes of construction disputes, means of avoiding them and alternative disputes resolutions. Such information was of help in resuscitating the problem at hand. Books related to the problem faced were used as well. Such were to give the basic background on construction disputes and were to enhance the researcher to be focused on the problem statement. Such information was available from the university library. Past information is believed to be of good help for researchers in order to come up with constructive solutions. 446 3.3 Phase Two Having gathered the information from sources, data was then collected from the parties believed to be part and parcel of the problem encountered. Questionnaires were distributed within the city of Johor Bahru. The questionnaire were focused more on causes of disputes caused by each of the following parties; clients, consultants and contractors. These were to enhance the study in coming up with the best results that would benefit the industry in Malaysia and other countries faced with similar problem. The questions had to be answered in such a way that the respondent were to choose the significance on which the cause were occurring. For example, the following is a set of questions related to causes of construction disputes caused by client. Causes of Construction Disputes caused by Client Indicator, 1 2 3 4 5 - Very rare - Rare - Average - Often - Very often 1 Failure to respond in timely manner. 1 2 3 4 5 2 Inadequate tracing mechanisms for RFIs. 1 2 3 4 5 3 Reluctant to check for constructability, clarity and completeness. 1 2 3 4 5 4 Discrepancies or ambiguities in contract documents. 1 2 3 4 5 5 Poor communication among members of the team. 1 2 3 4 5 6 Failure to appoint an overall project manager. 1 2 3 4 5 7 Lowest price mentality in engagement of contractors And designers 1 2 3 4 5 The absence of team spirit among members of the team. 1 2 3 4 5 8 457 The same was done with causes of construction disputes caused by designers and contractors. This shall enable the researcher to observe the major causes of construction disputes, by so doing recommendations were initiated to capacitate the results obtained. The second part of the questionnaire was focusing on the end results of the disputes in the client’s organization. This question would enhance the researcher in identifying the side effects of construction disputes in the industry at large. The last question from the questionnaire was on the most preferred method of resolving disputes among the three that are commonly used in Malaysia; mediation, arbitration and litigation. This again would help in using one method in resolving construction disputes incase the dispute has not been managed or properly handled such that it would need the intervention of the third party. Disputes have been observed as a menace in the industry such that it has affected the performance of the industry in the past years, this study is aimed at avoiding such characters to normalize the situation and even improve it for the better part of it. The flow chard diagram (figure. 1.1) illustrating the process of the research methodology to be used to carry out the study. 3.4 Analysis of Questionnaire For the purpose of analysis of data collected through the questionnaire, the research used frequency analysis and average index. The average index is calculated as follows (Al-Hammad, 1996; Abd Majid & MacCaffer, 1997 and Abd Majid 1997). Average Index = ∑a x ∑n i i 46 8 Where, a = constant expressing the weight given to i x = variables expressing the frequency of response for i = 1, 2,3,4,5 In order to determine the significance of the factors in this subject matter the classification of rating the scale was as follows: 1.0 < Average Index < 1.5 Very rare 1.5 < Average Index < 2.5 Rare 2.5 < Average Index < 3.5 Average 3.5 < Average Index < 4.5 Often 4.5 < Average Index < 5.0 Very The grading of the results was to signify the contribution factor of the question into the problem, very rare to rare were reckoned as non contributing factors to the problem, average were factors identified as averagely contributing to the problem and, often and very often were identified as major contributors to the problem and these were the very same factors to focus on in how to avoid them or rather how to solve them in order to normalize the situation in the industry. 3.5 Conclusions and Recommendations Based on the results obtained, conclusions and recommendations were developed. All the factors listed can cause serious dispute to the extent that the project can come to a halt but there are those factors seen to be frequently occurring, so they are the factors identified as major contributors and they have suffered the performance of the industry at large. Based on the results, conclusions and recommendations were later suggested on these factors on how to handle them for the better performance of the industry in future. 489 The next chapter has detailed information on the above mentioned statement. 10 Chapter 4 DATA ANALYSIS AND RESULTS 4.1 Introduction In this chapter, data collected is analyzed and interpreted as presented to achieve the objectives of the study. Conclusion has been derived on the major contributor that causes the construction dispute as the most appropriate measures were made to overcome the dispute occurrences. The data obtained from the questionnaire survey based on the response from client, consultants and contractors to the allocated questions on the construction dispute related issues were analyzed accordingly in the forthcoming sections: • Results and findings • Analyzed data collected from client • Analyzed data collected from consultants • Analyzed data collected from contractors There were forty questionnaires distributed and only thirty two responded, and these questionnaires were grouped accordingly, clients, consultants and contractors. Out of the thirty two respondents thirteen were contractors, eleven were consultants and eight were clients. 50 11 4.2 Analysis and Results 4.2.1 Causes of Construction Disputes by Client i) Client Point of View Scores were graded as mentioned earlier on that is (1) very rare (2) rare (3) average (4) often and (5) very often. The mean index was used to grade the weight of the question on how much it affected the industry or rather how much it had contributed to the problem. Table 4.1: Client’s Point of View Scores Questions 1 2 3 4 5 6 7 8 9 Failure to respond in timely manner Poor communications amongst Members of the team Inadequate tracing mechanisms For the request of information Deficient management, supervision and coordination efforts on the part of the project Lowest price mentality in engagement of contractor’s designers. Reluctance to check for constructability, clarity and completeness Failure to appoint a project manager Discrepancies/ ambiguities in contract documents The absence of team spirit among the participants Mean Index 1 2 3 4 5 0 0 2 4 2 4.00 0 0 1 3 4 4.40 0 0 3 4 1 3.80 0 0 2 3 3 4.10 0 1 3 4 0 3.00 0 0 3 3 2 3.90 1 0 2 3 3 4.30 0 0 3 3 2 3.90 0 0 4 3 1 3.600 51 12 ii) Consultant Point of View The respondence was eleven and all of them attempted the questions in the questionnaire, the results are as illustrated below in Table 4.2. Table 4.2: Consultants point of view Scores Questions 1 2 3 4 5 6 7 8 9 Failure to respond in timely manner Poor communications amongst Members of the team Inadequate tracing mechanisms For the request of information Deficient management, supervision and coordination efforts on the part of the project Lowest price mentality in engagement of contractor’s Designers. Reluctance to check for constructability, clarity and completeness Failure to appoint a project manager Discrepancies/ ambiguities in contract documents The absence of team spirit among the participants Mean Index 1 2 3 4 5 0 0 5 4 2 3.70 0 0 6 3 2 3.60 0 3 3 4 1 3.30 0 2 4 3 2 3.50 0 2 4 5 0 3.30 0 3 3 3 2 3.40 1 2 2 3 3 3.50 0 4 3 3 1 3.10 0 3 3 3 2 3.40 52 13 iii) Contractors Point of View The respondence to this question was thirteen and they answered all the questions, the results are as shown below in Table 4.3. Table 4.3: Contractor’s pint of view Scores Questions 1 2 3 4 5 6 7 8 9 Failure to respond in timely manner Poor communications amongst Members of the team Inadequate tracing mechanisms For the request of information Deficient management, supervision and coordination efforts on the part of the project Lowest price mentality in engagement of contractor’s designers. Reluctance to check for constructability, clarity and completeness Failure to appoint a project manager Discrepancies/ ambiguities in contract documents The absence of team spirit among the participants Mean Index 1 2 3 4 5 0 4 3 4 2 3.30 0 3 3 3 4 4.30 0 3 5 4 1 3.20 0 3 4 3 3 3.50 0 2 4 4 3 3.60 0 3 5 3 2 3.30 1 4 2 3 3 3.20 0 3 3 5 2 3.50 0 4 4 4 1 3.20 53 14 iv) Overall Respondents The significance of each question shall be graded in a sequence form to reveal the impact it has on the problem, this will show the weight of the factor and the major factors arranged in their order of significance. See overall respondents in Table 4.4. Table 4.4: Overall Response Question 1 Failure to appoint a project manager 2 Poor communication amongst members of the team 3 Deficient management, supervision and coordination efforts on the part of the project 4 Failure to appoint a project manager 5 Reluctance to check for constructability, clarity and completeness 6 Discrepancies/ ambiguities in contract documents 7 The absence of team spirit among the participants 8 Inadequate tracing mechanisms for the request of information 9 Lowest price mentality in engagement of contractor’s design Scores Mean index 1 2 3 4 5 0 3 10 9 10 3.81 0 4 10 12 6 3.63 0 5 10 9 8 3.63 2 6 6 9 9 3.53 0 6 11 13 3 3.50 0 6 11 9 6 3.47 0 6 6 9 9 3.44 0 7 9 11 5 3.44 0 7 11 10 4 3.34 54 15 4.2.2 Causes of Construction Disputes Caused by Consultants i) Clients Point of View The response to this question was 100% to all parties involved. The results obtained are shown on the following table according to grouped disciplines as done on the previous section. Causes of construction disputes caused by consultants, below Table 4.5 shows the clients point of view. Table 4.5: Client’s point of view Scores Questions 1 Failure to understand its responsibilities under design team contract 2 Over design and underestimating the costs involved 3 Late information delivery and cumbersome approach to request for information 4 Design and specification oversights and errors or omissions resulting from uncoordinated civil, architectural, mechanical and electrical designs 5 Incompleteness of drawings and specifications. Mean Index 1 2 3 4 5 0 0 2 5 4 4.20 0 0 1 5 5 3.90 0 0 1 3 7 4.50 0 0 0 3 8 4.70 0 0 0 4 7 4.60 16 55 ii) Consultants Point of View From the consultant’s point of view, most of them have observed factors affecting the industry as far as construction disputes are concerned are as listed below in table 4.6. It is common practice though that we will never see things from the same perspective, it is why we have different opinions in identifying the factors that are actually affecting the industry in terms of disputes respectively. To prove that, results of construction disputes caused by consultants from the consultant’s point of view are as shown below in Table 4.6. Table 4.6: Consultant’s Point of View Scores Questions 1 Failure to understand its responsibilities under design team contract 2 Over design and underestimating the costs involved 3 Late information delivery and cumbersome approach to request for information 4 Design and specification oversights and errors or omissions resulting from uncoordinated civil, architectural, mechanical and electrical designs 5 Incompleteness of drawings and specifications. Mean Index 1 2 3 4 5 0 0 2 4 2 4.00 0 0 2 2 4 4.30 0 0 1 2 5 4.50 0 0 0 1 7 4.90 0 0 0 2 6 4.80 17 56 iii) Contractors Point of View The results shown below clearly shows that 100% of the contractors contacted for the survey attempted the questions. It therefore reveals that most of the contractors are directly affected by the poor performance of the consultants because of the consequences they suffer during the construction process. Table 4.7 below shows the contractors point of view. Table 4.7: Contractor’s point of view Questions 1 Failure to understand its responsibilities under design team contract 2 Over design and underestimating the costs involved 3 Late information delivery and cumbersome approach to request for information 4 Design and specification oversights and errors or omissions resulting from uncoordinated civil, architectural, mechanical and electrical designs 5 Incompleteness of drawings and specifications. Scores Mean Index 1 2 3 4 5 0 0 4 2 7 4.20 0 0 1 5 7 4.70 0 0 0 4 9 4.70 0 0 0 3 10 4.80 0 0 0 3 10 4.80 18 57 iv) Overall Respondents The graded results are of high significance in this question, it therefore reveals that the major contributing factors are from the disputes caused by consultants. None of the factors range within average, all most all of them they range above average, this shows the impact it has on the performance of the industry see Table 4.8 below. Table 4.8: Overall Respondents Questions 1 Design and specification oversights and errors or omissions resulting from uncoordinated civil, mechanical and electrical designs 2 incompleteness of drawings and specifications 3 Late information delivery and cumbersome approach to request for information 4 over design and underestimating the costs involved 5 Failure to understand its responsibilities under design team contract Scores Mean Index 1 2 3 4 5 0 0 0 7 25 4.78 0 0 0 9 23 4.72 0 0 2 9 21 4.59 0 0 4 12 16 4.38 0 0 8 11 13 4.16 19 58 4.2.3 Causes of Construction Disputes Caused by Contractors i) Clients Point of View Contractors are believed to be the main culprit in dispute causation but the results obtained from the study they dispute the ideology. The results below in table 4.9 tell us more about the contributing factor by most contractors in the industry. Table 4.9: Client’s Point of View Scores Questions 1 Inadequate contractors management, supervision and coordination 2 delay/ suspension of works 3 failure to plan and execute the changes of works 4 Failure to understand and correctly bid or price the works 5 lack of understanding and agreement in contract procurement 6 Reluctance to check for clarification 7 Inadequate CPM scheduling and update requirements Mean Index 1 2 3 4 5 0 0 6 2 0 3.30 0 2 5 1 0 2.80 0 2 4 2 0 3.00 0 0 2 3 3 4.10 1 3 3 1 0 2.50 0 1 3 4 0 3.80 0 2 4 2 0 3.00 20 59 ii) Consultants Point of View Consultants have responded to the question though their response identifies the contractor as the main culprit in disputes causation in this regard as compared to the client’s point of view. This again takes us back to the fact that people will never see thing from the same perspective, nonetheless the results below in table 4.10 tells us more on factors contributed by the contractor in the problem at hand. Table 4.10: Consultant’s point of view Scores Questions 1 Inadequate contractors management, supervision and coordination 2 delay/ suspension of works 3 failure to plan and execute the changes of works 4 Failure to understand and correctly bid or price the works 5 lack of understanding and agreement in contract procurement 6 Reluctance to check for clarification 7 Inadequate CPM scheduling and update requirements Mean Index 1 2 3 4 5 0 3 6 2 0 2.90 0 4 4 3 0 2.90 0 2 4 5 0 3.30 0 0 3 4 4 4.40 1 3 3 4 0 2.90 0 1 6 4 0 3.30 0 2 5 4 0 3.20 21 60 iii) Contractors Point of View Contractors do not believe they are the major contributors to construction disputes. They initially believe the client and the designers are the people causing the problem due to poor planning and coordination of the project in process. The results below in Table 4.11 really reveal that contractors are not part and parcel in causing construction disputes and they are not the major contributing factor as per their point of view. Table 4.11: Contractor’s Point of View Scores Questions 1 Inadequate contractors management, supervision and coordination 2 delay/ suspension of works 3 failure to plan and execute the changes of works 4 Failure to understand and correctly bid or price the works 5 lack of understanding and agreement in contract procurement 6 Reluctance to check for clarification 7 Inadequate CPM scheduling and update requirements Mean Index 1 2 3 4 5 0 3 7 3 0 3.00 0 5 5 3 0 2.80 0 5 6 2 0 2.80 0 0 5 6 2 3.80 4 4 4 1 0 2.20 1 5 3 4 0 2.80 2 4 4 3 0 2.60 61 iv) 22 Overall Respondents The results in Table 4.12 show how much are contractors contributing to the problem faced and the results reveal that they are not the major contributor. To prove that only one factor signifies often and the rest they are average and one factor is below average. Table 4.12: Overall Respondents Questions 1 Failure to understand and correctly bid or price the works 2 Reluctance to check for clarification 3 Inadequate contractor’s management, supervision and coordination. 4 Failure to plan and execute the changes of works 5 Inadequate CPM scheduling and update requirements 6 Delay/ suspension of works 7 Lack of understanding and agreement in contract procurement Mean Index Scores 1 2 3 4 5 0 0 10 13 9 3.97 1 7 12 12 0 3.09 0 6 19 7 0 3.03 0 9 14 9 0 3.00 2 0 8 11 13 14 9 7 0 0 2.91 2.88 6 10 10 6 0 2.50 23 62 4.2.4 Impact of Construction Disputes in Client’s Organization i) Client’s Point of View The problem of construction disputes impact on all stakeholders which may lead to inequitable modes of project delivery such as reduced margins, increased costs and even poor quality and poor services. Most disputes are of minor nature and can be settled quickly, fairly and amicably by the building team. The impact of construction disputes in client organizations can be summed up as shown in Table 4.13. Table 4.13: Client’s point of view Question Disciplines Mean Index 1 2 3 4 5 1 Cost effective 0 0 1 2 5 4.50 2 Possibility of litigation 0 0 4 2 2 3.75 3 Loss of reputation 0 0 3 4 1 4.13 4 High tender pricing 0 0 4 3 1 3.63 5 Time consuming 0 0 2 3 3 4.13 0 0 1 3 4 3.88 0 0 1 2 5 3.88 6 Loss of profit and business validity 7 Sour relationship between stakeholders and tenants 24 63 ii) Consultant’s Point of View The impact of construction disputes in client’s organization has brought about distrust and lack of confidence in clients organization to work with consultants and contractors. The client believes that if consultants are engaged in projects there will be a smooth running of the project but it seems that the fact is being disputed. Some of the factors that client thinks will be undertaken are seen to be the major cause of construction disputes the under listed factors in Table 4.14 are results of the factors of contributed by the stakeholders and it’s from the consultants point of view. Table 4.14: Consultant point of view Question Disciplines Mean Index 1 2 3 4 5 1 Cost effective 0 0 2 3 6 4.36 2 Possibility of litigation 0 0 2 5 4 4.18 3 Loss of reputation 0 0 4 4 3 3.91 4 High tender pricing 0 0 5 4 2 3.73 5 Time consuming 0 0 1 2 8 4.64 0 0 0 4 7 4.64 0 0 0 5 6 4.55 6 Loss of profit and business validity 7 Sour relationship between stakeholders and tenants 25 64 iii) Contractors Point of View The impact of construction disputes in client’s organization was observed as measured at different levels by the parties involved. In this regard the contractor was observed seeing the impact not major in the client’s organization, the results in Table 4.15 reveals the same. Table 4.15: Contractor’s point of view Question Disciplines Mean Index 1 2 3 4 5 1 Cost effective 0 0 1 5 7 4.46 2 Possibility of litigation 0 0 4 5 4 4.00 3 Loss of reputation 0 0 4 4 5 4.08 4 High tender pricing 0 0 6 5 2 3.69 5 Time consuming 0 0 1 4 8 4.54 0 0 1 6 6 4.38 0 0 2 5 6 4.31 6 Loss of profit and business validity 7 Sour relationship between stakeholders and tenants 26 65 iv) Overall Respondents The overall results of the impact in client’s organization due to construction disputes were all graded above average mean, this identifies that there is a course of concern amongst the stakeholders on the consequences the client’s organization suffers during and after the construction process. Table 4.16 identifies the impact in client’s organization from overall respondents. Table 4.16: Overall Respondents Questions Mean Index Scores 1 2 3 4 5 1 Time consuming 0 0 2 13 17 4.47 2 Loss of profit and business validity 3 Loss of reputation 0 0 4 10 18 4.44 0 0 3 12 17 4.44 4 Sour relationship between stakeholders and tenants 5 Cost effective 0 0 6 9 17 4.34 0 0 10 12 10 4.00 6 Possibility of litigation 0 0 11 12 9 3.94 7 High tender pricing 0 0 15 12 5 3.69 27 66 4.2.5 The Most Preferred Method of Resolving Disputes The last question was on the most preferred method of resolving disputes in the industry. As earlier on mentioned that people will never see things from the same perspective, same applies in this regard, and people had deferent views in resolving construction disputes. Respondents were requested to choose the most preferred method that he deemed fit in resolving construction disputes and they were given three forms of dispute resolutions, ADRs (Alternative Dispute Resolutions), Arbitration and Litigation. The results obtained are as shown in Table 4.17 below. Table 4.17: The Most preferred Method of Resolving Construction Disputes Methods of Resolving No. of Respondents Total Percentage disputes 1 ADRs 16 50% 2 Arbitration 10 31.25 3 Litigation 6 18.75 4.3 Analysis and Discussions Most of the information gathered is more likely in agreement with the information gathered by most researchers in developed countries; therefore it proves that even the under developing countries are faced with the same problem in the industry. In Malaysia, the construction industry is flooded with disputes that are encountered with other countries. It is; therefore, wise to identify the causes and the consequences of unsolved disputes which can affect the smooth running in the construction process. 28 67 The analysis of the questionnaire was categorized into four sections. The first section was about the causes of dispute by clients, consultants and contractors. In this section each question is allocated with scores which values its impact, such as very rare, rare, average, often and very often. In each of the above scores, marks are allocated in each score for grading. In the second section, the question is based on the impact that construction disputes have on the client’s organization. The same method for scoring points that is used in the first section is used again here The third section is based on methods that can be used in solving disputes in the industry. The question asked was “which method of solving dispute is most preferred between arbitration, mediation and litigation”. The respondent was expected to chose the most preferred method and was expected to give reason if any that may be affecting the method from being effective. Out of forty questionnaires distributed thirty two were returned as respondents and out of the thirty two respondents thirteen were contractors, eleven were consultants and eight from clients. Each respondent was expected to answer the first section, which was on causes of disputes by client, consultant and contractor. The second section, the impact of causes of dispute it has on the client’s organization and the last section which was based on the most preferred method of solving disputes in construction industry. The results were obtained by grouping the questionnaires according to their disciplines that is questionnaires from contractors were put together, same applies with the other disciplines. Scores of marks were allocated as follows: a) Very rare b) Rare c) Average d) Often e) Very often 68 29 The overall marks were graded by means of using the mean index formula as illustrated in previous chapter, refer to table 4.1, the major factors are also identified according to their forms of significance to identify the most problematic factors to the problem in question. Results obtained are discussed as follows: 4.3.1 Causes of Construction Disputes Caused by Clients i) Clients Point of View The client has observed that most of the factors that are causing construction disputes are of various reasons and they have an effect in the industry. It has been observed that as much as the factors are contributing to the problem they have different significances, there were those with major significance and there were those with average significance though none of the factors had been observed below average. Nonetheless the fact remains that they were the root causes of construction disputes and they are a subject matter in this regard and they are a subject for remedy. The major factors that were observed by the client as contributing factors are as shown below in their order of significance: • Poor communication amongst members of the team. • Failure to respond in timely manner. • Failure to appoint a project manger. • Deficient management, supervision and coordination efforts on the part of the project. • Reluctance to check for constructability, clarity and completeness. • Discrepancies/ ambiguities in contract documents. • Inadequate tracing mechanisms for the request of information. • The absence of team spirit amongst members of the participants. 30 69 ii) Consultants Point of View The consultants had observed that factors contributing to the problem caused by the client are of average significance. This means that they are in fact a contributing factor even though they are not the major significance. It becomes clear that the remedy for such factors can be easily resolved. Most of the factors were graded below the often significance and the factors observed by the consultant as main contributors are as listed below, they are: iii) • Failure to respond in timely manner. • Poor communication amongst members of the team. • Failure to appoint a project manager. • Deficient tracing mechanisms for the request of information. • Reluctance to check for constructability, clarity and completeness. • The absence of team spirit amongst members of the participants. Contractors Point of View Contractors observed construction disputes caused by client as of average significance except for only one that was observed as the major contributing factor. The major contributing factor observed by the contractor was the poor communication amongst members of the team, it really proves that communication break down is a major factor in this regard because client and consultant has also observed the same factor as the major contributing factor to the problem. Factors observed by the contractor as contributing factors in their order of significance to the problem besides the one mentioned above were: • Lowest price mentality in engagement of contractor’s designers. • Deficient management, supervision and coordination efforts on the part of the project. • Discrepancies/ ambiguities in contract documents. 31 70 iv) • Reluctance to check for constructability, clarity and completeness. • Failure to respond in timely manner. • Failure to appoint a project manager. • Inadequate tracing mechanisms for the request of information. • The absence of team spirit amongst members of the participants. Overall Respondents The overall response on causes of construction disputes by client was observed as average significance to the problem. The respondents viewed this from different angles as factors that were observed as major contributing factors were not of the same caliber, furthermore the significance of the factors differed from one another. Client observed differently from consultants same applies with contractors. This implies that factors affecting disciplines in construction sites differs from one another and it also counts on how much is that particular factor affecting that discipline. The results revealed that the major contributing factor was the poor communication breakdown amongst members of the team. At most communication in the contraction industry plays a vital roll, this is because of the information that has to be communicated from one party to another in a short period of time. Construction is basically based on time frame so everything done is basically done against time, if information would take long to be received by the other party because of poor communication automatically the project will delay and that is a major cause of construction dispute on its own. The essence of a contract is to fulfill the obligations required in time. Factors observed as major factors in this case were as follows and they are in their order of significance: • Poor communication amongst members of the team. • Failure to appoint a project manager. 32 71 • Failure to respond in timely manner. • Deficient management, supervision and coordination efforts on the part of the project. • Reluctance to check for constructability, clarity and completeness. • Discrepancies/ ambiguities in contract documents. • The absence of team spirit among the participants. • Inadequate tracing mechanisms for the request of information. • Lowest pricing mentality in engagement of contractors designs. 4.3.1.1 Summary The overall response on construction disputes caused by clients reveals that most of the factors observed to be of major significance, ranging between the averages and often while none were measured below average. It is clear that most of the factors contributed by the client were averagely contributing to the problem. Below a fish bond diagram (Fig. 4.1) shows the factors contributed by clients. 33 72 Reluctance to check for constructability, clarity and completeness Poor communication among members of the team Failure to respond in timely manner Inadequate tracing mechanisms for the request of information Dispute Failure to appoint a project manager Discrepancies/ambiguities in contract documents The absence of team spirit among members Lowest price mentality in engagement of contractor’s design Deficient management, supervision and coordination efforts on the part of the project Figure 4.1: Fish bone diagram showing major causes of disputes caused by clients 4.3.2 Causes of Construction Disputes Caused by Consultants i) Clients Point of View Cause of construction disputes caused by consultants were few in number that were eventually identified as root causes nonetheless they were observed as the major contributing factors in this regard and the significance of their occurrences were observed to be above the often significance. This revealed that the major contributor to the problem faced were consultants (designers). It is common practice in the industry more especially in the traditional procurement system that an architect will lead the 34 73 team, this is where most of the dispute arises when the architect as designer and leader at the same time would fail to produce drawings in time or incomplete drawings or rather issue deficient drawings to the contractor. The architect on the other hand will be the one reported too if the contractor wants to loge a protest on some of the technicalities that went wrong take for instance excusable delays due to deficient drawings or late delivery of drawings, at most the architect would award a resolution on his favor and this ill lead to a dispute. The client in this regard observed that consultants were the major contributor based on the following factors: • Design and specification oversights and errors or omissions resulting from uncoordinated civil, architectural, mechanical and electrical designs. • Incompleteness of drawings and specifications. • Late information delivery and cumbersome approach to request for information. ii) • Failure to understand its responsibilities under design team contract. • Over design and underestimating the costs involved. Consultants Point of View The circulation of information from one consultant to the other was cited as root cause amongst the consultants, therefore they end up pointing fingers to each other as he is the cause of the problem. Nonetheless the finger pointing had ended up as a major contributing factor to that fact and it had caused them in identifying different contributing factors to the problem at hand. The significance of the factors was observed to be above often to very often. They had thus observed major contributing factors in their order of significance as follows: • Design and specification oversights and errors or omissions resulting from uncoordinated civil, architectural, mechanical and electrical designs. • Incompleteness of drawings and specifications. 35 74 • Late information delivery and cumbersome approach to request for information. iii) • Over design and underestimating the costs involved. • Failure to understand its responsibilities under design team contract. Contractors Point of View Causes of construction dispute caused by consultants are of major impact to the contractor thus leading to serious disputes. The lack of appropriate information from drawings compels the contractor to seek for clarity from the consultant and these will lead to delay in the construction progress eventually causing disputes. From the results obtained from this study they revealed that consultants had few major factors that they were failing to handle for the smooth running of the project, though these factors were few but they had major significance in the problem faced. All the factors were ranging above often and very often significance. This proved that such factors are a course of concern to the industry and the factors identified by contractor as major root causes were as listed below in their order of significance: • Design and specification oversights and errors or omissions resulting from uncoordinated civil, architectural, mechanical and electrical designs. • Incompleteness of drawings and specifications. • Late information delivery and cumbersome approach to request for information iv) • Over design and underestimating the costs involved. • Failure to understand its responsibilities under design team contract. Overall Respondents The course of concern to all parties in this regard was a subject matter and it proved that consultants were really the major contributing factor to the problem. All of the factors identified were of high significance ranging from often to very often 75 36 significance, this means they were frequently occurring thus causing disputes that lead to the project suffering at the end. To incapacitate the subject matter the following factors were identified as the major contributing factors and they are arranged in their order of significance: • Design and specification oversights and errors or omissions resulting from uncoordinated civil, architectural, mechanical and electrical designs. • Incompleteness of drawings and specifications. • Late information delivery and cumbersome approach to request for information. • Over design and underestimating the costs involved. • Failure to understand its responsibilities under the design team contract. 4.3.2.1 Summary The response reveals that consultants were observed as the most significant contributors to the problem. Five factors related to this were ranging above the often scale and this reveals that they were occurring frequently thus causing serious disputes. The fish bone diagram below (fig. 4.2) shows the factors contributed by consultants. 37 76 Design and specification oversight and errors or omissions resulting from uncoordinated civil, architectural, mechanical and electrical designs Failure to understand its responsibilities under the design team contract Incompleteness of drawings and specifications Dispute Over design and underestimating the costs involved Late information delivery and cumbersome approach to request for information Figure 4.2: Fish bone diagram showing major causes of disputes caused by consultants 4.3.3 Causes of Construction Disputes Caused by Contractor i) Client’s Point of View The clients had observed that contractors were also contributing to the problem though their contributing factor was identified as minimal or rather not major contributing factors. From the results obtained the factors were ranging average and below average this revealed that the contractors were not a major contributing factor in this regard. The client observed the factors as listed below in their order of significance: • Failure to understand and correctly bid or price the works. • Reluctance to check for clarification. • Inadequate contractor’s management, supervision and coordination. • Failure to plan and execute the changes of works. 38 77 • ii) Inadequate CPM scheduling and update requirement. Consultants Point of View The consultants had also observed that causes of construction disputes caused by contractor were not a course of concern even though one was identified as a major factor to the problem. This revealed that contractors were not the major contributor in causing construction disputes but instead they were observed as the suffering ends. The consultants had observed the following factors as average contributing factors: iii) • Failure to understand and correctly bid or price the works. • Failure to plan and execute the changes of works. • Reluctance to check for clarification. • Inadequate CPM scheduling and update requirements. Contractors Point of View Contractors had observed that there were not part and parcel in causing construction disputes this was of the fact that few of their factors identified as contributing factors were ranging average and most of them below average. These clearly shows that contractors were doing their best in avoiding disputes in construction sites but instead they were doing what they new best in the construction process. The few factors that were identified as contributing factors were: • Failure to understand and correctly bid or price the works. • Inadequate contractor’s management, supervision and coordination. • Reluctant to check for clarification. 78 39 iv) Overall respondents The overall respondents revealed that contractors were not the major contributing factor to the problem though few factors identified as averagely contributing factors were observed. This revealed that contractors were really cooperating towards fulfilling the obligations intended in achieving their goal. The factors identified by the overall respondents as contributing factors by the contractors were: • Failure to understand and correctly bid or price the works. • Reluctance to check for clarification. • Inadequate contractors management, supervision and coordination • Failure to and execute the changes of works • Inadequate CPM scheduling and update requirements 4.3.3.1 Summary The response revealed that contractors were observed as averagely contributing to disputes. Five factors ranged the average and above and this reveals that their contribution had not much effect to the problem. The fish bone diagram below (Fig. 4.3) shows the factors observed to be contributed by contractors. 79 40 Inadequate CPM scheduling and update requirements Failure to understand and correctly bid or price the works Reluctance to check for clarification Dispute Failure to plan and execute the changes of works Inadequate contractor’s management, supervision and coordination Figure 4.3: Fish bone diagram showing major causes of disputes caused by contractors 4.3.4 Impact of Construction Disputes in Client’s Organization i) Client’s Point of View The problem of construction disputes impact on all stakeholders which may lead to inequitable modes of project delivery such as reduced margins, increased costs and even poor quality and poor services. Most disputes are of minor nature and can be settled quickly, fairly and amicably by the building team. The impact of construction disputes in client’s organization had been observed as a drawback in the industry and at most all the participants observed it at a similar angle. The clients observed it this way: • Time consuming. • Loss of reputation. • Loss of profit and business validity • Sour relationship between stakeholders and tenants • Cost effective • Possibility of litigation and • High tender pricing 41 80 ii) Consultants Point of View The impact of construction disputes in client’s organization did not actually affected the client’s organization per say but all the parties involved had been affected by the actions taken against other disciplines during the process of trying to resolve the dispute at hand. The consultants thus observed that the side effects of construction disputes also played a major roll in spoiling the companies’ names that were involved in that project. It was for this reason they saw it as a major draw back to all parties involved. The consultants observed the listed factors below as major drawbacks and these were: iii) • Loss of profit and business validity • Time consuming • Sour relationship between stakeholders and tenants • Cost effective • Loss of company reputation • Possibility of litigation • High tender pricing. Contractors Point of View Contractors had observed the same way the consultant had observed it and this revealed that all most all the parties involved observed that disputes were a course of concern to this problem at hand and the only resolution to this was identified as avoiding construction disputes for the smooth running of construction projects. iv) Overall respondents Construction disputes are observed as a burden in the industry and they have a remedy that will not be cost effective to neither of the parties partaking in that particular project. The overall respondents observed that most of the identified factors were drawback in the industry and they were a subject matter in this regard. The respondents 42 81 observed the following factors as major drawbacks and they are in their order of significance: • Time consuming • Loss of profit and business validity • Loss of reputation • Sour relationship between stakeholders and tenants • Cost effective • Possibility of litigation • High tender pricing 4.3.4.1 Summary The results obtained reveals that all parties involved showed a cause of concern to the impact of construction disputes. It can be observed that the factors identified are frequently occurring thus causing serious impact in client’s organization. In concluding, the impact of disputes to client’s organization are shown below (Fig. 4.4) in a fish bone diagram. 82 43 Loss of profit and business validity High tender pricing Cost effective Loss of company’s reputation Impact in client’s organization Possibility of litigation Time consuming Sour relationship between stakeholders and tenant Figure 4.4: Fish bone diagram showing the impact of disputes in client’s organization. 4.3.5 The Most Preferred method of resolving disputes Results obtained in this effect showed a major concern from all parties due to the fact that disputes occurring in the industry are good business to other professions. The respondents thus preferred to select the best method that has no effect to them as entrepreneurs. The method was observed to be cheap and very quick in resolving construction disputes without delaying the project. This has resulted in most members preferring ADRs as the most suitable method to resolve disputes. There were factors though that were identified to be affecting the selection of the resolving methods, these were the nature of the dispute, interest in the dispute, technicalities of the dispute and lack of trust among members of the team thus leading the award being biased. From interviews conducted with professionals within the city of Johor Bahru, the researcher observed that most cases were not treated fairly thus people preferred to engage lawyers for their self interests. The lack of transparency in awarding decisions in 83 44 any dispute occurred it has affected the industry. The engagement of construction professionals has been observed a major concern in this subject matter. The reasons cited were, professionals in the industry would handle the matter with diligent care because they have an idea about the industry and they have a clear understanding of the technicalities in the construction process. So this would enable them to award fair judgment in any dispute that might occur. 45 Chapter 5 CONCLUSIONS AND RECOMMENDATIONS 5.1 Introduction This is the last chapter of the study; it includes the recommendations based on the findings and conclusion. The main objective of the study is to identify the causes of construction disputes and the impact of construction disputes in the client’s organization. Recommendations will be suggested on how to avoid the causes of construction disputes for Malaysian construction industry. This study has also help in identifying the most preferred method of solving disputes in the industry that is most preferred by the parties involved in the industry in Malaysia. 5.2 Conclusions Interviews were held with professionals within the city of Johor Bahru to verify the most important parts that needed most concentration in order to achieve the objectives of the study. The conclusion can be drawn from the findings to justify the results obtained from this study and the data collected being the true reflection of the results obtained. Moreover the factors observed as major factors to the problem in question none of them were under-graded, this means there are effective to the industry and a remedy to this is a must to keep the industry performing to its full capacity. 85 46 5.2.1 Identifying the Causes of Major Contributors of Construction Disputes The results reveal that most significant causes of construction disputes contributed by the designers are incompleteness of drawings and specifications, design and specification oversight and errors or omissions resulting from uncoordinated civil, structural, mechanical and electrical designs. Poor communication is another factor that has contributed in causing disputes in this regard. Causes of construction disputes contributed by the client are deficient or poor management, supervision and coordination efforts on the part of the project have ambiguities in contract documents, reluctance to check for constructability, clarity and completeness of construction process. Moreover, the most causes of construction disputes contributed by the contractors are delays, poor supervision of works executed on sites, inadequate contractor’s management, and coordination, failure to understand and correctly bid or price the works, reluctance to seek clarification and failure to plan and execute the changes of works. Below is a fish bone diagram (Fig. 5.1) showing the major contributing factors to the problem. 86 47 Design and specification oversight and errors or omissions resulting from uncoordinated civil, architectural, mechanical and electrical designs Late information delivery and cumbersome approach to request for information Failure to understand its responsibilities under the design team contract Incompleteness of drawings and specifications Inadequate contractor’s management, supervision and coordination Reluctance to check for clarification Over design and underestimating the costs involved Failure to plan and execute the changes of works Failure to understand and correctly bid or price the works Dispute Lowest price mentality in engagement of contractor’s designers Failure to respond in timely manner Reluctance to check for constructability, clarity and completeness Poor communication among members of the team Discrepancies/ ambiguities in contract documents Deficient management, supervision and coordination The absence of team spirit among the participants Inadequate tracing mechanisms for the request of information Failure to appoint a project manager Figure 5.1: Fish bone diagram showing all major root causes of construction disputes 5.2.2 Identifying the Impact of Construction Disputes in Client’s Organization From the findings all parties respondent positively in this regard, time, delays and cost overruns, diminution of respect between parties, deterioration of relationship and breakdown in cooperation and expenses in managerial and administration are concluded 48 87 in the findings as the most significant impact of construction disputes on client’s organization 5.2.3 The Most Preferred Method of Resolving Disputes It can be concluded from the results that the most preferred method of resolving disputes was the ADR (mediation, conciliation and negotiation). This has been observed as the fastest and none cost effective method in resolving disputes. Unlike the other methods witch are observed to be time consuming and cost effective. Change of clauses in the JKR will be of good benefit to the industry in as far as managing construction disputes is concerned, though change is not easily accepted in the society but for piece to reign in the industry the above mentioned point should be considered. Clauses that encourages litigation should be avoided so that problems could be easily solved at grass root level without the involvement of none professions of this industry. Only professionals in the industry must solve such kind of disputes without being biased. Such problems can even be easily avoided; moreover this prevention is better than cure. 5.3 Recommendations This study has identified the root causes of construction disputes caused by various parties involved in the industry and they were analyzed to identify their effects in the industry. The impact of construction disputes in client’s organization were also identified and analyzed to measure their effect in the industry and furthermore ADRs were observed as the best method to resolve disputes in Malaysia. However there are recommendations for future research and these are as listed below: • The research has been conducted within the city of Johor Bahru only, this study 49 88 can be expanded by taking samples in other cities in Malaysia. • The data collected in this research did not specify the categories of contractors as stipulated by the registrar of contractors in Malaysia. Data must be collected from contractors at different categories in order to identify the major contributing factors at different levels. • In this research ADRs are observed as the best method for resolving disputes. For further studies a better method for resolving disputes can be developed. . 50 89 REFERENCES Association of Soil and Foundation Engineers (ASFE). (1995a). Annual strategic plan 1995-1996, Silver Spring, Md. Association of Soil and Foundation Engineers (ASFE). (1995b). Loss prevention through project management. Professional Firms Practicing in the Geosciences, ASFE, Silver Spring, Md. Bachner, J. (1995). Alternative dispute resolution: Successful new approaches to ancient problems, a massage to client from ASFE. Association of Soil and Foundation Engineers, Silver Spring, Md. Bachner, J. (1988). ADR, alternative dispute resolution for the construction industry, 18 Association of Soil and Foundation Engineers, Silver Spring, Md 18. Battelle, A.E. (1995). The growing impact of AD on the construction industry: ‘Real Time’ dispute processing on the Boston Central Artery/ Tunnel Project. Constr. Law, Nov. 13. Boston’s CA/T project warrants a better review. (1997). Eng. News Rec. 239(6), 94. Carmicheal, D.G. (2002). Disputes and international projects. Liisse: A.A. Balkema Publishers Carr, F., Lockwood, K. M., McDade, J., and Ruttinger, G. D. (1995). The untapped potential of ADR in the construction industry. Fed. Law, 42(32), note 3, 36. Cheeks, J. R. (1996). Settlements of shallow foundations on uncontrolled mine spoil fill, J. Perform. Constr. Facil., 10(4), 143-151. Cheung, S.O., Tam, C.M. and Harris, F.C. Project Dispute Resolution Satisfaction Classification through Neural Network. 70 Journal of Management in Engineering, ASCE, January/ February 2000. Essex, J. R. (1996). Means of avoiding and resolving disputes during construction. Elsevier science Ltd: Tunneling and underground space technology. Vol. 11, No.i. 27-31 Fenn, P. Lowe, D. and Speek C. Conflict and dispute in construction. Contract Management Economics. Journal of Management in Engineering, ASCE, Vol. 18No. 1:20, November 1997. 90 51 Groton, J. P. (1996). A new, comprehensive approach to dispute avoidance and resolution. Charting the course to the year 2000-Together, A landmark international multidisciplinary conference on dispute avoidance and resolution in the construction industry, 4. Univ. Of Kentucky, Lexington, Ky. Goyal, B.B. construction claims and disputes. Causes and coat/ time overruns. Journal of Construction Engineering and Management, ASCE, 195-196, February/ March 1996. Groton, J. (1991). Preventing and Resolving Construction Disputes, CPR Legal Program Construction Disputes Committee, center for Public Resources, New York, N.Y. Hall, J.M. (2002). Ineffective communication: Common causes of construction disputes. Alliance’s Advisory Council Legal Notes. Vol. 13, No.2 Hellard, B.R. (1997). Preventing and solving construction contract disputes. Litton educational publishing company. Hohns, M.H. (1979). Preventing and solving construction disputes. New York: van Nostrand Reinhold Company. Hall, J.M. (2002). Ineffective communication: Common causes of construction disputes. Alliance’s Advisory Council Legal Notes. Vol. 13, No.2 Jessup, W. E., Jr., and Jessup, W.E. (1963). Law and specifications for engineers and scientists, 28-29. McManamy, R. (1994). “Industry pounds away at disputes.’ Eng. News, 24,3. Mix, D.M. (1997). ADR in the construction industry: Continuing the development of a more efficient dispute resolution mechanism.’ Ohio St J. on Disp. Resol., 12, 463-464. Ruskin, A. M., and Estes, W. E. (1982). What every engineer should know about project management, Association of Soil and Foundation Engineers, Silver Spring, Md., 14. Smith, R. F., MacPherson, R.j., and Thomson, D. B. (1996). Dysfunctional ADR: Tips to avoid the pain.” Constr. Lawyer, 16(26), 29-30. Stipanowich, R.j. (1996). Beyond arbitration: Innovation and evolution in the United States construction industry. Wake forestl. Rev., 31, 65. Stipanowich, T.J. (1998a). Reconstructing construction law: Reality and reform in a transactional system. Wis. L. Rev., 463-465. Stipanowich, T.J. (1998b). The multi-door contract and other possibilities Ohio St. J. On Disp. Resol., 13, 303-32 52 91 APPENDIX 1 QUESTIONNAIRE SURVEY Research Title: MANAGING CONSTRUCTION DISPUTES This research aims to manage or rather avoid construction disputes in construction sites. The purpose of the survey is to collect information on construction disputes at large by using the approach shown below from relevant stakeholders with vast experience in the industry. 92 53 Causes of Construction Disputes in Construction Industry Questionnaire survey Section I: Company and Respondent Profile Please fill in the blank space or tick in the box where appropriate. 1. Respondent Name : 2. Company Name : 3. Type of Job/ Position: 4. Experience: Less than 5 years 5 years to 10 years 10 years and above 5. Type of Organization. Client Consultant Contractor 54 93 Causes of Construction Disputes in the Construction Industry Section II Please indicate your opinion for the following causes of construction disputes Indicator, 1; 2; 3; 4; 5; Very rare Rare Average Often Very often A. Causes of construction Disputes by client 1) Failure to respond in timely manner. 1 2 3 4 5 2) Inadequate tracing mechanisms for RFIs. 1 2 3 4 5 3) Reluctant to check for constructability, Clarity and completeness. 1 2 3 4 5 4) Discrepancies or ambiguities in contract documents. 1 2 3 4 5 5) Poor communication among members of the team. 1 2 3 4 5 6) Failure to appoint an overall project manager. 1 2 3 4 5 7) Lowest price mentality in engagement of contractors And designers 1 2 3 4 5 8) The absence of team spirit among members of the team. 1 2 3 4 5 9) Deficient management, supervision and coordination efforts on the part of the project. 1 2 3 4 5 94 55 Causes of Construction Disputes in the Construction Industry B. Causes of construction disputes by consultants 1) Failure to understand its responsibilities under the design team contract. 1 2 3 4 5 2) Over-design and underestimating the costs involved. 1 2 3 4 5 3) Late information issued and cumbersome approaches to RFIs. 1 2 3 4 5 4) Inadequate in open and factual communication. 1 2 3 4 5 5) Design and specification oversights and errors or omissions Resulting from uncoordinated civil, structural, architectural, mechanical and electrical designs. 1 2 3 4 5 6) Incompleteness of drawings and specifications. 1 2 3 4 5 C. Causes of construction disputes by contractor 1) Inadequate contractor management, supervision and coordination. 1 2 3 4 5 2) Lack of understanding and agreement in contract procurement system. 1 2 3 4 5 3) failure to understand and incorrectly bid or estimating the works. 1 2 3 4 5 4) Reluctance to seek clarification. 1 2 3 4 5 5) Failure to plan and execute the changes of works. 1 2 3 4 5 6) Inadequate CPM scheduling and update requirements. 1 2 3 4 5 7) Delay due to suspension of works. 1 2 3 4 5 95 56 Causes of Construction Disputes in the Construction Industry Section III The Impact of Construction Disputes in Clients Organization • Additional expense in managerial and administration 1 2 3 4 5 • Possibility of litigation cases 1 2 3 4 5 • Loss of company reputation 1 2 3 4 5 • Loss of profitability and perhaps business viability 1 2 3 4 5 • Time delays and costs overruns 1 2 3 4 5 • Extended and / or more complex award process 1 2 3 4 5 • Loss of professional reputation 1 2 3 4 5 • Diminution of respect between parties and deterioration of 1 2 3 4 5 relationship and break down in cooperation 1 2 3 4 5 • High tender prices 1 2 3 4 5 • Rework and relocation costs for men, equipment and materials 1 2 3 4 5 96 57 Causes of Construction Disputes in the Construction Industry Section IV. The Most Preferred Method for Resolving Construction Disputes Please circle the most preferred answer. 1) From your own opinion, which is the best solution to resolve disputes? a) ADR (Negotiation, Conciliation, Mediation, etc.) b) Arbitration c) Litigation 2) Is the method effective? Yes or Not 3) If not please state your reasons, what are the factors affecting the method not to be effective?